ice & iosh session outline merseyside cdm project
TRANSCRIPT
15/11/2013
1
ICE & IOSH
Merseyside
CDM project lifecycle
and best practice
12th
November 2013
Speaker: Dave Haddon CMIOSH
1st Choice Health and Safety Ltd
www.1stchoicehealthandsafetyltd.co.uk 1
Session outline
• Typical project
lifecycle
• Does CDM apply
to my project?
• Brief outline of
duties
• Best practice,
competence and
lessons learned
• Anticipated legal
changes 2
Disclaimer
Disclaimer: Any views or opinions expressed on any matters by the presenters or participants during or in connection with this presentation are solely the views of the authors of the respective comments and/or opinions and must not be taken to be the views of ICE or any other organisation. ICE makes no representations, warranties or assurances concerning any information provided in these presentations and accept no responsibility for the content and/or accuracy
3
Typical project lifecycle
Five phases of construction projects for H&S
purposes, regardless of project size:-
1) Concept and feasibility
2) Design and planning
3) Tender/selection of contractors
4) Construction phase
5) Commissioning and handover
N.B. Construction work is not just “new-build”
4
Examples - 1
Construction work includes:-
• Building works, e.g. new buildings with foundations
• Renovation, e.g. non-structural improvements
• Alteration, e.g. structural modification/conversion
• Maintenance of existing premises (occupied or
unoccupied), e.g. minor repairs, repainting, replacing
roof tiles, re-glazing windows
5
Examples - 2
• Civil engineering or engineering construction work,
e.g. drainage, roads, bridges, railways.
• Decommissioning, e.g. services isolation & removal
• Demolition, e.g. breaking down, removing
• Dismantling, e.g. disassembly of structures
A construction site is where construction work occurs
6
15/11/2013
2
Range of Activities - 1
A wide range of activities will take place during a typical construction project, e.g:-
• Site investigation, e.g. boreholes, asbestos survey
• Site clearance, e.g. removal of hardcore
• Excavation, e.g. earthworks, trench, shaft, tunnel
• Loading, unloading and storage of materials
• Site movements, e.g. plant, vehicles, people
7
Range of Activities - 2
• Fabrication of structural parts, installation/removal
• Decoration, refurbishment or redecoration
• Cleaning of structures, e.g. pressure spray or corrosive substances
• Installation, removal and maintenance of services (electricity, water, gas)
• Landscaping
8
QUESTION 1
DOES CDM APPLY TO
MY CONSTRUCTION
PROJECT?
9
ANSWER
YES!
GENERAL CDM
DUTIES FOR ALL
PROJECTS 10
Key Players
ALL PROJECTS:-
• Client
• Designers
• Contractors
PLUS FOR NOTIFIABLE PROJECTS:-
• CDM Co-ordinator
• Principal Contractor
11
QUESTION 2
WHEN IS
CONSTRUCTION
WORK NOTIFIABLE?
12
15/11/2013
3
ANSWER
LIKELY MORE THAN
30 WORKING DAYS
OF CONSTRUCTION
WORK (OR 500
PERSON DAYS) 13
Project notification
(F10) - 1
CDM Regs Schedule 1:
1) Date of forwarding
2) Exact address of construction site
3) Name of local authority where the site is
located
4) Brief description of the project and the
construction work it includes
5) Client contact details (name, address, tel,
email)
14
Project notification
(F10) - 2
6) CDM Co-ordinator contact details (name,
address, tel, email)
7) Principal Contractor contact details (name,
address, tel, email)
8) Date planned for start of construction phase
9) Time allowed by Client for Principal
Contractor planning and preparation for
construction work
10) Planned duration of construction phase
15
Project notification
(F10) - 3
11) Estimated maximum number of people at
work on the construction site
12) Planned number of contractors on the
construction site
13) Name and address of any contractor
already appointed
14) Name and address of any designer already
engaged
15) Declaration signed by or on behalf of Client
that he is aware of his CDM Regs duties 16
Everyone’s CDM duties - 1
For all construction projects:
• Check own competence
• Co-operate with others and co-ordinate work so as to ensure the health and safety of construction workers and others who may be affected by the work
• Report obvious risks
17
Everyone’s CDM duties - 2
• For any work under their control, comply with the requirements in Schedule 3 of the CDM Regulations, for reports of inspections of excavations, cofferdams and caissons
• For any work under their control, comply with the requirements of Part 4 of the CDM Regulations, for health and safety on construction sites
18
15/11/2013
4
Everyone’s CDM duties - 3
• Take account of and apply “the general principles of prevention” when carrying out their duties (L144 Appendix 7):
Avoid risks
Evaluate risks which cannot be avoided
Combat risks at source
Adapt the work to the individual, especially workplace design, choice of work equipment & working/production methods, particularly to alleviate monotony and pre-determined work rate and to reduce their effect on health
19
Everyone’s CDM duties - 4
Adapt to technical progress
Replace the dangerous by non-dangerous or less dangerous
Develop a coherent overall prevention policy which covers technology, organisation of work, working conditions, social relationships and the influence of factors relating to the working environment
Give collective protective measures priority over individual protective measures
Give appropriate instructions to employees
20
Who is a Client?
• A Client is an organisation or individual for
whom a construction project is carried out.
• Clients only have duties under CDM when
the project is associated with a business or
other undertaking (whether for profit or not).
• Domestic clients have no duties under the
current CDM Regulations
21
Exemption of Domestic
Clients
• Domestic clients have no duties under the
current CDM Regulations
• Domestic clients are people who have
construction work carried out on their own
home, where the work is not business-
related, eg. not alterations to a shop or a
rented-out flat
• Designers and contractors working for
domestic clients still have all H&S duties
including CDM requirements
22
Client’s CDM Duties - 1
For all projects:
• Check competence and resources of all their appointees
• Ensure there are suitable management arrangements for the project, including:
Health and safety in construction work
Welfare facilities to CDM Regs Schedule 2
Workplace designs to suit the Workplace (Health, Safety & Welfare) Regulations 1992
23
Client’s CDM Duties - 2
• Allow sufficient time and resources for all stages
• Ensure that relevant pre-construction information is provided promptly to all designers and contractors, including:
any information about the site or the construction work and any future use as a workplace
the minimum time allowed to client-appointed contractors for planning and preparation before they begin construction work
any information in any existing Health & Safety File
24
15/11/2013
5
Client’s CDM Duties - 3
Additionally for notifiable projects:
• Appoint a CDM Co-ordinator, as soon as practicable after any initial design work or other preparation for construction work has begun
• Then appoint a competent principal contractor, as soon as practicable after the Client knows enough about the project to select a suitable appointee
N.B. Client takes on the respective duties by default if the appointments not made, or if gaps in appointments
25
Client’s CDM Duties - 4
• Make sure the construction phase does not start unless there are suitable welfare facilities and construction phase plan in place
• Provide CDM co-ordinator with pre-construction information (including the minimum time allowed to the Principal Contractor for planning and preparation for construction work), and information for inclusion in the Health and Safety File
• After the construction phase, keep Health and Safety File available for inspection and revised if necessary
26
Who are CDM
Designers?
• Designers are those who have a trade or business
which involves preparing or modifying designs for
construction work and variations.
• Also those who arrange for employees or others
under their control to prepare designs relating to a
structure or part of a structure
• A designer could be an architect, structural
engineer, building surveyor, materials purchaser,
contractor, temporary works engineer, shopfitter etc
• Design includes drawings, design details,
specification, bill of quantities, design calculations
27
Designers Duties - 1
For all projects, ensure that:
• Before starting design work, check the Client for the
project is aware of their duties
• Take due account of other design considerations in
performing their CDM design duties
• Design to avoid foreseeable risk to persons during
construction, cleaning, maintenance, and use as a
workplace
28
Designers Duties - 2
• In design, eliminate hazards which may give rise to
risks, and reduce risks from any remaining hazards,
giving collective measures priority over individual
measures
• Take account of the Workplace (HSW) Regs 1992
provisions relating to design and materials used in
workplace structures
• Provide information with the design about design
aspects, construction and maintenance to assist the
Client, other designers and contractors to comply
with CDM (e.g. notes on drawings , specifications)
29
Designers Duties - 3
Additionally where a project is notifiable:
• Shall not commence beyond initial design work
unless a CDM Co-ordinator has been appointed
• Provide information with the design about design
aspects, construction and maintenance to assist the
CDM Co-ordinator to comply with CDM (e.g. notes on
drawings), including in relation to the health and
safety file
30
15/11/2013
6
Overseas Designers
For designs prepared or modified outside GB, the
responsibility for ensuring compliance with CDM
designer duties rests with:
• the person who commissions the design if he is
established in GB; or if not established in GB, with
• any Client for the project
31
Who are Contractors?
• Contractors are those doing the physical
construction work and are those most at risk
of injury and ill health.
• All contractors have a part to play in
ensuring the site is a safe and healthy place
to work.
32
Contractors Duties - 1
On all construction projects:
• Check client aware of client’s duties
• Plan, manage and monitor own work and that
of workers
• Check competence of all their appointees
and workers
• Information and training for own workers,
e.g. site induction, risk assessments, site
rules, emergency procedures
33
Contractors Duties - 2
• Do not start work unless site secure from
unauthorised access
• Ensure that there are adequate welfare
facilities for all their workers – Schedule 2
• Comply with the specific requirements of
part 4 of the CDM Regulations for site health
and safety
34
Schedule 2 - Welfare
• Sanitary Conveniences
• Washing Facilities
• Drinking Water
• Changing rooms and lockers
• Facilities for rest
35
Site H&S Duties
CDM Regulations Part 4
Regulations 25 to 44
(Reg 25: Application of Regs 26 to 44)
36
15/11/2013
7
26: Safe Places of Work
37
27: Good Order and Site
Security
38
28: Stability of
structures
39
29: Demolition or
Dismantling
40
30: Explosives
41
31: Excavations
42
15/11/2013
8
32: Cofferdams and
Caissons
43
33: Reports of
Inspections
44
Schedule 3: reports
• Name and address for whom carried out
• Location of place of work inspected
• Description of place of work inspected
• Date and time of inspection
• Details of risks identified
• Details of actions taken to eliminate or reduce risk
• Details of any further action necessary
• Name and position of person making the report.
45
34: Energy Distribution
Installations
46
35: Prevention of
Drowning
47
36: Traffic routes
48
15/11/2013
9
37: Vehicles
49
38: Prevention of Risk
from Fire etc
50
39: Emergency
Procedures
51
40: Emergency Routes
and Exits
52
41: Fire Detection and
Fire-Fighting
53
42: Fresh Air
54
15/11/2013
10
43: Temperature and
Weather Protection
55
44: Lighting
56
Contractors Duties - 3
Additionally for notifiable projects:
• Before starting work, have names of CDM co-
ordinator and principal contractor, relevant
parts of construction phase plan, and check
HSE (or ORR) has been notified.
• Cooperate with Principal Contractor in
planning and managing work, including
reasonable directions and site rules.
57
Contractors Duties - 4
• Provide details to the principal contractor of any contractor whom he engages in connection with carrying out the work.
• Provide any information needed for the health and safety file.
• Inform Principal Contractor of problems with construction phase plan.
• Inform Principal Contractor of any RIDDOR reportable incidents etc.
58
CDM Co-ordinator
• Replaces the CDM1994 Planning Supervisor
• Appointed by the Client, on notifiable projects only
• Assists with Health and Safety risk management matters, primarily for planning and design (including ongoing design during construction, eg. design changes, temporary works), and as-built information for H&S
59
CDM Co-ordinator
Duties - 1
• Advise and assist the Client with his/her
duties, eg. competence, mgmt arrangements
• Notify the project to HSE/ORR, on F10 form
• Facilitate co-operation and co-ordination of
health and safety measures during planning
and preparation for the construction phase
• Liaise with Principal Contractor regarding
the contents of the Health and Safety File,
information needed for the construction
phase plan, and relevant design development
60
15/11/2013
11
CDM Co-ordinator
Duties - 2
• Identify, collect and pass on pre-construction
information
• Ensure designers comply with their duties
• Ensure co-operation between designers and
principal contractor during construction
phase, regarding any ongoing design or
design change
• Prepare/update the Health and Safety File
and pass to the Client at the end of the
construction phase
61
Principal Contractor
• Appointed by the Client, on notifiable
projects only
• The Principal Contractor is the main
managing contractor on site responsible for
properly planning, managing and co-
ordinating the work during the construction
phase.
62
Principal Contractor
Duties - 1
• Plan, manage and monitor construction
phase in liaison with contractors
• Prepare, develop and implement a written
plan and site rules (initial plan to be
completed before the construction phase
begins)
• Give contractors relevant parts of the plan
and display the F10 notification. Ensure all
contractors are informed of the minimum
time allowed for planning and preparation
before they begin construction work
63
Principal Contractor
Duties - 2
• Make sure adequate welfare facilities to CDM
Schedule 2 are provided from the start and
maintained throughout the construction
phase
• Check competence of all appointees
• Ensure all workers have site inductions and
any further information and training needed
for the work
• Consult with the workers
64
Principal Contractor
Duties - 3
• Liaise with CDM co-ordinator regarding
ongoing design
• Secure the site against unauthorised access
65
H&S Planning
• CDM1994 pre-tender plan now replaced by
CDM2007 pre-construction information and
applies to all projects (some additional
requirements for notifiable projects) – typical
contents in L144 Appendix 2
• Construction Phase Plan by principal
contractor, on notifiable projects only –
typical contents in L144 Appendix 3
• Demolition or dismantling – advance written
arrangements always, all projects (Reg 29)
66
15/11/2013
12
Provision of information
All projects – (see L144 page 13):-
• THE RIGHT INFORMATION FOR THE RIGHT
PEOPLE AT THE RIGHT TIME
• Clients must provide designers and
contractors who may be bidding for the work
(or who they intend to engage), with the
project-specific H&S information needed to
identify hazards and risks associated with
the design and construction work (THE PRE-
CONSTRUCTION INFORMATION)
67
Pre-construction
information
All projects (see L144 Appendix 2):-
• Description of project – eg. dates, client
• Client’s considerations and management
requirements – eg. H&S goals, site security
• Environmental restrictions and existing on-
site risks – safety hazards, health hazards
• Significant design and construction hazards
• Health and safety file – format, content
requirements
68
Construction Phase
Plan
Notifiable projects (see L144 Appendix 3):-
• Description of project – eg. dates, client
• Management of the work – eg. management
structure & responsibilities, H&S goals, site
liaison, design changes, inductions, welfare
• Arrangements for controlling significant site
risks – safety risks, health risks
• Health and safety file – layout & format,
collection/gathering/storage of information
69
Health & Safety File - 1
The purpose of the file is to give information
on the building or structure for any persons
who may later have to carry out any:
• Construction work
• Refurbishment
• Repairs
• Maintenance or Cleaning work.
70
Health & Safety File - 2
Typical content of H&S File (L144 para 263):-
• a brief description of work carried out
• any residual hazards that remain and how
they have been dealt with
• key structural principles and safe working
loads for floors and roofs
• hazardous materials used
• information regarding the removal or
dismantling of installed plant and equipment
71
Health & Safety File - 3
• health and safety information about
equipment provided for cleaning or
maintaining the structure
• the nature, location and markings of
significant services, including underground
cables; gas supply equipment; fire-fighting
services etc
• information and as-built drawings of the
structure, its plant and equipment
72
15/11/2013
13
Best practice &
competence - 1
• Leadership – IoD/HSE leaflet INDG417
• Workforce engagement and competence
• Competent health and safety assistance,
in-house and/or external
• Prepare for emergencies!
• Monitor, audit and review
• CDM competence criteria
• Personal development and CPD
73
Competence
• Part 2 of CDM2007, Regulation 4, all projects
• All key players must check competence of all
appointees.
• CDM dutyholders must not themselves
accept appointments unless competent
• Competence criteria: L144 Appendix 4 and 5
74
Contractors - 1
• Experience in type of work to be carried out
• Suitable H&S policy, organisation and
arrangements
• Quality and extent of risk assessments
• Recent H&S performance, eg. accident stats
• Any enforcement action record
• Suitable, up-to-date method statements
• Monitor H&S and carry out site inspections
• Qualifications and skills brought
75
Contractors - 2
• Construction Skills Certification Scheme
(CSCS) or equivalent cards for employees
• Membership of professional body or trade
association
• Employers’ liability & public liability
insurance
• References from previous clients
• Appraisal and selection of subcontractors
• Client liaison arrangements
76
WHERE is further info?
• Official websites (eg. www.hse.gov.uk)
• Trade associations
• Safety groups
• Professional bodies
• Solicitors
• Health and safety professionals
• Seminars, conferences and free events
77
Best practice &
competence - 2
• Use the HSE website – guidance and
current priorities for construction
• Management action plan, eg. training
• Target priorities, eg. higher risks
• Documented system if FIVE employees or
more (N.B. “employees” may include those
self-employed for tax and NI purposes)
78
15/11/2013
14
Material breach - FFI
• In the opinion of the HSE Inspector, there
is or has been a contravention of relevant
health and safety law that requires them to
notify the dutyholder in writing of their
opinion
• Whole visit fee, plus subsequent work –
identifying the breach, helping to put it
right, investigating, taking enforcement
action
79
Case study example
Work at height on unsafe working platform
• Maintenance employee standing on raised
forks of fork-lift truck approx 2.5m above
concrete floor, expected for one day
working on air-conditioning units
• Enforcement Management Model expects
Prohibition Notice to stop work (high risk)
• Risk gap analysis – actual risk: death or
serious personal injury is possible 80
Best practice &
competence - 3
• “If you comply with the law you will not pay
a fee” (ref: HSE48)
• Understand your legal duties
• Manage health, safety and welfare
• MIND THE RISK GAP!
• Brokers may arrange free help from
insurers (eg. construction sites)
81
FFI rates
• Inspector - £124 per hour (no VAT)
• Add costs for specialists
• “COIN” timesheet system at HSE
• Total time to end of investigation or
enforcement, or to start of prosecution
How much for an 8 hour day?
82
WHY introduce FFI?
• DWP – “Good health and safety, good for
everyone” 2011
• Theme – changing the culture of health
and safety in Britain
• FFI – shifting costs of regulation from
public purse to businesses that break
health and safety laws
83
Where next?
• Understand the law, including changes
• Manage health, safety and welfare
• Be proactive – risk action plan, training
• Documented H&S System
• Get help if you need it, eg. peer review
84
15/11/2013
15
Anticipated legal
changes - 1
• CDM 2014:-
More aligned with EU Directive
Loss of the competence requirements
CDM-C role swapped to Lead Designer
Domestic clients to have duties…..
BUT, LET’S WAIT AND SEE!
85
Anticipated legal
changes - 2
• HSE Approved Codes of Practice:-
Reduced in number (L21 already gone)
Reduced in length
• Further consolidation of Regulations
• Implementation of further EU laws
86
Acknowledgement
Copyright acknowledgement: This
presentation contains public sector
information published by the HSE and
licensed under the Open Government
Licence v1.0
87