hyspec instrument: status and performance m. hagen neutron facilities development division, sns, oak...

10
HYSPEC Instrument: Status and Performance M. Hagen Neutron Facilities Development Division, SNS, Oak Ridge National Lab. W.J. Leonhardt and A. Ruga Condensed Matter Physics & Materials Science, Brookhaven National Lab.

Upload: dinah-golden

Post on 24-Dec-2015

219 views

Category:

Documents


1 download

TRANSCRIPT

Page 1: HYSPEC Instrument: Status and Performance M. Hagen Neutron Facilities Development Division, SNS, Oak Ridge National Lab. W.J. Leonhardt and A. Ruga Condensed

HYSPEC Instrument:Status and Performance

M. HagenNeutron Facilities Development Division,

SNS, Oak Ridge National Lab.

W.J. Leonhardt and A. Ruga Condensed Matter Physics & Materials Science,

Brookhaven National Lab.

Page 2: HYSPEC Instrument: Status and Performance M. Hagen Neutron Facilities Development Division, SNS, Oak Ridge National Lab. W.J. Leonhardt and A. Ruga Condensed

OAK RIDGE NATIONAL LABORATORYU. S. DEPARTMENT OF ENERGY

2

Instrument Performance by Phase

Page 3: HYSPEC Instrument: Status and Performance M. Hagen Neutron Facilities Development Division, SNS, Oak Ridge National Lab. W.J. Leonhardt and A. Ruga Condensed

OAK RIDGE NATIONAL LABORATORYU. S. DEPARTMENT OF ENERGY

3

Overview

CVI

Shutter

External Building

Control Cabin

Detector VesselSample

Chopper Box B

Drum Shield

Chopper Box A

HDCShielding

Curved Beam Guide

Concrete Shielding

Page 4: HYSPEC Instrument: Status and Performance M. Hagen Neutron Facilities Development Division, SNS, Oak Ridge National Lab. W.J. Leonhardt and A. Ruga Condensed

OAK RIDGE NATIONAL LABORATORYU. S. DEPARTMENT OF ENERGY

4

External building

Share common foundationslab with BL13 (FnPB)

Year 1 – Foundation slab+ HYSPEC building

Year 2 – FnPB building

HYSPEC specificationsare done.

FnPB specifications arealmost done.

A&E bids in July/August.

Page 5: HYSPEC Instrument: Status and Performance M. Hagen Neutron Facilities Development Division, SNS, Oak Ridge National Lab. W.J. Leonhardt and A. Ruga Condensed

OAK RIDGE NATIONAL LABORATORYU. S. DEPARTMENT OF ENERGY

5

Page 6: HYSPEC Instrument: Status and Performance M. Hagen Neutron Facilities Development Division, SNS, Oak Ridge National Lab. W.J. Leonhardt and A. Ruga Condensed

OAK RIDGE NATIONAL LABORATORYU. S. DEPARTMENT OF ENERGY

6

Drum Shield

Sample

Polarization Analyzer or

Radial Collimator

Sample Stage

Detector Vessel

Focusing Crystals (inside)

Page 7: HYSPEC Instrument: Status and Performance M. Hagen Neutron Facilities Development Division, SNS, Oak Ridge National Lab. W.J. Leonhardt and A. Ruga Condensed

OAK RIDGE NATIONAL LABORATORYU. S. DEPARTMENT OF ENERGY

7

Non-polarizing

Polarizing (Heusler)

Ordered 33 crystals from ILLFirst 11 in December 2008Second 11 in June 2009Final 11 in December 2009

Page 8: HYSPEC Instrument: Status and Performance M. Hagen Neutron Facilities Development Division, SNS, Oak Ridge National Lab. W.J. Leonhardt and A. Ruga Condensed

OAK RIDGE NATIONAL LABORATORYU. S. DEPARTMENT OF ENERGY

8

Page 9: HYSPEC Instrument: Status and Performance M. Hagen Neutron Facilities Development Division, SNS, Oak Ridge National Lab. W.J. Leonhardt and A. Ruga Condensed

OAK RIDGE NATIONAL LABORATORYU. S. DEPARTMENT OF ENERGY

9

IDT Executive Committee Meeting2nd April 2007, CNMS, ORNL

Peter Allenspach (PSI), Rob McQueeney (Ames/Iowa), Jim Rhyne (LANL),Steve Shapiro (BNL), Igor Zaliznyak (BNL)

SINGScheduleEngineering designBuildingsProcurementsPolarization – mirrors & 3He

Page 10: HYSPEC Instrument: Status and Performance M. Hagen Neutron Facilities Development Division, SNS, Oak Ridge National Lab. W.J. Leonhardt and A. Ruga Condensed

OAK RIDGE NATIONAL LABORATORYU. S. DEPARTMENT OF ENERGY

10

Summary

• Design is continuing Completed = primary beamline (choppers, guides, shielding) Current = drum shield system Future = sample stage, detector vessel, 3He polarization analyzer

• Procurements = CVI, BSI, T0 chopper, Heusler crystals, (A&E drawings for building)

• Installed = CVI, BSI, 6-15m poured in place