how to develop a permit— t he process and implementation
DESCRIPTION
How to Develop a Permit— T he Process and Implementation. Gila River Indian Community By Will Antone III, Air Quality Specialist. Summary of Presentation. Community Background Air Quality Management Plan Permit Process Review Technical Support Document Overview of Permit - PowerPoint PPT PresentationTRANSCRIPT
![Page 1: How to Develop a Permit— T he Process and Implementation](https://reader033.vdocuments.net/reader033/viewer/2022051002/56815f55550346895dce3558/html5/thumbnails/1.jpg)
1
How to Develop a Permit—The Process and Implementation
Gila River Indian CommunityBy Will Antone III, Air Quality Specialist
![Page 2: How to Develop a Permit— T he Process and Implementation](https://reader033.vdocuments.net/reader033/viewer/2022051002/56815f55550346895dce3558/html5/thumbnails/2.jpg)
2
Summary of PresentationCommunity BackgroundAir Quality Management PlanPermit ProcessReview Technical Support DocumentOverview of PermitEnforcement Case Study
![Page 3: How to Develop a Permit— T he Process and Implementation](https://reader033.vdocuments.net/reader033/viewer/2022051002/56815f55550346895dce3558/html5/thumbnails/3.jpg)
3
Gila River Indian Community Background
Established in 1859 by Executive OrderConsists of two (2) tribes
Akimel O’odham (Pimas) – Districts 1 thru 5Pii-Pash (Maricopas) – Districts 6 & 7
Landbase374,000 Acres
Population On reservation 15,000Off reservation 5,000
![Page 4: How to Develop a Permit— T he Process and Implementation](https://reader033.vdocuments.net/reader033/viewer/2022051002/56815f55550346895dce3558/html5/thumbnails/4.jpg)
4
![Page 5: How to Develop a Permit— T he Process and Implementation](https://reader033.vdocuments.net/reader033/viewer/2022051002/56815f55550346895dce3558/html5/thumbnails/5.jpg)
5
Monitoring Stations
Gila River Indian Community
Industrial ParksSand & Gravel
![Page 6: How to Develop a Permit— T he Process and Implementation](https://reader033.vdocuments.net/reader033/viewer/2022051002/56815f55550346895dce3558/html5/thumbnails/6.jpg)
6
Industry BackgroundTwo industrial parks, 50 businesses &
industriesPacific Scientific, Triumph, Local Motors,
Superlite Block, Pimalco, Champion Homes, etc.Other GRIC-Area Sources
40,000 agricultural acresAcreage will increase to 146,000 over next 10
yearsInterstate 10 bisects Community
(largest source of air pollution)
![Page 7: How to Develop a Permit— T he Process and Implementation](https://reader033.vdocuments.net/reader033/viewer/2022051002/56815f55550346895dce3558/html5/thumbnails/7.jpg)
7
Air Quality Management PlanPart I. General ProvisionsPart II. Permit RequirementsPart III. Enforcement OrdinancesPart IV. Administrative AppealsPart V. Area Source Emission Limits
Open BurningFugitive Dust
![Page 8: How to Develop a Permit— T he Process and Implementation](https://reader033.vdocuments.net/reader033/viewer/2022051002/56815f55550346895dce3558/html5/thumbnails/8.jpg)
8
Air Quality Mgmt. Plan (cont.)Part VI. General Requirements
Visible EmissionsVOC Usage, Storage, HandlingDegreasing, Solvent Metal Cleaning
Part VII. Source/Category Specific Emission LimitsSecondary Aluminum ProcessingAerospace Manufacturing and Rework
OperationsNon-Metallic Mineral Mining and Processing
![Page 9: How to Develop a Permit— T he Process and Implementation](https://reader033.vdocuments.net/reader033/viewer/2022051002/56815f55550346895dce3558/html5/thumbnails/9.jpg)
9
AQMP Background
2006 GRIC Enacts
Complete AQMP
2007 GRIC Submits AQMP to
USEPA for Federal
Enforceability
2009 GRIC Submits AQMP
supplemental packet to
USEPA
2011 USEPA
approves AQMP
2002 GRIC Enacts Part I of AQMP
![Page 10: How to Develop a Permit— T he Process and Implementation](https://reader033.vdocuments.net/reader033/viewer/2022051002/56815f55550346895dce3558/html5/thumbnails/10.jpg)
10
![Page 11: How to Develop a Permit— T he Process and Implementation](https://reader033.vdocuments.net/reader033/viewer/2022051002/56815f55550346895dce3558/html5/thumbnails/11.jpg)
11
Permit ProcessMail permit packet to facility
Application, O&M Guidelines, Dust Control Plan, offer to meet
Permit meetingBackground informationAQMP overviewApplication reviewTimeframeContact information
![Page 12: How to Develop a Permit— T he Process and Implementation](https://reader033.vdocuments.net/reader033/viewer/2022051002/56815f55550346895dce3558/html5/thumbnails/12.jpg)
12
Permit Process (cont.)Completeness check
Request additional informationAdditional on-site meeting, if necessary
Draft PermitResearch GRIC regulations, federal
regulations, and emission factorsTechnical Support Document Emission calculations
![Page 13: How to Develop a Permit— T he Process and Implementation](https://reader033.vdocuments.net/reader033/viewer/2022051002/56815f55550346895dce3558/html5/thumbnails/13.jpg)
13
Permit Process (cont.)Mail final permit to facility 2 weeks prior
to 30-day public comment periodPermit invoice
30-day public comment periodNotice publish in local paper (Gila River
Indian News)Respond to comments, if necessaryHold public hearing, if necessary
Issue air quality operating permit
![Page 14: How to Develop a Permit— T he Process and Implementation](https://reader033.vdocuments.net/reader033/viewer/2022051002/56815f55550346895dce3558/html5/thumbnails/14.jpg)
14
![Page 15: How to Develop a Permit— T he Process and Implementation](https://reader033.vdocuments.net/reader033/viewer/2022051002/56815f55550346895dce3558/html5/thumbnails/15.jpg)
15
![Page 16: How to Develop a Permit— T he Process and Implementation](https://reader033.vdocuments.net/reader033/viewer/2022051002/56815f55550346895dce3558/html5/thumbnails/16.jpg)
16
CEMEX Enforcement ActionAQP observed emissions from Asphalt PlantConducted an inspection on San Tan Plant
Lead to inspection of Maricopa PlantObserved visible emissionsConducted visible emissions readings (U.S. EPA
Method 9) on baghouse, passive baghouses and asphalt silo
Exceeded emission limitations 7% Opacity limitations for storage silo20% Opacity limitations for baghouse
![Page 17: How to Develop a Permit— T he Process and Implementation](https://reader033.vdocuments.net/reader033/viewer/2022051002/56815f55550346895dce3558/html5/thumbnails/17.jpg)
17
![Page 18: How to Develop a Permit— T he Process and Implementation](https://reader033.vdocuments.net/reader033/viewer/2022051002/56815f55550346895dce3558/html5/thumbnails/18.jpg)
18
U.S. EPA Method 9 Visible Emissions Observations
![Page 19: How to Develop a Permit— T he Process and Implementation](https://reader033.vdocuments.net/reader033/viewer/2022051002/56815f55550346895dce3558/html5/thumbnails/19.jpg)
19
![Page 20: How to Develop a Permit— T he Process and Implementation](https://reader033.vdocuments.net/reader033/viewer/2022051002/56815f55550346895dce3558/html5/thumbnails/20.jpg)
20
CEMEX Enforcement Action (cont.)Completed inspection reportInternal meetings discussing enforcement
actionResearch regulating authoritiesResearch facility background and track recordDecision on enforcement route in accordance
with AQMPIssued three (3) NOVs
Offered an opportunity to meet to discuss corrective actions
![Page 21: How to Develop a Permit— T he Process and Implementation](https://reader033.vdocuments.net/reader033/viewer/2022051002/56815f55550346895dce3558/html5/thumbnails/21.jpg)
21
![Page 22: How to Develop a Permit— T he Process and Implementation](https://reader033.vdocuments.net/reader033/viewer/2022051002/56815f55550346895dce3558/html5/thumbnails/22.jpg)
22
CEMEX Enforcement Action (cont.)Received “NO” response from CEMEXProceeded with a Compliance Order and
issued a $15K administrative penalties$5K per violation per day
Issued letter to CEO of CEMEXWebsite claimed CEMEX
environmentally conscious company
![Page 23: How to Develop a Permit— T he Process and Implementation](https://reader033.vdocuments.net/reader033/viewer/2022051002/56815f55550346895dce3558/html5/thumbnails/23.jpg)
23
CEMEX Enforcement Action (cont.)CEMEX Environmental personnel arranged
meetingCEMEX signed order and paid $15K penalty
CEMEX submitted a Corrective Action Plan
![Page 24: How to Develop a Permit— T he Process and Implementation](https://reader033.vdocuments.net/reader033/viewer/2022051002/56815f55550346895dce3558/html5/thumbnails/24.jpg)
24
![Page 25: How to Develop a Permit— T he Process and Implementation](https://reader033.vdocuments.net/reader033/viewer/2022051002/56815f55550346895dce3558/html5/thumbnails/25.jpg)
25
![Page 26: How to Develop a Permit— T he Process and Implementation](https://reader033.vdocuments.net/reader033/viewer/2022051002/56815f55550346895dce3558/html5/thumbnails/26.jpg)
26
![Page 27: How to Develop a Permit— T he Process and Implementation](https://reader033.vdocuments.net/reader033/viewer/2022051002/56815f55550346895dce3558/html5/thumbnails/27.jpg)
27
HighlightsConducted enforcement actions using
tribes inherent sovereign authorityOther jurisdictions all had
enforcement actions against CEMEX, sought advice from Air Quality Program on compliance strategies
Achieved compliance and working relationship with CEMEX
![Page 28: How to Develop a Permit— T he Process and Implementation](https://reader033.vdocuments.net/reader033/viewer/2022051002/56815f55550346895dce3558/html5/thumbnails/28.jpg)
28
Questions?
Gila River Indian CommunityDept. of Environmental Quality
Will Antone III, Air Quality Specialist(520) 562-2234