i-65/i-70 north split project...north split interchange indot is preparing an environmental study...

34
I-65/I-70 North Split Project Project Update & CSS Neighborhood Workshop April 2019

Upload: others

Post on 21-Aug-2021

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: I-65/I-70 North Split Project...North Split Interchange INDOT is preparing an environmental study for the North Split interchange • Where I-65 and I-70 meet at the northeast corner

I-65/I-70 North Split ProjectProject Update & CSS Neighborhood WorkshopApril 2019

Page 2: I-65/I-70 North Split Project...North Split Interchange INDOT is preparing an environmental study for the North Split interchange • Where I-65 and I-70 meet at the northeast corner

North Split InterchangeINDOT is preparing an environmental study for the North Split interchange

• Where I-65 and I-70 meet at the northeast corner of downtown inner loop

• Constructed 40 to 50 years ago• Second-most heavily-traveled interchange in the state –

214,000 vehicles per day• Project goals:

• Replace deteriorated pavement and bridges• Improve safety• Improve traffic flow

Page 3: I-65/I-70 North Split Project...North Split Interchange INDOT is preparing an environmental study for the North Split interchange • Where I-65 and I-70 meet at the northeast corner

North Split ProjectMajor Project Milestones

• September, 2017 – Project Initiation• May, 2018 – System-Level Analysis of Downtown

Interstates• September, 2018 – Alternatives Screening Report• March, 2019 – Context Sensitive Solutions (CSS) process• Early 2020 – Environmental Assessment complete• 2021 - 2022 – Project Construction

Page 4: I-65/I-70 North Split Project...North Split Interchange INDOT is preparing an environmental study for the North Split interchange • Where I-65 and I-70 meet at the northeast corner

Environmental Context

North Split Project Area• Historic Districts• Park Property• Monon Greenway• Cultural Trail• CSX Railroad

Page 5: I-65/I-70 North Split Project...North Split Interchange INDOT is preparing an environmental study for the North Split interchange • Where I-65 and I-70 meet at the northeast corner

Physical Condition and Safety

Deteriorated pavement and bridge conditions. • Constructed in the 1960s and 1970s –

pavement is past its life expectancy

• Bridge conditions are poor and getting worse:

Under 5 years of life (11 bridges)

5 - 10 years of life (16 bridges)

• Over 1,600 crashes from 2012 to 2016

• Most Crashes Rear-end and Sideswipe

Page 6: I-65/I-70 North Split Project...North Split Interchange INDOT is preparing an environmental study for the North Split interchange • Where I-65 and I-70 meet at the northeast corner

Safety – High Crash Locations

Top 4 Crash Locations

Page 7: I-65/I-70 North Split Project...North Split Interchange INDOT is preparing an environmental study for the North Split interchange • Where I-65 and I-70 meet at the northeast corner

Safety - Weaving Areas

• Highest number of crashes are on west leg of the interchange, in weaving areas:

Most frequent crash type: • Rear-end, followed by sideswipe

Pennsylvania Street Exit Ramp Delaware Street Entrance Ramp

Most frequent crash type: • Sideswipe, followed by rear-end

Page 8: I-65/I-70 North Split Project...North Split Interchange INDOT is preparing an environmental study for the North Split interchange • Where I-65 and I-70 meet at the northeast corner

• Replaces all pavement and bridges• Improves safety at the most hazardous

locations• Removes the worst bottlenecks• More compact interchange• Does not add through lanes• Within existing right-of-way• Minimizes outside walls• Two restricted ramp movements

• Delaware ramp to I-70 only• Pennsylvania exit from I-65 only

Preliminary Preferred Alternative

3/26/19

Page 9: I-65/I-70 North Split Project...North Split Interchange INDOT is preparing an environmental study for the North Split interchange • Where I-65 and I-70 meet at the northeast corner

North Split West Leg

Current

Proposed

Page 10: I-65/I-70 North Split Project...North Split Interchange INDOT is preparing an environmental study for the North Split interchange • Where I-65 and I-70 meet at the northeast corner

North Split Interchange Area

I-70

I-65

I-70I-65

Current Proposed

Page 11: I-65/I-70 North Split Project...North Split Interchange INDOT is preparing an environmental study for the North Split interchange • Where I-65 and I-70 meet at the northeast corner

North Split South Leg

I-65 I-70I-70

I-65

Current Proposed

Page 12: I-65/I-70 North Split Project...North Split Interchange INDOT is preparing an environmental study for the North Split interchange • Where I-65 and I-70 meet at the northeast corner

North Split Project

Reconstruct the Interchange• Replace pavement and bridges• Address major safety problems• Eliminate bottlenecks to improve level of service

• Provide smaller footprint and modern design

Consider the Neighborhood Context• Do not add through lanes• Minimize outside walls• Enhance neighborhood integration• Provide neighborhood connectivity

Page 13: I-65/I-70 North Split Project...North Split Interchange INDOT is preparing an environmental study for the North Split interchange • Where I-65 and I-70 meet at the northeast corner

CSS Neighborhood Workshop

Page 14: I-65/I-70 North Split Project...North Split Interchange INDOT is preparing an environmental study for the North Split interchange • Where I-65 and I-70 meet at the northeast corner

CSS Process

What is CSS?“Context Sensitive Solutions and Design" (CSS/D) is a collaborative, interdisciplinary decision‐making process and design approach that involves all stakeholders to develop a transportation facility that fits 

its physical setting.‐ US Department of Transportation Federal Highway Administration

Page 15: I-65/I-70 North Split Project...North Split Interchange INDOT is preparing an environmental study for the North Split interchange • Where I-65 and I-70 meet at the northeast corner

CSS Process

What are we trying to do with our process?Develop a series of design recommendations that aid the integration of 

the new interchange (the current Preferred Alternative) into the surrounding community.

Page 16: I-65/I-70 North Split Project...North Split Interchange INDOT is preparing an environmental study for the North Split interchange • Where I-65 and I-70 meet at the northeast corner

CSS Process

What are some parameters of the                 CSS analysis?

• Interchange project• Needs to be constructed in the next 3 years• Must connect to existing elevated interstates• INDOT is open to partnerships• Enhancements evaluated with maintenance in mind

Page 17: I-65/I-70 North Split Project...North Split Interchange INDOT is preparing an environmental study for the North Split interchange • Where I-65 and I-70 meet at the northeast corner

CSS Process

What are we trying to understand with our process?

Character and themesTreatment typologyBasic materials

Community connectionsCommunity response 

Page 18: I-65/I-70 North Split Project...North Split Interchange INDOT is preparing an environmental study for the North Split interchange • Where I-65 and I-70 meet at the northeast corner

CSS Process: What will we be examining?

Page 19: I-65/I-70 North Split Project...North Split Interchange INDOT is preparing an environmental study for the North Split interchange • Where I-65 and I-70 meet at the northeast corner

CSS Process: What will we be examining?

Page 20: I-65/I-70 North Split Project...North Split Interchange INDOT is preparing an environmental study for the North Split interchange • Where I-65 and I-70 meet at the northeast corner

CSS Process: What will we be examining?

Page 21: I-65/I-70 North Split Project...North Split Interchange INDOT is preparing an environmental study for the North Split interchange • Where I-65 and I-70 meet at the northeast corner

CSS Process: What will we be examining?

Page 22: I-65/I-70 North Split Project...North Split Interchange INDOT is preparing an environmental study for the North Split interchange • Where I-65 and I-70 meet at the northeast corner

CSS Process: What will we be examining?

Page 23: I-65/I-70 North Split Project...North Split Interchange INDOT is preparing an environmental study for the North Split interchange • Where I-65 and I-70 meet at the northeast corner

CSS Process

North Split CSS Design Process

Part 1:  VisioningPurpose is to identify overall design vision, specifically in terms of character and theme, and to establish the type and extents of 

applications for consideration.

Page 24: I-65/I-70 North Split Project...North Split Interchange INDOT is preparing an environmental study for the North Split interchange • Where I-65 and I-70 meet at the northeast corner

CSS Process

North Split CSS Design Process

Part 2:  Develop Preliminary Design Treatments

Begin to show how character and theme can translate to design treatment concepts.

Page 25: I-65/I-70 North Split Project...North Split Interchange INDOT is preparing an environmental study for the North Split interchange • Where I-65 and I-70 meet at the northeast corner

CSS Process

North Split CSS Design Process

Part 3:  Develop CSS Design Guidelines Package

Finalize conceptual treatments into design guidelines.

Page 26: I-65/I-70 North Split Project...North Split Interchange INDOT is preparing an environmental study for the North Split interchange • Where I-65 and I-70 meet at the northeast corner

CSS Process

Page 27: I-65/I-70 North Split Project...North Split Interchange INDOT is preparing an environmental study for the North Split interchange • Where I-65 and I-70 meet at the northeast corner

Next Steps…

• Continue to collect and document  the Inventory and Assessment of the surrounding context

• Neighborhood Workshops

CSS Process

Page 28: I-65/I-70 North Split Project...North Split Interchange INDOT is preparing an environmental study for the North Split interchange • Where I-65 and I-70 meet at the northeast corner

Workshop Orientation ‐ Station 1: CSS OverviewCSS Process

Page 29: I-65/I-70 North Split Project...North Split Interchange INDOT is preparing an environmental study for the North Split interchange • Where I-65 and I-70 meet at the northeast corner

Workshop Orientation ‐ Station 2: ContextCSS Process

Page 30: I-65/I-70 North Split Project...North Split Interchange INDOT is preparing an environmental study for the North Split interchange • Where I-65 and I-70 meet at the northeast corner

CSS Process

Workshop Orientation ‐ Station 2: Context

TELL US: Feedback

Opportunity

Page 31: I-65/I-70 North Split Project...North Split Interchange INDOT is preparing an environmental study for the North Split interchange • Where I-65 and I-70 meet at the northeast corner

Workshop Orientation ‐ Station 3: PrioritiesCSS Process

Page 32: I-65/I-70 North Split Project...North Split Interchange INDOT is preparing an environmental study for the North Split interchange • Where I-65 and I-70 meet at the northeast corner

CSS Process

Workshop Orientation ‐ Station 3: Priorities

TELL US: Feedback

Opportunity

Page 33: I-65/I-70 North Split Project...North Split Interchange INDOT is preparing an environmental study for the North Split interchange • Where I-65 and I-70 meet at the northeast corner

CSS Process

Workshop Orientation – Feedback Form

TELL US: Feedback

Opportunity

Page 34: I-65/I-70 North Split Project...North Split Interchange INDOT is preparing an environmental study for the North Split interchange • Where I-65 and I-70 meet at the northeast corner

Project Information: www.northsplit.comSubmit Feedback: [email protected]

CONTACT:Ali HernandezPublic InvolvementPO Box 44141Indianapolis, IN 46244Phone: 317.749.0309

WORKSHOP OPEN HOUSE