huntington power plant - berkshire hathaway energy · the final cover system or cap for the...
TRANSCRIPT
Huntington Power Plant
CCR LANDFILL CLOSURE PLAN
Prepared for:
Prepared by:
Moonlight Professional Building
480 East Park Street Butte, MT 59701
September 2016
Huntington Power Plant – CCR Landfill Closure Plan
i
INDEX AND CERTIFICATION
PacifiCorp Huntington Power Plant
CCR Landfill Closure Plan
REPORT INDEX
Chapter Number Chapter Title Number of Pages
1.0 Introduction 1
2.0 Closure Plan 5
Attachment 1 Construction Drawings 4
CERTIFICATION
I certify, as a Professional Engineer in the State of Utah, that this document was assembled by me or by
someone under my direct supervision. This report is not intended or represented to be suitable for
reuse by PacifiCorp or others without specific verification or adaptation by the Engineer.
I certify, as a Professional Engineer in the State of Utah, that, to the best of my knowledge and
engineering judgment, the CCR landfill post-closure plan provided in this document meets the
requirements of 40 Code of Federal Regulations §257.104.
Steven M. Anderson
License Number UT PE 8049139-2202
My license renewal date is March 31st, 2017
Steven M. Anderson , P.E.
Date: 9/6/16
Huntington Power Plant – CCR Landfill Closure Plan
ii
Table of Contents
1.0 INTRODUCTION ................................................................................................................................. 1
1.1 Facility Description ........................................................................................................................ 1
1.2 Maximum Inventory of Waste ...................................................................................................... 1
2.0 CLOSURE PLAN .................................................................................................................................. 2
2.1 Notice of Intent to Close ............................................................................................................... 2
2.2 Final Grading ................................................................................................................................. 2
2.3 Temporary Erosion and Sediment Control ................................................................................... 3
2.4 Final Closure .................................................................................................................................. 3
2.5 Final Cover Description ................................................................................................................. 3
2.5.1 Erosion Control Features ...................................................................................................... 3
2.6 Testing Requirements ................................................................................................................... 4
2.7 Recording/Notice in Deed to the Property ................................................................................... 4
2.8 Closure Schedule ........................................................................................................................... 4
2.9 Closure Certification ..................................................................................................................... 4
2.10 Largest Area Requiring Final Closure ........................................................................................ 5
2.11 Landfill Geometry and Slope Stability ....................................................................................... 5
3.0 SUMMARY ......................................................................................................................................... 5
List of Attachments Attachment 1 Construction Drawings
Attachment 2 Construction Gantt Chart
List of Abbreviations
Abbreviation Term/Phrase
CCR Coal Combustion Residual
1
1.0 INTRODUCTION
This Closure Plan describes the steps necessary to partially or entirely close the Huntington
Power Plant CCR Landfill at any point during its active life or at the end of its operating life. This
Plan will be updated if any changes occur at the facility which requires a deviation from the
approved Closure and Post Closure Plan.
1.1 Facility Description
The Huntington Plant is a coal-fired power plant owned and operated by PacifiCorp and
located near Huntington, Utah. The Huntington Plant disposes of coal combustion ash at
a combustion waste landfill located southeast of the existing plant.
Huntington Plant produces 895 megawatts of electricity per year. The plant burns
approximately 3 million tons of sub-bituminous coal per year.
1.2 Maximum Inventory of Waste
The estimated maximum inventory of waste over the active life of the landfill is
estimated to be about 8.4 million cubic yards. This is based on the current operations
plan. Upon final closure of this facility, PacifiCorp – Huntington Power Plant shall submit
to the appropriate agencies an estimate of the maximum amount of waste that has
been disposed in the landfill. This may be accomplished by comparing the initial and
final contours of the facility or the use of volume reports completed during the active
life of the landfill.
2
2.0 CLOSURE PLAN The purpose of this Closure Plan is to describe the steps necessary to close the landfill or portion thereof at any point during its intended operating life in accordance with the CCR current regulations. These procedures apply to the final closing of the solid waste disposal cells during the landfill operation and at final closure of the landfill.
2.1 Notice of Intent to Close PacifiCorp – Huntington Power Plant shall begin closure of the CCR Landfill, per the
approved closure plan no later than thirty (30) days after the last receipt of waste in the
CCR Landfill. PacifiCorp – Huntington Power Plant shall notify appropriate parties, by
letter, the date closure of the CCR Landfill begins, and, unless otherwise approved, the
application of final cover on the CCR Landfill shall be completed within six (6) months of
the last receipt of waste in the CCR Landfill.
2.2 Final Grading The final surface of the landfill cover shall be graded to promote drainage, minimize erosion of cover, prevent ponding, and provide a surface drainage system consistent with the surrounding area without adversely affecting proper drainage from adjacent areas. The side slopes of the landfill's final cover surface will not be any steeper than 3 horizontal to 1 vertical to prevent erosion and facilitate maintenance. The exterior side slope of this landfill vertical expansion will include terraces to reduce the velocity of storm water runoff and minimize erosion of the final cover. The final grade maintained on top of the landfill between the crest of the side slope and the center of the landfill shall be at least 3 percent but not greater than 5 percent. An alternate final cover design may be submitted for review and approval. The maximum height of the landfill will be approximately 240 feet above the lowest elevation of the landfill. The final cover will be placed on top of the waste. Terraces will be constructed to convey storm water and will be sloped to drain storm water runoff from high points to down drains at low points on the terraces. Additional terraces will be located approximately every 50 feet of vertical rise in elevation. The top of waste surface for the terraces will slope away from the landfill to allow for
sheet flow of storm water runoff over the side slopes until the down drains and final
cover on the terrace can be installed. The final cover surface on the drainage terraces
will be built up above the surface of the waste to allow for the installation of the down
drains and to divert storm water away from the side slopes. Grade and slope stakes will
be set up as needed prior to placement of the final waste layers to assist the operator in
placing the waste. This will ensure that the maximum disposal capacity of the landfill is
fully utilized. Grade stakes will minimize the need to move waste or add fill soil to
achieve final subgrade elevations.
3
2.3 Temporary Erosion and Sediment Control Prior to the start of final cover construction, temporary erosion control features (i.e., silt
fencing, temporary sediment control areas) will be installed. During final cover
construction activities, the temporary erosion control features will be inspected every
seven (7) calendar days until adequate vegetative cover is achieved; or, according to
schedule, in compliance with the most current storm water regulation. Temporary
erosion control features will be repaired or replaced if any such features have been
damaged from runoff or if there is excessive sediment buildup behind the silt fence or
other erosion control device that would impede the performance of the feature. When
the inspection results show that a repair is required, the repair or replacement shall
occur within 30 days of such a notice.
2.4 Final Closure The landfill will be progressively closed by constructing a final cover (i.e., cap). Final
cover shall be completed within 6 months, unless such activity is delayed by an event of
force majeure, after last receipt of waste. Just prior to final closure, the landfill cell shall
be surveyed to assist the landfill operator in placing and grading the final layers of
waste. The site engineer shall develop a detailed set of Construction Drawings with
control points for final closure of the landfill based on the approved closure plan and the
actual survey data just prior to closure.
2.5 Final Cover Description The final cover system or cap for the landfill will be designed to minimize infiltration and
erosion and improve the esthetics. The final cover system for this landfill will consist of
thirty (30) inches of soil with a maximum permeability of 1 x 10-5 centimeters per
second, and a minimum of six (6) additional inches of soil capable of supporting native
vegetation or an approved alternative final cover system. This layer is designed to
minimize infiltration through the closed landfill and prevent erosion of the landfilled
material. This layer shall be free from deleterious material and consist of natural soils
classified as MH, CH, CL, SC, ML or SC-SM according to the unified soil classification
system, or approved equal. Soil used for the compacted earth cover shall be placed over
the waste in loose lift thicknesses of 12 inches or less and compacted to greater than 80
percent of its standard Proctor maximum dry density. If the underlying waste
foundation is soft, a lesser degree of compaction may be acceptable provided it still
meets the thickness requirement. The Construction Quality Assurance I Quality Control
(CQA/QC) engineer should approve any compaction less than 80 percent.
2.5.1 Erosion Control Features
Dozer basins will be installed as soon as a significant section of slope is covered with the design thickness of cover material. Dozer basins, if properly constructed, are effective in limiting erosion on steep slopes. The dozer basins will be constructed with as straight of dozer blade as possible, with the outer rim of one basin aligning vertically with the central-third of the down-slope basin.
4
Contour ditches will be completed on benches at varying lengths not greater than 800 feet of the landfill slope length. The contour ditches will be constructed according to design specifications and sloped at no more than 5% and no less than 0.25 % toward the conveyance channels. These ditches will be grass lined following the revegetation of the landfill cover surface. The maximum flow for each contour ditch will be calculated by using the rational method with the area between adjacent contour ditches and the maximum length of a contour ditch as the area used in the Rational Equation. Conveyance channels will be constructed to convey the storm water collected by the contour ditches to the existing sediment catch basins in as little time as possible. Conveyance channels will convey the 10-year and 100-year storm events in the main channel. The slope of these ditches will range from 2.5:1 (40%) to 20:1 (5%) depending on the site topography. Conveyance ditches will be rip-rap lined at all locations where the slope exceeds 10%. Maximum allowable velocities for rip rap-lined channels on steep slopes range between 9 ft/s and 11 ft/s. Maximum allowable velocities for grass-lined channels on flat to moderate slopes range from 4 ft/s to 6 ft/s. An important component of erosion control on steep slopes is establishing vegetation as quickly as possible. The seed mix will include native species as well as strong-establishing, introduced species, primarily crested wheatgrass, and sheep fescue. Broadcast seeding followed by a chain harrow to loosen the topsoil and lightly cover the seeds is recommended. On steep slopes, a dozer may need to be used for seeding activities. Seeding will be done in the fall or spring, to take advantage of cooler temperatures and increased precipitation.
2.6 Testing Requirements A minimum of four thickness checks per acre per lift will be conducted to verify the
thickness of the infiltration layer is at least thirty inches thick. Field density testing may
also be performed at the same time and location. A Utah Registered Professional
Engineer must certify that the required thickness has been achieved.
2.7 Recording/Notice in Deed to the Property Following completion of closure activities, a notation will be placed on the property deed, or some other instrument normally examined during a title search, indicating in perpetuity that the property has been used for the disposal of solid waste. The notation will define the final boundaries of the waste disposal area including the latitude, longitude, and identify the type, location, and quantity of solid waste disposed of on the property.
2.8 Closure Schedule PacifiCorp – Huntington Power Plant will begin final closure activities no later than
within thirty (30) days of receipt of the final load of waste at the landfill. Closure
activities will be completed within six (6) months following the last receipt of waste.
2.9 Closure Certification PacifiCorp – Huntington Power Plant shall notify appropriate agencies by letter the date
that closure of the CCR Landfill begins, and, unless otherwise approved, the application
5
of final cover on the CCR Landfill shall be completed within six (6) months of the last
receipt of waste in the CCR Landfill. Following closure of the entire landfill, PacifiCorp –
Huntington Power Plant will submit a certification to the appropriate agencies that the
landfill has been properly closed. The Certification shall be signed and sealed by a Utah
Registered Professional Engineer, verifying that closure has been completed in
accordance with the Closure Plan. Any deviations from the Closure Plan shall be
identified and include an explanation. A copy of the certification will be kept on file in
the facility operating record.
2.10 Largest Area Requiring Final Closure Currently none of the 73-acre landfill has received final cover or certificate of closure.
Therefore the largest area to ever require final closure is the full 73 acres.
2.11 Landfill Geometry and Slope Stability A veneer stability analysis will be conducted to check the stability of a 3-foot thick cap
section on the 3-horizontal to 1-vertical side slopes. An adequate factor of safety will be
determined to insure stability.
3.0 SUMMARY The purpose of final closure implementation is to preclude post closure release of pollutants to the environment. The final cover system will minimize infiltration of precipitation into the waste and erosion of the cap in order to protect public health and the environment. Final closure details may vary as operation of the landfill proceeds. After final closure, the post closure plan will be implemented.
ATTACHMENT 1
CONSTRUCTION DRAWINGS
0+
00
1+
00
2+
00
3+
00
4+
00
5+
00
6+
00
7+
00
8+
00
9+
00
10+
00
11+
00
12+
00
13+
00
14+
00
15+
00
16+
00
SE
DIM
EN
TA
TIO
N P
ON
D
6780
6780
6780
6770
6
7
7
0
6770
6760
6760
6760
6
7
6
0
6770
6780
PR
OF
ILE
E
-W
SH
EE
T 2
PROFILE N-S
SHEET 2
6520
6540
6550
6560
6570
6580
6590
6600
6
6
2
0
6
6
3
0
6
6
4
0
6
6
5
0
6610
6620
6630
6640
6650
6650
6660
6670
6680
6690
6700
6650
6660
6670
6680
6690
6700
6
6
5
0
6660
6670
6
6
8
0
6
6
9
0
6700
6710
6720
6730
6740
6750
6710
6720
6730
6740
6750
6530
0+001+00
2+003+00 4+00
5+00 6+007+00
8+009+00 10+00
11+00 12+0013+00
14+0015+00
16+0017+00
18+0019+00 20+00
21+00 22+00 23+0024+0024+00
480 E
. P
ark S
treet
Butte, M
T 59701
(406) 782-5220
WA
TE
RE
NV
TE
CH
.C
OM
JOB NO:
DATE:
DRAFTER:
CHECKED BY:
M:\P
ER
CM
70-H
untington C
CR
C
om
pliance\C
AD
\C
IV
IL\S
C_G
P01_Landfill F
G.dw
g P
LO
T D
AT
E 2016-4-19
16:57 U
SE
R: bsiddow
ay
SHEET
PR
OJE
CT
N
AM
E:
LO
CA
TIO
N:
FILE
N
O.
2016
CO
PY
RIG
HT
No.
Water &
E
nvironm
ental T
echnologies P
C hereby reserves our com
mon law
copyright in
this docum
ent and the ideas and designs incorporated herein as an instrum
ent of
professional service w
hich shall not be used in w
hole or part for any other projects or
other use w
ithout our express w
ritten authorization.
HU
NT
IN
GT
ON
C
CR
C
LO
SU
RE
P
LA
N
HU
NT
IN
GT
ON
, U
TA
H
SC
_G
P01_Landfill F
G.dw
g
4/19/16
BS
SA
Draw
n B
yD
ate
Description
PERCM70
HU
NT
IN
GT
ON
C
CR
D
IS
PO
SA
L L
AN
DF
IL
L
FIN
AL
S
IT
E P
LA
N
1
FEET
0 100 200
N
Profile E-W
VERTICAL EXAGGERATION = 2:1 (H:V)
6580
6600
6620
6640
6660
6680
6700
6720
6740
6760
6780
6800
6820
6840
6860
6880
6580
6600
6620
6640
6660
6680
6700
6720
6740
6760
6780
6800
6820
6840
6860
6880
0+00
EG
: 6
63
0.5
8
FG
:
1+00
EG
: 6
62
5.2
9
FG
: 6
63
2.3
1
2+00
EG
: 6
62
2.2
6
FG
: 6
65
9.4
2
3+00
EG
: 6
62
0.2
4
FG
: 6
69
2.7
5
4+00
EG
: 6
61
5.3
7
FG
: 6
71
9.8
1
5+00
EG
: 6
61
3.3
0
FG
: 6
75
2.8
7
6+00
EG
: 6
62
8.5
7
FG
: 6
76
9.2
6
7+00
EG
: 6
65
5.7
4
FG
: 6
77
8.7
6
8+00
EG
: 6
65
5.0
3
FG
: 6
78
4.0
0
9+00
EG
: 6
65
3.6
8
FG
: 6
77
8.8
2
10+00
EG
: 6
65
2.5
7
FG
: 6
76
8.7
1
11+00
EG
: 6
65
1.8
4
FG
: 6
75
3.7
5
12+00
EG
: 6
65
0.7
5
FG
: 6
72
1.9
4
13+00
EG
: 6
64
9.9
2
FG
: 6
69
5.9
4
14+00
EG
: 6
64
8.8
8
FG
: 6
66
3.9
4
15+00
EG
: 6
64
8.0
1
FG
:
3
:
1
(
H
:
V
)
3
:
1
(
H
:
V
)
3
:
1
(
H
:
V
)
1
0
:1
(H
:V
)
5.0
%-5
.0%
-1
0
:1
(H
:V
)
-
3
:
1
(
H
:
V
)
-
3
:
1
(
H
:
V
)
GR
AD
E B
RE
AK
S
TA
=
0
+8
3.9
9
EL
EV
=
6
62
7.5
9
GR
AD
E B
RE
AK
S
TA
=
1
+5
2.8
9
EL
EV
=
6
65
0.4
0
GR
AD
E B
RE
AK
S
TA
=
1
+7
1.7
1
EL
EV
=
6
65
0.0
0
GR
AD
E B
RE
AK
S
TA
=
3
+2
1.7
6
EL
EV
=
6
70
0.4
0
GR
AD
E B
RE
AK
S
TA
=
3
+4
1.7
6
EL
EV
=
6
70
0.0
0
GR
AD
E B
RE
AK
S
TA
=
5
+2
3.3
9
EL
EV
=
6
76
0.0
0
GR
AD
E B
RE
AK
S
TA
=
7
+1
3.2
8
EL
EV
=
6
78
0.0
0
GR
AD
E B
RE
AK
S
TA
=
7
+9
1.9
7
EL
EV
=
6
78
4.0
0
GR
AD
E B
RE
AK
S
TA
=
8
+0
7.9
7
EL
EV
=
6
78
4.0
0
GR
AD
E B
RE
AK
S
TA
=
8
+8
8.2
0
EL
EV
=
6
78
0.0
0
GR
AD
E B
RE
AK
S
TA
=
1
0+
79
.4
9
EL
EV
=
6
76
0.0
0
GR
AD
E B
RE
AK
S
TA
=
1
2+
67
.3
1
EL
EV
=
6
70
0.0
0
GR
AD
E B
RE
AK
S
TA
=
1
2+
87
.3
1
EL
EV
=
6
70
0.4
0
GR
AD
E B
RE
AK
S
TA
=
1
4+
43
.5
7
EL
EV
=
6
65
0.0
0
GR
AD
E B
RE
AK
S
TA
=
1
4+
62
.3
3
EL
EV
=
6
65
0.4
0
GR
AD
E B
RE
AK
S
TA
=
1
4+
68
.3
5
EL
EV
=
6
64
8.1
1
PROFILE N-S
VERTICAL EXAGGERATION = 2:1 (H:V)
6540
6560
6580
6600
6620
6640
6660
6680
6700
6720
6740
6760
6780
6800
6820
6840
6860
6880
6900
6540
6560
6580
6600
6620
6640
6660
6680
6700
6720
6740
6760
6780
6800
6820
6840
6860
6880
6900
0+00
EG
: 6
54
7.8
0
FG
:
1+00
EG
: 6
55
0.9
0
FG
: 6
57
0.9
8
2+00
EG
: 6
55
6.0
8
FG
: 6
60
0.0
0
3+00
EG
: 6
55
9.3
1
FG
: 6
62
5.9
2
4+00
EG
: 6
56
2.0
1
FG
: 6
65
0.5
8
5+00
EG
: 6
56
5.4
3
FG
: 6
68
2.5
8
6+00
EG
: 6
56
2.1
7
FG
: 6
70
8.5
2
7+00
EG
: 6
56
1.7
1
FG
: 6
74
0.5
8
8+00
EG
: 6
56
4.2
1
FG
: 6
76
4.1
3
9+00
EG
: 6
56
6.1
1
FG
: 6
77
4.6
5
10+00
EG
: 6
58
9.9
6
FG
: 6
78
2.2
0
11+00
EG
: 6
63
3.2
3
FG
: 6
78
4.0
0
12+00
EG
: 6
65
4.9
3
FG
: 6
78
4.0
0
13+00
EG
: 6
65
5.0
3
FG
: 6
78
4.0
0
14+00
EG
: 6
65
5.4
2
FG
: 6
78
4.0
0
15+00
EG
: 6
65
7.3
6
FG
: 6
78
4.0
0
16+00
EG
: 6
66
7.9
8
FG
: 6
78
4.0
0
17+00
EG
: 6
66
8.8
8
FG
: 6
78
4.0
0
18+00
EG
: 6
66
8.0
0
FG
: 6
78
4.0
0
19+00
EG
: 6
66
8.3
4
FG
: 6
78
4.0
0
20+00
EG
: 6
66
9.7
4
FG
: 6
78
3.7
4
21+00
EG
: 6
68
6.1
4
FG
: 6
77
9.3
6
22+00
EG
: 6
69
0.9
6
FG
: 6
76
9.2
3
23+00
EG
: 6
73
2.0
9
FG
: 6
75
5.1
9
24+00
EG
: 6
73
6.1
4
FG
:
3
:
1
(
H
:
V
)
3
:
1
(
H
:
V
)
3
:
1
(
H
:
V
)
3
:
1
(
H
:
V
)
1
0
:1
(H
:V
)
4.0
%
0.0%
-4.0
%
-1
0
:1
(H
:V
)
-
3
:
1
(
H
:
V
)
GR
AD
E B
RE
AK
S
TA
=
0
+3
1.9
2
ELE
V =
65
49
.1
8
GR
AD
E B
RE
AK
S
TA
=
1
+9
2.7
8
ELE
V =
66
00
.4
0
GR
AD
E B
RE
AK
S
TA
=
2
+1
3.6
2
ELE
V =
66
00
.0
0
GR
AD
E B
RE
AK
S
TA
=
3
+7
8.2
0
ELE
V =
66
50
.4
0
GR
AD
E B
RE
AK
S
TA
=
3
+9
8.2
0
ELE
V =
66
50
.0
0
GR
AD
E B
RE
AK
S
TA
=
5
+5
4.4
5
ELE
V =
67
00
.4
0
GR
AD
E B
RE
AK
S
TA
=
5
+7
4.4
5
ELE
V =
67
00
.0
0
GR
AD
E B
RE
AK
S
TA
=
7
+6
2.2
6
ELE
V =
67
60
.0
0
GR
AD
E B
RE
AK
S
TA
=
9
+5
3.5
4
ELE
V =
67
80
.0
0
GR
AD
E B
RE
AK
S
TA
=
1
0+
54.0
7
ELE
V =
6
784
.00
GR
AD
E B
RE
AK
S
TA
=
1
9+
92.1
6
ELE
V =
6
784
.00
GR
AD
E B
RE
AK
S
TA
=
2
0+
93.7
0
ELE
V =
6
779
.94
GR
AD
E B
RE
AK
S
TA
=
22
+8
4.22
ELE
V =
6
760
.00
GR
AD
E B
RE
AK
S
TA
=
2
3+
64.1
3
ELE
V =
6
734
.93
480 E
. P
ark S
treet
Butte, M
T 59701
(406) 782-5220
WA
TE
RE
NV
TE
CH
.C
OM
JOB NO:
DATE:
DRAFTER:
CHECKED BY:
M:\P
ER
CM
70-H
untington C
CR
C
om
pliance\C
AD
\C
IV
IL\S
C_G
P01_Landfill F
G.dw
g P
LO
T D
AT
E 2016-4-19
16:58 U
SE
R: bsiddow
ay
SHEET
PR
OJE
CT
N
AM
E:
LO
CA
TIO
N:
FILE
N
O.
2016
CO
PY
RIG
HT
No.
Water &
E
nvironm
ental T
echnologies P
C hereby reserves our com
mon law
copyright in
this docum
ent and the ideas and designs incorporated herein as an instrum
ent of
professional service w
hich shall not be used in w
hole or part for any other projects or
other use w
ithout our express w
ritten authorization.
HU
NT
IN
GT
ON
C
CR
C
LO
SU
RE
P
LA
N
HU
NT
IN
GT
ON
, U
TA
H
SC
_G
P01_Landfill F
G.dw
g
4/19/16
BS
SA
Draw
n B
yD
ate
Description
PERCM70
HU
NT
IN
GT
ON
C
CR
D
IS
PO
SA
L L
AN
DF
IL
L
TY
PIC
AL
P
RO
FIL
ES
2
FEET
0 100 200
HORIZONTAL SCALE:
NORTH SOUTH
WEST EAST
FEET
0 60 120
HORIZONTAL SCALE:
180'
20' 150'
20' VARIES
3
:1
(h
:v
)
NATIVE GROUND
ELEV = 6650.4
3
:1
(h
:v
)
3
:1
(h
:v
)
ELEV = 6650.0
ELEV = 6700.4
ELEV = 6700.0
ELEV = 6760.0
10:1
(h:v
)
ELEV = 6600.4
ELEV = 6600.0
VARIES20'
3
:1
(h
:v
)
3
SH-3
180'
20' 150'
20' VARIES
STORM WATER
CONVEYANCE DITCH
ELEV. VARIES
3
:1
(h
:v
)
BOTTOM ASH
COMBUSTION WASTE
CAP MATERIAL
PREPARED SUBGRADE
HAUL ROAD
NATIVE GROUND
ROAD SECTION
ELEV = 6650.4
3
:1
(h
:v
)
3
:1
(h
:v
)
ELEV = 6650.0
ELEV = 6700.4
ELEV = 6700.0
ELEV = 6760.0
ELEV. VARIES
10:1
(h:v
)
3
:
1
(
h
:
v
)
6" VEGETATED
TOPSOIL LAYER
30" COMPACTED
INFILTRATION LAYER
@ k = 1X10
-5
CM/S MAX.
CCR SUBGRADE
TO DESIGN ELEVATIONS
3
SH-3
480 E
. P
ark S
treet
Butte, M
T 59701
(406) 782-5220
WA
TE
RE
NV
TE
CH
.C
OM
JOB NO:
DATE:
DRAFTER:
CHECKED BY:
M:\P
ER
CM
70-H
untington C
CR
C
om
pliance\C
AD
\C
IV
IL\S
C_G
P01_Landfill F
G.dw
g P
LO
T D
AT
E 2016-4-19
16:58 U
SE
R: bsiddow
ay
SHEET
PR
OJE
CT
N
AM
E:
LO
CA
TIO
N:
FILE
N
O.
2016
CO
PY
RIG
HT
No.
Water &
E
nvironm
ental T
echnologies P
C hereby reserves our com
mon law
copyright in
this docum
ent and the ideas and designs incorporated herein as an instrum
ent of
professional service w
hich shall not be used in w
hole or part for any other projects or
other use w
ithout our express w
ritten authorization.
HU
NT
IN
GT
ON
C
CR
C
LO
SU
RE
P
LA
N
HU
NT
IN
GT
ON
, U
TA
H
SC
_G
P01_Landfill F
G.dw
g
4/19/16
BS
SA
Draw
n B
yD
ate
Description
PERCM70
HU
NT
IN
GT
ON
C
CR
D
IS
PO
SA
L L
AN
DF
IL
L
TY
PIC
AL
S
EC
TIO
NS
3
NORTH
Scale: NTS
TYPICAL FILL PLAN W/ HAUL ROAD - SECTION VIEW
1
WEST
Scale: NTS
TYPICAL FILL PLAN NORTH FACE - SECTION VIEW
2
Scale: NTS
VEGETATED CAP DETAIL - SECTION VIEW
3
SE
DIM
EN
TA
TIO
N P
ON
D
6780
6780
6780
6770
6
7
7
0
6770
6760
6760
6760
6
7
6
0
6770
6780
6520
6540
6550
6560
6570
6580
6590
6600
6
6
2
0
6
6
3
0
6
6
4
0
6
6
5
0
6610
6620
6630
6640
6650
6650
6660
6670
6680
6690
6700
6650
6660
6670
6680
6690
6700
6
6
5
0
6660
6670
6
6
8
0
6
6
9
0
6700
6710
6720
6730
6740
6750
6710
6720
6730
6740
6750
6530
H
P
:
6
7
0
2
LP: 6700
H
P
:
6
7
0
0
HP
: 6
70
2
LP: 6700
LP: 6700
HP
: 6702
H
P
:
6
6
5
2
H
P
:
6
6
5
2
LP: 6650
LP: 6600
H
P
:
6
6
0
2
HP: 6602
480 E
. P
ark S
treet
Butte, M
T 59701
(406) 782-5220
WA
TE
RE
NV
TE
CH
.C
OM
JOB NO:
DATE:
DRAFTER:
CHECKED BY:
M:\P
ER
CM
70-H
untington C
CR
C
om
pliance\C
AD
\C
IV
IL\S
C_G
P01_Landfill F
G.dw
g P
LO
T D
AT
E 2016-4-19
16:58 U
SE
R: bsiddow
ay
SHEET
PR
OJE
CT
N
AM
E:
LO
CA
TIO
N:
FILE
N
O.
2016
CO
PY
RIG
HT
No.
Water &
E
nvironm
ental T
echnologies P
C hereby reserves our com
mon law
copyright in
this docum
ent and the ideas and designs incorporated herein as an instrum
ent of
professional service w
hich shall not be used in w
hole or part for any other projects or
other use w
ithout our express w
ritten authorization.
HU
NT
IN
GT
ON
C
CR
C
LO
SU
RE
P
LA
N
HU
NT
IN
GT
ON
, U
TA
H
SC
_G
P01_Landfill F
G.dw
g
4/19/16
BS
SA
Draw
n B
yD
ate
Description
PERCM70
HU
NT
IN
GT
ON
C
CR
D
IS
PO
SA
L L
AN
DF
IL
L
RU
NO
FF
M
AN
AG
EM
EN
T P
LA
N
4
FEET
0 100 200
N
PRIMARY
CONVEYANCE DITCH
PRIMARY
CONVEYANCE DITCH
HAUL ROAD
SECONDARY
CONVEYANCE DITCH
DISCHARGE TO
EXISTING DITCH
CULVERT
RUNOFF
CONTROL BERM
HDPE COLLECTION
CHANNEL (TYP.)
BENCH CONVEYANCE
CHANNEL (TYP.)
ATTACHMENT 2
CONSTRUCTION GANTT CHART
Closure Construction Gantt ChartActivity Plan Start Duration (Days)Permitting/Closure NOI 1/1/2036 120Contractor Mobilization 4/30/2036 30Grading/Placing Cap 5/30/2036 135Final Grading/Revegetation 10/12/2036 15Closure Certification 10/27/2036 15
July-36 August-36 September-36 October-36 November-36June-36January-36 February-36 March-36 April-36 May-36
You created this PDF from an application that is not licensed to print to novaPDF printer (http://www.novapdf.com)