idm21 construction project maanagement technics
TRANSCRIPT
-
8/10/2019 Idm21 Construction Project Maanagement Technics
1/26
ASSIGNMENT
COURSE TITLE:CONSTRUCTION PROJECT MANAGEMENT TECHNICS
COURSE NO. : IDM 21
MODULE: 52
ASSIGNMENT NO: FIVE
ASSIGNMENT NAME: Project management techniques forinternationalri!et "ta#i$% on"tr$tion
COURSE:PGPIDM &Po"t Gra#$ate Pro'ra%%e in In(ra"tr$t$reDe)elo*%ent Mana'e%ent+
NAME:,IS-A .ESHAN PANDA
REG/NO: 2110 102033340215
DATE:110110212
NICMAR
NATIONAL INSTITUTE OF CONSTRUCTIONMANAGEMENT AND RESEARCH
PUNE
INDE6
0
-
8/10/2019 Idm21 Construction Project Maanagement Technics
2/26
1/ INTRODUCTION
2/ PROJECT MANAGEMENT TECHNICS
/ PROJECT IDENTIFICATION
5/ PROJECT DEVELOPMENT PROCEDURE
4/ PROJECT PLANNING AND COORDINATION
7/ PROJECT -OR. ,REAC.DO-N
8/ CPM NET-OR. ANAL9SIS
/ NET-OR. ELEMENTS ; MILESTONE
3/ RECOMANDATION AND CONCLUSION
1/ ,I,LOGRAPH9
INTROUDUCTION:0
1
-
8/10/2019 Idm21 Construction Project Maanagement Technics
3/26
A new international cricket facility is to be constructed outside a mega city
over a piece of land. Facility to include:
i. Capacity of spectator: 80,000
ii. ay ! "ig#t play facility.
iii. $% camera platform in si& directions.
iv. 'afety of players from spectators.
v. (avilion for %)(s to sit *00.
vi. (arking +adeuate space for all above-
$ime available is 1 mont#s including monsoon. Cost of construction need to
be recovered in / years. Average cost of ticket is s.100!. Appro&imate 2 matc#es
per year.
)n t#is assignment ) #ave done detailed study of t#is pro3ect regarding pro3ect
identification, needs, cost of pro3ect, development stages, development process,
pro3ect planning 4 controlling tact5s, pro3ect work breakdown met#odology,
duration of pro3ect completion etc. we see t#e pro3ect report of total work in t#is
assignment
6
-
8/10/2019 Idm21 Construction Project Maanagement Technics
4/26
-
8/10/2019 Idm21 Construction Project Maanagement Technics
5/26
Players living lodge " changing room
Parking security buildings
#ain entrance gates
$ompound walls
%atchman&s cabins
#edia room " message room
'core board " instruction board
(dvertisement sources
COST OF PROJECT: 0
For completion of our prestigious pro3ect work we #ave to give ma3or
attention towards t#e total cost of pro3ect.
-
8/10/2019 Idm21 Construction Project Maanagement Technics
6/26
Collection amount of one matc# > 80,000 & 100! s
> 80, 00,000! s
Collection amount of 1 year > 80, 00,000 & 2
> *, 60, 00,000! s
Collection amount of / years > *, 60, 00,000 & /
> 1, 00, 00,000! s
$otal collection amount in / yrs. > 1, 00, 00,000! s
$#erefore
Project cost of construction * +,- 00- 00-000". /s
PROJECT DEFINATION: 0
(une cricket stadium pro3ect is to be started in t#e first week of ?un 600@
and will be completed by t#e end of t#e first week of ?an 6008 suc# t#at after 1
mont# ground will be ready for arranging matc# to be played. $#e pro3ect is to
cost an estimated cost of 1, 00,00,000 s. and most of t#e funds necessary for
t#e stadium will be repaid of from t#e revenue generated from t#e stadium. $#e
stadium is designed for international day and nig#t matc#es to be conducted to
take place as well for $% camera s#ooting #ence t#e lig#ting levels are en#anced
to 1800 lu&. $#ere will be four ma3or entry points for stadium. All t#e facilities
/
-
8/10/2019 Idm21 Construction Project Maanagement Technics
7/26
vi;. c#anging rooms, massage room, food court, etc are at t#e ground level wit#in
t#e pavilion. 'eparate four buildings are proposed for tackling t#e ve#icles traffic
problems and stadium security problem.
PROJECT DEVELOPMENT PROCESS: 0
PROJECT MANGEMENT ORGANI
-
8/10/2019 Idm21 Construction Project Maanagement Technics
8/26
@
? 4 '.
99CB$) :(
-
8/10/2019 Idm21 Construction Project Maanagement Technics
9/26
-
8/10/2019 Idm21 Construction Project Maanagement Technics
10/26
(roper mobili;ation
esources finali;ation
'killed staff and workforce
aterial 4 vendor of good uality
'ubcontractor preualification
Gork e&ecution met#od
ec#ani;ation in work
Bse of euipment ! mac#inery
otivation 4 bonus sc#emes for worker
Finis#ed product acceptance criteria
After doing all t#e preplanning due to some une&pected reasons like
natural climactic planning get elongated in t#is condition day to day planning is
very important.
ay to day planning and t#eir daily review is very important for successful
completion of pro3ect. ue to daily review we understand t#e problem facing by
our team and we can solve t#em wit#out any risk.
CONTROLLING =
Controlling is t#e way of c#ecking is t#e progressing work is as per t#e
planning sc#edule, desired specification, reuired uality or not. )f any finis#ed
facility fails in ac#ieving norms it easily get catc#ed in controlling stage.
I
-
8/10/2019 Idm21 Construction Project Maanagement Technics
11/26
(lanning and controlling are closely interrelated. (lanning and controlling
may be viewed as t#e blades of a pair of scissor: t#e scissor cannot work unless
t#ere are two blades. Git#out ob3ectives and plans, control is not possible
because performance #as to be measured against some establis#ed criteria. )f
controls are to work, t#ey must be specially tailored to plans and position, to
individual managers, and to t#e needs for efficiency and effectiveness of pro3ect.
-
8/10/2019 Idm21 Construction Project Maanagement Technics
12/26
PROJECT -OR. ,REA.DO-N: 0
Gork reak down 'tructure +G'- means break down t#e given pro3ect into
its components and component operations or activities. )t is t#e manager5s task to
plan: t#at is, to decide on strategies and tactics, to break down t#e work to be done
into tasks and subtasks, and to assign t#e responsibility for completing t#ese tasks
to individuals or organi;ations. Gork reak own 'tructure #elp to define actual
work to be carried t#e responsibility wit# it and also time reuired to complete t#e
element of t#e pro3ect. As a board guideline t#e items of sc#edule of work can be
considered as t#e operations to tasks. owever it is possible to eit#er of:
a. Combine a few items to constitute one operation for t#e network.
b. 'ingle item of sc#edule can be split up into various operations.
Any pro3ect can be break down in activities by above two points, so as to easy
to delegate t#e work and #ave better control on pro3ect. $#is pro3ect can also be
break down in number of sub activities wit# #elp of G' met#od, so as to complete
it in wellstipulated time wit# minimum cost. $#is pro3ect can be break down into
sub activities by Gork reak own 'tructure +G'- met#od as follows:
-OR. ,REA.DO-N FOR STADIUM CONSTRUCTION PROJECT =
1+ MO,ILISATION ; GROUND PREPARION
11
-
8/10/2019 Idm21 Construction Project Maanagement Technics
13/26
o Carrying out survey for knowing t#e elevation of ground.
o arking t#e lineout of t#e stadium and playground.
o Eeveling t#e ground as per reuired or specified in drawing.
o (reparation of temp structure like site office, labs, stores.
o (reparation of (.C.C.
2+ R/C/C -OR. ; STRUCTURAL -OR.0 it inl$#e" RCC/ -or! (or
"ta#i$% >l#'"? *ar!in' >l#'"? "er)ie >l#'"? %ain 'ate"?
o%*o$n# @all" et/
A+ Sta#i$% >$il#in' = "te**in' "la>
o (reparation of (.C.C.
o Casting of footing
o Casting of column
o Casting of stepping slab
o Casting of entrance gate ! staircase
o Fi&ing of structural roof
,+ Ser)ie" >$il#in' = *a)ilion? lo#'in' >l#'?
o (reparation of (.C.C.
o Casting of footing
o Casting of column
16
-
8/10/2019 Idm21 Construction Project Maanagement Technics
14/26
o Casting of 1st slab
o Casting of staircase
o Casting of coln above 1stslab, casting of 6ndslabup to roof slab
+ ,RIC.-OR. ; CEMENTPLASTER -OR. =
o rickwork of stadium area
o rickwork of services building 1stfloor, 6ndfloor up to roof floor
o rickwork of compound wall
o rickwork of main gate, entrance lobby
o Cement plaster same as per brickwork activity
5+ FINISHING ; INTERIOR DESINGINING -OR.0
o Gypsum plaster work
o Tiling work, granite, marble fixing work
o Dado tiling work
o False ceiling work
o Painting work
o Carpentry work door fixing window fixing
o Gla!ing work
1*
-
8/10/2019 Idm21 Construction Project Maanagement Technics
15/26
o C"air fixing work in stadium area
o Toilets, pa#ilion area, main entrance lobby main gate special
finis"ing work as per re$uirement.
o Fixing of escalator
4+ SERVICES -OR. =
A+ Eletrial @or!
o %lectrification work for ser#ice building
o %lectrification work for pa#ilion building
o %lectrification work for stadium building
o %lectrification work for groundfor day nig#t playing facility
o electrical supply for advertisement board ,cc tv camera
o 9lectrical work for main lobby, entrance gates parking buildings,
compound wall.
,+ -ater "$**l @or!
o stadium building 4 ground water supply
o stadium development buildings water supply
+ Draina'e ""te% @or!
12
-
8/10/2019 Idm21 Construction Project Maanagement Technics
16/26
o stadium building 4 ground drainage 4 storm lines
o stadium development buildings drainage 4 storm lines
#+ T6 $amera- media- advertising- display screens work
0
o provision 4 arrangement of $% camera in si& direction of stadium
o display screens, score boards, advertising boards fi&ing work
7+ DEVELOPMENT -OR.0
o &oad construction
o Planter construction
o 'atc"man cabin construction
o Compound wall construction
o (ll de#elopment finis"ing work
8+ GROUND PREPARATON -OR.0
o )e#eling of ground
o &emo#ing loose soil and wastage material up to re$uired dept"
* brickbat filling
o Filing of special soil up to specified dept"
o 'atering * compaction of soil
o Plantination of grass
1/
-
8/10/2019 Idm21 Construction Project Maanagement Technics
17/26
o Playing pitc" making
+ DEMO,ILISATION OF TEMP/ STRUCTURE ; HANDOVERING -OR. =
o emobili;ation of temp. 'tructure like site office, construction labs,
store rooms, mi&ing plants, labor camp.
o andover of all finis#ed facility to client.
CPM NET-OR. ANAL9SIS: 0
)n Critical (at# et#od, t#e durations of various activities could be assumed
to a reasonable degree of certainty. 9ssentially Critical (at# et#od is adopted for
planning t#e pro3ects consisting of activities w#ose durations can be reasonably
assumed, based on past e&perience of similar works. C( is sop#isticated and
simple but reuires special training and mitigation for understanding of t#e user. )t
provides over all view of t#e pro3ect, especially wit# respect to completion of pro3ect
and it can be arranged according to work sections or responsibilities, wit# time
s#own as on scale for location of work on it at any particular p#ase of pro3ect. $o
save time in #eavy calculation part we can use Computer application for it. C(
network are firm time estimates, are made and it is because enoug# e&perience and
enoug# information is available in pro3ects of t#is sort to make firm time estimates.
1
-
8/10/2019 Idm21 Construction Project Maanagement Technics
18/26
NET-OR. ELEMENTS: 0
1+ Ati)it: 0
Activity is an element of t#e work or an individual item of a 3ob.
Activity consumes time but it may or may not consumer resources. )ts tail
"A9
-
8/10/2019 Idm21 Construction Project Maanagement Technics
19/26
"etwork is t#e grap#ical representation of a pro3ect drawn wit# t#e
#elp of activity arrows and event circles. $#e grap#ical representation
s#ows t#e seuence of activities.
5+ F$n#a%ental *ro*ertie" o( ati)itie" an# e)ent": 0
a. An event cannot be said to be completed or ac#ieved until all t#e
activities leading into it are completed.
b. "o activity can start until its tail event is completed.
G#ile arranging t#e activities, it is necessary to first enuire.
a. G#ic# activities must precedes t#e activity under consideration.
b. G#ic# activities can be concurrent wit# t#e activity under
consideration.
c. G#ic# activities can follow t#e activity under consideration.
4+ N$%>erin' e)ent": 0
%ertically downwards numbering met#od is adopted. $#is is also
known as t#e Kfoot rule met#od. ead events always #ave #ig#er number
t#an t#e tail events.
7+ D$%% ati)it: 0
$#ese activity indicate t#e interrelations#ip between two activities
to w#ic# are not directly preceding or succeeding activities to eac# ot#er
but indicate t#at one activity cannot be undertaken unless t#e earlier
activity is completed.
18
-
8/10/2019 Idm21 Construction Project Maanagement Technics
20/26
8+ Error" in lo'i: 0 $#ere are two types of errors in logic, vi;. looping and
dangling, w#ic# are e&plain briefly below:
a. Eooping errors: +closed circuits-
$#is can be avoided by carefully c#ecking t#e logical
interrelations. As far as possible, arrows +even dummies- s#ould not
be drawn backwards.
b. angling errors:
"ormally a pro3ect network s#ould #ave only one starting
event and only one end event. $#oug# t#is is not a rigid reuirement,
it is desirable to follow t#is convention. $wo rules if followed will
avoid dangling. +i- All events e&cept first and last must #ave atleast
one activity entering and one activity leaving t#em. +ii- All activities
must start and finis# wit# an event.
ANAL9SIS PROCEDURE: 0
CALCULATING EVENT TIME: 0
arly vent Time@ .
9arly event time is t#e earliest possible time at w#ic# t#e event can
be reac#ed or ac#ieved. $#e event is said to be complete or reac#ed or
ac#ieved only w#en all t#e activities leading into it are complete. G#en
more t#an one activity is merging in an event, t#e value of t#e activity
taking largest duration is adopted. $#e $9 of initial event is ;ero. $#e $9
1I
-
8/10/2019 Idm21 Construction Project Maanagement Technics
21/26
of t#e final event gives t#e minimum time reuired to complete t#e pro3ect.
$#e is known as minimum pro3ect duration.
!orward Pass@ .
$#e process of finding $9s of all events beginning wit# t#e initial or
start event of t#e pro3ect and ending wit# t#e final or end event of t#e
pro3ect is known as forward pass.
Eatest Allowable $ime:
Eatest allowable event time is t#e latest time at w#ic# t#e event must
be completed wit#out delaying t#e pro3ect. For t#e end event of t#e pro3ect,
t#e value of $9 is taken as t#e value of $E.
ackward (ass:
$o find t#e $E values of all t#e events starting from t#e end event and
ending in t#e start event, we adopt t#e process known as backward pass. )n t#is
process we start from t#e end event and start deducing t#e duration of eac#
activity from t#e $E of its #ead event and putting its values as $E of t#e tail
event. )n t#e case of a burst event, least value is adopted. $#e $E value of t#e
start event will always be eual to $9 value of t#at event i.e. ;ero.
Critical 9vent:
All t#e events #aving identical values for $9 and $E are known as critical
events.
$ritical (ctivity@ .
60
-
8/10/2019 Idm21 Construction Project Maanagement Technics
22/26
Critical activities are t#ose, w#ic# fulfill t#e following conditions:
i. 'uc# activity must lie between t#e two critical events.
ii. $#e difference between t#e event times s#ould be eual to t#e
duration of t#e activity.
iii. $otal float in t#e activity is ;ero.
$ritical Path@ .
Critical pat# is t#e continuous c#ain of critical activities starting from t#e
start event and passing t#roug# t#e network reac#ing to end event of t#e pro3ect.
$#ese are t#e c#ain of t#e activities t#at takes longest duration and #ence are
known as longest c#ain of t#e activities in t#e pro3ect. )n ot#er words t#e total
durations of all t#e critical activities in a continuous c#ain give us t#e total
pro3ect duration. )t is t#e longest pat# in t#e network.
)n a network, t#ere must be atleast one critical pat# starting from start
event to end event. $#ere may be more t#an one in a single network. 'ome time a
critical c#ain diverges into two or more critical c#ains, w#ic# may again
converge into one critical c#ain.
$1#P9T(T714 1! ($T767T> T7#'@ .
9arly 'tart $ime: +9'$-
9arly start time is t#e earliest possible time at w#ic# t#e activity can be
started. )t will be evident t#at t#is must be eual to $9 of t#e start event i.e.
$9+i-. "ow, we can write t#is as
61
-
8/10/2019 Idm21 Construction Project Maanagement Technics
23/26
9'$+i3- > $9+i-
9arly Finis# $ime: +9F$-
9arly finis# time is t#e earliest possible time at w#ic# t#e activity could
be finis#ed. )t will be obvious t#at t#is must be eual to early start plus t#e
duration reuired for t#e completion of t#at activity. "ow, we can write t#is as
EF$+i3- > 9'$+i3- L uration +i3-
Eatest Allowable 'tart $ime: +E'$-
Eatest allowable start time is t#e latest time at w#ic# t#e activity must be
started, so t#at t#e pro3ect will not be delayed. $#is can be arrived at, by
deducting activity duration from t#e latest finis# time of t#e activity. Ge can
write t#is as
E'$+i3- > EF$+i3- = uration +i3-
Eatest allowable finis# time is t#e latest time at w#ic# t#e activity must be
finis# time for an event. "aturally EF$ of t#e activity will be $E of t#e end event
of t#at activity. Ge can write t#is as
EF$+i3- > $E+3-
E'$+i3- L uration +i3-
66
-
8/10/2019 Idm21 Construction Project Maanagement Technics
24/26
!loat (nd 'lack@ . An event t#at is not critical is said to #ave slack. 'lack is t#e
calculated time span wit#in w#ic# t#e event must occur. $#e term MslackM is used
only in referring to events.
-
8/10/2019 Idm21 Construction Project Maanagement Technics
25/26
)ndependent Float > earliest end = latest start duration
RECOMMENDATIONS: 0
)n t#is type of pro3ect w#ere fi&ed target of completion is t#ere pro3ect
management is plays vital role. )n t#is type of pro3ect we #ave to give special
attention towards all t#e p#ases of management like planning, directing, co
coordinating 4 controlling. Ge #ave to arrange special team or any consultant s#ip
for ac#ieving batter result or ac#ieving target.
Eooking towards our pro3ect is a construction of international cricket stadium
facility w#ic# #ave target of completion 1 mont#s w#ic# includes rainy season,
#olidays and festivals. ue to any problems like design problem of structure,
natural climates, s#ortage in markets, labor s#ortage, labor strike, festivals or any
ot#er problem t#e completion target get delays t#en t#is creates a big problem of
prestigious, pride of organi;ation. )n t#is condition we #ave to give muc# more
attention towards all p#ases of management.
"ow a day t#ere are too many organi;ation working in construction industry
w#ic# #ave a lot of personnel staff of #ig# ualification, well e&perience and e&pert
from specific work. $#ey are working as a pro3ect management consultant +(C-
we are make preplanning of pro3ect, t#ere s#ows well direction to e&ecute t#e workH
t#ey control t#e work and continuously try for batter result. $#ey plan work on day
62
-
8/10/2019 Idm21 Construction Project Maanagement Technics
26/26
to day basis, t#ey make alternative solution for market s#ortages, t#ey always try for
mec#ani;ation, and t#ey take responsibility to complete t#e pro3ect in given target.
For t#is pro3ect ) will recommend to make arrangement of suc# (C organi;ation
,I,LIOGRAPH9: 0
1+ 74T/1;9$T714 T1 P/12$T #(4(#4T C
?y '? kulkarni 4?$haphalkar
2+ P/12$T #(4(#4T C
?y 4irali prakashan
+ $14'T/9$T714 P/12$T #(4(#4T T$:47$' C
?y teDtbook of 47$#(/ '1;