HUNTER MILL ASSEMBLAGE
February/March 2020 Project Update
Agenda • Overview
• Recap
– Planned road improvements
– Implementation options
– Planning principles
• Update from last meeting (Fall 2019)
– Detail benefits of acceleration
– Address land plan priorities
– Land plan options
• Next steps
2
Hunter Mill Road &Sunset Hills Road
Intersection:
Existing Conditions
• Heavy congestion at intersections of Sunset Hills Road, Hunter Mill Road, and Dulles Toll Road ramps.
• Two intersections are approximately 150 feet apart
• Comprehensive Plan previously recommended to keep this existing alignment
3
Hunter Mill Road &Sunset Hills Road
Intersection:
Comprehensive Plan Updates (2014-2018)
• February 2014: Update of the Reston Transit Stations Areas in the Comprehensive Plan
• July 2014: Opening of the Wiehle-Reston East Metrorail station
• December 2014-November 2016: Hunter Mill Road study (initiated by FCDOT)
– Six alignment scenarios identified and studied
– Preferred alignment identified
• May 2017-March 2018: Comprehensive Plan Amendment initiated and adopted to incorporate planned realignment
– Did not address changes to surrounding land use
4
Hunter Mill Road &Sunset Hills Road
Intersection:
Existing Conditions& Comprehensive Plan amendment
• Heavy congestion at intersections of Sunset Hills Road, Hunter Mill Road, and Dulles Toll Road ramps.
• Comprehensive Plan Amendment adopted in March 2018 for Sunset Hills Road realignment
• Projected cost: $73 million
5
6
• Relocation of Sunset Hills Road to Crowell Road
• Roundabout at Hunter Mill Road/Crowell Road
• Widen Hunter Mill Road to 4 lanes from Sunrise Valley Drive to Crowell Road
Source: Fairfax County Department of Transportation (FCDOT)
7
• Relocation of Sunset Hills Road to Crowell Road
• Roundabout at Hunter Mill Road/Crowell Road
• Widen Hunter Mill Road to 4 lanes from Sunrise Valley Drive to Crowell Road
Source: Fairfax County Department of Transportation (FCDOT)
Hunter Mill Road &Sunset Hills Road
Intersection:
Challenges to Implementation
• Four separate owners own the needed right-of-way for Sunset Hills Road relocation, widening of Hunter Mill Road (north of DTR) and portions of the proposed roundabout
• Current planning and zoning permits low density residential development at 0.2-0.5 dwelling units per acre
– Discourages consolidation and cooperation
– Planned road improvements not implemented with by-right development
• Lack of available public funds to complete the work
– Projected cost: $73 million
8
Hunter Mill Road &Sunset Hills Road
Intersection:
Opportunity to Accelerate
Improvements
• With appropriate development and coordination, Brookfield Residential would complete the upgrades years ahead of schedule
• Public funds can be reallocated to facilitate other improvements
• Requires Comprehensive Plan amendment and rezoning to address surrounding land uses
9
Planning Principles
1. Community engagement
2. Respect Hunter Mill Road as a Scenic Byway
3. Acknowledge area history and incorporate elements into design
4. Implement the Transportation Master Plan
5. Contribute to public facilities for regional benefit
6. Create quality design
10
COMMUNITY FEEDBACK
11
Benefits of Acceleration
• Preliminary scenarios studied using VDOT standards for Level of Service (“LOS”) and delays with and without improvements
• LOS is valued with a letter grade (A through F)
• Length of delay determines grades
12
13
Acceleration of Improvements =
Hunter Mill/Crowell Road intersection:
• 27 seconds better in AM
• 45 seconds better in PM
Dulles Toll Road ramps:
• 1-10 seconds better
2025 conditions withoutrealignment
2025 conditions with realignment
= 236 new trips in AM peak hour and 308 new trips in PM peak hour
• Formal operational analysis will be completed with rezoning and subject to VDOT and Fairfax County Department of Transportation (FCDOT) review and approval
• FCDOT will also likely conduct a traffic analysis as part of the Comp Plan Amendment
Hunter Mill/Crowell Road intersection:
• Add 1.7 seconds in AM
• Add 0.7 seconds in PM
Dulles Toll Road ramps:
• Add 1-10 seconds14
Adding Proposed Development
15
Acceleration of Improvements + New Development =
Hunter Mill/Crowell Road intersection:
• 26 seconds better in AM over existing
• 44 seconds better in PM over existing
Dulles Toll Road ramps:
• +/- 3 seconds over existing2025 conditions with realignment and without Brookfield development
2025 conditions with realignment and withBrookfield development
16Consistency in transit service
Land Plan Priorities
1. The realigned Sunset Hills Road will avoid adverse impacts to the Resource Protection Area (RPA).
2. The distance between the realigned road and the Hunting Crest community will be maximized.
3. There will be no direct or indirect connection from the realigned road to Hunting Crest Way (pedestrian or vehicular).
4. The project will have sufficient density to fund road improvements.
5. The project will focus on single-family homes with diverse unit types and a range of price points.
17
18
Image received from Hunting Crest community
19
201. The realigned Sunset Hills Road will avoid adverse impacts to the Resource Protection Area (RPA).
RPA
21
2. The distance
between the realigned road and Hunting
Crest will be maximized.
22
23
24
25
26
27
3. There will be no direct or indirect
connection from the realigned road to
Hunting Crest Way.
28
Proposed Barrier
Preliminary Land Plan4. The project will have
sufficient density to fund road improvements.
29
Preliminary Site Tabulations
Site Area 62 acres
Baseline Density 4.5 du/ac
Baseline Units 277 units
ADUs 30 units
Bonus Units 44 units
Total Units 351 units
Overall Density 5.7 du/ac
5. The project will focus on single-
family homes with diverse unit types
and a range of price points.
• Preliminary design includes a range of home sizes, up to ~4,200 SF per home
• Base prices will generally range between $600,000 and $1,200,000 (+ purchaser options)
• All single-family homes (detached and attached)
• No multifamily/apartments or traditional townhomes
30
Next Steps • Request Comprehensive Plan Amendment (Q1/Q2 2020)
• Prepare rezoning application for submission to Fairfax County (Q2 2020)
• Review and revise development per County review (Q3 2020 - Q2 2021)
• Present to the Planning Commission for recommendation, and Board of Supervisors for approval (Q2 2021)
• Further site plan, construction permits, building plans, etc. to be reviewed and approved by the County (TBD)
33
34
To contact our team and share any questions or feedback, please visit our website:www.huntermillinfo.com