iac presentation, august 17, 2017 ground movement impact … · 2018. 6. 12. · concerns...

43
Ground Movement Impact Assessment Trevor O’Shannessy IAC Presentation, August 17, 2017

Upload: others

Post on 28-Oct-2020

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: IAC Presentation, August 17, 2017 Ground Movement Impact … · 2018. 6. 12. · Concerns groundwater alteration (reduction) that may cause subsidence Concerns dewatering may cause

Ground Movement Impact Assessment

Trevor O’Shannessy

IAC Presentation, August 17, 2017

Page 2: IAC Presentation, August 17, 2017 Ground Movement Impact … · 2018. 6. 12. · Concerns groundwater alteration (reduction) that may cause subsidence Concerns dewatering may cause

Overview

Construction Engineering Scoping requirements Existing conditions summary Assessment approach Key considerations of design Key assessment findings Key submission issues

By key areas West Gate, Tunnel, Port CityLink, city connections

August 17, 2017 2

Page 3: IAC Presentation, August 17, 2017 Ground Movement Impact … · 2018. 6. 12. · Concerns groundwater alteration (reduction) that may cause subsidence Concerns dewatering may cause

Construction Engineering – West Gate

August 17, 2017 3

West Gate Freeway

Surface works

Road widening

Bridges

Page 4: IAC Presentation, August 17, 2017 Ground Movement Impact … · 2018. 6. 12. · Concerns groundwater alteration (reduction) that may cause subsidence Concerns dewatering may cause

Construction Engineering – Tunnel

August 17, 2017 4

Tunnel (Overview)

Portals

Bored Tunnels x2

Cross Passages (120 m spacing)

Spoil Transport routes

Laydown areas

Page 5: IAC Presentation, August 17, 2017 Ground Movement Impact … · 2018. 6. 12. · Concerns groundwater alteration (reduction) that may cause subsidence Concerns dewatering may cause

Construction Engineering - Tunnel

August 17, 2017 5

Portal Structures Entry / exit to tunnel Large excavations (approx. 25m deep) with engineered ground support

Source – Herrenknecht (Katzenberg 2007) 11.2m diameter

Secant pile wallGround anchors

Page 6: IAC Presentation, August 17, 2017 Ground Movement Impact … · 2018. 6. 12. · Concerns groundwater alteration (reduction) that may cause subsidence Concerns dewatering may cause

Construction Engineering - Tunnel

August 17, 2017 6

Tunnel Metrics Outer Diameter = 15.6 m

Typical depth to top of tunnel = 20-30 m

Minimum (at portals) = 5-8 m

Combined length = 6.8 km

(2.8 km east bound tunnel)

(4.0 km west bound tunnel)

Dug using Tunnel Boring Machine (TBM)

Built below the water table

Page 7: IAC Presentation, August 17, 2017 Ground Movement Impact … · 2018. 6. 12. · Concerns groundwater alteration (reduction) that may cause subsidence Concerns dewatering may cause

Construction Engineering - Tunnel

August 17, 2017 7

Earth Pressure Balance (EPB)Tunnel Boring Machine (TBM)

Source – Herrenknecht

Page 8: IAC Presentation, August 17, 2017 Ground Movement Impact … · 2018. 6. 12. · Concerns groundwater alteration (reduction) that may cause subsidence Concerns dewatering may cause

Construction Engineering - Tunnel

August 17, 2017 8

Adopted in hard rock (Tvn)

Not used (free draining)

Adopted in soil and mixed ground

(controls groundwater inflow)

Tunnelling Modes (EPB TBM)

(controls groundwater inflow)

Page 9: IAC Presentation, August 17, 2017 Ground Movement Impact … · 2018. 6. 12. · Concerns groundwater alteration (reduction) that may cause subsidence Concerns dewatering may cause

Construction Engineering - Tunnel

August 17, 2017 9

Principles of Earth Pressure Balance (EPB) tunnelling

A plug of modified soil formed behind the cutter head

Bentonite mud injected around TBM & segments grouted in

Controls soil in-rush / over excavation and groundwater leakage

Page 10: IAC Presentation, August 17, 2017 Ground Movement Impact … · 2018. 6. 12. · Concerns groundwater alteration (reduction) that may cause subsidence Concerns dewatering may cause

Construction Engineering - Tunnel

August 17, 2017 10

Segmental Tunnel Lining

Approx. 500 mm thick steel reinforced segments

Built in 10 pieces to form a ‘ring’

Rings built progressively within the rear of the TBM

Cemented in place behind TBM (Simultaneous tail skin grouting)

Source – Mechanised Shield Tunnelling - Maidl, et al (2013)

Page 11: IAC Presentation, August 17, 2017 Ground Movement Impact … · 2018. 6. 12. · Concerns groundwater alteration (reduction) that may cause subsidence Concerns dewatering may cause

Construction Engineering - Tunnel

August 17, 2017 11

Cross passages Emergency exits between

tunnels & EOU’s for single tunnel case

Probe & grout first

Excavated with small plant

Jacked concrete box or sprayed concrete support

Plastic membrane or gasket seals for waterproofing

Note – EOU stands for Emergency Out & Under.

Page 12: IAC Presentation, August 17, 2017 Ground Movement Impact … · 2018. 6. 12. · Concerns groundwater alteration (reduction) that may cause subsidence Concerns dewatering may cause

Construction Engineering - Tunnel

August 17, 2017 12

Spoil Management

Tunnel spoil conveyed to Northern portal

Detained in bunded concrete bays within covered sheds

Moved off site via truck

Page 13: IAC Presentation, August 17, 2017 Ground Movement Impact … · 2018. 6. 12. · Concerns groundwater alteration (reduction) that may cause subsidence Concerns dewatering may cause

Construction Engineering - Tunnel

August 17, 2017 13

Main construction laydown areas

Spoil transport route via FootscrayRoad to CityLink

Southern portals - spoil transport route via West Gate Freeway

Final disposal of spoil in accordance with legislation & EPRs

Source – Technical report A (Transport)

Northern Portal

Page 14: IAC Presentation, August 17, 2017 Ground Movement Impact … · 2018. 6. 12. · Concerns groundwater alteration (reduction) that may cause subsidence Concerns dewatering may cause

Construction Engineering

August 17, 2017 14

Port, CityLink and City Connections

River Crossings (Bridges)

Elevated Viaducts

Ramps

Page 15: IAC Presentation, August 17, 2017 Ground Movement Impact … · 2018. 6. 12. · Concerns groundwater alteration (reduction) that may cause subsidence Concerns dewatering may cause

Construction Engineering

August 17, 2017 15

Port, CityLinkand City Connections

Thick weak soil

Deep piled supports required

Page 16: IAC Presentation, August 17, 2017 Ground Movement Impact … · 2018. 6. 12. · Concerns groundwater alteration (reduction) that may cause subsidence Concerns dewatering may cause

Existing Conditions – Site Investigations

EES supported by extensive investigations and existing data

Geology distribution

Hydrogeology

Geomechnical properties

August 17, 2017 16

Page 17: IAC Presentation, August 17, 2017 Ground Movement Impact … · 2018. 6. 12. · Concerns groundwater alteration (reduction) that may cause subsidence Concerns dewatering may cause

Regional Surface Geology – Project Scale

August 17, 2017 17

Complex layer cake of hard basalt rock and sediments

‘Melbourne Formation’ bedrock tilted and buried deeply below younger geology

Capped at surface by younger (Newer) basalts

Trough of ‘Yarra Delta’ sediments east of river

Massive basalt flows~2-4 million years old Overlies older stratum

Trough of weak deltaic sediments to east of river<2 million year old

Source – Technical report D (Ground Movement)

Page 18: IAC Presentation, August 17, 2017 Ground Movement Impact … · 2018. 6. 12. · Concerns groundwater alteration (reduction) that may cause subsidence Concerns dewatering may cause

Existing conditions - human effects

Diversion & filling of waterways

Backfilled quarries

Contamination

Major infrastructure (e.g. North Yarra Main Sewer)

August 17, 2017 18

Source – Technical report D (Ground Movement)

Page 19: IAC Presentation, August 17, 2017 Ground Movement Impact … · 2018. 6. 12. · Concerns groundwater alteration (reduction) that may cause subsidence Concerns dewatering may cause

Assessment – Ground Movement The Ground Movement study objectives include:

Understand the risk of ground movement and potential impacts

To identify risk and mitigation measures to minimise adverse effects on land and river bank geomorphic stability from project activities

To develop performance requirements that drive acceptable outcomes

Note: Aspects associated with river erosion are addressed separately in Technical report E (Surface Water)

August 17, 2017 19

Page 20: IAC Presentation, August 17, 2017 Ground Movement Impact … · 2018. 6. 12. · Concerns groundwater alteration (reduction) that may cause subsidence Concerns dewatering may cause

Assessment – Ground Movement Ground movement risks include:

Damage to linear infrastructure pipelines rail lines roads bridges, etc.

Damage to buildings residential buildings, commercial buildings

August 17, 2017 20

Page 21: IAC Presentation, August 17, 2017 Ground Movement Impact … · 2018. 6. 12. · Concerns groundwater alteration (reduction) that may cause subsidence Concerns dewatering may cause

Assessment Methodology

Characterise the existing ground conditions and identify triggers

Develop predictive models of ground movement

Assess the level of risk of ground movement

Incorporate EPR’s measures to control and minimise risk

August 17, 2017 21

Page 22: IAC Presentation, August 17, 2017 Ground Movement Impact … · 2018. 6. 12. · Concerns groundwater alteration (reduction) that may cause subsidence Concerns dewatering may cause

West Gate Freeway

Works involve ‘at surface’ freeway widening and some bridge structure (common urban road works – example Tullamarine widening)

Ground movement risks localised and confined to road corridor assets (examples: pavement cracking, slope retention, settlement of new structures)

Considered manageable with existing EPRs (GMP1 to GMP6)

August 17, 2017 22

Page 23: IAC Presentation, August 17, 2017 Ground Movement Impact … · 2018. 6. 12. · Concerns groundwater alteration (reduction) that may cause subsidence Concerns dewatering may cause

Tunnel - Existing Conditions (Geology)

August 17, 2017 23

Strong ‘Newer’ basalt rock (Tvn) Variable ‘Tertiary’ sediments (Tmn, Tpa, Tpb, Tew) – clays and sands Weathered ‘Older basalt’ (Tvo)

Source – Technical report D (Ground Movement)

Page 24: IAC Presentation, August 17, 2017 Ground Movement Impact … · 2018. 6. 12. · Concerns groundwater alteration (reduction) that may cause subsidence Concerns dewatering may cause

Simplified Tunnel Geology

August 17, 2017 24

Simplified geology overview - sediments ‘sandwiched’ between two ancient volcanic flows

‘Newer’ Basalt rock

‘Older’ Basalt rock

SedimentsTunnel

Page 25: IAC Presentation, August 17, 2017 Ground Movement Impact … · 2018. 6. 12. · Concerns groundwater alteration (reduction) that may cause subsidence Concerns dewatering may cause

Tunnel – key issues (potential triggers)

August 17, 2017 25

Ground movement (settlement) impacting on existing buildings and other sensitive infrastructure along the tunnel alignment

Ground movement due to soil relaxation or instability towards large open excavations

Depressurisation of groundwater in areas underlain by compressible soils, which may trigger consolidation settlement

Page 26: IAC Presentation, August 17, 2017 Ground Movement Impact … · 2018. 6. 12. · Concerns groundwater alteration (reduction) that may cause subsidence Concerns dewatering may cause

SUBSIDENCE

August 17, 2017 26

TUNNELLING SETTLEMENT

GROUND RELAXATION

Tunnel – key issues (potential triggers)

Page 27: IAC Presentation, August 17, 2017 Ground Movement Impact … · 2018. 6. 12. · Concerns groundwater alteration (reduction) that may cause subsidence Concerns dewatering may cause

Tunnel – Design considerations

August 17, 2017 27

Piled retention and sprayed concrete to support portal excavations

Injection grouting (reduced groundwater inflow)

Recharge wells (mitigates groundwater lowering)

EPB tunnel boring machine (controls ground stability and groundwater inflow)

Undrained ‘tanked’ design

Page 28: IAC Presentation, August 17, 2017 Ground Movement Impact … · 2018. 6. 12. · Concerns groundwater alteration (reduction) that may cause subsidence Concerns dewatering may cause

Tunnel - Assessment Findings (Portal & Tunnel)

August 17, 2017 28

Largest settlements predicted near northern portal (industrial zone), approximately 60-70mm

Predicted movements reduce as tunnel deepens

Thick (10-15 m) cap of strong basalt geology assists in protection of residential areas

Negligible ground movement west of Williamstown road (in strong rock)

Predicted area of higher settlement

Source – Technical report D (Ground Movement)

Former Stony Creek

Page 29: IAC Presentation, August 17, 2017 Ground Movement Impact … · 2018. 6. 12. · Concerns groundwater alteration (reduction) that may cause subsidence Concerns dewatering may cause

Tunnel - Assessment Findings

August 17, 2017 29

Controlling uncertainty - Tunnelling under buried creek (former Stony Creek)

Source – Technical report D (Ground Movement)

3D model

2D model

Buried creek

Design allowance – 5 m rock cover Consultation with VicRoads (EPR GMP1 to 4) Detailed design Construction (ALARP)

(EPR GMP1, GMP5, GMP6)

ALARP = As Low As Reasonably Practical

Page 30: IAC Presentation, August 17, 2017 Ground Movement Impact … · 2018. 6. 12. · Concerns groundwater alteration (reduction) that may cause subsidence Concerns dewatering may cause

Risk - combined sources (Construction case)

August 17, 2017 30

Source – Technical report D (Ground Movement)

moderate risk(low cover)

moderate risk(former Stony Creek)

low risk

Combined ground movement risk prediction for groundwater subsidence, tunnelling & portal excavation

Groundwater drawdowns based on modelling (Technical Report E)

Conservative - does not consider groundwater reinjection (favourable) low risk

Page 31: IAC Presentation, August 17, 2017 Ground Movement Impact … · 2018. 6. 12. · Concerns groundwater alteration (reduction) that may cause subsidence Concerns dewatering may cause

Risk during operation

August 17, 2017 31

Risk issues are limited to dewatering

Tunnel and portals designed as undrained ‘tanked’ structures

Predicted operational groundwater drawdown due to ‘leakage’ less than 1m*

Negligible ground movement (subsidence) predicted

* Based on Technical report C (Groundwater

Page 32: IAC Presentation, August 17, 2017 Ground Movement Impact … · 2018. 6. 12. · Concerns groundwater alteration (reduction) that may cause subsidence Concerns dewatering may cause

Tunnel EPR’s

August 17, 2017 32

GMP1 – Geotechnical model & assessment (maintain & update)

GMP2 – Drainage control (design and as reactive contingency)

GMP3 – Condition surveys (before and after)

GMP4 – Determine settlement limits of utilities with relevant service authority

(example – VicRoads, Melbourne Water, Mobil Exxon, etc)

GMP5 – Monitoring (linked with GMP1)

GMP6 – Implement timely mitigation to limit impacts if detected (plan, monitor, act)

Page 33: IAC Presentation, August 17, 2017 Ground Movement Impact … · 2018. 6. 12. · Concerns groundwater alteration (reduction) that may cause subsidence Concerns dewatering may cause

Port, CityLink and city connections

Area underlain by thick deposits of weak compressible Coode Island Silt (CIS) soil

Ground conditions poor

Risk would be mitigated by standard engineering design solutions used such as:1. Deep piled support common to area and well understood2. Limiting fill loads (e.g. embankment weight that may compress CIS) or alternatively

adopt ground improvement

August 17, 2017 33

Page 34: IAC Presentation, August 17, 2017 Ground Movement Impact … · 2018. 6. 12. · Concerns groundwater alteration (reduction) that may cause subsidence Concerns dewatering may cause

Key submission issues

Summary of issueConcerns regarding tunnel northern portal position (options east of Maribyrnong River)

Response

Functional objectives constrained or compromised (covered by others)

Geotechnically unfavourable (thick deposits of weak compressible soils)

Potential long term subsidence risks (i.e. drainage and consolidation of Coode Island Silt)

Significant risk of ‘blow outs’ into base of river if tunneled (risk to river health)

Greater presence of contaminated soil and acid sulphate soil east of river (spoil issues)

Significant risk of encountering obstructions (e.g. old piles) due to soft ground

August 17, 2017 34

Page 35: IAC Presentation, August 17, 2017 Ground Movement Impact … · 2018. 6. 12. · Concerns groundwater alteration (reduction) that may cause subsidence Concerns dewatering may cause

Key submission issues

Summary of issueConcerns groundwater alteration (reduction) that may cause subsidence

Concerns dewatering may cause moisture loss and shrinkage of reactive founding soils.

Response

Favourable geology (i.e. compressible soil deposits in tunnel area thin or absent)

Analysis shows low risk of adverse subsidence impacts due to construction dewatering

Groundwater located within the basalt rock, significantly below reactive soil zone

EPR GMP 2 – minimise adverse changes to groundwater level

August 17, 2017 35

Page 36: IAC Presentation, August 17, 2017 Ground Movement Impact … · 2018. 6. 12. · Concerns groundwater alteration (reduction) that may cause subsidence Concerns dewatering may cause

Key submission issues

Summary of issueConcern about how condition surveys will be undertaken

Response GMP3 requires condition surveys to be undertaken in areas of possible ground movement

risk: 1. Building condition surveys of buildings are required before & after construction for

comparison2. Any damage caused as a result of the project must be rectified or the asset owner

compensated3. Mediation and independent assessment would be undertaken to assess claims

August 17, 2017 36

Page 37: IAC Presentation, August 17, 2017 Ground Movement Impact … · 2018. 6. 12. · Concerns groundwater alteration (reduction) that may cause subsidence Concerns dewatering may cause

Key submission issues

Summary of issueConcern about impacts of ground movement on property and assets

Response Impacts for West Gate Freeway and City, Port, city connection localized For the Tunnel area:

Low Risk (residential zone) Two small moderate risk areas (industrial and freeway reserve)

Protection measures embodied within EPRs GMP1 to GMP6 (included in design)

August 17, 2017 37

Page 38: IAC Presentation, August 17, 2017 Ground Movement Impact … · 2018. 6. 12. · Concerns groundwater alteration (reduction) that may cause subsidence Concerns dewatering may cause

Response to IAC review report

The IAC review has concluded the that the relevant EES reports have been rigorous, comprehensive and diligent (14)

A number of detailed risks / issues have been identified: Ground Movement (67,68,70,78) Contaminated Soil and Spoil Management (93,94,96,101) Groundwater (20,34,35,38,39,40,42)

These risks would be subject to detailed design and where necessary, measures would be included in the CEMP and OEMP (as indicated in 43,46,71,79,80)

Specific responses for some items are provided by each Technical Expert

August 17, 2017 38

Page 39: IAC Presentation, August 17, 2017 Ground Movement Impact … · 2018. 6. 12. · Concerns groundwater alteration (reduction) that may cause subsidence Concerns dewatering may cause

Response to IACSummary of issueGround or groundwater related risks due to construction delays or TBM performance

Examples: Mixed ground types (fluctuation in TBM face pressure & plug consistency) Areas of low cover (heave / frac-out) Uncontrolled water in-rush

Known construction risks considered in design and selection of tunneling methodology

BUT - some variance in local geological conditions always possible

Risks continually reassessed during construction – observational principle (EPR GMP1,5 & 6)

August 17, 2017 39

Page 40: IAC Presentation, August 17, 2017 Ground Movement Impact … · 2018. 6. 12. · Concerns groundwater alteration (reduction) that may cause subsidence Concerns dewatering may cause

Response to IACCEMP controls examples: Technical (engineering controls)

1. Ground improvement, structural support, service isolation or diversion 2. Real time monitoring and adjustment of TBM pressures (linked to GM instrumentation)3. Jaw crusher (breaks down boulders)4. Tail skin grouting (minimises annular closure)5. Compressed air, bentonite, polymer, foam (stabilize ground and water)

Procedural1. Risk register (a live document)2. Permit to excavate (reviews risks on a daily basis)3. Planned interventions (reduces the risk of mechanical breakdown)

Contingency Planning

August 17, 2017 40

Page 41: IAC Presentation, August 17, 2017 Ground Movement Impact … · 2018. 6. 12. · Concerns groundwater alteration (reduction) that may cause subsidence Concerns dewatering may cause

Response to IACSummary of issueDepressurization of compressible soil (Coode) impacting on the West Gate Freeway

Considered in Tunnel section of study (7.4.1) Freeway embankment on stable soils – Coode replaced with engineered fill Ground movement prediction assumes drawdown with no reinjection (conservative) Grout curtain and reinjection as part of design around southern portals

August 17, 2017 41

Page 42: IAC Presentation, August 17, 2017 Ground Movement Impact … · 2018. 6. 12. · Concerns groundwater alteration (reduction) that may cause subsidence Concerns dewatering may cause

Response to IACSummary of issueResponse 78: residual soil moisture depletion (clay shrinkage) Near surface drying/wetting (Hs zone approx. 1.8m) Unsaturated soil problem (suction u change in clay) Water table is in rock (no suction change)

August 17, 2017 42

Water table

ROCK

CLAY

Source – AS 2870-2011

Page 43: IAC Presentation, August 17, 2017 Ground Movement Impact … · 2018. 6. 12. · Concerns groundwater alteration (reduction) that may cause subsidence Concerns dewatering may cause

Thank youTrevor O’Shannessy

August 17, 2017 43