How to use this example
The presentation covers a complete IDEA cycle, covering all stages, phases, and workstreams
There is more material than you will need depending on the client situation pick the element that
fit best in terms of volume and contents
The following elements have to be adapted to the specific client situation
Timelines and duration of stages and phases
Deliverables: Might have to be extended or reduced
Indication of in scope/out of scope (color code applies only to fix price projects)
Assignment of tasks to Lodestone, client business, client IT
In case you need additional material, please contact Jo-Ann Chua
-
8/11/2019 IDEA Method Overview Slides_REVIEWED_PF
3/87
Page 3 August 20, 2014IDEA Method Overview Slides_REVIEWED.ppt
Overview slides
-
8/11/2019 IDEA Method Overview Slides_REVIEWED_PF
4/87
Page 4 August 20, 2014IDEA Method Overview Slides_REVIEWED.ppt
IDEA methodology
Overview
The SAP Solution Manager IDEAroadmaps give SAP implementation projects a rapid start, a clear
structure and an access to the full library of the IDEAmethod accelerators
IDEA is a Lodestone owned methodology, structured into a Insight- Design-, Execute-, and Achieve phase to support allstages of global ERP program initiatives
Lodestone maintains its IDEAmethods as SAP Solution Manager IDEAroadmaps
The IDEAmethodology is managed within Lodestone by using a Wiki application platform. Via the Wiki every Lodestone
employee has got an access to the IDEAmethodology and the ability for an active contribution to the methodology
The methodology has proved to be successful in multiple large, international programs, and is
continuously enhance with our experience
The IDEAmethodology is based upon the standard SAP ASAP roadmap, but enlarged by specific stages, accelerators, and
tools to address complex business transformation requirements
-
8/11/2019 IDEA Method Overview Slides_REVIEWED_PF
5/87Page 5 August 20, 2014IDEA Method Overview Slides_REVIEWED.ppt
IDEA methodology
Knowledge sources
Lodestone has based its methodology on SAP ASAP, Six Sigma and the international
standard from the Project Management Institute (PMI) (www.pmi.org)
It combines these standard methodologies with its own best practices and extensive
experience from various global business harmonization and SAP rollouts projects with
major global companies
Lodestone trains its employee communities according to the Lodestone methodology and
provides them with standard tools, templates and best practices to ensure high qualityand consistency in project work
+
Extensive project experience
and best-practices from
complex businesstransformation project with
major global companies
http://www.pmi.org/http://www.pmi.org/ -
8/11/2019 IDEA Method Overview Slides_REVIEWED_PF
6/87Page 6 August 20, 2014IDEA Method Overview Slides_REVIEWED.ppt
Stages and work streams
According to the methodology a business transformation live cycle can be
divided into four stagesand eleven work-streamsas shown in the figure
Business Process Management (BPM)
Training (TRN)
Org. Change Management (OCM)
Project Management (PJM)
Program Management (PRM)
Data Management (DMA)
Security and Authorization (SAA)
Development Management (DEM)
System and Performance Testing (SPT)
Centre of Excellence (COE)
Technical Infrastructure (TIN)
Achievestage
Executestage
Designstage
Insightstage
-
8/11/2019 IDEA Method Overview Slides_REVIEWED_PF
7/87Page 7 August 20, 2014IDEA Method Overview Slides_REVIEWED.ppt
Stages and phases on Solution Manager
-
8/11/2019 IDEA Method Overview Slides_REVIEWED_PF
8/87Page 8 August 20, 2014IDEA Method Overview Slides_REVIEWED.ppt
IDEA on ASAP through the Wiki (HTML version)
IDEA on ASAPlink on the Wiki homepage provides access
Information, documentation, and contact details are all available
-
8/11/2019 IDEA Method Overview Slides_REVIEWED_PF
9/87Page 9 August 20, 2014IDEA Method Overview Slides_REVIEWED.ppt
IDEA model based on five terms
Stage, phase, work stream, work package, accelerator
ExecuteInsight AchieveDesign
Global
preparation
Global
realization
Ongoing
support,
rollout and
maintenance
Global
business
blueprint
Work streams Work packagesPhasesStages Accelerators
-
8/11/2019 IDEA Method Overview Slides_REVIEWED_PF
10/87Page 10 August 20, 2014IDEA Method Overview Slides_REVIEWED.ppt
Long version of stage overview
Responsibilities for single activities and deliverables have to be checked
Number and contents of columns client IT, client business, Lodestone have to be checked
Adapt logic of fixed price offer
-
8/11/2019 IDEA Method Overview Slides_REVIEWED_PF
11/87Page 11 August 20, 2014IDEA Method Overview Slides_REVIEWED.ppt
Insight phase
Insight
Program
definition
Insight
preparation
Strategic
blueprint
Month 1
Year
Month 2 Month 3 Month 4 Month 5 Month 6 Month 7 Month 8 Month 9 Month 10
Insight
M M
Insight preparation
Program definition
Strategic blueprint
Insight
Insight Design Execute Achieve
-
8/11/2019 IDEA Method Overview Slides_REVIEWED_PF
12/87
Page 12 August 20, 2014IDEA Method Overview Slides_REVIEWED.ppt
Insight phase
Insight preparation
Month 1
Year
Month 2 Month 3 Month 4 Month 5 Month 6 Month 7 Month 8 Month 9 Month 10
Insight
Insight preparation
Program definition
Strategic blueprintMM
Main activities Main deliverables
Defining the main prerequisites and directions
Initiate and plan the Insight stage Set up Insight stage organization Set up Insight stage infrastructure Review the initial risks Check and adapt methods and structure of the Insight stage
Insight phase kick off pack and workshop materials Overview and insight stage plan Insight stage project organization chart Insight stage roles and responsibilities High level risk assessment Documentation standards and naming conventions Documentation processes and tools Status management approach Updated budget
Insight Design Execute Achieve
-
8/11/2019 IDEA Method Overview Slides_REVIEWED_PF
13/87
Page 13 August 20, 2014IDEA Method Overview Slides_REVIEWED.ppt
Workstream Client IT Client bus. LodestoneActivities
Insight phase
Main activities
Initiate and plan the Insight stage PRM C C C
Set up Insight stage organization PJM C C C
Set up Insight stage infrastructure PJM C C C
Review the initial risks PRM C C C
Check and adapt methods and structure of the Insight stage PRM C C C
In scope of fix price offer Out of scope of fix price offer A = Accountable, R = Responsible, C = Consulted
Month 1
Year
Month 2 Month 3 Month 4 Month 5 Month 6 Month 7 Month 8 Month 9 Month 10
Insight
Insight preparation
Program definition
Strategic blueprintMM
Insight preparation
Insight Design Execute Achieve
-
8/11/2019 IDEA Method Overview Slides_REVIEWED_PF
14/87
Page 14 August 20, 2014IDEA Method Overview Slides_REVIEWED.ppt
Workstream Client IT Client bus. LodestoneDeliverables
Insight phase kick off pack and workshop materials PRM C C C
Overview and Insight stage plan PJM C C C
Insight stage project organization chart PRM C C C
Insight stage roles and responsibilit ies PRM C C C
High level risk assessment PJM C C C
Documentation standards and naming conventions PRM C C C
Documentation processes and tool PRM C C C
Status management approach PRM C C C
Updated budget PRM C C C
Insight phase
Insight preparation
Main deliverables
In scope of fix price offer Out of scope of fix price offer A = Accountable, R = Responsible, C = Consulted
Month 1
Year
Month 2 Month 3 Month 4 Month 5 Month 6 Month 7 Month 8 Month 9 Month 10
Insight
Insight preparation
Program definition
Strategic blueprintMM
Insight Design Execute Achieve
-
8/11/2019 IDEA Method Overview Slides_REVIEWED_PF
15/87
Page 15 August 20, 2014IDEA Method Overview Slides_REVIEWED.ppt
Insight phase
Strategic blueprint
Month 1
Year
Month 2 Month 3 Month 4 Month 5 Month 6 Month 7 Month 8 Month 9 Month 10
Insight
Insight preparation
Program definition
Strategic blueprintMM
Main activities Main deliverablesDefining the main prerequisites and directions
Understand the current strategic business objectives andas-is way of working
Define/develop the strategic business objectives Describe major future business opportunities/initiatives Identify target benefits Conduct synthesis workshop with senior management and
key stakeholders Document the strategic vision and case for change Describing the level 0 process overview
Decomposing the processes to level 2 Developing high level KPIs for the organization at the
appropriate levels within in the process model Develop a business rules matrix defining the structures within
the operating model
Strategic business objectives Identified business initiatives Target business benefits for the business initiatives Level 0 process overview Decomposition of processes to level 2 Strategy blueprint SAP mapping SAP solution map Operations design
Business rules matrix
Insight Design Execute Achieve
-
8/11/2019 IDEA Method Overview Slides_REVIEWED_PF
16/87
Page 16 August 20, 2014IDEA Method Overview Slides_REVIEWED.ppt
Insight phase
Workstream Client IT Client bus. LodestoneActivities
Understand the current strategic business objectives and as-is
way of workingPRM C C C
Define/develop the strategic business objectives PJM
Describe major future business opportunities/initiatives PJM C C C
Identify target benefits PRM C C C
Conduct synthesis workshop with senior management and
key stakeholdersPRM C C C
Document the strategic vision and case for change PRM C C C
Describing the level 0 processes overview PRM C C CDecomposing the processes to level 2 PRM C C C
Developing high level KPIs PRM C C C
Develop a business rules matrix PRM C C C
Main activities
In scope of fix price offer Out of scope of fix price offer A = Accountable, R = Responsible, C = Consulted
Strategic blueprint
Month 1
Year
Month 2 Month 3 Month 4 Month 5 Month 6 Month 7 Month 8 Month 9 Month 10
Insight
Insight preparation
Program definition
Strategic blueprintMM
Insight Design Execute Achieve
-
8/11/2019 IDEA Method Overview Slides_REVIEWED_PF
17/87
Page 17 August 20, 2014IDEA Method Overview Slides_REVIEWED.ppt
Workstream Client IT Client bus. Lodestone
In scope of fix price offer Out of scope of fix price offer A = Accountable, R = Responsible, C = Consulted
Strategic business objectives PJM C C C
Business initiatives PJM
Target business benefits for the business initiatives PJM C C C
Level 0 process overview PRM C C C
Decomposition of processes to level 2 PRM C C C
Strategy blueprint PRM C C C
SAP mapping PRM C C C
SAP solution map PRM C C C
Operations design PRM C C CBusiness rules matrix PRM C C C
DeliverablesMain deliverables
Insight phase
Strategic blueprint
Month 1
Year
Month 2 Month 3 Month 4 Month 5 Month 6 Month 7 Month 8 Month 9 Month 10
Insight
Insight preparation
Program definition
Strategic blueprintMM
Insight Design Execute Achieve
-
8/11/2019 IDEA Method Overview Slides_REVIEWED_PF
18/87
Page 18 August 20, 2014IDEA Method Overview Slides_REVIEWED.ppt
Insight phase
Program definition
Month 1
Year
Month 2 Month 3 Month 4 Month 5 Month 6 Month 7 Month 8 Month 9 Month 10
Insight preparation
Program definition
Strategic blueprintMM
Insight
Main activities Main deliverablesDetails the strategies for the program
Define the future setup of all related processes and organizations Definition of the scope and structure of projects, identifying the pilot
project, and elaborating a implementation plan and sequence Define methods, techniques, tools, standards, and procedures that
will be applied throughout the life of the program Consolidate the figures and set up a business case and
describes the transformation concept
Enterprise IT strategy Implementation scope and strategy Program Management strategy Data Management strategy Organizational Change Management strategy Business case Transformation concept
Insight Design Execute Achieve
-
8/11/2019 IDEA Method Overview Slides_REVIEWED_PF
19/87
Page 19 August 20, 2014IDEA Method Overview Slides_REVIEWED.ppt
In scope of fix price offer Out of scope of fix price offer A = Accountable, R = Responsible, C = Consulted
Define the future setup of processes and organizations PRM C C C
Definition of the scope and structure of projects, identifying
the pilot project, and elaborating a implementation plan
and sequence
PRM C C C
Define methods, techniques, tools, standards, and procedures
that will be applied throughout the life of the programPRM C C C
Consolidate the figures and set up a business case and
describes the transformation conceptPRM C C C
Workstream Client IT Client bus. LodestoneActivitiesMain activities
Insight phase
Program definition
Month 1
Year
Month 2 Month 3 Month 4 Month 5 Month 6 Month 7 Month 8 Month 9 Month 10
Insight preparation
Program definition
Strategic blueprintMM
Insight
Insight Design Execute Achieve
-
8/11/2019 IDEA Method Overview Slides_REVIEWED_PF
20/87
Page 20 August 20, 2014IDEA Method Overview Slides_REVIEWED.ppt
Enterprise IT strategy PRM C C C
Implementation scope and strategy PRM C C C
Organizational Change Management strategy PRM C C C
Program Management strategy PRM C C C
Data Management strategy PRM C C C
Business case PRM C C C
In scope of fix price offer Out of scope of fix price offer A = Accountable, R = Responsible, C = Consulted
Workstream Client IT Client bus. LodestoneDeliverablesMain deliverables
Insight phase
Program definition
Month 1
Year
Month 2 Month 3 Month 4 Month 5 Month 6 Month 7 Month 8 Month 9 Month 10
Insight preparation
Program definition
Strategic blueprintMM
Insight
Insight Design Execute Achieve
I D E A
-
8/11/2019 IDEA Method Overview Slides_REVIEWED_PF
21/87
Page 21 August 20, 2014IDEA Method Overview Slides_REVIEWED.ppt
Design stageglobal template
Template setup and maintenance
Ongoing
support,
rollout &
maintenance
Global
preparation
Global
business
blueprint
Global
realization
Month 1
Year
Month 2 Month 3 Month 4 Month 5 Month 6 Month 7 Month 8 Month 9 Month 10
M M
Global blueprint Global realization
Globalpreparation
M
Design
Design
Insight Design Execute Achieve
I i h D i E A hi
-
8/11/2019 IDEA Method Overview Slides_REVIEWED_PF
22/87
Page 22 August 20, 2014IDEA Method Overview Slides_REVIEWED.ppt
Month 1
Year
Month 2 Month 3 Month 4 Month 5 Month 6 Month 7 Month 8 Month 9 Month 10
Global realizationGlobal blueprint
Globalpreparation M MM
Design
Main activities Main deliverablesInitiate and plan the global implementation program
Initiate and plan the global program Initiate and start planning of the template project Define and document the solution scope Define the implementation strategy, overall program plan,
and schedule Define and document the program and project standards,
guiding procedures and governance process Set up project organization Set up project infrastructure
Review initial risk assessment
High level program plan Detailed template project plan Template project charter High level risk assessment Solution scope Business scenario and process inventory Data migration strategy Develop implementation standards Develop program standards
Project organization chart Project team training concept and plan System and client concept
Design stageglobal template
Template setup and maintenance
Insight Design Execute Achieve
I i ht D i E t A hi
-
8/11/2019 IDEA Method Overview Slides_REVIEWED_PF
23/87
Page 23 August 20, 2014IDEA Method Overview Slides_REVIEWED.ppt
Initiate and plan the global program PRM C C R, A
Initiate and start planning of the template project PJM C C R, A
Define and document the level solution scope PJM C C R, A
Define the implementation strategy, overall program plan
and schedulePRM C C R, A
Define and document the program and project standards,
guiding procedures and governance processPRM R C R, A
Set up project organization PRM R R R, A
Set up project infrastructure PRM R, A C C
Review initial risk assessment PRM R R R
Workstream Client IT Client bus. LodestoneActivities
Main activities
In scope of fix price offer Out of scope of fix price offer A = Accountable, R = Responsible, C = Consulted
Month 1
Year
Month 2 Month 3 Month 4 Month 5 Month 6 Month 7 Month 8 Month 9 Month 10
Global realizationGlobal blueprint
Globalpreparation M MM
Design
Design stageglobal template
Global preparation
Insight Design Execute Achieve
Insight Design Execute Achieve
-
8/11/2019 IDEA Method Overview Slides_REVIEWED_PF
24/87
Page 24 August 20, 2014IDEA Method Overview Slides_REVIEWED.ppt
Workstream Client IT Client bus. Lodestone
High level program plan PRM R R R, A
Detailed template project plan PRM R R R, A
Template project charter PRM R R R, A
High level risk assessment PRM R R R, A
Solution scope PRM R R R, A
Business scenario and process inventory PJM C R, A R, A
Data migration strategy DMA R R R, A
Develop implementation standards PRM R R R, A
Develop program standards PRM R R R, A
Project organization chart PJM C C R, A
Project team training concept and plan TRN C C R, A
In scope of fix price offer Out of scope of fix price offer A = Accountable, R = Responsible, C = Consulted
Deliverables
Main Deliverables
Month 1
Year
Month 2 Month 3 Month 4 Month 5 Month 6 Month 7 Month 8 Month 9 Month 10
Global realizationGlobal blueprint
Globalpreparation M MM
Design
Design stageglobal template
Global preparation
Insight Design Execute Achieve
Insight Design Execute Achieve
-
8/11/2019 IDEA Method Overview Slides_REVIEWED_PF
25/87
Page 25 August 20, 2014IDEA Method Overview Slides_REVIEWED.ppt
Design stageglobal template
Global blueprint
Finalize template project planning Define template scope Define communication strategy and plan Perform team training (phase specific) Develop end-user training strategy Prepare and conduct Business Requirements Workshops
(BRW)(collect documentation about current processes,standards, systems)
Propose and decide on solution for gaps
Prepare and conduct White Smoke (WS) Workshop 1 (businessprocess and design decisions, incl. rough cut prototyping)
Create blueprint documentation Define center of excellence high level implementation plan Define system specification Quality review
End-user training strategy Organizational Change Management plan Project team training Business scenario Business process flows Process Master List (PML) Functional specifications (RICEF list) Data conversion object list Authorization strategy
Job role list Development and configuration standards Technical Change Management strategy User requirements specifications Business blueprint CoE high level processes Quality review report (incl. action plan) Realization phase WBS
Month 1
Year
Month 2 Month 3 Month 4 Month 5 Month 6 Month 7 Month 8 Month 9 Month 10
Global blueprint
Globalpreparation MBRW WS 1
Global realization
MM
Design
Main activities Main deliverables
Finalize the scope in all details and provide a "paper" solution for all processes using "White Smoke" workshops
Insight Design Execute Achieve
Insight Design Execute Achieve
-
8/11/2019 IDEA Method Overview Slides_REVIEWED_PF
26/87
Page 26 August 20, 2014IDEA Method Overview Slides_REVIEWED.ppt
Design stageglobal template
Global blueprint
Month 1
Year
Month 2 Month 3 Month 4 Month 5 Month 6 Month 7 Month 8 Month 9 Month 10
Global blueprint
Globalpreparation MBRW WS 1
Global realization
MM
Design
Workstream Client IT Client bus. LodestoneActivities
Main activities
In scope of fix price offer Out of scope of fix price offer A = Accountable, R = Responsible, C = Consulted
Finalize template project planning PJM R C R, A
Define template scope BPM R R R, A
Define communication strategy and plan PRM C R, A R
Perform team training (phase specific) TRN C C R, A
Develop end-user training strategy TRN C C R, A
Prepare and conduct Business Requirements
Workshops (BRW)PJM C R R, A
Propose and decide on solution for gaps BPM R R R, A
Prepare and conduct White Smoke Workshop 1 (WS1) BPM C R R, A
Create blueprint documentation BPM R R R, A
Define center of excellence high level implementation plan COE C C R, A
Define system specification TIN R R, A
Quality review PJM R R R, A
Insight Design Execute Achieve
Insight Design Execute Achieve
-
8/11/2019 IDEA Method Overview Slides_REVIEWED_PF
27/87
Page 27 August 20, 2014IDEA Method Overview Slides_REVIEWED.ppt
Design stageglobal template
Global blueprint
Month 1
Year
Month 2 Month 3 Month 4 Month 5 Month 6 Month 7 Month 8 Month 9 Month 10
Global blueprint
Globalpreparation MBRW WS 1
Global realization
MM
Design
Workstream Client IT Client bus. Lodestone
In scope of fix price offer Out of scope of fix price offer A = Accountable, R = Responsible, C = Consulted
End-user training strategy TRN C R R, A
Organizational change management plan OCM C R R, A
Authorization strategy SAA R R R, A
Business blueprint BPM R R R, A
CoE high level processes COE R R C
Development and configuration standards TIN R, A C C
Technical change management strategy PRM R R, A R
Project team training TRN C C R, A
User requirements specifications BPM C R R, A
Business scenario, process flows and PML BPM R R, A R
Functional specifications (RICEF List) BPM R R, A R
Job role list SAA C R, A R
Data conversion object list DMA R R, A R
Realization phase WBS PJM R R R, A
Quality review report (incl. action plan) PRM C C R, A
Deliverables
Main deliverables
g g
Insight Design Execute Achieve
-
8/11/2019 IDEA Method Overview Slides_REVIEWED_PF
28/87
Page 28 August 20, 2014IDEA Method Overview Slides_REVIEWED.ppt
Design stageglobal template
Global realization
Month 1
Year
Month 2 Month 3 Month 4 Month 5 Month 6 Month 7 Month 8 Month 9 Month 10
Global blueprint
Globalpreparation M
Global realization
MMWS 2 WS 3
Design
Main activities Main deliverables
Generate a SAP solution template according to the defined business blueprint
Build template system (configuration) Build template system (RICEF development) Update template documentation Perform data cleansing Prepare and conduct White Smoke (WS) workshop 2 for approval of
template system configuration Perform functional risk assessment Plan, prepare and execute unit- and integration testing Promote template scope to quality system
Plan cut over Plan data migration Set up of global security and authorization concept Start pilot rollout preparation Prepare and conduct White Smoke (WS) workshop 3 for approval
of tested template environment Quality review
System configuration documentation Detail design specifications Data cleansing schedule Test strategy and plan Data migration plan SOP list Functional risk assessment procedure Unit-/integration test overview list Unit-/integration test scripts
Unit-/integration test data Authorization matrix Cutover plan Promote changes to quality system Quality review/report (incl. action plan)
g g
Insight Design Execute Achieve
-
8/11/2019 IDEA Method Overview Slides_REVIEWED_PF
29/87
Page 29 August 20, 2014IDEA Method Overview Slides_REVIEWED.ppt
Design stageglobal template
Global realization
Month 1
Year
Month 2 Month 3 Month 4 Month 5 Month 6 Month 7 Month 8 Month 9 Month 10
Global blueprint
Globalpreparation M
Global realization
MMWS 2 WS 3
Design
Workstream Client IT Client bus. LodestoneActivities
Main activities
In scope of fix price offer Out of scope of fix price offer A = Accountable, R = Responsible, C = Consulted
Build template system (configuration) BPM R R R, A
Build template system (RICEF development) DEM R, A R
Update template documentation BPM R R R, A
Perform data cleansing DMA R R, A
Prepare and conduct White Smoke workshop 2 and 3 BPM C R R, A
Perform functional risk assessment SPT R, A R
Promote template scope to quality system TIN R, A C R
Plan, prepare and execute unit- and integration testing SPT R R R, A
Plan cut over PJM R R, A R
Plan data migration DMA R R R, ASet up of global security and authorization concept SAA R R R, A
Quality review PJM R R R, A
Start pilot rollout preparation PRM R R R, A
Insight Design Execute Achieve
-
8/11/2019 IDEA Method Overview Slides_REVIEWED_PF
30/87
Page 30 August 20, 2014IDEA Method Overview Slides_REVIEWED.ppt
Design stageglobal template
Global realization
Month 1
Year
Month 2 Month 3 Month 4 Month 5 Month 6 Month 7 Month 8 Month 9 Month 10
Global blueprint
Globalpreparation M
Global realization
MMWS 2 WS 3
Design
Workstream Client IT Client bus. Lodestone
In scope of fix price offer Out of scope of fix price offer A = Accountable, R = Responsible, C = Consulted
System configuration documentation BPM R R, A
Detail design specifications DEM R, A R
Test strategy and plan SPT R R R, A
Authorization matrix SAA R R R, A
Data migration plan DMA R R, A R
Data cleansing schedule DMA R R, A R
Unit-/integration test overview list SPT R R R, A
Unit-/integration test scripts SPT R R R, A
Unit-/integration test data SPT R R, A R
SOP list PJM R, A R, A Functional risk assessment PJM R R R,A
Cutover plan PJM/TIN R,A C R,A
Promote changes to quality system TIN R,A C R,A
Quality review/report (including action list) PRM C C R, A
Deliverables
Main deliverables
Insight Design Execute Achieve
-
8/11/2019 IDEA Method Overview Slides_REVIEWED_PF
31/87
Page 31 August 20, 2014IDEA Method Overview Slides_REVIEWED.ppt
Design stageglobal template
Ongoing support, rollout and maintenance
Month 1
Year
Month 2 Month 3 Month 4 Month 5 Month 6 Month 7 Month 8 Month 9 Month 10
Global blueprint
Globalpreparation M
Global realization
MWS 2 WS 3
Month 10+
Design
MOngoing support,
rollout andmaintenance
Main activities Main deliverables
Stabilize the template, finish rollout plans, and finalize packaging of the rollout package
Production support Going live check: verification session Performance monitoring for long term support Updated long term rollout plan Handover solution to centre of excellence Enhancement of global template Program closure
Going live check: verification session report Updated long term rollout plan Program closure document
Insight Design Execute Achieve
-
8/11/2019 IDEA Method Overview Slides_REVIEWED_PF
32/87
Page 32 August 20, 2014IDEA Method Overview Slides_REVIEWED.ppt
Design stageglobal template
Ongoing support, rollout and maintenance
Month 1
Year
Month 2 Month 3 Month 4 Month 5 Month 6 Month 7 Month 8 Month 9 Month 10
Global blueprint
Globalpreparation M
Global realization
MWS 2 WS 3
Month 10+
Design
MOngoing support,
rollout andmaintenance
Workstream Client IT Client bus. LodestoneActivities
Main activities
Production support PRM
Going live check: Verification session PRM
Performance monitoring for long term support PRM
Updated long term rollout plan PRM
Handover solution to centre of excellence PJM
Enhancement of global template PRM
Program closure PJM
In scope of fix price offer Out of scope of fix price offer A = Accountable, R = Responsible, C = Consulted
Insight Design Execute Achieve
-
8/11/2019 IDEA Method Overview Slides_REVIEWED_PF
33/87
Page 33 August 20, 2014IDEA Method Overview Slides_REVIEWED.ppt
Design stageglobal template
Ongoing support, rollout and maintenance
Month 1
Year
Month 2 Month 3 Month 4 Month 5 Month 6 Month 7 Month 8 Month 9 Month 10
Global blueprint
Globalpreparation M MWS 2 WS 3
Month 10+
Design
MOngoing support,
rollout andmaintenance
Going live check: verification session report PJM
Updated long term rollout plan PRM
Program closure document PJM
In scope of fix price offer Out of scope of fix price offer A = Accountable, R = Responsible, C = Consulted
Workstream Client IT Client bus. LodestoneDeliverables
Main deliverables
Global realization
Insight Design Execute Achieve
-
8/11/2019 IDEA Method Overview Slides_REVIEWED_PF
34/87
Page 34 August 20, 2014IDEA Method Overview Slides_REVIEWED.ppt
Execute stagepilot and rollout projects
Pilot and rollouts
Local
preparation
Month 1
Year
Month 2 Month 3 Month 4 Month 5 Month 6 Month 7 Month 8 Month 9 Month 10
Local blueprint Local realizationLocal
preparation
Local
cut-over
Local
business
blueprint
Local
realizatio
n
Local
cut-over
preparati
on
Local cut-over prep.
Local
cut-over
Execute
Execute
Insight Design Execute Achieve
-
8/11/2019 IDEA Method Overview Slides_REVIEWED_PF
35/87
Page 35 August 20, 2014IDEA Method Overview Slides_REVIEWED.ppt
Local preparation
Month 1
Year
Month 2 Month 3 Month 4 Month 5 Month 6 Month 7 Month 8 Month 9 Month 10
Local realizationLocal blueprintLocal
preparation
Execute
Local cut-over prep.
Local cut-over
M MMM M
Main activities Main deliverables
Provide detailed planning and preparation for the local rollout and mobilize the local project team
Update rollout project plan Detail blueprint WBS Define project goals and objectives Write local business case Identify project risks Define and document local project scope Perform DRAFT FIT/GAP against template Provide DRAFT solution for GAPs and develop effort estimate for
solution (GAPS: legal requirements, translations for forms andreports, interfaces to local systems, specific requirements frommajor customers)
Define local project organizational structure Define local project roles and responsibilities Prepare on-boarding documentation for project team Prepare local project infrastructure Prepare team training
Updated rollout project plan Business blueprint WBS Project charter Project communication plan Local business case Project organization chart Project roles and responsibilities Project effort estimation Resource plan Documented DRAF FIT/GAP analysis Project team training material Project risk management plan
Execute stagepilot and rollout projects
Insight Design Execute Achieve
-
8/11/2019 IDEA Method Overview Slides_REVIEWED_PF
36/87
Page 36 August 20, 2014IDEA Method Overview Slides_REVIEWED.ppt
Workstream Client IT Client bus. LodestoneActivities
Local preparation
Month 1
Year
Month 2 Month 3 Month 4 Month 5 Month 6 Month 7 Month 8 Month 9 Month 10
Local realizationLocal blueprintLocal
preparation
Execute
Local cut-over prep.
Local cut-over
M MMM M
Main activities
Update rollout project plan PRM R R R, A
Detail blueprint WBS PRM R R R, A
Define project goals and objectives PRM R R R,A
Write local business case PJM R A, R C
Define and document local project scope PJM R R R, A
Perform DRAFT FIT/GAP against template BPM R C A, R
Provide DRAFT solution for GAPs BPM R C A, R
Define local project organizational structure PJM C C A, R
Define local project roles and responsibilities PJM C C A, R
Prepare on-boarding documentation for project team PJM C A, RPrepare local project infrastructure PRM R, A C C
Prepare team training TRN C C R, A
In scope of fix price offer Out of scope of fix price offer A = Accountable, R = Responsible, C = Consulted
Execute stagepilot and rollout projects
Insight Design Execute Achieve
-
8/11/2019 IDEA Method Overview Slides_REVIEWED_PF
37/87
Page 37 August 20, 2014IDEA Method Overview Slides_REVIEWED.ppt
Workstream Client IT Client bus. Lodestone
Local preparation
Month 1
Year
Month 2 Month 3 Month 4 Month 5 Month 6 Month 7 Month 8 Month 9 Month 10
Local realizationLocal blueprintLocal
preparation
Execute
Local cut-over prep.
Local cut-over
M MMM M
Updated rollout project plan PJM R R R, A
Business blueprint WBS PJM R R R, A
Project charter PJM R R R, A
Project communication plan PJM R, A R
Local business case PJM R R R, A
Project organization chart PJM R R R, A
Project roles and responsibilities PJM R R R, A
Project effort estimation PJM C C R, A
Resource plan PJM R R R, A
Documented DRAF FIT/GAP analysis PJM R R R, AProject team training material TRN C C R, A
Project risk management plan PJM R R R, A
In scope of fix price offer Out of scope of fix price offer A = Accountable, R = Responsible, C = Consulted
Deliverables
Main deliverables
Execute stagepilot and rollout projects
Insight Design Execute Achieve
-
8/11/2019 IDEA Method Overview Slides_REVIEWED_PF
38/87
Page 38 August 20, 2014IDEA Method Overview Slides_REVIEWED.ppt
Local blueprint
Month 1
Year
Month 2 Month 3 Month 4 Month 5 Month 6 Month 7 Month 8 Month 9 Month 10
Local realizationLocal blueprintLocal
preparation
Execute
Local cut-over prep.
Local cut-over
M MMM MBRW WS 1
Project team training (template scope and methodology) Perform user requirement workshop to identify local GAPs Agree on solution for local GAPs (reject, local add-on, extend template) Planning for implementation of GAPs (local add ons and
template extensions) Prepare and conduct Business Requirements Workshops (BRW) Prepare local project documentation Align local data cleansing approach Align local data migration approach Identify and manage required organizational changes Define local end-user training strategy Conduct White Smoke (WS) Workshop to get blueprint approval Perform quality review
Local kick-off meeting Team and infrastructure setup Template training executed Documented FIT/GAP analysis Process Master List (PML) for project scope Functional specifications for approved local specifics Local business scenarios Local process flows and requirements Data cleansing and collection plan Local data migration object list Assessment of end-user role design Local training strategy Approved local blueprint Detailed work plan for realization phase Quality review/report (incl. action plan)
Main activities Main deliverables
Template enhancement with the local specifics, i.e., legal requirements, forms and reports.
Strict change and scope management to keep local specifics to a minimum and ensure common processes
Execute stagepilot and rollout projects
-
8/11/2019 IDEA Method Overview Slides_REVIEWED_PF
39/87
Insight Design Execute Achieve
-
8/11/2019 IDEA Method Overview Slides_REVIEWED_PF
40/87
Page 40 August 20, 2014IDEA Method Overview Slides_REVIEWED.ppt
Local blueprint
Month 1Year
Month 2 Month 3 Month 4 Month 5 Month 6 Month 7 Month 8 Month 9 Month 10
Local realizationLocal blueprintLocal
preparation
Execute
Local cut-over prep.
Local cut-over
M MMM MBRW WS 1
Workstream Client IT Client bus. Lodestone
Team and infrastructure setup TIN R R R, A
Local kick-off meeting PJM R R R, A
Template training executed TRN R R R, A
Documented FIT/GAP analysis BPM R R R, A
Process Master List (PML) for project scope PJM R R, A R
Functional specifications for approved local specifics BPM R R, A R
Local business scenarios BPM R R, A R
Local process flows and requirements BPM R R, A R
Data cleansing an collection plan DMA R R, A R
Local data migration object list DMA R, A R RAssessment of end-user role design SAA C R, A R
Local training strategy TRN C R R, A
Approved of local blueprint PJM R R R, A
Detailed work plan for realization phase PJM R R R, A
Quality review/report (incl. action plan) PRM C C R, A
In scope of fix price offer Out of scope of fix price offer A = Accountable, R = Responsible, C = Consulted
Deliverables
Main deliverables
Execute stagepilot and rollout projects
E t t il t d ll t j t
Insight Design Execute Achieve
-
8/11/2019 IDEA Method Overview Slides_REVIEWED_PF
41/87
Page 41 August 20, 2014IDEA Method Overview Slides_REVIEWED.ppt
Local realization
Month 1Year
Month 2 Month 3 Month 4 Month 5 Month 6 Month 7 Month 8 Month 9 Month 10
Local realizationLocal blueprintLocal
preparation
Execute
Local cut-over prep.
Local cut-over
M MMM M
Implement local add ons and template extensions(configuration, developments)
Prepare testing for local scope and template extensions Set up/adapt authorization profiles Prepare test plan Promote local project scope to quality/productive environment Execute unit- and integration testing Execute data collection and cleansing Define data migration plan Prepare cut over plan Preparation of end-user training material Create/update local SOPs Prepare and execute data migration trial runs Promote local project scope to production environment Perform quality review
Project report (scope, resources, timeline, risks) Configuration logs and development specifications Detail design papers Data conversion programs Functional risk assessment Test strategy and test plan Prepared test documentation (unit-, integration-, user acceptance) Unit- and integration test executed and signed off Data migration plan and schedule defined Cutover strategy and plan defined Training plan and training documentation Local SOPs defined Local authorization concept defined Approval of local build Quality review/report (incl. action plan)
Main activities Main deliverables
Implementation of the local specifics like local forms,
additional local configuration, local interfaces, operational testing, end- user training
Execute stagepilot and rollout projects
E t t il t d ll t j t
Insight Design Execute Achieve
-
8/11/2019 IDEA Method Overview Slides_REVIEWED_PF
42/87
Page 42 August 20, 2014IDEA Method Overview Slides_REVIEWED.ppt
Local realization
Month 1Year
Month 2 Month 3 Month 4 Month 5 Month 6 Month 7 Month 8 Month 9 Month 10
Local realizationLocal blueprintLocal
preparation
Execute
Local cut-over prep.
Local cut-over
M MMM M
Workstream Client IT Client bus. LodestoneActivities
Project team training (local realization) TRN R R R, A
Impl. local add ons and template ext. (configuration, developm.) BPM/DEM R R R, A
Build local RICEF DEM R, A R
Prepare testing for local scope and template extensions SPT R R R, A
Set up/adapt authorization profiles SAA R R R, A
Prepare test plan PJM R R R, A
Promote local project scope to quality/productive environment TIN R, A R
Execute unit- and integration testing SPT R R R, A
Execute data collection and cleansing DMA R R, A C
Define data migration plan DMA R R R, APrepare cut over plan PJM R R R, A
Preparation of end user training material TRN R R, A R
Create/update local SOPs OCM/BPM R R, A
Prepare and execute data migration trial runs DMA R, A R R
Perform quality review PJM R R R, A
In scope of fix price offer Out of scope of fix price offer A = Accountable, R = Responsible, C = Consulted
Main activities
Execute stagepilot and rollout projects
E t t il t d ll t j t
Insight Design Execute Achieve
-
8/11/2019 IDEA Method Overview Slides_REVIEWED_PF
43/87
Page 43 August 20, 2014IDEA Method Overview Slides_REVIEWED.ppt
Local realization
Month 1
Year
Month 2 Month 3 Month 4 Month 5 Month 6 Month 7 Month 8 Month 9 Month 10
Local realizationLocal blueprintLocal
preparation
Execute
Local cut-over prep.
Local cut-over
M MMM M
In scope of fix price offer Out of scope of fix price offer A = Accountable, R = Responsible, C = Consulted
Workstream Client IT Client bus. Lodestone
System configuration documentation BPM/DEM R R, A
Detail design papers DEM R, A R
Data conversion programs DMA R, A R, A
Functional risk assessment PJM R R R, A
Test strategy and test plan SPT R R R, A
Training plan and training documentation TRN R R R, A
Prepared test documentation SPT R R, A R
Unit- and integration test executed and signed off SPT C R, A R
Cutover strategy and plan defined PJM R R R, A
Data migration plan and schedule defined DMA R R R, ALocal authorization concept defined SAA R R R, A
Local SOPs defined OCM/BPM R R, A
Project reporting (scope, resources, timeline, risks) PJM R R, A
Approval of local build PRM R R, A R
Quality review/report (incl. action plan) PRM C C R, A
Deliverables
Main deliverables
Execute stagepilot and rollout projects
Execute stage pilot and rollout projects
Insight Design Execute Achieve
-
8/11/2019 IDEA Method Overview Slides_REVIEWED_PF
44/87
Page 44 August 20, 2014IDEA Method Overview Slides_REVIEWED.ppt
Local cut-over preparation
Month 1
Year
Month 2 Month 3 Month 4 Month 5 Month 6 Month 7 Month 8 Month 9 Month 10
Local realizationLocal blueprintLocal
preparation
Execute
Local cut-over prep.
Local cut-over
M MMM M
Support local business during user acceptance testing Define and agree upon go-live criteria list Execute master and transactional data loads Carry out data verification Conduct end-user training Set up user profiles Create quality report Define action plan for open issues Go-live communication to business and customers Perform gono go decision Cut over support and bug fixing
User acceptance testing executed and signed off Go-live criteria fulfilled and approved Data loads signed off and execute Date verification performed and accepted End-user training executed Training need analysis updated after training execution User profiles setup and blocked Project report (scope, resources, timeline, risks) Quality report signed Corrective actions defined and agreed upon Go live communication Detailed support organization for local cut-over defined Approval for go-live
Main activities Main deliverables
Complete the final preparation, system management, move from a pre-production environment to the live system
Execute stagepilot and rollout projects
Execute stage pilot and rollout projects
Insight Design Execute Achieve
-
8/11/2019 IDEA Method Overview Slides_REVIEWED_PF
45/87
Page 45 August 20, 2014IDEA Method Overview Slides_REVIEWED.ppt
Local cut-over preparation
Month 1
Year
Month 2 Month 3 Month 4 Month 5 Month 6 Month 7 Month 8 Month 9 Month 10
Local realizationLocal blueprintLocal
preparation
Execute
Local cut-over prep.
Local cut-over
M MMM M
Workstream Client IT Client bus. LodestoneActivities
Support local business during user acceptance testing SPT R R R, A
Define and agree upon go-live criteria list PJM R R R, A
Execute master and transactional data loads DMA R, A R R
Conduct end-user training TRN A R R, A
Carry out data verification DMA R R, A R
Set up user profiles SAA R R, A
Create quality report PJM R R, A
Define action plan for open issues PJM R R R, A
Go-live communication to business and customers PJM R R, A C
Perform gono go decision PJM R R, A RCut over support and bug fixing COE R R R, A
In scope of fix price offer Out of scope of fix price offer A = Accountable, R = Responsible, C = Consulted
Main activities
Execute stagepilot and rollout projects
Execute stage pilot and rollout projects
Insight Design Execute Achieve
-
8/11/2019 IDEA Method Overview Slides_REVIEWED_PF
46/87
Page 46 August 20, 2014IDEA Method Overview Slides_REVIEWED.ppt
Local cut-over preparation
Month 1
Year
Month 2 Month 3 Month 4 Month 5 Month 6 Month 7 Month 8 Month 9 Month 10
Local realizationLocal blueprintLocal
preparation
Execute
Local cut-over prep.
Local cut-over
M MMM M
Workstream Client IT Client bus. LodestoneDeliverables
Main deliverables
User acceptance testing executed and signed off SPT C R, A R
Go-live criter ia fulfilled and approved PJM R R, A R
Data loads signed off and executed DMA R R, A R
Date verification performed and accepted DMA R R, A R
End-user training executed TRN R R, A C
Project report (scope, resources, timeline, risks) PJM R R, A
Quality report signed PJM R, A R
Corrective actions defined and agreed upon PJM R R, A R
Approval for go-live PJM R R, A R
Go live communication OCM R, A CUser profiles setup and blocked SAA R, A R R
Training need analysis updated after training execution TRN R R, A
Detailed support organization for local cut-over defined COE R R R, A
In scope of fix price offer Out of scope of fix price offer A = Accountable, R = Responsible, C = Consulted
Execute stagepilot and rollout projects
Execute stage pilot and rollout projects
Insight Design Execute Achieve
-
8/11/2019 IDEA Method Overview Slides_REVIEWED_PF
47/87
Page 47 August 20, 2014IDEA Method Overview Slides_REVIEWED.ppt
Local cut-over
Month 1
Year
Month 2 Month 3 Month 4 Month 5 Month 6 Month 7 Month 8 Month 9 Month 10
Local realizationLocal blueprintLocal
preparation
Execute
Local cut-over prep.
Local cut-over
M MMM M
End-user support Bug fixing Prepare and execute first month end closing Hand over from local project team to local organization Hand over to support organization and ongoing support
Final Data loads executed and signed off (finance, after closing) Controlled ramp-up in Hyper-care mode Preparation of handover and handover sessions
Main activities Main deliverables
Ramp up live system and finalize cut-over, prepare handover to support organization
Execute stagepilot and rollout projects
Execute stage pilot and rollout projects
Insight Design Execute Achieve
-
8/11/2019 IDEA Method Overview Slides_REVIEWED_PF
48/87
Page 48 August 20, 2014IDEA Method Overview Slides_REVIEWED.ppt
Local cut-over
Month 1
Year
Month 2 Month 3 Month 4 Month 5 Month 6 Month 7 Month 8 Month 9 Month 10
Local realizationLocal blueprintLocal
preparation
Execute
Local cut-over prep.
Local cut-over
M MMM M
Workstream Client IT Client bus. LodestoneActivities
End-user support BPM R R R, A
Bug fixing BPM R R, A
Prepare and execute first month end closing BPM R R R, A
Hand over from local project team to local organization PJM R R R, A
Hand over to support organization and ongoing support PJM R R R, A
In scope of fix price offer Out of scope of fix price offer A = Accountable, R = Responsible, C = Consulted
Main activities
Execute stagepilot and rollout projects
Execute stage pilot and rollout projects
Insight Design Execute Achieve
-
8/11/2019 IDEA Method Overview Slides_REVIEWED_PF
49/87
Page 49 August 20, 2014IDEA Method Overview Slides_REVIEWED.ppt
Local cut-over
Month 1
Year
Month 2 Month 3 Month 4 Month 5 Month 6 Month 7 Month 8 Month 9 Month 10
Local realizationLocal blueprintLocal
preparation
Execute
Local cut-over prep.
Local cut-over
M MMM M
Workstream Client IT Client bus. LodestoneDeliverables
Main deliverables
Final data loads executed and signed off (finance, after closing) DMA R R, A R
Controlled ramp-up PJM R R R, A
Preparation of handover and handover sessions PJM R R R, A
In scope of fix price offer Out of scope of fix price offer A = Accountable, R = Responsible, C = Consulted
Execute stagepilot and rollout projects
Achieve stage sustain and continuous improvement
Insight Design Execute Achieve
-
8/11/2019 IDEA Method Overview Slides_REVIEWED_PF
50/87
Page 50 August 20, 2014IDEA Method Overview Slides_REVIEWED.ppt
Achieve stage sustain and continuous improvement
Sustain and improve
Month 1Year
Month 2 Month 3 Month 4 Month 5 Month 6 Month 7 Month 8 Month 9 Month 10
Achieve
Ensure
sustain
Continuous
improvement
Ensure sustain
Continuous improvement
Achieve stage sustain and continuous improvement
Insight Design Execute Achieve
-
8/11/2019 IDEA Method Overview Slides_REVIEWED_PF
51/87
Page 51 August 20, 2014IDEA Method Overview Slides_REVIEWED.ppt
Ensure sustain
Achieve stage sustain and continuous improvement
Month 1
Year
Month 2 Month 3 Month 4 Month 5 Month 6 Month 7 Month 8 Month 9 Month 10
Ensure sustain
Continuous improvement
System monitoring, management and tuning Incident and problem management Service management User authorizations and profiles management Change request and transport management Job scheduling Support pack and upgrade management Data archiving
Available and efficient SAP systems Efficient service processes Satisfied end-users Business value generating SAP solution Archived solution data
Main activities Main deliverables
Ensure smooth operations of the live site
Achieve stage sustain and continuous improvement
Insight Design Execute Achieve
-
8/11/2019 IDEA Method Overview Slides_REVIEWED_PF
52/87
Page 52 August 20, 2014IDEA Method Overview Slides_REVIEWED.ppt
Ensure sustain
Achieve stage sustain and continuous improvement
Workstream Client IT Client bus. LodestoneActivities
System monitoring, management and tuning COE
Incident and problem management COE
Service management COE
User authorizations and profiles management SAA
Change request and transport management COE
Job scheduling DEM
Support pack and upgrade management DEM
Data archiving PRM
Main activities
Month 1
Year
Month 2 Month 3 Month 4 Month 5 Month 6 Month 7 Month 8 Month 9 Month 10
Ensure sustain
Continuous improvement
In scope of fix price offer Out of scope of fix price offer A = Accountable, R = Responsible, C = Consulted
Achieve stagesustain and continuous improvement
Insight Design Execute Achieve
-
8/11/2019 IDEA Method Overview Slides_REVIEWED_PF
53/87
Page 53 August 20, 2014IDEA Method Overview Slides_REVIEWED.ppt
Workstream Client IT Client bus. LodestoneDeliverables
Main deliverables
Available and efficient SAP systems COE
Efficient service processes COE
Satisfied end-users COE
Business value generating SAP solution PRM
Archived solution data PRM
In scope of fix price offer Out of scope of fix price offer A = Accountable, R = Responsible, C = Consulted
Ensure sustain
c e e stage susta a d co t uous p o e e t
Month 1
Year
Month 2 Month 3 Month 4 Month 5 Month 6 Month 7 Month 8 Month 9 Month 10
Ensure sustain
Continuous improvement
Achieve stagesustain and continuous improvement
Insight Design Execute Achieve
-
8/11/2019 IDEA Method Overview Slides_REVIEWED_PF
54/87
Page 54 August 20, 2014IDEA Method Overview Slides_REVIEWED.ppt
Continuous improvement
g p
Month 1
Year
Month 2 Month 3 Month 4 Month 5 Month 6 Month 7 Month 8 Month 9 Month 10
Ensure sustain
Continuous improvement
Identify, scope, and implement improvement projects (on top of allensure sustain activities)
Optimized SAP system Continuous improvement of business value
Main activities Main deliverables
Secure continuous improvement of business value
Achieve stagesustain and continuous improvement
Insight Design Execute Achieve
-
8/11/2019 IDEA Method Overview Slides_REVIEWED_PF
55/87
Page 55 August 20, 2014IDEA Method Overview Slides_REVIEWED.ppt
Continuous improvement
g p
Month 1
Year
Month 2 Month 3 Month 4 Month 5 Month 6 Month 7 Month 8 Month 9 Month 10
Ensure sustain
Continuous improvement
Workstream Client IT Client bus. LodestoneActivities
Identify, scope, and implement improvement projects (on top ofall ensure sustain activities)
PRM
Main activities
In scope of fix price offer Out of scope of fix price offer A = Accountable, R = Responsible, C = Consulted
Workstream Client IT Client bus. LodestoneDeliverables
Main deliverables
Optimized SAP system BPM
Continuous improvement of business value PRM
Short version of stage overview
-
8/11/2019 IDEA Method Overview Slides_REVIEWED_PF
56/87
Page 56 August 20, 2014IDEA Method Overview Slides_REVIEWED.ppt
g
Would be good for an overview of the IDEA stages
An overview of the 4 stages and the phases
A high level listing of activities; deliverables and timelines by stages
IDEA: Stage implementation approach
-
8/11/2019 IDEA Method Overview Slides_REVIEWED_PF
57/87
Page 57 August 20, 2014IDEA Method Overview Slides_REVIEWED.ppt
Insight AchieveDesign Execute
Insight preparationGlobal
preparation
Local
preparationEnsure sustain
Global business
bueprint
Global realization
Ongoing support,
rollout and
maintenance
Local cutover
Local business
blueprint
Local realization
Local cutover
preparation
Strategy
bueprint
Program
definition
Continuous
improvement
IDEA: Stage implementation approach
-
8/11/2019 IDEA Method Overview Slides_REVIEWED_PF
58/87
Page 58 August 20, 2014IDEA Method Overview Slides_REVIEWED.ppt
Understand the current
strategic business
objectives and as-is way
of working
Define/develop the
strategic business
objectives, scope,
and structure Document the strategic
vision and case
for change
Define and document
the solution scope
Define the
implementation strategy,
overall program plan
and schedule
Build and test template
system (configurationand RICEF
development)
Handover solution to
centre of excellence
Rollout project plan
Perform DRAFT FIT/
GAP against template
Conduct "White Smoke
Workshop" to get
blueprint approval
Conduct testing
Prepare cut over plan
Hand over to support
organization and
ongoing support
System monitoring,
management and tuning
Incident and problem
management
Service management
Identify, scope, and
implement improvement
projects (on top of allensure sustain activities)
Key stakeholders
Business owners
Sponsors
Program management
Business owners
Project team
Key users
Local business owners
Project team
Key users
Centre of excellence
Support team
6 months 10 months 10 months TBDDuration
(estimate)
Activities
Required
resources
Insight AchieveDesign Execute
Timelines
-
8/11/2019 IDEA Method Overview Slides_REVIEWED_PF
59/87
Page 59 August 20, 2014IDEA Method Overview Slides_REVIEWED.ppt
Please update according to the project!
MFJDNOSAJJMAMFJDNOSAJ
Year 1 Year 2
JMAMFJ
Year 3
Phases
Global realization
Local business blueprint
Global business blueprint
Local cut-over prep
Execute
Design
Global project prep
Local project prep
Achieve
Insight
Local realization
Ongoing support, rollout & maint
Local cut over
Stage: Insight
I D E A
-
8/11/2019 IDEA Method Overview Slides_REVIEWED_PF
60/87
Page 60 August 20, 2014IDEA Method Overview Slides_REVIEWED.ppt
Activities
Initiate and plan the Insight stage Set up Insight stage organization and infrastructure Review the initial risks Understand the current strategic business objectives
and as-is way of working Define/develop the strategic business objectives Identify target benefits Conduct synthesis workshop with senior management and
key stakeholders Document the strategic vision and case for change Developing high level KPIs for the organization at the appropriate
levels within in the process model Define the future setup of all related processes and organizations Definition of the scope and structure of projects, identifying the pilot
project and elaborating a implementation plan and sequence Define methods, techniques, tools, standards, and procedures that
will be applied throughout the life of the program Consolidate the figures and set up a business case and describes
the transformation concept
Deliverables
Insight stage project organization chart Overview and Insight stage plan High level risk assessment Insight phase plan and status management approach Insight phase kick off pack and workshop materials Updated budget Strategic business objectives Strategy blueprint SAP solution map Operations design Business initiatives Target business benefits for the business initiatives Enterprise IT strategy Implementation scope and strategy Program management strategy Data management strategy Organizational change management strategy Business case Transformation concept
Purpose Create a compelling and adaptive business framework for future business processes/scenarios aligned with all stakeholders
Stage: Design
I D E A
-
8/11/2019 IDEA Method Overview Slides_REVIEWED_PF
61/87
Page 61 August 20, 2014IDEA Method Overview Slides_REVIEWED.ppt
Initiate and start planning of the template project Define and document the solution scope Define the implementation strategy, overall program plan and schedule Define and document the program and project standards, guiding
procedures and governance process Define template scope Prepare and conduct business requirements workshops Prepare and conduct White Smoke Workshop 1.
Create blueprint documentation Build template system (configuration and RICEF development) Perform data cleansing Prepare and conduct White Smoke Workshop 2 for approval of template
system configuration Perform functional risk assessment Promote template scope to quality system Plan, prepare and execute unit- and integration testing Plan cut over Set up of global security and authorization concept
Prepare and conduct White Smoke Workshop 3 for approval of testedtemplate environment
Production support Going live check: verification session Updated long term rollout plan Handover solution to centre of excellence
Activities Deliverables
High level program plan System and client concept End-user training strategy Organizational change management plan Data migration strategy Authorization strategy Development and configuration standards Technical change management strategy Business blueprint Business scenario Business process flows Process Master List (PML) Functional specifications (RICEF List) Data conversion object list System configuration documentation Test strategy and plan Authorization matrix Data Migration plan
Cut over plan Unit-/integration test overview list Quality review/report (incl. Action plan) Going live check: Verification session report Program closure document
Purpose
Design and build of harmonized processes supported by common data standards, and realization of a system global template
Stage: Execute
I D E A
-
8/11/2019 IDEA Method Overview Slides_REVIEWED_PF
62/87
Page 62 August 20, 2014IDEA Method Overview Slides_REVIEWED.ppt
Activities
Update rollout project plan Detail blueprint WBS Write local business case Perform DRAFT FIT/GAP against template Perform user requirement workshop to identify local GAPs Planning for implementation of GAPs (local add ons and
template extensions) Align local data cleansing approach Align local data migration approach Identify and manage required organizational changes Define local end-user training strategy Conduct White Smoke Workshop to get blueprint approval Prepare testing for local scope and template extensions Execute unit- and integration testing Execute data collection and cleansing Prepare cut over plan Preparation of end user training material Create/update local SOPs
Promote local project scope to production environment Define and agree upon go-live criteria list Perform gono go decision Cut over support and bug fixing End-user support Hand over from local project team to local organization Hand over to support organization and ongoing support
Deliverables
Business blueprint WBS Project communication plan Project risk management plan Local kick-off meeting Documented FIT/GAP analysis Process Master List (PML) for project scope
Functional specifications for approved local specifics Local business scenarios Local process flows and requirements Local data migration object list Configuration logs and development specifications Detail design papers Test strategy and test plan Training plan and training documentation Unit and integration test executed and signed off Cutover strategy and plan defined User acceptance testing executed and signed off Go-live criteria fulfilled and approved
Approval for go-live Training need analysis updated after training execution Preparation of handover and handover sessions
Purpose
Implementation of harmonized processes by rolling out the template and managing organizational change
Stage: Achieve
I D E A
-
8/11/2019 IDEA Method Overview Slides_REVIEWED_PF
63/87
Page 63 August 20, 2014IDEA Method Overview Slides_REVIEWED.ppt
Activities
System monitoring, management, and tuning Incident and problem management Service management User authorizations and profiles management Change request and transport management Job scheduling
Support pack and upgrade management Data archiving Identify, scope, and implement improvement projects (on top of all
ensure sustain activities)
Deliverables
Available and efficient SAP systems Efficient service processes Satisfied end users Business value generating SAP solution Archived solution data Optimized SAP system
Continuous improvement of business value
Purpose
Stabilization of harmonized processes after the systems are live and the management of continuous improvement
Mini version focused on description
-
8/11/2019 IDEA Method Overview Slides_REVIEWED_PF
64/87
Page 64 August 20, 2014IDEA Method Overview Slides_REVIEWED.ppt
This is more focusing on an overview and explicitly explains difference between
pilot and rollouts
"Is that all there is?"
Insight stagestrategy blueprint and program definition
Insight Design Execute Achieve
-
8/11/2019 IDEA Method Overview Slides_REVIEWED_PF
65/87
Page 65 August 20, 2014IDEA Method Overview Slides_REVIEWED.ppt
Overview
Improvement
Insight stage contains a number of work packages setting the framework and directionfor the program
Strategic visionclarifies the overall direction the organization is heading to and aligns these
results among all senior management. The strategic vision is the basis for all follow-up activities
of the program, It describes the business objectives and collects ideas on business
opportunities to reach the business objectives
Macro designdelivers a process overview down to level 2 representing the future operating
setup. In addition, the processes are mapped to SAP solutions and a first cut of the future
system landscape is sketched
IT strategy and architecture: Future setup and governance of the new IT system landscapeand the transformation process towards the system landscape
Business case and transformation planconsolidates the figures elaborated in previous work
packages sets up a business case and describes the transformation concept, thus preparing
the necesSAAy qualitative and quantitative data for the program charter
Finally program charterbrings together all elements of the Insight phase and enables a formal
sign off and closure
Strategy blueprintand program
definition
Global template
Pilot
Rollout
Design stageglobal template
O i
Insight Design Execute Achieve
-
8/11/2019 IDEA Method Overview Slides_REVIEWED_PF
66/87
Page 66 August 20, 2014IDEA Method Overview Slides_REVIEWED.ppt
Overview
Creation of a global system and papertemplatethat covers the majority of business
processes, systems and data. The template system is created, including test scripts, training
material, high level pilot plan, focusing on global harmonizationof processes
A core teamof business and IT people from the client together with our consultants will design
the template and prototype it, business involvement is ensured by following the White Smoke
Workshopapproach
The template will cover global conceptsand standardized processesfor all business areas,
plus standardized datasettings and numbering conventions to support the clients business
The template design will be based on SAP standard functionalitywherever possible, any
enhancements or modification to SAP standard functionality have to be covered by a
business/benefit case and must be approved
All requirements for new processes or process changes are coordinated by the central
template team(template guardianship), consisting of business process owners and
IT model owners
Strong change controlwill be employed to manage and ensure the integrity of respectiveapplications and infrastructure, all changes have to be approved by the change control board
Only approved changerequests are implemented
Improvement
Strategy blueprintand program
definition
Global template
Pilot
Rollout
Execute stagepilot and rollout projects
O i ( il t)
Insight Design Execute Achieve
-
8/11/2019 IDEA Method Overview Slides_REVIEWED_PF
67/87
Page 67 August 20, 2014IDEA Method Overview Slides_REVIEWED.ppt
Overview (pilot)
A pilot sitehas been chosen that is representative for the business needs across all sites.
Focusing on one pilot site mitigates the risksthat endangers business continuity andis seen as the best learning tool for client staff to familiarize themselves with the technical
solution and global processes
The pilot implementation will cover The pilot will prove the designed solution, before parallel
rolloutsto other countries are initiated
The pilot will not only prove process designand system functionalitybut also the
rollout approach
During the template design and pilot implementation Lodestone experts will conduct
knowledge transferto client employees, allowing client to start building up an internal SAP
expert teamthat can execute later rollouts and replace external consultantsImprovement
Strategy blueprintand program
definition
Global template
Pilot
Rollout
Execute stagepilot and rollout projects
O i ( ll t )
Insight Design Execute Achieve
-
8/11/2019 IDEA Method Overview Slides_REVIEWED_PF
68/87
Page 68 August 20, 2014IDEA Method Overview Slides_REVIEWED.ppt
Overview (rollouts)
All rollouts follow the same project phases as the pilot implementation, with defined tasks,deliverables,and responsibilities
To ensure business continuitythe rollout team will also provide a post go-live support
to each country, while continuing with the next rollout
The external time and resourcesrequired for the rollouts decrease constantlysince
solutions developed in earlier implementations can be leveraged across various countries
Client will build up an internal organization to support all countriesthat are live on SAP;
the pilot implementation will be supported by the core team
Cross functions work streams such as scoping, rollout planning, security, and authorization,
testing, training, and data migration management will be covered centrallyacross all rollouts,
to ensure consistency across all rollouts and focused risk and issue management
Improvement
Strategy blueprintand program
definition
Global template
Pilot
Rollout
Achieve stagesustain and continuous improvement
Overview
Insight Design Execute Achieve
-
8/11/2019 IDEA Method Overview Slides_REVIEWED_PF
69/87
Page 69 August 20, 2014IDEA Method Overview Slides_REVIEWED.ppt
Overview
Lodestone will assist the client to setup and implement a powerful and sustainable
support organization
The built support organization is responsible for the daily support and takes over
the planned rollouts in new market organizationsafter program closure
Improvement
Strategy blueprintand program
definition
Global template
Pilot
Rollout
Alternative non-scientific soft version
-
8/11/2019 IDEA Method Overview Slides_REVIEWED_PF
70/87
Page 70 August 20, 2014IDEA Method Overview Slides_REVIEWED.ppt
Activities and deliverables represent a client exampleand haveto be adapted!
They are not always in line with the typical IDEA approach
Project timelines
Insight stage
Insight Design Execute Achieve
-
8/11/2019 IDEA Method Overview Slides_REVIEWED_PF
71/87
Page 71 August 20, 2014IDEA Method Overview Slides_REVIEWED.ppt
Insight stage
WeekWeekWeekWeekWeek
MonthMonthMonth
Year
Week WeekWeekWeekWeekWeekWeek
Insight
Design
Strategy blueprint
Process and organization review
Business case transform. conc., project charter
Program definition
Program preparation
Phases
IDEA Insight stage establishes the project team and the necesSAAy infrastructure and procedures required,
elaborates a compelling and adaptive business framework for future business processes/scenarios aligned withall stakeholders and details the strategies for implementation, program management, change management and
data management, the future IT setup. It combines all results and decisions in a business case, a transformation
concept and a program charter
Insight: Strategy blueprint
Detailed timelines strategy blueprint
-
8/11/2019 IDEA Method Overview Slides_REVIEWED_PF
72/87
Page 72 August 20, 2014IDEA Method Overview Slides_REVIEWED.ppt
Detailed timelines strategy blueprint
Month 1
Year
Month 2 Month 3 Month 4 Month 5 Month 6 Month 7 Month 8 Month 9 Month 10
Insight
Process/organizationreview and strategy vision
Program definition
Strategic blueprint
M
Strategy blueprint establishes a compelling and adaptive business framework for future business processes/scenarios. It describes the level 0 process model
and develop it further down to a level 2 process model representing the future operating setup and evaluating the benefits of changes
Business case trans-form. conc., project charter
M M M
Week
MonthMonth
Week WeekWeek Week
Business rules matrixDevelop business rules matrix
Opportunities/target benefitsDescribe opportunities/target benefits
Define SAP mapping/SAP solution map
Process modelProcess macro design
Gaps identified
Fit/Gap-Workshop process macro design
SAP mapping/SAP solution map
Fit/Gap-Workshop organization, and roles
Prototype Workshop
Define key performance indicators
Org. setup, roles and responsibility
Key performance indicators
Organization, roles and responsibilities
Deliverables
Prototype, deltas identified
Activities
Aligned strategy blueprint
Define service level agreements Service level agreements
Approval Workshop OCM/Training Strategy
Gaps identified
Insight: Program definition
Detailed timelines methodology and validation
-
8/11/2019 IDEA Method Overview Slides_REVIEWED_PF
73/87
Page 73 August 20, 2014IDEA Method Overview Slides_REVIEWED.ppt
Detailed timelines methodology and validation
CLIENT will use the Lodestone IDEA methodology and the validation approach incorporated in it. However, IDEA has to be tailored and sized to the CLIENT
requirements in order to deliver all necessary elements and at the same time chose an efficient approach. At the same time it has to be decided, if and how
the methodology already used in the ongoing projects can be integrated results will be aligned in two workshops
Month 1
Year
Month 2 Month 3 Month 4 Month 5 Month 6 Month 7 Month 8 Month 9 Month 10
Insight
Process/organizationreview and strategy vision
Program definition
Strategic blueprint
M
Business case trans-form. conc., project charter
M M M
Month
Week WeekWeek
Month
Week Week DeliverablesActivities
Approval Workshop OCM/Training Strategy
Aligned methodology/validationApproval WS meth./validation/document
Org. setup, roles and responsibility
Validation planCreate and approve validation plan
Review development/customizing stand.
Doc. catalogue/templates
Fit/Gap Workshop method./validation Identified gaps
Revized standards
Review method./validation approach Analyzed approach
Integrate IDEA into current approach Right sized project method.
Define document catalogue and templates
Insight: Program definition
Detailed program strategies
-
8/11/2019 IDEA Method Overview Slides_REVIEWED_PF
74/87
Page 74 August 20, 2014IDEA Method Overview Slides_REVIEWED.ppt
Program definition
Strategic blueprint
Detailed program strategies
Month 1
Year
Month 2 Month 3 Month 4 Month 5 Month 6 Month 7 Month 8 Month 9 Month 10
Insight
Process/organizationreview and strategy vision
M
The program strategies stream within program definition of the Insight phase sets the cornerstones for the overall implementation strategy by defining the
template scope, the sequence of country-rollouts and the pilot country, by setting up the organizational change vision and the data management strategy.
In addition, the overall program management strategy is set up
Business case trans-form. conc., project charter
M M M
WeekWeekWeekWeekWeek
MonthMonth
Program management toolsProgram management organization
Data management strategyApproved OCM/training strategyApproval Workshop OCM/training strategy
Training strategy
Organizational change visionOrganizational Change Mgmt. Strategy
Approved PM/implementationApproval Workshop PM/ implementation
Roadmap and rollout approachImplementation strategy
Approval Workshop data mgmt. strategy
Data management strategy
Org. setup, roles and responsibility
Approved data mgmt. strategy
Training strategy
DeliverablesActivities
Master data strategy development approach
Master data strategy is key for global solutions
-
8/11/2019 IDEA Method Overview Slides_REVIEWED_PF
75/87
Page 75 August 20, 2014IDEA Method Overview Slides_REVIEWED.ppt
Master data strategy is key for global solutions
Implementa-
tion approach
Target
benefits
Analysis Roadmap
Define strategic
benefits
Define
operational
benefits
Define cost
benefits
Define effort for
implementation
and change
Elaboration of
different
transition paths
with pros and
cons
Alignment with
overall
business and
IT roadmap
Change
management
concept
Strategic
framework
As Is
analysis
Understand as-
is process
structure and
behavior
Fix scope
Understand
and deepen
context
(business
strategy,
products,
processarchitecture,
organization)
Illustrate
system land-
scape with all
data sources
Identify As-Is
master data
situation
(design areas
along the
master data
strategy)
Identifyoptimization
potential (short
term, middle
term, long
term)
1 2
Design
Constitute rules
for structures
Define rules for
terminology
and syntax
Constitute
number range,
data fields etc.
Structures
& standards
Master data
processes with
roles for apply,
maintain and
close for
master data
Data quality
concept
Data ownership
Processes
& organization
Business
requirements
for system
support
Assessment of
different
system setups
MDM vs. ECC
Revise system
landscape
Decide about
leading systemper process
Systems
& technology
3 4 5 6 7
Constitute key design principles Potential changes, fit/gap to best practices
Master data strategy
The following approach will be applied for the master data objects materials, customers, vendors, and routing database
Insight: Program definition
Detailed IT strategy and architecture
-
8/11/2019 IDEA Method Overview Slides_REVIEWED_PF
76/87
Page 76 August 20, 2014IDEA Method Overview Slides_REVIEWED.ppt
Program definition
Strategic blueprint
Detailed IT strategy and architecture
Month 1
Year
Month 2 Month 3 Month 4 Month 5 Month 6 Month 7 Month 8 Month 9 Month 10
Insight
Process/organizationreview and strategy vision
M
IT strategy and architecture defines the funDMAentals of IT approach to the program and aligns it with the enterprise IT strategy.
It contains the design of the ERP architecture as well as the definition of the IT operational processes, the organizational structure of the support organization
and the technical change management processes and tools
Business Case Trans-form. conc.,project charter
M M M
WeekWeekWeek WeekWeek
Month Month
Activities
Org. setup, roles and responsibility
Approved IT org. and proc.
Technical CM processes/toolsDefine IT change management
Approval workshop IT org. and proc.
Define ERP architecture ERP Systems/clients/flows
Approval Workshop OCM/Training Strategy
Define IT operation IT Services/infrastr./organiz.
Deliverables
Define IT organization Support organization setup
Project timelines
Design stage
Insight Design Execute Achieve
-
8/11/2019 IDEA Method Overview Slides_REVIEWED_PF
77/87
Page 77 August 20, 2014IDEA Method Overview Slides_REVIEWED.ppt
g g
WeekWeekWeek
MonthMonthMonthMonth
YearYear
Week Week Week WeekWeekWeekWeekWeekWeekWeekWeekWeekWeek
Program preparation
M2
Label
M3
Phases
Solution build
Solution test
Global realization
Label
M1
Label
Global blueprint
Global blueprint signoff(White Smoke Workshop 1)
Global system configured(White Smoke Workshop 2)
Global system tested(White Smoke Workshop 3)
Design (template)
Design stageglobal template
"White Smoke" Workshop 1
Insight Design Execute Achieve
-
8/11/2019 IDEA Method Overview Slides_REVIEWED_PF
78/87
Page 78 August 20, 2014IDEA Method Overview Slides_REVIEWED.ppt
Business process design slides/flows
Abstracts of reengineering opportunities
Proposal for org structure
Gap list from blueprint phase
Pre-reading for participants
Agreed organizational structures
Agreed business processes and concepts
Decisions for closing identified gaps
Selections of business processes/solutions to be shown at WS2
Deliverables
p
Month
Year
Month Month Month
Global blueprintProgr.prep. WS 1
Global realization
Design (template)
Solution build Solution test
M
M M
Agree on blueprint deliverables (scope and solutions) as starting point
for the realization phase
Sign off/approval of key deliverables
Formally close blueprint phase
Objectives
Perform and finalize business process modeling and prepare slides todemonstrate the business processes with key business activities
Prepare abstracts on reengineering opportunities (slides) representing
key statements/decisions
Elaborate org structure based on business processes collected and
proposals for mandatory/best practice solutions
Prepare list of open decisions to be made for closing identified gaps and
work out options and proposals
Preparation
Present proposal for organizational structure set upPresent key content of reengineering opportunities
Present options and proposals for closing gaps and for degree of
standardization (mandatory/best practice)
Present business processes on slides containing key activities incl. brief
description and responsibilities. Discuss planned/defined harmonization
per key activity
Define business processes and/or functionalities to be shown at WS2
Execution
Design stageglobal template
"White Smoke" Workshop 2
Insight Design Execute Achieve
-
8/11/2019 IDEA Method Overview Slides_REVIEWED_PF
79/87
Page 79 August 20, 2014IDEA Method Overview Slides_REVIEWED.ppt
Detailed slides with further explanations of SAP functionalities
shown in SAP
Slides with description of new/pending decisions to be made incl.
proposals of team
Pre-reading for participants
Share touch and feel of SAP solutions worked out
Agree on proposals made for remaining decisions
Agree on rough cut prototype (RCP) solutions and sign off prototype
Identify and agree on remaining tasks for closing realization phase
Define solutions to be shown at last WS3
Deliverables
p
Month
Year
Month Month Month
WS 1Global realization
Design (template)
Solution build Solution test
M
M M
Show configured solutions in SAP
Match expectations/business understanding with solutions presented
with or without SAP
Collect areas for adjustments of current solutions
Objectives
Configure and set up SAP to be able to show selected businessscenarios, processes and solutions
Prepare synopsis and detailed slides for SAP demos
Prepare slides for solutions worked out which will not be shown in SAP
(e.g., interfaces/solutions based on functional specifications)
Work out proposals for new/pending decisions
Preparation
Present solutions in SAP (processes and functionalities). Use 2 beamers tohave slides for illustration and SAP screen in parallel
Present solutions not shown in SAP
Present proposals for new/pending decisions and agree on proposal or define
mitigating actions
Execution
Global blueprintProgr.prep.
Design stageglobal template
"White Smoke" Workshop 3
Insight Design Execute Achieve
-
8/11/2019 IDEA Method Overview Slides_REVIEWED_PF
80/87
Page 80 August 20, 2014IDEA Method Overview Slides_REVIEWED.ppt
Detailed slides with further explanations of SAP functionalities
shown in SAP
Slides with solutions worked out since WS2
Pre-reading for participants
Agree on core deliverables and sign off global realization phase
Deliverables
Month
Year
Month Month Month
Global blueprintProgr.prep. WS 1
Global realization