# Activity Name Original Duration Remaining Duration Start Finish Activity % Complete Resources 1 HNSB 11.30.15 264 213 14-Sep-15 A 28-Sep-16 2 Health, Nursing & Science Building 264 213 14-Sep-15 A 28-Sep-16 3 Design & Engineering 163 100 14-Sep-15 A 19-Apr-16 4 Package 2 Long Lead 163 100 14-Sep-15 A 19-Apr-16 5 Door Frames 20 15 16-Nov-15 A 18-Dec-15 25% WPI Doors 6 Elevator & Equipment 100 54 21-Sep-15 A 15-Feb-16 46% TK 7 Lighting 80 70 16-Nov-15 A 08-Mar-16 12.5% Reynolds 8 Electrical Gear 60 50 16-Nov-15 A 09-Feb-16 16.67% Reynolds 9 HW & CW Pumps 20 5 09-Nov-15 A 04-Dec-15 75% North Umpqua 10 AHU's 1, 2 & 3 40 15 26-Oct-15 A 18-Dec-15 62.5% FM 11 Exhaust Fans 40 15 26-Oct-15 A 18-Dec-15 62.5% FM 12 Mechanical Room Equipment 60 50 16-Nov-15 A 09-Feb-16 16.67% North Umpqua 13 Generator 60 35 26-Oct-15 A 19-Jan-16 41.67% Reynolds 14 Aluminum Storefront System & Glazing 90 75 09-Nov-15 A 15-Mar-16 16.67% Culver 15 Exterior Rain Screen 90 55 09-Nov-15 A 16-Feb-16 38.89% Wood Finishes 16 Exterior Sheet Metal 60 50 09-Nov-15 A 09-Feb-16 16.67% FM Ext 17 Lab Equipment 120 100 16-Nov-15 A 19-Apr-16 16.67% ACCO 18 Lab Casework/Countertops 120 65 14-Sep-15 A 01-Mar-16 45.83% S & B 19 Contractor Supplied Furniture 80 80 30-Nov-15 22-Mar-16 0% ACCO 20 Doors & Hardware 90 80 09-Nov-15 A 22-Mar-16 11.11% WPI Doors 21 Construction Phase 221 213 16-Nov-15 A 28-Sep-16 22 Building Milestones 195 195 24-Dec-15 28-Sep-16 23 Roof Complete & Building Dried In 1 1 24-Dec-15 24-Dec-15 0% 24 Interior Rough In Complete 1 1 10-Mar-16 10-Mar-16 0% 25 Interior Finishes Complete 1 1 04-Aug-16 04-Aug-16 0% 26 Site Finishes & Landscaping Complete 1 1 01-Aug-16 01-Aug-16 0% 27 Substantial Completion 1 1 17-Aug-16 17-Aug-16 0% 28 CO 1 1 28-Sep-16 28-Sep-16 0% 29 MEP Milestones 195 195 21-Dec-15 23-Sep-16 30 Replacement HW/CW Pumps In Service 0 0 21-Dec-15* 21-Dec-15 0% 31 Temp Heat Ready To Run 0 0 21-Dec-15 21-Dec-15 0% 32 Initial Energization 0 0 17-Feb-16 17-Feb-16 0% 33 Mechanical Piping Complete & Flushed 0 0 17-Feb-16 17-Feb-16 0% 34 Intitial AHU Air Run 1st Floor 0 0 24-Feb-16 24-Feb-16 0% 35 Initial AHU Air Run 2nd Floor 0 0 24-Feb-16 24-Feb-16 0% 36 All Coil Connections Complete 5 5 24-Feb-16 01-Mar-16 0% 37 MEP Running Under Control 0 0 18-Mar-16 18-Mar-16 0% 38 Prime & 1st Coat & Building Clean Complete 1 1 17-Mar-16 17-Mar-16 0% 39 Complete Loop Tuning 7 7 18-Mar-16 28-Mar-16 0% 40 Test & Balance Water/Air 20 20 15-Mar-16 11-Apr-16 0% 41 Fire Alarm Test Complete 58 58 12-Apr-16 01-Jul-16 0% 42 Commisioning Complete 58 58 05-Jul-16 23-Sep-16 0% 43 MEP Equipment Install & Startup 50 50 07-Dec-15 16-Feb-16 44 Replace Existing HW/CW Pumps In Mechanical Room 10 10 07-Dec-15 18-Dec-15 0% North Umpqua, Essential, Reynolds 45 HW & CW Pump Startup 5 5 15-Dec-15 21-Dec-15 0% Essential, North Umpqua, Reynolds 46 Install Switch Gear 5 5 10-Feb-16 16-Feb-16 0% Reynolds 47 Install Electrical Distribution 5 5 10-Feb-16 16-Feb-16 0% Reynolds 48 Install AHU-1, AHU-2 & AHU-3 5 5 24-Dec-15 31-Dec-15 0% FM, North Umpqua 49 MEP @ AHU-1, AHU-2 & AHU-3 10 10 04-Jan-16 15-Jan-16 0% North Umpqua, Reynolds, FM, North Umpqua, 50 AHU-1, AHU-2 & AHU-3 Startup 5 5 18-Jan-16 22-Jan-16 0% FM, North Umpqua, Essential, North Umpqua, 51 Install EF-1, EF-2 & EF-3 3 3 24-Dec-15 29-Dec-15 0% FM, Essential 52 Connect Electrical/Controls @ EF-1, EF-2 & EF-3 2 2 30-Dec-15 31-Dec-15 0% FM, Essential, Reynolds 53 EF-1, EF-2 & EF-3 Startup 2 2 04-Jan-16 05-Jan-16 0% FM, Essential, Reynolds 54 Underground Civil Outside 5' Outside Of Perimeter 33 33 30-Nov-15 A 15-Jan-16 55 Footing Drains 5 5 30-Nov-15 A 04-Dec-15 56 Complete Drain Rock Around Building Perimeter 5 5 30-Nov-15 A 04-Dec-15 0% North Umpqua, Knife River 57 West Concrete & South Utilities 4 1 30-Nov-15 A 30-Nov-15 Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct 2015 2016 28-Sep-1 28-Sep-1 19-Apr-16, Design & Engineering 19-Apr-16, Package 2 Long Lead Door Frames Elevator & Equipment Lighting Electrical Gear HW & CW Pumps AHU's 1, 2 & 3 Exhaust Fans Mechanical Room Equipment Generator Aluminum Storefront System & Glazing Exterior Rain Screen Exterior Sheet Metal Lab Equipment Lab Casework/Countertops Contractor Supplied Furniture Doors & Hardware 28-Sep-1 28-Sep-1 Roof Complete & Building Dried In Interior Rough In Complete Interior Finishes Complete Site Finishes & Landscaping Co Substantial Completion CO 23-Sep-16, Replacement HW/CW Pumps In Service Temp Heat Ready To Run Initial Energization Mechanical Piping Complete & Flushed Intitial AHU Air Run 1st Floor Initial AHU Air Run 2nd Floor All Coil Connections Complete MEP Running Under Control Prime & 1st Coat & Building Clean Complete Complete Loop Tuning Test & Balance Water/Air Fire Alarm Test Complete Commision 16-Feb-16, MEP Equipment Install & Startup Replace Existing HW/CW Pumps In Mechanical Room HW & CW Pump Startup Install Switch Gear Install Electrical Distribution Install AHU-1, AHU-2 & AHU-3 MEP @ AHU-1, AHU-2 & AHU-3 AHU-1, AHU-2 & AHU-3 Startup Install EF-1, EF-2 & EF-3 Connect Electrical/Controls @ EF-1, EF-2 & EF-3 EF-1, EF-2 & EF-3 Startup 15-Jan-16, Underground Civil Outside 5' Outside Of Perimeter 04-Dec-15, Footing Drains Complete Drain Rock Around Building Perimeter 30-Nov-15, West Concrete & South Utilities UCC Weekly Overall Sub Update 30-Nov-15 10:55 Page 1 of 21

Upload: others

Post on 13-Jun-2020

3 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: HNSB 11.30.15 Health, Nursing & Science Building...28-Sep-16, HNSB 11.30.15 28-Sep-16, Health, Nursing & Science Building 19-Apr-16, Design & Engineering 19-Apr-16, Package 2 Long

# Activity Name OriginalDuration

RemainingDuration

Start Finish Activity %Complete

Resources

1 HNSB 11.30.15 264 213 14-Sep-15 A 28-Sep-16

2 Health, Nursing & Science Building 264 213 14-Sep-15 A 28-Sep-16

3 Design & Engineering 163 100 14-Sep-15 A 19-Apr-16

4 Package 2 Long Lead 163 100 14-Sep-15 A 19-Apr-16

5 Door Frames 20 15 16-Nov-15 A 18-Dec-15 25% WPI Doors

6 Elevator & Equipment 100 54 21-Sep-15 A 15-Feb-16 46% TK

7 Lighting 80 70 16-Nov-15 A 08-Mar-16 12.5% Reynolds

8 Electrical Gear 60 50 16-Nov-15 A 09-Feb-16 16.67% Reynolds

9 HW & CW Pumps 20 5 09-Nov-15 A 04-Dec-15 75% North Umpqua

10 AHU's 1, 2 & 3 40 15 26-Oct-15 A 18-Dec-15 62.5% FM

11 Exhaust Fans 40 15 26-Oct-15 A 18-Dec-15 62.5% FM

12 Mechanical Room Equipment 60 50 16-Nov-15 A 09-Feb-16 16.67% North Umpqua

13 Generator 60 35 26-Oct-15 A 19-Jan-16 41.67% Reynolds

14 Aluminum Storefront System & Glazing 90 75 09-Nov-15 A 15-Mar-16 16.67% Culver

15 Exterior Rain Screen 90 55 09-Nov-15 A 16-Feb-16 38.89% Wood Finishes

16 Exterior Sheet Metal 60 50 09-Nov-15 A 09-Feb-16 16.67% FM Ext

17 Lab Equipment 120 100 16-Nov-15 A 19-Apr-16 16.67% ACCO

18 Lab Casework/Countertops 120 65 14-Sep-15 A 01-Mar-16 45.83% S & B

19 Contractor Supplied Furniture 80 80 30-Nov-15 22-Mar-16 0% ACCO

20 Doors & Hardware 90 80 09-Nov-15 A 22-Mar-16 11.11% WPI Doors

21 Construction Phase 221 213 16-Nov-15 A 28-Sep-16

22 Building Milestones 195 195 24-Dec-15 28-Sep-16

23 Roof Complete & Building Dried In 1 1 24-Dec-15 24-Dec-15 0%

24 Interior Rough In Complete 1 1 10-Mar-16 10-Mar-16 0%

25 Interior Finishes Complete 1 1 04-Aug-16 04-Aug-16 0%

26 Site Finishes & Landscaping Complete 1 1 01-Aug-16 01-Aug-16 0%

27 Substantial Completion 1 1 17-Aug-16 17-Aug-16 0%

28 CO 1 1 28-Sep-16 28-Sep-16 0%

29 MEP Milestones 195 195 21-Dec-15 23-Sep-16

30 Replacement HW/CW Pumps In Service 0 0 21-Dec-15* 21-Dec-15 0%

31 Temp Heat Ready To Run 0 0 21-Dec-15 21-Dec-15 0%

32 Initial Energization 0 0 17-Feb-16 17-Feb-16 0%

33 Mechanical Piping Complete & Flushed 0 0 17-Feb-16 17-Feb-16 0%

34 Intitial AHU Air Run 1st Floor 0 0 24-Feb-16 24-Feb-16 0%

35 Initial AHU Air Run 2nd Floor 0 0 24-Feb-16 24-Feb-16 0%

36 All Coil Connections Complete 5 5 24-Feb-16 01-Mar-16 0%

37 MEP Running Under Control 0 0 18-Mar-16 18-Mar-16 0%

38 Prime & 1st Coat & Building Clean Complete 1 1 17-Mar-16 17-Mar-16 0%

39 Complete Loop Tuning 7 7 18-Mar-16 28-Mar-16 0%

40 Test & Balance Water/Air 20 20 15-Mar-16 11-Apr-16 0%

41 Fire Alarm Test Complete 58 58 12-Apr-16 01-Jul-16 0%

42 Commisioning Complete 58 58 05-Jul-16 23-Sep-16 0%

43 MEP Equipment Install & Startup 50 50 07-Dec-15 16-Feb-16

44 Replace Existing HW/CW Pumps In Mechanical Room 10 10 07-Dec-15 18-Dec-15 0% North Umpqua, Essential, Reynolds

45 HW & CW Pump Startup 5 5 15-Dec-15 21-Dec-15 0% Essential, North Umpqua, Reynolds

46 Install Switch Gear 5 5 10-Feb-16 16-Feb-16 0% Reynolds

47 Install Electrical Distribution 5 5 10-Feb-16 16-Feb-16 0% Reynolds

48 Install AHU-1, AHU-2 & AHU-3 5 5 24-Dec-15 31-Dec-15 0% FM, North Umpqua

49 MEP @ AHU-1, AHU-2 & AHU-3 10 10 04-Jan-16 15-Jan-16 0% North Umpqua, Reynolds, FM, North Umpqua, Essential

50 AHU-1, AHU-2 & AHU-3 Startup 5 5 18-Jan-16 22-Jan-16 0% FM, North Umpqua, Essential, North Umpqua, Reynolds

51 Install EF-1, EF-2 & EF-3 3 3 24-Dec-15 29-Dec-15 0% FM, Essential

52 Connect Electrical/Controls @ EF-1, EF-2 & EF-3 2 2 30-Dec-15 31-Dec-15 0% FM, Essential, Reynolds

53 EF-1, EF-2 & EF-3 Startup 2 2 04-Jan-16 05-Jan-16 0% FM, Essential, Reynolds

54 Underground Civil Outside 5' Outside Of Perimeter 33 33 30-Nov-15 A 15-Jan-16

55 Footing Drains 5 5 30-Nov-15 A 04-Dec-15

56 Complete Drain Rock Around Building Perimeter 5 5 30-Nov-15 A 04-Dec-15 0% North Umpqua, Knife River

57 West Concrete & South Utilities 4 1 30-Nov-15 A 30-Nov-15

Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct

2015 2016

28-Sep-16, HNSB 11.30.15

28-Sep-16, Health, Nursing & Science Building

19-Apr-16, Design & Engineering

19-Apr-16, Package 2 Long Lead

Door Frames

Elevator & Equipment

Lighting

Electrical Gear

HW & CW Pumps

AHU's 1, 2 & 3

Exhaust Fans

Mechanical Room Equipment

Generator

Aluminum Storefront System & Glazing

Exterior Rain Screen

Exterior Sheet Metal

Lab Equipment

Lab Casework/Countertops

Contractor Supplied Furniture

Doors & Hardware

28-Sep-16, Construction Phase

28-Sep-16, Building Milestones

Roof Complete & Building Dried In

Interior Rough In Complete

Interior Finishes Complete

Site Finishes & Landscaping Complete

Substantial Completion

CO

23-Sep-16, MEP Milestones

Replacement HW/CW Pumps In Service

Temp Heat Ready To Run

Initial Energization

Mechanical Piping Complete & Flushed

Intitial AHU Air Run 1st Floor

Initial AHU Air Run 2nd Floor

All Coil Connections Complete

MEP Running Under Control

Prime & 1st Coat & Building Clean Complete

Complete Loop Tuning

Test & Balance Water/Air

Fire Alarm Test Complete

Commisioning Complete

16-Feb-16, MEP Equipment Install & Startup

Replace Existing HW/CW Pumps In Mechanical Room

HW & CW Pump Startup

Install Switch Gear

Install Electrical Distribution

Install AHU-1, AHU-2 & AHU-3

MEP @ AHU-1, AHU-2 & AHU-3

AHU-1, AHU-2 & AHU-3 Startup

Install EF-1, EF-2 & EF-3

Connect Electrical/Controls @ EF-1, EF-2 & EF-3

EF-1, EF-2 & EF-3 Startup

15-Jan-16, Underground Civil Outside 5' Outside Of Perimeter

04-Dec-15, Footing Drains

Complete Drain Rock Around Building Perimeter

30-Nov-15, West Concrete & South Utilities

UCC Weekly Overall Sub Update 30-Nov-15 10:55

Page 1 of 21

Page 2: HNSB 11.30.15 Health, Nursing & Science Building...28-Sep-16, HNSB 11.30.15 28-Sep-16, Health, Nursing & Science Building 19-Apr-16, Design & Engineering 19-Apr-16, Package 2 Long

# Activity Name OriginalDuration

RemainingDuration

Start Finish Activity %Complete

Resources

58 Complete SD & FDC Piping 4 1 30-Nov-15 A 30-Nov-15 75% Knife River

59 East Civil/Fire Lane 33 33 30-Nov-15 15-Jan-16

60 Fire Hydrant Supply 9 9 30-Nov-15 10-Dec-15

61 Install 12"X 8"Gate Valve & Block/Restrain 2 2 30-Nov-15 01-Dec-15 0% Knife River

62 Install 8" 22-1/2 MJ Bend & Block/Restrain 2 2 02-Dec-15 03-Dec-15 0% Knife River

63 Install 2" Temp Blowoff, For Tie In Install 8" MJ Sleeve & 8" DI Spool 2 2 04-Dec-15 07-Dec-15 0% Knife River

64 Test & Inspections 1 1 08-Dec-15 08-Dec-15 0% Knife River, Fire Marshall, County, UCC

65 Cap Pipe @ New Hydrant Location & Backfill 2 2 09-Dec-15 10-Dec-15 0% Knife River

66 Fire Lane Demo & Civil 24 24 11-Dec-15 15-Jan-16

67 Demo Existing Fire Lane 5 5 11-Dec-15 17-Dec-15 0% Knife River

68 Pothole, Locate & Reroute Existing Gas Lines 7 7 18-Dec-15 29-Dec-15 0% Knife River

69 Cut Tree Roots 1 1 30-Dec-15 30-Dec-15 0% Knife River

70 Install/Compact Base For New Fire Lane 5 5 31-Dec-15 07-Jan-16 0% Knife River

71 Remove Catch Basin, Install Cleanout & Install New Catch Basin 2 2 08-Jan-16 11-Jan-16 0% Knife River

72 Replace Catch Basins, Set Inlets To Elevation & Connect To Existing Storm2 2 12-Jan-16 13-Jan-16 0% Knife River

73 Replace Catch Basin & Install New Basin Near Admin Building 2 2 14-Jan-16 15-Jan-16 0% Knife River

74 Test & Inspections 1 1 15-Jan-16 15-Jan-16 0% County, UCC, Knife River

75 Exterior Facade 82 74 16-Nov-15 A 14-Mar-16

76 West Elevation 60 52 16-Nov-15 A 11-Feb-16

77 Install Roof Soffit/Parapet 5 2 16-Nov-15 A 01-Dec-15 60% Harver

78 Layout & Install Exterior Framing 10 6 16-Nov-15 A 07-Dec-15 40% Harver

79 Framing Inspections 2 1 30-Nov-15 A 30-Nov-15 50% Special Inspection, County

80 Install Exterior Sheathing 5 5 01-Dec-15 07-Dec-15 0% Harver

81 Sheathing Inspection 1 1 07-Dec-15 07-Dec-15 0% County

82 Install Exterior Weather Barrier 5 5 08-Dec-15 14-Dec-15 0% Weather Barrier

83 Install Hollow Metal Door Frames 2 2 21-Dec-15 22-Dec-15 0% Harver

84 Install Flashing Details 5 5 23-Dec-15 30-Dec-15 0% FM Ext

85 Install Aluminum Store Front/Glazing System SF-1 5 5 30-Dec-15 06-Jan-16 0% Culver

86 Install Rigid Installation 5 5 06-Jan-16 12-Jan-16 0% Harver Insulation

87 Install Insect Screen, Furring Strips & Wood Rain Screen System 8 8 08-Jan-16 19-Jan-16 0% Siding Specialist

88 Install Metal Furring, Mineral Wool, 2" X 4" & Concrete Tile 6 6 15-Jan-16 22-Jan-16 0% Siding Specialist

89 Install Plate Steel Trim/Closure Piece W/Clear Sealer 3 3 25-Jan-16 27-Jan-16 0% FM Ext

90 Install Aluminum Storefront Systems 5 5 27-Jan-16 02-Feb-16 0% Culver

91 Exterior Painting 5 5 01-Feb-16 05-Feb-16 0% WPI Paint

92 Exterior Punch & Corrections 5 5 04-Feb-16 10-Feb-16 0% Opsis, ACCO

93 Back Punch 2 2 10-Feb-16 11-Feb-16 0% UCC, ACCO

94 North Elevation 66 64 16-Nov-15 A 29-Feb-16

95 Layout & Install Exterior Framing 10 3 16-Nov-15 A 02-Dec-15 70% Harver

96 Framing Inspections 3 3 30-Nov-15 02-Dec-15 0% County, Special Inspection

97 Install Exterior Sheathing 8 8 01-Dec-15 10-Dec-15 0% Harver

98 Sheathing Inspection 2 2 09-Dec-15 10-Dec-15 0% County

99 Install Exterior Weather Barrier 10 10 15-Dec-15 29-Dec-15 0% Weather Barrier

100 Install Flashing Details 6 6 28-Dec-15 05-Jan-16 0% FM Ext

101 Install Aluminum Store Front System SF-1 10 10 04-Jan-16 15-Jan-16 0% Culver

102 Install Rigid Insulation 7 7 14-Jan-16 22-Jan-16 0% Harver Insulation

103 Install Insect Screen, Furring Strips & Wood Rain Screen System 10 10 20-Jan-16 02-Feb-16 0% Siding Specialist

104 Install Metal Furring, Mineral Wool, 2" X 4" & Concrete Tile 10 10 29-Jan-16 11-Feb-16 0% Siding Specialist

105 Install Plate Steel Trim/Closure Piece W/Clear Sealer 5 5 10-Feb-16 16-Feb-16 0% FM Ext

106 Exterior Painting 5 5 16-Feb-16 22-Feb-16 0% WPI Paint

107 Exterior Punch & Corrections 5 5 19-Feb-16 25-Feb-16 0% Opsis, ACCO

108 Back Punch 2 2 26-Feb-16 29-Feb-16 0% UCC, ACCO

109 East Elevation 70 70 30-Nov-15 A 08-Mar-16

110 Layout & Install Exterior Framing 10 9 30-Nov-15 A 10-Dec-15 10% Harver

111 Framing Inspections 2 2 09-Dec-15 10-Dec-15 0% County, Special Inspection

112 Install Exterior Sheathing 7 7 09-Dec-15 17-Dec-15 0% Harver

113 Sheathing Inspection 1 1 17-Dec-15 17-Dec-15 0% County, O & S

114 Install Exterior Weather Barrier 5 5 14-Jan-16 20-Jan-16 0% Weather Barrier

115 Install Flashing Details 5 5 21-Jan-16 27-Jan-16 0% FM Ext

Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct

2015 2016

Complete SD & FDC Piping

15-Jan-16, East Civil/Fire Lane

10-Dec-15, Fire Hydrant Supply

Install 12"X 8"Gate Valve & Block/Restrain

Install 8" 22-1/2 MJ Bend & Block/Restrain

Install 2" Temp Blowoff, For Tie In Install 8" MJ Sleeve & 8" DI Spool

Test & Inspections

Cap Pipe @ New Hydrant Location & Backfill

15-Jan-16, Fire Lane Demo & Civil

Demo Existing Fire Lane

Pothole, Locate & Reroute Existing Gas Lines

Cut Tree Roots

Install/Compact Base For New Fire Lane

Remove Catch Basin, Install Cleanout & Install New Catch Basin

Replace Catch Basins, Set Inlets To Elevation & Connect To Existing Storm

Replace Catch Basin & Install New Basin Near Admin Building

Test & Inspections

14-Mar-16, Exterior Facade

11-Feb-16, West Elevation

Install Roof Soffit/Parapet

Layout & Install Exterior Framing

Framing Inspections

Install Exterior Sheathing

Sheathing Inspection

Install Exterior Weather Barrier

Install Hollow Metal Door Frames

Install Flashing Details

Install Aluminum Store Front/Glazing System SF-1

Install Rigid Installation

Install Insect Screen, Furring Strips & Wood Rain Screen System

Install Metal Furring, Mineral Wool, 2" X 4" & Concrete Tile

Install Plate Steel Trim/Closure Piece W/Clear Sealer

Install Aluminum Storefront Systems

Exterior Painting

Exterior Punch & Corrections

Back Punch

29-Feb-16, North Elevation

Layout & Install Exterior Framing

Framing Inspections

Install Exterior Sheathing

Sheathing Inspection

Install Exterior Weather Barrier

Install Flashing Details

Install Aluminum Store Front System SF-1

Install Rigid Insulation

Install Insect Screen, Furring Strips & Wood Rain Screen System

Install Metal Furring, Mineral Wool, 2" X 4" & Concrete Tile

Install Plate Steel Trim/Closure Piece W/Clear Sealer

Exterior Painting

Exterior Punch & Corrections

Back Punch

08-Mar-16, East Elevation

Layout & Install Exterior Framing

Framing Inspections

Install Exterior Sheathing

Sheathing Inspection

Install Exterior Weather Barrier

Install Flashing Details

UCC Weekly Overall Sub Update 30-Nov-15 10:55

Page 2 of 21

Page 3: HNSB 11.30.15 Health, Nursing & Science Building...28-Sep-16, HNSB 11.30.15 28-Sep-16, Health, Nursing & Science Building 19-Apr-16, Design & Engineering 19-Apr-16, Package 2 Long

# Activity Name OriginalDuration

RemainingDuration

Start Finish Activity %Complete

Resources

116 Install Aluminum Store Front System SF-1 5 5 27-Jan-16 02-Feb-16 0% Culver

117 Install Rigid Insulation 5 5 02-Feb-16 08-Feb-16 0% Harver Insulation

118 Install Insect Screen, Furring Strips & Wood Rain Screen System 10 10 04-Feb-16 17-Feb-16 0% Siding Specialist

119 Install Metal Furring, Mineral Wool, 2" X 4" & Concrete Tile 7 7 15-Feb-16 23-Feb-16 0% Siding Specialist

120 Install Plate Steel Trim/Closure Piece W/Clear Sealer 3 3 24-Feb-16 26-Feb-16 0% FM Ext

121 Install Aluminum Store Front Systems 5 5 26-Feb-16 03-Mar-16 0% Culver

122 Exterior Painting 5 5 25-Feb-16 02-Mar-16 0% WPI Paint

123 Exterior Punch & Corrections 5 5 01-Mar-16 07-Mar-16 0% Opsis, ACCO

124 Back Punch 2 2 07-Mar-16 08-Mar-16 0% UCC, ACCO

125 South Elevation 70 70 04-Dec-15 14-Mar-16

126 Layout & Install Exterior Framing 10 10 04-Dec-15 17-Dec-15 0% Harver

127 Framing Inspections 4 4 14-Dec-15 17-Dec-15 0% Special Inspection, County

128 Install Exterior Sheathing 8 8 14-Dec-15 23-Dec-15 0% Harver

129 Sheathing Inspection 2 2 23-Dec-15 24-Dec-15 0% County

130 Install Exterior Weather Barrier 10 10 30-Dec-15 13-Jan-16 0% Weather Barrier

131 Install Flashing Details 6 6 12-Jan-16 19-Jan-16 0% FM Ext

132 Install Aluminum Store Front System SF-1 10 10 18-Jan-16 29-Jan-16 0% Culver

133 Install Rigid Insulation 7 7 28-Jan-16 05-Feb-16 0% Siding Specialist

134 Install Insect Screen, Furring Strips & Wood Rain Screen System 10 10 03-Feb-16 16-Feb-16 0% Siding Specialist

135 Install Metal Furring, Mineral Wool, 2" x 4" & Concrete Tile 10 10 12-Feb-16 25-Feb-16 0% Siding Specialist

136 Install Plate Steel Trim/Closure Piece W/Clear Sealer 5 5 24-Feb-16 01-Mar-16 0% FM Ext

137 Exterior Painting 5 5 01-Mar-16 07-Mar-16 0% WPI Paint

138 Exterior Punch & Corrections 5 5 04-Mar-16 10-Mar-16 0% Opsis, ACCO

139 Back Punch 2 2 11-Mar-16 14-Mar-16 0% UCC, ACCO

140 Roofing Installation 42 34 16-Nov-15 A 18-Jan-16

141 Install Roof Drains, Mech Curbs & MEP Penetrating Roof 10 5 16-Nov-15 A 04-Dec-15 50% North Umpqua, FM, Reynolds

142 Install PT Parapet Cap & Roof Hatch 9 9 30-Nov-15 10-Dec-15 0% Rough Carpentry

143 Install Parapet Sheathing 5 5 30-Nov-15 04-Dec-15 0% Harver

144 Install Roofing Insulation 10 10 03-Dec-15 16-Dec-15 0% Umpqua Roofing-1

145 Install Roofing Membrane 10 10 10-Dec-15 23-Dec-15 0% Umpqua Roofing-1

146 Install Penetration Flashing Details 5 5 22-Dec-15 29-Dec-15 0% Umpqua Roofing-1

147 Install Mechanical Curb Flashing Details 5 5 28-Dec-15 04-Jan-16 0% FM Ext

148 Install Parapet Flashing Details 10 10 05-Jan-16 18-Jan-16 0% FM Ext

149 Skylight 64 61 23-Nov-15 A 24-Feb-16

150 Field Measure For Skylights 1 1 30-Nov-15 30-Nov-15 0% DeMor

151 Install Wood Cap 2 2 30-Nov-15 01-Dec-15 0% ASI

152 Install Exterior Sheathing 1 1 02-Dec-15 02-Dec-15 0% Harver

153 Install SAM & Metal Flashing Details 5 5 03-Dec-15 09-Dec-15 0% LDC, FM Ext

154 Deliver & Install Skylights 60 60 23-Nov-15 A 23-Feb-16 0% DeMor

155 Inspection 1 1 24-Feb-16 24-Feb-16 0% County

156 Interior Rough In 80 83 30-Nov-15 A 25-Mar-16

157 Level 1 51 54 30-Nov-15 A 15-Feb-16

158 Mech, Riser, Elec Closet, Elevator Control & Shafts 31 34 30-Nov-15 A 18-Jan-16

159 Layout/Framing/Backing 5 5 30-Nov-15 A 04-Dec-15 0% Harver

160 Install Door Frames 1 1 21-Dec-15 21-Dec-15 0% Harver

161 MEP Rough In 10 10 03-Dec-15 16-Dec-15 0% FM, North Umpqua, Essential, Data, O & S, North Umpqua, Reynolds

162 Inspections To Cover Walls 1 1 16-Dec-15 16-Dec-15 0% County

163 QC Doors & Backing 1 1 16-Dec-15 16-Dec-15 0% Harver

164 Install Required Insulation 1 1 24-Dec-15 24-Dec-15 0% Harver

165 Hang Gyp 2 2 28-Dec-15 29-Dec-15 0% Harver

166 Tape Gyp 5 5 30-Dec-15 06-Jan-16 0% Harver

167 Install Fire Stopping Details 1 1 07-Jan-16 07-Jan-16 0% Harver

168 Prime & 1st Coat 2 2 08-Jan-16 11-Jan-16 0% WPI Paint

169 Layout/Form Equipment Pads @ Mechanical Room 2 2 11-Jan-16 12-Jan-16 0% Gerding, North Umpqua, Essential, North Umpqua, Reynolds

170 Inspection @ Equipment Pads 1 1 13-Jan-16 13-Jan-16 0% County, Special Inspection

171 Pour Equipment Pads In Mechanical Room 1 1 14-Jan-16 14-Jan-16 0% Gerding

172 Paint & Install FT Ply @ Telecom Room 2 2 15-Jan-16 18-Jan-16 0% WPI Paint

173 Install Temp Doors W/Locks 1 1 18-Jan-16 18-Jan-16 0% ASI

Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct

2015 2016

Install Aluminum Store Front System SF-1

Install Rigid Insulation

Install Insect Screen, Furring Strips & Wood Rain Screen System

Install Metal Furring, Mineral Wool, 2" X 4" & Concrete Tile

Install Plate Steel Trim/Closure Piece W/Clear Sealer

Install Aluminum Store Front Systems

Exterior Painting

Exterior Punch & Corrections

Back Punch

14-Mar-16, South Elevation

Layout & Install Exterior Framing

Framing Inspections

Install Exterior Sheathing

Sheathing Inspection

Install Exterior Weather Barrier

Install Flashing Details

Install Aluminum Store Front System SF-1

Install Rigid Insulation

Install Insect Screen, Furring Strips & Wood Rain Screen System

Install Metal Furring, Mineral Wool, 2" x 4" & Concrete Tile

Install Plate Steel Trim/Closure Piece W/Clear Sealer

Exterior Painting

Exterior Punch & Corrections

Back Punch

18-Jan-16, Roofing Installation

Install Roof Drains, Mech Curbs & MEP Penetrating Roof

Install PT Parapet Cap & Roof Hatch

Install Parapet Sheathing

Install Roofing Insulation

Install Roofing Membrane

Install Penetration Flashing Details

Install Mechanical Curb Flashing Details

Install Parapet Flashing Details

24-Feb-16, Skylight

Field Measure For Skylights

Install Wood Cap

Install Exterior Sheathing

Install SAM & Metal Flashing Details

Deliver & Install Skylights

Inspection

25-Mar-16, Interior Rough In

15-Feb-16, Level 1

18-Jan-16, Mech, Riser, Elec Closet, Elevator Control & Shafts

Layout/Framing/Backing

Install Door Frames

MEP Rough In

Inspections To Cover Walls

QC Doors & Backing

Install Required Insulation

Hang Gyp

Tape Gyp

Install Fire Stopping Details

Prime & 1st Coat

Layout/Form Equipment Pads @ Mechanical Room

Inspection @ Equipment Pads

Pour Equipment Pads In Mechanical Room

Paint & Install FT Ply @ Telecom Room

Install Temp Doors W/Locks

UCC Weekly Overall Sub Update 30-Nov-15 10:55

Page 3 of 21

Page 4: HNSB 11.30.15 Health, Nursing & Science Building...28-Sep-16, HNSB 11.30.15 28-Sep-16, Health, Nursing & Science Building 19-Apr-16, Design & Engineering 19-Apr-16, Package 2 Long

# Activity Name OriginalDuration

RemainingDuration

Start Finish Activity %Complete

Resources

174 Start MEP Equipment Install 1 1 18-Jan-16 18-Jan-16 0% TK, FM, North Umpqua, Data, Essential, Reynolds, North Umpqua

175 Restrooms, Janitor & Storage 31 31 07-Dec-15 20-Jan-16

176 Layout/Framing/Backing 3 3 07-Dec-15 09-Dec-15 0% Harver

177 Install Door Frames 1 1 21-Dec-15 21-Dec-15 0% Harver

178 MEP Rough In 5 5 07-Dec-15 11-Dec-15 0% FM, North Umpqua, Essential, O & S, North Umpqua, Reynolds

179 Layout Access Doors @ Restroom Walls 1 1 11-Dec-15 11-Dec-15 0% North Umpqua

180 MEP/Framing Inspections To Cover Walls 2 2 14-Dec-15 15-Dec-15 0% County

181 Quality Control Doors & Backing 1 1 14-Dec-15 14-Dec-15 0% Harver

182 Install Acoustical Insulation 1 1 15-Dec-15 15-Dec-15 0% Harver

183 Hang Gyp 3 3 24-Dec-15 29-Dec-15 0% Harver

184 Install Ceiling Framing @ Restrooms 2 2 30-Dec-15 31-Dec-15 0% Harver

185 Complete Above Ceiling MEP 4 4 04-Jan-16 07-Jan-16 0% O & S, FM, North Umpqua, Data, Essential, North Umpqua

186 Layout Access Doors @ Ceilings 1 1 08-Jan-16 08-Jan-16 0% Harver, FM, North Umpqua, Data, Essential, Reynolds, North Umpqua

187 MEP/Framing Inspections To Cover Ceilings 1 1 08-Jan-16 08-Jan-16 0% County

188 Install Gyp @ Restroom Ceilings 2 2 11-Jan-16 12-Jan-16 0% Harver

189 Install Access Doors @ Walls & Ceilings 1 1 11-Jan-16 11-Jan-16 0% Harver

190 Tape Gyp 5 5 12-Jan-16 18-Jan-16 0% Harver

191 Prime & 1st Coat 2 2 19-Jan-16 20-Jan-16 0% WPI Paint

192 Common Hallways & Vestibules 32 32 07-Dec-15 21-Jan-16

193 Layout/Framing/Backing 6 6 08-Dec-15 15-Dec-15 0% Harver

194 MEP Rough In 10 10 07-Dec-15 18-Dec-15 0% FM, North Umpqua, Data, Essential, O & S, Reynolds, North Umpqua

195 MEP/Framing Inspections To Cover Walls 2 2 17-Dec-15 18-Dec-15 0% County

196 Quality Control Doors & Backing 1 1 16-Dec-15 16-Dec-15 0% Harver

197 Hang & Tape Gyp @ Walls 7 7 24-Dec-15 05-Jan-16 0% Harver

198 Prime & 1st Coat 4 4 06-Jan-16 11-Jan-16 0% WPI Paint

199 Install Ceiling Framing 4 4 12-Jan-16 15-Jan-16 0% Harver

200 Complete Above Ceiling MEP 5 5 14-Jan-16 20-Jan-16 0% North Umpqua, Data, Essential, North Umpqua, Reynolds, O & S, FM

201 Layout Access Doors In Ceilings 1 1 20-Jan-16 20-Jan-16 0% Reynolds, Harver, FM, North Umpqua, Data, Essential, North Umpqua

202 MEP/Framing Inspections To Cover Ceilings 2 2 20-Jan-16 21-Jan-16 0% County

203 Labs 35 35 14-Dec-15 02-Feb-16

204 Layout/Framing/Backing 6 6 14-Dec-15 21-Dec-15 0% Harver

205 Install Door Frames 2 2 21-Dec-15 22-Dec-15 0% Harver

206 Frame Ceiling Soffits 8 8 22-Dec-15 04-Jan-16 0% Harver

207 MEP Rough In 15 15 14-Dec-15 05-Jan-16 0% O & S, FM, North Umpqua, Data, Essential, North Umpqua, Reynolds

208 Layout Access Doors 1 1 05-Jan-16 05-Jan-16 0% Harver, North Umpqua, North Umpqua

209 MEP/Framing Inspections To Cover Walls 2 2 05-Jan-16 06-Jan-16 0% County

210 Quality Control Doors & Backing 2 2 05-Jan-16 06-Jan-16 0% Harver

211 Install Acoustical Insulation 3 3 06-Jan-16 08-Jan-16 0% Harver

212 Hang Gyp 5 5 07-Jan-16 13-Jan-16 0% Harver

213 Install Access Doors 2 2 12-Jan-16 13-Jan-16 0% Harver

214 Tape Gyp 7 7 13-Jan-16 21-Jan-16 0% Harver

215 Complete Above Ceiling MEP 5 5 21-Jan-16 27-Jan-16 0% Essential, North Umpqua, O & S, FM, North Umpqua, Data

216 Prime & 1st Coat 4 4 28-Jan-16 02-Feb-16 0% WPI Paint

217 Classrooms 34 34 16-Dec-15 03-Feb-16

218 Layout/Framing/Backing @ Walls 4 4 18-Dec-15 23-Dec-15 0% Harver

219 Install Door Frames 2 2 16-Dec-15 17-Dec-15 0% Harver

220 Frame Ceiling Soffits 3 3 18-Dec-15 22-Dec-15 0% Harver

221 MEP Rough In 10 10 23-Dec-15 07-Jan-16 0% O & S, FM, North Umpqua, Data, Essential, North Umpqua, Reynolds

222 MEP/Framing Inspections 2 2 07-Jan-16 08-Jan-16 0% County

223 Quality Control Doors & Backing 1 1 07-Jan-16 07-Jan-16 0% Harver

224 Install Acoustical Insulation 2 2 08-Jan-16 11-Jan-16 0% Harver

225 Hang Gyp 4 4 12-Jan-16 15-Jan-16 0% Harver

226 Tape Gyp 5 5 18-Jan-16 22-Jan-16 0% Harver

227 Complete Above Ceiling MEP 5 5 22-Jan-16 28-Jan-16 0% O & S, FM, North Umpqua, Data, Essential, Reynolds, North Umpqua

228 Prime & 1st Coat 4 4 29-Jan-16 03-Feb-16 0% WPI Paint

229 Conference, Meeting & Work Rooms 28 28 22-Dec-15 01-Feb-16

230 Layout/Framing/Backing 3 3 24-Dec-15 29-Dec-15 0% Harver

231 Install Door Frames 2 2 22-Dec-15 23-Dec-15 0% Harver

Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct

2015 2016

Start MEP Equipment Install

20-Jan-16, Restrooms, Janitor & Storage

Layout/Framing/Backing

Install Door Frames

MEP Rough In

Layout Access Doors @ Restroom Walls

MEP/Framing Inspections To Cover Walls

Quality Control Doors & Backing

Install Acoustical Insulation

Hang Gyp

Install Ceiling Framing @ Restrooms

Complete Above Ceiling MEP

Layout Access Doors @ Ceilings

MEP/Framing Inspections To Cover Ceilings

Install Gyp @ Restroom Ceilings

Install Access Doors @ Walls & Ceilings

Tape Gyp

Prime & 1st Coat

21-Jan-16, Common Hallways & Vestibules

Layout/Framing/Backing

MEP Rough In

MEP/Framing Inspections To Cover Walls

Quality Control Doors & Backing

Hang & Tape Gyp @ Walls

Prime & 1st Coat

Install Ceiling Framing

Complete Above Ceiling MEP

Layout Access Doors In Ceilings

MEP/Framing Inspections To Cover Ceilings

02-Feb-16, Labs

Layout/Framing/Backing

Install Door Frames

Frame Ceiling Soffits

MEP Rough In

Layout Access Doors

MEP/Framing Inspections To Cover Walls

Quality Control Doors & Backing

Install Acoustical Insulation

Hang Gyp

Install Access Doors

Tape Gyp

Complete Above Ceiling MEP

Prime & 1st Coat

03-Feb-16, Classrooms

Layout/Framing/Backing @ Walls

Install Door Frames

Frame Ceiling Soffits

MEP Rough In

MEP/Framing Inspections

Quality Control Doors & Backing

Install Acoustical Insulation

Hang Gyp

Tape Gyp

Complete Above Ceiling MEP

Prime & 1st Coat

01-Feb-16, Conference, Meeting & Work Rooms

Layout/Framing/Backing

Install Door Frames

UCC Weekly Overall Sub Update 30-Nov-15 10:55

Page 4 of 21

Page 5: HNSB 11.30.15 Health, Nursing & Science Building...28-Sep-16, HNSB 11.30.15 28-Sep-16, Health, Nursing & Science Building 19-Apr-16, Design & Engineering 19-Apr-16, Package 2 Long

# Activity Name OriginalDuration

RemainingDuration

Start Finish Activity %Complete

Resources

232 Frame Ceiling Soffit @ 121 1 1 24-Dec-15 24-Dec-15 0% Harver

233 MEP Rough In 10 10 24-Dec-15 08-Jan-16 0% Essential, Fire Marshall, FM, North Umpqua, Data, North Umpqua, Reynolds

234 MEP/Framing Inspections 1 1 08-Jan-16 08-Jan-16 0% County

235 Quality Control Doors & Backing 1 1 08-Jan-16 08-Jan-16 0% Harver

236 Install Acoustical Insulation 1 1 11-Jan-16 11-Jan-16 0% Harver

237 Hang Gyp 3 3 12-Jan-16 14-Jan-16 0% Harver

238 Tape Gyp 5 5 15-Jan-16 21-Jan-16 0% Harver

239 Complete Above Ceiling MEP 4 4 21-Jan-16 26-Jan-16 0% O & S, FM, North Umpqua, Data, Essential, North Umpqua, Reynolds

240 Prime & 1st Coat 4 4 27-Jan-16 01-Feb-16 0% WPI Paint

241 Offices 33 33 30-Dec-15 15-Feb-16

242 Layout/Framing/Backing 3 3 30-Dec-15 04-Jan-16 0% Harver

243 Install Door Frames 2 2 05-Jan-16 06-Jan-16 0% Harver

244 Frame Ceiling Soffits 3 3 05-Jan-16 07-Jan-16 0% Harver

245 MEP Rough In 10 10 06-Jan-16 19-Jan-16 0% O & S, FM, North Umpqua, Data, Essential, Reynolds, North Umpqua

246 MEP/Framing Inspections 2 2 19-Jan-16 20-Jan-16 0% County

247 Quality Control Doors & Backing 1 1 21-Jan-16 21-Jan-16 0% Harver

248 Install Acoustical Insulation 2 2 22-Jan-16 25-Jan-16 0% Harver

249 Hang Gyp 4 4 26-Jan-16 29-Jan-16 0% Harver

250 Tape Gyp 5 5 28-Jan-16 03-Feb-16 0% Harver

251 Complete Above Ceiling MEP 5 5 02-Feb-16 08-Feb-16 0% Reynolds, O & S, FM, North Umpqua, Data, Essential, North Umpqua

252 Prime & 1st Coat 5 5 09-Feb-16 15-Feb-16 0% WPI Paint

253 Level 2 54 54 04-Jan-16 17-Mar-16

254 Restrooms, MDF & Storage 35 35 04-Jan-16 19-Feb-16

255 Layout/Framing/Backing 3 3 05-Jan-16 07-Jan-16 0% Harver

256 Install Door Frames 1 1 04-Jan-16 04-Jan-16 0% Harver

257 MEP Rough In 10 10 04-Jan-16 15-Jan-16 0% O & S, FM, North Umpqua, Data, Essential, North Umpqua, Reynolds

258 Layout & Install Access Doors @ Restroom Walls 1 1 18-Jan-16 18-Jan-16 0% North Umpqua

259 MEP/Framing Inspections To Cover Walls 2 2 19-Jan-16 20-Jan-16 0% County

260 Quality Control Doors & Backing 1 1 19-Jan-16 19-Jan-16 0% Harver

261 Install Acoustical Insulation 1 1 20-Jan-16 20-Jan-16 0% Harver

262 Hang Gyp @ Walls 3 3 21-Jan-16 25-Jan-16 0% Harver

263 Install Ceiling Framing @ Restrooms 3 3 26-Jan-16 28-Jan-16 0% Harver

264 Complete Above Ceiling MEP 4 4 29-Jan-16 03-Feb-16 0% Essential, Reynolds, North Umpqua, O & S, FM, North Umpqua, Data

265 Layout Access Doors @ Ceilings 1 1 04-Feb-16 04-Feb-16 0% FM, North Umpqua, Data, Essential, Reynolds

266 MEP/Framing Inspections To Cover Ceilings 1 1 05-Feb-16 05-Feb-16 0% County

267 Install Gyp @ Restroom Ceilings 2 2 08-Feb-16 09-Feb-16 0% Harver

268 Install Access Doors @ Walls & Ceilings 1 1 08-Feb-16 08-Feb-16 0% Harver

269 Tape Gyp 6 6 09-Feb-16 16-Feb-16 0% Harver

270 Prime & 1st Coat 3 3 17-Feb-16 19-Feb-16 0% WPI Paint

271 Common Hallways & Vestibules 27 27 06-Jan-16 11-Feb-16

272 Layout/Framing/Backing 10 10 06-Jan-16 19-Jan-16 0% Harver

273 MEP Rough In 10 10 08-Jan-16 21-Jan-16 0% O & S, FM, North Umpqua, Data, Essential, Reynolds, North Umpqua

274 MEP/Framing Inspections To Cover Walls 2 2 20-Jan-16 21-Jan-16 0% County

275 Quality Control Doors & Backing 1 1 21-Jan-16 21-Jan-16 0% Harver

276 Hang & Tape Gyp @ Walls 5 5 22-Jan-16 28-Jan-16 0% Harver

277 Prime & 1st Coat 4 4 27-Jan-16 01-Feb-16 0% Harver

278 Install Ceiling Framing 5 5 29-Jan-16 04-Feb-16 0% O & S, FM, North Umpqua, Data, Essential, Reynolds, North Umpqua

279 Complete Above Ceiling MEP 1 1 04-Feb-16 04-Feb-16 0% Data, Essential, Reynolds, FM, North Umpqua

280 Layout Access Doors In Ceilings 2 2 04-Feb-16 05-Feb-16 0% County

281 MEP/Framing Inspections To Cover Ceilings 4 4 08-Feb-16 11-Feb-16 0% Harver

282 Labs 46 46 14-Jan-16 17-Mar-16

283 Layout/Framing/Backing 5 5 18-Jan-16 22-Jan-16 0% Harver

284 Install Door Frames 3 3 14-Jan-16 18-Jan-16 0% Harver

285 Frame Ceiling Soffits 4 4 19-Jan-16 22-Jan-16 0% Harver

286 MEP Rough In 15 15 25-Jan-16 12-Feb-16 0% O & S, FM, North Umpqua, Data, Essential, Reynolds, North Umpqua

287 Layout Access Doors 1 1 12-Feb-16 12-Feb-16 0% North Umpqua, North Umpqua

288 MEP/Framing Inspections 2 2 11-Feb-16 12-Feb-16 0% County

289 Quality Control Doors & Backing 2 2 15-Feb-16 16-Feb-16 0% Harver

Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct

2015 2016

Frame Ceiling Soffit @ 121

MEP Rough In

MEP/Framing Inspections

Quality Control Doors & Backing

Install Acoustical Insulation

Hang Gyp

Tape Gyp

Complete Above Ceiling MEP

Prime & 1st Coat

15-Feb-16, Offices

Layout/Framing/Backing

Install Door Frames

Frame Ceiling Soffits

MEP Rough In

MEP/Framing Inspections

Quality Control Doors & Backing

Install Acoustical Insulation

Hang Gyp

Tape Gyp

Complete Above Ceiling MEP

Prime & 1st Coat

17-Mar-16, Level 2

19-Feb-16, Restrooms, MDF & Storage

Layout/Framing/Backing

Install Door Frames

MEP Rough In

Layout & Install Access Doors @ Restroom Walls

MEP/Framing Inspections To Cover Walls

Quality Control Doors & Backing

Install Acoustical Insulation

Hang Gyp @ Walls

Install Ceiling Framing @ Restrooms

Complete Above Ceiling MEP

Layout Access Doors @ Ceilings

MEP/Framing Inspections To Cover Ceilings

Install Gyp @ Restroom Ceilings

Install Access Doors @ Walls & Ceilings

Tape Gyp

Prime & 1st Coat

11-Feb-16, Common Hallways & Vestibules

Layout/Framing/Backing

MEP Rough In

MEP/Framing Inspections To Cover Walls

Quality Control Doors & Backing

Hang & Tape Gyp @ Walls

Prime & 1st Coat

Install Ceiling Framing

Complete Above Ceiling MEP

Layout Access Doors In Ceilings

MEP/Framing Inspections To Cover Ceilings

17-Mar-16, Labs

Layout/Framing/Backing

Install Door Frames

Frame Ceiling Soffits

MEP Rough In

Layout Access Doors

MEP/Framing Inspections

Quality Control Doors & Backing

UCC Weekly Overall Sub Update 30-Nov-15 10:55

Page 5 of 21

Page 6: HNSB 11.30.15 Health, Nursing & Science Building...28-Sep-16, HNSB 11.30.15 28-Sep-16, Health, Nursing & Science Building 19-Apr-16, Design & Engineering 19-Apr-16, Package 2 Long

# Activity Name OriginalDuration

RemainingDuration

Start Finish Activity %Complete

Resources

290 Install Acoustical Installation 3 3 17-Feb-16 19-Feb-16 0% Harver

291 Hang Gyp 5 5 18-Feb-16 24-Feb-16 0% Harver

292 Install Access Doors 2 2 23-Feb-16 24-Feb-16 0% Harver

293 Tape Gyp 7 7 25-Feb-16 04-Mar-16 0% Harver

294 Complete Above Ceiling MEP 5 5 04-Mar-16 10-Mar-16 0% O & S, FM, North Umpqua, Data, Essential, North Umpqua, Reynolds

295 Prime & 1st Coat 5 5 11-Mar-16 17-Mar-16 0% WPI Paint

296 Classrooms 31 31 20-Jan-16 02-Mar-16

297 Layout/Framing/Backing 4 4 21-Jan-16 26-Jan-16 0% Harver

298 Install Door Frames 2 2 20-Jan-16 21-Jan-16 0% Harver

299 Frame Ceiling Soffits 4 4 22-Jan-16 27-Jan-16 0% Harver

300 MEP Rough In 5 5 28-Jan-16 03-Feb-16 0% O & S, FM, North Umpqua, Data, Essential, North Umpqua, Reynolds

301 MEP/Framing Inspections 2 2 02-Feb-16 03-Feb-16 0% County

302 Quality Control Doors & Backing 1 1 02-Feb-16 02-Feb-16 0% Harver

303 Install Acoustical Insulation 2 2 03-Feb-16 04-Feb-16 0% Harver

304 Hang Gyp 4 4 05-Feb-16 10-Feb-16 0% Harver

305 Tape Gyp 6 6 11-Feb-16 18-Feb-16 0% Harver

306 Complete Above Ceiling MEP 5 5 18-Feb-16 24-Feb-16 0% Essential, O & S, FM, North Umpqua, Data, North Umpqua, Reynolds

307 Prime & 1st Coat 5 5 25-Feb-16 02-Mar-16 0% WPI Paint

308 Conference & Work Room 25 25 26-Jan-16 29-Feb-16

309 Layout/Framing/Backing 3 3 27-Jan-16 29-Jan-16 0% Harver

310 Install Door Frames 1 1 26-Jan-16 26-Jan-16 0% Harver

311 MEP Rough In 6 6 27-Jan-16 03-Feb-16 0% O & S, FM, North Umpqua, Data, Essential, North Umpqua, Reynolds

312 MEP/Framing Inspections 1 1 04-Feb-16 04-Feb-16 0% County

313 Quality Controls Doors & Backing 1 1 04-Feb-16 04-Feb-16 0% Harver

314 Install Acoustical Insualtion 1 1 05-Feb-16 05-Feb-16 0% Harver

315 Hang Gyp 2 2 08-Feb-16 09-Feb-16 0% Harver

316 Tape Gyp 6 6 10-Feb-16 17-Feb-16 0% Harver

317 Complete Above Ceiling MEP 5 5 17-Feb-16 23-Feb-16 0% O & S, FM, North Umpqua, Data, Essential, North Umpqua, Reynolds

318 Prime & 1st Coat 4 4 24-Feb-16 29-Feb-16 0% WPI Paint

319 Offices 34 34 29-Jan-16 16-Mar-16

320 Layout/Framing/Backing 4 4 01-Feb-16 04-Feb-16 0% Harver

321 Install Door Frames 2 2 29-Jan-16 01-Feb-16 0% Harver

322 Frame Ceiling Soffits 4 4 02-Feb-16 05-Feb-16 0% Harver

323 MEP Rough In 7 7 04-Feb-16 12-Feb-16 0% Data, Essential, North Umpqua, Reynolds, O & S, FM, North Umpqua

324 MEP/Framing Inspections 2 2 12-Feb-16 15-Feb-16 0% County

325 Quality Control Doors & Backing 1 1 16-Feb-16 16-Feb-16 0% Harver

326 Install Acoustical Insulation 2 2 17-Feb-16 18-Feb-16 0% Harver

327 Hang Gyp 4 4 19-Feb-16 24-Feb-16 0% Harver

328 Tape Gyp 6 6 25-Feb-16 03-Mar-16 0% Harver

329 Complete Above Ceiling MEP 5 5 03-Mar-16 09-Mar-16 0% O & S, FM, North Umpqua, Data, Essential, North Umpqua, Reynolds

330 Prime & 1st Coat 5 5 10-Mar-16 16-Mar-16 0% WPI Paint

331 Elevator 20 20 29-Feb-16 25-Mar-16

332 Deliver & Install Elevator 20 20 29-Feb-16 25-Mar-16 0% TK

333 Interior Finishes 98 98 17-Mar-16 03-Aug-16

334 Level 1 73 73 17-Mar-16 28-Jun-16

335 Restrooms 22 22 17-Mar-16 15-Apr-16

336 Mens 170 20 20 17-Mar-16 13-Apr-16

337 Uncover & Polish Floor - Install New Floor Protection 2 2 17-Mar-16 18-Mar-16 0% Floor Polish

338 Install Tile 3 3 21-Mar-16 23-Mar-16 0% Tile

339 Grout & Seal Tile 2 2 23-Mar-16 24-Mar-16 0% Tile

340 Install Lighting & Devices 1 1 25-Mar-16 25-Mar-16 0% Reynolds

341 Install Grills 1 1 28-Mar-16 28-Mar-16 0% FM

342 Install Plumbing Fixtures 2 2 29-Mar-16 30-Mar-16 0% North Umpqua

343 Install Partitions 2 2 30-Mar-16 31-Mar-16 0% Accessories

344 Install Accessories 2 2 31-Mar-16 01-Apr-16 0% Accessories

345 Install Door & Hardware 1 1 04-Apr-16 04-Apr-16 0% WPI Doors

346 Final Paint 1 1 05-Apr-16 05-Apr-16 0% WPI Paint

347 Uncover Floor & Final Buff 1 1 06-Apr-16 06-Apr-16 0% Floor Polish

Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct

2015 2016

Install Acoustical Installation

Hang Gyp

Install Access Doors

Tape Gyp

Complete Above Ceiling MEP

Prime & 1st Coat

02-Mar-16, Classrooms

Layout/Framing/Backing

Install Door Frames

Frame Ceiling Soffits

MEP Rough In

MEP/Framing Inspections

Quality Control Doors & Backing

Install Acoustical Insulation

Hang Gyp

Tape Gyp

Complete Above Ceiling MEP

Prime & 1st Coat

29-Feb-16, Conference & Work Room

Layout/Framing/Backing

Install Door Frames

MEP Rough In

MEP/Framing Inspections

Quality Controls Doors & Backing

Install Acoustical Insualtion

Hang Gyp

Tape Gyp

Complete Above Ceiling MEP

Prime & 1st Coat

16-Mar-16, Offices

Layout/Framing/Backing

Install Door Frames

Frame Ceiling Soffits

MEP Rough In

MEP/Framing Inspections

Quality Control Doors & Backing

Install Acoustical Insulation

Hang Gyp

Tape Gyp

Complete Above Ceiling MEP

Prime & 1st Coat

25-Mar-16, Elevator

Deliver & Install Elevator

03-Aug-16, Interior Finishes

28-Jun-16, Level 1

15-Apr-16, Restrooms

13-Apr-16, Mens 170

Uncover & Polish Floor - Install New Floor Protection

Install Tile

Grout & Seal Tile

Install Lighting & Devices

Install Grills

Install Plumbing Fixtures

Install Partitions

Install Accessories

Install Door & Hardware

Final Paint

Uncover Floor & Final Buff

UCC Weekly Overall Sub Update 30-Nov-15 10:55

Page 6 of 21

Page 7: HNSB 11.30.15 Health, Nursing & Science Building...28-Sep-16, HNSB 11.30.15 28-Sep-16, Health, Nursing & Science Building 19-Apr-16, Design & Engineering 19-Apr-16, Package 2 Long

# Activity Name OriginalDuration

RemainingDuration

Start Finish Activity %Complete

Resources

348 Final Clean 1 1 07-Apr-16 07-Apr-16 0% Cleaner

349 Punch & Corrections 3 3 08-Apr-16 12-Apr-16 0% Opsis, UCC

350 Back Punch 1 1 13-Apr-16 13-Apr-16 0% ACCO, UCC

351 Womens 171 20 20 21-Mar-16 15-Apr-16

352 Uncover & Polish Floor - Install New Floor Protection 2 2 21-Mar-16 22-Mar-16 0% Floor Polish

353 Install Tile 3 3 23-Mar-16 25-Mar-16 0% Tile

354 Grout & Seal Tile 2 2 25-Mar-16 28-Mar-16 0% Tile

355 Install Lighting & Devices 1 1 29-Mar-16 29-Mar-16 0% North Umpqua

356 Install Grills 1 1 29-Mar-16 29-Mar-16 0% Accessories

357 Install Plumbing Fixtures 2 2 30-Mar-16 31-Mar-16 0% Accessories

358 Install Partitions 2 2 01-Apr-16 04-Apr-16 0% Reynolds

359 Install Accessories 2 2 05-Apr-16 06-Apr-16 0% FM

360 Install Door & Hardware 1 1 07-Apr-16 07-Apr-16 0% WPI Doors

361 Final Paint 1 1 08-Apr-16 08-Apr-16 0% Cleaner

362 Uncover Floor & Final Buff 1 1 11-Apr-16 11-Apr-16 0% Opsis, UCC

363 Final Clean 1 1 12-Apr-16 12-Apr-16 0% ACCO, UCC

364 Punch & Corrections 2 2 13-Apr-16 14-Apr-16 0% Opsis, ACCO

365 Back Punch 1 1 15-Apr-16 15-Apr-16 0% UCC, ACCO

366 Support Rooms 15 15 22-Mar-16 11-Apr-16

367 Storage 173 12 12 22-Mar-16 06-Apr-16

368 Uncover & Polish Floor - Install New Floor Protection 2 2 22-Mar-16 23-Mar-16 0% Floor Polish

369 Install Lighting & Devices 1 1 24-Mar-16 24-Mar-16 0% Reynolds

370 Install Grills 1 1 25-Mar-16 25-Mar-16 0% FM

371 Install Door & Hardware 1 1 28-Mar-16 28-Mar-16 0% WPI Doors

372 Install Rubber Base 1 1 29-Mar-16 29-Mar-16 0% Flooring

373 Final Paint 1 1 30-Mar-16 30-Mar-16 0% WPI Paint

374 Uncover Floor & Final Buff 1 1 31-Mar-16 31-Mar-16 0% Floor Polish

375 Final Clean 1 1 01-Apr-16 01-Apr-16 0% Cleaner

376 Punch & Corrections 2 2 04-Apr-16 05-Apr-16 0% Opsis, UCC

377 Back Punch 1 1 06-Apr-16 06-Apr-16 0% ACCO, UCC

378 Vending Alcove 103A 9 9 23-Mar-16 04-Apr-16

379 Uncover & Polish Floor - Install New Floor Protection 2 2 23-Mar-16 24-Mar-16 0% Floor Polish

380 Install Lighting & Devices 1 1 25-Mar-16 25-Mar-16 0% Reynolds

381 Install Grills 1 1 28-Mar-16 28-Mar-16 0% FM

382 Install Wood Base 1 1 29-Mar-16 29-Mar-16 0% Wood Finishes

383 Final Paint 1 1 30-Mar-16 30-Mar-16 0% WPI Paint

384 Final Clean 1 1 31-Mar-16 31-Mar-16 0% Cleaner

385 Punch 1 1 01-Apr-16 01-Apr-16 0% Opsis, UCC

386 Back Punch 1 1 04-Apr-16 04-Apr-16 0% UCC, ACCO

387 Janitor 172 13 13 24-Mar-16 11-Apr-16

388 Uncover Floor & Polish - Install New Floor Protection 3 3 24-Mar-16 28-Mar-16 0% Floor Polish

389 Install Lighting & Devices 1 1 29-Mar-16 29-Mar-16 0% Reynolds

390 Install Grills 1 1 30-Mar-16 30-Mar-16 0% FM

391 Install Mop Sink 1 1 30-Mar-16 30-Mar-16 0% North Umpqua

392 Install FRP 1 1 31-Mar-16 31-Mar-16 0% Accessories

393 Remove Floor Protection & Final Buff 1 1 01-Apr-16 01-Apr-16 0% Floor Polish

394 Install Rubber Base 1 1 04-Apr-16 04-Apr-16 0% Flooring

395 Install Door & Hardware 1 1 05-Apr-16 05-Apr-16 0% WPI Doors

396 Final Paint 1 1 06-Apr-16 06-Apr-16 0% WPI Paint

397 Final Clean 1 1 07-Apr-16 07-Apr-16 0% Cleaner

398 Punch 1 1 08-Apr-16 08-Apr-16 0% Opsis, UCC

399 Back Punch 1 1 11-Apr-16 11-Apr-16 0% ACCO, UCC

400 Classrooms 30 30 29-Mar-16 09-May-16

401 Classroom 110 27 27 29-Mar-16 04-May-16

402 Uncover & Polish Floor - Install New Floor Protection 3 3 29-Mar-16 31-Mar-16 0% Floor Polish

403 Install Ceiling Grid & Tile For Devices 2 2 01-Apr-16 04-Apr-16 0% Harver

404 Complete Above Ceiling MEP 3 3 04-Apr-16 06-Apr-16 0% O & S, FM, North Umpqua, Data, Essential, Delta, North Umpqua, Reynolds

405 Inspections To Cover @ Ceiling 2 2 07-Apr-16 08-Apr-16 0% County

Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct

2015 2016

Final Clean

Punch & Corrections

Back Punch

15-Apr-16, Womens 171

Uncover & Polish Floor - Install New Floor Protection

Install Tile

Grout & Seal Tile

Install Lighting & Devices

Install Grills

Install Plumbing Fixtures

Install Partitions

Install Accessories

Install Door & Hardware

Final Paint

Uncover Floor & Final Buff

Final Clean

Punch & Corrections

Back Punch

11-Apr-16, Support Rooms

06-Apr-16, Storage 173

Uncover & Polish Floor - Install New Floor Protection

Install Lighting & Devices

Install Grills

Install Door & Hardware

Install Rubber Base

Final Paint

Uncover Floor & Final Buff

Final Clean

Punch & Corrections

Back Punch

04-Apr-16, Vending Alcove 103A

Uncover & Polish Floor - Install New Floor Protection

Install Lighting & Devices

Install Grills

Install Wood Base

Final Paint

Final Clean

Punch

Back Punch

11-Apr-16, Janitor 172

Uncover Floor & Polish - Install New Floor Protection

Install Lighting & Devices

Install Grills

Install Mop Sink

Install FRP

Remove Floor Protection & Final Buff

Install Rubber Base

Install Door & Hardware

Final Paint

Final Clean

Punch

Back Punch

09-May-16, Classrooms

04-May-16, Classroom 110

Uncover & Polish Floor - Install New Floor Protection

Install Ceiling Grid & Tile For Devices

Complete Above Ceiling MEP

Inspections To Cover @ Ceiling

UCC Weekly Overall Sub Update 30-Nov-15 10:55

Page 7 of 21

Page 8: HNSB 11.30.15 Health, Nursing & Science Building...28-Sep-16, HNSB 11.30.15 28-Sep-16, Health, Nursing & Science Building 19-Apr-16, Design & Engineering 19-Apr-16, Package 2 Long

# Activity Name OriginalDuration

RemainingDuration

Start Finish Activity %Complete

Resources

406 Install Ceiling Tile 2 2 08-Apr-16 11-Apr-16 0% Harver

407 Install Roller Shades 1 1 12-Apr-16 12-Apr-16 0% Accessories

408 Install Marker Boards 2 2 12-Apr-16 13-Apr-16 0% Accessories

409 Complete Electrical/AV/Data/Controls 3 3 14-Apr-16 18-Apr-16 0% Delta, Essential, Data, North Umpqua

410 Install Relites 1 1 19-Apr-16 19-Apr-16 0% Culver

411 Remove Floor Protection & Final Buff 1 1 20-Apr-16 20-Apr-16 0% Floor Polish

412 Install Rubber Base 1 1 21-Apr-16 21-Apr-16 0% Flooring

413 Install Door & Hardware 1 1 22-Apr-16 22-Apr-16 0% WPI Doors

414 Final Paint 1 1 25-Apr-16 25-Apr-16 0% WPI Paint

415 Final Clean 1 1 26-Apr-16 26-Apr-16 0% Cleaner

416 Punch & Corrections 2 2 27-Apr-16 28-Apr-16 0% Opsis, ACCO

417 Back Punch 2 2 29-Apr-16 02-May-16 0% ACCO, UCC

418 Move In Owner Furniture 2 2 03-May-16 04-May-16 0% UCC

419 Medical Legal Resolutions 120 28 28 31-Mar-16 09-May-16

420 Uncover & Polish Floor - Install New Floor Protection 3 3 31-Mar-16 04-Apr-16 0% Floor Polish

421 Install Ceiling Grid & Tile For Devices 2 2 05-Apr-16 06-Apr-16 0% Harver

422 Complete Above Ceiling MEP 3 3 07-Apr-16 11-Apr-16 0% Delta, Essential, North Umpqua, Reynolds, O & S, FM, North Umpqua, Data

423 Inspections To Cover @ Ceiling 2 2 12-Apr-16 13-Apr-16 0% County

424 Install Ceiling Tile 2 2 14-Apr-16 15-Apr-16 0% Harver

425 Install Roller Shades 1 1 15-Apr-16 15-Apr-16 0% Accessories

426 Complete Electrical/AV/Data/Controls 3 3 18-Apr-16 20-Apr-16 0% Delta, Essential, Reynolds

427 Remove Floor Protection & Final Buff 1 1 21-Apr-16 21-Apr-16 0% Floor Polish

428 Install Aluminum Frame/Relite/Door/Hardware @ 120-2 2 2 22-Apr-16 25-Apr-16 0% Culver

429 Install Rubber Base 1 1 26-Apr-16 26-Apr-16 0% Flooring

430 Final Paint 2 2 27-Apr-16 28-Apr-16 0% WPI Paint

431 Final Clean 1 1 29-Apr-16 29-Apr-16 0% Cleaner

432 Punch & Corrections 3 3 02-May-16 04-May-16 0% ACCO, Opsis

433 Back Punch 1 1 05-May-16 05-May-16 0% ACCO, UCC

434 Move In Owner Furniture 2 2 06-May-16 09-May-16 0% UCC

435 Conference, Meeting & Work Rooms 25 25 04-Apr-16 06-May-16

436 Meeting 121, 122 & 123 25 25 04-Apr-16 06-May-16

437 Install Ceiling Grid & Tiles For Devices 3 3 04-Apr-16 06-Apr-16 0% Harver

438 Complete Above Ceiling MEP 3 3 06-Apr-16 08-Apr-16 0% Data, Delta, Essential, O & S, FM, North Umpqua, Reynolds

439 Inspections To Cover @ Ceiling 1 1 11-Apr-16 11-Apr-16 0% County

440 Install Ceiling Tile 2 2 11-Apr-16 12-Apr-16 0% Harver

441 Install Relites @ 121-1, 122 & 123-1 1 1 13-Apr-16 13-Apr-16 0% Culver

442 Install Carpet & Rubber Base 2 2 14-Apr-16 15-Apr-16 0% Flooring

443 Install Doors & Hardware 3 3 15-Apr-16 19-Apr-16 0% WPI Doors

444 Install Roller Shades 2 2 19-Apr-16 20-Apr-16 0% Accessories

445 Complete Electrical/AV/Data/Controls 3 3 21-Apr-16 25-Apr-16 0% Delta, Essential, Data, Reynolds

446 Final Paint 2 2 26-Apr-16 27-Apr-16 0% WPI Paint

447 Final Clean 1 1 28-Apr-16 28-Apr-16 0% Cleaner

448 Punch & Corrections 3 3 29-Apr-16 03-May-16 0% Opsis, ACCO

449 Back Punch 1 1 04-May-16 04-May-16 0% UCC, ACCO

450 Move In Owner Furniture 2 2 05-May-16 06-May-16 0% UCC

451 Conference 150 21 21 06-Apr-16 04-May-16

452 Install Ceiling Grid & Tiles For Devices 1 1 06-Apr-16 06-Apr-16 0% Harver

453 Complete Above Ceiling MEP 3 3 07-Apr-16 11-Apr-16 0% O & S, FM, North Umpqua, Data, Delta, Essential, Reynolds, North Umpqua

454 Inspections To Cover @ Ceiling 1 1 12-Apr-16 12-Apr-16 0% County

455 Install Ceiling Tile 2 2 13-Apr-16 14-Apr-16 0% Harver

456 Install Relites, Door & Hardware 2 2 15-Apr-16 18-Apr-16 0% WPI Doors, Culver

457 Complete Electrical/AV/Data/Controls 3 3 19-Apr-16 21-Apr-16 0% Data, Essential, Delta, Reynolds

458 Install Carpet & Rubber Base 2 2 22-Apr-16 25-Apr-16 0% Flooring

459 Final Paint 1 1 26-Apr-16 26-Apr-16 0% WPI Paint

460 Final Clean 1 1 27-Apr-16 27-Apr-16 0% Cleaner

461 Punch & Corrections 2 2 28-Apr-16 29-Apr-16 0% Opsis, ACCO

462 Back Punch 1 1 02-May-16 02-May-16 0% UCC, ACCO

463 Move In Owner Furniture 2 2 03-May-16 04-May-16 0% UCC

Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct

2015 2016

Install Ceiling Tile

Install Roller Shades

Install Marker Boards

Complete Electrical/AV/Data/Controls

Install Relites

Remove Floor Protection & Final Buff

Install Rubber Base

Install Door & Hardware

Final Paint

Final Clean

Punch & Corrections

Back Punch

Move In Owner Furniture

09-May-16, Medical Legal Resolutions 120

Uncover & Polish Floor - Install New Floor Protection

Install Ceiling Grid & Tile For Devices

Complete Above Ceiling MEP

Inspections To Cover @ Ceiling

Install Ceiling Tile

Install Roller Shades

Complete Electrical/AV/Data/Controls

Remove Floor Protection & Final Buff

Install Aluminum Frame/Relite/Door/Hardware @ 120-2

Install Rubber Base

Final Paint

Final Clean

Punch & Corrections

Back Punch

Move In Owner Furniture

06-May-16, Conference, Meeting & Work Rooms

06-May-16, Meeting 121, 122 & 123

Install Ceiling Grid & Tiles For Devices

Complete Above Ceiling MEP

Inspections To Cover @ Ceiling

Install Ceiling Tile

Install Relites @ 121-1, 122 & 123-1

Install Carpet & Rubber Base

Install Doors & Hardware

Install Roller Shades

Complete Electrical/AV/Data/Controls

Final Paint

Final Clean

Punch & Corrections

Back Punch

Move In Owner Furniture

04-May-16, Conference 150

Install Ceiling Grid & Tiles For Devices

Complete Above Ceiling MEP

Inspections To Cover @ Ceiling

Install Ceiling Tile

Install Relites, Door & Hardware

Complete Electrical/AV/Data/Controls

Install Carpet & Rubber Base

Final Paint

Final Clean

Punch & Corrections

Back Punch

Move In Owner Furniture

UCC Weekly Overall Sub Update 30-Nov-15 10:55

Page 8 of 21

Page 9: HNSB 11.30.15 Health, Nursing & Science Building...28-Sep-16, HNSB 11.30.15 28-Sep-16, Health, Nursing & Science Building 19-Apr-16, Design & Engineering 19-Apr-16, Package 2 Long

# Activity Name OriginalDuration

RemainingDuration

Start Finish Activity %Complete

Resources

464 Work Room 151 19 19 06-Apr-16 02-May-16

465 Uncover & Polish Floor - Install New Floor Protection 2 2 06-Apr-16 07-Apr-16 0% Floor Polish

466 Install Ceiling Grid & Tiles For Devices 1 1 08-Apr-16 08-Apr-16 0% Harver

467 Complete Above Ceiling MEP 2 2 11-Apr-16 12-Apr-16 0% O & S, FM, North Umpqua, Data, Essential, North Umpqua, Reynolds

468 Inspections To Cover @ Ceiling 1 1 12-Apr-16 12-Apr-16 0% County

469 Install Ceiling Tile 1 1 13-Apr-16 13-Apr-16 0% Harver

470 Install Cabinets 2 2 14-Apr-16 15-Apr-16 0% S & B

471 Install Sink & Fixtures 1 1 15-Apr-16 15-Apr-16 0% North Umpqua

472 Install Relite 2 2 15-Apr-16 18-Apr-16 0% Culver

473 Complete Electrical/AV/Data/Controls 1 1 19-Apr-16 19-Apr-16 0% Delta, Data, Essential, Reynolds

474 Remove Floor Protection & Final Buff 1 1 20-Apr-16 20-Apr-16 0% Floor Polish

475 Install Door & Hardware 1 1 21-Apr-16 21-Apr-16 0% WPI Doors

476 Install Rubber Base 1 1 22-Apr-16 22-Apr-16 0% Flooring

477 Final Paint 1 1 25-Apr-16 25-Apr-16 0% WPI Paint

478 Final Clean 1 1 26-Apr-16 26-Apr-16 0% Cleaner

479 Punch & Corrections 2 2 27-Apr-16 28-Apr-16 0% Opsis, ACCO

480 Back Punch 1 1 29-Apr-16 29-Apr-16 0% UCC, ACCO

481 Move In Owner Furniture 1 1 02-May-16 02-May-16 0% UCC

482 Labs 54 54 07-Apr-16 22-Jun-16

483 Nursing 36 36 07-Apr-16 26-May-16

484 Skills Lab 130 36 36 07-Apr-16 26-May-16

485 Uncover & Polish Floor - Install New Floor Protection 3 3 07-Apr-16 11-Apr-16 0% Floor Polish

486 Install Patient Lift Supports 5 5 12-Apr-16 18-Apr-16 0% Accessories

487 Install Ceiling Grid & Tile For Devices 3 3 15-Apr-16 19-Apr-16 0% Harver

488 Complete Above Ceiling MEP 5 5 18-Apr-16 22-Apr-16 0% O & S, FM, North Umpqua, Data, Delta, Essential, Reynolds

489 Inspections To Cover @ Ceiling 2 2 22-Apr-16 25-Apr-16 0% County, Special Inspection

490 Install Ceiling Tile 2 2 26-Apr-16 27-Apr-16 0% Harver

491 Install Cabinets 8 8 21-Apr-16 02-May-16 0% S & B

492 Install Sinks & Fixtures 5 5 26-Apr-16 02-May-16 0% North Umpqua

493 Complete Med Gases Including Inspections 8 8 26-Apr-16 05-May-16 0% North Umpqua, Special Inspection

494 Complete Electrical/AV/Data/Controls 5 5 26-Apr-16 02-May-16 0% Delta, Data, Essential, Reynolds

495 Install Roller Shades 3 3 27-Apr-16 29-Apr-16 0% Accessories

496 Remove Floor Protection & Final Buff 3 3 02-May-16 04-May-16 0% Floor Polish

497 Install Rubber Base 2 2 05-May-16 06-May-16 0% Flooring

498 Install Privacy Curtains 3 3 05-May-16 09-May-16 0% Accessories

499 Final Paint 2 2 10-May-16 11-May-16 0% WPI Paint

500 Final Clean 2 2 12-May-16 13-May-16 0% Cleaner

501 Punch & Corrections 3 3 16-May-16 18-May-16 0% Opsis, ACCO

502 Back Punch 1 1 19-May-16 19-May-16 0% UCC, ACCO

503 Move In Equipment & Furniture 5 5 20-May-16 26-May-16 0% UCC, ACCO

504 Nursing Entry 130A 18 18 11-Apr-16 04-May-16

505 Uncover & Polish Floor - Install New Floor Protection 2 2 11-Apr-16 12-Apr-16 0% Floor Polish

506 Install Ceiling Grid & Tile For Devices 1 1 13-Apr-16 13-Apr-16 0% Harver

507 Complete Above Ceiling MEP 2 2 14-Apr-16 15-Apr-16 0% O & S, FM, North Umpqua, Data, Delta, Essential, Reynolds

508 Inspections To Cover @ Ceiling 1 1 15-Apr-16 15-Apr-16 0% County

509 Install Ceiling Tile 1 1 18-Apr-16 18-Apr-16 0% Harver

510 Complete Electrical/AV/Data/Controls 2 2 18-Apr-16 19-Apr-16 0% Delta, Data, Essential, Reynolds

511 Remove Floor Protection & Final Buff 1 1 20-Apr-16 20-Apr-16 0% Floor Polish

512 Install Rubber Base 1 1 21-Apr-16 21-Apr-16 0% Flooring

513 Install Doors & Hardware 2 2 22-Apr-16 25-Apr-16 0% WPI Doors

514 Final Paint 1 1 26-Apr-16 26-Apr-16 0% WPI Paint

515 Final Clean 1 1 27-Apr-16 27-Apr-16 0% Cleaner

516 Punch & Corrections 2 2 28-Apr-16 29-Apr-16 0% Opsis, ACCO

517 Back Punch 1 1 02-May-16 02-May-16 0% UCC, ACCO

518 Move In Owner Furniture 2 2 03-May-16 04-May-16 0% UCC, ACCO

519 Tech Station 130B 18 18 12-Apr-16 05-May-16

520 Uncover & Polish Floor - Install New Floor Protection 2 2 12-Apr-16 13-Apr-16 0% Floor Polish

521 Install Ceiling Grid & Tile For Devices 1 1 14-Apr-16 14-Apr-16 0% Harver

Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct

2015 2016

02-May-16, Work Room 151

Uncover & Polish Floor - Install New Floor Protection

Install Ceiling Grid & Tiles For Devices

Complete Above Ceiling MEP

Inspections To Cover @ Ceiling

Install Ceiling Tile

Install Cabinets

Install Sink & Fixtures

Install Relite

Complete Electrical/AV/Data/Controls

Remove Floor Protection & Final Buff

Install Door & Hardware

Install Rubber Base

Final Paint

Final Clean

Punch & Corrections

Back Punch

Move In Owner Furniture

22-Jun-16, Labs

26-May-16, Nursing

26-May-16, Skills Lab 130

Uncover & Polish Floor - Install New Floor Protection

Install Patient Lift Supports

Install Ceiling Grid & Tile For Devices

Complete Above Ceiling MEP

Inspections To Cover @ Ceiling

Install Ceiling Tile

Install Cabinets

Install Sinks & Fixtures

Complete Med Gases Including Inspections

Complete Electrical/AV/Data/Controls

Install Roller Shades

Remove Floor Protection & Final Buff

Install Rubber Base

Install Privacy Curtains

Final Paint

Final Clean

Punch & Corrections

Back Punch

Move In Equipment & Furniture

04-May-16, Nursing Entry 130A

Uncover & Polish Floor - Install New Floor Protection

Install Ceiling Grid & Tile For Devices

Complete Above Ceiling MEP

Inspections To Cover @ Ceiling

Install Ceiling Tile

Complete Electrical/AV/Data/Controls

Remove Floor Protection & Final Buff

Install Rubber Base

Install Doors & Hardware

Final Paint

Final Clean

Punch & Corrections

Back Punch

Move In Owner Furniture

05-May-16, Tech Station 130B

Uncover & Polish Floor - Install New Floor Protection

Install Ceiling Grid & Tile For Devices

UCC Weekly Overall Sub Update 30-Nov-15 10:55

Page 9 of 21

Page 10: HNSB 11.30.15 Health, Nursing & Science Building...28-Sep-16, HNSB 11.30.15 28-Sep-16, Health, Nursing & Science Building 19-Apr-16, Design & Engineering 19-Apr-16, Package 2 Long

# Activity Name OriginalDuration

RemainingDuration

Start Finish Activity %Complete

Resources

522 Complete Above Ceiling MEP 3 3 15-Apr-16 19-Apr-16 0% Data, Delta, Essential, Reynolds, O & S, FM, North Umpqua

523 Inspections To Cover @ Ceiling 1 1 19-Apr-16 19-Apr-16 0% County

524 Install Ceiling Tile 1 1 20-Apr-16 20-Apr-16 0% Harver

525 Install Cabinets/Tech Station 3 3 20-Apr-16 22-Apr-16 0% S & B

526 Complete Electrical/AV/Data/Controls 1 1 25-Apr-16 25-Apr-16 0% Delta, Data, Essential, Reynolds

527 Remove Floor Protection & Final Buff 1 1 26-Apr-16 26-Apr-16 0% Floor Polish

528 Install Rubber Base 1 1 26-Apr-16 26-Apr-16 0% Flooring

529 Final Paint 1 1 27-Apr-16 27-Apr-16 0% WPI Paint

530 Final Clean 1 1 28-Apr-16 28-Apr-16 0% Cleaner

531 Punch & Corrections 3 3 29-Apr-16 03-May-16 0% UCC, ACCO

532 Back Punch 1 1 04-May-16 04-May-16 0% UCC, ACCO

533 Move In Owner Furniture 1 1 05-May-16 05-May-16 0% UCC

534 Storage 131 18 18 13-Apr-16 06-May-16

535 Uncover & Polish Floor - Install New Floor Protection 2 2 13-Apr-16 14-Apr-16 0% Floor Polish

536 Install Ceiling Grid & Tile For Devices 1 1 15-Apr-16 15-Apr-16 0% Harver

537 Complete Above Ceiling MEP 3 3 18-Apr-16 20-Apr-16 0% O & S, North Umpqua, Data, Delta, Essential, FM, Reynolds

538 Inspections To Cover @ Ceiling 1 1 21-Apr-16 21-Apr-16 0% County

539 Install Ceiling Tile 1 1 22-Apr-16 22-Apr-16 0% Harver

540 Complete Electrical/AV/Data/Controls 1 1 25-Apr-16 25-Apr-16 0% Delta, Data, Essential, Reynolds

541 Remove Floor Protection & Final Buff 1 1 26-Apr-16 26-Apr-16 0% Floor Polish

542 Install Rubber Base 1 1 27-Apr-16 27-Apr-16 0% Flooring

543 Install Door & Hardware 1 1 28-Apr-16 28-Apr-16 0% WPI Doors

544 Final Paint 1 1 29-Apr-16 29-Apr-16 0% WPI Paint

545 Final Clean 1 1 02-May-16 02-May-16 0% Cleaner

546 Punch & Corrections 2 2 03-May-16 04-May-16 0% Opsis, ACCO

547 Back Punch 1 1 05-May-16 05-May-16 0% UCC, ACCO

548 Move In Owner Furniture 1 1 06-May-16 06-May-16 0% UCC

549 Simulation Labs & Control 133, 134 & 135 31 31 14-Apr-16 26-May-16

550 Uncover Floor, Polish & Install New Floor Protection 3 3 14-Apr-16 18-Apr-16 0% Floor Polish

551 Install Ceiling Grid & Tile For Devices 2 2 19-Apr-16 20-Apr-16 0% Harver

552 Complete Above Ceiling MEP 5 5 19-Apr-16 25-Apr-16 0% O & S, FM, North Umpqua, Data, Delta, Essential, Reynolds

553 Inspections To Cover @ Ceiling 1 1 25-Apr-16 25-Apr-16 0% County

554 Install Ceiling Tile 2 2 25-Apr-16 26-Apr-16 0% Harver

555 Install Cabinets 5 5 22-Apr-16 28-Apr-16 0% S & B

556 Install Sinks & Fixtures 2 2 28-Apr-16 29-Apr-16 0% North Umpqua

557 Complete Electrical/AV/Data/Controls 4 4 02-May-16 05-May-16 0% Essential, Delta, Data, Reynolds

558 Install One Way Glass @ 134 2 2 05-May-16 06-May-16 0% Culver

559 Install Roller Shades 1 1 09-May-16 09-May-16 0% Accessories

560 Remove Floor Protection & Final Buff 1 1 10-May-16 10-May-16 0% Floor Polish

561 Install Break Away Doors @ 133 & 135 4 4 10-May-16 13-May-16 0% WPI Doors

562 Install Rubber Base 2 2 16-May-16 17-May-16 0% Flooring

563 Final Paint 2 2 18-May-16 19-May-16 0% WPI Paint

564 Final Clean 1 1 20-May-16 20-May-16 0% Cleaner

565 Punch & Corrections 2 2 20-May-16 23-May-16 0% Opsis, ACCO

566 Back Punch 1 1 24-May-16 24-May-16 0% UCC, ACCO

567 Move In Equipment & Owner Furniture 2 2 25-May-16 26-May-16 0% UCC, ACCO

568 Debrief 132 & 136 18 18 18-Apr-16 11-May-16

569 Uncover Floor, Polish & Install New Floor Protection 3 3 18-Apr-16 20-Apr-16 0% Floor Polish

570 Install Ceiling Grid & Tile For Devices 2 2 20-Apr-16 21-Apr-16 0% Harver

571 Complete Above Ceiling MEP 3 3 21-Apr-16 25-Apr-16 0% North Umpqua, Data, Delta, Essential, Reynolds, O & S, FM

572 Inspections To Cover @ Ceiling 1 1 25-Apr-16 25-Apr-16 0% County

573 Install Ceiling Tile 2 2 26-Apr-16 27-Apr-16 0% Harver

574 Complete Electrical/AV/Data/Controls 2 2 27-Apr-16 28-Apr-16 0% Delta, Data, Essential, Reynolds

575 Install Roller Shades 1 1 28-Apr-16 28-Apr-16 0% Accessories

576 Remove Floor Protection & Final Buff 1 1 28-Apr-16 28-Apr-16 0% Floor Polish

577 Install Rubber Base 1 1 29-Apr-16 29-Apr-16 0% Flooring

578 Install Doors & Hardware 2 2 29-Apr-16 02-May-16 0% WPI Doors

579 Final Paint 2 2 02-May-16 03-May-16 0% WPI Paint

Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct

2015 2016

Complete Above Ceiling MEP

Inspections To Cover @ Ceiling

Install Ceiling Tile

Install Cabinets/Tech Station

Complete Electrical/AV/Data/Controls

Remove Floor Protection & Final Buff

Install Rubber Base

Final Paint

Final Clean

Punch & Corrections

Back Punch

Move In Owner Furniture

06-May-16, Storage 131

Uncover & Polish Floor - Install New Floor Protection

Install Ceiling Grid & Tile For Devices

Complete Above Ceiling MEP

Inspections To Cover @ Ceiling

Install Ceiling Tile

Complete Electrical/AV/Data/Controls

Remove Floor Protection & Final Buff

Install Rubber Base

Install Door & Hardware

Final Paint

Final Clean

Punch & Corrections

Back Punch

Move In Owner Furniture

26-May-16, Simulation Labs & Control 133, 134 & 135

Uncover Floor, Polish & Install New Floor Protection

Install Ceiling Grid & Tile For Devices

Complete Above Ceiling MEP

Inspections To Cover @ Ceiling

Install Ceiling Tile

Install Cabinets

Install Sinks & Fixtures

Complete Electrical/AV/Data/Controls

Install One Way Glass @ 134

Install Roller Shades

Remove Floor Protection & Final Buff

Install Break Away Doors @ 133 & 135

Install Rubber Base

Final Paint

Final Clean

Punch & Corrections

Back Punch

Move In Equipment & Owner Furniture

11-May-16, Debrief 132 & 136

Uncover Floor, Polish & Install New Floor Protection

Install Ceiling Grid & Tile For Devices

Complete Above Ceiling MEP

Inspections To Cover @ Ceiling

Install Ceiling Tile

Complete Electrical/AV/Data/Controls

Install Roller Shades

Remove Floor Protection & Final Buff

Install Rubber Base

Install Doors & Hardware

Final Paint

UCC Weekly Overall Sub Update 30-Nov-15 10:55

Page 10 of 21

Page 11: HNSB 11.30.15 Health, Nursing & Science Building...28-Sep-16, HNSB 11.30.15 28-Sep-16, Health, Nursing & Science Building 19-Apr-16, Design & Engineering 19-Apr-16, Package 2 Long

# Activity Name OriginalDuration

RemainingDuration

Start Finish Activity %Complete

Resources

580 Final Clean 1 1 04-May-16 04-May-16 0% Cleaner

581 Punch & Corrections 3 3 03-May-16 05-May-16 0% Opsis, ACCO

582 Back Punch 1 1 06-May-16 06-May-16 0% UCC, ACCO

583 Move In Owner Furniture 3 3 09-May-16 11-May-16 0% UCC

584 Clean Prep 137 20 20 20-Apr-16 17-May-16

585 Uncover Floor, Polish & Install New Floor Protection 2 2 20-Apr-16 21-Apr-16 0% Floor Polish

586 Install Ceiling Grid & Tile For Devices 1 1 22-Apr-16 22-Apr-16 0% Harver

587 Complete Above Ceiling MEP 3 3 25-Apr-16 27-Apr-16 0% O & S, FM, North Umpqua, Data, Essential, Delta, Reynolds

588 Inspections To Cover @ Ceiling 1 1 27-Apr-16 27-Apr-16 0% County

589 Install Ceiling Tile 1 1 28-Apr-16 28-Apr-16 0% Harver

590 Install Cabinets 3 3 29-Apr-16 03-May-16 0% S & B

591 Install Sink 1 1 03-May-16 03-May-16 0% North Umpqua

592 Complete Electrical/AV/Data/Controls 2 2 04-May-16 05-May-16 0% Delta, Data, Essential, Reynolds

593 Install Roller Shades 1 1 06-May-16 06-May-16 0% Accessories

594 Remove Floor Protection & Final Buff 1 1 09-May-16 09-May-16 0% Floor Polish

595 Install Rubber Base 1 1 10-May-16 10-May-16 0% Flooring

596 Install Door & Hardware 1 1 10-May-16 10-May-16 0% WPI Doors

597 Final Paint 1 1 11-May-16 11-May-16 0% WPI Paint

598 Final Clean 1 1 12-May-16 12-May-16 0% Cleaner

599 Punch & Corrections 2 2 12-May-16 13-May-16 0% Opsis, ACCO

600 Back Punch 1 1 16-May-16 16-May-16 0% UCC, ACCO

601 Move In Owner Furniture 1 1 17-May-16 17-May-16 0% UCC

602 Clean Supply 138 18 18 21-Apr-16 16-May-16

603 Uncover Floor, Polish & Install New Floor Protection 2 2 21-Apr-16 22-Apr-16 0% Floor Polish

604 Install Ceiling Grid & Tile For Devices 2 2 25-Apr-16 26-Apr-16 0% Harver

605 Complete Above Ceiling MEP 2 2 27-Apr-16 28-Apr-16 0% O & S, FM, North Umpqua, Data, Delta, Essential, Reynolds

606 Inspections To Cover @ Ceiling 1 1 29-Apr-16 29-Apr-16 0% County

607 Install Ceiling Tile 1 1 02-May-16 02-May-16 0% Harver

608 Complete Electrical/AV/Data/Controls 2 2 03-May-16 04-May-16 0% Delta, Data, Essential, Reynolds

609 Remove Floor Protection & Final Buff 1 1 05-May-16 05-May-16 0% Floor Polish

610 Install Rubber Base 1 1 05-May-16 05-May-16 0% Flooring

611 Install Door & Hardware 1 1 05-May-16 05-May-16 0% WPI Doors

612 Final Paint 1 1 06-May-16 06-May-16 0% WPI Paint

613 Final Clean 1 1 09-May-16 09-May-16 0% Cleaner

614 Punch @ Corrections 2 2 10-May-16 11-May-16 0% Opsis, ACCO

615 Back Punch 1 1 12-May-16 12-May-16 0% UCC, ACCO

616 Move In Owner Furniture 2 2 13-May-16 16-May-16 0% UCC

617 Soiled Holding/Laundry 139 18 18 22-Apr-16 17-May-16

618 Uncover Floor, Polish & Install New Floor Protection 2 2 22-Apr-16 25-Apr-16 0% Floor Polish

619 Install Ceiling Grid & Tile For Devices 1 1 26-Apr-16 26-Apr-16 0% Harver

620 Complete Above Ceiling MEP 2 2 26-Apr-16 27-Apr-16 0% Delta, Essential, O & S, FM, North Umpqua, Data, Reynolds

621 Inspections To Cover @ Ceiling 1 1 27-Apr-16 27-Apr-16 0% County

622 Install Ceiling Tile 1 1 28-Apr-16 28-Apr-16 0% Harver

623 Install Cabinets 3 3 29-Apr-16 03-May-16 0% S & B

624 Install Sink 1 1 04-May-16 04-May-16 0% North Umpqua

625 Complete Electrical/AV/Data/Controls 2 2 04-May-16 05-May-16 0% Reynolds, Data, Delta, Essential

626 Remove Floor Protection & Final Buff 1 1 06-May-16 06-May-16 0% Floor Polish

627 Install Rubber Base 1 1 06-May-16 06-May-16 0% Flooring

628 Install Doors & Hardware 2 2 06-May-16 09-May-16 0% WPI Doors

629 Final Paint 1 1 10-May-16 10-May-16 0% WPI Paint

630 Final Clean 1 1 11-May-16 11-May-16 0% Cleaner

631 Punch & Corrections 2 2 11-May-16 12-May-16 0% Opsis, ACCO

632 Back Punch 1 1 13-May-16 13-May-16 0% UCC, ACCO

633 Move Owner Furniture In 2 2 16-May-16 17-May-16 0% UCC

634 Dental 42 42 25-Apr-16 22-Jun-16

635 Dental Department 140 42 42 25-Apr-16 22-Jun-16

636 Uncover & Polish Floor - Install New Floor Protection 2 2 25-Apr-16 26-Apr-16 0% Floor Polish

637 Install Ceiling Grid & Tile For Devices 2 2 27-Apr-16 28-Apr-16 0% Harver

Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct

2015 2016

Final Clean

Punch & Corrections

Back Punch

Move In Owner Furniture

17-May-16, Clean Prep 137

Uncover Floor, Polish & Install New Floor Protection

Install Ceiling Grid & Tile For Devices

Complete Above Ceiling MEP

Inspections To Cover @ Ceiling

Install Ceiling Tile

Install Cabinets

Install Sink

Complete Electrical/AV/Data/Controls

Install Roller Shades

Remove Floor Protection & Final Buff

Install Rubber Base

Install Door & Hardware

Final Paint

Final Clean

Punch & Corrections

Back Punch

Move In Owner Furniture

16-May-16, Clean Supply 138

Uncover Floor, Polish & Install New Floor Protection

Install Ceiling Grid & Tile For Devices

Complete Above Ceiling MEP

Inspections To Cover @ Ceiling

Install Ceiling Tile

Complete Electrical/AV/Data/Controls

Remove Floor Protection & Final Buff

Install Rubber Base

Install Door & Hardware

Final Paint

Final Clean

Punch @ Corrections

Back Punch

Move In Owner Furniture

17-May-16, Soiled Holding/Laundry 139

Uncover Floor, Polish & Install New Floor Protection

Install Ceiling Grid & Tile For Devices

Complete Above Ceiling MEP

Inspections To Cover @ Ceiling

Install Ceiling Tile

Install Cabinets

Install Sink

Complete Electrical/AV/Data/Controls

Remove Floor Protection & Final Buff

Install Rubber Base

Install Doors & Hardware

Final Paint

Final Clean

Punch & Corrections

Back Punch

Move Owner Furniture In

22-Jun-16, Dental

22-Jun-16, Dental Department 140

Uncover & Polish Floor - Install New Floor Protection

Install Ceiling Grid & Tile For Devices

UCC Weekly Overall Sub Update 30-Nov-15 10:55

Page 11 of 21

Page 12: HNSB 11.30.15 Health, Nursing & Science Building...28-Sep-16, HNSB 11.30.15 28-Sep-16, Health, Nursing & Science Building 19-Apr-16, Design & Engineering 19-Apr-16, Package 2 Long

# Activity Name OriginalDuration

RemainingDuration

Start Finish Activity %Complete

Resources

638 Complete Above Ceiling MEP 5 5 27-Apr-16 03-May-16 0% O & S, FM, North Umpqua, Data, Delta, Essential, Reynolds

639 Inspections To Cover @ Ceiling 2 2 03-May-16 04-May-16 0% County

640 Install Ceiling Tile 2 2 05-May-16 06-May-16 0% Harver

641 Complete Electrical/AV/Data/Controls 5 5 09-May-16 13-May-16 0% Delta, Data, Essential, Reynolds

642 Complete Med Gas Including Inspections 8 8 09-May-16 18-May-16 0% Special Inspection, North Umpqua

643 Install Roller Shades 1 1 19-May-16 19-May-16 0% Accessories

644 Remove Floor Protection & Final Buff 1 1 20-May-16 20-May-16 0% Floor Polish

645 Install Rubber Base 1 1 23-May-16 23-May-16 0% Flooring

646 Final Paint 2 2 24-May-16 25-May-16 0% WPI Paint

647 Final Clean 2 2 26-May-16 27-May-16 0% Cleaner

648 Punch & Corrections 3 3 27-May-16 01-Jun-16 0% Opsis, ACCO

649 Back Punch 2 2 02-Jun-16 03-Jun-16 0% UCC, ACCO

650 Install Dental Equipment & Furniture 15 15 02-Jun-16 22-Jun-16 0% ACCO, UCC

651 Entry/Lockers 140A 21 21 27-Apr-16 25-May-16

652 Uncover & Polish Floor - Install New Floor Protection 2 2 27-Apr-16 28-Apr-16 0% Floor Polish

653 Install Ceiling Grid & Tile For Devices 1 1 29-Apr-16 29-Apr-16 0% Harver

654 Complete Above Ceiling MEP 3 3 02-May-16 04-May-16 0% Reynolds, North Umpqua, Data, Delta, Essential, O & S, FM

655 Inspections To Cover @ Ceiling 1 1 05-May-16 05-May-16 0% County

656 Install Ceiling Tile 1 1 06-May-16 06-May-16 0% Harver

657 Install Glazing 2 2 06-May-16 09-May-16 0% Culver

658 Install Lockers 3 3 09-May-16 11-May-16 0% S & B

659 Complete Electrical/AV/Data/Controls 2 2 12-May-16 13-May-16 0% Delta, Data, Essential, Reynolds

660 Uncover Floor & Final Buff 1 1 16-May-16 16-May-16 0% Floor Polish

661 Install Rubber Base 1 1 16-May-16 16-May-16 0% Flooring

662 Install Doors & Hardware 2 2 17-May-16 18-May-16 0% WPI Doors

663 Final Paint 1 1 19-May-16 19-May-16 0% WPI Paint

664 Final Clean 1 1 20-May-16 20-May-16 0% Cleaner

665 Punch & Corrections 2 2 20-May-16 23-May-16 0% Opsis, ACCO

666 Back Punch 1 1 24-May-16 24-May-16 0% UCC, ACCO

667 Move In Owner Furniture 1 1 25-May-16 25-May-16 0% UCC

668 Shared Office 141 23 23 28-Apr-16 31-May-16

669 Uncover & Polish Floor - Install New Floor Protection 2 2 28-Apr-16 29-Apr-16 0% Floor Polish

670 Install Ceiling Grid & Tile For Devices 1 1 02-May-16 02-May-16 0% Harver

671 Complete Above Ceiling MEP 3 3 02-May-16 04-May-16 0% O & S, FM, North Umpqua, Data, Delta, Essential, Reynolds

672 Inspections To Cover @ Ceiling 1 1 04-May-16 04-May-16 0% County

673 Install Ceiling Tile 1 1 05-May-16 05-May-16 0% Harver

674 Install Desktops 4 4 05-May-16 10-May-16 0% S & B

675 Complete Electrical/AV/Data/Controls 1 1 11-May-16 11-May-16 0% Reynolds, Delta, Data, Essential

676 Install Relite 2 2 12-May-16 13-May-16 0% Culver

677 Install Roller Shades 1 1 16-May-16 16-May-16 0% Accessories

678 Uncover Floor & Final Buff 1 1 17-May-16 17-May-16 0% Floor Polish

679 Install Rubber Base 1 1 18-May-16 18-May-16 0% Flooring

680 Install Door & Hardware 2 2 19-May-16 20-May-16 0% WPI Doors

681 Final Paint 1 1 23-May-16 23-May-16 0% WPI Paint

682 Punch & Corrections 2 2 24-May-16 25-May-16 0% Opsis, ACCO

683 Back Punch 1 1 26-May-16 26-May-16 0% UCC, ACCO

684 Move In Owner Furniture 2 2 27-May-16 31-May-16 0% UCC

685 Sterilization 143 30 30 29-Apr-16 10-Jun-16

686 Uncover & Polish Floor - Install New Floor Protection 2 2 29-Apr-16 02-May-16 0% Floor Polish

687 Install Ceiling Grid & Tile For Devices 2 2 03-May-16 04-May-16 0% Harver

688 Complete Above Ceiling MEP 5 5 03-May-16 09-May-16 0% O & S, FM, North Umpqua, Data, Delta, Essential, Reynolds

689 Inspections To Cover @ Ceiling 2 2 09-May-16 10-May-16 0% County

690 Install Ceiling Tile 2 2 11-May-16 12-May-16 0% Harver

691 Install Cabinets 5 5 12-May-16 18-May-16 0% S & B

692 Complete Med Gases Including Inspections 5 5 16-May-16 20-May-16 0% North Umpqua, Special Inspection

693 Install Roller Shades 1 1 23-May-16 23-May-16 0% Accessories

694 Uncover Floor & Final Buff 1 1 24-May-16 24-May-16 0% Floor Polish

695 Install Rubber Base 1 1 25-May-16 25-May-16 0% Flooring

Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct

2015 2016

Complete Above Ceiling MEP

Inspections To Cover @ Ceiling

Install Ceiling Tile

Complete Electrical/AV/Data/Controls

Complete Med Gas Including Inspections

Install Roller Shades

Remove Floor Protection & Final Buff

Install Rubber Base

Final Paint

Final Clean

Punch & Corrections

Back Punch

Install Dental Equipment & Furniture

25-May-16, Entry/Lockers 140A

Uncover & Polish Floor - Install New Floor Protection

Install Ceiling Grid & Tile For Devices

Complete Above Ceiling MEP

Inspections To Cover @ Ceiling

Install Ceiling Tile

Install Glazing

Install Lockers

Complete Electrical/AV/Data/Controls

Uncover Floor & Final Buff

Install Rubber Base

Install Doors & Hardware

Final Paint

Final Clean

Punch & Corrections

Back Punch

Move In Owner Furniture

31-May-16, Shared Office 141

Uncover & Polish Floor - Install New Floor Protection

Install Ceiling Grid & Tile For Devices

Complete Above Ceiling MEP

Inspections To Cover @ Ceiling

Install Ceiling Tile

Install Desktops

Complete Electrical/AV/Data/Controls

Install Relite

Install Roller Shades

Uncover Floor & Final Buff

Install Rubber Base

Install Door & Hardware

Final Paint

Punch & Corrections

Back Punch

Move In Owner Furniture

10-Jun-16, Sterilization 143

Uncover & Polish Floor - Install New Floor Protection

Install Ceiling Grid & Tile For Devices

Complete Above Ceiling MEP

Inspections To Cover @ Ceiling

Install Ceiling Tile

Install Cabinets

Complete Med Gases Including Inspections

Install Roller Shades

Uncover Floor & Final Buff

Install Rubber Base

UCC Weekly Overall Sub Update 30-Nov-15 10:55

Page 12 of 21

Page 13: HNSB 11.30.15 Health, Nursing & Science Building...28-Sep-16, HNSB 11.30.15 28-Sep-16, Health, Nursing & Science Building 19-Apr-16, Design & Engineering 19-Apr-16, Package 2 Long

# Activity Name OriginalDuration

RemainingDuration

Start Finish Activity %Complete

Resources

696 Complete Electrical/AV/Data/Controls 3 3 25-May-16 27-May-16 0% Delta, Data, Essential, Reynolds

697 Final Paint 2 2 27-May-16 31-May-16 0% WPI Paint

698 Final Clean 2 2 31-May-16 01-Jun-16 0% Cleaner

699 Punch & Corrections 3 3 31-May-16 02-Jun-16 0% Opsis, ACCO

700 Back Punch 1 1 03-Jun-16 03-Jun-16 0% UCC, ACCO

701 Move Equipment & Furniture In 5 5 06-Jun-16 10-Jun-16 0% UCC, ACCO

702 PANO X-Ray 144 18 18 02-May-16 25-May-16

703 Uncover & Polish Floor - Install New Floor Protection 2 2 02-May-16 03-May-16 0% Floor Polish

704 Install Ceiling Grid & Tile For Devices 2 2 04-May-16 05-May-16 0% Harver

705 Complete Above Ceiling MEP 2 2 06-May-16 09-May-16 0% Data, Delta, Essential, Reynolds, O & S, FM, North Umpqua

706 Inspections To Cover @ Ceiling 1 1 10-May-16 10-May-16 0% County

707 Install Ceiling Tile 1 1 11-May-16 11-May-16 0% Harver

708 Install X-Ray Glass 2 2 12-May-16 13-May-16 0% Culver

709 Complete Electrical/AV/Data/Controls 1 1 16-May-16 16-May-16 0% TK, Reynolds

710 Uncover Floor & Final Buff 1 1 17-May-16 17-May-16 0% Floor Polish

711 Install Rubber Base 1 1 18-May-16 18-May-16 0% Flooring

712 Final Paint 1 1 19-May-16 19-May-16 0% WPI Paint

713 Final Clean 1 1 20-May-16 20-May-16 0% Cleaner

714 Punch & Corrections 2 2 20-May-16 23-May-16 0% Opsis, ACCO

715 Back Punch 1 1 23-May-16 23-May-16 0% UCC, ACCO

716 Move In Owner Furniture 2 2 24-May-16 25-May-16 0% UCC, ACCO

717 Model Trim Lab 145 26 26 03-May-16 08-Jun-16

718 Uncover & Polish Floor - Install New Floor Protection 2 2 03-May-16 04-May-16 0% Floor Polish

719 Install Ceiling Grid & Tile For Devices 2 2 05-May-16 06-May-16 0% Harver

720 Complete Above Ceiling MEP 5 5 05-May-16 11-May-16 0% O & S, FM, North Umpqua, Data, Delta, Essential, Reynolds

721 Inspection To Cover @ Ceiling 2 2 12-May-16 13-May-16 0% County

722 Install Ceiling Tile 2 2 13-May-16 16-May-16 0% Harver

723 Install Cabinets 5 5 16-May-16 20-May-16 0% S & B

724 Install Sinks 2 2 20-May-16 23-May-16 0% North Umpqua

725 Install Glazing 2 2 23-May-16 24-May-16 0% Culver

726 Complete Electrical/AV/Data/Controls 2 2 24-May-16 25-May-16 0% Delta, Data, Essential, Reynolds

727 Uncover Floor & Final Buff 1 1 26-May-16 26-May-16 0% Floor Polish

728 Install Rubber Base 1 1 27-May-16 27-May-16 0% Flooring

729 Install Door & Hardware 1 1 27-May-16 27-May-16 0% WPI Doors

730 Final Paint 1 1 31-May-16 31-May-16 0% WPI Paint

731 Final Clean 2 2 01-Jun-16 02-Jun-16 0% Cleaner

732 Punch & Corrections 2 2 02-Jun-16 03-Jun-16 0% Opsis, ACCO

733 Back Punch 1 1 06-Jun-16 06-Jun-16 0% UCC, ACCO

734 Move Owner Equipment & Furniture In 5 5 02-Jun-16 08-Jun-16 0% UCC, ACCO

735 Offices 39 39 04-May-16 28-Jun-16

736 Offices 160A Thru 160L 39 39 04-May-16 28-Jun-16

737 Uncover & Polish Floor - Install New Floor Protection 4 4 04-May-16 09-May-16 0% Floor Polish

738 Install Ceiling Grid & Tile For Devices 4 4 09-May-16 12-May-16 0% Harver

739 Complete Above Ceiling MEP 5 5 10-May-16 16-May-16 0% O & S, FM

740 Inspections To Cover @ Ceiling 2 2 16-May-16 17-May-16 0% County

741 Install Ceiling Tile 5 5 16-May-16 20-May-16 0% Harver

742 Complete Electrical/AV/Data/Controls 5 5 18-May-16 24-May-16 0% Delta, Data, Essential, Reynolds

743 Install Relites 5 5 18-May-16 24-May-16 0% Culver

744 Install Roller Shades 3 3 23-May-16 25-May-16 0% Accessories

745 Remove Floor Protection & Final Buff 5 5 24-May-16 31-May-16 0% Floor Polish

746 Install Doors & Hardware 4 4 27-May-16 02-Jun-16 0% WPI Doors

747 Install Rubber Base 3 3 03-Jun-16 07-Jun-16 0% Flooring

748 Final Paint 5 5 08-Jun-16 14-Jun-16 0% WPI Paint

749 Final Clean 2 2 15-Jun-16 16-Jun-16 0% Cleaner

750 Punch & Corrections 4 4 16-Jun-16 21-Jun-16 0% Opsis, ACCO

751 Back Punch 2 2 22-Jun-16 23-Jun-16 0% UCC, ACCO

752 Move In Owner Furniture 5 5 22-Jun-16 28-Jun-16 0% UCC

753 Office Corridors 18 18 09-May-16 02-Jun-16

Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct

2015 2016

Complete Electrical/AV/Data/Controls

Final Paint

Final Clean

Punch & Corrections

Back Punch

Move Equipment & Furniture In

25-May-16, PANO X-Ray 144

Uncover & Polish Floor - Install New Floor Protection

Install Ceiling Grid & Tile For Devices

Complete Above Ceiling MEP

Inspections To Cover @ Ceiling

Install Ceiling Tile

Install X-Ray Glass

Complete Electrical/AV/Data/Controls

Uncover Floor & Final Buff

Install Rubber Base

Final Paint

Final Clean

Punch & Corrections

Back Punch

Move In Owner Furniture

08-Jun-16, Model Trim Lab 145

Uncover & Polish Floor - Install New Floor Protection

Install Ceiling Grid & Tile For Devices

Complete Above Ceiling MEP

Inspection To Cover @ Ceiling

Install Ceiling Tile

Install Cabinets

Install Sinks

Install Glazing

Complete Electrical/AV/Data/Controls

Uncover Floor & Final Buff

Install Rubber Base

Install Door & Hardware

Final Paint

Final Clean

Punch & Corrections

Back Punch

Move Owner Equipment & Furniture In

28-Jun-16, Offices

28-Jun-16, Offices 160A Thru 160L

Uncover & Polish Floor - Install New Floor Protection

Install Ceiling Grid & Tile For Devices

Complete Above Ceiling MEP

Inspections To Cover @ Ceiling

Install Ceiling Tile

Complete Electrical/AV/Data/Controls

Install Relites

Install Roller Shades

Remove Floor Protection & Final Buff

Install Doors & Hardware

Install Rubber Base

Final Paint

Final Clean

Punch & Corrections

Back Punch

Move In Owner Furniture

02-Jun-16, Office Corridors

UCC Weekly Overall Sub Update 30-Nov-15 10:55

Page 13 of 21

Page 14: HNSB 11.30.15 Health, Nursing & Science Building...28-Sep-16, HNSB 11.30.15 28-Sep-16, Health, Nursing & Science Building 19-Apr-16, Design & Engineering 19-Apr-16, Package 2 Long

# Activity Name OriginalDuration

RemainingDuration

Start Finish Activity %Complete

Resources

754 Corridor 103 18 18 09-May-16 02-Jun-16

755 Uncover & Polish Floor - Install New Floor Protection 4 4 09-May-16 12-May-16 0% Floor Polish

756 Install Ceiling Grid & Tile For Devices 3 3 12-May-16 16-May-16 0% Harver

757 Complete Above Ceiling MEP 3 3 16-May-16 18-May-16 0% O & S, FM, North Umpqua, Data, Delta, Essential, Reynolds

758 Instpections To Cover @ Ceiling 2 2 18-May-16 19-May-16 0% County

759 Install Ceiling Tile 2 2 19-May-16 20-May-16 0% Harver

760 Complete Electrical/AV/Data/Controls 2 2 20-May-16 23-May-16 0% Delta, Data, Essential, Reynolds

761 Remove Floor Protection & Final Buff 1 1 23-May-16 23-May-16 0% Floor Polish

762 Install Rubber Base 2 2 24-May-16 25-May-16 0% Flooring

763 Final Paint 2 2 26-May-16 27-May-16 0% WPI Paint

764 Final Clean 1 1 31-May-16 31-May-16 0% Cleaner

765 Punch & Corrections 2 2 31-May-16 01-Jun-16 0% Opsis, ACCO

766 Back Punch 1 1 02-Jun-16 02-Jun-16 0% UCC, ACCO

767 Commons & Circulation 32 32 12-May-16 27-Jun-16

768 Corridor 102 17 17 12-May-16 06-Jun-16

769 Uncover & Polish Floor - Install New Floor Protection 3 3 12-May-16 16-May-16 0% Floor Polish

770 Complete Electrical/AV/Data/Controls 3 3 17-May-16 19-May-16 0% Delta, Data, Essential, Reynolds

771 Remove Floor Protection & Final Buff 2 2 20-May-16 23-May-16 0% Floor Polish

772 Install Rubber Base 2 2 24-May-16 25-May-16 0% Flooring

773 Final Paint 2 2 26-May-16 27-May-16 0% WPI Paint

774 Final Clean 2 2 27-May-16 31-May-16 0% Cleaner

775 Punch & Corrections 3 3 01-Jun-16 03-Jun-16 0% Opsis, ACCO

776 Back Punch 1 1 06-Jun-16 06-Jun-16 0% UCC, ACCO

777 Vestibule 102A 25 25 17-May-16 21-Jun-16

778 Complete MEP @ Walls 2 2 17-May-16 18-May-16 0% North Umpqua, Data, North Umpqua, Delta, Reynolds

779 Inspection To Cover @ Walls 1 1 18-May-16 18-May-16 0% County

780 Install Gyp @ Walls 1 1 19-May-16 19-May-16 0% Harver

781 Install Ceiling Framing 1 1 20-May-16 20-May-16 0% Harver

782 Complete Above Ceiling MEP 3 3 20-May-16 24-May-16 0% Reynolds, Delta, North Umpqua, Data, North Umpqua

783 Inspections To Cover @ Ceiling 1 1 24-May-16 24-May-16 0% County

784 Install Gyp @ Ceiling 1 1 24-May-16 24-May-16 0% Harver

785 Tape Gyp 5 5 24-May-16 31-May-16 0% Harver

786 Prime & 1st Coat 2 2 01-Jun-16 02-Jun-16 0% WPI Paint

787 Install Store Fronts 5 5 02-Jun-16 08-Jun-16 0% Culver

788 Install Ceiling/Wall Devices 3 3 08-Jun-16 10-Jun-16 0% FM, Reynolds, Delta, Essential

789 Install Walk Off Mats 2 2 13-Jun-16 14-Jun-16 0% Flooring

790 Final Paint 1 1 15-Jun-16 15-Jun-16 0% WPI Paint

791 Final Clean 1 1 16-Jun-16 16-Jun-16 0% Cleaner

792 Punch & Corrections 3 3 16-Jun-16 20-Jun-16 0% Opsis, ACCO

793 Back Punch 1 1 21-Jun-16 21-Jun-16 0% UCC, ACCO

794 Corridor 101 17 17 18-May-16 10-Jun-16

795 Uncover & Polish Floor - Install New Floor Protection 3 3 18-May-16 20-May-16 0% Floor Polish

796 Complete Electrical/AV/Data/Controls 2 2 23-May-16 24-May-16 0% Essential, Reynolds, Delta, Data

797 Remove Floor Protection @ Final Buff 2 2 25-May-16 26-May-16 0% Floor Polish

798 Install Rubber Base 2 2 27-May-16 31-May-16 0% Flooring

799 Final Paint 2 2 01-Jun-16 02-Jun-16 0% WPI Paint

800 Final Clean 2 2 03-Jun-16 06-Jun-16 0% Cleaner

801 Punch & Corrections 3 3 07-Jun-16 09-Jun-16 0% ACCO, Opsis

802 Back Punch 1 1 10-Jun-16 10-Jun-16 0% UCC, ACCO

803 Vestibule 100A 25 25 23-May-16 27-Jun-16

804 Complete MEP @ Walls 2 2 23-May-16 24-May-16 0% Reynolds, North Umpqua, Data, North Umpqua, Delta

805 Inspections To Cover @ Walls 1 1 24-May-16 24-May-16 0% County

806 Install Gyp @ Walls 1 1 25-May-16 25-May-16 0% Harver

807 Install Ceiling Framing 1 1 26-May-16 26-May-16 0% Harver

808 Complete Above Ceiling MEP 3 3 26-May-16 31-May-16 0% FM, North Umpqua, Data, North Umpqua, Reynolds, Delta, Essential

809 Inspections To Cover @ Ceiling 1 1 31-May-16 31-May-16 0% County

810 Install Gyp @ Ceiling 1 1 31-May-16 31-May-16 0% Harver

811 Tape Gyp 5 5 31-May-16 06-Jun-16 0% Harver

Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct

2015 2016

02-Jun-16, Corridor 103

Uncover & Polish Floor - Install New Floor Protection

Install Ceiling Grid & Tile For Devices

Complete Above Ceiling MEP

Instpections To Cover @ Ceiling

Install Ceiling Tile

Complete Electrical/AV/Data/Controls

Remove Floor Protection & Final Buff

Install Rubber Base

Final Paint

Final Clean

Punch & Corrections

Back Punch

27-Jun-16, Commons & Circulation

06-Jun-16, Corridor 102

Uncover & Polish Floor - Install New Floor Protection

Complete Electrical/AV/Data/Controls

Remove Floor Protection & Final Buff

Install Rubber Base

Final Paint

Final Clean

Punch & Corrections

Back Punch

21-Jun-16, Vestibule 102A

Complete MEP @ Walls

Inspection To Cover @ Walls

Install Gyp @ Walls

Install Ceiling Framing

Complete Above Ceiling MEP

Inspections To Cover @ Ceiling

Install Gyp @ Ceiling

Tape Gyp

Prime & 1st Coat

Install Store Fronts

Install Ceiling/Wall Devices

Install Walk Off Mats

Final Paint

Final Clean

Punch & Corrections

Back Punch

10-Jun-16, Corridor 101

Uncover & Polish Floor - Install New Floor Protection

Complete Electrical/AV/Data/Controls

Remove Floor Protection @ Final Buff

Install Rubber Base

Final Paint

Final Clean

Punch & Corrections

Back Punch

27-Jun-16, Vestibule 100A

Complete MEP @ Walls

Inspections To Cover @ Walls

Install Gyp @ Walls

Install Ceiling Framing

Complete Above Ceiling MEP

Inspections To Cover @ Ceiling

Install Gyp @ Ceiling

Tape Gyp

UCC Weekly Overall Sub Update 30-Nov-15 10:55

Page 14 of 21

Page 15: HNSB 11.30.15 Health, Nursing & Science Building...28-Sep-16, HNSB 11.30.15 28-Sep-16, Health, Nursing & Science Building 19-Apr-16, Design & Engineering 19-Apr-16, Package 2 Long

# Activity Name OriginalDuration

RemainingDuration

Start Finish Activity %Complete

Resources

812 Prime & 1st Coat 2 2 07-Jun-16 08-Jun-16 0% WPI Paint

813 Install Store Fronts 5 5 08-Jun-16 14-Jun-16 0% Culver

814 Install Ceiling/Wall Devices 3 3 14-Jun-16 16-Jun-16 0% FM, North Umpqua, Data, Reynolds, Delta, Essential

815 Install Walk Off Mats 2 2 17-Jun-16 20-Jun-16 0% Flooring

816 Final Paint 1 1 21-Jun-16 21-Jun-16 0% WPI Paint

817 Final Clean 1 1 22-Jun-16 22-Jun-16 0% Cleaner

818 Punch & Corrections 3 3 22-Jun-16 24-Jun-16 0% Design, ACCO

819 Back Punch 1 1 27-Jun-16 27-Jun-16 0% UCC

820 Level 2 52 52 20-May-16 03-Aug-16

821 Restrooms 19 19 20-May-16 16-Jun-16

822 Mens 270 18 18 20-May-16 15-Jun-16

823 Uncover & Polish Floor- Install New Floor Protection 2 2 20-May-16 23-May-16 0% Floor Polish

824 Install Tile 3 3 24-May-16 26-May-16 0% Tile

825 Grout & Seal Tile 2 2 27-May-16 31-May-16 0% Tile

826 Install Lighting & Devices 1 1 01-Jun-16 01-Jun-16 0% Reynolds

827 Install Grills 1 1 01-Jun-16 01-Jun-16 0% FM

828 Install Plumbing Fixtures 3 3 31-May-16 02-Jun-16 0% North Umpqua

829 Install Partitions 2 2 02-Jun-16 03-Jun-16 0% Accessories

830 Install Accessories 2 2 03-Jun-16 06-Jun-16 0% Accessories

831 Final Paint 1 1 07-Jun-16 07-Jun-16 0% WPI Paint

832 Uncover Floor & Final Buff 1 1 08-Jun-16 08-Jun-16 0% Floor Polish

833 Final Clean 1 1 09-Jun-16 09-Jun-16 0% Cleaner

834 Punch & Corrections 3 3 10-Jun-16 14-Jun-16 0% Opsis, ACCO

835 Back Punch 1 1 15-Jun-16 15-Jun-16 0% UCC, ACCO

836 Womens 271 18 18 23-May-16 16-Jun-16

837 Uncover & Polish Floor - Install New Floor Protection 2 2 23-May-16 24-May-16 0% Floor Polish

838 Install Tile 3 3 25-May-16 27-May-16 0% Tile

839 Grout & Seal Tile 2 2 31-May-16 01-Jun-16 0% Tile

840 Install Lighting & Devices 1 1 02-Jun-16 02-Jun-16 0% Reynolds

841 Install Grills 1 1 02-Jun-16 02-Jun-16 0% FM

842 Install Plumbing Fixtures 3 3 01-Jun-16 03-Jun-16 0% North Umpqua

843 Install Partitions 2 2 03-Jun-16 06-Jun-16 0% Accessories

844 Install Accessories 2 2 06-Jun-16 07-Jun-16 0% Accessories

845 Final Paint 1 1 08-Jun-16 08-Jun-16 0% WPI Paint

846 Uncover Floor & Final Buff 1 1 09-Jun-16 09-Jun-16 0% Floor Polish

847 Final Clean 1 1 10-Jun-16 10-Jun-16 0% Cleaner

848 Punch & Corrections 3 3 13-Jun-16 15-Jun-16 0% Opsis, ACCO

849 Back Punch 1 1 16-Jun-16 16-Jun-16 0% UCC, ACCO

850 Unisex 272 13 13 24-May-16 10-Jun-16

851 Uncover & Polish Floor - Install New Floor Protection 2 2 24-May-16 25-May-16 0% Floor Polish

852 Install Lighting & Devices 1 1 26-May-16 26-May-16 0% Reynolds

853 Install Grills 1 1 26-May-16 26-May-16 0% FM

854 Install Plumbing Fixtures 2 2 27-May-16 31-May-16 0% North Umpqua

855 Install Accessories 2 2 01-Jun-16 02-Jun-16 0% Accessories

856 Final Paint 1 1 03-Jun-16 03-Jun-16 0% WPI Paint

857 Uncover Floor & Final Buff 1 1 06-Jun-16 06-Jun-16 0% Floor Polish

858 Final Clean 1 1 07-Jun-16 07-Jun-16 0% Cleaner

859 Punch & Corrections 2 2 08-Jun-16 09-Jun-16 0% Opsis, ACCO

860 Back Punch 1 1 10-Jun-16 10-Jun-16 0% UCC, ACCO

861 Support Rooms 14 14 25-May-16 14-Jun-16

862 Janitor 252 14 14 25-May-16 14-Jun-16

863 Uncover Floor & Polish - Install New Floor Protection 2 2 25-May-16 26-May-16 0% Floor Polish

864 Install Lighting & Devices 1 1 27-May-16 27-May-16 0% Reynolds

865 Install Grills 1 1 27-May-16 27-May-16 0% FM

866 Install Mop Sink 2 2 31-May-16 01-Jun-16 0% North Umpqua

867 Install FRP 2 2 02-Jun-16 03-Jun-16 0% Accessories

868 Remove Floor Protection & Final Buff 1 1 06-Jun-16 06-Jun-16 0% Floor Polish

869 Install Rubber Base 1 1 07-Jun-16 07-Jun-16 0% Flooring

Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct

2015 2016

Prime & 1st Coat

Install Store Fronts

Install Ceiling/Wall Devices

Install Walk Off Mats

Final Paint

Final Clean

Punch & Corrections

Back Punch

03-Aug-16, Level 2

16-Jun-16, Restrooms

15-Jun-16, Mens 270

Uncover & Polish Floor- Install New Floor Protection

Install Tile

Grout & Seal Tile

Install Lighting & Devices

Install Grills

Install Plumbing Fixtures

Install Partitions

Install Accessories

Final Paint

Uncover Floor & Final Buff

Final Clean

Punch & Corrections

Back Punch

16-Jun-16, Womens 271

Uncover & Polish Floor - Install New Floor Protection

Install Tile

Grout & Seal Tile

Install Lighting & Devices

Install Grills

Install Plumbing Fixtures

Install Partitions

Install Accessories

Final Paint

Uncover Floor & Final Buff

Final Clean

Punch & Corrections

Back Punch

10-Jun-16, Unisex 272

Uncover & Polish Floor - Install New Floor Protection

Install Lighting & Devices

Install Grills

Install Plumbing Fixtures

Install Accessories

Final Paint

Uncover Floor & Final Buff

Final Clean

Punch & Corrections

Back Punch

14-Jun-16, Support Rooms

14-Jun-16, Janitor 252

Uncover Floor & Polish - Install New Floor Protection

Install Lighting & Devices

Install Grills

Install Mop Sink

Install FRP

Remove Floor Protection & Final Buff

Install Rubber Base

UCC Weekly Overall Sub Update 30-Nov-15 10:55

Page 15 of 21

Page 16: HNSB 11.30.15 Health, Nursing & Science Building...28-Sep-16, HNSB 11.30.15 28-Sep-16, Health, Nursing & Science Building 19-Apr-16, Design & Engineering 19-Apr-16, Package 2 Long

# Activity Name OriginalDuration

RemainingDuration

Start Finish Activity %Complete

Resources

870 Install Door & Hardware 2 2 07-Jun-16 08-Jun-16 0% WPI Doors

871 Final Paint 1 1 09-Jun-16 09-Jun-16 0% WPI Paint

872 Final Clean 1 1 10-Jun-16 10-Jun-16 0% Cleaner

873 Punch & Corrections 2 2 10-Jun-16 13-Jun-16 0% Opsis, UCC

874 Back Punch 1 1 14-Jun-16 14-Jun-16 0% ACCO, UCC

875 Closet 233A 12 12 26-May-16 13-Jun-16

876 Install Ceiling Grid & Tile For Devices 1 1 27-May-16 27-May-16 0% Floor Polish

877 Complete Above Ceiling MEP 3 3 26-May-16 31-May-16 0% FM, North Umpqua, Data, North Umpqua, Reynolds, Delta, Essential

878 Complete Electrical Panel Installation 3 3 26-May-16 31-May-16 0% Reynolds

879 Inspections To Cover @ Ceiling 1 1 31-May-16 31-May-16 0% County

880 Install Lights & Grills 1 1 31-May-16 31-May-16 0% Reynolds, FM

881 Install Ceiling Tile 1 1 01-Jun-16 01-Jun-16 0% Harver

882 Complete Electrical/AV/Data/Controls 2 2 01-Jun-16 02-Jun-16 0% Reynolds, Delta, Data, Essential

883 Install Door & Hardware 1 1 03-Jun-16 03-Jun-16 0% WPI Doors

884 Install Flooring & Rubber Base 1 1 06-Jun-16 06-Jun-16 0% Flooring

885 Final Paint 1 1 07-Jun-16 07-Jun-16 0% WPI Paint

886 Final Clean 1 1 08-Jun-16 08-Jun-16 0% Cleaner

887 Punch & Corrections 2 2 09-Jun-16 10-Jun-16 0% Opsis, ACCO

888 Back Punch 1 1 13-Jun-16 13-Jun-16 0% UCC

889 Classrooms 21 21 27-May-16 27-Jun-16

890 Flex Classrooms 210 & 211 21 21 27-May-16 27-Jun-16

891 Uncover & Polish Floor - Install New Floor Protection 2 2 27-May-16 31-May-16 0% Floor Polish

892 Install Ceiling Grid & Tile For Devices 2 2 01-Jun-16 02-Jun-16 0% Harver

893 Complete Above Ceiling MEP 3 3 02-Jun-16 06-Jun-16 0% O & S, FM, North Umpqua, Data, Delta, Essential, Reynolds

894 Install Partition 3 3 06-Jun-16 08-Jun-16 0% Accessories

895 Inspections To Cover @ Ceiling 2 2 07-Jun-16 08-Jun-16 0% County

896 Install Ceiling Tile 2 2 08-Jun-16 09-Jun-16 0% Harver

897 Install Roller Shades 1 1 09-Jun-16 09-Jun-16 0% Accessories

898 Install Marker Boards 1 1 09-Jun-16 09-Jun-16 0% Accessories

899 Complete Electrical/AV/Data/Controls 3 3 09-Jun-16 13-Jun-16 0% Reynolds, Data, Delta, Essential

900 Install Relites 2 2 13-Jun-16 14-Jun-16 0% Culver

901 Remove Floor Protection & Final Buff 1 1 15-Jun-16 15-Jun-16 0% Floor Polish

902 Install Rubber Base 2 2 15-Jun-16 16-Jun-16 0% Flooring

903 Install Doors & Hardware 2 2 16-Jun-16 17-Jun-16 0% WPI Doors

904 Final Paint 2 2 17-Jun-16 20-Jun-16 0% WPI Paint

905 Final Clean 2 2 21-Jun-16 22-Jun-16 0% Cleaner

906 Punch & Corrections 2 2 23-Jun-16 24-Jun-16 0% Opsis, ACCO

907 Back Punch 2 2 24-Jun-16 27-Jun-16 0% UCC, ACCO

908 Move In Owner Furniture 1 1 27-Jun-16 27-Jun-16 0% UCC

909 Classrooms 212 & 213 19 19 31-May-16 24-Jun-16

910 Uncover & Polish Floor - Install New Floor Protection 3 3 31-May-16 02-Jun-16 0% Floor Polish

911 Install Ceiling Grid & Tile For Devices 2 2 03-Jun-16 06-Jun-16 0% Harver

912 Complete Above Ceiling MEP 3 3 06-Jun-16 08-Jun-16 0% O & S, FM, North Umpqua, Data, Delta, Essential, Reynolds

913 Inspections To Cover @ Ceiling 2 2 07-Jun-16 08-Jun-16 0% County

914 Install Ceiling Tile 2 2 09-Jun-16 10-Jun-16 0% Harver

915 Install Relites 2 2 09-Jun-16 10-Jun-16 0% Culver

916 Install Roller Shades 1 1 13-Jun-16 13-Jun-16 0% Accessories

917 Install Marker Boards 1 1 13-Jun-16 13-Jun-16 0% Accessories

918 Complete Electrical/AV/Data/Controls 3 3 10-Jun-16 14-Jun-16 0% TK, Delta, Data, Essential, Reynolds

919 Remove Floor Protection & Final Buff 1 1 15-Jun-16 15-Jun-16 0% Floor Polish

920 Install Rubber Base 2 2 15-Jun-16 16-Jun-16 0% Flooring

921 Install Doors & Hardware 1 1 17-Jun-16 17-Jun-16 0% WPI Doors

922 Final Paint 1 1 20-Jun-16 20-Jun-16 0% WPI Paint

923 Final Clean 1 1 21-Jun-16 21-Jun-16 0% Cleaner

924 Punch & Corrections 2 2 22-Jun-16 23-Jun-16 0% Opsis, ACCO

925 Back Punch 1 1 24-Jun-16 24-Jun-16 0% UCC, ACCO

926 Move In Owner Furniture 1 1 24-Jun-16 24-Jun-16 0% UCC

927 Conference & Work Room 22 22 03-Jun-16 05-Jul-16

Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct

2015 2016

Install Door & Hardware

Final Paint

Final Clean

Punch & Corrections

Back Punch

13-Jun-16, Closet 233A

Install Ceiling Grid & Tile For Devices

Complete Above Ceiling MEP

Complete Electrical Panel Installation

Inspections To Cover @ Ceiling

Install Lights & Grills

Install Ceiling Tile

Complete Electrical/AV/Data/Controls

Install Door & Hardware

Install Flooring & Rubber Base

Final Paint

Final Clean

Punch & Corrections

Back Punch

27-Jun-16, Classrooms

27-Jun-16, Flex Classrooms 210 & 211

Uncover & Polish Floor - Install New Floor Protection

Install Ceiling Grid & Tile For Devices

Complete Above Ceiling MEP

Install Partition

Inspections To Cover @ Ceiling

Install Ceiling Tile

Install Roller Shades

Install Marker Boards

Complete Electrical/AV/Data/Controls

Install Relites

Remove Floor Protection & Final Buff

Install Rubber Base

Install Doors & Hardware

Final Paint

Final Clean

Punch & Corrections

Back Punch

Move In Owner Furniture

24-Jun-16, Classrooms 212 & 213

Uncover & Polish Floor - Install New Floor Protection

Install Ceiling Grid & Tile For Devices

Complete Above Ceiling MEP

Inspections To Cover @ Ceiling

Install Ceiling Tile

Install Relites

Install Roller Shades

Install Marker Boards

Complete Electrical/AV/Data/Controls

Remove Floor Protection & Final Buff

Install Rubber Base

Install Doors & Hardware

Final Paint

Final Clean

Punch & Corrections

Back Punch

Move In Owner Furniture

05-Jul-16, Conference & Work Room

UCC Weekly Overall Sub Update 30-Nov-15 10:55

Page 16 of 21

Page 17: HNSB 11.30.15 Health, Nursing & Science Building...28-Sep-16, HNSB 11.30.15 28-Sep-16, Health, Nursing & Science Building 19-Apr-16, Design & Engineering 19-Apr-16, Package 2 Long

# Activity Name OriginalDuration

RemainingDuration

Start Finish Activity %Complete

Resources

928 Conference 250 17 17 03-Jun-16 27-Jun-16

929 Install Ceiling Grid & Tiles For Devices 1 1 03-Jun-16 03-Jun-16 0% Harver

930 Complete Above Ceiling MEP 3 3 06-Jun-16 08-Jun-16 0% Data, Essential, O & S, FM, North Umpqua

931 Inspections To Cover @ Ceiling 1 1 09-Jun-16 09-Jun-16 0% County

932 Install Ceiling Tile 1 1 10-Jun-16 10-Jun-16 0% Harver

933 Install Relites, Door & Hardware 2 2 13-Jun-16 14-Jun-16 0% WPI Doors, Culver

934 Complete Electrical/AV/Data/Controls 3 3 15-Jun-16 17-Jun-16 0% Delta, Essential, Reynolds

935 Install Carpet & Rubber Base 1 1 20-Jun-16 20-Jun-16 0% Flooring

936 Final Paint 1 1 21-Jun-16 21-Jun-16 0% WPI Paint

937 Final Clean 1 1 22-Jun-16 22-Jun-16 0% Cleaner

938 Punch & Corrections 2 2 23-Jun-16 24-Jun-16 0% Opsis, ACCO

939 Back Punch 1 1 27-Jun-16 27-Jun-16 0% UCC, ACCO

940 Move In Owner Furniture 1 1 27-Jun-16 27-Jun-16 0% UCC

941 Work 251 22 22 03-Jun-16 05-Jul-16

942 Uncover & Polish Floor - Install New Floor Protection 2 2 03-Jun-16 06-Jun-16 0% Floor Polish

943 Install Ceiling Grid & Tile For Devices 2 2 07-Jun-16 08-Jun-16 0% Harver

944 Complete Above Ceiling MEP 3 3 08-Jun-16 10-Jun-16 0% O & S, FM, North Umpqua, Data, Delta, Essential, Reynolds

945 Inspections To Cover @ Ceiling 1 1 10-Jun-16 10-Jun-16 0% County

946 Install Ceiling Tile 1 1 13-Jun-16 13-Jun-16 0% Harver

947 Install Cabinets 5 5 13-Jun-16 17-Jun-16 0% S & B

948 Install Sink & Fixtures 2 2 17-Jun-16 20-Jun-16 0% North Umpqua

949 Install Relite 1 1 20-Jun-16 20-Jun-16 0% Culver

950 Complete Electrical/AV/Data/Controls 2 2 21-Jun-16 22-Jun-16 0% Delta, Data, Essential, Reynolds

951 Remove Floor Protection & Final Buff 1 1 23-Jun-16 23-Jun-16 0% Floor Polish

952 Install Door & Hardware 1 1 24-Jun-16 24-Jun-16 0% WPI Doors

953 Install Rubber Base 1 1 27-Jun-16 27-Jun-16 0% Flooring

954 Final Paint 1 1 28-Jun-16 28-Jun-16 0% WPI Paint

955 Final Clean 1 1 29-Jun-16 29-Jun-16 0% Cleaner

956 Punch & Corrections 2 2 30-Jun-16 01-Jul-16 0% Opsis, ACCO

957 Back Punch 1 1 05-Jul-16 05-Jul-16 0% UCC, ACCO

958 Move In Owner Furnitrue 1 1 05-Jul-16 05-Jul-16 0% UCC

959 Labs 35 35 06-Jun-16 25-Jul-16

960 Physics & Geology 214 27 27 06-Jun-16 13-Jul-16

961 Uncover & Polish Floor - Install New Floor Protection 2 2 06-Jun-16 07-Jun-16 0% Floor Polish

962 Install Ceiling Grid & Tile For Devices 2 2 08-Jun-16 09-Jun-16 0% Harver

963 Complete Above Ceiling MEP 5 5 09-Jun-16 15-Jun-16 0% O & S, FM, North Umpqua, Data, Delta, Essential, Reynolds

964 Inspections To Cover @ Ceiling 2 2 15-Jun-16 16-Jun-16 0% County

965 Install Ceiling Tile 2 2 16-Jun-16 17-Jun-16 0% Harver

966 Install Cabinets 5 5 16-Jun-16 22-Jun-16 0% S & B

967 Install Counter Tops 5 5 21-Jun-16 27-Jun-16 0% S & B

968 Install Sinks & Fixtures 3 3 27-Jun-16 29-Jun-16 0% North Umpqua

969 Install Hood H - 6A 3 3 29-Jun-16 01-Jul-16 0% Accessories

970 Complete G, A ,V & ICW Including Testing 5 5 29-Jun-16 06-Jul-16 0% North Umpqua, North Umpqua

971 Complete Electrical/AV/Data/Controls 5 5 29-Jun-16 06-Jul-16 0% Essential, Delta, Data, Reynolds

972 Install Relites 1 1 06-Jul-16 06-Jul-16 0% Culver

973 Install Marker Boards 1 1 06-Jul-16 06-Jul-16 0% Accessories

974 Uncover Floor & Final Buff 1 1 07-Jul-16 07-Jul-16 0% Floor Polish

975 Install Doors & Hardware 1 1 07-Jul-16 07-Jul-16 0% WPI Doors

976 Install Rubber Base 1 1 07-Jul-16 07-Jul-16 0% Flooring

977 Install Roller Shades 1 1 07-Jul-16 07-Jul-16 0% Accessories

978 Final Paint 1 1 08-Jul-16 08-Jul-16 0% WPI Paint

979 Final Clean 1 1 11-Jul-16 11-Jul-16 0% Cleaner

980 Punch & Corrections 3 3 08-Jul-16 12-Jul-16 0% Opsis, ACCO

981 Back Punch 1 1 13-Jul-16 13-Jul-16 0% UCC, ACCO

982 Move In Owner Equipment 1 1 13-Jul-16 13-Jul-16 0% ACCO, UCC

983 Anatomy/Physiology 220 29 29 07-Jun-16 18-Jul-16

984 Uncover & Polish Floor - Install New Floor Protection 2 2 07-Jun-16 08-Jun-16 0% Floor Polish

985 Install Ceiling Grid & Tile For Devices 2 2 08-Jun-16 09-Jun-16 0% Harver

Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct

2015 2016

27-Jun-16, Conference 250

Install Ceiling Grid & Tiles For Devices

Complete Above Ceiling MEP

Inspections To Cover @ Ceiling

Install Ceiling Tile

Install Relites, Door & Hardware

Complete Electrical/AV/Data/Controls

Install Carpet & Rubber Base

Final Paint

Final Clean

Punch & Corrections

Back Punch

Move In Owner Furniture

05-Jul-16, Work 251

Uncover & Polish Floor - Install New Floor Protection

Install Ceiling Grid & Tile For Devices

Complete Above Ceiling MEP

Inspections To Cover @ Ceiling

Install Ceiling Tile

Install Cabinets

Install Sink & Fixtures

Install Relite

Complete Electrical/AV/Data/Controls

Remove Floor Protection & Final Buff

Install Door & Hardware

Install Rubber Base

Final Paint

Final Clean

Punch & Corrections

Back Punch

Move In Owner Furnitrue

25-Jul-16, Labs

13-Jul-16, Physics & Geology 214

Uncover & Polish Floor - Install New Floor Protection

Install Ceiling Grid & Tile For Devices

Complete Above Ceiling MEP

Inspections To Cover @ Ceiling

Install Ceiling Tile

Install Cabinets

Install Counter Tops

Install Sinks & Fixtures

Install Hood H - 6A

Complete G, A ,V & ICW Including Testing

Complete Electrical/AV/Data/Controls

Install Relites

Install Marker Boards

Uncover Floor & Final Buff

Install Doors & Hardware

Install Rubber Base

Install Roller Shades

Final Paint

Final Clean

Punch & Corrections

Back Punch

Move In Owner Equipment

18-Jul-16, Anatomy/Physiology 220

Uncover & Polish Floor - Install New Floor Protection

Install Ceiling Grid & Tile For Devices

UCC Weekly Overall Sub Update 30-Nov-15 10:55

Page 17 of 21

Page 18: HNSB 11.30.15 Health, Nursing & Science Building...28-Sep-16, HNSB 11.30.15 28-Sep-16, Health, Nursing & Science Building 19-Apr-16, Design & Engineering 19-Apr-16, Package 2 Long

# Activity Name OriginalDuration

RemainingDuration

Start Finish Activity %Complete

Resources

986 Complete Above Ceiling MEP 5 5 07-Jun-16 13-Jun-16 0% O & S, FM, North Umpqua, Data, Delta, Essential, Reynolds

987 Inspections To Cover @ Ceiling 2 2 13-Jun-16 14-Jun-16 0% County

988 Install Ceiling Tile 2 2 14-Jun-16 15-Jun-16 0% Harver

989 Install Cabinets 5 5 15-Jun-16 21-Jun-16 0% S & B

990 Install Counter Tops 5 5 20-Jun-16 24-Jun-16 0% S & B

991 Install Sinks & Fixtures 5 5 23-Jun-16 29-Jun-16 0% North Umpqua

992 Complete LCW, LHW, G, LV & LA Including Testing 5 5 24-Jun-16 30-Jun-16 0% North Umpqua, North Umpqua

993 Complete Electrical/AV/Data/Controls 5 5 24-Jun-16 30-Jun-16 0% Delta, Data, Essential, Reynolds

994 Install Relites 1 1 30-Jun-16 30-Jun-16 0% Culver

995 Install Marker Boards 1 1 01-Jul-16 01-Jul-16 0% Accessories

996 Uncover Floor & Final Buff 1 1 05-Jul-16 05-Jul-16 0% Floor Polish

997 Install Doors & Hardware 2 2 06-Jul-16 07-Jul-16 0% WPI Doors

998 Install Rubber Base 1 1 08-Jul-16 08-Jul-16 0% Flooring

999 Install Roller Shades 1 1 11-Jul-16 11-Jul-16 0% Accessories

1000 Final Paint 1 1 12-Jul-16 12-Jul-16 0% WPI Paint

1001 Final Clean 1 1 13-Jul-16 13-Jul-16 0% Cleaner

1002 Punch & Corrections 3 3 13-Jul-16 15-Jul-16 0% ACCO, Opsis

1003 Back Punch 1 1 18-Jul-16 18-Jul-16 0% UCC, ACCO

1004 Move In Owner Equipment 1 1 18-Jul-16 18-Jul-16 0% UCC, ACCO

1005 Chemistry Lab 231 27 27 08-Jun-16 15-Jul-16

1006 Install Ceiling Grid & Tile For Devices 2 2 09-Jun-16 10-Jun-16 0% Harver

1007 Complete Above Ceiling MEP 5 5 08-Jun-16 14-Jun-16 0% North Umpqua, Data, Delta, Reynolds, Essential, O & S, FM

1008 Inspections To Cover @ Ceiling 2 2 14-Jun-16 15-Jun-16 0% County

1009 Install Ceiling Tile 2 2 15-Jun-16 16-Jun-16 0% Harver

1010 Install Cabinets 5 5 15-Jun-16 21-Jun-16 0% S & B

1011 Install Counter Tops 5 5 20-Jun-16 24-Jun-16 0% S & B

1012 Install Sinks & Fixtures 4 4 24-Jun-16 29-Jun-16 0% North Umpqua

1013 Install Fume Hoods 5 5 29-Jun-16 06-Jul-16 0% Accessories

1014 Complete G, A, V & ICW Including Testing 5 5 06-Jul-16 12-Jul-16 0% North Umpqua, North Umpqua, Special Inspection

1015 Complete Electrical/AV/Data/Controls 5 5 06-Jul-16 12-Jul-16 0% Delta, Data, Essential, Reynolds

1016 Install Relites 2 2 11-Jul-16 12-Jul-16 0% Culver

1017 Install Marker Boards 1 1 12-Jul-16 12-Jul-16 0% Accessories

1018 Install Doors & Hardware 2 2 12-Jul-16 13-Jul-16 0% WPI Doors

1019 Install Flooring & Rubber Base 2 2 12-Jul-16 13-Jul-16 0% Flooring

1020 Install Roller Shades 1 1 13-Jul-16 13-Jul-16 0% Accessories

1021 Final Paint 1 1 14-Jul-16 14-Jul-16 0% WPI Paint

1022 Final Clean 1 1 14-Jul-16 14-Jul-16 0% Cleaner

1023 Punch & Corrections 3 3 13-Jul-16 15-Jul-16 0% Opsis, ACCO

1024 Back Punch 1 1 15-Jul-16 15-Jul-16 0% UCC, ACCO

1025 Move In Owner Equipment 1 1 15-Jul-16 15-Jul-16 0% UCC, ACCO

1026 Insturment Prep 232 26 26 13-Jun-16 19-Jul-16

1027 Install Ceiling Grid & Tile For Devices 2 2 13-Jun-16 14-Jun-16 0% Harver

1028 Complete Above Ceiling MEP 5 5 13-Jun-16 17-Jun-16 0% O & S, FM, North Umpqua, Data, Delta, Essential, Reynolds

1029 Inspections To Cover @ Ceiling 1 1 17-Jun-16 17-Jun-16 0% County

1030 Install Ceiling Tile 1 1 20-Jun-16 20-Jun-16 0% Harver

1031 Install Cabinets 5 5 20-Jun-16 24-Jun-16 0% S & B

1032 Install Counter Tops 5 5 23-Jun-16 29-Jun-16 0% S & B

1033 Install Sink & Fixtures 4 4 29-Jun-16 05-Jul-16 0% North Umpqua

1034 Complete G, A, V & ICW Including Testing 5 5 01-Jul-16 08-Jul-16 0% North Umpqua, Special Inspection, North Umpqua

1035 Complete Electrical/AV/Data/Controls 5 5 01-Jul-16 08-Jul-16 0% Reynolds, Delta, Data, Essential

1036 Install Doors & Hardware 2 2 07-Jul-16 08-Jul-16 0% WPI Doors

1037 Install Flooring & Rubber Base 2 2 11-Jul-16 12-Jul-16 0% Flooring

1038 Final Paint 1 1 13-Jul-16 13-Jul-16 0% WPI Paint

1039 Final Clean 1 1 14-Jul-16 14-Jul-16 0% Cleaner

1040 Punch & Corrections 3 3 14-Jul-16 18-Jul-16 0% Opsis, ACCO

1041 Back Punch 1 1 19-Jul-16 19-Jul-16 0% UCC, ACCO

1042 Move In Owner Equipment 1 1 19-Jul-16 19-Jul-16 0% UCC, ACCO

1043 Stock Room/Closet 233 24 24 14-Jun-16 18-Jul-16

Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct

2015 2016

Complete Above Ceiling MEP

Inspections To Cover @ Ceiling

Install Ceiling Tile

Install Cabinets

Install Counter Tops

Install Sinks & Fixtures

Complete LCW, LHW, G, LV & LA Including Testing

Complete Electrical/AV/Data/Controls

Install Relites

Install Marker Boards

Uncover Floor & Final Buff

Install Doors & Hardware

Install Rubber Base

Install Roller Shades

Final Paint

Final Clean

Punch & Corrections

Back Punch

Move In Owner Equipment

15-Jul-16, Chemistry Lab 231

Install Ceiling Grid & Tile For Devices

Complete Above Ceiling MEP

Inspections To Cover @ Ceiling

Install Ceiling Tile

Install Cabinets

Install Counter Tops

Install Sinks & Fixtures

Install Fume Hoods

Complete G, A, V & ICW Including Testing

Complete Electrical/AV/Data/Controls

Install Relites

Install Marker Boards

Install Doors & Hardware

Install Flooring & Rubber Base

Install Roller Shades

Final Paint

Final Clean

Punch & Corrections

Back Punch

Move In Owner Equipment

19-Jul-16, Insturment Prep 232

Install Ceiling Grid & Tile For Devices

Complete Above Ceiling MEP

Inspections To Cover @ Ceiling

Install Ceiling Tile

Install Cabinets

Install Counter Tops

Install Sink & Fixtures

Complete G, A, V & ICW Including Testing

Complete Electrical/AV/Data/Controls

Install Doors & Hardware

Install Flooring & Rubber Base

Final Paint

Final Clean

Punch & Corrections

Back Punch

Move In Owner Equipment

18-Jul-16, Stock Room/Closet 233

UCC Weekly Overall Sub Update 30-Nov-15 10:55

Page 18 of 21

Page 19: HNSB 11.30.15 Health, Nursing & Science Building...28-Sep-16, HNSB 11.30.15 28-Sep-16, Health, Nursing & Science Building 19-Apr-16, Design & Engineering 19-Apr-16, Package 2 Long

# Activity Name OriginalDuration

RemainingDuration

Start Finish Activity %Complete

Resources

1044 Install Ceiling Grid & Tile For Devices 2 2 15-Jun-16 16-Jun-16 0% Harver

1045 Complete Above Ceiling MEP 5 5 14-Jun-16 20-Jun-16 0% O & S, FM, North Umpqua, Data, Delta, Essential, Reynolds

1046 Inspections To Cover @ Ceiling 2 2 20-Jun-16 21-Jun-16 0% County

1047 Install Ceiling Tile 2 2 21-Jun-16 22-Jun-16 0% Harver

1048 Install Cabinets 5 5 22-Jun-16 28-Jun-16 0% S & B

1049 Install Counter Tops 5 5 24-Jun-16 30-Jun-16 0% S & B

1050 Install Sinks & Fixtures 3 3 30-Jun-16 05-Jul-16 0% North Umpqua, North Umpqua

1051 Complete G, A, V & ICW Including Testing 5 5 29-Jun-16 06-Jul-16 0% North Umpqua, North Umpqua

1052 Complete Electrical/AV/Data/Controls 5 5 29-Jun-16 06-Jul-16 0% Delta, Data, Essential, Reynolds

1053 Install Relite 1 1 06-Jul-16 06-Jul-16 0% Culver

1054 Install Roller Shades 1 1 06-Jul-16 06-Jul-16 0% Accessories

1055 Install Doors & Hardware 2 2 05-Jul-16 06-Jul-16 0% WPI Doors

1056 Install Flooring & Rubber Base 3 3 05-Jul-16 07-Jul-16 0% Flooring

1057 Final Paint 2 2 08-Jul-16 11-Jul-16 0% WPI Paint

1058 Final Clean 2 2 11-Jul-16 12-Jul-16 0% Cleaner

1059 Punch & Corrections 3 3 13-Jul-16 15-Jul-16 0% Opsis, ACCO

1060 Back Punch 1 1 18-Jul-16 18-Jul-16 0% UCC, ACCO

1061 Move In Owner Equipment 1 1 18-Jul-16 18-Jul-16 0% UCC, ACCO

1062 Roof Access 234 9 9 16-Jun-16 28-Jun-16

1063 Uncover & Polish Floor - Install New Floor Protection 2 2 16-Jun-16 17-Jun-16 0% Floor Polish

1064 Complete Electrical/AV/Data/Controls 1 1 17-Jun-16 17-Jun-16 0% Delta, Data, Essential, Reynolds

1065 Install Door & Hardware 1 1 20-Jun-16 20-Jun-16 0% WPI Doors

1066 Uncover Floor & Final Buff 1 1 21-Jun-16 21-Jun-16 0% Floor Polish

1067 Install Rubber Base 1 1 22-Jun-16 22-Jun-16 0% Flooring

1068 Final Paint 1 1 23-Jun-16 23-Jun-16 0% WPI Paint

1069 Final Clean 1 1 24-Jun-16 24-Jun-16 0% Cleaner

1070 Punch & Corrections 3 3 23-Jun-16 27-Jun-16 0% Opsis, ACCO

1071 Back Punch 1 1 28-Jun-16 28-Jun-16 0% Opsis, ACCO

1072 Chem Storage 235 20 20 20-Jun-16 18-Jul-16

1073 Install Ceiling Grid & Tile For Devices 2 2 20-Jun-16 21-Jun-16 0% Harver

1074 Complete Above Ceiling MEP 3 3 20-Jun-16 22-Jun-16 0% North Umpqua, Data, Delta, Essential, O & S, FM, Reynolds

1075 Inspections To Cover @ Ceiling 1 1 22-Jun-16 22-Jun-16 0% County

1076 Install Ceiling Tile 1 1 23-Jun-16 23-Jun-16 0% Harver

1077 Install Cabinets 5 5 22-Jun-16 28-Jun-16 0% S & B

1078 Install Counter Tops 5 5 27-Jun-16 01-Jul-16 0% S & B

1079 Install Sink & Fixtures 3 3 01-Jul-16 06-Jul-16 0% North Umpqua

1080 Install Hood H-4 2 2 06-Jul-16 07-Jul-16 0% Accessories

1081 Complete G, A, V & ICW Including Testing 5 5 05-Jul-16 11-Jul-16 0% North Umpqua, North Umpqua

1082 Complete Electrical/AV/Data/Controls 5 5 05-Jul-16 11-Jul-16 0% Delta, Data, Essential, Reynolds

1083 Install Doors & Hardware 2 2 08-Jul-16 11-Jul-16 0% WPI Doors

1084 Install Flooring & Rubber Base 3 3 08-Jul-16 12-Jul-16 0% Flooring

1085 Final Paint 1 1 13-Jul-16 13-Jul-16 0% WPI Paint

1086 Final Clean 1 1 13-Jul-16 13-Jul-16 0% Cleaner

1087 Punch & Corrections 3 3 13-Jul-16 15-Jul-16 0% Opsis, ACCO

1088 Back Punch 1 1 18-Jul-16 18-Jul-16 0% UCC, ACCO

1089 Move In Owner Furniture 1 1 18-Jul-16 18-Jul-16 0% UCC, ACCO

1090 Biology Lab 236 23 23 22-Jun-16 25-Jul-16

1091 Install Ceiling Grid & Tile For Devices 2 2 22-Jun-16 23-Jun-16 0% Harver

1092 Complete Above Ceiling MEP 3 3 22-Jun-16 24-Jun-16 0% O & S, FM, North Umpqua, Data, Reynolds, Delta, Essential

1093 Inspections To Cover @ Ceiling 2 2 24-Jun-16 27-Jun-16 0% County

1094 Install Ceiling Tile 2 2 24-Jun-16 27-Jun-16 0% Harver

1095 Install Cabinets 5 5 23-Jun-16 29-Jun-16 0% S & B

1096 Install Counter Tops 5 5 27-Jun-16 01-Jul-16 0% S & B

1097 Install Sinks & Fixtures 3 3 01-Jul-16 06-Jul-16 0% North Umpqua

1098 Install Fume Hood 2 2 05-Jul-16 06-Jul-16 0% Accessories

1099 Complete G, A, V & ICW Including Testing 5 5 05-Jul-16 11-Jul-16 0% North Umpqua

1100 Complete Electrical/AV/Data/Controls 5 5 05-Jul-16 11-Jul-16 0% Delta, Data, Essential, Reynolds

1101 Install Relite 1 1 11-Jul-16 11-Jul-16 0% Culver

Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct

2015 2016

Install Ceiling Grid & Tile For Devices

Complete Above Ceiling MEP

Inspections To Cover @ Ceiling

Install Ceiling Tile

Install Cabinets

Install Counter Tops

Install Sinks & Fixtures

Complete G, A, V & ICW Including Testing

Complete Electrical/AV/Data/Controls

Install Relite

Install Roller Shades

Install Doors & Hardware

Install Flooring & Rubber Base

Final Paint

Final Clean

Punch & Corrections

Back Punch

Move In Owner Equipment

28-Jun-16, Roof Access 234

Uncover & Polish Floor - Install New Floor Protection

Complete Electrical/AV/Data/Controls

Install Door & Hardware

Uncover Floor & Final Buff

Install Rubber Base

Final Paint

Final Clean

Punch & Corrections

Back Punch

18-Jul-16, Chem Storage 235

Install Ceiling Grid & Tile For Devices

Complete Above Ceiling MEP

Inspections To Cover @ Ceiling

Install Ceiling Tile

Install Cabinets

Install Counter Tops

Install Sink & Fixtures

Install Hood H-4

Complete G, A, V & ICW Including Testing

Complete Electrical/AV/Data/Controls

Install Doors & Hardware

Install Flooring & Rubber Base

Final Paint

Final Clean

Punch & Corrections

Back Punch

Move In Owner Furniture

25-Jul-16, Biology Lab 236

Install Ceiling Grid & Tile For Devices

Complete Above Ceiling MEP

Inspections To Cover @ Ceiling

Install Ceiling Tile

Install Cabinets

Install Counter Tops

Install Sinks & Fixtures

Install Fume Hood

Complete G, A, V & ICW Including Testing

Complete Electrical/AV/Data/Controls

Install Relite

UCC Weekly Overall Sub Update 30-Nov-15 10:55

Page 19 of 21

Page 20: HNSB 11.30.15 Health, Nursing & Science Building...28-Sep-16, HNSB 11.30.15 28-Sep-16, Health, Nursing & Science Building 19-Apr-16, Design & Engineering 19-Apr-16, Package 2 Long

# Activity Name OriginalDuration

RemainingDuration

Start Finish Activity %Complete

Resources

1102 Install Marker Boards 1 1 11-Jul-16 11-Jul-16 0% Accessories

1103 Install Doors & Hardware 2 2 11-Jul-16 12-Jul-16 0% WPI Doors

1104 Install Flooring & Rubber Base 3 3 11-Jul-16 13-Jul-16 0% Flooring

1105 Install Roller Shades 1 1 14-Jul-16 14-Jul-16 0% Accessories

1106 Final Paint 1 1 15-Jul-16 15-Jul-16 0% WPI Paint

1107 Final Clean 2 2 18-Jul-16 19-Jul-16 0% Cleaner

1108 Punch & Corrections 3 3 20-Jul-16 22-Jul-16 0% ACCO, Opsis

1109 Back Punch 1 1 25-Jul-16 25-Jul-16 0% UCC, ACCO

1110 Move In Owner Equipment 1 1 25-Jul-16 25-Jul-16 0% UCC, ACCO

1111 Offices 18 18 23-Jun-16 19-Jul-16

1112 Offices 260A Thru 260L 18 18 23-Jun-16 19-Jul-16

1113 Uncover & Polish Floor - Install New Floor Protection 3 3 23-Jun-16 27-Jun-16 0% Floor Polish

1114 Install Ceiling Grid & Tile For Devices 3 3 24-Jun-16 28-Jun-16 0% Harver

1115 Complete Above Ceiling MEP 3 3 24-Jun-16 28-Jun-16 0% Reynolds, Delta, Essential, O & S, FM, North Umpqua, Data

1116 Inspections To Cover @ Ceiling 2 2 27-Jun-16 28-Jun-16 0% County

1117 Install Ceiling Tile 3 3 27-Jun-16 29-Jun-16 0% Harver

1118 Complete Electrical/AV/Data/Controls 3 3 28-Jun-16 30-Jun-16 0% Delta, Data, Essential, Reynolds

1119 Install Relites 3 3 28-Jun-16 30-Jun-16 0% Culver

1120 Install Roller Shades 2 2 29-Jun-16 30-Jun-16 0% Accessories

1121 Remove Floor Protection & Final Buff 3 3 29-Jun-16 01-Jul-16 0% Floor Polish

1122 Install Doors & Hardware 3 3 29-Jun-16 01-Jul-16 0% WPI Doors

1123 Install Rubber Base 3 3 01-Jul-16 06-Jul-16 0% Flooring

1124 Final Paint 3 3 06-Jul-16 08-Jul-16 0% WPI Paint

1125 Final Clean 2 2 11-Jul-16 12-Jul-16 0% Cleaner

1126 Punch & Corrections 4 4 12-Jul-16 15-Jul-16 0% Opsis, ACCO

1127 Back Punch 2 2 18-Jul-16 19-Jul-16 0% UCC, ACCO

1128 Move In Owner Furniture 1 1 19-Jul-16 19-Jul-16 0% UCC, ACCO

1129 Office Corridors 18 18 27-Jun-16 21-Jul-16

1130 Corridor 203 18 18 27-Jun-16 21-Jul-16

1131 Uncover & Polish Floor - Install New Floor Protection 3 3 27-Jun-16 29-Jun-16 0% Floor Polish

1132 Install Ceiling Grid & Tile For Devices 3 3 29-Jun-16 01-Jul-16 0% Harver

1133 Complete Above Ceiling MEP 4 4 30-Jun-16 06-Jul-16 0% O & S, FM, North Umpqua, Data, Reynolds, Delta, Essential

1134 Inspections To Cover @ Ceilings 2 2 06-Jul-16 07-Jul-16 0% County

1135 Install Ceiling Tile 2 2 08-Jul-16 11-Jul-16 0% Harver

1136 Complete Electrical/AV/Data/Controls 2 2 11-Jul-16 12-Jul-16 0% Delta, Data, Essential, Reynolds

1137 Remove Floor Protection & Final Buff 1 1 12-Jul-16 12-Jul-16 0% Floor Polish

1138 Install Rubber Base 1 1 13-Jul-16 13-Jul-16 0% Flooring

1139 Final Paint 2 2 14-Jul-16 15-Jul-16 0% WPI Paint

1140 Final Clean 1 1 18-Jul-16 18-Jul-16 0% Cleaner

1141 Punch & Corrections 3 3 18-Jul-16 20-Jul-16 0% Opsis, ACCO

1142 Back Punch 1 1 21-Jul-16 21-Jul-16 0% UCC, ACCO

1143 Commons & Circulation 25 25 29-Jun-16 03-Aug-16

1144 Corridor 202 17 17 29-Jun-16 22-Jul-16

1145 Uncover & Polish Floor - Install New Floor Protection 3 3 29-Jun-16 01-Jul-16 0% Floor Polish

1146 Complete Electrical/AV/Data/Controls 3 3 05-Jul-16 07-Jul-16 0% Delta, Data, Essential, Reynolds

1147 Remove Floor Protection & Final Buff 2 2 08-Jul-16 11-Jul-16 0% Floor Polish

1148 Install Rubber Base 2 2 11-Jul-16 12-Jul-16 0% Flooring

1149 Final Paint 2 2 13-Jul-16 14-Jul-16 0% WPI Paint

1150 Final Clean 2 2 15-Jul-16 18-Jul-16 0% Cleaner

1151 Punch & Corrections 3 3 19-Jul-16 21-Jul-16 0% Opsis, ACCO

1152 Back Punch 1 1 22-Jul-16 22-Jul-16 0% UCC, ACCO

1153 Vestibule 202A 10 10 01-Jul-16 15-Jul-16

1154 Install Ceiling Framing 1 1 05-Jul-16 05-Jul-16 0% Harver

1155 Complete Above Ceiling MEP 2 2 01-Jul-16 05-Jul-16 0% Reynolds, O & S, North Umpqua, Data, Delta, Essential

1156 Inspection To Cover @ Ceiling 1 1 05-Jul-16 05-Jul-16 0% County

1157 Install Store Fronts 3 3 06-Jul-16 08-Jul-16 0% Culver

1158 Install Walk Off Mats 2 2 08-Jul-16 11-Jul-16 0% Flooring

1159 Final Paint 1 1 12-Jul-16 12-Jul-16 0% WPI Paint

Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct

2015 2016

Install Marker Boards

Install Doors & Hardware

Install Flooring & Rubber Base

Install Roller Shades

Final Paint

Final Clean

Punch & Corrections

Back Punch

Move In Owner Equipment

19-Jul-16, Offices

19-Jul-16, Offices 260A Thru 260L

Uncover & Polish Floor - Install New Floor Protection

Install Ceiling Grid & Tile For Devices

Complete Above Ceiling MEP

Inspections To Cover @ Ceiling

Install Ceiling Tile

Complete Electrical/AV/Data/Controls

Install Relites

Install Roller Shades

Remove Floor Protection & Final Buff

Install Doors & Hardware

Install Rubber Base

Final Paint

Final Clean

Punch & Corrections

Back Punch

Move In Owner Furniture

21-Jul-16, Office Corridors

21-Jul-16, Corridor 203

Uncover & Polish Floor - Install New Floor Protection

Install Ceiling Grid & Tile For Devices

Complete Above Ceiling MEP

Inspections To Cover @ Ceilings

Install Ceiling Tile

Complete Electrical/AV/Data/Controls

Remove Floor Protection & Final Buff

Install Rubber Base

Final Paint

Final Clean

Punch & Corrections

Back Punch

03-Aug-16, Commons & Circulation

22-Jul-16, Corridor 202

Uncover & Polish Floor - Install New Floor Protection

Complete Electrical/AV/Data/Controls

Remove Floor Protection & Final Buff

Install Rubber Base

Final Paint

Final Clean

Punch & Corrections

Back Punch

15-Jul-16, Vestibule 202A

Install Ceiling Framing

Complete Above Ceiling MEP

Inspection To Cover @ Ceiling

Install Store Fronts

Install Walk Off Mats

Final Paint

UCC Weekly Overall Sub Update 30-Nov-15 10:55

Page 20 of 21

Page 21: HNSB 11.30.15 Health, Nursing & Science Building...28-Sep-16, HNSB 11.30.15 28-Sep-16, Health, Nursing & Science Building 19-Apr-16, Design & Engineering 19-Apr-16, Package 2 Long

# Activity Name OriginalDuration

RemainingDuration

Start Finish Activity %Complete

Resources

1160 Final Clean 1 1 12-Jul-16 12-Jul-16 0% Cleaner

1161 Punch & Corrections 3 3 12-Jul-16 14-Jul-16 0% Opsis, ACCO

1162 Back Punch 1 1 15-Jul-16 15-Jul-16 0% Opsis, ACCO

1163 Corridor 201 13 13 01-Jul-16 20-Jul-16

1164 Uncover & Polish Floor - Install New Floor Protection 3 3 01-Jul-16 06-Jul-16 0% Floor Polish

1165 Complete Electrical/AV/Data/Controls 3 3 07-Jul-16 11-Jul-16 0% Delta, Data, Essential, Reynolds

1166 Remove Floor Protection & Final Buff 2 2 12-Jul-16 13-Jul-16 0% Floor Polish

1167 Install Rubber Base 2 2 13-Jul-16 14-Jul-16 0% Flooring

1168 Final Paint 2 2 15-Jul-16 18-Jul-16 0% WPI Doors

1169 Final Clean 1 1 18-Jul-16 18-Jul-16 0% Cleaner

1170 Punch & Corrections 3 3 15-Jul-16 19-Jul-16 0% Opsis, ACCO

1171 Back Punch 1 1 20-Jul-16 20-Jul-16 0% UCC, ACCO

1172 Stair 1 & Atrium Handrails 20 20 07-Jul-16 03-Aug-16

1173 Install Handrails @ Stairs & Level 2 Opening 7 7 07-Jul-16 15-Jul-16 0% L & M/Westside Iron

1174 Prime & 1st Coat 3 3 14-Jul-16 18-Jul-16 0% WPI Doors

1175 Install Treads 5 5 18-Jul-16 22-Jul-16 0% Mason

1176 Final Paint 4 4 22-Jul-16 27-Jul-16 0% WPI Doors

1177 Install Cable Handrails 4 4 27-Jul-16 01-Aug-16 0% Accessories

1178 Punch & Corrections 3 3 01-Aug-16 03-Aug-16 0% Opsis, ACCO

1179 Back Punch 1 1 03-Aug-16 03-Aug-16 0% UCC, ACCO

1180 West Bridge 25 25 30-Jun-16 04-Aug-16

1181 Complete Bridge Structure 1 1 30-Jun-16 30-Jun-16 0% L & M/Westside Iron

1182 Install Handrail Supports 5 5 01-Jul-16 08-Jul-16 0% L & M/Westside Iron

1183 Prime & 1st Coat 3 3 11-Jul-16 13-Jul-16 0% WPI Paint

1184 Complete Handrails 5 5 14-Jul-16 20-Jul-16 0% Wood Finishes

1185 Final Paint 2 2 21-Jul-16 22-Jul-16 0% WPI Paint

1186 Final Clean 2 2 25-Jul-16 26-Jul-16 0% Cleaner

1187 Punch & Corrections 5 5 27-Jul-16 02-Aug-16 0% Design, ACCO

1188 Back Punch 2 2 03-Aug-16 04-Aug-16 0% UCC, ACCO

1189 Site Finishes & New Fire Lane 40 40 19-May-16 15-Jul-16

1190 Layout & Install Site Finish & Fire Lane Concrete 40 40 19-May-16 15-Jul-16 0% Knife River, Guido

1191 Landscaping 40 40 03-Jun-16 29-Jul-16

1192 Layout & Install Landscaping 40 40 03-Jun-16 29-Jul-16 0%

1193 Install PV Array 30 30 19-May-16 30-Jun-16

1194 Install PV Array 30 30 19-May-16 30-Jun-16 0%

1195 Project Closeout 56 56 11-Jul-16 27-Sep-16

1196 Substantial Completion 28 28 11-Jul-16 17-Aug-16

1197 Weather Days 10 10 11-Jul-16 22-Jul-16 0% ACCO

1198 Final Inspections Complete 1 1 04-Aug-16 04-Aug-16 0% Opsis, UCC, ACCO

1199 Substantial Completion & Temporary Occupancy 1 1 17-Aug-16 17-Aug-16 0% ACCO, UCC, County, Special Inspection, Fire Marshall

1200 Final Completion 28 28 17-Aug-16 27-Sep-16

1201 Commissioning Complete 1 1 23-Sep-16 26-Sep-16 0% ACCO

1202 Leed Documentation Complete 20 20 17-Aug-16 14-Sep-16 0% ACCO

1203 Certificate of Occupancy & Final Completion 1 1 27-Sep-16 27-Sep-16 0% ACCO, UCC

Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct

2015 2016

Final Clean

Punch & Corrections

Back Punch

20-Jul-16, Corridor 201

Uncover & Polish Floor - Install New Floor Protection

Complete Electrical/AV/Data/Controls

Remove Floor Protection & Final Buff

Install Rubber Base

Final Paint

Final Clean

Punch & Corrections

Back Punch

03-Aug-16, Stair 1 & Atrium Handrails

Install Handrails @ Stairs & Level 2 Opening

Prime & 1st Coat

Install Treads

Final Paint

Install Cable Handrails

Punch & Corrections

Back Punch

04-Aug-16, West Bridge

Complete Bridge Structure

Install Handrail Supports

Prime & 1st Coat

Complete Handrails

Final Paint

Final Clean

Punch & Corrections

Back Punch

15-Jul-16, Site Finishes & New Fire Lane

Layout & Install Site Finish & Fire Lane Concrete

29-Jul-16, Landscaping

Layout & Install Landscaping

30-Jun-16, Install PV Array

Install PV Array

27-Sep-16, Project Closeout

17-Aug-16, Substantial Completion

Weather Days

Final Inspections Complete

Substantial Completion & Temporary Occupancy

27-Sep-16, Final Completion

Commissioning Complete

Leed Documentation Complete

Certificate of Occupancy & Final Completion

UCC Weekly Overall Sub Update 30-Nov-15 10:55

Page 21 of 21