idnr engineering

14
Heath Delzell – Engineering Bureau IDNR Engineering Progress to Date and Timeline for Project Completi Design and Construction Obstacles

Upload: leona

Post on 17-Jan-2016

27 views

Category:

Documents


0 download

DESCRIPTION

IDNR Engineering. Heath Delzell – Engineering Bureau. Progress to Date and Timeline for Project Completion Design and Construction Obstacles. Construction Activities. Phase 1 – Dam and Spillway Renovation Phase 2 - In-Lake Construction Sediment Retention Basins Sediment Removal - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: IDNR Engineering

Heath Delzell – Engineering Bureau

IDNR Engineering

Progress to Date and Timeline for Project CompletionDesign and Construction Obstacles

Page 2: IDNR Engineering

Construction ActivitiesPhase 1 – Dam and

Spillway RenovationPhase 2 - In-Lake

ConstructionSediment Retention

Basins Sediment RemovalShoreline ArmoringUniversally Accessible

Fishing PierPhase 3 – Boat Ramp

and Parking Lot

Page 3: IDNR Engineering

Progress – Phase 1 History

1991 – Voids filled under spillway

2007 – Contracted French-Reneker Associates to determine cause

2008 – F-R concluded leak in weathered bedrock

Solution: Remove weathered bedrock

StatusF-R Design complete and

permitted for constructionFunding has been

securedCurrently out for bids –

Letting date October 21, 2010

Page 4: IDNR Engineering

Timeline – Phase 1Winter 2010

Early Start Date: December 1, 2010

Portion of dam to be removed

Tree ClearingConcrete Removal

Page 5: IDNR Engineering

Timeline – Phase 1Spring-Summer 2011

Excavate Core Trench

Construct Principal Spillway Outlet/Drawdown Pipe

Place Embankment Fill

Page 6: IDNR Engineering

Timeline – Phase 1Summer-Fall 2011

Place Embankment FillConstruct Principal

Spillway InletAuxiliary Spillway

GradingClose Drawdown Pipe

Winter 2011 – No Construction

Spring 2012Final GradingProject Complete: May

31, 2012

Page 7: IDNR Engineering

Progress – Phase 2Sediment Retention

BasinsUpper Arm Basin

Preliminary DesignDesigned as a

Sediment PondFilled with Dredge

Material1-2 feet deep

State Contract for completionFinish DesignApply For PermitWetland Mitigation Plan

Page 8: IDNR Engineering

Progress – Phase 2Sediment Retention

BasinsCampground Arm

Design Complete Increasing Dam

HeightSame function as

Upper Arm Basin

Page 9: IDNR Engineering

Progress – Phase 2Sediment Removal

Design CompleteRemoving sediment via

mechanical meansScrapers, Bulldozers,

Excavators, Etc.Shoreline Armoring

Design CompletePlacing Riprap in

normally inaccessible locations

Universally Accessible Fishing PierDesign 95% Complete

Page 10: IDNR Engineering

Timeline – Phase 2Winter 2010

Design and permit application complete January 1Wetland mitigation

Spring 2011Bid Letting: March 17,

2011Early Start Date: May 1,

2011Summer-Fall-Winter 2011

ConstructionSpring 2012

Final Grading and SeedingProject Completion: March

15, 2012

Page 11: IDNR Engineering

Progress – Phase 3Boat Ramp and

Parking LotDesign is 25%

completeSchedule dependant

on Phase 21-2 Months for

construction

Page 12: IDNR Engineering

Construction ObstaclesRAIN!!!

Dam construction would slowLarge storms can severely erode a partially

constructed damSediment removal would stop

Green Valley <10% complete

Page 13: IDNR Engineering

Construction ObstaclesPerspective:

Annual Precipitation for Brighton (inches)

1991 / 2008 1992 / 2009 1993 / 2010

44.0”

30.2”

55.3”

40.5”

54.3”

48.4”

Page 14: IDNR Engineering

ConclusionDam construction

begins in DecemberPhase 2 starts

Spring 2011Boat Ramp starts

Fall 2011 or Spring 2012

All phases should be complete and the lake nearly full by the end of May 2012