Design, Engineering, Finance, Construction, operation and Maintenance of Access controlled Highway on Bangalore – Nelamangala section of NH-4 from Km 10+000 to 29+500 in the state of Karnataka on Build, Operate and Transfer Basis (BOT).
I N D E P E N D E N T E N G I N E E R
C O N S U L T I N G E N G I N E E R S G R O U P L T D
INDEX
Sl No Description Page Nos
1 Preamble 01 – 03
2 Project Details 04 – 05
3 Summary of Current Months Maintenance 06 – 07
4 Critical issues and Action taken 08 – 10
5 Safety Management on Project Highway 11 – 15
6 IC and Concessionaire Management structure 16 -17
7 IC Inspection Report (O&M) 18 – 22
8 Status of Damage of Action taken 23 – 23
9 Recommendations 24 – 24
Annexures
I Accident Report 25 – 25
II Weather Report 26 – 26
III QC Tests 27 – 27
IV Emergency Phone Numbers 28 – 28
V Site Instructions 29 – 29
VI Site Photographs 30 – 32
Consultancy Services as Independent Engineers for Access controlled highway M/s CEG Ltd
From Bangalore to Nelamangala section of NH-4 (Km 10.00 to Km 29.50) Bangalore
BANGALORE-NELAMANGALA SECTION OF NH4 PROJECT
(KM 10+000 TO KM 29+500)
END Km: 29+500
START Km: 10+000
Consultancy Services as Independent Engineers for Access controlled highway M/s CEG Ltd
From Bangalore to Nelamangala section of NH-4 (Km 10.00 to Km 29.50) Bangalore
1 O & M Progress Report August-2017
1.0 PREAMBLE
BACKGROUND
NHAI under took the development of Access Control Highway from Km 10.00 to Km
29.50 of Bangalore – Nelamangala Section of NH-4, in the State of Karnataka on Build,
Operate and Transfer (BOT) basis through a Concessionaire under NHDP Phase III
Program of development. NHAI awarded the works to the Concessionaire, M/s
Navayuga Bengalooru Tollway Pvt Limited in May 2007 with a concession period of 20
years.
The works consists of construction of a stretch length of 19.5 km. as access Control
Highway. Out of this a length of 4.5 kms from Km.10.00 to Km.14.50 is a 4-lane elevated
highway and 15 kms of length from Km.14.50 to Km.29.50 is 6-lanes Access Control
Stretch at ground level.
Aarvee - Bonifica JV was appointed by NHAI as Independent Consultant (IC) to supervise
the development of Access controlled highway and maintenance of existing highway
during construction stage. The project highway along with the facilities except as per
details given below ITEM – 4 (Completion Certificate of the Project Highway) was
completed by the Concessionaire on 10th
December 2010 and accordingly the IC issued
the Provisional completion certificate on 12th
December 2010 along with the punch list in
compliance with the provision of the Concession Agreement (CA).
The Project Highway from Km.10.00 to Km.29.50 of Bangalore-Nelamangala section of
NH4 has been under Commercial operations since 10th
December 2010 and the IC (M/s
Aarvee –Bonifica JV) has been monitoring the completion of the works and the operation
and maintenance (O&M) activities up till 31 December 2011.
Pursuant to the provision in the Concessionaire Agreement, NHAI appointed M/s Unihorn
India Pvt Ltd, as Independent Consultant w.e.f April 2012 to October 2015 to monitor the
O&M activities after the completion of the services of M/s Aarvee-Bonifica JV on 31
December 2011.
Now, NHAI has appointed M/s Consulting Engineers Group Ltd. as Independent
Engineers to monitoring the O&M activities of the project Highway with its
commencement of services w.e.f from 19 October 2015.
1.1 Monitoring and Supervision during Operation & Maintenance of the Project
Highway.
In accordance to the various requirement of the Clause 19.2, IC during his monthly
inspection report has pointed out defects and deficiencies for immediate rectification by
the Concessionaire on the Project Highway in the O&M period. The Concessionaire has
started to carryout some of the rectification works and is yet to submit para wise
compliance.
Consultancy Services as Independent Engineers for Access controlled highway M/s CEG Ltd
From Bangalore to Nelamangala section of NH-4 (Km 10.00 to Km 29.50) Bangalore
2 O & M Progress Report August-2017
1.2 Operation of Toll Plazas
At present the six lanes provided for collection of toll fees from vehicles in Toll Plaza at
Km.14.825 and at Km.26.050. On many occasions, there are long queue more than the
permissible of 5 vehicles (5 vehicles/lane max. to be allowed as per the Agreement). It is found that the present six lanes found not sufficient at present may leads to serious
problems in managing the traffic at Toll plazas.
The concessionaire has been reminded to conduct the traffic survey.
2. Completion Certificate of the Project Highway
2.1 The Concessionaire has completed the works included in the punch list except the
following:
i. Shoulders on Service Roads
All works on service roads and earthen shoulder have been completed except a length
of 1.5Km, where land is not available for shoulder works. Details are provided in
Table 1 (chapter-3).
ii. Outer drain along ROW
The drain along ROW on both side of Project Highway has been completed except the
stretches where additional land required has not been made available by NHAI so far.
The total length remains to be constructed is 4.727 km. out of 30.660Km. The details
are provided in Table 1 (chapter-3).
iii. Head walls of Culverts The head walls of some of the culverts could not be completed due to dispute in the
ownership of the land and resistance of the people. The details of such culverts are in
Table 2 (chapter-3).
iv. Truck Lay Bye
The Truck lay-Bye with all the facilities could not be constructed for want of land
acquisition by NHAI.
PD/PIU-NHAI requested the details regarding land acquisition/possession certificate of
the above land for which concessionaire could not take up the work. The issue was
discussed in PD/PIU- NHAI office in detail with SLAO, concessionaire and IE to get the
above details. It was decide in the meeting to have a site inspection along with SLAO,
concessionaire and IE to have clarity on the issue. The verification of land acquisition /
possession was verified at site. The issue is yet to be resolved.
2.2 Deviation in Proposed Project Facilities:
The than IC M/s Unihorn India has observed during the inspection that some changes
from the Proposed Project Facilities provided in the Schedule ‘C’ of the Concession
Agreement have been made during the execution at site in the provision of Lay-Bye at
Elevated section of the Project Highway. The Concessionaire has intimated through his
letter of 23rd
August 2012 that Lay Bye has been provided at location as per the scope,
whereas IC has observed that the Concessionaire has not provided the length of Lay Bye
as per scope of the Concession Agreement and accordingly the PIU NHAI and the
Concessionaire has been informed by IC’s letter of 10th
September 2012.
Consultancy Services as Independent Engineers for Access controlled highway M/s CEG Ltd
From Bangalore to Nelamangala section of NH-4 (Km 10.00 to Km 29.50) Bangalore
3 O & M Progress Report August-2017
3. CHANGE OF SCOPE OF WORKS
Detailed Status of Change of Scope of work orders issued by NHAI is given in tables
attached in Chapter-4.
3.1 Proposed VUP in front of BIEC Bangalore - Nelamangala Section of NH-4
from Km.10+000 to Km.29+500.from Km.10+000 to Km.29+500.
Government of Karnataka proposed the requirement of Vehicle Under pass near BIEC,
and the same was intimated by the NHAI for submission of detailed proposal of 2X12
Mtrs VUP in front of BIEC. Secretary, PWD, Government of Karnataka finalized the
proposal or Rs: 11.95 crores with the cost sharing basis, in that 50% of the share borne by
the Government of Karnataka and the other 50% has to be borne by the NHAI.
Concessionaire has been submitted their final cost estimate amounting to
Rs.15,70,88,405/-. IC (M/s Consulting Engineers Group) checked, scrutinized and review
of the proposal based on design incorporations, drawings and SOR of NH-2014/15, the
total re-revised cost of the 'COS' proposal works out to Rs.15,63,51,198/-. The GOK has
deposited an amount of Rs: 5.975 Cr out of Rs:7,81,75,799/- and persuasion is being done
for the deposition of balance amount of Rs: 1,84,25,520/- for the COS proposal for
construction of VUP.
NHAI RO has issued a COS notice vide their letter no: NHAI/RO-
BNG/11018/13/2016/1436, dt: 15.07.2016 with a final cost of Rs: 15,63,51,198/-.
Concessionaire has commenced the widening of Service Road (BHS) on 31 September
2016 in lieu of Construction of VUP at BIEC.
The CGM(T)-RO and PD-PIU Bangalore asked for re submission of final detailed re-
revised cost estimation vide their letter no: NHAI/RO-BNG/11018/13/2016/4063
Dt:09.03.2017, accordingly the concessionaire submitted the re-revised cost estimate vide
letter no: NBTPL/O&M/CEG/2016-17/288 Dt:22.03.2017.
The re-revised final detailed cost estimation scrutinized and finalized The Total construction cost of Rs: 26,59,52,271/-. The component wise breakup as follows and
submitted the same vide our letter no: CEG/BNG-NEL/NH-4/O&M/2016-17/379 Dt:
22.03.2017.
PD-PIU Bangalore instructed to start the construction of VUP without further delay through their letter no: NHAI160125/01/15-16/PIU-BNG/158 DT: 22.04.2017.
3.2 Construction 4 Nos of additional FOB
Based on directions of NHAI PIU, the Concessionaire transmitted the estimate for
construction of the 4 additional FOBs, along with their justification. IC (M/s Unihorn
India) has examined the estimate and the same has been transmitted to PD NHAI PIU
Bangalore on 25th
September 2012.
*****
Consultancy Services as Independent Engineers for Access controlled highway M/s CEG Ltd
From Bangalore to Nelamangala section of NH-4 (Km 10.00 to Km 29.50) Bangalore
4 O & M Progress Report August-2017
2.0 PROJECT DETAILS
Project : Design, Engineering, Finance, Construction, operation and
Maintenance of Access controlled Highway on Bangalore –
Nelamangala section of NH-4 from Km 10+000 to 29+500 in
the state of Karnataka on Build, Operate and Transfer Basis
(BOT).
Client / Employer : National Highways Authority of India G-5&6, Sector – 10,
Dwarka, New Delhi – 110075.
Phone: 011-25074100 / 25074200, Fax: 011-25093501.
NHAI-PIU Office : National Highways Authority of India
Project Implementation Unit, Survey No13, 14th Km,
Nagasandra, Bangalore–Tumkur Road (NH-4),
Bengaluru - 560 073. Phone: - 080- 28394403,
Fax: 080-28394383. E-MAIL [email protected].
Independent Consultant : M/s Aarvee Associate & Bonifica Spa JV
(2 Years Construction & One year O&M)
(November 2007 to December 2010)
: M/s Unihorn India Pvt. Ltd
(O&M Consultants- April 2012 to October 2015)
: M/s Consulting Engineers Group Ltd.
(O&M Consultants from October 2015 onwards)
EPC Contractor : M/s. Navayuga Engineering Company,
Hyderabad – 500034.
Concessionaire (SPV) : M/s. Navayuga Bengalooru Tollway Private Limited,
Hyderabad –500034.
DPR Consultant : M/s. SPAN Consultants Pvt. Ltd. New Delhi
*****
Consultancy Services as Independent Engineers for Access controlled highway M/s CEG Ltd
From Bangalore to Nelamangala section of NH-4 (Km 10.00 to Km 29.50) Bangalore
5 O & M Progress Report August-2017
2.1 SALIENT FEATURES:
Date of Concession Agreement : 09th May 2007 Period of Construction : 24 Months Appointed date : 05th November 2007 Actual Completion Date : 10th December 2010 Delay in Completion of Works : 367 Days Commercial Operation Date (COD) : 10thDecember 2010 Estimated Project Cost : 445 Crores (Basic Cost) Actual Project Cost : 718.59 crores Total Concession Period : 20 Years from Appointed Date
(i.e from 05/11/2007 to 04/11/2027)
Project Length : 19.50 Km.
(Including 4.5km Elevated Highway) No of PUPs : 13 Nos No of VUPs : 06 Nos No. of Subways for pedestrian : 03 Nos No of Major Junctions : 08 Nos No of Bus Bays : 32 Nos (16+16) No of Toll Plazas : 06 Nos Elevated Highway : 4.50 Km
(From km 10+000 to km 14+500) No of Box Culverts : 09 Nos
No of Pipe Culverts : 27 Nos No of Flyovers : 01 No
No of Minor Bridges : 01 No ROB : 01 No FOB : 08 Nos
*****
Consultancy Services as Independent Engineers for Access controlled highway M/s CEG Ltd
From Bangalore to Nelamangala section of NH-4 (Km 10.00 to Km 29.50) Bangalore
6 O & M Progress Report August-2017
3.0 SUMMARY OF CURRENT MONTH MAINTENANCE:
a) Periodic Renewal work is in progress which is going to complete by the end of September
2017 as per Concessionaire’s programme.
b) As a part of Periodic Renewal work Milling of road surface is completed.
c) As per the discussion held with NHAI PD Milling material to be used for Service road
shoulders rectification by blending gravel in 60:40 ratios.
d) Shoulder rectifications works has been started in some locations where they have dumped the
blended milling material and just graded and not rolled which was highlighted to rectify as
per the NHAI norms, concessionaire agrees to do the same.
3.1 STATUS OF CHANGE OF SCOPE OF WORKS:
3.1.1 Proposed Construction of VUP in front of BIEC at Km. 17.200
a) BC laying at LHS from Km.17.080 to Km.17.261 & Km 17.280 to Km 17.540 and RHS
Km.17.500 to Km.17.235 is completed.
b) BC laying on Extension of Box Culvert @ Km.17.400 is completed.
c) Dismantling of New jersey concrete Crash Barrier on RHS side from Km16+939 to
Km16+979 & Km17+470 to Km17+560.
3.1.2 Installation of WIMS at all Toll plaza & SWB at TP-1 (K.14.825) & TP-6 (Km.26.050)
a) At TP-1 installation of WIM’S on all available eight lanes had been completed.
b) At TP-6 installation of WIMS on all available seven lanes had been completed.
c) At TP-1 & TP-6 Static Weigh Bridge platform had been installed ramp work along with
control room is completed.
Consultancy Services as Independent Engineers for Access controlled highway M/s CEG Ltd
From Bangalore to Nelamangala section of NH-4 (Km 10.00 to Km 29.50) Bangalore
7 O & M Progress Report August-2017
PUNCH LIST BALANCE WORKS:
TABLE - 1
No Activity Unit Scope of
work Balance Locations Remarks
1
Earthen
Shoulder along
Service Roads
Rm 39000 1500
meters
RHS; 10+580 to 11+090, 12+664 to 12+767, &
LHS: 10+580 to 11+028, 11+097 to 11+201,
12+215 to 12+319, 12+422 to 12+653.
Land not made
available by
NHAI
2
Truck Lay bye
with all
facilities
No 1 1 17+350 RHS
Land not made
available by
NHAI
3 Lined drain Rm 30,660
4727
meters
LHS- 10+790 to 10+960, 12+022 to 13+200,
13+340 to 13+580, 17+300 to 17+330, 17+750
to 17+800, 17+900 to 17+920, 17+975 to
18+050, 18+380 to 18+652, 24+600 to 24+630,
25+360 to 25+375
RHS:- 10+820 to 10+880, 10+910 to 10+920,
11+000 to 11+050, 11+650 to 11+700, 12+020
to 13+380, 16+035 to 16+360, 17+800 to
17+850, 21+700 to 21+735, 21+800 to 21+920,
22+370 to 22+390,22+800 to 23+150, 26+440
to 26+525 , 27+700 to 27+832.
Land not made
available by
NHAI
Status of Head Walls Construction (culverts)
TABLE - 2 SNo. Location Balance Work of Head Walls Action to be taken
1 10+590 LHS Land acquisition required
2 11+200 LHS Land acquisition required
3 12+480 LHS Land acquisition required
4 13+030 LHS Land acquisition required
5 13+070 LHS Land acquisition required
6 14+478 LHS Land acquisition required
7 15+081 LHS Land acquisition required
8 15+780 RHS Land acquisition required
9 17+220 LHS Land acquisition required
10 18+100 RHS Land acquisition required
11 18+632 LHS Land acquisition required
12 18+632 RHS Land acquisition required
13 19+589 LHS Land acquisition required
14 21+733 RHS Land acquisition required
15 21+843 RHS Land acquisition required
16 23+081 RHS Land acquisition required
17 25+456 LHS Land acquisition required
*****
Consultancy Services as Independent Engineers for Access controlled highway M/s CEG Ltd
From Bangalore to Nelamangala section of NH-4 (Km 10.00 to Km 29.50) Bangalore
8 O & M Progress Report August-2017
4.0 CRITICAL ISSUES AND ACTION TAKEN
CHANGE OF SCOPE:
Status of Change of Scope of work orders issued by NHAI is given below:
Sl.
No Location
Date of issue
of COS by
NHAI
Amount in
INR
Financial implication in %
on the
Status
Estimated
Project cost
of Rs:445
Crs,
Actual
Project cost
of
Rs:718.59
Crs
1 Subway at km 16+035 27.05.2010 59,49,000 0.134 0.0827 Completed
2 Subway at km 23+195 27.05.2010 1,26,09,000 0.283 0.175 Completed
3 Interior Works to CGM office 22.02.2011 29,92,357 0.067 0.0416 Completed
4
Additional Interior Works to
CGM office and PIU
Bangalore
04.04.2011 7,63,825 0.017 0.0106 Completed
5 ROB at 28+400 24.11.2011 7,11,44,693 1.60 0.990 Completed
6 Subway at Km 18+740 14.02.2013 3,12,35,351 0.70 0.434 Completed
The following additional Change of Scope of works are completed at site and its financial
implication have not been finalized by NHAI. (As reported in the available records of previous
IE M/s Unihorn India Pvt Ltd.,
Sl.
No Location Date
Amount in
INR
Financial
implication in %
on the Project
cost
Status
1 FOB 8 Numbers 01.04.2010 Not finalized Not finalized Completed
2 Merging of Service Road at Km
29+500 07.09.2011 Not finalized Not finalized Completed
3 Interior Works to PD office 24.06.1011 Not finalized Not finalized Completed
Consultancy Services as Independent Engineers for Access controlled highway M/s CEG Ltd
From Bangalore to Nelamangala section of NH-4 (Km 10.00 to Km 29.50) Bangalore
9 O & M Progress Report August-2017
Now proposed:
Sl.
No Location
Date of issue of
COS by NHAI Amount in INR
Financial implication
in % on the
Estimated Project
cost of Rs:445 Crs,
Status
1 Installation of WIM &
SWB
28-07-2016
2,85,92,000 0.64% Work under
Progress
2 VUP at BIEC 21-04-2017 26,59,52,571 6.01% Work under
Progress
3
Safety Aspects
(Providing MS railing in
Central Median)
Awaited from
NHAI 1,90,39,068 0.42%
Approved by
Competent
Authority
4
Proposal for widening of
LHS S/R from 10+600 to
km 14+875 on NH-4
Awaited from
NHAI 8,45,26,333 1.89%
Approved by
Competent
Authority
5 Construction of Additional
4 Nos FOBs
Awaited from
NHAI 3,96,00,000 0.89%
Proposal
submitted to
NHAI
4.1 Construction of 8 No FOBs:
All the 8 FOBs have been completed by the Concessionaire and the detailed estimate
received from the Concessionaire has been submitted to NHAI.
4.2. Construction 4 No additional FOB:
Based on the directions of NHAI PIU, the Concessionaire submitted the estimate for
construction of the 4 additional FOBs, along with their justification .The than IC M/s Unihorn
India had examined the estimate and the same was submitted to PD NHAI PIU Bangalore on
25th
September 2012.
The CGM(T)-RO and PD-PIU Bangalore asked for re submission of final detailed re-revised
cost estimation vide their RO letter no: NHAI/RO-BNG/11018/12/2015/2655 Dt:09.11.2015,
and PIU letter no: NHAI/160125/01/15-16/PIU-BNG/3443 Dt:15.12.2015 accordingly the
concessionaire has been submitted the re-revised cost estimate for each FOB vide letter nos:
1)1235/RO/COS/CEG/14 Dt:20.07.2017. 2) 1235/RO/COS/CEG/15 Dt:20.07.2017
3) 1235/RO/COS/CEG/16 Dt:20.07.2017. 4) 1235/RO/COS/CEG/17 Dt:20.07.2017
The re-revised final detailed cost estimation for FOBs scrutinized and finalized that the total
construction cost of 4 additional FOBs with a sum of Rs: 3,96,00,000/- (for each FOB
costing of Rs: .99,00,000/-) and submitted the same vide our letter nos as follows:
1) CEG/BNG-NEL/NH-4/O&M/2017-18/492 Dt: 25.07.2017. 2) CEG/BNG-NEL/NH-4/O&M/2017-18/493 Dt: 25.07.2017. 3) CEG/BNG-NEL/NH-4/O&M/2017-18/494 Dt: 25.07.2017. 4) CEG/BNG-NEL/NH-4/O&M/2017-18/495 Dt: 25.07.2017.
Consultancy Services as Independent Engineers for Access controlled highway M/s CEG Ltd
From Bangalore to Nelamangala section of NH-4 (Km 10.00 to Km 29.50) Bangalore
10 O & M Progress Report August-2017
4.3 Proposed VUP in front of BIEC Bangalore - Nelamangala Section of NH-4
from Km.10+000 to Km.29+500.
The CGM(T)-RO and PD-PIU Bangalore asked for re submission of final detailed re-revised
cost estimation vide their letter no: NHAI/RO-BNG/11018/13/2016/4063 Dt:09.03.2017,
accordingly the concessionaire submitted the re-revised cost estimate vide letter no:
NBTPL/O&M/CEG/2016-17/288 Dt:22.03.2017.
The re-revised final detailed cost estimation scrutinized and finalized, the component
wise breakup as follows and submitted the same vide our letter no: CEG/BNG-
NEL/NH-4/O&M/2016-17/379 Dt: 22.03.2017..
1) VUP – 2,37,38,734/-.
2) Retaining wall – 10,19,00,656/-.
3) PUP – 43,58,687/-.
4) MCW Road Works – 7,20,80,566/-.
5) Service Road Widening including culvert extension and Toe walls – 3,84,01,766/-.
6) Dismantling of FOB – 19,26,000/-.
7) Cost of additional toll booth – 69,92,611/-
8) Miscellaneous Cost ,such as Traffic Signal, Median kerb, and filling, Hand railing on
crash barrier and utility crossing ducts, Electrical pole shifting etc. – 41,79,600/-.
9) Design (2%) and Contingency charges (3%) Rs. 1,23,73,650/-.
10) The Total construction cost of Rs: 26,59,52,271/-.
PD-PIU Bangalore instructed to start the construction of VUP without further delay through
their letter no: NHAI160125/01/15-16/PIU-BNG/158 Dt: 22.04.2017.
4.4 Merging of service:
Merging of service road at Km. 29.500 issue has been pending with NHAI.
*****
Consultancy Services as Independent Engineers for Access controlled highway M/s CEG Ltd From Bangalore to Nelamangala section of NH-4 (Km 10.00 to Km 29.50) Bangalore
O & M Progress Report August-2017 11
5.0 SAFETY MANAGEMENT AT SITE
It is of paramount importance to ensure safety issues are tackled by the Concessionaire as
per the requirement of agreement in Schedule ’L’ and ‘S’. IC is supervising/monitoring the
activities regularly.
5.1 TRAFFIC MANAGEMENT
There are 2 VMS on each side of main carriageway and 3 CCTV. ECB are not functioning
as most of them are damaged. CCTV system does not cover the entire area and in absence
of electricity power break down, no back up is available at all locations.
5.2 PROJECT FACILITIES
5.2.1 ABSTRACT OF SAFETY MEASURES ON PROJECT HIGHWAY AS PER CA.
Sl.No. Item Unit Qty.
1 Sign Boards in Elevated Highway Nos 126
2 Sign Boards in Main carriageway Nos 123
3 Sign Boards in Service Road. Nos 528
4 Sign Boards at Toll Plazas Nos 65
5 Sign Boards at Major junctions Nos 66
6 Sign Boards at Minor junctions Nos 161
7 Hazard Markers(Left, Right & Two-way) Nos 138
8 Object Markers Nos 36
9 Delineators/Road way indicators Nos 486
10 Raised Pavement Markers (Road Studs) Nos 18700
11
Pavement Marking
(i) Main Carriageway
(ii) Service Roads
Kms
Kms
43
39
12
Highway Traffic Management System.
a) ECBs
b) VMS
c) CCTV
d) Plaza monitoring cameras
Nos
Nos
Nos
Nos
20
4
3
6
13 Speed Breakers Nos 213
14 Traffic Signal Nos 4+2
15 a) Metal Beam Crash barrier
b) Concrete barrier
Kms
Kms
7.163
39.00
Consultancy Services as Independent Engineers for Access controlled highway M/s CEG Ltd From Bangalore to Nelamangala section of NH-4 (Km 10.00 to Km 29.50) Bangalore
O & M Progress Report August-2017 12
5.3 WORK SITE SAFETY MANAGEMENT-MARKING AND RATING SCALE
(AUGUST-2017)
Road marking has worn out/faded in most of the service road section and also on main
carriage way. Proper road marking is essential for safe travel especially at night times.
The Concessionaire is required to comply with safety requirement while taking up construction and periodical works as per Schedule ‘L’ & ‘S’ of the Agreement.
The Concessionaire has taken up the excavation works for widening of Service Road on Both Sides for proposed VUP at Km.17+220 near BIEC. There are no incidents
found during this period.
5.4 WORK SITE SAFETY MANAGEMENT-MARKING AND RATING SCALE
(AUGUST -2017)
(Refer CEG letter no: CEG/BNG-NEL/NH-4/O&M/2017-18/521 Dated: 11/09/2017)
Cumulative/Total Marks Range Rating Scale
1-10 Highly Unsatisfactory (HU)
11-20 Unsatisfactory (U)
21-30 Moderately Unsatisfactory (MU)
31-40 Moderately Satisfactory (MS)
41-50 Satisfactory (S)
51-60 Highly Satisfactory (HS)
Total Marks scored Rating Scale
37.05 Moderately Satisfactory (MS)
5.5 REPORT ON SAFETY ISSUES:
In accordance to the requirement of safety at site, the following Annexure 1, 2 and
Appendix are shown the Action taken report on safety issues for the month of August-
2017.
Consultancy Services as Independent Engineers for Access controlled highway
From Bangalore to Nelamangala section of NH-4 (Km 10.00 to Km 29.50)
M/s CEG Ltd
Bangalore
S.NO NAME OF THE ROADRHS &
LHS
CHAINAGE
NUMBERDISTRICT
TYPE OF WINE LIQUOR
SHOP
ACTION Issued/
REMARKS
Distance From
the Central
Median(m)
Remarks
1 MAKALI RHS 19+450 BANGALORE NORTH CM WINESLicense Issued by
KA State
Government
31
2 M N HALLI RHS 18+400 BANGALORE NORTH MADHU WINESLicense Issued by
KA State
Government
30
3 ANCHE PALYA RHS 16+500 BANGALORE NORTH S L N BAR & RESTURANTLicense Issued by
KA State
Government
33
4 ANCHE PALYA RHS 16+450 BANGALORE NORTH V K BAR & RESTURANTLicense Issued by
KA State
Government
33
5 MARRISON RHS 15+350 BANGALORE NORTH SHEKAR WINESLicense Issued by
KA State
Government
28
6 8TH MAIL RHS 13+400 BANGALORE NORTHCHITRA BAR &
RESTURANT
License Issued by
KA State
Government
26
7 DASARA HALLI RHS 12+900 BANGALORE NORTH RADHA NADA WINESLicense Issued by
KA State
Government
24
8 JALA HALLI CROSSE RHS 12+150 BANGALORE NORTHDEEPASHREE BAR &
RESTURANT
License Issued by
KA State
Government
24
9 PEENYA LHS 11+160 BANGALORE NORTH R V WINESLicense Issued by
KA State
Government
24
10 JALA HALLI CROSSE LHS 12+050 BANGALORE NORTHSRI NIDHI BAR &
RESTARANT
License Issued by
KA State
Government
24
11 JALA HALLI CROSSE LHS 12+350 BANGALORE NORTH MAHALAKSHMI B & RLicense Issued by
KA State
Government
24
12 DASARA HALLI LHS 12+400 BANGALORE NORTH SURESH WINESLicense Issued by
KA State
Government
24
13 DASARA HALLI LHS 12+590 BANGALORE NORTHWHOLE SALE SPIRITS
ZONE
License Issued by
KA State
Government
24
14 DASARA HALLI LHS 12+750 BANGALORE NORTH KADAMBA B & RLicense Issued by
KA State
Government
24
15 8TH MAIL LHS 13+350 BANGALORE NORTH ABILASH B & RLicense Issued by
KA State
Government
26
16 8TH MAIL LHS 13+350 BANGALORE NORTHGREEN PARK FAMILY B&
R
License Issued by
KA State
Government
26
17 MADHAVARA LHS 17+900 BANGALORE RURAL VINAYAKA WINESLicense Issued by
KA State
Government
30
18 M N HALLI LHS 18+050 BANGALORE RURAL VINAYAKA B & RLicense Issued by
KA State
Government
29.5
19 M N HALLI LHS 18+500 BANGALORE RURAL SRINIVAS B & RLicense Issued by
KA State
Government
30
20 M N HALLI LHS 18+550 BANGALORE RURAL GANAPATHI B & RLicense Issued by
KA State
Government
30
21 M N HALLI LHS 18+650 BANGALORE RURAL GURU CHARAN B & RLicense Issued by
KA State
Government
30
22 MAKALI LHS 18+700 BANGALORE RURAL MANJUNATHA WINESLicense Issued by
KA State
Government
34
23 MAKALI LHS 19+000 BANGALORE RURAL B G LIQUORLicense Issued by
KA State
Government
28
24 ADAKAMARANAHALLI LHS 19+650 BANGALORE RURAL ARKAVATHI B & RLicense Issued by
KA State
Government
34
25 DASANAPURA LHS 22+550 BANGALORE RURAL SRI VEERABADRA B & RLicense Issued by
KA State
Government
34
26 KUNIGAL BYPASS LHS 27+700 BANGALORE RURAL BHARATH B & RLicense Issued by
KA State
Government
40
Annexure-1
As per
supreme
court order
all the
Liquor
Shops
adjacent to
National
Highways
within a
radial
distance of
500m have
been closed
w.e f 01-07-
2017.
LIQUOR SHOPS DETAILS
Bangalore Nelamangala Section of NH-4 Stretch KM 10+000 to KM 29+500 LHS & RHS
13 O & M Progress Report August-2017
Consultancy Services as Independent Engineers for Access controlled highway
From Bangalore to Nelamangala section of NH-4 (Km 10.00 to Km 29.50)
M/s CEG Ltd
Bangalore
Appendix
SL No Safety Issue Action taken for closing / removal
/attended/ replaced
Locations action
pending with
reasons
Issue raised with
enforcing agency
Penal action by IE
due to delay / no
action
1 Unauthorised Median Openings NIL NIL NIL NIL
2 Liquor shops adjacent to highway Annexure-1 Attached _ _ _
3
Black spots (No of 10 accidents & more in a
year at any spot causing fatal) Identified by
IE & Safety Consultant based on last 3
years statistics.
NIL NIL NIL NIL
4
Major/ Minor junctions Transverse bar
marking rumble strips speed breakers on X
–Road sinages etc.., Seep restriction
signage’s as per enforcing agency
requirement .
Annexure-2 Attached _ _ _
5 Encroachment within ROW Annexure-3 Attached NIL NIL NIL
6 Dumped / Surplus waste material.
Being removed by concessionaire
however not so effective in complete
removal of the garbage, there is ample
scope for effective & needful
implementation.
_ _ _
LHS.
Km. 11+201
(Speed Limit board)
RHS:
16+850
(Go Slow
Board),
Not done
Km.11+270
(Cautionary Board)
18+550(No
Parking Board), Not done
Km.15+600 (Pedestrian
Crossing)
18+900
(Pedestrian
Crossing),
Not done
Km.14+700
(TP-1 All notification boards)
19+450
(U-Turn
Prohibited).
Not done
Km.18+500
(No Parking Board)Not done
19+000
(Hazard Board)Not done
19+000 (Stop Board) Not done
8Public demand /VIP ref. for VUP/ PUP/
FOB subway /Service roads etc.Now being processed _ _ _
9Any other unauthorized / illegal / unsafe
activities on along project highway._ _ _ _
Being initiated now
Proposed 4 No.FOB i.e
28+675( vishweshpura)
25+840(Nelamangala)
22+700(Devannanapalya)
21+350(Dasanapura)
Details at Annx - 3
LHS: 15+650, 16+700, 17+300, 18+620,
27+100.
RHS: 13+250, 19+300, 23+850, 25+400.
(Surplus material are dumped within ROW)
7Damaged/ deficient signage as per codal
/CA_ _
NATIONAL HIGHWAYS AUTHORITY OF INDIA, KARNATAKA REGION, REGIONAL OFFICE, BANGALORE
Report on Safety Issues on National Highways in the State of Karnataka
Name of Project : Design, Engineering, Finance, Construction, Operartion and Maintenance of access controlled highway project of Bengaluru - Nelamangala section of NH-4
from Km 10.000 to Km 29.500 in the State of Karnatka on Build, Operate and Transfer (BOT) Basis.
Name of Concessionaire: Navayuga Bengalooru Tollway Private Limited.
Name of IE : M/s Consulting Engineers Group Ltd
* There is no proper check on over speeding
vehicles on the highway beyond Km. 14+500 after
BBMP limits.
* Indiscrete crossing of Pedestrians at number of
unauthorized locations.
* Indiscrete parking vehicles on Main Carriage
way more specifically near Chikbidarikallu,
Madanakayanahalli, Madavara, Makali, BIEC
portions and Indiscrete parking of sand trucks on
both sides of Service Road Shoulders from
Chikbidrikallu to TCI (i.e 15+000 to 18+000).
Locations as on (13/07/2017)
NIL
Details at Annx - 1
NIL
Details at Annx - 2
14 O & M Progress Report August-2017
Consultancy Services as Independent Engineers for Access controlled highway
From Bangalore to Nelamangala section of NH-4 (Km 10.00 to Km 29.50)
M/s CEG Ltd
Bangalore
Annexture-2Annexure-2
Sl NoName of the Junctions
(BHS)Chainage
Action to be Taken
(Proposed By IC
for the month of July-2017)
Action Taken by ConcessionaireStatus as on 31/07/2017
1 SRS Junction (BHS) 10+625
a)'GO SLOW' signage/cautionary board
b)Bar marking and road markings
c)2 Rows of road studs on either side
pedestrain crossing
d) Lane studs on curve portion
a)All Sinage Boards are installed.
b)Bar marking and road markings completed.
c) Road studs fixing work has been completed.
d) Lane studs Fixing work has been completed.
a) Sign boards installed.
b)Bar marking and road markings
including pedestrian markings are painted
but partially fadedoff as of now.
c) Road studs/cateyes are not fixed.
d)Lane studs have been fixed as of now.
2Penya Industrial Estate
Road(BHS)11+500
a)'GO SLOW' signage/cautionary board
b)Bar marking and road markings
c)2 Rows of road studs on either side
pedestrain crossing
d) Lane studs on curve portion
a)All Sinage Boards are installed.
b)Bar marking and road markings completed.
c) Road studs fixing work has been completed.
d) Lane studs Fixing work has been completed.
a) Sign boards installed.
b)Bar marking and road markings
including pedestrian markings are painted
but Partially fadedoff as of now.
c) Road studs are not fixed.
d)Lane studs have been fixed as of now.
3 Jalahalli Cross(BHS) 12+000
a)'GO SLOW' signage/cautionary board
b)Bar marking and road markings
c)2 Rows of road studs on either side
pedestrain crossing
d) Lane studs on curve portion
a)All Sinage Boards are installed.
b)Bar marking and road markings completed.
c) Road studs fixing work has been completed.
d) Lane studs Fixing work has been completed.
a) Sign boards installed.
b)Bar marking and road markings
including pedestrian markings are painted
but Partially fadedoff as of now.
c) Road studs are not fixed.
d)Lane studs have been fixed as of now.
4Hesaraghatta Junction
(BHS)13+350
a)'GO SLOW' signage/cautionary board
b)Bar marking and road markings
c)2 Rows of road studs on either side
pedestrain crossing
d) Lane studs on curve portion
a)All Sinage Boards are installed.
b)Bar marking and road markings completed.
c) Road studs fixing work has been completed.
d) Lane studs Fixing work has been completed.
a) Sign boards installed.
b)Bar marking and road markings
including pedestrian markings are painted
but Partially fadedoff as of now.
c) Road studs are not fixed.
d)Lane studs have been fixed as of now.
7 Nos VUP's(BHS)
1 i) Jindal 15+835
a)'GO SLOW' signage/cautionary board
b)Bar marking and road markings on
junction & cross roads
c)2 Rows of road studs on either side of
pedestrain crossing
d) Lane studs on curve portion
a)All Sinage Boards are installed.
b)Bar marking and road markings completed.
c) Road studs fixing work has been completed.
d) Lane studs Fixing work has been completed.
a) Sign boards installed.
b)Bar marking and road markings on
junction and cross road portions not done.
c) Road studs are not fixed.
d)Renewal completed in VUP portion,
Lane marking and fixing of cateyes not
done.
2 ii) TCI 18+010
a)'GO SLOW' signage/cautionary board
b)Bar marking and road markings on
junction & cross roads
c)2 Rows of road studs on either side of
pedestrain crossing
d) Lane studs on curve portion
a)All Sinage Boards are installed.
b)Bar marking and road markings completed.
c) Road studs fixing work has been completed.
d) Lane studs Fixing work has been completed.
a) Sign boards missing.
b)Bar marking and road markings on
junction and cross road portions not done.
c) Road studs are not fixed.
d)Renewal completed in VUP portion,
Lane marking and fixing of cateyes not
done.
3 iii) Adakimaranahalli 20+350
a)'GO SLOW' signage/cautionary board
b)Bar marking and road markings on
junction & cross roads
c)2 Rows of road studs on either side of
pedestrain crossing
d) Lane studs on curve portion
a)All Sinage Boards are installed.
b)Bar marking and road markings completed.
c) Road studs fixing work has been completed.
d) Lane studs Fixing work has been completed.
a) Sign boards missing.
b)Bar marking and road markings on
junction and cross road portions not done.
c) Road studs are not fixed.
d)Renewal completed in VUP portion,
Lane marking and fixing of cateyes not
done.
4 iv) Dasanapura 22+070
a)'GO SLOW' signage/cautionary board
b)Bar marking and road markings on
junction & cross roads
c)2 Rows of road studs on either side of
pedestrain crossing
d) Lane studs on curve portion
a)All Sinage Boards are installed.
b)Bar marking and road markings completed.
c) Road studs fixing work has been completed.
d) Lane studs Fixing work has been completed.
a) Sign boards installed.
b)Bar marking and road markings on
junction and cross road portions not done.
c) Road studs are not fixed.
d)Renewal completed in VUP portion,
Lane marking and fixing of cateyes not
done.
STEPS TO IMPROVE FOR ROAD SAFETY AT JUNCTIONS
1 of 15 O & M Progress Report August-2017
Consultancy Services as Independent Engineers for Access controlled highway
From Bangalore to Nelamangala section of NH-4 (Km 10.00 to Km 29.50)
M/s CEG Ltd
Bangalore
5v) Start of Nelamangala
Bypass23+815
a)'GO SLOW' signage/cautionary board
b)Bar marking and road markings on
junction & cross roads
c)2 Rows of road studs on either side of
pedestrain crossing
d) Lane studs on curve portion
a)All Sinage Boards are installed.
b)Bar marking and road markings completed.
c) Road studs fixing work has been completed.
d) Lane studs Fixing work has been completed.
a) Sign boards installed.
b)Bar marking and road markings on
junction and cross road portions not done.
c) Road studs are not fixed.
d)Renewal completed in VUP portion,
Lane marking and fixing of cateyes not
done.
6 vi) Sondekoppa 26+675
a)'GO SLOW' signage/cautionary board
b)Bar marking and road markings on
junction & cross roads
c)2 Rows of road studs on either side of
pedestrain crossing
d) Lane studs on curve portion
a)All Sinage Boards are installed.
b)Bar marking and road markings completed.
c) Road studs fixing work has been completed.
d) Lane studs Fixing work has been completed.
a) Sign boards installed.
b)Bar marking and road markings on
junction and cross road portions not done.
c) Road studs are not fixed.
d)Renewal completed in VUP portion,
Lane marking and fixing of cateyes not
done.
7
vi) Kunigal Bypass
( NH- 4 & NH-48
Junction)
27+833
a)'GO SLOW' signage/cautionary board
b)Bar marking and road markings on
junction & cross roads
c)2 Rows of road studs on either side of
pedestrain crossing
d) Lane studs on curve portion
a)All Sinage Boards are installed.
b)Bar marking and road markings completed.
c) Road studs fixing work has been completed.
d) Lane studs Fixing work has been completed.
a) Sign boards installed.
b)Bar marking and road markings on
junction and cross road portions not done.
c) Road studs are not fixed.
d)Renewal completed in VUP portion,
Lane marking and fixing of cateyes not
done.
13 Nos PUP's(BHS)
1 i) Jindal (Up ramp) 15+647
a)'GO SLOW' signage/cautionary board
b)Bar marking and road markings
c)2 Rows of road studs on either side
pedestrain crossing
d) Lane studs on curve portion
a)All Sinage Boards are installed.
b)Bar marking and road markings completed.
c) Road studs fixing work has been completed.
d) Lane studs Fixing work has been completed.
a) Sign boards installed.
b)Bar marking and road markings on
junction and cross road portions not done.
c) Road studs are not fixed.
d)Renewal completed in VUP portion,
Lane marking and fixing of cateyes not
done.
2 ii) TCI (Up ramp) 17+900
a)'GO SLOW' signage/cautionary board
b)Bar marking and road markings
c)2 Rows of road studs on either side
pedestrain crossing
d) Lane studs on curve portion
a)All Sinage Boards are installed.
b)Bar marking and road markings completed.
c) Road studs fixing work has been completed.
d) Lane studs Fixing work has been completed.
a) Sign boards missing.
b)Bar marking and road markings on
junction and cross road portions not done.
c) Road studs are not fixed.
d)Renewal completed in VUP portion,
Lane marking and fixing of cateyes not
done.
3 ii) TCI (Down ramp) 18+160
a)'GO SLOW' signage/cautionary board
b)Bar marking and road markings
c)2 Rows of road studs on either side
pedestrain crossing
d) Lane studs on curve portion
a)All Sinage Boards are installed.
b)Bar marking and road markings completed.
c) Road studs fixing work has been completed.
d) Lane studs Fixing work has been completed.
a) Sign boards missing.
b)Bar marking and road markings on
junction and cross road portions not done.
c) Road studs are not fixed.
d)Renewal completed in VUP portion,
Lane marking and fixing of cateyes not
done.
4iii) Adakimaranahalli
(Up ramp)20+180
a)'GO SLOW' signage/cautionary board
b)Bar marking and road markings
c)2 Rows of road studs on either side
pedestrain crossing
d) Lane studs on curve portion
a)All Sinage Boards are installed.
b)Bar marking and road markings completed.
c) Road studs fixing work has been completed.
d) Lane studs Fixing work has been completed.
a) Sign boards missing.
b)Bar marking and road markings on
junction and cross road portions not done.
c) Road studs are not fixed.
d)Renewal completed in VUP portion,
Lane marking and fixing of cateyes not
done.
5iii) Adakimaranahalli
(Down ramp)20+530
a)'GO SLOW' signage/cautionary board
b)Bar marking and road markings
c)2 Rows of road studs on either side
pedestrain crossing
d) Lane studs on curve portion
a)All Sinage Boards are installed.
b)Bar marking and road markings completed.
c) Road studs fixing work has been completed.
d) Lane studs Fixing work has been completed.
a) Sign boards missing.
b)Bar marking and road markings on
junction and cross road portions not done.
c) Road studs are not fixed.
d)Renewal completed in VUP portion,
Lane marking and fixing of cateyes not
done.
6iv) Dasanapura
(Up ramp)21+950
a)'GO SLOW' signage/cautionary board
b)Bar marking and road markings
c)2 Rows of road studs on either side
pedestrain crossing
d) Lane studs on curve portion
a)All Sinage Boards are installed.
b)Bar marking and road markings completed.
c) Road studs fixing work has been completed.
d) Lane studs Fixing work has been completed.
a) Sign boards installed.
b)Bar marking and road markings on
junction and cross road portions not done.
c) Road studs are not fixed.
d)Renewal completed in VUP portion,
Lane marking and fixing of cateyes not
done.
2 of 15 O & M Progress Report August-2017
Consultancy Services as Independent Engineers for Access controlled highway
From Bangalore to Nelamangala section of NH-4 (Km 10.00 to Km 29.50)
M/s CEG Ltd
Bangalore
7iv) Dasanapura
(Down ramp)22+250
a)'GO SLOW' signage/cautionary board
b)Bar marking and road markings
c)2 Rows of road studs on either side
pedestrain crossing
d) Lane studs on curve portion
a)All Sinage Boards are installed.
b)Bar marking and road markings completed.
c) Road studs fixing work has been completed.
d) Lane studs Fixing work has been completed.
a) Sign boards installed.
b)Bar marking and road markings on
junction and cross road portions not done.
c) Road studs are not fixed.
d)Renewal completed in VUP portion,
Lane marking and fixing of cateyes not
done.
8v) Start of Nelamangala
Bypass (Up ramp)23+630
a)'GO SLOW' signage/cautionary board
b)Bar marking and road markings
c)2 Rows of road studs on either side
pedestrain crossing
d) Lane studs on curve portion
a)All Sinage Boards are installed.
b)Bar marking and road markings completed.
c) Road studs fixing work has been completed.
d) Lane studs Fixing work has been completed.
a) Sign boards missing.
b)Bar marking and road markings on
junction and cross road portions not done.
c) Road studs are not fixed.
d)Renewal completed in VUP portion,
Lane marking and fixing of cateyes not
done.
9v) Start of Nelamangala
Bypass (Down ramp)24+000
a)'GO SLOW' signage/cautionary board
b)Bar marking and road markings
c)2 Rows of road studs on either side
pedestrain crossing
d) Lane studs on curve portion
a)All Sinage Boards are installed.
b)Bar marking and road markings completed.
c) Road studs fixing work has been completed.
d) Lane studs Fixing work has been completed.
a) Sign boards installed.
b)Bar marking and road markings on
junction and cross road portions not done.
c) Road studs are not fixed.
d)Renewal completed in VUP portion,
Lane marking and fixing of cateyes not
done.
10vi) Sondekoppa
( Up ramp)26+530
a)'GO SLOW' signage/cautionary board
b)Bar marking and road markings
c)2 Rows of road studs on either side
pedestrain crossing
d) Lane studs on curve portion
a)All Sinage Boards are installed.
b)Bar marking and road markings completed.
c) Road studs fixing work has been completed.
d) Lane studs Fixing work has been completed.
a) Sign boards installed.
b)Bar marking and road markings on
junction and cross road portions not done.
c) Road studs are not fixed.
d)Renewal completed in VUP portion,
Lane marking and fixing of cateyes not
done.
11vi) Sondekoppa
(Down ramp)26+840
a)'GO SLOW' signage/cautionary board
b)Bar marking and road markings
c)2 Rows of road studs on either side
pedestrain crossing
d) Lane studs on curve portion
a)All Sinage Boards are installed.
b)Bar marking and road markings completed.
c) Road studs fixing work has been completed.
d) Lane studs Fixing work has been completed.
a) Sign boards installed.
b)Bar marking and road markings on
junction and cross road portions not done.
c) Road studs are not fixed.
d)Renewal completed in VUP portion,
Lane marking and fixing of cateyes not
done.
12
vi) Kunigal Bypass
( NH- 4 & NH-48
Junction)
Up ramp
27+660
a)'GO SLOW' signage/cautionary board
b)Bar marking and road markings
c)2 Rows of road studs on either side
pedestrain crossing
d) Lane studs on curve portion
a)All Sinage Boards are installed.
b)Bar marking and road markings completed.
c) Road studs fixing work has been completed.
d) Lane studs Fixing work has been completed.
a) Sign boards missing.
b)Bar marking and road markings on
junction and cross road portions not done.
c) Road studs are not fixed.
d)Renewal completed in VUP portion,
Lane marking and fixing of cateyes not
done.
13
vi) Kunigal Bypass
( NH- 4 & NH-48
Junction)
Down ramp
28+080
a)'GO SLOW' signage/cautionary board
b)Bar marking and road markings
c)2 Rows of road studs on either side
pedestrain crossing
d) Lane studs on curve portion
a)All Sinage Boards are installed.
b)Bar marking and road markings completed.
c) Road studs fixing work has been completed.
d) Lane studs Fixing work has been completed.
a) Sign boards installed.
b)Bar marking and road markings on
junction and cross road portions not done.
c) Road studs are not fixed.
d)Renewal completed in VUP portion,
Lane marking and fixing of cateyes not
done.
14Service road
(Both Hand Sides)
Km 10.000
to Km
29.500
a)Speed breakers marking
b) Lane/ road markings
c)Cleaning of service road is not
satisfactory
a)Speed breakers marking completed.
b) Lane/ road marking completed.
c)For Cleaning of service road more no of
labour we be deployed.
a)Speed Breakers markings are painted
but Partially fadedoff as of now.
b)Lane/ road markings are not done.
c)Cleaning of service road is not
satisfactory
*****
3 of 15 O & M Progress Report August-2017
Consultancy Services as Independent Engineers for Access controlled highway
From Bangalore to Nelamangala section of NH-4 (Km 10.00 to Km 29.50)
M/s CEG Ltd
Bangalore
6.1: IE MANAGEMENT STRUCTURE
Office Manager
Mr. Venkata Kiran. P
Steno cum Computer Operator :1
Mr. Abhishek .G
Highway Maintenance . Eng.
Mr. Faiz Ahmed. D
Technical Supervisor : 1
Mr. Syed Numan
Team Leader
D.T Sridhar
Assistant Bridge Engineer.
Mr. Manjunath. N
Technical Supervisor : 2
Miss. Umadevi . G
Technical Supervisor : 3
Miss. Kritika . P
Technical Supervisor : 4
Mr. Sai Praneeth . K
Accountant cum Cashier
Mr. Sandeep.P.K
Steno cum Computer Operator : 2
Mr. Pradeep. B.S
Quality Cum Material Expert.
Mr. Bapu Reddy. N
CAD / Draughtsman
Miss. Sowmya.N
Laboratory Assistant
Mr. Mallikarjuna Reddy. G
16 O & M Progress Report August-2017
Consultancy Services as Independent Engineers for Access controlled highway
From Bangalore to Nelamangala section of NH-4 (Km 10.00 to Km 29.50)
M/s CEG Ltd
Bangalore
Navayuga Bengalooru Tollway Pvt. Ltd.6.2: Concessionaire Management Structre
Gopi Reddy
Director
NBTPL
Operations Manager
Mr. Anchi Chowdappa
# 9900020806
Operations Team
Mr. M S Y Rao
Plaza Manager
# 09703246551
Admin & Saftey
Mr. Janardhana.S
# 7259000388
RPO, RPA
9 nos. in 3 shifts
HTMS
6 nos. in 3 shifts
Crane Operator
Helper / Towing
2 nos in 2 shifts
Para Medical
6 nos. in 3 shifts
Accounts
Mr. Srikanth
# 7259000390
MIS
3 nos in 3 shifts
Accountants
6 nos in 3 shifts
POS
1no. in General
Toll Officer
Mr. A Lakshmana Rao
# 08277127194
Shift In Charge
3 nos in 3 shifts
Lane Supervisor
24 nos in 3 shifts
Toll Collector
63 nos in 3 shifts
Electricians /
DG Operator
2 nos in each shift
Office Boys
9 nos. in 3 shifts
Mr. C.H. Sankar Rao
Chief Manager (Project)
# 9980977689
Construction Team
Suresh
Sr.Engineer
# 9492913166
Shiva Krishna
Site Supervisor 8919637774
Suverna Raju
(Sr. Engineer) Construction Team
Mr. Sekhar
Road& drain
maintenance
#9900020818
Hussain (sup)
Road &Drain Cleaning
workers: 80 nos
Srinivas
Electrical Team
Nagaraju Technician
Krishna Mohana Reddy.B (Gardening)
# 99859135790
Workers: 16 nos
Krishna Mohana Reddy.B
Road Cleaning
Workers: 12 nos.
Srinivas
Safety Supervisor
Workers: 3 nos
Change of scope works
Suresh
Sub Contractor
17 O & M Progress Report August-2017
Consultancy Services as Independent Engineers for Access controlled highway M/s CEG Ltd
From Bangalore to Nelamangala section of NH-4 (Km 10.00 to Km 29.50) Bangalore
O & M Progress Report August-2017 18
7.0 IC-INSPECTION REPORT:
The concessionaire has to ensure that at all times during the operations Period, the
Project Highway is maintained in a manner that it complies with the Specifications and
Standards and the minimum maintenance requirements set forth in Clause 18, Schedule
‘L’ & Schedule ‘S’ of the concession Agreement. Accordingly the inspection report by
IC is based upon the requirements under the provisions of the Agreement. The status of
construction works under Change of scope has been provided in section 4 of this
report.
7.1 MONITORING O&M ACTIVITIES ON THE PROJECT HIGHWAY:
In accordance to the requirement of the Clause 19.2, IC during his monthly inspection
report has pointed out defects and deficiencies for remedy by the Concessionaire on the
Project Highway in the O&M period. The Concessionaire has not started to carryout
rectification works and is yet to submit para wise compliance except routine cleaning
work.
7.1.1 MAINTENANCE:
The details of the deficiencies and defects noticed on the Project Highway during
inspection in the month of August - 2017 are as under:
7.1.1.1 Main Carriageway (Elevated Corridor) Section Km 10.000 - Km 14.500:
Works under routine Maintenance:
i. Expansion Joints: Cleaning of Expansion Joints is now Moderately satisfactory.
Regular monitoring is being done and the concessionaire has been instructed to deploy
more number of labours to clean periodically.
ii. General Cleaning: It is Moderately satisfactory, the concessionaire has been
instructed to deploy more number of labours for regular cleaning.
iii. Painting on kerb: The kerb painting is faded in most of the locations and the same
was instructed to the concessionaire to re-paint.
iv. Median Planatation: The Concessionaire has been instructed to replace the dead trees
with new plant and to maintain the planted tress properly. The work is under progress.
v. Drainage spouts: The Concessionaire has been instructed to clean drainage spouts and
clear the blockages in pipe for the free flow of rain water as early monsoon is expected.
Work under progress.
7.1.1.2 Main Carriageway at Ground Level from Km 10.000-Km 29.500 (LHS & RHS)
excluding elevated corrider:
Shoulder rectification: The concessionaire has been instructed to use Blending of
milling metrial with gravel in 50-50 proportion for shoulder rectification. But the
concessionaire using only gravel material and for which Site instruction issued.
7.1.1.3 Road at Ground level of Main Carriageway Km 10.000–Km 29.500 (LHS):
i. General cleaning: It is Moderately satisfactory, now the concessionaire to be
instructed to deploy more number of labours for regular cleaning.
ii. Drain pipes : It is Moderately satisfactory, now the concessionaire to be instructed to
deploy more number of labours for regular cleaning.
Consultancy Services as Independent Engineers for Access controlled highway M/s CEG Ltd
From Bangalore to Nelamangala section of NH-4 (Km 10.00 to Km 29.50) Bangalore
O & M Progress Report August-2017 19
iii. Painting on kerb: The kerb painting work is taken up and completed at all the
Periodical Renewal works completed locations. And also instructed to the
concessionaire to paint simuntaniously after completion of Periodical Renewal works.
iv. Median Planatation: The Concessionaire has been instructed to replace the dead trees
with new plant and to maintain the planted tress properly. And also instructed to fill the
gaps in the median with newly plants, which is under progress.
v. Avenue Plantation: The Concessionaire has been instructed to plant missing plants
along with treeguards at ROW to maintain minimum number of avenue plantation as
per PCOD time from km.14+500 to km.29+500.
vi. Ornamental rails: The Concessionaire has been completed the painting of the
ornamental rails, and also instructed to re-paint when found faded.
7.1.1.4 Road at Ground level of Main Carriageway Km 10.000 –Km 29.500 (RHS):
i. General cleaning: It is Moderately satisfactory, now the concessionaire to be
instructed to deploy more number of labours for regular cleaning.
ii. Service road cleaning on RHS and damaged Guard rail replacement due to Metro work
(BMRCL) has been taken up and completed.
iii. Painting on kerb: The kerb painting work is taken up and completed at all the PR
works completed locations. And also instructed to the concessionaire to paint
simuntaniously after completion of PR work.
iv. Median Planatation: The Concessionaire has been instructed to replace the dead trees
with new plant and to maintain the planted tress properly. And also instructed to fill the
gaps in the median with newly plants.
7.1.1.5 Service Road from Km 10.000 –Km 29.500 (LHS & RHS):
Painting on Speed Breakers: The Speed Breaker painting work is taken up and it is
under progress at all the PR works completed locations. And also instructed to the
concessionaire to paint simuntaniously after completion of PR work
7.1.1.6 Service Road from Km 10.000 –Km 29.500 (LHS):
General cleaning: It is Moderately unsatisfactory, now the concessionaire to be
instructed to deploy more number of labours for regular cleaning of culverts and line
drains in the stretch.
The Concessionaire has been instructed to taken up and completed the Pavement
marking as soon as possible and also instructed to re-paint when found faded.
The Road marking and speed breaker marking work was takn up in the month of
March and it was completed in the month of April.
7.1.1.7 Service Road from Km 10.0 –Km 29.5 (RHS):
General cleaning: It is Moderately unsatisfactory, now the concessionaire to be
instructed to deploy more number of labours for regular cleaning of culverts and line
drains in the stretch.
The Concessionaire has been instructed to taken up the Pavement marking on Service
Road and to complete as soon as possible and also instructed to re-paint when found
faded.
Consultancy Services as Independent Engineers for Access controlled highway M/s CEG Ltd
From Bangalore to Nelamangala section of NH-4 (Km 10.00 to Km 29.50) Bangalore
O & M Progress Report August-2017 20
The Road marking and speed breaker marking work was takn up in the month of
March and it was completed in the month of April.
7.1.1.8 Flyover and Vehicular/Pedestrian under Passes:
(a) Flyover:
Expansion Joints: Cleaning of Expansion Joints is now Moderately satisfactory.
Regular monitoring is being done and the concessionaire has been instructed to clean
periodically.
Drainage spouts & pipes: The Concessionaire has been instructed to clean spouts and
clear the blockages in pipe for the free flow of rain water for early monsoon expecting.
Work under progress.
(b) Vehicular Under Passes:
Expansion Joints: Cleaning of Expansion Joints is now Moderately Satisfactory.
Regular monitoring is being done and the concessionaire has been instructed to clean
periodically.
Drainage spouts & pipes: The Concessionaire has been instructed to clean spouts and
clear the blockages in pipe for the free flow of rain water.
(c) Pedestrian Under Passes (PUP):
The PUP provided on the approaches to Fly over and Vehicular passes are cleaning
Moderately Satisfactory.
7.1.1.9 Minor Bridges & Culverts:
No defects noticed during the Inspection.
7.2 Routine maintenance:
Routine Maintenance has been planned in 2016-2017 on the following items: 1.General
Cleaning of Road, 2.Maintaining of Safety signs, 3.Cleaning of vegitaiton, 4.Cleaning
of Drains, 5.Plantation Maintenance, 6.Lighting Maintenance, 7.Road Marking and
8.Improveing Toll Maintenance.
7.3 Pick-up bus stops and shelters:
The Concessionaire has been instructed to clean the Pick-up bus stops and shelters
regularly.
7.4 Base camp facilities:
7.4.1 Following facilities have been provided (outsourced):
(a) Welding Shop
(b) Washing shed and Tyre Repair Shop.
(c) Paint and Sign Shop
(d) Equipment has now been provided in the Laboratory at base Camp in Km 26+000.
Consultancy Services as Independent Engineers for Access controlled highway M/s CEG Ltd
From Bangalore to Nelamangala section of NH-4 (Km 10.00 to Km 29.50) Bangalore
O & M Progress Report August-2017 21
7.5 Highway Traffic Management System (HTMS):
There are 2 VMS on each side of main carriageway and 3 CCTVs. CCTV system does
not cover the entire area, and observed during the site inspection and found that All the
3 CCTVs and ATCC, MET were not working. ECB are not functioning as most of
them are damaged, and in absence of electricity power break down, no back up is
available at all locations. The system of ECB needs to be set in order without delay.
The Concessionaire has submitted the alternate proposal of providing help line number
in lieu of the ECB, which was forwarded to NHAI and NHAI has not agreed for the
proposal.
7.6 Operation of Toll plazas:
At present the six lanes provided for collection of toll fees from vehicles are not
sufficient at Toll Plaza at Km 14.825 and at Km 26.050. On many occasions, there are
long queue more than the permissible of 5 vehicles (5 vehicles/lane max. allowed in
the Agreement). The Concessionaire to conduct traffic survey for the purpose of
determination and verification of the actual traffic on the Project Highway.
7.7 Corridor Control for preventing Encroachments, unauthorized parking and
construction of entrance connection on Project highway:
It has been observed that unauthorized posters, bills and other advertisement signs are
being installed/erected on the project Highway. The Concessionaire is required to
ensure that no unauthorized sticking/erecting of posters/bills are allowed with in the
ROW of the Project Highway.
7.8 Highway Lighting:
The luminance provided in stretch from Km 10.000 to Km 29.500 is Moderately
satisfactory. Concessionaire has been instructed to rectify light points to match with
the requirements.
7.9 Arboriculture & Landscaping:
Avenue plantation provided along the ROW on both side of the Project Highway has
been damaged in about 20% area, of course mostly due to the parking by Trucks.
However there are stretches available along the Highway, where parking problem is not
there, especially near the Bye pass at Nelamangala and at underpasses more plantation
should be provided in lieu of the damaged plants in other areas.
7.10 Building Maintenance including other facilities:
Concessionaire has not taken up the annual maintenance of toll plazas and all buildings
of other facilities provided by the Concessionaire under the scope of works (Schedule
‘C’). These are required to be taken up without further delay.
7. 11 Redressal of Public Grievances:
The Concessionaire has instructed to maintain complaint register for the public
grievances redressal at both the main Toll Plazas at Km 14.800 and Km 26.000. The
Complaint register must be contain with their names, address and telephone numbers.
Consultancy Services as Independent Engineers for Access controlled highway M/s CEG Ltd
From Bangalore to Nelamangala section of NH-4 (Km 10.00 to Km 29.50) Bangalore
O & M Progress Report August-2017 22
7.12 Over Lay Due:
The Concessionaire have been started the trail patch of BT from Km25+950 to Km
25+840 RHS S/R near to Base camp from Source-1. Periodical renewal laying work
have been started on 15th
April 2016, cumulative periodical renewal of laying is done
up to end of July 2017, as follows:
1) 15.00 Km RHS Service road completed in the month of March 2017.
2) 15.00 Km RHS Main Carriageway completed, in the month of August-2017.
3) 9.00 Kms (4.500 kms LHS and 4.500 kms RHS) Main Carriageway below
Elevated Highway completed, in the month of September 2016.
4) 4.50 kms LHS Service road Below Elevated Highway completed in February-2017.
5) 1.33kms RHS Service road Below Elevated Highway up to end of August-2017.
6) 15.00 kms Service Road on LHS up to end of March-2017.
7) 15.00 kms MCW-LHS up end of July-2017.
8) Elevated Highway:- 4.350 Km RHS & LHS completed in month of August-2017.
DBM: 11.00 Kms MCW on LHS, 11.00 Kms MCW on RHS completed in the month
of August-2017.
Against total quantity of 87 Kms (includes Elevated Highway, Both MCW and Both
SR) concessionaire completed 83.53 Kms up to the end of August-2017.
*****
Consultancy Services as Independent Engineers for Access controlled highway M/s CEG Ltd
From Bangalore to Nelamangala section of NH-4 (Km 10.00 to Km 29.50) Bangalore
O & M Progress Report August-2017 23
8.0 DEFICIENCIES & ACTION TAKEN:
In accordance to the requirement of the Clause 19.2, IC during his monthly inspection
report has pointed out defects and deficiencies for remedy by the Concessionaire on the
Project Highway in the O&M period. The Concessionaire has started to carryout
rectification works and is yet to submit para wise compliance.
The details of the Site Instructions issued to the Concessionaire on account of defects
and deficiencies on the Project Highway. The Detailed status of the SI attached in
Annexure-5.
1) Site Instructions SI-001 to SI-002 – issued in the month of December-2015.
2) Site Instructions SI-003 to SI-011 – issued in the month of January-2016.
3) Site Instructions SI-012 to SI-015 – issued in the month of February-2016.
4) Site Instructions SI-016 – issued in the month of April-2016.
5) Site Instructions SI-017 to SI-018 – issued in the month of May-2016.
6) Site Instructions SI-019 to SI-021 – issued in the month of June-2016.
7) Site Instructions SI-022 – issued in the month of August-2016.
8) Site Instructions SI-023 – issued in the month of September-2016.
9) Site Instructions SI-024 to SI-025 issued in the month of October-2016.
10) Site Instructions SI-026 to SI-031 issued in the month of December-2016.
11) Site Instructions SI-032 to SI-033 – issued in the month of January-2017.
12) Site Instructions SI-034 to SI-037 – issued in the month of February-2017.
13) Site Instructions SI-038 to SI-039 issued in the month of March-2017.
14) Site Instructions SI-40 to SI-043 – issued in the month of April-2017.
15) Site Instructions SI-44 to SI-047 – issued in the month of May-2017.
16) Site Instructions SI-47-A – issued in the month of June-2017.
17) Site Instructions SI-48 to SI-54 – issued in the month of July-2017.
18) Site Instruction SI-55 – issued in the month of August-2017.
Some of the above works are still under progress.
*****
Consultancy Services as Independent Engineers for Access controlled highway M/s CEG Ltd
From Bangalore to Nelamangala section of NH-4 (Km 10.00 to Km 29.50) Bangalore
24 O & M Progress Report August-2017
9. RECOMMENDATIONS
Following actions by the Concessionaire are recommended for better maintenance of highway:
Round the clock attention to traffic management issues.
Round the clock attention to safety management to create safe environment.
Round the clock attention to carriageway maintenance issues.
Round the clock attention to Corridor control to ensure prevention of encroachments.
Senior management should inspect the highway at regular interval to ensure his team is performing the duties as per scope of the Maintenance Manual and Concession
Agreement.
The Concessionaire has instructed to conduct traffic survey for the purpose of determination and verification of the actual traffic on the Project Highway.
The Concessionaire has instructed to maintain complaint register for the public
grievances redressal at the main Toll Plazas at Km 14+800 and Km 26+000. The
Complaint register must be containing with their names, address and telephone.
The Concessionaire has instructed to mobilize sufficient qualified technical staff to rectify the Operation and maintenance issues.
*****
Consultancy Service as Independent Engineers for Access controlled Highway From Bangalore to
Nelamangala section of NH-4 (Km 10.00 to Km 29.50)
M/s CEG Ltd
Bangalore
A B C D E F G H I
Location Nature Classification Causes Road Feature Road ConditionJunction
TypeWeather Vehicle No & Details Fatal Grievous Minor Non-Injured
1 01-08-17 10:30PM LHS 19.900 M/C 3 4 2 & 3 3 4 N/A 4 KSRTC BUS ( KA 19 F 3019)HIT TO LCV ( KA 12 A 9345) 0 0 0 0 0 0 RPO 0127 NO INJURY, NO PROPERTY DAMAGES, INFORMED TO POLICE & KEY PERSONS.
2 04-08-17 08:40PM LHS 23.700 M/C 2 3 5 3 1 N/A 1 UNKNOWN LCV HIT ROAD CROSSING PERSON/ 0 0 1 0 0 0 AMB & 3526 PROVIDED FIRST AID, NO PROPERTY DAMAGES & INFORMED KEY PERSONS.
3 05-08-17 03:55AM RHS 18.600 M/C 2 1 5 3 4 N/A 1 CAR ( KA03 D 6436 ) HIT PEDESTRIAN 1 0 0 0 0 0 RPO 3526,AMBDEAD BODY SHIFTED TO NELAMANGALA GOVT HOSPITAL INFORMED KEY PERSON & POLICE
STATION
4 06-08-17 07:40PM RHS 18.600 M/C 3 4 3 3 4 N/A 1CAR(KA.51.MA.6267) HIT CAR(KA.02.AB.5847) HIT CAR(KA.04.D.3358) HIT KSRTC
BUS (KA.40.F.856)0 0 0 0 0 0 RPO-3526 NO INJURY, NO PROPERTY DAMAGES, INFORMED TO POLICE & KEY PERSONS.
5 08-08-17 03:15PM RHS 18.000 S/R 2 4 4 2 2 N/A 1 BIKE(KA.02.JG.7967) HIT BIKE(KA.50.R.2896) 0 0 0 0 0 0 RPO-3526NO INJURY, NO PROPERTY DAMAGES & INFORMED KEY PERSONS. BOTH VEHICLES HANDOVER
TO NEL TRAFFIC POLICE STATION
6 09-08-17 6:00AM RHS 17.500 M/C 2 4 4 2 2 N/A 1 CAR(KA.31.N.0736) WENT ON DEVIDER 0 0 1 0 0 0 AMB-3526 1PERSON MINER INJURI NOPROPERTY DAMAGES & INFORMED ALL KEY PERSONS.
7 09-08-17 02:50PM RHS 22.600 M/C 3 1 2 & 3 3 1 N/A 1 UNKNOWN VEHICLE HIT (KA 04 HT 0840) 1 0 0 0 0 0 AMB-3526DEAD BODY SHIFTED TO NELAMANGALA GOVT HOSPITAL ,INFORMED POLICE BIKE
HANDOVERED TO STATION . NO PROPERTY DAMAGED INFORMED TO ALL KEY PERSON.
8 11-08-17 06:20AM RHS 26.200 M/C 3 2,3 & 4 2 & 4 4 7 N/A 1 LCV ( KA 53 5136) HIT TO UNKNOWN VEHICLE 0 2 3 1 0 0 AMB, RPO 0127 & TOWING INJURY PERSONS SHIFTED TO NEL. GOVT HOSPITAL INFORM TO POLICE & KEY PERSONS.
9 13-08-17 07:30PM RHS 21.500 M/C 3 2 4 4 1 N/A 1 CAR(KA 02 MD 8050) HIT ROAD CROSSING PERSON 0 1 0 0 0 0 AMBSHIFTED TO NEL GOVT HOSPITAL, NO PROPERTY DAMAGES, VEH H/O TO POLICE STN,
INFORMED NHAI & KEY PERSONS.
10 13-08-17 05:AM RHS 26.200 M/C 3 4 4 4 1 N/A 1 MAV(KA 51 A 4917) HIT BUS(KA 51 B 5566) 0 0 0 0 0 0 RPO 0127 MAV HIT BUS NO INJURIES AND NO PROPERTY DAMAGES INFORMED ALL KEYPERSONS
11 14-08-17 06:15PM RHS 23.150 M/C 2 1 2 2 1 N/A 1 CAR(KA 01 AF 9678) HIT ROAD CROSSING PERSON 1 0 0 0 0 0 AMB, RPO 0127 & TOWINGDEAD BODY SHIFTED TO NELAMANGALA GOVT. HOSPITAL, NFORMED POLICE STATION AND
KEYPERSON NO PROPERTY DAMAGE
12 14-08-17 06:15PM LHS 19.350M/C 2 1 4 2 1 N/A 1 MAV (HR 55 L 2504) HIT UNKNOWN VECHILE 0 0 0 0 0 0 AMB, RPO 0127 MAV HIT UNKNOWN VEHICLE INJURIES AND NO PROPERTY DAMAGES INFORMED ALL
KEYPERSONS
13 14-08-17 05:30AM RHS 15.500 M/C 3 4 4 3 1 N/A 1 TRUCK(KA 16 9645) HIT BT MACHINE 0 0 0 0 0 0 RPO(3526) NO PROPERTY DAMAGES, INFORMED POLICE & KEY PERSONS.
14 15-08-17 01:30PM RHS 26.000 M/C 3 3 4 3 1 N/A 1 MAV(HR.55.Y.0938) HIT CAR(KA.44.7909) 0 0 0 0 0 0 RPO(3526) NO PROPERTY DAMAGES, INFORMED POLICE & KEY PERSONS.
15 15-08-17 09:25PM LHS 19.400 M/C 3 1 2 4 1 N/A 4 CAR(KA 05 MS 8882) HIT MAV (HR 55 L 2504) 0 0 0 2 0 0 RPO(0127 & AMB )CAR HIT MAV 1 PERSON MAJOR INJURED SHIFTED TO HARSHA HOSPITAL INFORMED TO
POLICE & KEY PERSONS.
16 16-08-17 11.30AM LHS 17.450 M/C 2 2 2 3 1 N/A 1 UNKNOWN VEHICLE HIT ROAD CROSSING PERSON 0 1 0 0 0 0 RPO(0127 & AMB )UNKNOWN VEHICLE HIT ROAD CROSSING PERS0N MAJOR INJURED SHIFTED TO VP MAGNUS
HOSPITAL INFORMED ALL KEYPERONS AND NELAMANAGALA POLICE.
17 17-08-17 07:20PM RHS 21.150 SER 2 2 5 2 1 N/A 4 BIKE HIT PEDESTRIAN 0 1 0 0 0 0 AMBULANCE INJURY PERSONS SHIFTED TO NEL. GOVT HOSPITAL INFORM TO POLICE & KEY PERSONS.
18 19-08-17 08:10AM LHS 18.700 M/C 3 4 2,3 & 4 3 1 N/A 4CHAIN ACCIDENT 1 TRUCK & 3 CARS(TRUCK TN 34 S 7585, CARS- KA 02 MH 4941,
KA 53 MD 3950 & KA 05 MF 2774)0 0 0 0 0 0 RPO 0127 NO INJURY & NO PROPERTY DAMAGES, INFORMED POLICE & KEY PERSONS.
19 21-08-17 1:10AM LHS 28.500 M/C 3 3 2 3 1 N/A 4 BIKE(kA 04 JG 8516) HIT UNKNOWN VEHICLE 0 0 1 0 0 0 RPO(0127 & AMB ) 1 PERSON MINOR INJURI SHIFTED TO HARSHA HOSPITAL INFORMED POLICE & KEY PERSONS.
20 22-08-17 12:20PM LHS 10.350 UNDER FLY OVER 6 4 2 & 3 3 1 N/A 1 CAR (KA 04 MP 5939) UPSIDE AND HIT MEDIAN GREEN GRILLS 0 0 0 0 0 0 RPO 3526 .10 METER MEDIAN GREEN GRILLS DAMAGED . NO INJURIES . INFORMED TO POLICE AND ALL
KEY PERSONS.
21 23-08-17 02:30PM RHS 22.350 M/C 4 3 4 3 1 N/A 1 UNKNOWN VEH HIT LCV(KA 03 C 0610) 0 0 1 0 0 0 AMB & 0127 FIRST AID PROVIDED, NO PROPERTY DAMAGES & INFORMED KEY PERSONS.
22 25-08-17 09:00AM LHS 17.200 M/C 2 1 5 3 1 N/A 1 CAR(KA 03 MR 8587) HIT ROAD CROSSING PERSONS. 1 0 0 0 0 0 AMB & 3526DEAD BODY SHIFTED TO NEL GOVT HOSPITAL, NO PROPERTY DAMAGES, INFORMED KEY
PERSONS & NHAI PERSONALS.
23 25-08-17 03:30PM RHS 19.500 M/C 2 1 4 3 1 N/A 3 AUTO (KA 02 AF 3357) HIT CAR (KA 03 AC 5385) 0 0 1 0 0 0 RPO 0127 & AMB INJURY PERSONS SHIFTED TO PRIVATE VEHICAL INFORM TO POLICE & KEY PERSONS..
24 26-08-17 03:00AM LHS 28.000 M/C 2 3 2 & 3 3 1 N/A 1 UNKNOWN VEH HIT BIKE(KA 02 JD 2557) 0 0 1 0 0 0 AMB & 3526INJURED SHIFTED TO MAGNUS HOSPITAL, NO PROPERTY DAMAGES & INFORMED KEY
PERSONS.
25 27-08-17 03:45PM RHS 14.500 M/C 2 3 4 3 1 N/A 1 BIKE(KA 02 HJ 1468) HIT MAV(KA02 B 9675) 0 0 1 0 0 0 3526 INJURED SHIFTED BY 108 AMB, NO PROPERTY DAMAGES & INFORMED KEY PERSONS.
26 27-08-17 03:00AM RHS 12.000 ELE 8 4 3 1 1 N/A 1 LCV(KA 16 B 8646) UNSIDE 0 0 0 0 0 0 0127, 3526 & HYDRA NO PROPERTY DAMAGES, PROVIDE HYDRA & VEHICLE CLEARED & INFORMED KEY PERSONS .
27 28-08-17 06:00PM LHS 23.600 UNDER PASS 2 4 4 2 2 N/A 1 CAR(KA03 MN 9262) HIT CAR(KA 05 Z 5155) 0 0 0 0 0 0 3526 & TOWINGNO PROPERTY DAMAGES, BOTH VEHICLES HANDED OVER TO POLICE STATION , INFORMED
POLICE & KEY PERSONS.
28 30-08-17 06:30PM LHS 12.900 ELE 3 4 2 2 1 N/A 1 CAR(KA04 ME 4592) HIT MAV(PB 02 CC 7545) 0 0 0 0 0 0 RPO 0127NO PROPERTY DAMAGES, BOTH VEHICLES HANDED OVER TO POLICE STATION , INFORMED
POLICE & KEY PERSONS.
4 5 10 3 0 0
A
B
C
D
E
F
G
H
F
G
H
ANNEXURE-1 ACCIDENTS REPORT FOR THE MONTH OF AUGUST - 2017
SL. No Date Time
Affected personsNo.of Animals
injuredNo.of Animals killed
Help provided by Ambulance/Patrol
VehicleRemarks
1-T-junction,2-Y-junction,3-Four armed junction,4-Straggerred junction,5-junction with more than 4 arms,6-Round about junction,7-Manned rail.
1-Fine,2-Mist/Fog,3-Cloudy,4-Light rain,5-Heavy rain,6-Hail/Sleet,7-Snow,8-Strong wind,9-Dust storm,10-Very hot,11-Very cold,12-Others
TOTAL
NOTE:-
urban/Rural and details of surrounding land use
1-overturning,2-Head on collision,3-Rear end collison,4-Collision brush/side wipe,5-Left turn collision,6-Skidding,7-Right turn collisoin,8-Others
1-Fatal,2-Grievous injured,3-Minor injured 4-Non injured
1-Drunken,2-Over speeding,3-Vehicle out of control,4-Fault of driver,5-Fault of pedestrain passanger,6-Defect in road surface
1-Single lane,2-Two lanes,3-Three lanes or more without divider(median),4-Four lanes or more with central divider.
1-Straight road,2-Slight curve,3-Sharp curve,4-Flat road,5-Gentle incline,7-Hump,8-Dip,9-Others(pl specific)-Straight road with bus stand.
1-T-junction,2-Y-junction,3-Four armed junction,4-Straggerred junction,5-junction with more than 4 arms,6-Round about junction,7-Manned rail.
1-Fine,2-Mist/Fog,3-Cloudy,4-Light rain,5-Heavy rain,6-Hail/Sleet,7-Snow,8-Strong wind,9-Dust storm,10-Very hot,11-Very cold,12-Others
1-Straight road,2-Slight curve,3-Sharp curve,4-Flat road,5-Gentle incline,7-Hump,8-Dip,9-Others(pl specific)-Straight road with bus stand.
25 O & M Progress Report August-2017
Consultancy Services as Independent Engineers for Access controlled highway
From Bangalore to Nelamangala section of NH-4 (Km 10.00 to Km 29.50)
M/s CEG Ltd
Bangalore
MIN (0C) MAX (
0C)
1 1-Aug-17 29 23 0 0 Sunny
2 2-Aug-17 31 26 0 0 Sunny
3 3-Aug-17 30 25 0 0 Sunny
4 4-Aug-17 28 25 0 0 Sunny
5 5-Aug-17 30 32 0 0 Sunny
6 6-Aug-17 28 31 0 0 Sunny
7 7-Aug-17 27 31 0 0 Rainy
8 8-Aug-17 28 30 0 0 Sunny
9 9-Aug-17 31 28 0 0 Cloudy
10 10-Aug-17 31 28 0 0 Sunny
11 11-Aug-17 30 31 0 0 Sunny
12 12-Aug-17 29 29 0 0 Sunny
13 13-Aug-17 27 30 0 0 Sunny
14 14-Aug-17 27 30 0 0 Sunny
15 15-Aug-17 25 30 0 0 Sunny
16 16-Aug-17 29 30 0 0 Sunny
17 17-Aug-17 28 27 0 0 Cloudy
18 18-Aug-17 27 26 0 0 Cloudy
19 19-Aug-17 27 26 0 0 Cloudy
20 20-Aug-17 28 25 0 0 Cloudy
21 21-Aug-17 29 24 0 0 Cloudy
22 22-Aug-17 31 27 0 0 Cloudy
23 23-Aug-17 30 31 0 0 Cloudy
24 24-Aug-17 30 31 0 0 Cloudy
25 25-Aug-17 31 31 0 0 Cloudy
26 26-Aug-17 30 31 0 0 Rainy
27 27-Aug-17 31 28 0 0 Rainy
28 28-Aug-17 29 28 0 0 Rainy
29 29-Aug-17 30 27 0 0 Rainy
30 30-Aug-17 29 26 0 0 Rainy
31 31-Aug-17 30 27 0 0 Rainy
ANNEXURE-II: WEATHER REPORT FOR THE MONTH OF AUGUST-2017
Sl.NO DATE TEMPERATURE
RemarksRain Fall
mm
Cum. Rain
Fall mm
26 O & M Progress Report August-2017
Consultancy Services as Independent Engineers for Access Controlled
Highway From Bangalore to Nelmangala section of NH-4(Km.10.00 to Km.29.50)
M/s CEG Ltd
Bangalore
TESTED PASS FAIL1 CONCRETE
i) Fine Aggreate 12 12 0
a Gradation /Sieve Analysis 1 Test /day 12 12 0
ii) Coarse Aggreate 12 12 0
a Gradation /Sieve Analysis 1 Test /day 12 12 0b Aggreate Impact Value 1 Test /day 12 12 0c Flakiness Index 1 Test /day 12 12 02 Concrete Cube Testing (WIM)
M-15a 7 - DAYS 0 0 0b 28 - Days 4 4 0
M -35a 7 - DAYS 3 3 0b 28 - Days 9 9 03 Concrete Cube Testing (VUP)
M-15a 7 - DAYS 0 0 0b 28 - Days 0 0 0
M -30a 7 - DAYS 8 8 0b 28 - Days 12 12 04 Subgradea Free swell index(FSI) 4 4 0b Grane size analysis (GSA) 4 4 0c Atterberg limt 0 0 0d Proctor Density 4 4 0e CBR 1 test /3000m3 2 2 0f Field Density Compaction 1 Test /500m2 0 0 05 GSBa Gradation /Sieve Analysis 1 test /200m3 0 0 0b Atterberg limt 1 test /200m3 0 0 0c Field Density Compaction 1 Test /500m2 0 0 06 WMMa Gradation /Sieve Analysis 1 test /100m3 0 0 0b Aggreate Impact Value 1 test /200m3 0 0 0c EI&FI 1 test /200m3 0 0 0d Atterberg limt 1 test /100m3 0 0 0e Field Density Compaction 1 Test /500m2 0 0 07 Bituminous Worksa Prime coat 1 Test /500m2 0 0 0b Tack coat 1 Test /500m2 118 118 08 DBMa Aggreate Impact Value 1 test /50m3 4 4 0b Combined Flaki&Elongation Index 1 test /50m3 4 4 0c Dry Gradation 4 4 0d Extraction 4 4 0e Marshall Stability Test 4 4 0f Core density 1 test /250m2 28 28 09 BCa Aggreate Impact Value 1 test /50m3 38 38 0b Combined Flaki&Elongation Index 1 test /50m3 38 38 0c Dry Gradation 34 34 0d Extraction 34 34 0e Marshall Stability Test 34 34 0
f Core density 1 test /250m2 202 202 0
6 Cubes / day *
If Concrete quantity exceeds,
No.of samples as per clause
1716.2.4.
2 test /3000m3
2 Tests /400 tonnes
2 Tests /400 tonnes
ANNEXURE-III QC TEST REPORTS FOR THE MONTH OF AUGUST-2017
Sl.N
ODescription of test
Test Frequency
(Minimum)
Test Conducted in August -
2017
6 Cubes / day *
If Concrete quantity exceeds,
No.of samples as per clause
1716.2.4.
27 O & M Progress Report August-2017
Consultancy Services as Independent Engineers for Access controlled highway M/s CEG Ltd From Bangalore to Nelamangala section of NH-4 (Km 10.00 to Km 29.50) Bangalore
28 O & M Progress Report August-2017
ANNEXURE-IV:
EMERGENCY SERVICE LOCATIONS ALONG PROJECT HIGHWAY
Sl.No. Description Contact No.
A. Major Hospitals & Ambulance Services
1. NBTPL Ambulance Service 080-50050056
2. Emergency Ambulance 108
3. Sarojini Hospital 080-28396739 &
9880823924
4. Premier Sanjeevani Hospital 080-65375555 & 65374444
5. Ramachandra Hospital 080-28372888 &
9880714563
6. Harsha Hospital 080-27723697
B. Police Stations
1. Peenya Police Station 080-22942532
2. Madnayakanahalli Police Station. 080-23713699
3. Nelamangala Police Station 080- 27722133
C. Police Highway Patrol Units
1. Peenya Traffic Police. 080-22943020
2. NBTPL Patrolling 080-50050056
D. Fire Stations
1. AMPC 080-29171500 (or) 101
2. Nelamangala 080-27726999 & 27726570
E. Crane Towing Services
1. Crane and Towing Operator 080-50050056
*****
Consultancy Services as Independent Engineers for Access Controlled Highway
From Bangalore to Nelmangala section of NH-4(Km.10.00 to Km.29.50)
M/s CEG Ltd
Bangalore
Concessionaire
Letter NoCOMPLIANCE REPORT
1 CEG/IE/SI/O&M/SAFETY/HIGHWAY/55(A) 03.08.2017
We are collected Road Studs jointly all three colour
samples(i.e White, Red & Amber) in the month of 1st week
of may and sent third party laboratory for testing,but till
date not submitted third party test reports. Hence we are
instructing to submit above all 3 colour Road Studs test
report as early as possible.
ANNEXURE-V: ABSTRACT OF SITE INSTRUCTIONS August - 2017
SL. NO IE SITE INSTRUCTION NUMBER DATE BRIEF DESCRIPTION OF THE SITE INSTRUCTION
ACTION TAKEN BY THE CONCESSIONAIRE
COMMENTS BY IC
29 O & M Progress Report August-2017
Consultancy Services as Independent Engineers for Access controlled highway M/s CEG Ltd
From Bangalore to Nelamangala section of NH-4 (Km 10.00 to Km 29.50) Bangalore
30 O & M Progress Report August-2017
ANNEXURE VI - PHOTOGRAPHS:
Construction of VUP (Traffic Diversion) :-
Consultancy Services as Independent Engineers for Access controlled highway M/s CEG Ltd
From Bangalore to Nelamangala section of NH-4 (Km 10.00 to Km 29.50) Bangalore
31 O & M Progress Report August-2017
SWB & WIM :-