America’s Force of Decisive Action
I3C2 Program Update
AFCEA Luncheon
Army Acquisition, Logistics and Technology
Col Deb Theall PM, I3C2
Date 20 November 2013
![Page 2: I3C2%Program%Update% AFCEALuncheon%...We are systems integrator working with 7th & DISA in CONUS America’s Force of Decisive Action 13 Future Enterprise VoIP Architecture • UC](https://reader033.vdocuments.net/reader033/viewer/2022060517/604a2111cab0214c28686bf3/html5/thumbnails/2.jpg)
2 America’s Force of Decisive Action
Agenda
• Mission • Projects (the big ones & all the other ones) • The Network Today & Tomorrow • Institutional Capability Set (ICS) • Changes to Installation IT Modernization • NETMOD (focus on CONUS) • Enterprise VoIP • Pulling it all together at Fort Hood • NetOps − ESMSaaS − Transition
• YRP/LPP • The Other 100+ Projects • Conclusion
![Page 3: I3C2%Program%Update% AFCEALuncheon%...We are systems integrator working with 7th & DISA in CONUS America’s Force of Decisive Action 13 Future Enterprise VoIP Architecture • UC](https://reader033.vdocuments.net/reader033/viewer/2022060517/604a2111cab0214c28686bf3/html5/thumbnails/3.jpg)
3 America’s Force of Decisive Action
Mission
To modernize and deliver global network infrastructure, technologies, and capabili6es worldwide in direct support to the Army, joint troops and other mission and coaliCon partners enabling strategic informaCon sharing, enterprise services and command and control while transforming the network into a centralized, more secure, operaConalized, and sustainable enterprise.
![Page 4: I3C2%Program%Update% AFCEALuncheon%...We are systems integrator working with 7th & DISA in CONUS America’s Force of Decisive Action 13 Future Enterprise VoIP Architecture • UC](https://reader033.vdocuments.net/reader033/viewer/2022060517/604a2111cab0214c28686bf3/html5/thumbnails/4.jpg)
4 America’s Force of Decisive Action
Projects (the big ones)
• MPLS/JRSS/EUB&ADN
• YRP/LPP
• ESMSaaS
• Enterprise VoIP & Transitioning/Migrating off Legacy TDM
• NetOps Transition
• Life Cycle/Configuration Management IAW signed MOU − Data Centers/IPNs, ICAN, NetOps, AESD, etc
• Lowering Total Cost of Ownership – Bulk Buys, Bundling, Standardization
![Page 5: I3C2%Program%Update% AFCEALuncheon%...We are systems integrator working with 7th & DISA in CONUS America’s Force of Decisive Action 13 Future Enterprise VoIP Architecture • UC](https://reader033.vdocuments.net/reader033/viewer/2022060517/604a2111cab0214c28686bf3/html5/thumbnails/5.jpg)
5 America’s Force of Decisive Action
Projects (all the other ones) PdM/PD Proposed Projects = SRD Pre-Award Projects = Contract Post Award Projects = Capability
CONUS 45 8 44
OCONUS 25 8 15
Totals 70 16 59
What makes I3C2 Different? • We conduct surveys and initial engineering assessments and develop System Requirements Documents (SRDs) for every project • We go through the pre-award phase (PWS, IGCE) for every project • We don’t have an overarching integrator; we ARE the integrator • We span worldwide with a very complex stakeholder environment (COCOMS, AMC, FORSCOM, etc) and a product that is ubiquitous • We are in perpetual fielding working multiple phases of lifecycle ALL at the same time • Average total time to complete project from initial receipt to close is 48 months – depending on complexity, stakeholder involvement,
executive sponsorship and resources • Total dollar for Pre/Post Award projects is ~$920M
![Page 6: I3C2%Program%Update% AFCEALuncheon%...We are systems integrator working with 7th & DISA in CONUS America’s Force of Decisive Action 13 Future Enterprise VoIP Architecture • UC](https://reader033.vdocuments.net/reader033/viewer/2022060517/604a2111cab0214c28686bf3/html5/thumbnails/6.jpg)
6 America’s Force of Decisive Action
• ADN: Area Distribution Nodes • DEE: DoD Enterprise Email • DISN: Defense Information System Network • ETFM: Enterprise Telephony Firewall Management • EUB: End-user Building Switch • Gb/s IP: Gigabits per second Internet Protocol • ICAN: Installation Campus Area Network • Mbps: Megabits per second • MCN: Main Communication Node • PBX: Private Business Exchange • P/C/S: Post/Camp/Station • PSTN: Public Switched Telephone Network • RHN: Regional Hub Nodes • TLA: Top Level Architecture VCS: Video Conference Switch • TNOSCs: Theater Network Operations and Security
Center
The Network Today (FY13)
DISA
TNOSCs
NECs
AESD
SIG BDEs
SIG CMD
NETCOM
Customer Customer’s Command
Tech Channel
Command Channel
1-10 Gigabit IP 2-Leased circuits sized by P/C/S 3-Tactical unit reaches back to locally stored services and applications 4-Local TLA stacks (400+ in CONUS alone)
Global Defense Network
Home Work TDY
InstallaCon
Local Storage Local ApplicaCons Local SharePoint
Enterprise Business Systems
Army Enterprise Service Desk
Defense CollaboraCon
(DCO)
TLA
Internet
EUB
ICAN
User Data
MCN
ADN ADN ADN
EUB EUB
EUB User Voice PBX
User Video
PSTN
VCS
Varies, 600Mbps – up
100 Mbps
10/100 Mbps
ETFM
“Reach Back”
Deployed, TacCcal
Local Storage Local
ApplicaCons Local SharePoint
RHN
DEE Managed Service
FY 11-‐13
DISN SubscripCon
Service
10 Gb/s IP
Leased Circuits,
sized by P/C/S
IT Support
![Page 7: I3C2%Program%Update% AFCEALuncheon%...We are systems integrator working with 7th & DISA in CONUS America’s Force of Decisive Action 13 Future Enterprise VoIP Architecture • UC](https://reader033.vdocuments.net/reader033/viewer/2022060517/604a2111cab0214c28686bf3/html5/thumbnails/7.jpg)
7 America’s Force of Decisive Action
The Network Tomorrow
7
DISA
TNOSCs
NECs
AESD
SIG BDEs
SIG CMD
NETCOM
Customer Customer’s Command
Tech Channel
Command Channel
• ES: Enterprise Services • ITSM: IT Service Management • LSC: Local Session Controller • RSS: Regional Security Stack • UC: Unified Capabilities • VOIP: Voice Over Internet Protocol
IT Support
Global Defense Network
Internet
Home Work TDY
InstallaCon
Local ApplicaCons
Army Enterprise
Service Desk & ITSM
DEE Managed Service
Defense CollaboraCon
(DCO)
FY 11-‐13
EUB
ICAN
User Data
ADN ADN
EUB EUB
EUB User Voice
User Video
PSTN
10 Gb/s
“Reach to the cloud”
Local Storage Local
ApplicaCons Local SharePoint
RHN
100 Gb/s MPLS
FY 13-‐14 RSS
LSC
Failover & excepCons only
VOIP Managed Service
UC So_ware Managed Service
FY 14-‐15 FY 14-‐15
FY 14-‐15
Future ES
TacCcal EE
Can operate disconnected @mail.mil
FY 15-‐17
FY 15-‐17
Deployed, TacCcal
100 Gb/s MPLS FY 13-‐14
Voice / Video Convergence
DISN SubscripCon
Service
1-100 Gigabit MPLS / 100 Gigabit to P/C/S / 10 Gigabit to EUB 2-Enterprise Services and Applications in the cloud – Soldiers reach to the cloud 3-JRSS replaces local TLA stacks
![Page 8: I3C2%Program%Update% AFCEALuncheon%...We are systems integrator working with 7th & DISA in CONUS America’s Force of Decisive Action 13 Future Enterprise VoIP Architecture • UC](https://reader033.vdocuments.net/reader033/viewer/2022060517/604a2111cab0214c28686bf3/html5/thumbnails/8.jpg)
8 America’s Force of Decisive Action
Institutional Capability Set (Foundational Pieces)
CDC
ICAM
GFEBS
GCSS -A
IPN Core Data Centers: Enterprise Services and Applications are hosted from here
Joint Security Architecture: Performs network security, packet inspection, etc. for traffic going in and out of CDCs and at NIPRNet Hubs
WAN Capacity: Remove Legacy TLA stacks, Implement 10Gb MPLS cloud
Installation Campus Area Network (ICAN): Main Communications Nodes (MCN), Area Distribution Nodes (ADN), End User Building (EUB) switches
Installation Processing Nodes: Local Applications & Services are hosted here (e.g. print servers, thin client back-end, VoIP Local Session Controller), includes JIE-Lite Security
Land Mobile Radio: Towers and Radios, integrated with ICAN and IPN for installation emergency services
Host Security: including HBSS operationalization and Network Access Control (802.1x) to reduce impact of larger security enclaves
Army Enterprise Service Desk: Providing centralized, standard customer interface, standard service management and processes
VoIP/VoSIP: Services to replace aging legacy copper telephone switches
Installation as a Docking Station: Tactical forces connect to Enterprise Services via the ICAN
WAN Diversity: Add Physical, Path, and/or Logical Diversity.
Build Capacity: CONNECT
Improve Cyber Security: SECURE
Enterprise Services to the Edge: OPERATE
Build Capacity: CONNECT
Build Capacity: CONNECT
Build Capacity: CONNECT
Build Capacity: SHARE
Build Capacity: SHARE
Improve Cyber Security: SECURE
Enterprise Services to the Edge: SHARE
Enterprise Services to the Edge: SHARE
P/C/S Enterprise
![Page 9: I3C2%Program%Update% AFCEALuncheon%...We are systems integrator working with 7th & DISA in CONUS America’s Force of Decisive Action 13 Future Enterprise VoIP Architecture • UC](https://reader033.vdocuments.net/reader033/viewer/2022060517/604a2111cab0214c28686bf3/html5/thumbnails/9.jpg)
9 America’s Force of Decisive Action
What Changes with Installation IT Modernization?
• Inside/Outside Plant Upgrade • LMR System • Area Distribution Node Switch • Main Distribution Frame • Power/HVAC • Tech Control Facility (Where Required) • Lifecycle Refresh PBX Phone Switch to VoIP • Voice connectivity • TDM Voice Call Processor • End-user Building Switch • Security System (TLA) • Main Communications Node Switch
Previous Installation Capability Set Modernization Plan
• Unified Capabilities Software
• VoIP Managed Service
• Reduced Cost Through Commodity
• Purchasing
• Regional Security Stack (RSS)
• Eliminate with Multi-Protocol Labeling Switch (MPLS) Router
New Enterprise Model
Moving to Enterprise Model
for Modernization FY14-15
• Consistent with JIE – Now Partnering with AF and DISA • CENTCOM – Fully Funded for Infrastructure (MPLS/JRSS/ESC) • CONUS – Funding for Infrastructure (MPLS/JRSS/ESC) provided –
Regional Fielding Approach (SW, SE, NE, MW, W) • Allows us to reach a tipping point for collapsing into One Network
![Page 10: I3C2%Program%Update% AFCEALuncheon%...We are systems integrator working with 7th & DISA in CONUS America’s Force of Decisive Action 13 Future Enterprise VoIP Architecture • UC](https://reader033.vdocuments.net/reader033/viewer/2022060517/604a2111cab0214c28686bf3/html5/thumbnails/10.jpg)
10 America’s Force of Decisive Action
NETMOD-C Lines of Effort (aka MPLS/JRSS/EUB&ADN)
ADN -‐ Area DistribuCon Node B/P/C/S -‐ Base/Post/Camp/StaCon DISN – Defense InformaCon Systems Network EUB – End User Building
• Set condiCons for future success • Improve foundaConal network elements • Pave the way for CIO/G-‐6 InstallaCon Capability Sets
ICAN – InstallaCon Campus Area Network ISP – Inside Plant OSP – Outside plant SC(T) – Theater Signal Command
Line of Effort (LOE) Description
DISN Optical Upgrade DISA upgrade of aging DISN Infrastructure
Core Routers DISA installation of new DISN Core Routers at Army B/P/C/S
Regional Security Stacks (RSS) DISA procurement/installation of 11 regionalized security stacks in CONUS
Physical Diversity to DISN Connection of Army B/P/C/S to the DISN via two physically diverse routes
ICAN ADN/EUB Switch Upgrade Army upgrade ICAN Ethernet switches
Sensoring the Network End-to-End network visibility w/ common views between DISA and Services
ICAN Outside & Inside Plant Upgrades Complete OSP and ISP required upgrades/ expansions (FY15 and beyond)
![Page 11: I3C2%Program%Update% AFCEALuncheon%...We are systems integrator working with 7th & DISA in CONUS America’s Force of Decisive Action 13 Future Enterprise VoIP Architecture • UC](https://reader033.vdocuments.net/reader033/viewer/2022060517/604a2111cab0214c28686bf3/html5/thumbnails/11.jpg)
11 America’s Force of Decisive Action
NETMOD-C is a Regional Approach
#1 #2
Top 40 P/C/S = 88% of the Population
![Page 12: I3C2%Program%Update% AFCEALuncheon%...We are systems integrator working with 7th & DISA in CONUS America’s Force of Decisive Action 13 Future Enterprise VoIP Architecture • UC](https://reader033.vdocuments.net/reader033/viewer/2022060517/604a2111cab0214c28686bf3/html5/thumbnails/12.jpg)
12 America’s Force of Decisive Action
NETMOD-C Schedule FY 2013 FY 2014 FY 2015
Functional Areas
Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3
J A S O N D J F M A M J J A S O N D J F M A M J
Milestones
Contracts
Systems Engineering
Testing
Logistics
Fielding
EIP Approval
Commodity Buy #1
ImplementaCon
TesCng
Cisco Proof of Concept (CPOC)
IniCate Fielding
Warehouse Rent
Survey
CDR PDR
Engineer
JBSA
Engineering Support– Fielding
Survey and Engineering InstallaCon Plan (EIP)
Fielding for remaining sites
Ongoing TesCng (per site) – ConfiguraCon & VerificaCon DISA TesCng
Complete Fielding
Survey Engineering
Commodity Buy #2
Engineering Support – Surveys
Inbound Receiving
Test Plans ROC Drill (per site)
Ancil Equip Buy
Fielding Start
DISA JBSA EPE
Note: TYAD will provide AC Power upgrade throughout duraCon of installs
Rental Trucks (GSA or Contract)
Follow-‐on Eng Contracts
Warehouse Support
MulCple Shipments to B/P/C/S
PM Test
CDR
Outbound Shipping
TesCng
Note: TYAD procuring items for fielding
LEGEND
Completed Document/AcCvity
Planned Document/AcCvity
Planned Contract Award
Milestone
JBSA
PDR
As of 25 Oct 2013
We are systems integrator working with 7th & DISA in CONUS
![Page 13: I3C2%Program%Update% AFCEALuncheon%...We are systems integrator working with 7th & DISA in CONUS America’s Force of Decisive Action 13 Future Enterprise VoIP Architecture • UC](https://reader033.vdocuments.net/reader033/viewer/2022060517/604a2111cab0214c28686bf3/html5/thumbnails/13.jpg)
13 America’s Force of Decisive Action
Future Enterprise VoIP Architecture
• UC features provided are VoIP and VoSIP; Chat, presence, and awareness will be provided as a separate service offering
• Replaces TDM voice switch with VoIP switch
• ESCs at DISA level (could be located at DISN core or P/C/S)
• As is: Hard Phones
• To be: Soft Phones (majority)
Enterprise Session Controller (ESC)
![Page 14: I3C2%Program%Update% AFCEALuncheon%...We are systems integrator working with 7th & DISA in CONUS America’s Force of Decisive Action 13 Future Enterprise VoIP Architecture • UC](https://reader033.vdocuments.net/reader033/viewer/2022060517/604a2111cab0214c28686bf3/html5/thumbnails/14.jpg)
14 America’s Force of Decisive Action
Fort Hood ICAN Modernization
PHASE 1: Set Conditions & Hospital Connectivity
PHASE 3: ADN / EUB Switches
PHASE 2: Outside Plant – ADN-To-EUB and Inside Plant Upgrades (Est. 12-18 Months)
AWD O/A 15 Oct 13
OCT 14
IMOD Vendor Executes Funded in FY13
DEC 14
MAR 14
IMOD Vendor Executes FY14 Funding
DEC 13
E-PE Router
MAR 14
ESC (JBSA)
JUL 14
JRSS (Est.)
SEP 15
Integrated 7th SC(T) / PdM I3MP Team Executes FY14 Funding
JUL 14 Hospital BOD
FEB 15 Assumes NO major delays from Phase 2
PHASE 4: Voice (TDM to VoIP) Self Help and/or Integrator Expecting FY15 Funding Priority
TBD TBD
DISA Projects
2014 2015 2016
ModernizaCon Begun! Contract Award in Oct 13
Seeking Opportunities to accelerate Phase 3
to Summer 2014 PHASE 1: Shaping Operation! • Critical step to modernization • Build new Shelter for MCN/ DISA Core Router • Collapse from 3 MCNs down to 2 MCNs • Reduce number of ADNs • Outside Plant – MCN-to-ADNs • Connectivity for Hospital
PHASE 2: Fix Outside Plant Issues • #1 Priority Daisy-chained End User Buildings Replace Multi-mode Fiber with Single Mode
Fiber • #2 Priority: Complete ISP work in TRs Power / HVAC / Grounding
PHASE 3: ADN/EUB Switches • Assumption is that JRSS is operational • Constrained by work being done in Phases 1 & 2 • Must avoid disruption of contract work in Phase 1 & 2 • Will accelerate start depending on Phase 1 progress • Phase 2 progress “may” cause breaks in switch installs
PHASE 4: TDM-to-VoIP Transition • Transition voice users from TDM to the ESC or LSC by either: Installing VoIP phones connected to ESC or LSC Connecting existing phone to Integrated Access Device (IAD)
• Decommission TDM switches and remotes • Duration depends on fielding methodology • Endstate: Primary trunking for Voice service is via IP
![Page 15: I3C2%Program%Update% AFCEALuncheon%...We are systems integrator working with 7th & DISA in CONUS America’s Force of Decisive Action 13 Future Enterprise VoIP Architecture • UC](https://reader033.vdocuments.net/reader033/viewer/2022060517/604a2111cab0214c28686bf3/html5/thumbnails/15.jpg)
15 America’s Force of Decisive Action
What’s left to do at the Installation?
• Extend capacity to the desktop & remove local traffic bottlenecks
• Provide network services; decommission legacy infrastructure
• Align infrastructure to enable installation-specific missions (L/V/C training, Emergency Services, etc.)
• Possible Future Actions: “Smart” Buildings, Video Teleconferencing, Installation Operations Centers, Wireless Campus (enable Mobility)
![Page 16: I3C2%Program%Update% AFCEALuncheon%...We are systems integrator working with 7th & DISA in CONUS America’s Force of Decisive Action 13 Future Enterprise VoIP Architecture • UC](https://reader033.vdocuments.net/reader033/viewer/2022060517/604a2111cab0214c28686bf3/html5/thumbnails/16.jpg)
16 America’s Force of Decisive Action
NetOps BLUF
• U.S. Army NetOps capabilities have been generated, engineered, and procured in a decentralized manner across many commands and echelons.
• Challenges: − Disparate and non-interoperable systems/tools/configurations − Doctrinal Disconnects: NetOps, Defensive Cyberspace Operations, DoD Information
Network Operations (DoDIN), Joint Information Environment (JIE) CONOPS − Multiple NetOps and Cyber Working Groups/IPTs − Maintaining “as is” while moving to the “to be”
• The Army needs a more centralized approach to defining, validating, procuring, and fielding NetOps capabilities.
• ASA(ALT) is establishing a Cyber “Focal” in the near term (90 days) under SOSE&I in response to ARCYBER CG request for assistance − Coordinate, Integrate, and Synchronize across 4 PEOs – IEWS, EIS, C3T, and STRI − Support of the 3 Cyberspace Operations mission areas – Offensive, Defense, and
DoDIN (NetOps) − Sets conditions for a future Cyber Directorate or Task Force under ASA(ALT)
• I3C2 is working with NETCOM to transition NetOps materiel development role to the PM.
![Page 17: I3C2%Program%Update% AFCEALuncheon%...We are systems integrator working with 7th & DISA in CONUS America’s Force of Decisive Action 13 Future Enterprise VoIP Architecture • UC](https://reader033.vdocuments.net/reader033/viewer/2022060517/604a2111cab0214c28686bf3/html5/thumbnails/17.jpg)
17 America’s Force of Decisive Action
NetOps Capabilities and Defensive Cyberspace Operations
IP Management Computing Platform Management Security Management Enterprise Support Enterprise Services &
Application Management
IP Network Management System (NetMan) 6+1
Host Based Security System (HBSS) 6+1
Network Access Control (NAC)
Enterprise Services Management System (ESMS) 6+1
Database Element Manager
Network Intrusion Prevention System (NIPS)
Systems Management (SysMan) 6+1
IAVM IP Network Vulnerability Scanner6+1
Domain Name Service (DNS) Management
Directory Services Management
Wireless Intrusion Prevention System (WIPS)
Storage Management System
Security Information Management System (SIMS) 6+1
IP Capacity, Availability, & Performance (CAP) Monitoring System
Firewall Element Management
Backup and Recovery Management
Identity Management System
Proxy Management Virtualization Management System (VSM)
Crypto Security Management
Router Element Management
IAVM Computing Platform Management
Switch Element Management
Virtual Private Network (VPN) Management
Wireless IP Network Management
* NDAA 2011 SecCon 933 sCpulates the requirement to provide cyber quick reacCon capabiliCes (QRC)
![Page 18: I3C2%Program%Update% AFCEALuncheon%...We are systems integrator working with 7th & DISA in CONUS America’s Force of Decisive Action 13 Future Enterprise VoIP Architecture • UC](https://reader033.vdocuments.net/reader033/viewer/2022060517/604a2111cab0214c28686bf3/html5/thumbnails/18.jpg)
18 America’s Force of Decisive Action
PD NetOps Space
PD, NetOps
![Page 19: I3C2%Program%Update% AFCEALuncheon%...We are systems integrator working with 7th & DISA in CONUS America’s Force of Decisive Action 13 Future Enterprise VoIP Architecture • UC](https://reader033.vdocuments.net/reader033/viewer/2022060517/604a2111cab0214c28686bf3/html5/thumbnails/19.jpg)
19 America’s Force of Decisive Action
ESMSaaS BLUF
• Situation: − Current Information Technology Service Management (ITSM) tools and services across the Army and DoD are
acquired and engineered in a decentralized manner.
− To address the disparate ITSM/trouble ticketing tools and processes, the Army will migrate to an Enterprise Service Management System as a Service (ESMSaaS).
• Objectives: − Initiate a Tiger Team to capture current ITSM workflows across Army MACOMs and produce a Product Neutral
Service Workflow (PNSW) package for the Army Enterprise .
− Execute an ESMSaaS global contract with a Proof of Concept of limited scope, size, and time.
• Demonstrate a commercially managed ITSM service, using "out of the box" ITIL v3 (2011) process workflow, can replace highly customized government owned ITSM tool(s).
• Identify business processes that can be implemented in commercial solution vs those that require the commercial solution to be customized or the process modified.
• Capture lessons learned to inform the Business Capability Lifecycle (BCL) governance process, and the follow-on global task order .
• Execute ESMSaaS globally across the LandWarNet, and for interested mission partners.
• Integrate ESMSaaS with tactical and Joint ITSM services/platforms.
• Goal is to have the global fielding complete by end of FY17.
![Page 20: I3C2%Program%Update% AFCEALuncheon%...We are systems integrator working with 7th & DISA in CONUS America’s Force of Decisive Action 13 Future Enterprise VoIP Architecture • UC](https://reader033.vdocuments.net/reader033/viewer/2022060517/604a2111cab0214c28686bf3/html5/thumbnails/20.jpg)
20 America’s Force of Decisive Action
ESMSaaS PNSW Approach Workflow
IPT Guidance
Glossary Recommendations Gaps & Issues
3 Current State –Service Comparison
• Consolidation of processes across services and commands.
• Highlight and callout process duplication, gaps, and other areas of importance.
Current State –C4IM Service Focus 2
• CONUS and OCONUS travel to investigate individual locations and NEC’s.
• Capture service-specific process details. • Leverage Enterprise Level diagram to elicit
corrections.
4 PNSW Consolidated Future
• Consolidated view across services and processes.
• Accompanying RFP-ready formats.
Current State – Enterprise Level 1
• Review of existing standard processes and procedures.
• Consolidate all standard processes into a single ITIL-centric view (e.g. Incident Management, Problem Management).
• Focus on ABITS services.
Goals & Objectives
PNSW Scenarios
![Page 21: I3C2%Program%Update% AFCEALuncheon%...We are systems integrator working with 7th & DISA in CONUS America’s Force of Decisive Action 13 Future Enterprise VoIP Architecture • UC](https://reader033.vdocuments.net/reader033/viewer/2022060517/604a2111cab0214c28686bf3/html5/thumbnails/21.jpg)
21 America’s Force of Decisive Action
ESMSaaS Schedule
4QFY13 1QFY14 2QFY14 3QFY14 4QFY14 1QFY15 2QFY15 3QFY15 4QFY15 1QFY16 2QFY16 3QFY16 4QFY16 1QFY17
Initial Proposal Evaluation
Draft RFP
Final RFP
Red Team
Contract and Task Order (TO) 1 Award
TO1: Design and Reviews
TO1: IATO
RFP Package Development
Directive to Proceed
Proposals Due
Discussions
Final Proposal Evaluation
TO1: IATT
TO1: ATO
TO1: Acceptance
Decision Point for TO2
TO2 Award
Tiger Team work
Today
RFI – 1st/2nd Quarter FY14 RFP – 3rd/4th Quarter FY14
![Page 22: I3C2%Program%Update% AFCEALuncheon%...We are systems integrator working with 7th & DISA in CONUS America’s Force of Decisive Action 13 Future Enterprise VoIP Architecture • UC](https://reader033.vdocuments.net/reader033/viewer/2022060517/604a2111cab0214c28686bf3/html5/thumbnails/22.jpg)
22 America’s Force of Decisive Action
US-ROK Strategic Alliance 2015
• Consolidate U.S. military units within two enduring hubs as part of the Yongsan Relocation Plan and the Land Partnership Plan
• Transition wartime OPCON of ROK forces in 2015 • Develop new organizational structures to support
the ROK lead for the combined defense • Acquire, organize, and train systems/capabilities,
which enable ROK to lead combined defense
• Employ realistic training and exercises based on current and future threats to the Alliance
• Refine and improve combined defense plans • Enhance the Alliance’s strategic significance though
regional exercises and humanitarian assistance/disaster (HA/DR) relief support
• Continue to enforce and abide by terms of Armistice Agreement now and in the future
Lee-Obama Joint Vision Statement The United States of America and the Republic of Korea are building an Alliance to ensure
a peaceful, secure and prosperous future for the
Korean Peninsula, the Asia-Pacific region, and the World
– June 16, 2009
• Supports implementation of US – ROK Presidential Joint Vision Statement (Jun 2009) and Ministerial Guidelines for US – ROK Defense Cooperation (Oct 2010)
• More closely synchronize U.S. transition of wartime Operational Control (OPCON) of ROK forces with other Alliance transformation initiatives.
“Standing on a foundation of the shared sacrifices and deep bonds from the alliance’s past, our defense relationship is also growing into a comprehensive strategic alliance for the future.”
– The Guidelines for US - ROK Defense Cooperation, October 8, 2010
![Page 23: I3C2%Program%Update% AFCEALuncheon%...We are systems integrator working with 7th & DISA in CONUS America’s Force of Decisive Action 13 Future Enterprise VoIP Architecture • UC](https://reader033.vdocuments.net/reader033/viewer/2022060517/604a2111cab0214c28686bf3/html5/thumbnails/23.jpg)
23 America’s Force of Decisive Action
YRP/LPP
Engineer and Implement C4I Systems and Services to support YRP/LPP Mission:
• USFK moving from 104 Camps and Stations to 2 enduring hubs
• Support 30,000 people moving to USAG Humphries • Requires: C4I Installs in 600+ buildings (including
Communications Center, 4 General Officer HQs, 1 BDE HQ, Hospital, 2 Simulation Centers, OPS Center, Health Clinic)
Migration of existing 65 C4I systems 2x Main Communications Nodes, 4 Area
Distribution Nodes 140k voice and data outlets 412 manholes and 136 hand holes 25,000 km of conduit and 8000 km of cable
![Page 24: I3C2%Program%Update% AFCEALuncheon%...We are systems integrator working with 7th & DISA in CONUS America’s Force of Decisive Action 13 Future Enterprise VoIP Architecture • UC](https://reader033.vdocuments.net/reader033/viewer/2022060517/604a2111cab0214c28686bf3/html5/thumbnails/24.jpg)
24 America’s Force of Decisive Action
YRP/LPP Project Schedule
Phases 2013 2014 2015 2016
10 11 12 01 02 03 04 05 06 07 08 09 10 11 12 01 02 03 04 05 06 07 08 09 10 11 12 01 02 03 04 05 06 07 08 09 10 11 12
1
35
14 3
13
10 12 20
13 17
11 19 30
20 17 16
20 37 2
5 4 7
3 7 7
5 5
2 14
18 bldg
51 bldg
43 bldg 42 bldg
60 bldg
53 bldg
59 bldg 16 bldg
17 bldg
10 bldg
Total 369 buildings BOD (20-May-2014 ~ 16-Sep-2016)
- Remarks - 14 : 14 blds in May 3 : 3 bldgs in June 1 : 1 bldgs in July
Order Period #2 (7/30/2013-‐7/29/2014) Order Period #3 (7/30/2014-‐7/29/2015) Order Period #4 (7/30/2015-‐7/29/2016)
EIP Development����������� ������������������
Procurement����������� ������������������
PreparaCon of installaCon����������� ������������������
InstallaCon of General FaciliCes (EsCmate BOD)����������� ������������������
Intense General FaciliCes (GF) InstallaCon starCng JUL 14
(308 Buildings over 18 month period).
Scope similar (NIPR, SIPR, Voice) but volume is huge…
C4I Intensive Facility BOD
Increment 2 Award: ~ 2nd to 3rd Qtr / FY14
![Page 25: I3C2%Program%Update% AFCEALuncheon%...We are systems integrator working with 7th & DISA in CONUS America’s Force of Decisive Action 13 Future Enterprise VoIP Architecture • UC](https://reader033.vdocuments.net/reader033/viewer/2022060517/604a2111cab0214c28686bf3/html5/thumbnails/25.jpg)
25 America’s Force of Decisive Action
CONUS FY14-16 Strategy (I3MP Efforts)
FY14 FY15 FY16
Prop
osed
Planning development of 10 SRDs Planning development of 10 SRDs
Planning development of 10 SRDs
Pre-
Aw
ard Planning 8 D.O. or contract awards Planning 8 D.O. or contract awards Planning 10 D.O. or contract awards
Post
A
war
d Managing 32 projects Expecting to Close 20
Projecting 20 on-going projects Expecting to Close 13
Projecting 15 on-going projects Expecting to Close 5
NET
MO
D-C
A
DN
/ EU
B S
witc
h U
pgra
des
Survey / Eng / Test: 11 Sites Initiate fielding at 7 sites in FY14 Complete fielding at 5 sites
Continue Survey / Eng / Test of sites Complete fielding at 19 sites
Finish Survey / Eng / Test of sites Complete fielding at 15 sites
• Ft McNair • APG JLENS • Ft Bliss ICS* • Ft Sill ICS • JBSA ICS
• Ft Polk ICS • Ft Benning ICS • Ft Bragg ICS • Ft Stewart ICS • USAG Miami ICS
• Ft Hood P1 • APG JLENS • Ft Detrick • Ft Rucker
• Ft McNair • Ft Hood P2 • JBLM • Commodity Buy #2
• Ft Sill ICS • Ft Polk ICS • JBSA ICS • Ft Bliss ICS
• Ft Stewart ICS • Ft Benning ICS • USAG Miami ICS • Ft Bragg ICS
• Ft Knox ICS • Ft Drum ICS • CP Roberts ICS • Ft Carson ICS • JBLM ICS
• Detroit Arsenal ICS • Ft Campbell ICS • USAR/ARNG #1 ICS • USAR/ARNG #2 ICS • USAR/ARNG #3 ICS
• TBD
• Ft Knox ICS • Ft Drum ICS • CP Roberts ICS • Ft Carson ICS • JBLM ICS
• Detroit Arsenal ICS • Ft Campbell ICS • USAR/ARNG #1 ICS • USAR/ARNG #2 ICS • USAR/ARNG #3 ICS
• JBSA • Ft Sill • Ft Bliss
• Ft Stewart • Redstone Arsenal
• Ft Polk • CCAD • Ft Benning • Ft Jackson • Ft Hood • Anniston AD • Ft Gordon • Ft Rucker • Ft Bragg • Ft Eustis
• Ft Dix • West Point • Ft Drum • Ft Meade • Ft Belvoir • APG • TYAD • Ft Lee • Ft Detrick
• Ft McCoy • Ft Campbell • Ft Knox • Rock Island • WSMR • Detroit • Leonard Wood • Ft Riley • Ft Leavenworth
• JBLM • NTC • CP Roberts • POM • Ft Huachuca • Ft Carson
TRA
DIT
ION
AL
I3M
P PR
OJE
CTS
*ICS = InstallaCon Capability Set As of 25 Oct 2013
![Page 26: I3C2%Program%Update% AFCEALuncheon%...We are systems integrator working with 7th & DISA in CONUS America’s Force of Decisive Action 13 Future Enterprise VoIP Architecture • UC](https://reader033.vdocuments.net/reader033/viewer/2022060517/604a2111cab0214c28686bf3/html5/thumbnails/26.jpg)
26 America’s Force of Decisive Action
CONUS FY14-16 Strategy (I3MP SCC Efforts)
As of 25 Oct 2013
FY14 FY15 FY16
Prop
osed
Planning development of 6 SRDs Planning development of 6 SRDs
Planning development of 6 SRDs
Pre-
Aw
ard
Planning 4 D.O. or contract awards Planning 4 D.O. or contract awards Planning 4 D.O. or contract awards
Post
Aw
ard Managing 3 projects
Expecting to Close 3 Projecting 4 on-going projects Expecting to Close 2
Projecting 6 on-going projects Expecting to Close 4
• Site R x2 • AOC • JSOC • SOUTHCOM x2
• Site R • AOC • JSOC • SOUTHCOM
• Site R • AOC • JSOC • SOUTHCOM
• Site R • AOC • JSOC • SOUTHCOM
• Site R • AOC • JSOC • SOUTHCOM
• Site R • AOC • JSOC • SOUTHCOM
• SOUTHCOM • JSOC • Site R
• AOC • SOUTHCOM
• Site R • AOC • JSOC • SOUTHCOM
![Page 27: I3C2%Program%Update% AFCEALuncheon%...We are systems integrator working with 7th & DISA in CONUS America’s Force of Decisive Action 13 Future Enterprise VoIP Architecture • UC](https://reader033.vdocuments.net/reader033/viewer/2022060517/604a2111cab0214c28686bf3/html5/thumbnails/27.jpg)
27 America’s Force of Decisive Action
TLA FY14-16 Strategy (I3MP Efforts)
As of 25 Oct 2013
FY14 FY15 FY16
Prop
osed
Planning development of 1 SRDs TBD
TBD
Pre-
Aw
ard Planning 9 D.O. or contract awards Planning 4 D.O. or contract awards Planning 3 D.O. or contract awards
Post
Aw
ard
Managing 9 projects Expecting to Close 8
Projecting 4 on-going projects Expecting to Close 9
Projecting 3 on-going projects Expecting to Close 4
• Develop Army SIPR JRSS
Requirements
• SIPR JRSS CHESS task order , if necessary
• 8x DRSN CHESS Contracts SOUTHCOM Ft Greely x 5
• 4 DRSN CHESS Contracts SOUTHCOM x 2 SHAPE EUCOM
• 3 DRSN CHESS Contracts Yongsan Site R EUCOM
• TLA -‐ Hood -‐ Stewart -‐ Gordon DRSN -‐ Ft Greely -‐ Site R
• SIPR JRSS • DRSN -‐ Ft Greely -‐ SOUTHCOM -‐ SHAPE -‐ Yongsan
• DRSN -‐ SOUTHCOM x 2 -‐ SHAPE -‐ EUCOM
-‐ Buchanan -‐ Detrick -‐ Redstone
SHAPE Yongsan
![Page 28: I3C2%Program%Update% AFCEALuncheon%...We are systems integrator working with 7th & DISA in CONUS America’s Force of Decisive Action 13 Future Enterprise VoIP Architecture • UC](https://reader033.vdocuments.net/reader033/viewer/2022060517/604a2111cab0214c28686bf3/html5/thumbnails/28.jpg)
28 America’s Force of Decisive Action
OCONUS FY14-16 Strategy (P2E Efforts)
FY14 FY15 FY16
Prop
osed
Planning development of 9 SRDs Capability Set at USAG Stuttgart 311th C2 Virtualization SIPR & NIPR Korea C2 Virtualization NMI-PACOM Korea Area 4 Capability Set Korea Area 1 OSP Capability Set at Schofield Barracks Capability Set at Pohakuloa Training Area USARPAC MCF Phase 2
Planning development of 9 SRDs NMI-EUCOM DISA JEN Power Europe UC Infrastructure Modernization Europe Capability Set at USAG Weisbaden Capability Set at USAG K-Town Korea 2ID-Red Cloud Virtualization 2ID Commend Post Bunker Upgrade CRC Japan Unified Capabilities at Sagami Depot USARPAC MCF Phase 3
Planning development of 6 SRDs Weilerbach Hospital (EUR) Capability Set Grafenwoehr Capability Set Livorno Capability Set Alaska Capability Set Japan USARPAC MCF Phase 4
Pre-
Aw
ard
Planning 6 DO or contract awards Wiesbaden Information Processing Center USARPAC MCF NMI-SWA ADN/EUB Palm Circle ISP Korea Area I & II MOD Camps Carroll & Henry Area 3 MODs
Planning 9 DO or contract awards Capability Set at USAG Stuttgart 311th C2 Virtualization SIPR & NIPR Korea C2 Virtualization NMI-PACOM Korea Area 4 Capability Set Korea Area 1 OSP Capability Set at Schofield Barracks Capability Set at Pohakuloa Training Area USARPAC MCF Phase 2
Planning 9 DO or contract awards NMI-EUCOM Capability Set at USAG Weisbaden Capability Set at USAG K-Town Korea 2ID-Red Cloud Virtualization 2ID Commend Post Bunker Upgrade CRC Japan Unified Capabilities at Sagami Depot USARPAC MCF Phase 3
Post
A
war
d Managing 15 projects Expecting to Close 13
Projecting 12 on-going projects Expecting to Close 8
Projecting 11 on-going projects Expecting to Close 5
YRP/
LPP Execute: YRP/LPP Increment I
(SDPs, EIPs) Survey: YRP/LPP Increment 2 Award: YRP/LPP Increment 2
(C4I Intensive Facilities)
Execute: YRP/LPP Increment 1 (SDPs, EIPs)
Execute: YRP/LPP Increment 2 (C4I Intensive Facilities)
Survey: YRP/LPP Increment 3 Award: YRP/LPP Increment 3
(Yongsan Residual/Migration)
Execute: YRP/LPP Increment 1 (SDPs, EIPs)
Execute: YRP/LPP Increment 2 (C4I Intensive Facilities)
Execute: YRP/LPP Increment 3 (Yongsan Residual/Migration)
![Page 29: I3C2%Program%Update% AFCEALuncheon%...We are systems integrator working with 7th & DISA in CONUS America’s Force of Decisive Action 13 Future Enterprise VoIP Architecture • UC](https://reader033.vdocuments.net/reader033/viewer/2022060517/604a2111cab0214c28686bf3/html5/thumbnails/29.jpg)
29 America’s Force of Decisive Action
OCONUS FY14-16 Strategy (P2E Efforts)
FY14 FY15 FY16
Prop
osed
Planning development of 9 SRDs Capability Set at USAG Stuttgart 311th C2 Virtualization SIPR & NIPR Korea C2 Virtualization NMI-PACOM Korea Area 4 Capability Set Korea Area 1 OSP Capability Set at Schofield Barracks Capability Set at Pohakuloa Training Area USARPAC MCF Phase 2
Planning development of 9 SRDs NMI-EUCOM DISA JEN Power Europe UC Infrastructure Modernization Europe Capability Set at USAG Weisbaden Capability Set at USAG K-Town Korea 2ID-Red Cloud Virtualization 2ID Commend Post Bunker Upgrade CRC Japan Unified Capabilities at Sagami Depot USARPAC MCF Phase 3
Planning development of 6 SRDs Weilerbach Hospital (EUR) Capability Set Grafenwoehr Capability Set Livorno Capability Set Alaska Capability Set Japan USARPAC MCF Phase 4
Pre-
Aw
ard
Planning 6 DO or contract awards Wiesbaden Information Processing Center USARPAC MCF NMI-SWA ADN/EUB Palm Circle ISP Korea Area I & II MOD Camps Carroll & Henry Area 3 MODs
Planning 9 DO or contract awards Capability Set at USAG Stuttgart 311th C2 Virtualization SIPR & NIPR Korea C2 Virtualization NMI-PACOM Korea Area 4 Capability Set Korea Area 1 OSP Capability Set at Schofield Barracks Capability Set at Pohakuloa Training Area USARPAC MCF Phase 2
Planning 9 DO or contract awards NMI-EUCOM Capability Set at USAG Weisbaden Capability Set at USAG K-Town Korea 2ID-Red Cloud Virtualization 2ID Commend Post Bunker Upgrade CRC Japan Unified Capabilities at Sagami Depot USARPAC MCF Phase 3
Post
A
war
d Managing 15 projects Expecting to Close 13
Projecting 12 on-going projects Expecting to Close 8
Projecting 11 on-going projects Expecting to Close 5
YRP/
LPP
Execute: YRP/LPP Increment I (SDPs, EIPs)
Survey: YRP/LPP Increment 2 Award: YRP/LPP Increment 2
(C4I Intensive Facilities)
Execute: YRP/LPP Increment 1 (SDPs, EIPs)
Execute: YRP/LPP Increment 2 (C4I Intensive Facilities)
Survey: YRP/LPP Increment 3 Award: YRP/LPP Increment 3
(Yongsan Residual/Migration)
Execute: YRP/LPP Increment 1 (SDPs, EIPs)
Execute: YRP/LPP Increment 2 (C4I Intensive Facilities)
Execute: YRP/LPP Increment 3 (Yongsan Residual/Migration)
As of 29 Oct 2013
![Page 30: I3C2%Program%Update% AFCEALuncheon%...We are systems integrator working with 7th & DISA in CONUS America’s Force of Decisive Action 13 Future Enterprise VoIP Architecture • UC](https://reader033.vdocuments.net/reader033/viewer/2022060517/604a2111cab0214c28686bf3/html5/thumbnails/30.jpg)
30 America’s Force of Decisive Action
OCONUS FY14-16 Strategy (P2E Efforts)
FY14 FY15 FY16
Prop
osed
Planning development of 2 SRDs Planning development of 2 SRDs
Planning development of 2 SRDs
Pre-
Aw
ard Planning 2 D.O. or contract awards Planning 2 D.O. or contract awards Planning 2 D.O. or contract awards
Post
A
war
d Managing 0 projects Expecting to Close 0
Projecting 2 on-going projects Expecting to Close 2
Projecting 2 on-going projects Expecting to Close 2
![Page 31: I3C2%Program%Update% AFCEALuncheon%...We are systems integrator working with 7th & DISA in CONUS America’s Force of Decisive Action 13 Future Enterprise VoIP Architecture • UC](https://reader033.vdocuments.net/reader033/viewer/2022060517/604a2111cab0214c28686bf3/html5/thumbnails/31.jpg)
31 America’s Force of Decisive Action
• I3C2 vision is to acquire and deliver a standardize global infrastructure that is scalable, accessible, flexible and defensible.
• I3C2 provides the full spectrum of network and information and communications technology (ICT) capabilities in support of the Army and Joint Troops I (PACOM, CENTCOM, ARCENT, EUCOM, AFRICOM, USAREUR, and USARAF)
• I3C2 is currently managing 100+ projects valued at approximately $1B
• With all the projects on our plate, where we could use Industry assistance
Lowering total cost of ownership – bulk buys, bundling, standardization.
Migrating/transitioning from current TDM legacy environment to VoIP
Any ideas on how to help? Please get on my calendar!