hydraullic turbine man

Upload: manishdce09

Post on 02-Apr-2018

215 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/27/2019 Hydraullic turbine Man

    1/18

    MANUFACTURINGCAPABILITIES FOR PLANT &

    EQUIPMENT FOR HYDROPOWER PLANTS

    S.K.Kaul18thAugus t2009

  • 7/27/2019 Hydraullic turbine Man

    2/18

    SCENARIO OF 10TH PLAN

    CAPACITY ADDITION

    Sector Target (MW) Achievement

    (MW)

    Central 8742 4495

    State 4481 2691

    Private 1170 700

    Total 14393 7886

    Delay on account of Equipment supply constraint : 679 MW

  • 7/27/2019 Hydraullic turbine Man

    3/18

    Summary of ordering status of TG Sets

    of Hydro Projects in 10th Plan

    The Hydro capacity addition Target 14393 MW

    Electro-Mechanical equipments awarded 12004 MW

    Indian Suppliers

    BHEL 4945 MW

    Alstom 680 MW

    VA Tech 216 MW

    Foreign Suppliers 6163 MW

  • 7/27/2019 Hydraullic turbine Man

    4/18

    HYDRO CAPACITY ADDITION PROGRAMME

    FOR 11TH PLAN

    Central Sector 8654 MW

    State Sector 3482 MW

    Private Sector 3491 MW

    Total 15627 MW

    No. of Project 45

    No. of Units 166

    Highest unit size 250 MW

    Smallest unit size 11 MW

  • 7/27/2019 Hydraullic turbine Man

    5/18

    Summary of ordering status of TG Sets of HE

    Projects for likely benefits in 11th Plan

    The Hydro capacity addition programme: 15627 MW

    Ordering Status of T.G. Sets:

    Indian Supplier

    BHEL 6017 MW

    VA Tech 366 MW

    Alstom 339 MW

    Foreign suppliers 8905 MW

  • 7/27/2019 Hydraullic turbine Man

    6/18

    Manufacturing Capabilities of main

    indigenous manufacturers for plants &

    equipment for Hydro Power Plants

    M/s BHEL 2500 MW

    M/s Alstom 1260 MW

    M/s VA Tech order based

    M/s Voith Siemens order based

  • 7/27/2019 Hydraullic turbine Man

    7/18

    Preparedness for 12th Plan & beyond

    Candidate Hydro projects prioritised for benefits during 12th Plan: 87

    Total no. of Projects under execution in 11th Plan: 45

    Projects already under construction for benefits in 12th Plan: 8 (1327MW)

    Categorisation of capacity of Hydro Plants 12th Plan

    Type of

    Scheme

    Capacity (MW) No. of Stations

    ROR 16,116 77

    STO 2,448 7

    PSS 1,770 3

    TOTAL 20,334 87

  • 7/27/2019 Hydraullic turbine Man

    8/18

    Preparedness for 12th Plan & beyond

    Hydro capacity totaling to 24,500 MW has been proposedduring the 13th Plan. A shelf of hydro projects totaling to about43,000 MW has been drawn up out of which the aboverequirement of 24,500 MW would be selected.

    In addition, the requirement of capacity addition programmesin neighbouring countries namely, Bhutan (5000 MW), Nepal(1000 MW) are to be considered by the manufacturers /suppliers

    It is observed that there is an appreciable increase (almost 2times) in the no. of proposed Hydro Power schemes in the12th Plan. Thus, there is a need to revisit the Manufacturing

    capabilities for Plant & Equipment for Hydro Power Plants.

  • 7/27/2019 Hydraullic turbine Man

    9/18

    ESTIMATED REQUIREMENT OF EQUIPMENT

    FOR HYDRO POWER PLANTS FOR

    12th & 13th PLANS

    No. Equipment 12th Plan

    (20,000

    MW)

    13th Plan

    (24,500

    MW)

    Total

    Hydro-Mechanical

    1 Gates & Hoist

    i. Radial Spillway Gates (set) 415 505 920

    ii. Vertical lift gates (set) 630 767 1397

    Electro-Mechanical2 Turbine (MW) 20,130 24,495 44,625

    3 Turbine (No.) 238 286 524

    4 Butterfly Valve (Set) 48 58 106

    5 Main Inlet Valve (Set) 198 241 439

  • 7/27/2019 Hydraullic turbine Man

    10/18

    ESTIMATED REQUIREMENT OF EQUIPMENT

    FOR HYDRO POWER PLANTS FOR

    12th & 13th PLANSNo. Equipment 12th Plan

    (20,000

    MW)

    13th Plan

    (24,500

    MW)

    Total

    6 Digital Governor (Set) 238 286 524

    7 Synchronous Generator(MVA) 22,366 27,216 49,5828 Synchronous Generator (No.) 238 286 524

    9 Unit Control Board (set) 238 286 524

    10 Motor & MCC (unit) 1596 1943 3539

    11 Transformer(UAT & SST) MVA 267 286 553

    12 Static Excitation System (set) 238 286 524

    13 Dynamic Excitation System

    (set)

    238 286 524

    14 NG cubicle incl. Tranfr, (set) 238 286 524

  • 7/27/2019 Hydraullic turbine Man

    11/18

  • 7/27/2019 Hydraullic turbine Man

    12/18

    ESTIMATED REQUIREMENT OF EQUIPMENT FOR

    HYDRO POWER PLANTS FOR

    12th & 13th PLANS

    No. Equipment 12th Plan(20,000 MW)

    13th Plan(24,500 MW)

    Total

    20 EHV Equipment

    Circuit breaker (No.) 390 515 908

    Capacitor voltage transformer(CVT) (Set)

    1125 1367 2492

    EHV Voltage Transformer(No.) 522 640 1162

    Lightning Arrestor (LA) (No.) 1344 1627 2971

    Isolator (Set) 920 1120 2040

    EHV Current Transformer(Set) 1318 1604 2922

    21 415 V Switchgear Board (Unit) 650 791 1441

    22 220/400 kV GIS Bay (No.) 167 203 370

    23 EHV XLPE Cable (km) 49 60 10924 EHV Bus Duct km 22 25 47

  • 7/27/2019 Hydraullic turbine Man

    13/18

    REQUIREMENT OF OTHER KEY INPUTS FOR

    12th & 13th PLANS

    Steel and cement are key inputs needed for construction of hydro powerprojects & the requirement of the same vary from project to projectdepending upon type of scheme.

    For 12th Plan, the requirement corresponds to a hydro capacity of about20,000 MW & for The 13th Plan requirement is based on the proposed

    programme of 24500 MW

    Sl.No. Material Quantity (in million tonne)

    12th Plan 13th Plan

    1 Cement 19.244 23.422

    2 Structure Steel 0.684 0.833

    3 Reinforcement Steel 1.872 2.278

  • 7/27/2019 Hydraullic turbine Man

    14/18

    Areas of Development Specific to Indian Industry

    Creation of facility for higher sized runner castings. Presently

    large size castings are beings imported.

    Creation of manufacturing facilities for 220kV & 400kV Gas

    Insulated Switchgear.

    Creation of manufacturing facilities for 220kV & 400kV XPLE

    Cables.

    R&D Needs in the following fields:

    Hard coatings for turbine runners & other under water parts

    New materials and alloys for turbines & other under water

    parts resistant to the silt damages

  • 7/27/2019 Hydraullic turbine Man

    15/18

    Action points

    To meet additional capacity requirements for 12th plan &beyond, manufacturers/ suppliers need to take appropriatesteps.

    Advance action shall be taken by Project Authorities toAward Contracts for projects identified for the benefits in the12th Plan so that timely action can be taken bymanufacturers/suppliers

    Qualifying requirements may be modified/ rationalized toenable financially sound new players to compete.

    The project promoters should streamline, wherever required,the payment system to have better response from thesuppliers.

    Placement of orders, where in few cases, has taken longertime due to various technical & other intricacies creatinguncertainty in the planning process of manufacturers, needsto be expedited.

  • 7/27/2019 Hydraullic turbine Man

    16/18

    Action points

    Tail end bunching can not be avoided. It is observed that in

    11th Plan around 40% of the capacity is programmed to be

    commissioned in the last half of the year 2011-12. The

    erection, testing & commissioning engineers/contractors have

    to plan & gear up accordingly.

    Better quality control at manufacturer works would reduce the

    erection as well as operational problems. Manufacturers need

    to review the quality assurance programme of the E&M and HM

    equipments.

    Demand for Gas Insulated supplier (GIS) & XLPE Cables isexpected to increase Indigenous manufacturing of such

    equipments/items need to be pursued more vigorously.

  • 7/27/2019 Hydraullic turbine Man

    17/18

    Action points

    Delivering of equipment needs to be critically verified rightfrom shop to the site store. Non-receipt of even one itemwhich is essential for commissioning may delay the wholeprocess.

    Enhance the availability of O&M engineers as shortage ofoperation & maintenance engineers particularly in PowerStations located in remote/difficult areas may also becomea bottle neck in near future

  • 7/27/2019 Hydraullic turbine Man

    18/18

    THANKS