ho_p2_06

Upload: kriza-sevilla-matro

Post on 09-Mar-2016

186 views

Category:

Documents


10 download

DESCRIPTION

DFYUQcf

TRANSCRIPT

  • 1 P2 - 06

    IMUS INSTITUTE SY 2015- 2016 PRACTICAL ACCOUNTING II SPECIAL REVENUE RECOGNITION LONG TERM CONSTRUCTIONS CONTRACTS PROBLEM 1 In 2013, DJ Builders Construction agreed to construct an apartment building at a price of P2,000,000. The information relating to the costs and billings for the contract is as follows:

    2013 2014 2015 Costs incurred to date 560,000 1,200,000 1,570,000 Estimated costs yet to be incurred 1,040,000 400,000 - Customer billings each year 750,000 560,000 690,000 Collection of billings each year 560,000 640,000 700,000 Determine the following:

    1. Using Percentage-of-completion Method- for the year ended December 31, 2013, 2014 and 2015 a. Current assets, cost and profits in excess of billings (gross amount due from customers) b. Current liability, billings in excess of cost and profits (gross amount due to customers) c. Current asset, contract amount in excess of billings d. Current asset, deferred profit e. Construction In-Progress Account f. Contract Billings g. Recognize revenue h. Construction Costs i. Gross Profit 2. Using Cost Recovery Method/ Zero-profit Approach - for the year ended December 31, 2013, 2014 and 2015 j. Current assets, cost and profits in excess of billings (gross amount due from customers) k. Current liability, billings in excess of cost and profits (gross amount due to customers) l. Current asset, contract amount in excess of billings m. Current asset, deferred profit n. Construction In-Progress Account o. Contract Billings p. Recognize revenue q. Construction Costs r. Gross Profit PROBLEM 2 On February 01, 2013, JJD Construction Company obtained a contract to build an athletic stadium. The stadium was to be built at a total cost of P10,800,000 and was scheduled for completion by September 01, 2011. One clause of the contract stated that JJD was to deduct P30,000 from the P13,200,000 billing for each week that completion was delayed. Completion was delayed six weeks, which resulted in a P180,000 penalty. Below are the data pertaining to the construction period.

    2013 2014 2015 Costs incurred each year 3,664,000 * 4,136,000 3,200,000 Estimated costs to complete 7,136,000 3,200,000 - Progress billings each year 3,600,000 5,900,000 3,520,000 Cash collection to date 3,600,000 9,400,000 13,020,000 Operating expenses 200,000 180,000 140,000 *including cement materials stored amounting to P100,000 that is held offsite to be used in 2015 to complete the project. For each year show how the details related to this contract would be disclosed on the balance sheet and on the income statement:

    1. Using Percentage-of-completion Method a. Construction In-Progress Account b. Net income c. Recognize revenue d. Construction Costs e. Gross Profit 2. Using Cost Recovery Method/ Zero-profit Approach

  • 2 P2 - 06

    a. Construction In-Progress Account b. Net income c. Recognize revenue d. Construction Costs e. Gross Profit

    PROBLEM 3 On July 01, 2013, GB Construction Corp. Contracted to build an office building for RX, Inc. For a total contract price of P1,825,000

    2013 2014 2015 Contract cost incurred 350,000 930,000 670,000 Estimated costs to complete 1,050,000 6,850,000 - Billings to RX, Inc 192,500 1,420,000 212,500 Determine the following:

    a. Inventory account, net at December 31, 2014, assuming no dependable estimates are available b. Inventory account, net at December 31, 2014, using cost to cost method c. Recognized revenue or loss in 2013, 2014 & 2015 using zero profit method d. Gross Profit using percentage of completion method PROBLEM 4 DM , Inc. Works on a P10,500,000 contract in 2015 to construct an office building. During 2015, DM, Inc uses the cost to cost method. At December 31, 2015, the balances in certain accounts were: Construction In Progress P3,780,000 ; accounts receivable P360,000 ; billings on construction in progress P1,800,000 ; contract retention P180,000 : mobilization fee P140,000 . At December 31, 2015, the estimated cost at completion is P7,350,000. How much is the realized gross profit in 2015? PROBLEM 5 On January 01, 2013, Brave Construction Corp. Began constructing a P2,100,000 contract. The following are relevant information provided by the corporation. Brave uses percentage of completion method. For the year ended December 31, 2014, Brave Construction billed its client an additional 55% of the contract price.

    2013 2014 2015 Construction in Progress 441,000 ? ? Estimated costs to complete ? ? - Cost incurred 425,250 969,000 675,750 Excess of Construction in Progress over Billings P84,000 current liabilty P330,750 current liabilty - Determine the following:

    a. Estimated remaining cost in 2013 b. Realized gross profit (loss) in 2014 c. Construction in progress in 2014