To change the document information in the footer, press [Alt + F8] and use the „Nokia_Siemens_Networks_–_Change_Document_Information“ macro.

Creating Parameter DumpsUsing Netact Manager & Plan Editor

For internal use

To change the document information in the footer, press [Alt + F8] and use the „Nokia_Siemens_Networks_–_Change_Document_Information“ macro.

Overall Workflow

(1) Get the *.xml dump from the Netact CM Manager

(2) Ready the Empty Access Dump

(3) Using Plan Editor, Load the xml onto the empty access file to get the Parameter Dump

NetAct CM Manager

*.xml dump

Microsoft Access File Parameter Dump (*.mdb)

Emtpy MS Access PE 4.8-1 Database (*.mdb)

NSN Plan Editor

For internal use

To change the document information in the footer, press [Alt + F8] and use the „Nokia_Siemens_Networks_–_Change_Document_Information“ macro.

(1) Get parameter dump from Netact CM Manager

(2) Ready Empty PE_4.8-1 Database

(3) Use Plan Editor to Load the dump onto the PE_4.8-1DB

For internal use

To change the document information in the footer, press [Alt + F8] and use the „Nokia_Siemens_Networks_–_Change_Document_Information“ macro.

(1) Get parameter dump from Netact CM Manager

(2) Ready Empty PE_4.8-1 Database

(3) Use Plan Editor to Load the dump onto the PE_4.8-1DB

For internal use

To change the document information in the footer, press [Alt + F8] and use the „Nokia_Siemens_Networks_–_Change_Document_Information“ macro.

(1) Getting the actual configuration file (*.xml) from Netact

1. Access Netact2. On the Left window

pane, click on CONFIGURATION

3. On the main window, click on CM Operations Manager

For internal use

To change the document information in the footer, press [Alt + F8] and use the „Nokia_Siemens_Networks_–_Change_Document_Information“ macro.

(1) Getting the actual configuration file (*.xml) from Netact

1. Click on Upload > 2. New Upload

For internal use

To change the document information in the footer, press [Alt + F8] and use the „Nokia_Siemens_Networks_–_Change_Document_Information“ macro.

(1) Getting the actual configuration file (*.xml) from Netact Uploading Site Data

1. Click on the LTE Tab2. Click Select All (to

upload all sites conf)3. Click Start

(A new window will appear which shows the upload progress)

For internal use

To change the document information in the footer, press [Alt + F8] and use the „Nokia_Siemens_Networks_–_Change_Document_Information“ macro.

(1) Getting the actual configuration file (*.xml) from Netact Downloading Actual Config

1. Click on File2. Click Export Actual

Configuration

For internal use

To change the document information in the footer, press [Alt + F8] and use the „Nokia_Siemens_Networks_–_Change_Document_Information“ macro.

(1) Getting the actual configuration file (*.xml) from Netact Downloading Actual Config

1. Tick on PLMN Level on the left pane

2. Tick Deselect All on the Top pane

3. Tick the Technology of the dump you want to export

4. Tick select all if you want to export all parameters for that technologyu

5. Input the Export format name

6. Format should be RAML 2.0

7. Make sure to export INTERNAL values

8. Click Start

For internal use

To change the document information in the footer, press [Alt + F8] and use the „Nokia_Siemens_Networks_–_Change_Document_Information“ macro.

(1) Getting the actual configuration file (*.xml) from Netact Downloading Actual Config

Wait until the downloading finishes. It is finished once the close button can be clicked

(changes from grey to black font)

For internal use

To change the document information in the footer, press [Alt + F8] and use the „Nokia_Siemens_Networks_–_Change_Document_Information“ macro.

(1) Get parameter dump from Netact CM Manager

(2) Ready Empty PE_4.8-1 Database

(3) Use Plan Editor to Load the dump onto the PE_4.8-1DB

For internal use

To change the document information in the footer, press [Alt + F8] and use the „Nokia_Siemens_Networks_–_Change_Document_Information“ macro.

(2) Readying the PE Database

The PE database comes along with the installer of NetAct Planeditor. If you have the PlanEditor SW installer, the Planeditor (PE) database is also extracted in directory of the

Else you can get it from sharenethttps://sharenet-ims.inside.nokiasiemensnetworks.com/livelink/livelink?func=ll&objId=390002169&objAction=Browse

For internal use

To change the document information in the footer, press [Alt + F8] and use the „Nokia_Siemens_Networks_–_Change_Document_Information“ macro.

(1) Get parameter dump from Netact CM Manager

(2) Ready Empty PE_4.8-1 Database

(3) Use Plan Editor to Load the dump onto the PE_4.8-1DB

For internal use

To change the document information in the footer, press [Alt + F8] and use the „Nokia_Siemens_Networks_–_Change_Document_Information“ macro.

(3) Using Plan Editor to Load the LTE Dump onto the MS Access Database

Open the NSN Plan Editor Software

Upon starting you will be asked to open a database.

For internal use

To change the document information in the footer, press [Alt + F8] and use the „Nokia_Siemens_Networks_–_Change_Document_Information“ macro.

(3) Using Plan Editor to Load the LTE Dump onto the MS Access Database

In the actual ‘open PE’ window, choose the MS Access File (mdb) where you want to have the xml file loaded.

For internal use

To change the document information in the footer, press [Alt + F8] and use the „Nokia_Siemens_Networks_–_Change_Document_Information“ macro.

(3) Using Plan Editor to Load the LTE Dump onto the MS Access Database

Click on import

For internal use

To change the document information in the footer, press [Alt + F8] and use the „Nokia_Siemens_Networks_–_Change_Document_Information“ macro.

(3) Using Plan Editor to Load the LTE Dump onto the MS Access Database

Click the appropriate profile

For internal use

To change the document information in the footer, press [Alt + F8] and use the „Nokia_Siemens_Networks_–_Change_Document_Information“ macro.

(3) Using Plan Editor to Load the LTE Dump onto the MS Access Database

Locate the configuration dump from Netact (.xml)

For internal use

To change the document information in the footer, press [Alt + F8] and use the „Nokia_Siemens_Networks_–_Change_Document_Information“ macro.

(3) Using Plan Editor to Load the LTE Dump onto the MS Access Database

Tick on Import Actual Data

And choose any preferred value for the NMS ID

Leave the RNC & WBTS ID blank

For internal use

To change the document information in the footer, press [Alt + F8] and use the „Nokia_Siemens_Networks_–_Change_Document_Information“ macro.

(3) Using Plan Editor to Load the LTE Dump onto the MS Access Database

Click Start, and click on yes when a window pops up

Wait for PE to finish loading loading the dump.