hsr compilation report july 2011
TRANSCRIPT
-
8/6/2019 HSR Compilation Report July 2011
1/19
Is High Speed Rail Coming Through
Your Town Soon?
By: Assemblywoman
Diane Harkey
73rd AD
A Compilation Report on
issues, concerns and actions
July 2011
-
8/6/2019 HSR Compilation Report July 2011
2/19
The Legislature Lacks Information because the
High Speed Rail Authority Lacks Details
Legislature suffers from a lack of good information that is needed to makedecisions about the appropriation of funds for the high-speed rail project.
Given the very large size of this project, its extended construction timeline,
and the novelty of this type of project for California, it is reasonable that
some key project decisions must be based on the best available analysis and
assumptions rather than hard numbers. (HSR at Critical Junction; LAO Pg 11)
The December 2009 business plan of the High-Speed Rail Authority
(Authority) lacks detail regarding how it proposes to finance the high-speed
rail network (program) and mitigate associated risks.
The Authority Anticipates needing $17 billion to $19 billion from the federalgovernment. ..it will need $10 billion to $12 billion in private investmentthe
Authority has not received any commitments from private investors.
Additionally, a revenue guarantee, without which the private investors are
unlikely to participate, lacks specifics. (State Auditor; pg 17)
-
8/6/2019 HSR Compilation Report July 2011
3/19
Cost Estimates - Outdated & Likely Understated
the project is likely to cost muchmore than the $43 billion originally
estimated for the first phase from San
Francisco to Anaheim. For example,
based on the states agreement with
FRA, the cost of the initial
construction segment between Fresno
and Bakersfield alone is now
estimated to be $4.5 billion, which is
57 % higher. ..If the cost of building
the entire Phase 1 system were to
grow as much as the revised HSRA
estimate for the 100-mile segment
discussed above, construction would
cost about $67 billion. (LAO)
-
8/6/2019 HSR Compilation Report July 2011
4/19
Vague CHSRA Funding PlansPrivate investors will require a revenue guarantee. The business plan
indicates the Authority plans to rely on them to supply $10 billion to $12
billion, primarily backed by projected future operating surpluses50 parties
who responded to the spring 2008 request and others [state that] private
investors will require minimum revenue guarantee from a public entity in the
event that ridership projections, and thus operating surplus projections, are
not met. This viewpoint is also expressed in the 2009 CHSRA business plan.
(State Auditor Pg22)
The Authoritys spending plan includes almost $12 billion in exclusively
federal and state funds through 2013, more than 2.5 times what is now
available. Before it may commit funds from Prop 1A for construction, state
law requires that the CHSRA: 1) have estimates of the full cost ofconstruction; 2) identifies the sources of all funds; 3) the anticipated time of
receipt based on commitments or assurances from potential funding sources;
4) verified by Director of the Department of Finance.
(State Auditor; pg 21)
-
8/6/2019 HSR Compilation Report July 2011
5/19
No State Subsidies?
Potential Need for Operating Subsidies Could Lead to General Fund Cost
Pressures. The CHSRAs business plan indicates that the initial costs ofoperating a high-speed rail system may exceed $1 billion per year.
Proposition 1A requires HSRA to submit a plan which certifies that, once
complete, service will not require a local, state, or federal operating subsidy
prior to appropriation of the $9 billion in state bond funds for capital costs. The state could discover during development or after construction that the
system needs [an operating] subsidy. If the train does not attract the number
of riders projected, operating revenues would likely be less than expected.
This situation could place an additional financial pressure on the states
General Fund. (HSR at Critical Juncture; LAO; Pg 7-8)
That a revenue guarantee might violate state law - CHSRA consultantindicated that the revenue guarantee would not be used as an operating
subsidy but a limited-term contingent liability used to support up-front
capital investmentTherefore, a guarantee could increase costs to the public
[or General Fund. No] indication of who would be responsible or cost.
(State Auditor pg 22-23)
-
8/6/2019 HSR Compilation Report July 2011
6/19
Can You Define Subsidy?
Section 2704.08 (J) in Assembly Bill 3034 of August 2008states, The planned passenger service by the authority in the
corridor or usable segment thereof will not require a local,state, or federal operating subsidy.
However, there is confusion over the definition
initial operating years of any project...especially in one inwhich the initial phase cannot serve primary markets as
planned, will incur early operating lossesAs noted in our
November report, the definition of operating subsidy is
unclear and urgently needs further clarification by the
Legislature. (CHSRA Peer Review Committee Report to CHSRA May 2, 2011)
-
8/6/2019 HSR Compilation Report July 2011
7/19
CHSRA on Compliance Issues
No system in place to track expenditures funded by Proposition
1A to ensure compliance with statutory limitations on
administrative and preconstruction task costs As Authority
staff began spending funds from Proposition 1A in 2009, we
expected them to have defined the types of costs and to haveestablished systems for recording, reporting, and planning for
these costs, but that was not the case.
CHSRAneeds to develop some systems to track and report on
the use of Recovery Act funds. Because of its $2.25 billion
federal award, the Authority will be required to comply withboth the Recovery Act reporting requirementsand with the
readiness requirements of the California Recovery Task Force.
(State Auditor ; pg. 28-29)
-
8/6/2019 HSR Compilation Report July 2011
8/19
HSR Ridership Calculations
Dont Add UpWe can say that the sheer number of constraints placed on themodel parameters makes this model system unreliable forpredicting the shares of the competing modes (air, train, automobileand HSR) in the CHSR corridor. While there are advancedeconometric techniques that could alleviate some of the
biases we have found, it is likely that application of these
techniques would lead to larger standard errors than are
reported. ..the true confidence bands around the estimates fromthese models are probably wide enough to include demand
scenarios where HSR will lose substantial amounts of money aswell as those where it will make a healthy profit.(ITS Berkley, pg 9-10)
-
8/6/2019 HSR Compilation Report July 2011
9/19
-
8/6/2019 HSR Compilation Report July 2011
10/19
Questioning the High Speed Rail
AuthorityAssemblywoman Harkey and Senator Lowenthal questioning the project & Authority
http://www.youtube.com/watch?v=5a9gROsdSlU&feature=relatedhttp://www.youtube.com/user/derailhsr#p/u/51/9zabuRbLlew
http://www.youtube.com/user/derailhsr#p/u/55/nslMiQQm-gw
http://www.youtube.com/user/derailhsr#p/u/60/hnI4CYF0NK8
Legislative Analyst Office Report: High Speed Rail is at a Critical Juncture
http://www.lao.ca.gov/reports/2011/trns/high_speed_rail/high_speed_rail_051011.pdf
The State Auditors Office Report on the High Speed Rail Authority
http://www.bsa.ca.gov/pdfs/reports/2009-106.pdf
The Institute of Transportation Studies from The University of California, Berkeley Report
Review of Bay Area/California High-Speed Rail Ridership and Revenue Forecasting Study
http://www.its.berkeley.edu/publications/UCB/2010/RR/UCB-ITS-RR-2010-1.pdf
-
8/6/2019 HSR Compilation Report July 2011
11/19
Media Reaction: Washington Post
If federal high-speed rail investment makes
sense at all, it's probably in the densely
populated Northeast Corridor, where demand
for passenger trains is highest. At the very
least, California should have to fill in its
project's economic and logistical blanks before
any more money - from state taxpayers or therest of us - is spent. Washington Post
-
8/6/2019 HSR Compilation Report July 2011
12/19
Media on Ridership
Supposedly 39 million people will eagerly pay much more than an airfarein order to travel slower. Between 2008 and 2009, the projected costincreased from $33 billion to $42.6 billion. Newsweek
In 2010, Amtrak carried 29.1 million passengers for the entire year. That'sabout 4 percent of annual air travel (2010 estimate: 725 millionpassengers). Washington Post
The irony is that California has the highest rate of car-ownership in thecountry, if not the world. It also, despite years of neglect, has one of thebest road networks anywherecertainly leagues ahead of Japans. On topof that, it enjoys a highly competitive network of budget airlines serving itsmain cities. The Economist
-
8/6/2019 HSR Compilation Report July 2011
13/19
On Debt & Taxpayer Dollars
if I had to sell a purehigh speed rail bond,
that the uncertainties,
the (issues of) revenue
streampassenger
volumerevenues were
so unsettled that noinvestor would want to
take that risk. State
Treasurer Bill Lockyer
We must examine and
re-examine everypossible way to save
taxpayer dollars
Governor Jerry Brown
-
8/6/2019 HSR Compilation Report July 2011
14/19
But Other Countries Are Doing It
Japan, with the worlds leadingsystem, illustrates the financial
devastation that high-speed railcan produce. For 25 years, Japanborrowed to build a systemserving the ideal rail corridor,nestled along a single coast witha population of more than 75million people. Ridership wasartificially increased by highgasoline prices and one of thehighest highway tolls in theworld. National Review
Building trains is an immenselycostly enterprise--not just
financially costly, butenvironmentally and personallycostly, as people and habitats areuprooted, and metal is torturedinto rails and switches andcars. If you are going to installone, you should be reasonably
certain that there will be peoplearound with an interest in ridingyour train. After all, a trainrunning mostly empty emits a lotof carbon. The Atlantic
-
8/6/2019 HSR Compilation Report July 2011
15/19
Media Coverage on the Subsidy
Question But the rail authoritys analysis suggests that itwill be unable to attract the minimum $10billion in private funding it needs without arevenue or ridership guarantee. The LegislativeAnalysts Office says such a guarantee amountsto a promise of a subsidy if the project doesntmeet expectations, and is thus illegal. SanDiego Union Tribune
Ridership on a train traversing our sprawlingstate is unlikely to ever be high enough to beprofitable without heavy, ongoing taxpayersubsidies. Orange County Register
It is dismaying that the federal government hasoffered $2.8 billion for the project, when even acursory examination would show that the railsystem cannot operate without huge continuinghandouts from a state that has the largestbudget deficit in the nation. Oakland Tribune
-
8/6/2019 HSR Compilation Report July 2011
16/19
LAO: Voter Packet with Corresponding AB 3034 Language
(AB 3034 Passed in 2008 is the CHSRA Authorizing Legislation)
Limitations . bond funds may be used to provide only up to one-half of the total cost ofconstruction of each corridor or segment of a corridor. The measure requires the authority
to seek private and other public funds to cover the remaining costs. The measure also limits
the amount of bond funds that can be used to fund certain pre-construction and
administrative activities.
Accountability and Oversight Specifically, the bond funds must be appropriated by theLegislature, and the State Auditor must periodically audit the use of the bond funds. In
addition, the authority generally must submit to the Department of Finance and theLegislature a detailed funding plan for each corridor or segment of a corridor, before bond
funds would be appropriated for that corridor or segment. The funding plans must also be
reviewed by a committee whose members include financial experts and high-speed train
experts. An updated funding plan is required to be submitted and approved by the Director
of Finance before the authority can spend the bond funds, once appropriated.
Bond Costs If the bonds are sold at an average interest rate of 5 percent, and assuming a
repayment period of 30 years, the General Fund cost would be about $19.4 billion to pay offboth principal ($9.95 billion) and interest ($9.5 billion). The average repayment would be
about $647 million per year.
Operating Costs When constructed, the high-speed train system will incur unknownongoing maintenance and operation costs, probably in excess of $1 billion a year.
-
8/6/2019 HSR Compilation Report July 2011
17/19
High-Speed Rail: Dead and Loving It
Excerpts from: reason.com/blog by Tim Cavanaugh, June 7, 2011
Thanks to the wording of the law, the California High Speed Rail project now may die a quiet
death. Last Wednesday, the California Senate voted to place the California High Speed Rail Authority(CHSRA, which is currently a standalone agency) under the authority of the states Business,
Transportation and Housing Agency. The State Assembly passed a bill that would demote the CHSRA
to an advisory body while shifting control of the project to a Department of High-Speed
Trains. The creation of a brand new bureaucracy is ominous. But these complementary legislative
moves, by a Democratic legislature under a Democratic governor, have all the characteristics of a face-
saving admission that the Golden States high-speed rail project is either dead or in a persistent
vegetative stateThe Corcoran-Borden route was selected by the Federal Rail Authority specifically
for the relative ease with which the state could roll over rusticated local landowners who lack the
resources to mount a challenge like the one that has emerged on the wealthy San Francisco
peninsula.
The legislature has so far gone along with the Legislative Analysts recommendations, and those
recommendations include scrapping Corcoran-Borden altogether. As if thats not enough, it turns out
we wont always have Palmdale. That plan was scrapped in favor of a track going through the Mojave
Desert and the Antelope Valley into Sylmar. Now the route may be switched back to the Grapevine
again, after a report that the Antelope Valley route would require rebuilding of the California
Aqueduct and/or altering a dam.
Since 1996, the Golden State has managed to disappear a quarter of a billion dollars without laying
any track. In a floor speech, Assemblywoman Diane L. Harkey (R-Dana Point) argues that even the
new bureaucratic deep freeze is too good a fate for the misguided HSR project. Still, better a trickle
of wasted money than a torrent.
-
8/6/2019 HSR Compilation Report July 2011
18/19
Howard Jarvis Taxpayers Association:Court of Appeals rules that CA Legislature violated Political Reform Act over High SpeedRail
January 28, 2011
Sacramento --- Today, Howard Jarvis Taxpayers Association won a major victory on behalf of taxpayers as well as the integrity of
the ballot process. In a 23-page published decision, the Court of Appeal ruled that the California Legislature violated the Political
Reform Act, an initiative approved by the voters in 1974, when it dictated the contents of what is supposed to be objective
material in the ballot pamphlet.
No longer can the California Legislature use the ballot pamphlet as biased advertising for its own pet ballot
measures, said Jon Coupal, President of Howard Jarvis Taxpayers Association. At issue in the legal action was the High Speed
Train Bond Act of 2008, a measure sponsored and placed on the ballot by the Legislature. Rather than complying with the voter-
prescribed process of having the Attorney General prepare the ballot label, title and official summary, the Legislature hijacked the
process and dictated the language that would appear in the ballot pamphlet. HJTA had alleged that the material was little more
than a sales job on behalf of the bond.
Coupal added the Courts ruling is a stinging rebuke of the California Legislature for manipulating voters by
substituting the proponents advocacy for what is supposed to be a neutral summary by an impartial third party. Voters knowthat the arguments in the ballot pamphlet are advocacy, but they assume wrongly, in this case that the ballot label, title and
official summary are objective. We are very pleased that the Courts ruling demands that, in the future, only an objective party
can prepare those portions of the ballot material which are currently recognized as being official.
While the Courts ruling does not reverse the e lection on the High Speed Rail bonds, it does insure that the California Legislature
cannot manipulate the process in the future.
Tim Bittle, HJTAs Director of Legal Affairs who argued the case before the Court, stated, we have no doubt that,
had the voters been presented with a truly impartial ballot description, the HSR bond would have gone down in defeat. (The HSR
bond barely passed with a 52.5-47.5 % vote). But this ruling slams on the brakes to the future manipulation of the voters by
what, up until now, had been an increasing practice by the California Legislature.Jon Coupal added, the timing of the ruling is important for taxpayers as the Governor and the Legislature are
planning to place massive tax increases on the ballot in June. This ruling will help assure that the material presented to the voters
as official, is indeed objective and not merely advertising for tax increases.
The ruling also has the potential for affecting the two measure placed on the ballot by the Legislature relating to a
Water Bond and Budgeting Reform Measure.
To read the full text of the Courts ruling, visit: http://www.courtinfo.ca.gov/opinions/documents/C060441.PDF.
-
8/6/2019 HSR Compilation Report July 2011
19/19
Resources
www.bsa.ca.gov
www.lao.ca.gov
www.asm.ca.gov/Harkey www.cc-hsr.org
www.HighSpeedRailBoondoggle.com
www.calhsr.com
www.examiner.com/user-katham3 www.youtube.com/derailhsr
Other references as noted in report