h.l. bajaj chairman, central electricity authority 12 th june, 2003
DESCRIPTION
Power Ministers Conference. Presentation on “Capacity Addition” and “Renovation & Modernization” - targets for the X th Plan. H.L. Bajaj Chairman, Central Electricity Authority 12 TH JUNE, 2003. Capacity addition in the X th Plan - the target. (figs. in MW). - PowerPoint PPT PresentationTRANSCRIPT
1
Presentation on “Capacity Addition”
and “Renovation & Modernization”
- targets for the Xth Plan
Presentation on “Capacity Addition”
and “Renovation & Modernization”
- targets for the Xth PlanH.L. Bajaj
Chairman, Central Electricity Authority
12TH JUNE, 2003
Power Ministers Conference
2
Capacity addition in the Xth Plan - the target
Central State Private Total
Thermal 12,790 6,676 5,951 25,417
Hydro 8,742 4,481 1,170 14,393
Nuclear 1,300 - - 1,300
Total 22,832 11,157 7,121 41,110
(figs. in MW)
Contd. .....
3
Present status of projects identified for addition during Xth Plan
* Includes additional projects over and above the original
target for possible addition during Xth Plan.
Projects completed Projects to be started
/ Under execution in 2003-04 positively
Central 14,095 10,027
State 6,705 9,682
Private 3,857 4,860
Overall 24,657 24,569
4
Statewise projects to positively
start in 2003-04 for achieving
Xth Plan capacity addition target
- The issues / holdup and targets
5
PUNJAB
Shahpurkandi, State - 168 MW Investment decision Works to start by Sept.'03.
Lehra Mohabat, State - 500 MW Main plant equipment award bySept.'03
Goindwal Sahib,Private
- 500 MW Issue of Captive Mining / Coalpricing
Financial Closure
HARYANA
Yamunanagar, State(additional project)
- 500 MW Clearance from M/o E&F / CWC Main plant equipment award by
Sept.'03.
6
HIMACHAL PRADESH
Kashang -I, State - 66 MW
UHL -III, State(additional project)
- 100 MW
Civil package award Works to commence by
Sept.'03.
RAJASTHAN
Mathania ISCC - 140 MW Gas Supply Agreementwith GAIL.
JAMMU & KASHMIR
Baghaliar, State - 450 MW Project works to bespeeded up.
7
UTTAR PRADESH
Anpara 'C', State - 500 MW Funding tie up Main Plant equipment award
by Sept.'03.
Rosa, Private(additional project)
- 567 MW Escrow Agreement Financial Closure EPC contract finalization
MAHARASHTRA
Paras Extn., State(additional project)
- 250 MW
Parli Extn., State - 250 MW
Implementation decision Main plant equipment award
by March '04.
Dabhol -II, Private - 1444 MW Dispute between Promotorand State.
8
GUJARAT
Jamnagar, Private - 500 MW Issue of change of EPCcontractor
Financial Closure
Additional projects identified :
Sikka Extn., State - 500 MW
Surat Lignite, State - 250 MW
Implementation decision Main plant equipment award by
Dec.'03.
Akrimota, State - 250 MW Resolution of dispute :Material handling package
9
MADHYA PRADESH
Bina, Private - 578 MW Escrow agreement Revalidation of FSA.
Maheshwar, Private - 400 MW Works held up due to financialconstraints.
Amarkantak, State(additional project)
- 210 MW Project clearances Land for ash disposal
CHATTISGARH
Korba East Extn.,State
- 420 MW Investment decision Main Plant equipment award
by Mar.'04.
10
ANDHRA PRADESH
Jurala Priyadarshini,State
- 78.2 MW Works to commence by Sept.'03
Rayalseema -II, State - 420 MW Deferred payment guaranteeissued by PFC to be accepted bycontractor
Works to commence by Sept.'03
Vemagiri -I, Pvt. - 370 MW
Gauthami, Pvt. - 464 MW
Jegarupadu Extn., Pvt. - 230 MW
Konaseema, Pvt. - 445 MW
Financial Closure Issues pertaining MOA to be
resolved with Financial Institutions
Ramagundam, Pvt. - 520 MW Financial closure
Vijayawada Extn., State(additional project)
- 660 MW Funding tie up Project clearances Main Plant equipment award
11
KARNATAKA
Bellary, State - 500 MW Funds tie up Main Plant equipment award by
Sept.'03Additional / replacement projects identified :
Raichur U-8, State - 210 MW Main plant equipment award byMar.'04
Bidadi, State - 1400 MW Gas Supply Agreement
Bijapur, Private - 350 MW
Nagarjuna, Pvt. - 1015 MW
Project clearances
KERALA
Kuttiyadi Augm.,State
- 100 MW Clearance linked with sharingof Cauvery water
12
PONDICHERRY
Karaikal, State - 100 MW Main Plant equipment award byDec.'03.
TAMIL NADU
Bhawani Barrage - 90 MW Inter State aspect due toCauvery water angle
ORISSA
Balimela, State - 150 MW Pending issues resolution withcontracting agency
Works to start at siteimmediately.
13
WEST BENGAL
Sagardighi, State - 500 MW
Santaldih, State(additional project)
- 250 MW
Investment decision Main plant equipment award by
Dec.'03.
Bakreshwar, State - 420 MW Main plant equipment award byDec.'03.
JHARKHAND
Tenughat Extn.,State
- 210 MW Main Plant equipment award byDec.'03.
Jojobera, Private - 120 MW Financial closure Project clearances Land availability for ash
disposal
14
BIHAR
Bihta - 135 MW Project clearances
MIZORAM
Bairabi, State - 80 MW Investment decision Works to start by Sept.'03.
MEGHALAYA
Myntdu Leiska, State - 84 MW Civil works award /works to commence Sept.'03.
ASSAM
Karbi Langpi - 100 MW Project works held up due tofinancial constraints.
15
Renovation & Modernization - Xth Plan Thermal units
106 units under Life Extension Programme
• Benefits to accrue - increase in generation - 23,700 MU/ year
- increase in life span - 15 to 20 years
60 units under Renovation & Modernization
• Capacity involved - 13,900 MW
• Benefits to accrue - 3,000 MU/ year
Hydro units
240 units under Renovation & Modernization & uprating
• Capacity involved - 8,088 MW
• Benefits to accrue - 2,887 MW
- 10,203 MU/ year
Contd. .....
16
Renovation & Modernization ….. Contd. ….
Funds available through PFC and REC for R&M schemes and
RLA studies under Accelerated Generation and Supply Programme
(AG&SP)
Interest subsidy of 3% available subject to compliance within
stipulated time frame :
• Completion of RLA studies and
preparation of feasibility reports Dec,’03
• Calling of tenders Feb./ Mar.’04
• Placement of orders for Life Extension Dec.’04
• Commencement of execution Mar.’05
17
Need to further strengthen and streamline monitoring mechanism at all levels of review in the State / SEB
Project specific coordinators identified in CEA for expediting and assistance of project authorities
• Need for system for regular reporting of inter-ministerial / inter state issues to enable take up with appropriate
authorities
Funds now available for Generation projects from Rural Electrification Corporation (REC) also
Work at all project sites to commence within current year to ensure completion within Xth Plan
18
Thank you