hv-squid compatibility test study the squid performance in a hv environment. study the hv breakdown...
TRANSCRIPT
HV-SQUID Compatibility Test
• Study the SQUID performance in a HV environment.
• Study the HV breakdown
– in superfluid under pressure.
– using different materials for electrodes.
Craig Huffer, Chen-Yu Liu, Josh Long Indiana University
Squid Performance in HV environments• Physical damage
• Direct HV discharge hitting the SQUID chip would destroy the SQUID.
• Large induced current flowing in the feedback circuit could destroy components. Large induced current flowing through the SQUID could destroy the Josephson junctions.
• Most of you are concerned with this. However, these extreme conditions are unlikely to happen.
• HV ripple and micro-discharge inside the dielectric materials in electrodes, cell, etc...
• High frequency components could disturb the feedback circuit and cause SQUID readings to jump randomly.
• increase the noise level.
• This could be a bigger concern. Remedy: RF shield.
1
2
3
4
5
6
7
9
8
1. LHe Volume Cap2. G10 Ground Electrode Support3. Macor rod for gradiometers4. HV electrode5. Ground electrode
6. HV feedthrough (25kV)7. SQUID feedthrough (multi-pin)8. LHe needle valve (superfluid- tight)9. SQUID
HV Breakdown vs Pressurization • Janis liquid helium dewar
1. pump on the reservoir to make superfluid
• Pressurization2. Close superfluid-tight needle
valve.3. Test probe has a bellows at
bottom. It can be pressed against the bottom of the liquid helium reservoir.
4. Temperature is maintained and controlled by the superfluid outside.
5. ~5% volume change to make 1atm.
to pump
17” 7”
Some design details
• The HV electrode is on top, to be screwed onto the end of the HV feedthrough.
• The ground electrode will be attached to the G-10 sleeve via 3 screws.
• The HV conductor (or cable) is placed inside a SS tube, which can be evacuated. This protect the HV from breaking down in helium vapor.
• A lot of room below the ground electrode to accommodate different SQUIDs & pickup coils.
Cryostat Top Flange
Bellows for vertical translation of probe.
Progress
• Currently preparing Janis cryostat. – modify components, leak checking, etc..
• Design is finalized (please comment...) – Some major components (HV feedthrough, bellows)
ordered.– Physics machine shop is scheduled to machine parts
(electrodes).
• Waiting for SQUIDs and electronics to be shipped from Los Alamos.
• Cool down test in ~ 1 month.• Preliminary results may be possible next
collaboration meeting.