hong kong polytechnic universityeeserver.ee.polyu.edu.hk/fyp/fyp_201718/ft/fyp_21/final... · 2018....

50
- 1 - The Hong Kong Polytechnic University Department of Electrical Engineering Project ID : FYP_21 Anti-islanding Protection for Distributed Generation by CHEUNG Kok Wai Raymond 14116265d Final Report Bachelor of Engineering (Honours) in Electrical Engineering Of The Hong Kong Polytechnic University Supervisor: Dr. Kevin Ka-wing CHAN Date: March 31, 2018

Upload: others

Post on 28-Jan-2021

3 views

Category:

Documents


0 download

TRANSCRIPT

  • - 1 -

    The Hong Kong Polytechnic University

    Department of Electrical Engineering

    Project ID : FYP_21

    Anti-islanding Protection for Distributed Generation

    by

    CHEUNG Kok Wai Raymond

    14116265d

    Final Report

    Bachelor of Engineering (Honours) in

    Electrical Engineering

    Of

    The Hong Kong Polytechnic University

    Supervisor: Dr. Kevin Ka-wing CHAN Date: March 31, 2018

  • - 2 -

    Abstract

    While a power grid was suddenly unstable and unintentional disturbance, the commonly used

    protection relays (voltage and frequency) would detect the islanding of the distributed

    generator (DG) which is connected to the power grid. Meanwhile, the ROCOF and frequency

    relays are common adopted to detect the islanding and tripped the circuit breaker of loads

    automatically. Unfortunately, these relays are not fully reliable because of their associated

    non-detection zone (NDZ). The main contribution of the project is to demonstrate the simple

    and practical analytical methods to implement the islanding detection. Passive method

    (frequency relays & ROCOF) are separately selected to built-in to the power supply system, and

    tried to suspend the power supply to the load. Then, find out the range of NDZ in frequency

    relay. These simulation results are carried out on MATLAB / SIMULINK software.

    Keywords: Islanding detection, NDZ, RoCoF & frequency replays.

  • - 3 -

    Table of Content

    ABSTRACT……………………………………………………………………………………2

    TABLE OF CONTENT...……………………………………………………………………..3

    LIST OF ACRONYMS…………………………………………………………………….…4

    CHAPTER 1 INTRODUCTION……………………………………………………………..5

    1.1 OVERVIEW……………………………………………………………………………5

    1.2 PROPOSAL OUTLINE…...………………………………………………………..…10

    CHAPTER 2 OBJECTIVES………………………………………………………………...11

    CHAPTER 3 BACKGROUND…………………………………………………….………..12

    CHAPTER 4 METHODOLOGY…………………………………………………………...15

    4.1 ROCOF PROTECTION RELAY…...…………………………………………………18

    4.2 FREQUENCY PROTECTION RELAY………………………………………………29

    4.3 NON DETECTION ZONE…………………………………………………………....34

    4.4 THRESHOLD SETTING & OPTIMIZATION………………………………………..37

    4.5 OTHER DETECTION METHOD…………………………………………………….39

    CHPATER 5 RESULTS……………………………………………………………………..41

    CHPATER 6 CONCLUSION AND FUTURE DEVELOPMENT.……………………….47

    REFERENCES…………………………………………………………………………….…49

  • - 4 -

    List of Acronyms

    DG Distributed Generation (DG)

    ROCOF Rate of Change of Frequency

    FR Frequency-based Relays

    NDZ Non Detection Zone

    AI Anti-islanding

    DWT Discrete wavelet transform

    PCC Point of Common Coupling

  • - 5 -

    Chapter 1 Introduction

    1.1 Overview

    Over the past few decades, fossil fuels (oil, coal and natural gas) have been traditionally used

    to generate the sources of electrical energy. In fact, burning fossil fuels will release the

    environmental pollutions, these pollutions cause smog, acid rain, greenhouse effect and

    climate change. In addition, the electrical energy from the generating plants will be

    transmitted to the customer load through long distances transmission lines and the certain

    kind of step down transformers. Although the higher voltage of transmitting electricity can

    reduce the current and resistive losses, others factors will also affect the resistance of the

    conductor of transmission line. For example, the electrons would be collided together in the

    transmission line and the energy lost (heat and crackling sound) would also be produced

    under the sunlight. To replace the thermal energy sources, many countries are willing to put in

    more resources to develop renewable energy to meet the energy consumption. Renewable

    energy resources-such as geothermal, hydro, solar and wind energy-are naturally replenished

    and will never terminate in the earth. Thus, the amount of the renewable energy generations

    are increased to the distributed network to share of electrical supply in many countries.

    Moreover, the advantages of the distributed generation (DG) system are energy conservation,

    reducing electrical losses due to no need of large transmission line and as backup power

    supply for important loads. The DG systems in parallel with the electric utility network will

    typically generate the small-scale energy in size from 3 kilowatts (kW) to 10 megawatts

  • - 6 -

    (MW). Normally, DG systems are connected to the power grid through power electronic

    converters [1]. Although DG systems are going to play an important role in mitigation of

    climate change, rising the sustainable electric power for demanders, it causes the islanding

    phenomenon while the electric utility is suddenly down.

    If the electrical energy are only supplied from the power station, the reactive power and others

    energy loss will be produced, as shown in Fig 1.1.

    Fig 1.1 – Power flows in traditional network

  • - 7 -

    When embedded generators are newly increased to the distribution network, it can reduce the

    capacity of power output from power stations and the extent of complementarity between

    power stations and embedded generators will be greatly enhanced in the grid network system,

    as shown in Fig 1.2.

    Fig 1.2 – Power flows with distributed generator

  • - 8 -

    Although the advantage of the distribution generation can decrease the energy loss from the

    transmission line, there is the disadvantages associated with using embedded generators

    during the power stations provides the unstable electrical energy.

    In normal condition, both the power plants and the embedded generators will generate the

    electrical energy to the loads through power grid network, as showed in Fig 1.3

    In unintentional condition, the embedded generators continue to keep working even through

    the utility grid has suddenly fault. Unwanted islanding will be appeared, as shown in Fig

    1.4.

    Embedded Generator

    Distribution Feeder to Loads

    Overhead Line

    Fig. 1.3 - Normal Condition Network

  • - 9 -

    There are common causes of islanding in the distribution networks:

    - Some distributions are isolated from the reset of the power system but still energized by

    the connected DG systems in the distribution networks.

    - The utility power supply is accidently shut down.

    - For maintenance operations, utility switching of the loads and distribution system.

    - Vandalism

    - Natural disasters.

    Generally, the influence of the islanding phenomenon will adversely cause the problems:

    - Safety hazard for line-workers who may assume the DG systems are not energized during

    the inspection of power grid failure.

    Embedded Generator

    Fig. 1.4 - Unintentional Condition Network

    Distribution Feeder to Loads

    Overhead Line

    Fault occurred

    before step down

    transformer.

  • - 10 -

    - Without the voltage/frequency rating of main grid network for reference, the DGs might

    generate unstable voltage and frequency (under or over), it is a probability of damage the

    customer’s loads or power grid network.

    - After islanded is solved, a large current may flow to the DG due to out of voltage phase of

    circuit breaker. It may trip the utility power supply again.

    - Islanding may distribute the restoration of power to the customers

    To effectively isolate the operation of DG during islanding, each DG must have the anti-

    islanding protection systems to detect islanded and to prevent the unstable rating of voltage

    and frequency to the loads immediately.

    1.2 Proposal Outline

    Chapter 2 will discuss the objective about the selection of the better islanding protection

    method, simulation model design and observation of the NDZ size at different load.

    Chapter 3 will briefly introduce the advantage and disadvantage of the detection methods to

    monitor between the grid network and DG.

    Chapter 4 will study the procedure of selected methods (Passive method : RoCoF & FR) to

    the islanded.

    Chapter 5 will plan the preliminary result to the project.

    Chapter 6 is a brief conclusion of the proposal regarding the benefits and drawback of the

    methods and future development.

  • - 11 -

    Chapter 2 Objectives

    For islanding detection methods, it is developed in the distributed power system so far. The

    objectives of this proposal are :

    1. Selection of the better islanding protection method

    To consider the advantage and disadvantage of both active and passive methods, it will try

    to combine both methods in this proposal. In normal electrical supply, passive method

    (either Rate of Change of Frequency (ROCOF) or Frequency-based Relay(FR)) will the

    detection devices. In ideal concept, it is anticipated to solve the islanding phenomone in

    different conditions.

    2. Simulation model design

    Using the Matlab software, it will simulate the power grid network with DG. The circuit

    breaker of the loads will receive the rating of frequency change or phase shift at the

    instant from the Point of Common Coupling (PCC) to control the the electrical supply.

    Moreover, the rating of reactive power will be detected by the active method during

    islanded.

    3. Observation of the NDZ size

    According to the IEEE 929[2] and UL1741 standard[3], it states that the loads will be set

    to the power output. The reason of different loads are observed which of passive methods

    that is more suitable for the detection of the NDZ size.

  • - 12 -

    Chapter 3 Background

    According to the international standard of the IEEE 1547, islanding should be detected and

    disconnected within 200ms[2]. Moreover, there are 2 nos. of main methods have been

    propsed to monitor the islanding: Remote and Local Methods[4]. Generally, the remote

    islanding detection method depends on the communication between the power grid network

    and the DG. The local islanding detection mehtod depends on the measurement of some

    parameters on the DG side, such as voltage, frequency and current. Local methods are also

    classified as active and passive methods. Active methods : it will intentionally peturb a

    disturbances signal to the output of the inverter and observe the influence of parameters

    outlined; Passive methods : it uses the local measurments of the parameters to montior the

    operatrion of both DG and

    grid networks. The Fig. 3.1 is

    shown the classification of the

    islanding detection methods.

    Remote Methods

    (Communication methods) is a most effective, high reliability to approach protection

    detection, but it is very expensive for small system compared to local methods and need

    communication infrastructure.

    Fig. 3.1 - Classification of islanding detection methods

  • - 13 -

    The common remote methods are included :

    - Transfer Trip Scheme

    - Power Line Carrier Communication (PLCC)

    - Supervisory Control and Data Acquisition (SCADA)

    Active Methods (Local Methods) are characterized by their small NDZ size, useful for

    multiple DG and apply to inverter based DG. Due to the intentional injection of perturbation

    in the grid network, the methods will affect the power quality, long time for detection and

    implement difficulty. The common active methods are included :

    - Impedance Measurement

    - Active Frequency Drift (with positive feedback)

    - Sandia Frequency/Voltage Shift

    - Sliding Mode Frequency Shift

    - Negative Sequence Current Injection

    - Variation of Active and Reactive Power

    - Detection of Impedance as Specific Frequency

    Passive Methods (Local Methods) has fast response during detection, non-influence of power

    quality, without perturbation in system and cost-effective. However, it is useless for multiple

    DG and nuisance tripping when maintaining work. The significant problem of passive

    method has a large NDZ size without false trips. The common passive methods are included :

  • - 14 -

    - Rate of Change of Frequency (RoCoF)

    - Phase Jump Detection (Vector Surge)

    - Voltage Unbalance

    - Over/Under Voltage and Frequency

    - Harmonic Distortion

    - Rate of Change of Output Power

  • - 15 -

    Chapter 4 Methodology

    Before adopting the anti-islanding protection, it will focus on the characteristics of the

    distributed generator unit. The power generated by distributed generator should be keep in

    constant equilibrium of power supply and demand to prevent the power deviation. However, the

    operation of the generator must produce the electrical speed from the same mechanical speeds.

    Both of the speeds are related to the number of machine poles “p”,

    The equation is We = [p / 2 * Wm] … (1) (We – electrical speed, Wm – mechanical speed)

    To ensure electrical speed from one to another generator, the synchronous generators must keep

    constant of the mechanical speed. The equation of the synchronous speed is n(sync) = [f * 60 / p]

    (f – frequency of 3 phase power supply, p – no. of pole pairs)

    When the amount of pole pair is increased, the speed of synchronous generator will be

    decreased, the result is shown in the table 4.1.

    Pole Pair number 1 2 3 4 5 6

    Synchronous speed [rpm]

    at 50 Hz

    3000 1500 1000 750 600 500

    Synchronous speed [rpm]

    at 60 Hz

    3600 1800 1200 900 720 600

    Table 4.1 - Relationship of pole pair no. and Synchronous speed (rpm)

  • - 16 -

    In addition, the mechanical speed of the rotation in rad/s would also be changed to the

    synchronous speed, the equation is Nm = [We * 2 / p (rad/s) * 60 / (2 * π) (sec/min)

    /(rad/rev)] ... (2). The result is shown in Table 4.2.

    No. of

    poles(P)

    Synchronous

    speed(Ns)

    No. of

    poles(P)

    Synchronous

    speed(Ns)

    No. of

    poles(P)

    Synchronous

    speed(Ns)

    2 ( 30/π )*We 8 ( 7.5/π )*We 14 ( 4.285/π )*We

    4 ( 15/π )*We 10 ( 6/π )*We 16 ( 3.75/π )*We

    6 ( 10/π )*We 12 ( 5/π )*We 18 ( 3.333/π )*We

    In fact, it is difficult to maintain the constant speed during the operation. For example, the

    amount of the power demand is more than the system generation, the rate of the speed will be

    fallen, and the power demand is less than other, the rate of the speed will be risen.

    According to the block diagram of speed governing (Fig 4.1), it illustrates the power variations

    between ∆Pm and ∆Pe :

    Table 4.2 Mechanical speed and synchronous speed at different poles

    Fig. 4.1 Block diagram of speed governing

  • - 17 -

    The speed deviation (∆w) formulation becomes:

    ∆w(s) = (1/2*Hs)( ∆Pm - ∆PL - D∆w) or ∆w(s) = (1/(2*Hs + D))( ∆Pm - ∆PL) … (3)

    ∆Pe = ∆PL + D*∆w … (4)

    Pm – Mechanical power input to generator,

    Pe – Electrical power output of generator,

    PL – Non-frequency sensitive load change,

    H – Inertia constant of the generator,

    D – Load damping constant

    If the Pm is step down, it may cause the unbalance of the power: Pe > Pm. The speed w(s) will

    be decreased below nominal until the Pe is reduced to the Pm. Using the Laplace transformed,

    the steady-state speed deviation (∆wss) can be calculated by change in time domain ∆w(t) from

    frequency domain ∆w(s). The feedback of speed governing is determined by H & D.

    The equation of the inertia constant H = Stored kinetic energy in megajoules at synchronous

    speed / machine MVA rating = (1/2) * (J* {w(rad/s)}² / Sbase) … (5)

  • - 18 -

    4.1 ROCOF protection relay

    ROCOF is another popular protection relay to detect the islanded in the power network.

    However, if the load and generation on the part of the network that becomes islanded are closely

    matched; the limitation is recognised in Engineering Recommendation (ETR) 113 [5] section

    3.4.5. The trip signal will transfer to the circuit breaker to cut off the power supply of distributed

    generated immediately whether the result of ROCOF is out of the pre-set range (threshold). The

    settings of ROCOF are between 0.1 Hz/s and 1.2 Hz/s in 50 Hz [6].

    The ROCOF is proportional to the value of active power imbalance between the generator

    output and local load. The equation of ROCOF

    is ∆f/∆t = [- (PL - Pdg) * f(rated) / (2H *

    Sn) ] … (6), drawing is shown in Fig 4.2

    H - inertia constant of the generator[s]

    f (rated) - rated frequency of the generator[Hz]

    PL – Local load[MW]

    Pdg – generator output[MW]

    Sn – nominal generator rating[MVA]

    Using the Matlab / Simulink to design power network with main power supply, customer load

    and the synchronous generator, it is the common method to simulate the situation of power

    distribution. The model of main power supply (swing type) is shown in Fig 4.3. The power

    Fig 4.2 - ROCOF

  • - 19 -

    source provides 1000V rated voltage to the 15kW load through a 11000V/380V transformer.

    On the other hand, the model of distributed generator network is shown in Fig 4.4. It also

    provides the electrical power to the customer load through another 3-phase transformer.

    Fig 4.3 Main power supply network

    Fig 4.4 - distributed generator network

  • - 20 -

    The circuit breakers (CB) in the network acts as a part of ROCOF relay. When the main power

    supply is suddenly broken down in the main grid. The CB on distributed generation side will

    receive the order to turn off the power supply to customer load. Then, each parameter has

    connected to the 3 phase measurements in the circuit, the function of the measurement is to

    indicate the value of the voltage and current in the network instantaneously. The scope will

    collect the measured data and display signals produced during simulation in terms of time. The

    signal is displayed in the scope, as shown in Fig 4.5.

    In the power network, 3 phase delta / star (Dy) transformers are used to step up the voltage

    rating, the information of two transformers are shown in Fig 4.6:

    The turn ratio of (Dy) transformer (a) = V1/V2 * (3)^(½)

    = (11000/380) * (3)^(½) = 50.1

    The current of apparent power of main power supply = 15000 / [(3)^(½) * 11000] = 0.787A.

    The current of apparent power of customer load = 15000 / [(3)^(½) * 380] = 22.8A.

    Fig. 4.5 - Scope displays the signals

  • - 21 -

    In normal condition, both main power supply and distributed generator supply the electricity to

    the customer load. However, the main power grid is unable to supply the power to the load due

    to unpredictable disasters or power fault. The 3 phase measurement of main power grid will

    obtain the no power signal on 0.3 second and display on the screen, as shown on Fig 4.7.

    Fig 4.6 - 11kV/380V transformer

    Fig 4.7 No current supplied from the main grid

  • - 22 -

    Meanwhile, the distributed generator has increased the current rating to the customer load after

    the main grid has suspended the power supply on the 0.3 second, as shown on Fig 4.8.

    In the distributed generator, the typical synchronous generator will also provide the electricity to

    customer load. The information of synchronous generator is shown in Fig 4.9.

    The inertia constant H = (1/2) * (J(w(rad/s))² / Sbase) = (1/2) * ( 4.86 * (50 * π)² / 15000) = 4s

    The synchronous speed of the generator = (50 * π)rad/s / (2 * π / 60) = 1500 rpm.

    The synchronous generator has 2 important parts: Hydraulic Turbine & Governor (HTG) block

    and Excitation System block (refer to Fig 4.2.). In HTG block, the machine actual speed (we),

    machine actual electrical power (Pe0) and speed deviation (dw) are connected to receive the

    data of feedback loop from the synchronous generator.

    Fig 4.8 - Larger amount of current supplied from Distributed Generator

  • - 23 -

    Reference speed (wref) and reference mechanical power (Pref) are indicated to the constant

    valve. The output of HTG acts as the mechanical power (pm) for the synchronous generator

    block. For Excitation System, the vd and vq inputs are connected to receive the data of feedback

    loop from the synchronous generator. The desired valve of the stator terminal voltage (vref) is

    indicated to the constant valve and the power system stabilizer (vstab) is connected to ground

    block. The output of excitation system acts as the field voltage (Vf) for the synchronous

    generator. The machine initialization of the powergui tool should be set up before running the

    synchronous generator.

    On the other hand, the output A, B and C of synchronous generator are connected to the parallel

    load (GL15kW). It is because the generator acts as a current source in Simulink software and it

    Fig 4.9 - Synchronous Generator

  • - 24 -

    is unable to connect in series with the 3 phase transformer (the inductive component). The high

    value of parallel load can prevent bad effect on simulated system.

    To understand ROCOF protection relay in the network, there is a flow chart of ROCOF to

    describe the operation in each step, as shown in Fig 4.10.

    Fig 4.10 – Flow Chart of ROCOF

  • - 25 -

    - Different frequency will be measured from Point of Common Coupling (PCC).

    - Then, keeping measuring the rate of change of frequency. When the power mismatch occurs,

    the frequency will be change.

    - If the variation of frequency is detected within the acceptable range of setting, ROCOF does

    not detect the change in frequency.

    - If the change in frequency is out of the range of setting, ROCOF can detect the changed and

    generate the signal to circuit breaker for breakdown the circuit.

  • - 26 -

    The model of ROCOF protection relay is created in the Matlab / Simulink, as shown in Fig 4.11.

    The operation of ROCOF protection relay model in the simulation

    The Phase Lock Loop ‘PLL’ block determine will continuously track the frequency of 3 phase

    sinusoidal signals. An initial frequency must be specified because the function measures the

    frequency of input signal based on the difference between the actual frequency and the initial

    frequency [7].

    When receiving the voltage signal from the 3 phase measurement of customer load, the ‘PLL’

    block will change the input signal from Clarke’s transformation [e.g. 3 phase (ABC) to 2 phase

    (ab)] to Park transform [e.g. stationary 2-phase windings (ab) to rotating 2-phase windings (dq)].

    The (dp) signal will be transferred to the derivative block and the real time frequency signal will

    be displayed in the scope block. After leaving the derivative block, the (dq) signal will change to

    the value of ROCOF that will enter to the transfer function block. The transfer function makes

    the curve of the data versus time more fluent. The Abs block will adjust the value to “absolute”

    Fig 4.11 – ROCOF Relay Simulation Model

  • - 27 -

    value. Then, the absolute value will compare with the pre-set constant block which is the

    threshold. The relational operator will also collect the comparison result to decide the operation

    of the circuit breaker for the synchronous generator. If the absolute value of ROCOF is smaller

    than the threshold, it means no islanding in the circuit and the relational operator will display to

    “1”, the circuit breaker will keep in switch on. Otherwise, if the absolute value of ROCOF is

    larger than the threshold, it means islanding will occur in the circuit and the relational operator

    will display to “0”, the circuit breaker will switch off to terminate the power supply to the

    customer load.

    The simulation model of ROCOF protection system is shown in Fig 4.12.

  • - 28 -

    Fig 4.12 – Simulation Model of ROCOF Protection Relay

    Simulation Model

  • - 29 -

    4.2 Frequency Protection Relay

    Generally, the detection time of islanding should be set within 200 to 400ms. Many distributed

    synchronous generator systems have built in under/over frequency relays (FR). Although the

    IEEE distributed resources interconnection guide recommends that a DG must not be

    disconnected due to small frequency variation. [2], the FR is much simpler for the protection

    system of the distributed generators. The operation of the FR is dependent on the active power

    imbalance which is happened on the islanded system, mismatch between the bus-bar generation

    and load. When the mismatch of active power decreases, the capability to quickly detect

    islanding of these devices diminishes accordingly [8]. However, the generation and load are

    very close, the frequency relays may fail to detect an islanding. When Pm is balanced to Pe, the

    rotor speed (w) and angle (δ) of the distributed generator are constant respectively. If the

    disturbance is occurred at the distributed network, the frequency will be changed because the

    active power imbalance (∆P) will causes the transients in the distributed generators. The swing

    equation of synchronous generators is listed below:

    (2*H/wo) * (dδ/dt) = ∆Pm - ∆PL = ∆P … (7)

    dδ/dt = w – wo … (8) (w : generator rotor speed, wo - synchronous speed)

    Substitute (8) into (7)

    w = (wo* ∆P / 2*H) * t + wo … (9)

    The system angular speed in the time w = wo + ∆w,

  • - 30 -

    wo + ∆w = (wo*∆P / 2*H) * t + wo => ∆w = (wo*∆P / 2*H) * t … (10)

    where w = 2πf.

    So, ∆w = (wo*∆P / 2*H) * t => ∆f = (fo*∆P) / (2*H) * t … (11)

    Equation (11) is provided the relationship between active power imbalance (∆P), frequency

    deviation(∆f) and the detection time(t). The frequency relays can also be adjusted with the time-

    delay settings (tset).

    t = (2*H*∆f) / (fo*∆P) + tset … (12)

    In order to estimate the operation of the frequency relay, the swing equation is used to observe

    the performance of frequency relays between the detection time and active power imbalance.

    Using the equation (12) to find out the performance curve of frequency relays at the detection

    time from 0 to 1 second, as shown in Table 4.3 and Fig 4.13.

    Table 4.3 – Active power imbalance vs detection time

  • - 31 -

    In the curve of performance of FR, x-axis is the active power imbalance and y-axis is the

    operating time of frequency relays. If the detection time is required within 0.4 second after the

    islanding happened, the intersection of 0.4s horizontal line obtains the 0.25 of active power

    imbalance level. If the islanded occurs high above 0.25 of the active power imbalance, it will

    detect the islanding condition less than 0.4s. If the islanded occurs less than 0.25 level of active

    power imbalance, the relay will take more than 0.4s to operate in the moment. The threshold is

    called the critical power imbalance.

    The variation of frequency is affected by the electrical speed of generator, if the signal is over

    frequency or under frequency setting, the relay will send a trip signal to circuit breaker of the

    generator. The frequency relays can be operated with a time delay to persist the tripping mode

    during the pre-determined time to trigger the frequency relay. In normal condition, the relay will

    be set using the multi-stage, the setting of the time delay are operated at the same time.

    Non-

    Detection

    Zone

    Detection Zone

    Fig 4.13. – Performance Curve of Frequency Relay

  • - 32 -

    The model of Frequency relay is created in the Matlab / Simulink, as shown in Fig 4.14.

    Similarity with the ROCOF simulation model, there are the ‘PLL’ block to collect the voltage

    signal from the 3 phase measurement of customer load and change to the (dp) signal. Before

    entering to the transfer function block, the frequency value will be displayed immediately. The

    transfer function makes the curve of the data versus time more fluent. The output signal from

    the transfer function will compare with 2 nos. of constant block which is connected to Over

    frequency or Under frequency comparator individually. After comparing with the over / under

    frequency comparators, the comparison result will be logically determined by the ‘OR’ gate

    logic. Finally, if the “1” number is indicated on the display, the circuit breaker will keep in

    switch on. Also, if the “0” number is indicated on the display, the circuit breaker will switch off

    to terminate the power supply to the customer load.

    The simulation model of Frequency relay system is shown in Fig 4.15.

    Fig 4.14 – Frequency Relay Simulation

    Model

  • - 33 -

    Fig 4.15 – Simulation Model of Frequency Relay

    Simulation Model

  • - 34 -

    4.3 Non-Detection Zone

    The non-detection-zone (NDZ) method is one of the techniques available to characterize the

    capabilities and limitations of the frequency and voltage relays [9]. If the power imbalance

    between generation and load is not far away, the protection relays could not detect an islanding

    occurrence in a well-timed. Constant current control or constant power control are the 2 used

    control system in distribution generation network. In constant current control, the root mean

    square valve of current is injected to the network as constant. In constant power control, the

    active power and reactive power in each line period are controlled as constant [10]. As shown

    Fig 4.16,

    Before the disconnection of the network, both active and passive power of the load is :

    P(load) = V² / R = P + ∆P … (13)

    Q(load) = ∆Q = V² * [[1/(2 * π * f * L)]-[2 * π * f * C]] … (14)

    Fig 4.16 – Typical distribution generation connected with power network

  • - 35 -

    After the disconnection of the network as shown Fig 4.17, the reactive current will remain zero

    under the current control. The resonant frequency (f ’) of load is :

    f ’ = 1 / (2 * π * (L * C)^½) … (15)

    Using equation (14) is divided by equation (13), then

    Q(load) / P(load) = [[1/(2 * π * f * L)]-[2 * π * f * C]] * R

    = R * (C / L) ^½ * [[1/(2 * π * f * (C * L) ^½ )]-[2 * π * f * (C * L) ^½ ]] … (16)

    Then, substituting equation (15) into equation (16)

    Q(load) / P(load) = ∆Q / P * (1 + ∆P / P)^(-1) = Q(f) * [(f ’ / f) – (f / f ’)] … (17)

    Therefore, Q(f) = R * (C / L) ^½ … (18)

    When the new value of frequency remains between the frequency thresholds, the frequency

    relay will not operate. The non-detection zone of frequency relay for current controlled is

    Q(f) * [(f(min) / f) – (f / f(min))]

  • - 36 -

    f(max))] … (19) (f(min) and f(max) are the setting of frequency thresholds).

    Under the IEEE 1547, the tolerance of the normal voltage frequency is 98.83% to 100.83%.

    So, f(min) = 50 – 0.6 = 49.4 Hz and f(max) 50 + 0.4 = 50.4 … (20)

    Equation (19) will be changed to

    Q(f) * -0.024

  • - 37 -

    4.4 Threshold setting and Optimization

    In order to find the reasonable threshold for the Frequency relay and ROCOF relay that achieve

    to stable and sensitive in the network, automated islanding and reconnections methods have

    been developing in many power plants. If the unpredictable fault has happened in the power grid,

    the power plant will terminate the electrical supply to the customer load. Until the fault is

    resolved, it will be auto-reconnected to the power supply in the network. The question is how to

    detect and breakdown the power supply of the distributed generator during reconnection time, it

    will cause the serious damage of the customer loads due to the confliction of current from both

    sides. The response of the islanding detecting relay should be within 0.2 second. The ideal

    operating time of the relay is recommended to detect the islanding within 0.1 second. Therefore,

    both frequency relay and ROCOF relay should be reliable and sensitive to prevent the operation

    mistake when disturbance occurs in the main grid.

    Several factors may affect the performance of frequency and ROCOF during the islanding. It

    includes the different types of load and power factor, temporary fault in main grid, low value

    power mismatch.

    Different type of load and power factor :

    Investigate the different of certain type of constant load (power, impedance and current) under

    the same model setting. Then searching the reasonable threshold setting for FR and ROCOF

    bases on the acceptable power factor of customer load.

    Temporary fault in main grid:

  • - 38 -

    Many factor will cause the temporary fault in the main grid. Such as, trees growth into

    conductors, trees contact can cause the short circuit of overhead distribution line, or animal-

    caused faults may occur on overhead distribution lines, underground distribution circuits,

    substations, and transmission line [11]. Moreover, the detecting relay has the ability to

    distinguish the real islanding and temporary fault.

    Low value power mismatch:

    The most challenging situation of detecting islanding situation is when the output power of

    distributed generator can exactly match the power consumption of customer load [12]. If the

    frequency of the supply is vibrated intensely, the value change of the FR or ROCOF relay will

    be obscure. Setting the zero output of reactive power can maintain the 100% of the power factor,

    the FR and ROCOF method can easily detect the full power supply from the distributed

    generator during islanding conditions.

  • - 39 -

    4.5 Other detection method

    Wavelet-transform Islanding detection method

    Wavelet transform has been commonly used in power system, like feature power system

    protection, data compression of power quality waveforms, extraction, de-noising etc. [13][14].

    Actually, transient state of voltages and currents has high frequency waveforms, it is unable to

    be detected by general methods on a power frequency. Therefore, wavelet analysis can

    distinguish the islanding or non-islanding in normal operation, it will extract a useful feature to

    achieve the classification [15].

    The structure of wavelet is shown in Fig 4.18[16], there are two paths of filter in each level of

    discrete wavelet transform (DWT). In first level, the low pass filter with impulse response (g)

    can find out the approximation coefficient (a1(n)) and the high pass filter (h) can find out the

    detail coefficients (d1(n)) respectively. The filter outputs are subsampled by 2.

    Fig 4.18 – Structure of wavelet filter level.

    Fig 4.19 – 3 level discrete wavelet transform

    decomposition

  • - 40 -

    Through iterative methods as shown in Fig 4.19[16] in each level, it can be decomposed to

    contain the approximation coefficients and details coefficients in each level.

    The equation of approximation coefficients and details coefficients are listed below :

    … (22)

    … (23)

    (am(n) – approximation coefficient at level m and dm(n) – detail coefficient at level m)

    Compared with other passive islanding methods, wavelet method can react to the spectral

    changes occurring at higher frequency waveform of PCC voltage caused by islanding and detect

    the islanding situation in a smaller NDZ.

  • - 41 -

    Chapter 5 Result

    ROCOF protection relay

    Before connecting to ROCOF relay, the freqency of synchronous generator has raised and

    fallen extremely within 1 second, as shown in Fig 5.1. The crazy stator current is in Fig 5.2

    These frequency and stator current from the generator have caused the ugly sinusoidal

    waveform of current of customer load when both generator and main grid supplied the power

    to the customer load, as shown in (Fig 5.3a, b & c).

    During computing the load flow, it indicates the ‘warning

    notice’ to prohibit the compute of the load flow in the

    powergui, as shown in Fig 5.4. To solve the Load Flow

    Fig 5.1 – Frequency curve from the

    synchronous generator

    Fig 5.2 – Abnormal stator current

    from the synchronous generator

    Fig 5.4 – warning notice

  • - 42 -

    data error, it is recommended to change the status of synchronous generator from PV type to

    swing type. Then the load flow table could be computed, as shown in Fig 5.5

    Fig 5.3a – The output of main supply:

    Voltage rms = 1.075e+4 V, Current rms = 1.779 A

    The power = 33,124 W

    Fig 5.3b – The output of generator:

    Voltage rms = 3.67e+2 V, Current rms = 5.754e+1 A

    The power = 36,576 W

  • - 43 -

    After connecting to the ROCOF relay, the frequency of the customer load voltage decreases

    because of the system islanding occurrence, as shown in Fig 5.6. The value of df/dt of

    ROCOF relay is sufficient to meet the islanding detection. The relay threshold is set to 0.3

    second, if the df/dt value is more than 0.3 to 1 second as shown in Fig 5.7, the relay will

    transfer the tripping signal to the ciruit breaker of generator.

    Fig 5.3c – The customer load :

    Voltage rms = 3.67e+2 V, Current rms = 7.08A

    The power = 4500 W

    Fig 5.5 –Load flow data

  • - 44 -

    Due to trigger the circuit breaker of the generator, the current supply to the customer load is

    decreaed at 0.3 second, as shown in Fig 5.8.

    Fig 5.6 – Frequency curve after islanding

    Fig 5.7 – ROCOF curve after islanding

    Fig 5.8 – Generator current after 0.3 second

  • - 45 -

    Frequency relay

    The situration of results of frequency relay are similar to the ROCOF record before the

    connection to ROCOF relay. If the value of frequency touch up the range of preset threshold,

    the circuit breaker of generator will be turned off, as shown in Fig 5.7.

    Meanwhile, the circuit breaker is received the signal of islanding from frequency relay, it will be

    turned off itself to terminate the power supply to the customer load, as shown in Fig. 5.8. And

    then, the current supply of generator is zero, as shown in Fig. 5.9.

    Fig 5.7 – the frequency touch up the range of preset threshold of the

    relay, it will resume quickly to nominal frequency.

    Fig 5.8 – touching the boundary of preset range, the signal will be

    changed from ‘1’ to ‘0’

  • - 46 -

    Fig 5.9 –The circuit breaker of the generator will be triggered.

  • - 47 -

    Chapter 6 Conclusion & Future Development

    This project presented the typical methods to detect islanding situation for distribution

    generations was proposed. These methods are passive and make decision according to the

    measurement of signal of frequency (ROCOF and Frequency relay). These results indicated the

    relays how to monitor and disconnect the power output from the synchronous generators during

    the islanding occurrence. The results of the protection methods are simulated in Matlab /

    Simulink environment, it can be easily observed the operation of protection relay to power

    supply network.

    In this project, I understood the materiality concept of the anti-islanding protection system to

    power grid network, it can reduce the threats to personnel safety, improve the power quality and

    enhance the sensitivity of the grid networks in normal operation. In order to prevent to the

    islanding effect, the certain kinds of detection method have been developed to solve the any

    situations. The detection methods are categorized into 2 groups: Local methods and Remote

    methods. Each group of detection methods have their own benefits and drawbacks. In local

    methods, passive methods are able to use the inexpensive hardware to activate the protecting

    devices through the measurement of the frequency or voltage, but the limitation of it has the

    NDZ; active methods can inject the intentional signal or harmonic effects to inspect the

    islanding, it can effective minimize the range of NDZ, but more perturbative signals will affect

    the quality of electrical grid network. In remote methods, they are more effective to conquer the

    NDZ problems but they also tend to be more expensive. In the future, remote methods may be

  • - 48 -

    perhaps the most important devices to monitor the islanding effect.

    On the other hand, there are many differences between the fixed parameters and real in change,

    such as alternative of supplies and demands for electrical grids, natural change, etc. Under the

    mandate of IEEE 1547 standard, the simulation results of detection method should be fulfilled

    to the requirement, but the results can only reflect the general condition. In addition, the experts

    will extend more effort to improve the islanding method or create the new technology.

    Overall, this project has very difficult and challenging for me, I need to understand the meaning

    of the islanded situation and the power supply from the utilities power supply and the DG to

    customer load. To seek the different kinds of the journals and reference books, it can be useful

    for analysing the complication equation of detection methods. Unfortunately, I don’t understand

    these complicated journals. It is not much the frequency control of synchronous generator for

    the references in the market. And then, I can only find the basic knowledge of power system

    network in the teaching notes, it isn’t handle the anti-islanding protection project. On the other

    hand, the Matlab / Simulink software is another difficulty and challenging for me to learning.

    For example, I have no enough time and knowledge to understand all parameters setting of

    synchronous generator. Insufficient knowledge leads to incorrect simulated result, etc. In fact it

    is hard to resolves the errors of the simulation result and settle down the mistake.

  • - 49 -

    References

    [1] Hassan Nikkhajoei, Reza Iravani "Steady-State Model and Power Flow Analysis of

    Electronically-Coupled Distributed Resource Units" IEEE Transactions on Power Delivery, Vol.

    22, No. 1, January 2007.

    [2] Standards Coordintating Committee 21: “IEEE standard for interconnecting distributed

    resources with electric power systems”, 1547–2003, 2008, pp. 1–16

    [3] UL 1741, Inverters, Converters, Controllers and Interconnection System Equipment for Use

    with Distributed Energy Resources, 2005.

    [4] M. Ropp, and W. Bower, “Evaluation of islanding detection methods for photovoltaic utility

    interactive power systems,” International Energy Agency Implementing agreement on

    Photovoltaic Power Systems, Tech. Rep. IEA PVPS T5-09, March 2002.

    [5] Engineering Technical Report (ETR) 113, notes of guidance for protection of embedded

    generating plant up to 5MW for operation in parallel with public electricity suppliers’

    distribution systems, 1995 Electricity association.

    [6] W. Freitas, X. Wilsun, C.M. Affonso, H. Zhenyu, “Comparative analysis between ROCOF

    and vector surge relays for distributed generation applications,” IEEE Transactions on Power

    Delivery, vol. 20, pp. 1315-1324, 2005.

    [7] X. Ding and P. A. Crossley, “Islanding detection for distributed generation,” Power Tech,

    2005 IEEE Russia, St. Petersburg, 2005, pp. 1-4.

    [8] W. Freitas, Z. Huang, and W. Xu, “A practical method for assessing the effectiveness of

    vector surge relays for distributed generation applications,” IEEE Trans. Power Del., vol. 1, pp.

    57–63, Jan. 2005.

    [9] J. C. M. Vieira, W. Freitas, W. Xu, and A. Morelato, “An investigate n on the non-detection

    zones of synchronous distributed generation anti-islanding protection,” IEEE Trans. Power Del.,

    vol. 23, no. 2, pp. 593-600, Apr. 2008.

    [10] Zhihong Ye; Kolwalkar, A.; Yu Zhang; Pengwei Du; Reigh Walling, “Evaluation of anti-

    islanding schemes based on non-detection zone concept,” Power Electronics, IEEE

    Transactions, vol. 19, issue 5, pp.1171-1176, Sept. 2004.

    [11] Li Wang, “The Fault Causes of Overhead Lines in Distribution Network,” State Grid

    Nanchong Power Supply Information & Telecommunication Co. Ltd., Matec Web of

    Conferences 61, 02017 (2016), pp. 3.

  • - 50 -

    [12] H. Laaksonen, “Advanced Islanding Detection Functionality for Future Electricity

    Distribution Networks,” in IEEE Transactions on Power Delivery, vol. 28, no. 4, pp. 2056-2064,

    Oct. 2013.

    [13] U. D. Dwivedi, S.N. Singh, "De-noising Techniques with Change Point Approach for

    Wavelet-Based Power Quality Monitoring," IEEE Transactions on Power Delivery, vol. 24, no.

    3, pp. 1719-1727, 2009.

    [14] Daubechies, J., "The wavelet transforms, time frequency localization and signal analysis,"

    IEEE Transaction IT, vol. 36, no. 5, pp. 961-1005, 1990.

    [15] M. R. Vatani, M. J. Sanjari, G. Gharehpetian, M. Noroozian, "A New Fast and Reliable

    Method for Islanding Detection Based on Transient Signal," in 2nd Iranian Conference on

    Smart Gird, Tehran, Iran, 212.

    [16] D.C. Robertson, O.I. Camps, J.S. Mayer, and W.B. Gish, "Wavelets and Electromagnetic

    Power System Transients," Proc. IEEE Transactions on Power 75 Del., vol. 11, no. 2, Apr.

    1996.