Creating Parameter DumpsUsing Netact Manager & Plan Editor
For internal use
To change the document information in the footer, press [Alt + F8] and use the „Nokia_Siemens_Networks_–_Change_Document_Information“ macro.
Overall Workflow
(1) Get the *.xml dump from the Netact CM Manager
(2) Ready the Empty Access Dump
(3) Using Plan Editor, Load the xml onto the empty access file to get the Parameter Dump
NetAct CM Manager
*.xml dump
Microsoft Access File Parameter Dump (*.mdb)
Emtpy MS Access PE 4.8-1 Database (*.mdb)
NSN Plan Editor
For internal use
To change the document information in the footer, press [Alt + F8] and use the „Nokia_Siemens_Networks_–_Change_Document_Information“ macro.
(1) Get parameter dump from Netact CM Manager
(2) Ready Empty PE_4.8-1 Database
(3) Use Plan Editor to Load the dump onto the PE_4.8-1DB
For internal use
To change the document information in the footer, press [Alt + F8] and use the „Nokia_Siemens_Networks_–_Change_Document_Information“ macro.
(1) Get parameter dump from Netact CM Manager
(2) Ready Empty PE_4.8-1 Database
(3) Use Plan Editor to Load the dump onto the PE_4.8-1DB
For internal use
To change the document information in the footer, press [Alt + F8] and use the „Nokia_Siemens_Networks_–_Change_Document_Information“ macro.
(1) Getting the actual configuration file (*.xml) from Netact
1. Access Netact2. On the Left window
pane, click on CONFIGURATION
3. On the main window, click on CM Operations Manager
For internal use
To change the document information in the footer, press [Alt + F8] and use the „Nokia_Siemens_Networks_–_Change_Document_Information“ macro.
(1) Getting the actual configuration file (*.xml) from Netact
1. Click on Upload > 2. New Upload
For internal use
To change the document information in the footer, press [Alt + F8] and use the „Nokia_Siemens_Networks_–_Change_Document_Information“ macro.
(1) Getting the actual configuration file (*.xml) from Netact Uploading Site Data
1. Click on the LTE Tab2. Click Select All (to
upload all sites conf)3. Click Start
(A new window will appear which shows the upload progress)
For internal use
To change the document information in the footer, press [Alt + F8] and use the „Nokia_Siemens_Networks_–_Change_Document_Information“ macro.
(1) Getting the actual configuration file (*.xml) from Netact Downloading Actual Config
1. Click on File2. Click Export Actual
Configuration
For internal use
To change the document information in the footer, press [Alt + F8] and use the „Nokia_Siemens_Networks_–_Change_Document_Information“ macro.
(1) Getting the actual configuration file (*.xml) from Netact Downloading Actual Config
1. Tick on PLMN Level on the left pane
2. Tick Deselect All on the Top pane
3. Tick the Technology of the dump you want to export
4. Tick select all if you want to export all parameters for that technologyu
5. Input the Export format name
6. Format should be RAML 2.0
7. Make sure to export INTERNAL values
8. Click Start
For internal use
To change the document information in the footer, press [Alt + F8] and use the „Nokia_Siemens_Networks_–_Change_Document_Information“ macro.
(1) Getting the actual configuration file (*.xml) from Netact Downloading Actual Config
Wait until the downloading finishes. It is finished once the close button can be clicked
(changes from grey to black font)
For internal use
To change the document information in the footer, press [Alt + F8] and use the „Nokia_Siemens_Networks_–_Change_Document_Information“ macro.
(1) Get parameter dump from Netact CM Manager
(2) Ready Empty PE_4.8-1 Database
(3) Use Plan Editor to Load the dump onto the PE_4.8-1DB
For internal use
To change the document information in the footer, press [Alt + F8] and use the „Nokia_Siemens_Networks_–_Change_Document_Information“ macro.
(2) Readying the PE Database
The PE database comes along with the installer of NetAct Planeditor. If you have the PlanEditor SW installer, the Planeditor (PE) database is also extracted in directory of the
Else you can get it from sharenethttps://sharenet-ims.inside.nokiasiemensnetworks.com/livelink/livelink?func=ll&objId=390002169&objAction=Browse
For internal use
To change the document information in the footer, press [Alt + F8] and use the „Nokia_Siemens_Networks_–_Change_Document_Information“ macro.
(1) Get parameter dump from Netact CM Manager
(2) Ready Empty PE_4.8-1 Database
(3) Use Plan Editor to Load the dump onto the PE_4.8-1DB
For internal use
To change the document information in the footer, press [Alt + F8] and use the „Nokia_Siemens_Networks_–_Change_Document_Information“ macro.
(3) Using Plan Editor to Load the LTE Dump onto the MS Access Database
Open the NSN Plan Editor Software
Upon starting you will be asked to open a database.
For internal use
To change the document information in the footer, press [Alt + F8] and use the „Nokia_Siemens_Networks_–_Change_Document_Information“ macro.
(3) Using Plan Editor to Load the LTE Dump onto the MS Access Database
In the actual ‘open PE’ window, choose the MS Access File (mdb) where you want to have the xml file loaded.
For internal use
To change the document information in the footer, press [Alt + F8] and use the „Nokia_Siemens_Networks_–_Change_Document_Information“ macro.
(3) Using Plan Editor to Load the LTE Dump onto the MS Access Database
Click on import
For internal use
To change the document information in the footer, press [Alt + F8] and use the „Nokia_Siemens_Networks_–_Change_Document_Information“ macro.
(3) Using Plan Editor to Load the LTE Dump onto the MS Access Database
Click the appropriate profile
For internal use
To change the document information in the footer, press [Alt + F8] and use the „Nokia_Siemens_Networks_–_Change_Document_Information“ macro.
(3) Using Plan Editor to Load the LTE Dump onto the MS Access Database
Locate the configuration dump from Netact (.xml)
For internal use
To change the document information in the footer, press [Alt + F8] and use the „Nokia_Siemens_Networks_–_Change_Document_Information“ macro.
(3) Using Plan Editor to Load the LTE Dump onto the MS Access Database
Tick on Import Actual Data
And choose any preferred value for the NMS ID
Leave the RNC & WBTS ID blank
For internal use
To change the document information in the footer, press [Alt + F8] and use the „Nokia_Siemens_Networks_–_Change_Document_Information“ macro.
(3) Using Plan Editor to Load the LTE Dump onto the MS Access Database
Click Start, and click on yes when a window pops up