Floating Operations • What is an FPSO / FLNG
– Spread Moored
– Turreted FPSO’s
• Components
• Drivers
• Cost reductions
Business Drivers – Safety
– Reliability / availability
– First Oil/Gas
– Efficiency
• Standardization
• Energy Efficiency
• Reduce staff
– Regulations
• Governments
• IMO - ECA (S and N)
• Lloyds / DNV / ABS
• Functional Safety
– Image – shareholder value
Components
• Hull • Cargo movement, distribution, unloading,
cleaning
• Ballast management
• Inert Gas Systems/fire fighting systems
• Power Gen and distribution
• Fuel treatment & supply
• Steam Boilers
• Cooling water
• Mooring management
• Station keeping propulsion
Components (continued)
• Hotel
• Crew quarters
• Workspaces (control rooms, offices, workshops, warehouses)
• HVAC, potable water, waste management
• Food services, entertainment & recreation
• Communications
• Transportation (helipad, companion way)
• Safety (life boats, etc)
© Invensys 21
November, 2014
Invensys proprietary & confidential
Components (continued)
• Topsides
– typically a Gas-Oil Separation plant
• Slug management
• separators
• Crude, gas, water treatment
• Water re-injection pumps
• Gas export and/or re-injection compressors
• Power generation
• Flare
Components (continued)
• Subsea Systems
– Connections (Risers)
• Down: control, hydraulics, power, re-injection gas
& water, treatment chemicals
• Up: production fluids, data connections
• Out: crude export line to tanker, gas export line to
shore
– Production Systems
• Subsea trees, manifolds, gathering lines
• May include subsea processing equipment, like
pumps, compressors and separators
Automation Systems
– Hull Management Systems • DCS / PLC solution
– Topsides Control Systems • DCS / ESD / F&G solution
• Operator Training Simulator
– Subsea Controls • Divided into Wet (on bottom) and Dry (on board FPSO)
– Turret Controls • OEM
– Hotel Management Systems • HVAC, Lighting, Physical Security
Safety System
DCS
Bonga Deepwater Project, Niger Delta, Nigeria
Bonga Shell Petroleum Development Company of Nigeria (SPDC)
Bonga Shell Petroleum Development Company of Nigeria (SPDC)
• Foxboro I/A Series Distributed Control Systems
• Triconex Emergency Shutdown and F&G Systems
• Network Design and Topology
• Commissioning and Start Up Spares
• Offshore Installation Supervision
• Offshore Pre-Commissioning and Commissioning Assistance
• Onshore Support Team through Pre-Commissioning Phase
• SimSci – Esscor Operator Training Simulator System
• Automated Checkout via Dynamic Simulation
Cost reduction opportunities
• Simulation:
– Static simulation
– Dynamic simulation
PROCESS
DESIGN
DCS
CONFIGURATION
STARTUP and
TRAINING PLANT
OPERATION
Cost reduction opportunities
• Remote control & collaboration:
– Cost of labour: $5-10k per week per man
• Incl. training, travelling, certification
– Remote expert collaboration
– Remote management
• Standardization
Goal: reduction of workforce
IHC: From many men
through one man