Page 1: How we changed the planning process… - Optilonoptilon.se/wp-content/uploads/2017/02/bucher_emhart_glass-m_brink...ERP system “BPCS” is missing; - Resource capacity constraints

Welcome

How we changed the planning process…

Supply Chain Conference 2015-09-03

Page 2: How we changed the planning process… - Optilonoptilon.se/wp-content/uploads/2017/02/bucher_emhart_glass-m_brink...ERP system “BPCS” is missing; - Resource capacity constraints

1. Company information

2. Back ground

3. The APS project

4. Q&A

2

Page 3: How we changed the planning process… - Optilonoptilon.se/wp-content/uploads/2017/02/bucher_emhart_glass-m_brink...ERP system “BPCS” is missing; - Resource capacity constraints

Company Information

3

Page 4: How we changed the planning process… - Optilonoptilon.se/wp-content/uploads/2017/02/bucher_emhart_glass-m_brink...ERP system “BPCS” is missing; - Resource capacity constraints

Bucher Industries AG

4

Bucher Hydraulics Kuhn Group Bucher Municipal

Emhart GlassBucher Specials

Page 5: How we changed the planning process… - Optilonoptilon.se/wp-content/uploads/2017/02/bucher_emhart_glass-m_brink...ERP system “BPCS” is missing; - Resource capacity constraints

5

Advanced Glass Forming Machines

Page 6: How we changed the planning process… - Optilonoptilon.se/wp-content/uploads/2017/02/bucher_emhart_glass-m_brink...ERP system “BPCS” is missing; - Resource capacity constraints

Animation process

6

Page 7: How we changed the planning process… - Optilonoptilon.se/wp-content/uploads/2017/02/bucher_emhart_glass-m_brink...ERP system “BPCS” is missing; - Resource capacity constraints

7

Worldwide Presence ...

Elmira NY

Windsor CT

Clearwater FL

Cham (CH)Savona (I)

Sundsvall (S)Örebro (S)

Manchester (UK)

Singapore

Johor, Malaysia

Kawasaki (J)

Moscow (RUS)

Owensville MO

Neuss (D)

Page 8: How we changed the planning process… - Optilonoptilon.se/wp-content/uploads/2017/02/bucher_emhart_glass-m_brink...ERP system “BPCS” is missing; - Resource capacity constraints

8

Worldwide Installed IS Machine Base

• 3374 active IS Lines

• 26030 active Sections

• 1167 Emhart Glass IS Lines

• 9740 Emhart Glass Sections

Page 9: How we changed the planning process… - Optilonoptilon.se/wp-content/uploads/2017/02/bucher_emhart_glass-m_brink...ERP system “BPCS” is missing; - Resource capacity constraints

9

Supply Chain of Bucher Emhart Glass

Örebro

Johor-Bahru

Luxemburg

SundsvallParts

Material

Page 10: How we changed the planning process… - Optilonoptilon.se/wp-content/uploads/2017/02/bucher_emhart_glass-m_brink...ERP system “BPCS” is missing; - Resource capacity constraints

10

Page 11: How we changed the planning process… - Optilonoptilon.se/wp-content/uploads/2017/02/bucher_emhart_glass-m_brink...ERP system “BPCS” is missing; - Resource capacity constraints

Emhart Glass Örebro - Facts

• 135 employees, 100b, 35w

• 80 direct machine operators

• 40 CNC machines, key resources, 3 shift production

• 100 work centers, planned resources

• Production responsibility of 3000 item numbers

• Annually;

– We supplies strategic parts for 50 IS-machines

– We make 1’300’000 kg’s of parts, and sub-assemblies

– We run our machines 120’000 hours

– We introduce 300 new items in production annually

• 98 years of experience from machining production

• Milling, turning, drilling, grinding, honing, heat-treatment,

welding, painting, assembly and testing.

11

Page 12: How we changed the planning process… - Optilonoptilon.se/wp-content/uploads/2017/02/bucher_emhart_glass-m_brink...ERP system “BPCS” is missing; - Resource capacity constraints

Back Ground

12

Page 13: How we changed the planning process… - Optilonoptilon.se/wp-content/uploads/2017/02/bucher_emhart_glass-m_brink...ERP system “BPCS” is missing; - Resource capacity constraints

How It was…

…a selection of things we used to say

• We only got 1500 hours of past due production in the work

shop now…

– So we are in good shape!

• I’ve got 200 hours to produce in my machine this week, so we

can skip over time this week-end!

– Right…?

• It’s so difficult to make a production plan…

– Especially if has to be a plan for the future.

• This machine has been overloaded for several months now,

maybe we should out-source some production?

– Well, let’s wait for another week or so and see what happens.

• Yes, I can make that re-schedule analyze, but it will take me

almost a week to get it done…

– So let’s say we make the change and hope for the best…

13

Page 14: How we changed the planning process… - Optilonoptilon.se/wp-content/uploads/2017/02/bucher_emhart_glass-m_brink...ERP system “BPCS” is missing; - Resource capacity constraints

14

What

can we

do?

ERP system “BPCS” is missing;

- Resource capacity constraints

- Visual interface

- Day by day capacity calendar

- Material availability check

- Etc..

In addition to that...

- We are used of MRP style production plan and we adopted some bad habits

- It’s not just a new system we need it’s also a new mind set

- A wise man said to me once… ”A fool with a tool is still a fool”

Advanced

Planning

Systems can

fix that!

Page 15: How we changed the planning process… - Optilonoptilon.se/wp-content/uploads/2017/02/bucher_emhart_glass-m_brink...ERP system “BPCS” is missing; - Resource capacity constraints

15

Constraint Work load Expectation

Page 16: How we changed the planning process… - Optilonoptilon.se/wp-content/uploads/2017/02/bucher_emhart_glass-m_brink...ERP system “BPCS” is missing; - Resource capacity constraints

The APS project

1

Page 17: How we changed the planning process… - Optilonoptilon.se/wp-content/uploads/2017/02/bucher_emhart_glass-m_brink...ERP system “BPCS” is missing; - Resource capacity constraints

Budget and expected savings

– Budget: 2,414 MSEK

– Expected savings

• Efficiency increase due to automated planning process

• Year 1 – 540 KSEK

• Year 2 – 1 080 KSEK

• WIP & Stock reduction due to decreased thru-put times

• 700 KSEK (one time)

• 20% less overtime usage, due to better production plans

• 320 KSEK

• Less shipping costs, reduced air freight

• PBT: 2,3 Years, NPV 4 548 KSEK

2

Page 18: How we changed the planning process… - Optilonoptilon.se/wp-content/uploads/2017/02/bucher_emhart_glass-m_brink...ERP system “BPCS” is missing; - Resource capacity constraints

APS Project Organization

Steering Group

LWAN, CFORMSVE, PSTE

Project Manager APS-Project

MBRI

Procurement

MLIN

Project Leader APS Implementation

Örebro

MSAN

Project TeamAAHN,CULA,HTOI

CSOH,JGUS,MHOO

Implementation Consultants from

Supplier

ITLWAN,ASJO

3

Page 19: How we changed the planning process… - Optilonoptilon.se/wp-content/uploads/2017/02/bucher_emhart_glass-m_brink...ERP system “BPCS” is missing; - Resource capacity constraints

Time Schedule

4

Interface

ready

System

supplier

quotes

evaluation

finalized

Assignment

description

approved

with system

supplier

Design

finished

IT-

infrastructure

installed

Production

plan and

simulation

generated

Test

finished

Investment

approved

Project

sign-off

Go

Live

2015

Jan Feb AprNov DecSep Oct

2014

Apr Jun Jun

Page 20: How we changed the planning process… - Optilonoptilon.se/wp-content/uploads/2017/02/bucher_emhart_glass-m_brink...ERP system “BPCS” is missing; - Resource capacity constraints

As simple as possible

• All reporting done thru ERP system “BPCS” = Nothing changed

for job reporting etc. 90% of the users

• All old KPI’s and reports remains thru “go-live”, will be changed

later, towards Tableau generated reports

• All affected users deeply involved in project = no surprise at

“Go live” day, we all knew what was coming

5

Page 21: How we changed the planning process… - Optilonoptilon.se/wp-content/uploads/2017/02/bucher_emhart_glass-m_brink...ERP system “BPCS” is missing; - Resource capacity constraints

Order flow

6

Customers

Central

sales

Cham

Switzerland

Sundsvall

Facility 50

Final

assembly

Johor Barhu

Facility 82

Final

assembly

Örebro

Facility 51

Luxemburg

Facillity 57

Global

spare parts

SuppliersRaw-material,

parts, sub-

assemblies

Örebro

Facility 51Parts

manufacturing

DRP-

Orders

Page 22: How we changed the planning process… - Optilonoptilon.se/wp-content/uploads/2017/02/bucher_emhart_glass-m_brink...ERP system “BPCS” is missing; - Resource capacity constraints

Production process

7

Purchased Raw-

material & parts

Sub-contracted

operations

Assemblies

Parts

Machines Assembly

Page 23: How we changed the planning process… - Optilonoptilon.se/wp-content/uploads/2017/02/bucher_emhart_glass-m_brink...ERP system “BPCS” is missing; - Resource capacity constraints

Visible/noticeable effects

• Production out-put +23%

• Delayed order lines +-0

• Less over time, (planners)

Order release is now 2-3 hours

compared to 8-10 hours per week

• More time is left to think about and

plan strategical, not just executing

MRP proposals

• Planners and supervisors plan

ahead, 2-3 months perspective,

compared to days or weeks in the

past

• Visual interface is really helpful in

getting a overview, material

availability, capacity bottlenecks

etc.

8

0

100

200

300

400

500

600

700

800

900

1000

1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9

2014 2015

Hours per day produced

A

P

S

G

o

li

v

e

Page 24: How we changed the planning process… - Optilonoptilon.se/wp-content/uploads/2017/02/bucher_emhart_glass-m_brink...ERP system “BPCS” is missing; - Resource capacity constraints

Visible/noticeable effects

• Progress reporting started before ”go live”, since this was

recognized as mandatory information to run the scheduler.

– Each direct operator/fitter reports achived production by end of each

shift.

– This created un-intentional a a competition effect, and significantly

equlized and increased productuion out-put.

9

Page 25: How we changed the planning process… - Optilonoptilon.se/wp-content/uploads/2017/02/bucher_emhart_glass-m_brink...ERP system “BPCS” is missing; - Resource capacity constraints

Visual

10

Page 26: How we changed the planning process… - Optilonoptilon.se/wp-content/uploads/2017/02/bucher_emhart_glass-m_brink...ERP system “BPCS” is missing; - Resource capacity constraints

• Production Planning

– Release manufacturing proposals

– Reschedule orders taking constraints into account

– Picking and release to production

• Order Planning

– Release forecast to customer order (DRP)

– Schedule customer order (DRP) according to iPlanner suggested due date

• Operational Purchasing

– Identify most critical shortages. Review POs with delivery issues in iPlanner.

Planning Processes addressed by iPlanner

Page 27: How we changed the planning process… - Optilonoptilon.se/wp-content/uploads/2017/02/bucher_emhart_glass-m_brink...ERP system “BPCS” is missing; - Resource capacity constraints

• Projected service level using 4 different measures

Delay Dashboard

Page 28: How we changed the planning process… - Optilonoptilon.se/wp-content/uploads/2017/02/bucher_emhart_glass-m_brink...ERP system “BPCS” is missing; - Resource capacity constraints

Load Graph – Total Plant

Total load Shop Order Total load Shop Order ProposalsGrid with filtering possibilities

Page 29: How we changed the planning process… - Optilonoptilon.se/wp-content/uploads/2017/02/bucher_emhart_glass-m_brink...ERP system “BPCS” is missing; - Resource capacity constraints

Demand Dashboard

• Demand graph based either on commit or required week

• Double click on bar to drill down and change coloring

Page 30: How we changed the planning process… - Optilonoptilon.se/wp-content/uploads/2017/02/bucher_emhart_glass-m_brink...ERP system “BPCS” is missing; - Resource capacity constraints

• Using finite or infinite plan

• Using daily, weekly or monthly buckets

Bottleneck Report

Page 31: How we changed the planning process… - Optilonoptilon.se/wp-content/uploads/2017/02/bucher_emhart_glass-m_brink...ERP system “BPCS” is missing; - Resource capacity constraints

• Detailed load per resource and time bucket

Capacity Details

Page 33: How we changed the planning process… - Optilonoptilon.se/wp-content/uploads/2017/02/bucher_emhart_glass-m_brink...ERP system “BPCS” is missing; - Resource capacity constraints