hydraullic turbine man
TRANSCRIPT
-
7/27/2019 Hydraullic turbine Man
1/18
MANUFACTURINGCAPABILITIES FOR PLANT &
EQUIPMENT FOR HYDROPOWER PLANTS
S.K.Kaul18thAugus t2009
-
7/27/2019 Hydraullic turbine Man
2/18
SCENARIO OF 10TH PLAN
CAPACITY ADDITION
Sector Target (MW) Achievement
(MW)
Central 8742 4495
State 4481 2691
Private 1170 700
Total 14393 7886
Delay on account of Equipment supply constraint : 679 MW
-
7/27/2019 Hydraullic turbine Man
3/18
Summary of ordering status of TG Sets
of Hydro Projects in 10th Plan
The Hydro capacity addition Target 14393 MW
Electro-Mechanical equipments awarded 12004 MW
Indian Suppliers
BHEL 4945 MW
Alstom 680 MW
VA Tech 216 MW
Foreign Suppliers 6163 MW
-
7/27/2019 Hydraullic turbine Man
4/18
HYDRO CAPACITY ADDITION PROGRAMME
FOR 11TH PLAN
Central Sector 8654 MW
State Sector 3482 MW
Private Sector 3491 MW
Total 15627 MW
No. of Project 45
No. of Units 166
Highest unit size 250 MW
Smallest unit size 11 MW
-
7/27/2019 Hydraullic turbine Man
5/18
Summary of ordering status of TG Sets of HE
Projects for likely benefits in 11th Plan
The Hydro capacity addition programme: 15627 MW
Ordering Status of T.G. Sets:
Indian Supplier
BHEL 6017 MW
VA Tech 366 MW
Alstom 339 MW
Foreign suppliers 8905 MW
-
7/27/2019 Hydraullic turbine Man
6/18
Manufacturing Capabilities of main
indigenous manufacturers for plants &
equipment for Hydro Power Plants
M/s BHEL 2500 MW
M/s Alstom 1260 MW
M/s VA Tech order based
M/s Voith Siemens order based
-
7/27/2019 Hydraullic turbine Man
7/18
Preparedness for 12th Plan & beyond
Candidate Hydro projects prioritised for benefits during 12th Plan: 87
Total no. of Projects under execution in 11th Plan: 45
Projects already under construction for benefits in 12th Plan: 8 (1327MW)
Categorisation of capacity of Hydro Plants 12th Plan
Type of
Scheme
Capacity (MW) No. of Stations
ROR 16,116 77
STO 2,448 7
PSS 1,770 3
TOTAL 20,334 87
-
7/27/2019 Hydraullic turbine Man
8/18
Preparedness for 12th Plan & beyond
Hydro capacity totaling to 24,500 MW has been proposedduring the 13th Plan. A shelf of hydro projects totaling to about43,000 MW has been drawn up out of which the aboverequirement of 24,500 MW would be selected.
In addition, the requirement of capacity addition programmesin neighbouring countries namely, Bhutan (5000 MW), Nepal(1000 MW) are to be considered by the manufacturers /suppliers
It is observed that there is an appreciable increase (almost 2times) in the no. of proposed Hydro Power schemes in the12th Plan. Thus, there is a need to revisit the Manufacturing
capabilities for Plant & Equipment for Hydro Power Plants.
-
7/27/2019 Hydraullic turbine Man
9/18
ESTIMATED REQUIREMENT OF EQUIPMENT
FOR HYDRO POWER PLANTS FOR
12th & 13th PLANS
No. Equipment 12th Plan
(20,000
MW)
13th Plan
(24,500
MW)
Total
Hydro-Mechanical
1 Gates & Hoist
i. Radial Spillway Gates (set) 415 505 920
ii. Vertical lift gates (set) 630 767 1397
Electro-Mechanical2 Turbine (MW) 20,130 24,495 44,625
3 Turbine (No.) 238 286 524
4 Butterfly Valve (Set) 48 58 106
5 Main Inlet Valve (Set) 198 241 439
-
7/27/2019 Hydraullic turbine Man
10/18
ESTIMATED REQUIREMENT OF EQUIPMENT
FOR HYDRO POWER PLANTS FOR
12th & 13th PLANSNo. Equipment 12th Plan
(20,000
MW)
13th Plan
(24,500
MW)
Total
6 Digital Governor (Set) 238 286 524
7 Synchronous Generator(MVA) 22,366 27,216 49,5828 Synchronous Generator (No.) 238 286 524
9 Unit Control Board (set) 238 286 524
10 Motor & MCC (unit) 1596 1943 3539
11 Transformer(UAT & SST) MVA 267 286 553
12 Static Excitation System (set) 238 286 524
13 Dynamic Excitation System
(set)
238 286 524
14 NG cubicle incl. Tranfr, (set) 238 286 524
-
7/27/2019 Hydraullic turbine Man
11/18
-
7/27/2019 Hydraullic turbine Man
12/18
ESTIMATED REQUIREMENT OF EQUIPMENT FOR
HYDRO POWER PLANTS FOR
12th & 13th PLANS
No. Equipment 12th Plan(20,000 MW)
13th Plan(24,500 MW)
Total
20 EHV Equipment
Circuit breaker (No.) 390 515 908
Capacitor voltage transformer(CVT) (Set)
1125 1367 2492
EHV Voltage Transformer(No.) 522 640 1162
Lightning Arrestor (LA) (No.) 1344 1627 2971
Isolator (Set) 920 1120 2040
EHV Current Transformer(Set) 1318 1604 2922
21 415 V Switchgear Board (Unit) 650 791 1441
22 220/400 kV GIS Bay (No.) 167 203 370
23 EHV XLPE Cable (km) 49 60 10924 EHV Bus Duct km 22 25 47
-
7/27/2019 Hydraullic turbine Man
13/18
REQUIREMENT OF OTHER KEY INPUTS FOR
12th & 13th PLANS
Steel and cement are key inputs needed for construction of hydro powerprojects & the requirement of the same vary from project to projectdepending upon type of scheme.
For 12th Plan, the requirement corresponds to a hydro capacity of about20,000 MW & for The 13th Plan requirement is based on the proposed
programme of 24500 MW
Sl.No. Material Quantity (in million tonne)
12th Plan 13th Plan
1 Cement 19.244 23.422
2 Structure Steel 0.684 0.833
3 Reinforcement Steel 1.872 2.278
-
7/27/2019 Hydraullic turbine Man
14/18
Areas of Development Specific to Indian Industry
Creation of facility for higher sized runner castings. Presently
large size castings are beings imported.
Creation of manufacturing facilities for 220kV & 400kV Gas
Insulated Switchgear.
Creation of manufacturing facilities for 220kV & 400kV XPLE
Cables.
R&D Needs in the following fields:
Hard coatings for turbine runners & other under water parts
New materials and alloys for turbines & other under water
parts resistant to the silt damages
-
7/27/2019 Hydraullic turbine Man
15/18
Action points
To meet additional capacity requirements for 12th plan &beyond, manufacturers/ suppliers need to take appropriatesteps.
Advance action shall be taken by Project Authorities toAward Contracts for projects identified for the benefits in the12th Plan so that timely action can be taken bymanufacturers/suppliers
Qualifying requirements may be modified/ rationalized toenable financially sound new players to compete.
The project promoters should streamline, wherever required,the payment system to have better response from thesuppliers.
Placement of orders, where in few cases, has taken longertime due to various technical & other intricacies creatinguncertainty in the planning process of manufacturers, needsto be expedited.
-
7/27/2019 Hydraullic turbine Man
16/18
Action points
Tail end bunching can not be avoided. It is observed that in
11th Plan around 40% of the capacity is programmed to be
commissioned in the last half of the year 2011-12. The
erection, testing & commissioning engineers/contractors have
to plan & gear up accordingly.
Better quality control at manufacturer works would reduce the
erection as well as operational problems. Manufacturers need
to review the quality assurance programme of the E&M and HM
equipments.
Demand for Gas Insulated supplier (GIS) & XLPE Cables isexpected to increase Indigenous manufacturing of such
equipments/items need to be pursued more vigorously.
-
7/27/2019 Hydraullic turbine Man
17/18
Action points
Delivering of equipment needs to be critically verified rightfrom shop to the site store. Non-receipt of even one itemwhich is essential for commissioning may delay the wholeprocess.
Enhance the availability of O&M engineers as shortage ofoperation & maintenance engineers particularly in PowerStations located in remote/difficult areas may also becomea bottle neck in near future
-