STP 3 & 4 Emergency Plan
Rev. 02
I Protective ResponseThis section of the Plan describes the protective response actions for the protection of site and offsite personnel in the plume exposure pathway. This Emergency Plan is applicable to the South Texas Project Electric Generating Station and the Emergency Planning Zone within the 10-mile and 50-mile radius of the Station. Maps depicting the 10 and 50 mile Emergency Planning Zones are included as Figures I-1 and I-2.
I.1 Onsite Personnel NotificationOnsite personnel are notified of an emergency via the Station Public Address Paging System. The Emergency Director, or his designee, will announce the emergency classification and other pertinent data relating to the emergency classification to Station personnel using the Station Public Address Paging System on site. This system is described in Section E of this Plan. Persons within the Protected Area are notified of the emergency classification via the Public Address Paging System. Notification of personnel located onsite but outside the Protected Area is accomplished through emergency sirens, Public Address announcements, pocket pager activation, and by Security Force personnel. To comply with emergency classification and severity, evacuation within the Protected Area will be initiated for non-essential personnel at a Site Area Emergency classification or if not already performed at a General Emergency classification (optional at an Unusual Event or Alert). The sounding of the alarms over the Public Address Paging System occurs for both classifications. Inside plant buildings, where hearing is difficult due to high ambient noise levels, flashing lights are used to supplement the Public Address Paging System.
I.2 Assembly and AccountabilityProtected Area assembly and accountability is initiated at the Emergency Director's discretion or when either a Site Area Emergency or a General Emergency has been declared. Protected Area assembly and accountability must be initiated when a Site Area Emergency or General Emergency is involved. Appropriate actions are implemented by 0ERP01-ZV-IN04, Assembly and Accountability and in Section F.3 of this Plan.
I.3 Site EvacuationSite evacuation will be performed in accordance with 0ERP01-ZV-IN05, Site Evacuation and Section F.5 of this Plan, after assembly and accountability is completed.
I.4 Onsite ShelterThe Emergency Response Organization (ERO) monitors hazards and appropriate protective actions are taken for emergency workers. Station nonessential personnel shelter instructions are contained in Emergency Response Procedure 0ERP01-ZV-IN05, Site Evacuation and Section F.6 of this Plan.
Protective Response I-1
STP 3 & 4 Emergency Plan
Rev. 02
I.5 Protective Action RecommendationsThe Station is designed and equipped with a series of safety systems engineered to meet Title 10 Code of Federal Regulations Part 100 criteria for reactor safety. The Station recognizes that in any accident situation, it is prudent and logical to make every effort to reduce and minimize exposure of the public to radioactive materials and radiation. This is accomplished by issuing offsite protective action recommendations when plant conditions indicate a potential for release of radioactive material or if a release is occurring or has occurred. The Protective Action Guidelines for the general public for thyroid dose due to inhalation from a passing plume and exposure to airborne radioactive material, as recommended by the Environmental Protection Agency, are five (5) rem Thyroid Committed Dose Equivalent and one (1) rem Total Effective Dose Equivalent respectively. Additional information is provided in Addendum I-1.
Recommendations for protective actions for the general public will originate from the Control Room, the Technical Support Center, or the Emergency Operations Facility (depending on facility activation and Emergency Director location) based on plant conditions and/or based on data derived from offsite dose assessment or actual field monitoring measurements. Emergency Response Procedures establishing these methodologies are 0ERP01-ZV-TP01, Offsite Dose Calculations and 0ERP01-ZV-IN07 Offsite Protective Action Recommendations. These procedures establish methods for determining projected dose to the public at risk. Recommendations will be made in accordance with agreements made with the Department of State Health Services. Whenever possible, message formats provided in the Emergency Response Procedure 0ERP01-ZV-IN02, Notifications to Offsite Agencies, in accordance with Section E of this Plan will be utilized. The implementing procedures relating to Protective Action Guidelines assure that the recommendations are determined through an approved process. The Emergency Director shall approve Offsite protective action recommendations.
I.6 Public NotificationIn the event public notification is required, both transient and resident population within the ten mile Emergency Planning Zone will be initially notified through the Prompt Notification System as referenced and described in Section E of this Plan and by the Matagorda County officials. Additional notification and information will be provided to the transient and resident population as well as the general public outside the ten mile Emergency Planning Zone through the Emergency Alert System. Radio station KMKS FM, Bay City, is the primary Emergency Alert System station for the Station nuclear emergency response and KZRC FM is secondary. Information brochures and other public information documents describing notification, protective actions and general radiological education are provided by mailing and by general distribution to residents and transients within the ten mile Emergency Planning Zone. Matagorda County will issue messages similar to those provided in the Matagorda County Emergency Management Plan describing the incident and recommended public protective actions.
I-2 Protective Response
STP 3 & 4 Emergency Plan
Rev. 02
I.6.1 Public Shelter and EvacuationShelter and Evacuation recommendations from the Station and/or the Department of State Health Services are considered, and appropriate actions are determined and conducted by Matagorda County officials. Pertinent information from the evacuation time estimate1 has been incorporated into Matagorda County emergency procedures.
The evacuation time estimate study is maintained by and on file in the Station Emergency Response Division.
I.6.2 Special Needs GroupsIndividuals with special needs will be accommodated as per Matagorda County plans and procedures.
I.7 Environmental Monitoring PointsIn the event of an emergency, the permanent air sampling stations may be utilized for long term evaluation concerning airborne releases. Environmental Thermoluminescent Dosimeters located at the background radiation stations provide exposure data. At least one dosimeter shall remain at each station until the end of the event to provide integrated dose data over the duration of the release. Sampling efforts may be combined with Offsite Field Team activities.
1 Evacuation Time Estimates for the South Texas Project Electric Generating Station Plume Exposure Pathway Emergency Planning Zone, Earth Tech 1994 KLD Associates, 2007
Protective Response I-3
I-4Protective R
esponse
STP 3 & 4
Emergency Plan
Intracoastal Waterway east of the Colorado River.y's Bayou which includes the town of Matagorda,
ich includes El Maton and Buckeye.portion of the Colorado River, north of Wilson Creek,portion of FM 1095, south of SH 35 west of the
ting Station within these boundaries: East of thegenerally north of the South Texas Project Electric
Tidewater Oaks, Tres Palacios Oaks.d the Tres Palacios River, north of FM 521, and whichth of SH 35, west of the northern portion of FMGenerating Station within these boundaries: Eastgenerally northwest of the South Texas Project
portion of Tres Palacios Bay.lough, and which includes Collegeport and the
south of FM 521, west of FM 1095, and MadGenerating Station within these boundaries: East ofgenerally southwest of the South Texas Project
th of West Matagroda Baysouth property boundary, west of the Colorado River,lough, south of the South Texas Project Generating
ting Station within these boundaries: East of Madgenerally south of the South Texas Project Electric
th of the protection levy at Matagorda, north ofwest of, CR 262, and CR 248, south of CR 237,Generating Station within these boundaries: East ofgenerally east and southeast of the South Texas Project
e Park, Hales Acres, and Meadowbrook Estates.CR 262, north of FM 521, FM 3057 and includesolorado River, south and west of Live Oak Creek,Generating Station within these boundaries: Eastgenerally northeast of the South Texas Project
ZONES AND POPULATIONS
8, and north of FM 521.s Palacios River, south of Wilson Creek, west ofGenerating Station within these boundaries: East ofgenerally northwest of the South Texas Project
Tin Top and Citrus Grove Community.f FM 521, west of CR 392, north of CR 391, and whichting Station within these boundaries: East of FM 1095,generally west of the South Texas Project Electric
s Selkirk Island, Exotic Isle, and Equistar.north of the protection levee at Matagorda, andrado River and Kelly Lake, south of FM 521, west ofGenerating Station within these boundaries: East ofgenerally southeast of the South Texas Project
21 East, and which includes Celanese.468, south of FM 3057, west of FM 2668, and northGenerating Station within these boundaries: Eastgenerally northeast of the South Texas Project
No population lives in this area.)hern portion of the Station.Generating Station and FM 521, running in an arc aroundgenerally north and northeast of the South Texas Project
PROTECTIVE RESPONSE
ZONE BOUNDARY DESCRIPTIONS
Rev. 02
Figure I-1 10 Mile Emergency Planning Zones
SW IT CH Y AR D
4T H ST RE E T
A U X.W A TE RT AN K
IV CF EE DT AN K
W A TE RF EE DA U X. CC LCC L
ST R UC TU R E
1
CA US T IC
E. C .W.IN TA K E
TG B
RC BFH BM E AB
DG B
TG B
M E ABFH B
IV CRC B
DG B
X
xx xxxxxxxxxxxx
x xxxxxxxxx xxxxxxxxx
x x x xxxx xxxx xx x
xxxxxxxxxxx
xx
x x xxx x xxx xx xx xx xx xx xxxxxxxxxxx xxxx
xx
xxx
xxxxx
xxxxx
xxxx
xx
xxxxxxxxxxxx
xxxxx
xxxxxxxxxxxxxxxxxx
xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx
xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx
x x
xxxxxxxxxxxxxxx xxxxxxxxxxxxxxxxxxx
xxxxxxxxxxxxxxxxx
xxxxxx xxxxxxxxxxxxxxxxxxxxxxxx x
xxxxxxxxx xxxxxxxxxxx x xxxxxxx xxx
x xxxxx xxxxxxxx
x
xxx
xx
xxxxxxx
xxxx
xx xx xx xx xx xx xx xx xx xx xx xx xx xx xx xx xx xx xxxx
xxxx xxxxxxxx xxxxxxxxxx
xx xxxxxx
xxxx
xxxx xx xxxxxxxxxx
x
x xx
xxxxx
xxx
xxx xxx
x
xxxx xxxxxx xx
x
xxxxxxxxxxxxxxxxxx xx x xx x x xx x x
xx x x xx xxx
x
xxxx x xxxxxxxx xxxxx
xx
xxx xx x xx xx xx x x
xxxxxxxx
xxxx xxxxx xxxxx
Baxte r
BlessingBlessing School Br
i ar
Buckeye
Cashs C reek
Citrus Grove
Collegeport
Crab
Dick
Dog
Donaldson
East
East Res ervoir
Egret I sland
El Maton
Freshwat er
Gillet t Lake
Got tschalk
Johnso
ns
Ke lly Lake
Li tt l e
Live
MadI sland
Markham
Matagorda
McN ab
McN abb
Mine
Palacios
Pelican
CR 325
Ratt lesnak e
Robbins
Robbin s Slough
Selkirk
Shell Lakes
Tidehaven
Tin Top
Pal
a cio
s
Wadsworth
West
Wild Cow
Wi ll ow
Willow
Wil s
on
1
SC
ALE
INM
ILES
Bay City
Lak e
Lak e
Lak e
Lak e
Lak e
Island
Island
Island
Island
Island
Lak e
Lak e
Island
RobbinsSl ough
Tres
Rive r
Tim
b er
Slough
Dam
Sloug
hCreek
Bran
chM
adIs
l an d
Slou
gh
Wes t
Branch
Mad
Islan
dS
l oug
h
Slough
Lak e
Lak e
Island
Bra n
chCo
lora d
oRiv
er
OakCr eek
Cottonwood
Creek
RIV
ER
OC
O
D
ARO
L
Le
Tul l e
Lak
e
P
P
High School
Tidehaven
Cree
k
Cul v
erC
ut
Communit y
RiversidePark
Junior High
OaksPalaciosTres
OaksTidewater
60
60
60
60
35
35
35
35
35
35
2668
3057
2668
2078
521
521
521
521
521
1468
1468
1095
1095
1095
2031
2853
2853
2853
459
2431
438
CR 371
CR 364
CR35
8
TRES
PALA
CI O
SB
AY
CR
365
CR 373
CR
378
CR 374
CR 372
CR 379
CR
388
CR
384
CR 390
CR 342
CR 385
CR
377
CR
387
CR 237
CR
262
EAST
MATAGO
RDABAY
WEST MATAGORDA BAY
CR
392
CR 391
CR
436
ROA
D
Equistar
CR 248
CR 244
CR 259
CR 171
New
C ut
PORT
Celanese
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
CR 323
CR 343
CR347
CR 346
CR349
CR 381
CR 224
CR 386
CR
383
CR 380
CR3
45
CR344
CR 357
CR358
CR 354
VACEK
RD
.
CR 352
CR 411
71 HALE'SAC RES
CEL
ANES
ER
D.
BUCK
EYE
RD.
Peyton
Creek
Wils
on
Cre
e k
MatagordaHarbor
CR 242
CR 239
CR 376
CR 348
CR 324
CR463
CR 432
CR 427CR
437
CR22
9
CR
263
CR
241
ad s
wo r t
h
S l
o u gh
CR444
Rat
tlesn
ake
Islan
dS
loug
h
35
ASHBYCEMETERY RD.
CR
428
ESTATESPR AIRIE
W
RE SPONSEEME RGENCY
NNNW
NW
WNW
WW
SW
SW
SSWS
SSE
SENE
NNE
0
315
270
225
180
135
90
4 5
ESEE
ENE
F.L
AW
Sc hool
FM521R iver Park
CR 355
CR 222
CR
243
CR
4 15
CR 356
CR
389
CR
305
CR
262
CR245
CR
247
CR394
CR 366
CR 237
Tres Palacios River
MeadowbrookEs tat es
3
9
4
8
10
11
52
1
6
and theSt. Mar
and whnorthernnorthernGeneraAn area
includes1095 anand souElectricAn area
northernIsland SSH 35,ElectricAn area
and norStationIsland SGeneraAn area
and souSH 60,ElectricAn area
Riversidwest ofof the CElectricAn area
650POPULATION6ZONE
POPULATIONPOPULATIONPOPULATIONPOPULATIONPOPULATION
BOUNDARYNOT DEFINED BY NATURAL LANDMARKS
POPULATION SOURCE: 2002 U.S. CE NSUS BUREAU / TEXAS STATEDATA CENTER, TEXAS A&M UNIVERS ITY
ZONEZONE
ZONEZONEZONE
1011
89
7
Zone 11Sub-total 2295
TOTAL 2875
692198
0237
518
POPULATIONPOPULATIONPOPULATIONPOPULATIONPOPULATION
Sub-total
ZONEZONEZONEZONEZONE
45
23
1
7
Zone 8
Zone 9
Zone 10
5682
40402
0
580
Zone 6
Zone 7
FM 146the TreElectricAn area
includessouth oGeneraAn area
includeSH 60,the ColoElectricAn area
of FM 5of FM 1ElectricAn area
(Note:the nortElectricAn area
Zone 4
Zone 5
Zone 2
Zone 3
Zone 1
SOUTH TEXAS PROJECT ELECTRIC GENERATING STATION 10-MILE EPZ
320
310
300
290
280
270
260
250
240
230
210
220
200
190
180170
160
150
140
130
120
110
100
90
80
70
60
50
40
30
20
360 10
0
330
340
N
P
Q
RA
B
C
D
F
HJ
K
LL
M
350
E
Legend
Major RoadElevated Surface
Paved RoadLow Surface
Gravel Surface
Dirt or GrassSurface
Gate
MatagordaElementary
1095
G
2
10Mi
5
11/20/03
STP 3 & 4 Emergency Plan
Rev. 02
Figure I-2 50 Mile Emergency Planning Zones
Protective Response I-5
STP 3 & 4 Emergency Plan
Rev. 02
Addendum I.1 Recommended Protective Actions for the PublicPage 1 of 1
1.0 Recognizing, in an accident situation, that it is prudent and logical to make every effort to reduce and minimize public exposure, the Station will make protective action recommendations to the State and County authorities. These recommendations are to assist the public officials in protecting the public in the Plume Exposure Pathway. It should be noted that the responsibility of final decision to implement offsite protective action recommendations made by the Station rests solely with Matagorda County authorities and respective authorities in other affected counties. Detailed instructions to implement protective actions will also be disseminated by County authorities.
2.0 The protective actions for offsite areas are discussed or presented in the State and County Emergency Management Plans. The State and County Plans have adopted the United States Environmental Protection Agency's Protective Action Guides for initiating actions to protect the health and safety of the public in the event of a nuclear power plant accident. These are the same guides used by the Station in developing their protective action recommendation to the State and County authorities. In addition, the Station has developed protective action recommendations based on plant conditions exclusive of actual or projected radiological exposures.
3.0 There are various types of actions that can be taken to protect the public. These include shelter, evacuation, access control, controlling distribution of food, water, milk, and livestock, and individual protective actions.
4.0 United States Environmental Protection Agency Protective Action Guidelines serve as the basis for offsite protective actions recommendations. The type, amount, and duration of the release source term, and the potential for radiological release based on plant conditions must also be considered when recommending protective actions.
5.0 Projected or measured doses that the public may be or is subject to receiving are correlated to protective action guides. Dose projections and measured dose are not prerequisites for issuance of a protective action recommendation.
6.0 The Emergency Director has the authority to make protective action recommendations and approve their release to governmental authorities. Protective action recommendations originate from the Control Room, Technical Support Center, Emergency Operations Facility or the Alternate Emergency Operations Facility based upon data derived from or received from assessment of plant conditions, radiological monitoring computer systems, field measurements, or process instrument readings. The Emergency Plan procedures relating to Protective Action Guides assure that recommendations are determined through an approved process. Emergency Plan Procedures, like the Plan, are based on the United States Environmental Protection Agency's Manual of Protective Action Guides and Protective Actions for Nuclear Incidents Environmental Protection Agency 400-R-92-001, revised May, 1992.
7.0 The Station agrees with the position of the State of Texas not to use radioiodine blocking drugs such as potassium iodide for the general public. It is the State's responsibility to stockpile and acquire the agent and disseminate it if it is to be distributed to the general public during an accident. The Station is responsible for maintaining and providing to the Department of State Health Services upon request, a quantity of potassium iodide sufficient for State and local emergency workers including any mobility impaired or institutionalized members of the general public whose evacuation could not be readily effected.
I-6 Protective Response