Horomill
Stefan SeemannResearch Institute of the Cement Industry (Düsseldorf)Seminar Grasim, 28 February, 2007
Structure
• Why a new mill?
• Horomill principle and design
• Summary
Why a new mill?
HPGR and VRM
+ low energy consumption
+ technically established
- narrow particle size distribution
- problematic intake conditions(HPGR)
Horomill
+ low energy consumption
+ small angle of nip
+ multiple stress of the material
+ fast change of cement type
- vibration problems
- coarse material recirculation during start up
- roller sealing
- wearing problems
Comparison of roller mill types
Structure
• Why a new mill?
• Horomill principle and design
• Summary
Principle
Principle
Inlet
Outlet
Centrifugationzone
Extractionzone
Grindingzone
4-6 grindingactions
GrindingForce
GrindingForce
Material speed control systemScrapers
Scrapers
Machine
Machine
Machine
Sold machines
Horomill 3800 (1800-2000kW)
130 t/h for OPC with 3100 cm²/g
82 t/h for Slag cement with 3200 cm²/g
225 t/h for Raw meal
Horomill 2800; 3400; 3600 (1000-1800kW)
Nowadays available up to Horomill 4600
Roller shaft
Mill shell lining
Energy consumption
source: FCB
Flow sheet
Flash dryer
Horomill®
Main feed Constant reject flow
Finalproduct
Main control loop
Hot gases supply
TSV®
BypassBag filter
Fan
Bucket elevator
Summary
A new mill combines a few advantages of already existing mill types
Results show a good performance but the handling is difficult
39 existing mills with medium throughput
Summary