International ConferenceIEC 61850 – The Future of Substation Protection and Automation
March 29 and 30, 2005 FURNAS – Rio de Janeiro
1
IEC 61850
Implementation experiences worldwide
Fernando Cobelo – Z I V
International ConferenceIEC 61850 – The Future of Substation Protection and Automation
March 29 and 30, 2005 FURNAS – Rio de Janeiro
2
IEC 61850 Implementation experiences worldwide
� Early experiences
� Interoperability demos
� Pilot Projects
� Real installations
International ConferenceIEC 61850 – The Future of Substation Protection and Automation
March 29 and 30, 2005 FURNAS – Rio de Janeiro
3
• Early experiences 1996 – 2001
• EPRI projects in USA (UCA2 – GOMSFE model) “Utility Substation Initiative”• AEP 24 substations• TVA 2 substations
• German project Open Communication in Substations (OCIS)• VEW (now REW)
•Other UCA2 projects:• TERNA (Italy)• ELETROSUL (Brasil)• COPEL (Brasil)• ESCOM (South Africa) 3 substations• CFE (Mexico) 17 installations (substations & power plants)
IEC 61850 Implementation experiences worldwide
International ConferenceIEC 61850 – The Future of Substation Protection and Automation
March 29 and 30, 2005 FURNAS – Rio de Janeiro
4
IEC 61850 Implementation experiences worldwide
• Early experiences
• Research• Cooperation • Proof of concept
International ConferenceIEC 61850 – The Future of Substation Protection and Automation
March 29 and 30, 2005 FURNAS – Rio de Janeiro
5
• Interoperability demos 2000 - 2005• Vancouver May 2001• Dana Point January 2002• Ponte Vedra September 2002• Manheim March 2003• Sun Valley April 2003• Paris August 2004
• Organized by UCA International User’s Group • First experiences from vendors of IED’s and client applications
• “plug and play” interoperability• GOOSE interchange• debuging of the “data model”• feed-back to IEC TC57 wg’s 10 / 11 / 12
• Latest UCA2 GOMSFE / earlier IEC 61850 implementations• Increasing number of vendors participating
IEC 61850 Implementation experiences worldwide
International ConferenceIEC 61850 – The Future of Substation Protection and Automation
March 29 and 30, 2005 FURNAS – Rio de Janeiro
6
RFL
AlstomBitronics
GE PowerMtg.ABB US ZIV BaslerSiemensABB Power
SISCO
Tamarack
Black &Veetch KEMA Powertec QEI SEL GE Harris Omnicron
DemonstrationSwitchRuggedCom RFL
Electrotec
SonetRing
100Mbps100Mbps
AlstomP&C
Interoperability demos Dana Point January 2002
IEC 61850 Implementation experiences worldwide
International ConferenceIEC 61850 – The Future of Substation Protection and Automation
March 29 and 30, 2005 FURNAS – Rio de Janeiro
7
Interoperabilitydemos
International ConferenceIEC 61850 – The Future of Substation Protection and Automation
March 29 and 30, 2005 FURNAS – Rio de Janeiro
8
IEC 61850 Implementation experiences worldwide
Interoperability demosParis August 2004
International ConferenceIEC 61850 – The Future of Substation Protection and Automation
March 29 and 30, 2005 FURNAS – Rio de Janeiro
9
Paris August 2004
IEC 61850 Implementation experiences worldwide
International ConferenceIEC 61850 – The Future of Substation Protection and Automation
March 29 and 30, 2005 FURNAS – Rio de Janeiro
10
IEC 61850 Implementation experiences worldwide
� TenneT (Netherlands) � Beverwijk: NCIT from ABB with a IEC 61850-9-1 connection to a
energy meter from Landis+Gyr (in service)� EDF (France)
� Vieux Moulin: NCIT from Areva with a IEC 61850-9-1 connection to a energy meter from Landis+Gyr (in service)
� Saumade: NCIT from Areva with IEC 61850-9-2 connection to protection from Areva and Siemens (target date 12-2004)
� NGC (UK)� Osbaldwick: NCIT from Areva with IEC 61850-9-2 connection to
protection from Areva (target date 03-2005)
� Iberdrola (Spain)
� Project Interuca Interoperability for distributed control of substations (Gernika substation)
Utilities – pilot projects
International ConferenceIEC 61850 – The Future of Substation Protection and Automation
March 29 and 30, 2005 FURNAS – Rio de Janeiro
11IEC 61850 Implementation experiences worldwide
Pilot projects
International ConferenceIEC 61850 – The Future of Substation Protection and Automation
March 29 and 30, 2005 FURNAS – Rio de Janeiro
12IEC 61850 Implementation experiences worldwide
� Terna (Italy)
�Project SICAS; several substation ordered using IEC 61850 as station bus(at least 1 substation already operational)
� RWE Rheinbraun (Germany)
�New substation Garzweiler II
� NGC (UK)
�SICAP Project
� DEWA (Emirates)
�Several substations over 5 years
� IBERDROLA (Spain)
�Substation Ciudad Universitaria
� TVA (USA) Bradley substation
� PPL (USA) pilot substations
Utilities – projects under preparation
International ConferenceIEC 61850 – The Future of Substation Protection and Automation
March 29 and 30, 2005 FURNAS – Rio de Janeiro
13IEC 61850 Implementation experiences worldwide
Bay Units forGeneral Reports
IEC 60870-5-101
Station Bus Ethernet TCP/IP
Station Bus Ethernet TCP/IP -IEC61850
Switchgear - 110kV
SICAM PASServer/DIP Entire System
SICAM PAS CCStation Visualization
Control Centre
Switchgear - 25/6kV Switchgear - 6kV
IEC 60870-5-101
4 SICAMminiRTU
HV Feeder Main Switchgear MV MV Distribution
Operator StationOffice-PC
10km Connection to TransformerMonitoring
Station Bus Ethernet TCP/IP -IEC61850
Station Bus Ethernet TCP/IP -IEC61850
Garzweiler (Germany)
International ConferenceIEC 61850 – The Future of Substation Protection and Automation
March 29 and 30, 2005 FURNAS – Rio de Janeiro
14
�IB is active within IEC TC57
�ST Guernika Pilot Project 2004
� S.T. UNIVERSITY CITY Feb 2006
�IBC is an expert in 61850
� PROCOME protocol
� More than 200 SAS substation
� Deep knowlege about SAS implications
Iberdrola Group and 61850
Yesterday
Today
Tomorrow
� 61850 will be the only solution
� 3 more ST´s
� IB Migration Strategy
Substation Ciudad Universitaria
IEC 61850 Implementation experiences worldwide
International ConferenceIEC 61850 – The Future of Substation Protection and Automation
March 29 and 30, 2005 FURNAS – Rio de Janeiro
15IEC 61850 Implementation experiences worldwide
Substation Ciudad UniversitariaFebruary 2006 – IED´s from 7 Manufacturers
51
Bay Unit
87
51
Bay Unit
51
Bay Unit
87
51
Bay Unit
21
87L
Bay Unit
21
87L
Bay Unit
132kV GIS
International ConferenceIEC 61850 – The Future of Substation Protection and Automation
March 29 and 30, 2005 FURNAS – Rio de Janeiro
16
� ATEL (Switzerland)� 20 kV distribution substation Winznauschachen (Siemens)
� EGL (Switzerland)� Retrofit of 380 kV transmission substation Laufenburg
(System Integrator:ABB, integrating a Siemens protection (main 2) in the ABB system)
Utilities – realized projects
IEC 61850 Implementation experiences worldwide
International ConferenceIEC 61850 – The Future of Substation Protection and Automation
March 29 and 30, 2005 FURNAS – Rio de Janeiro
17
IEC 61850 Implementation experiences worldwide
WinznauschachenWinznauschachen(Switzerland)(Switzerland)
In opeIn operation sincetion since11/200411/200420KV Distribution 20KV Distribution Comprising Substation Comprising Substation Controller, Relays, Engineering Controller, Relays, Engineering according to part 6according to part 6
International ConferenceIEC 61850 – The Future of Substation Protection and Automation
March 29 and 30, 2005 FURNAS – Rio de Janeiro
18IEC 61850 Implementation experiences worldwide
� Red Eléctrica (Spain)� SIGRES Project: Substation automation equipment management
� AEP (USA)� Intend to use only IEC 61850 products in the future
� Texas AM University / Arizona State University / AEP / TVA (USA)� Investigate all digital protection system with instrument transformers
connected with IEC 61850-9-2 to protection relays� Includes field tests� Project planned for 2005 - 2007
� Stadtwerke St. Gallen (Switzerland)� Issued a tender asking for IEC 61850 as station bus
� The following utilities consider a project with IEC 61850 in the future� RWE Net AG (Germany)� TenneT (Netherlands)� NUON (Netherlands)� Hydro One (Canada)� Tenaga (Malaysia)
Utilities – further projects