ieee application guide
TRANSCRIPT
-
8/4/2019 IEEE Application Guide
1/102
Application Guide for Distributed
Generation Interconnection
The NRECA Guide to IEEE 1547
Resource Dynamics Corporation
September 2001
-
8/4/2019 IEEE Application Guide
2/102
Application Guide for Distributed Generation Interconnection
The NRECA Guide to IEEE 1547 September 2001
2
Introduction................................................................................................................................................... 1
Section 1: Cooperative Distribution System Circuits ................................................................................... 3
Section 2: Meeting IEEE 1547 Technical Requirements.............................................................................. 6
Voltage Regulation ....................................................................................................................................... 6P1547 Requirement (Section 4.1.1) .......................................................................................................... 6
Application Guidance ............................................................................................................................... 6
Background...........................................................................................................................................6
Impact of DR ........................................................................................................................................7
Tips, Techniques and Rules of Thumb ................................................................................................. 8
Integration with Area Electric Power System Grounding........................................................................... 10
P1547 Requirement (Section 4.1.2) ........................................................................................................ 10
Application Guidance ............................................................................................................................. 11
Background ......................................................................................................................................... 11
Impact of DR ......................................................................................................................................12
Tips, Techniques and Rules of Thumb ............................................................................................... 14
Synchronization .......................................................................................................................................... 16P1547 Requirement (Section 4.1.3) ........................................................................................................ 16
Application Guidance ............................................................................................................................. 16
Background ......................................................................................................................................... 16
Impact of DR ......................................................................................................................................16
Tips, Techniques and Rules of Thumb ............................................................................................... 18
Inadvertent Energizing of Area EPS........................................................................................................... 23
P1547 Requirement (Section 4.1.5) ........................................................................................................ 23
Application Guidance ............................................................................................................................. 23
Background ......................................................................................................................................... 23
Impact of DR ......................................................................................................................................23
Tips, Techniques and Rules of Thumb ............................................................................................... 24
Monitoring .................................................................................................................................................. 26P1547 Requirement (Section 4.1.6) ........................................................................................................ 26
Application Guidance ............................................................................................................................. 26
Background ......................................................................................................................................... 26
Impact of DR ......................................................................................................................................26
Tips, Techniques and Rules of Thumb ............................................................................................... 27
Isolation Device .......................................................................................................................................... 30
P1547 Requirement (Section 4.1.7) ........................................................................................................ 30
Application Guidance ............................................................................................................................. 30
Background ......................................................................................................................................... 30
Impact of DR ......................................................................................................................................31
Tips, Techniques and Rules of Thumb ............................................................................................... 31
Voltage Disturbances .................................................................................................................................. 33
P1547 Requirement (Section 4.2.1) ........................................................................................................ 33
Application Guidance ............................................................................................................................. 33
Background ......................................................................................................................................... 33
Impact of DR ......................................................................................................................................34
Tips, Techniques and Rules of Thumb ............................................................................................... 35
Frequency Disturbances.............................................................................................................................. 39
P1547 Requirement (Section 4.2.2) ........................................................................................................ 39
Application Guidance ............................................................................................................................. 39
-
8/4/2019 IEEE Application Guide
3/102
Application Guide for Distributed Generation Interconnection
The NRECA Guide to IEEE 1547 September 2001
3
Background ......................................................................................................................................... 39
Impact of DR ......................................................................................................................................39
Tips, Techniques and Rules of Thumb ............................................................................................... 40
Disconnection for Faults ............................................................................................................................. 42
P1547 Requirement................................................................................................................................. 42
Application Guidance ............................................................................................................................. 42Background ......................................................................................................................................... 42
Impact of DR ...................................................................................................................................... 43
Tips, Techniques and Rules of Thumb ............................................................................................... 43
Loss of Synchronism................................................................................................................................... 45
P1547 Requirement (Section 4.2.4) ........................................................................................................ 45
Application Guidance ............................................................................................................................. 45
Background ......................................................................................................................................... 45
Impact of DR ...................................................................................................................................... 45
Tips, Techniques and Rules of Thumb ............................................................................................... 45
Feeder Reclosing Coordination................................................................................................................... 47
P1547 Requirement (Section 4.2.5) ........................................................................................................ 47
Application Guidance ............................................................................................................................. 47Background ......................................................................................................................................... 47
Impact of DR ...................................................................................................................................... 47
Tips, Techniques and Rules of Thumb ............................................................................................... 49
Limitation of DC Injection.......................................................................................................................... 51
P1547 Requirement (Section 4.3.1) ........................................................................................................ 51
Application Guidance ............................................................................................................................. 51
Background ......................................................................................................................................... 51
Impact of DR ......................................................................................................................................51
Tips, Techniques and Rules of Thumb ............................................................................................... 52
Limitation of Voltage Flicker Induced by the DR ...................................................................................... 54
P1547 Requirement................................................................................................................................. 54
Application Guidance ............................................................................................................................. 54Background ......................................................................................................................................... 54Impact of DR ......................................................................................................................................56
Tips, Techniques and Rules of Thumb ............................................................................................... 57
Harmonics ................................................................................................................................................... 60
P1547 Requirement (Section 4.3.3) ........................................................................................................ 60
Application Guidance ............................................................................................................................. 60Background ......................................................................................................................................... 60
Impact of DR ...................................................................................................................................... 61
Tips, Techniques and Rules of Thumb ............................................................................................... 62
Immunity Protection ................................................................................................................................... 66
P1547 Requirement (Section 4.3.4) ........................................................................................................ 66
Application Guidance ............................................................................................................................. 66Background ......................................................................................................................................... 66
Impact of DR ...................................................................................................................................... 66
Tips, Techniques and Rules of Thumb ............................................................................................... 66
Surge Capability.......................................................................................................................................... 68
P1547 Requirement Section 4.3.5) ......................................................................................................... 68
Application Guidance ............................................................................................................................. 68
Background ......................................................................................................................................... 68
Impact of DR ...................................................................................................................................... 68
-
8/4/2019 IEEE Application Guide
4/102
Application Guide for Distributed Generation Interconnection
The NRECA Guide to IEEE 1547 September 2001
4
Tips, Techniques and Rules of Thumb ............................................................................................... 69
Islanding...................................................................................................................................................... 71
P1547 Requirement (Section 4.4) ........................................................................................................... 71
Application Guidance ............................................................................................................................. 71
Background ......................................................................................................................................... 71
Impact of DR ......................................................................................................................................71Tips, Techniques and Rules of Thumb ............................................................................................... 72
Appendix A................................................................................................................................................. 76
Glossary ...................................................................................................................................................... 76
Appendix B ................................................................................................................................................. 78
Discussion of Power Factor ........................................................................................................................ 78
Appendix C ................................................................................................................................................. 82
Grounding Fundamentals............................................................................................................................ 82
Appendix D - Example One Line Diagrams ............................................................................................... 90
Appendix E ................................................................................................................................................. 94
Example of Non-Islanding Test .................................................................................................................. 94
A.5 Interconnection Test to Verify Non-Islanding............................................................................94
A.5.1 Non-Islanding Test Procedure Background...........................................................................94A.5.2 Non-islanding Test Procedure................................................................................................ 95
Appendix F .................................................................................................................................................97
References................................................................................................................................................... 97
-
8/4/2019 IEEE Application Guide
5/102
Application Guide for Distributed Generation Interconnection
The NRECA Guide to IEEE 1547 September 2001
1
Application Guide for Distributed Generation InterconnectionThe NRECA Guide to IEEE 1547
Introduction
This application guide is intended to supplement, expand and clarify the technical requirements of
IEEE 1547 Standard for Interconnecting Distributed Resources with Electric Power Systems. While
the Standard includes distributed generation (DG) through 10 MVA, this guide addresses DG through 1MVA. Neither this guide nor the Standard covers revenue metering requirements. Tariff and contract
issues are also beyond the scope of this document. Because the Standard in not yet approved by the IEEE
Standards Board, Draft 07 has been used. It is assumed that the final version of the Standard will not
change significantly. When the final version of the Standard is published, changes will be made to this
guide to reflect actual wording of the Standard.
The subjects in part 2 of this guide closely parallel the Standard. For each topic the actual
Standard language is quoted followed by application guidance divided into three sections: 1) Background,
2) Impact of DR, and 3) Tips, Techniques and Rules of Thumb. A Discussion of Power Factor inAppendix B is not addressed in the Standard, but it an important topic to consider. Since grounding is
such an important topic and there are some non-standard grounding practices, Grounding Fundamentals
are discussed in Appendix C. This guide does not cover testing, but since the issue of islanding is so
important, Appendix E gives some examples of non-islanding tests.
While the Standard was designed to cover the bulk of DG installations, in some circumstances
additional technical specifications may be required. Especially in some remote areas, the addition of DG
may be a significant percentage of the circuit load. The Tips, Techniques and Rules of Thumb section
under each topic gives guidelines and thresholds where additional specifications may be required. In
addition, most installations over 1 MW will require a specific engineering study to determine any
additional requirements.
The National Rural Electric Cooperative Association wishes to give special thanks to N. Richard
Friedman of the Resource Dynamics Corporation for the compilation of this guide. Jay Morrison of the
NRECA Energy Policy Department contributed to this document. Appreciation is also noted to the
members of the NRECA T&D Engineering System Planning Subcommittee for their input, review and
suggestions.
The current members of the System Planning Subcommittee are:
Ronnie Frizzell, Arkansas Electric Cooperative Corp., AK (Chairman)
Brian Tomlinson, Coserv Electric, TX (Vice Chair)
Mark Evans, Volunteer Electric Co-op, TN (Recorder)
Robin W. Blanton, Piedmont EMC, NC Robert Dew, United Utility Supply, KY
David E. Garrison, Allgeier Martin & Associates, MO
H. Wayne Henson, East Mississippi EPA, MS
Bill Koch, Rural Electric Magazine, WA
Joe Perry, Patterson & Dewar Engineers, GA
Georg Schulz, RUS, DC
Mike Smith, Singing River EPA, MS
-
8/4/2019 IEEE Application Guide
6/102
Application Guide for Distributed Generation Interconnection
The NRECA Guide to IEEE 1547 September 2001
2
Chris Tuttle, RUS, DC
Kenneth Winder, Moon Lake Electric Assn., UT (Former Chairman)
This is a working document. Any comments or suggestions are welcome. Please address all
comments to:
Bob Saint, Principal, T&D Engineering
National Rural Electric Cooperative Association
4301 Wilson Blvd.
Arlington, VA 22203
Phone: (703) 907-5863
Email: [email protected]
mailto:[email protected]:[email protected] -
8/4/2019 IEEE Application Guide
7/102
Application Guide for Distributed Generation Interconnection
The NRECA Guide to IEEE 1547 September 2001
3
Section 1: Cooperative Distribution System Circuits
Nearly half of the distribution circuits in the United States are owned by cooperatives. As energy markets
are restructured, more pressure will be felt by cooperatives to control costs, increase operating flexibility,and maintain system and supply source reliability. Distributed generation (DG) offers new options for
cooperatives and their customers. Understanding how DG systems are designed, interconnected and
operated is key to understanding the impact of DG on cooperative distribution systems.
The Electric Power System
An electric power system generally consists of generation, transmission, subtransmission, and
distribution. Most electric power is generated by central station generating units. Generator step-up
transformers at the generation plant substation raise the voltage to high levels for moving the power on
transmission lines to bulk power transmission substations. The purpose of high voltage transmission lines
is to lower the current, reduce voltage drop and reduce the real power loss (l2R). Real power is the
product of voltage, current and the power factor (the angle between the voltage and the current phasors).As the voltage is increased for a fixed amount of power, the current decreases proportionately. The
power transmitted remains constant, but the decrease in current results in reduced losses.
Transmission lines are usually 138 kV and above. Transmission substations reduce the voltage to
subtransmission levels, usually between 44 kV and 138 kV. Subtransmission lines are those lines where
the voltage is stepped directly to the customer utilization voltage. Interconnections to other electric utility
transmission and subtransmission systems form the power grid.
The system voltage is stepped down beyond the transmission system to lower the cost of equipment
serving loads from the subtransmission and distribution segments of the power system.
The transmission and subtransmission systems are generally networked. In contrast, the distributionsystem consists of radial distribution circuits fed from single substation sources. The distribution system
includes distribution substations, the primary voltage circuits supplied by these substations, distribution
transformers, secondary circuits including services to customers premises and circuit protective, voltage
regulating and control devices.
The Distribution System
The distribution system typically consists of three phase, four wire Y grounded and single phase, two
wire grounded circuits. Distribution circuits have voltages ranging from 19.9/34.5 kV to 7.2/12.5 kV
(phase-to-ground voltage/phase-to-phase voltage), although there are some lower voltage 4 kV three
wire ungrounded systems still in existence. These lines are typically referred to as primary circuits
and their nominal voltage may be referred to as the primary voltage.
Transformers on the distribution system step the voltage from the distribution line voltage to the
customers utilization voltage commonly referred to as the secondary voltage. The secondary system
serves most customer loads at 120/240 volts, single phase, three wire; 208Y/120 volts three phase four
wire; or 480Y/277 volts three phase four wire. A complete list of preferred voltage levels is tabulated in
American National Standards Institute (ANSI) C84.1.
mailto:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected] -
8/4/2019 IEEE Application Guide
8/102
Application Guide for Distributed Generation Interconnection
The NRECA Guide to IEEE 1547 September 2001
4
Residential, small commercial, and rural loads are served by overhead distribution feeders and lateral
circuits, or by underground distribution circuits. Most residential loads are served by three phase, four
wire primary feeders with single phase lateral circuits, although some three phase laterals serve small
industrial and large commercial loads. Most rural loads are served with single phase primary and
typically have one customer per distribution transformer.
Distribution Primary Circuits
A typical radial 12.5 kV distribution circuit would be served from a distribution substation transformer
fed from one subtransmission line. If loads are large enough or of a critical nature, a second
subtrasmission feed and transformer will be installed. Most existing primary distribution circuits are
overhead construction, but much new construction is underground, especially in residential and
commercial areas. Most primary distribution circuits are a radial design with one source per circuit.
The trend to higher distribution voltages means more load may be served from each distribution circuit.
This would normally imply reduced reliability, because more load is affected by clearing faults on the
distribution circuit. However, automatic switching and protective relaying devices mitigate this effect.
Also, customers are demanding a higher level of reliability due to the increased use of home computersand other electronic appliances.
Distribution Secondary Systems
The secondary system is that portion of the distribution system between the primary feeders and the
customers premises. The secondary system is composed of distribution transformers, secondary circuits,
customer services, and revenue (billing) meters to measure the energy (kWh) usage. In some cases the
demand (kW) and power factor are also measured.
The secondary circuits connect the customer service to the low voltage side of the distribution
transformer. Although secondary systems are predominantly single phase, three wire, three phase
secondaries are used where a combination of large commercial and small industrial loads are located in aresidential area.
There are three different secondary system configurations:
radial secondary;
solid banked secondary; and,
loose banked secondary.
The radial secondary system is the most common configuration for serving cooperative rural areas, as
well as residential and light commercial loads. Secondary banking1 is used in areas where the loads are
close together and there is a need to reduce voltage flicker due to motor starting.
1Banking means paralleling on the secondary side a number of distribution transformers which areconnected to the same primary. Banked transformers are still a form of radial distribution, because theyare connected to one primary feeder. This configuration should not be confused with a secondarynetwork configuration where the distribution transformers are connected to two or more primary feeders.
mailto:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected] -
8/4/2019 IEEE Application Guide
9/102
Application Guide for Distributed Generation Interconnection
The NRECA Guide to IEEE 1547 September 2001
5
Banked secondary systems for residential or rural (if practical) are single phase, but three-phase banking
is also used for commercial applications. The advantages of banking distribution transformers are as
follows: (1) reduces voltage drop during motor starting by 50 to 70%, (2) improves the overall voltage
profile, (3) provides clearing of secondary faults, (4) reduces the size of secondary conductors, (5)
reduces the size of the distribution transformer (due to load sharing) by as much as 20-30%, (6) improves
reliability of service, and (7) new load may be added without changing out the transformers andsecondary conductors.
mailto:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected] -
8/4/2019 IEEE Application Guide
10/102
Application Guide for Distributed Generation Interconnection
The NRECA Guide to IEEE 1547 September 2001
6
Section 2: Meeting IEEE 1547 Technical Requirements
Voltage Regulation
P1547 Requirement (Section 4.1.1)
DR shall not degrade the voltage provided to the customers of the Area EPS to service voltages outside
the limits of ANSI C84.1, Range A.
Apart from the effect on the voltage of the Area EPS due to the real power generation of the DR, the DR
shall not attempt to oppose or regulate changes in the prevailing voltage level of the Area EPS at the PCC,
except that DR generators shall be permitted to use automatic voltage regulation when such regulation
can be accomplished without detriment to either the Area EPS or Local EPS.
Application Guidance
BACKGROUND
Voltage regulation is the term used to describe the process and equipment used by an electric power
system (EPS) operator to maintain approximately constant voltage to users despite the normal variations
in voltage caused by changing loads. Voltage regulation and voltage stability are important factors thataffect the operation of a power distribution system. If a system is not well regulated or stable, machines
receiving power from the system will not operate efficiently. Voltage regulation is considered in every
step of design and when sizing conductors.
Several different methods can be used to regulate voltage in a power distribution system. Typical radialdistribution systems are regulated at substations using feeder-voltage regulators2 or automatic load-tap-
changing transformers. Switched shunt capacitor banks3 may also be used at the substation for part of the
system voltage control. On distribution feeders, both line regulators and switched capacitors are used.
Rural areas served by cooperatives typically include long stretches of power lines with single-phase
automatic step regulators for supplementary voltage regulation. These step regulators are smaller in rating
than the feeder regulators and are often pole mounted. Ideally, utilities aim to keep the service voltage at
all customers within Range A as specified in ANSI Standard C84.14.
2A feeder-voltage regulator can be either single-phase or 3-phase construction. The single-phaseregulator is available in sizes ranging from 25-400kVA and the 3-phase regulator is available in sizesranging from 500-2000kVA. Today's voltage regulators are all the step-voltage type. A step voltageregulator is basically an autotransformer which has numerous taps in series with the windings. Thesetaps are changed automatically under a load by a voltage-sensing, switching mechanism. The taps areswitched in order to maintain a voltage as close to the predetermined level as possible.
3 Switched shunt capacitor banks are often used on distribution systems as part of the overall voltage-regulation scheme. Unswitched shunt capacitors are typically applied to bring the light-load power factorto about 100%. Then automatically switched shunt capacitor banks are added to achieve the economicfull-load power factor, which is typically 95% to 100%.
4Voltage Ratings of 60 Hz Electric Power Systems, ANSI C84.1-1995, Published by the National ElectricalManufacturers Association, 1995.
mailto:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected] -
8/4/2019 IEEE Application Guide
11/102
Application Guide for Distributed Generation Interconnection
The NRECA Guide to IEEE 1547 September 2001
7
IMPACT OF DR
Voltage regulation practice is based on radial power flows from the substation to the loads. DR
introduces meshed power flows that may interfere with the effectiveness of standard voltage regulation
practice. The effect of DR on EPS voltage regulation can cause changes in power system voltage by
1) the generator offsetting the load current, and 2) the DR attempting to regulate voltage. Most types of
DR generators and utility-interactive inverters should strive to maintain an approximately constant power
factor at any voltage within their rating; accordingly, the primary impact of DR on voltage regulation is
the result of the DR offsetting the load current. This is especially important in ensuring that a DR
installation will meet the intent of this P1547 requirement requiring the DR not to attempt to oppose or
regulate changes in the prevailing voltage level of the Area EPS.
The operation of DR on utility circuits basing voltage regulation on radial power flows can result in both
high and low service voltage unless precautions are taken. Examples of each of these situations are
discussed below.
Low Voltage
Most feeder regulators are equipped with line drop compensation (LDC) that raises the target regulator
output voltage in proportion to the load. This feature helps to maintain constant voltage at a point further
downstream by raising the regulator output voltage to compensate for line voltage drop between the
regulator and the load center. A DR located immediately downstream of a feeder voltage regulator may
interfere with the proper operation of the regulator, if the generation output is a significant fraction of the
normal regulator load. When the DR offsets 15 percent or more of the load current, this causes the
regulator to set a voltage lower than required to maintain adequate service levels at the end of the feeder.
The impact on feeder voltage regulation is as follows:
The feeder may be heavily loaded, but the regulator sees relatively low load due to the DR currentoffset.
The line voltage drop from the DR to the load center still reflects heavy loading, but the regulatoroutput voltage is not increased because of the low loading seen by the regulator.
As a result, low voltage conditions occur at the load center.
It should be noted that some cooperatives operate at lower voltage during lightly-loaded conditions to
reduce losses. These conditions typically occur during off-peak periods.
Compromises in the regulator settings, additional regulator controls or relocation of the regulator
to a point downstream of the DR interconnection point (or interconnection of the DR unit upstream
of the regulator) may be necessary to maintain adequate voltage at the load center.
mailto:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected] -
8/4/2019 IEEE Application Guide
12/102
Application Guide for Distributed Generation Interconnection
The NRECA Guide to IEEE 1547 September 2001
8
High Voltage
During normal radial feeder operation, there is a voltage drop across the distribution transformer and the
secondary conductors, and voltage at the customer service entrance is less than at the primary. Undercertain conditions with a DR unit installed, other customers on the feeder may see higher than normalservice voltage with associated unintended consequences. This situation can occur when:
1. A DR unit (such as in a small residential DR system) shares a common distribution transformerwith several other residences.
2. The distribution transformer serving these customers is located at a point on the feeder where theprimary voltage is near or above the ANSI C84.1 upper limit (126+ volts on a 120 volt base).
3. The DR introduces reverse power flow that counteracts the normal voltage drop, perhaps evenraising voltage somewhat.
With these conditions, the service voltage to the other customers may actually be higher at the customer
service entrance than on the primary side of the distribution transformer; it may even exceed the ANSIupper limit.
TIPS, TECHNIQUES AND RULES OF THUMB
In most cases, the impact on the feeder primary will be negligible for any individual residential scale DR
unit (
-
8/4/2019 IEEE Application Guide
13/102
Application Guide for Distributed Generation Interconnection
The NRECA Guide to IEEE 1547 September 2001
9
In this case (see box above), a voltage problem on the primary is unlikely. When the injected current is
much above 5%, there is more reason to worry about potential impacts.6
Synchronous Generator DR and Voltage Regulation
Synchronous generators equipped with voltage-regulator controls deliberately vary their field excitationin response to voltage changes, in an attempt to maintain constant voltage. When interconnected with a
large EPS, changes in field excitation cause reactive power exchange with the EPS.
The effect of constant-voltage regulated distributed generators on EPS voltage is a function of the short
circuit ratio of the distributed generator to the power system. If the short circuit ratio is small, the
distributed generator will have little actual effect on power system voltage, but the generator power factor
may become abnormally low under high or low voltage conditions on the EPS. Such a condition can limit
the real power capability of the generator and contributes to inefficient operation of the EPS.
A power factor controller can be used, instead of a voltage-regulator controller, to stabilize the excitation
system of synchronous rotating generators. The VAr/power factor controller can be used to maintain a
constant power factor or VAr output, making the synchronous machine voltage response resemble that ofan induction generator or utility-interactive inverter.
Siting DR to Reduce Distribution System Losses
Distributed generation will also impact losses on distribution systems. DR units can be placed at optimal
locations where they provide the best reduction in feeder losses. Siting of DR units to minimize losses is
like siting capacitor banks for loss reduction. The only difference is that the DR units will impact both the
real and reactive power flow. Capacitors only impact the reactive power flow. Most generators will be
operated between 0.85 lagging and 1.0 power factor, but some inverter technologies can provide reactive
compensation (leading current). A good load flow analysis software should be able to model the effects
on system losses. On feeders where losses are high, a small amount of strategically placed DR with an
output of just 10-20% of the feeder demand can have a significant loss reduction benefit for the system.Unfortunately, most utilities do not have control over the siting locations, since DR is usually customerowned. Nonetheless, for utilities that are moving forward with their own DR programs, optimal siting of
units can increase the performance of the system.
Siting DR and Consideration of Thermal Capacity Limits
Larger DR units must also be sited with consideration of feeder capacity limits. In some cases overhead
lines and cables may be thermally limited, meaning that the DR can inject power that exceeds the lines
thermal limit without causing a voltage problem on the feeder. The power flow analysis should flag the
locations where capacity constraints will be an issue from a thermal as well as a voltage perspective. In
general, a DR at a location that is thermally limited is not connected at the optimal point from a power
loss perspective.
6For shared secondaries, with DR even a small generator that injects less than 5% at the primary levelcould pose a voltage regulation risk to customers sharing the secondary. Thus, analysis of voltageconditions will almost always need to consider impacts on the secondary where the DR is located.
mailto:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected] -
8/4/2019 IEEE Application Guide
14/102
Application Guide for Distributed Generation Interconnection
The NRECA Guide to IEEE 1547 September 2001
10
Integration with Area Electric Power System Grounding
P1547 Requirement (Section 4.1.2)
The interconnection of the DR with the Area EPS shall be coordinated with the neutral grounding
method7 in use on the Area EPS as follows.
Three-Wire Area EPS Systems. (Section 4.1.2.1)
DR interconnections to Area EPS primary feeders of three-wire grounded or ungrounded systems, or to
tap lines of such systems, shall not provide any metallic path to ground from the primary feeder except
through suitably-rated surge arresters, high-impedance devices used only for fault detection purposes, or
both. 8
1. DR interconnections to Area EPS primary feeders of three-wire grounded or ungrounded systems, orto tap lines of such systems, shall not provide any metallic path to ground from the primary feeder
except through suitably-rated surge arresters or high-impedance devices used only for fault detection
purposes, or both. 9
2. For DR interconnections, directly or through a transformer,10 to Area EPS primary feeders of multi-grounded or uni-grounded four-wire construction, or to tap lines of such systems, the maximum
unfaulted phase (line-to-ground) voltages on the Area EPS primary feeder, during single line-to
ground fault conditions with the Area EPS source disconnected, shall not exceed those voltages that
would occur during the fault with the Area EPS source connected and no DR generation. 11
3. The ground-fault current contribution of the DR, and its interconnection transformer, shall not be
greater than 100% of the fault current contribution of the DR to a three-phase fault at the sameprimary feeder fault location. An interconnection to a primary feeder of a three-wire grounded or
ungrounded system shall have zero ground fault current contribution.12 These ground fault current
limitations shall not apply to any DR interconnected to an Area EPS through the existing distribution
transformer provided that neutral grounding, if any, of the high voltage winding is not changed.
7 For definition of grounding methods consult IEEE 62.92.1.
8 For the purposes of this subclause, grounded metallic enclosures or support structures such as steelpoles or metallic conduit, are not considered to be metallic paths to ground from the primary feeder.
9 For the purposes of this subclause, grounded metallic enclosures or support structures such as steelpoles or metallic conduit, are not considered to be metallic paths to ground from the primary feeder.
10 In many existing 4-wire multi-grounded distribution circuits the existing transformer for commercialand industrial facilities is a Y-Y connected transformer. In these cases consideration has to be given to thegrounding of the generator if the secondary service is a 4-wire service.
11 Voltages exceeding this limit are acceptable if it can be shown that they will not be detrimental to theequipment and customer loads connected to the Area EPS feeder.
12For DR technologies that have time-variant fault contribution characteristics, the characteristicproducing the highest fundamental-frequency fault current from the DR shall be used in this calculation(i.e., for synchronous generators, the subtransient reactance shall be used).
mailto:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected] -
8/4/2019 IEEE Application Guide
15/102
Application Guide for Distributed Generation Interconnection
The NRECA Guide to IEEE 1547 September 2001
11
Four-Wire Area EPS Systems. (Section 4.1.2.2)
For DR interconnections, directly or through a transformer13, to Area EPS primary feeders of multi-
grounded or uni-grounded four-wire construction, or to tap lines of such systems, the maximum unfaultedphase (line-to-ground) voltages on the Area EPS primary feeder, during single line-to-ground fault
conditions with the Area EPS source disconnected, shall not exceed those voltages that would occur
during the fault with the same Area EPS source connected and no DR generation.
The ground-fault current contribution (3I0) of the DR, including the effect of any transformers between
the DR and the primary feeder, shall not be greater than 100% of the fault current contribution of the DR
to a three-phase fault at the same primary feeder fault location.14 This ground fault current limitation
shall not apply to any DR interconnected to an Area EPS through the existing distribution transformer
provided that neutral grounding, if any, of the high voltage winding is not changed.
Application Guidance
BACKGROUND
A grounding system consists of all interconnected grounding connections in a specific power system and
is defined by its isolation or lack of isolation from adjacent grounding systems. The isolation is provided
by transformer primary and secondary windings that are coupled only by magnetic means.
System grounding, or the intentional connection of a phase or neutral conductor to earth, is for the
purpose of controlling the voltage to earth, or ground, within predictable limits. It also provides for a flow
of current that will allow detection of an unwanted connection between system conductors and ground.
When such a connection is detected, the grounding system may initiate operation of automatic devices to
remove the source of voltage from the conductors with undesired connections to ground.
The National Electric Code (IEEE/ANSI 70) prescribes certain system grounding connections that must
be made to be in compliance with the Code. The control of voltage to ground limits the voltage stress on
the insulation of conductors so that insulation performance can more readily be predicted. The control of
voltage also allows reduction of shock hazard to persons who might come in contact with live conductors.
Types of Distribution Feeders and Grounding Methods
13 In many existing 4-wire multi-grounded distribution circuits the existing transformer for commercialand industrial facilities is a Y-Y connected transformer. In these cases consideration has to be given to thegrounding of the generator if the secondary service is a 4-wire service.
14 For DR technologies that have time-variant fault contribution characteristics, the characteristicproducing the highest fundamental-frequency fault current from the DR shall be used in this calculation(i.e., for synchronous generators, the subtransient reactance shall be used).
mailto:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected] -
8/4/2019 IEEE Application Guide
16/102
Application Guide for Distributed Generation Interconnection
The NRECA Guide to IEEE 1547 September 2001
12
The grounding of utility distribution feeders is usually derived from a distribution substation transformer
with wye-connected secondary windings and with the neutral point of the windings solidly grounded or
connected to ground through a noninterrupting, current-limiting device such as a reactor. A grounding
transformer may also be used to establish a grounded system.The circuits associated with grounded
distribution systems generally have a neutral conductor connected to the supply grounding point. The
neutral conductor of the distribution circuits may be described as either multigrounded, unigrounded, or
ungrounded:
Multigrounded.....connected to earth at frequent intervals.
Unigrounded........fully insulated and have no other earth connection except at the source.
Ungrounded.........no intentional connection to earth.
U.S. utility distribution feeders are either: 1) four-wire-multigrounded or unigrounded systems, 2) three-
wire ungrounded systems, or 3) three-wire grounded systems. An example of the common neutral
method of distribution is shown in Figure 1.
IMPACT OF DR
DR interconnection to each type of distribution system can impact protection and coordination asdiscussed below.
Customer's water
pipe grounds
Single phase
secondary
Stationtransformer
Customer's water
pipes
Primary phase wires
Multigrounded neutral
1 transf
S. A.
NeutralCommon
Multigrounded
Figure 1. Common Neutral Method of Distribution
mailto:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected] -
8/4/2019 IEEE Application Guide
17/102
Application Guide for Distributed Generation Interconnection
The NRECA Guide to IEEE 1547 September 2001
13
Types of Distribution Systems
Three-Wire Ungrounded Systems
Three-wire ungrounded systems are clearly in the minority of U.S. distribution feeders. While this typeof system has no intentional connection to earth, connections to ground may occur through potential
indicating or measuring devices or other very high impedance devices.
Three-Wire Grounded Systems
In three-wire unigrounded systems, a neutral conductor is not run with each circuit, but the system is
grounded through the connections of the substation transformer or grounding transformer. On three-
phase three-wire primary distribution circuits, single-phase distribution transformers are connected phase-
to-phase. The connection of three single-phase distribution transformers or of three-phase distribution
transformers is usually delta-grounded wye or delta-delta. (The floating wye-delta or T-T connections
also can be used.) The grounded wye-delta connection is generally not used because it acts as a
grounding transformer. Surge arresters are generally connected phase-to-ground. However, the surgearrester rating is higher than those used on multigrounded neutral systems since the temporary 60 Hz
overvoltages expected under fault conditions are also higher.15
Four-Wire Multigrounded or Ungrounded Systems
Most U.S. utility distribution feeders are four-wire-multigrounded-neutral systems that are defined as
being effectively grounded with respect to the substation source. The neutral conductor associated with
the primary feeders of multigrounded neutral distribution systems is connected to earth at intervals
specified by national or local codes. It is also common practice to bond this neutral conductor to surge-
arrester ground leads and to all noncurrent-carrying parts, such as equipment tanks and guy wires, and to
interconnect it with the secondary neutral conductor or grounded conductor.16
For a single line to ground fault, this arrangement limits the voltage rise on unfaulted phases to about 125
to 135% of the prefault condition.17 Three-phase interconnections to multigrounded four-wire systems
must provide an adequate ground current source to control unfaulted-phase overvoltages for brief
islanding conditions during fault clearing, unless an interconnected DR is so small that it cannot support
any voltage on the system when isolated with load. However, the DR ground current source must also notbe so large that it significantly dilutes the fault current contribution from the utilitys source substation
and thereby degrades the ground fault detection sensitivity.
15IEEE Guide for the Application of Neutral Grounding in Power Systems, Part 4, IEEE Std. C62.92.4-1991.
16In some situations, the same neutral conductor is used for both the primary and secondary systems.There is some variation in this practice, however, and some utilities do not interconnect the primary andsecondary neutral conductors nor bond the neutral to the guy wire. If no direct interconnection is made,the secondary neutral conductor may be connected to the primary neutral conductor through a spark gapor arrester. Surge arresters on multigrounded neutral systems are connected directly to earth, and theirgrounding conductor may be interconnected directly to the primary neutral conductor and equipment tanks.They may also be interconnected with the secondary neutral at transformer installations.
17 IEEE Guide for the Application of Neutral Grounding in Power Systems, Parts 1-4, IEEE Std. C62.92 1991.
mailto:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected] -
8/4/2019 IEEE Application Guide
18/102
Application Guide for Distributed Generation Interconnection
The NRECA Guide to IEEE 1547 September 2001
14
Use of a DR source that does not appear as an effectively grounded source connected to such systems
may lead to overvoltages during line to ground faults on the utility system. This condition is especially
dangerous if a generation island develops and continues to serve a group of customers on a faulted
distribution system. Customers on the unfaulted phases could in the worst case see their voltage increase
to 173% of the prefault voltage level for an indefinite period. At this high level, utility and customer
equipment would almost certainly be damaged. Saturation of distribution transformers will help slightly
to limit this voltage rise. Nonetheless, the voltage can still become quite high (150% or higher).
TIPS, TECHNIQUES AND RULES OF THUMB
Assuring DR Integration with the EPS Ground
Multigrounded Neutral Systems
To avoid problems, all DR sources on multigrounded neutral systems that are large enough to sustain an
island should present themselves to the utility system as an effectively grounded source. If they do not,
they should use appropriate protective relaying to detect primary side ground fault overvoltages and
quickly trip off-line (instantaneous trip). The former approach is preferred since it limits by design the
voltage swells that the system will see during a fault. The latter approach, while used successfully in
many installations, could subject the customer to many cycles of severe overvoltage prior to the DG unit
being cleared from the system. Additionally, if the DR is not cleared quickly enough, equipment could bedamaged.
Static Power Converters
Integration of the ground system of a static power converter based DR facility with the existing grounding
system requires an examination of the circuit isolations from ground that might occur across the
interconnection. When operating in parallel with the Area EPS, effective grounding must be assured.
When the DR must disconnect itself to permit fault clearing on the utility system, or operate in a
standalone mode, the same grounding effectiveness must be designed into both systems.
A converter based DR directly connected to a grounded ac system through its static power converter is a
grounded source as long as the interconnection is made. If the DR has a neutral or grounded conductorwhich is not switched upon disconnect and is solidly tied to the ac system neutral then even during
disconnect and possible standalone operation without the ac system the DR remains grounded and has the
protective features of grounding still in force.
If a directly connected static power converter based DR was not tied to a grounded conductor during
separation from the utility for standalone electricity supply, balanced grounded operation will be lost. In
the case of single-phase systems, inclusion of an isolation transformer can eliminate this particular
Distributed generation must be applied with a transformer configuration and grounding
arrangement compatible with the utility system to which it is to be connected. Otherwise,
voltage swells and overvoltages may be imposed on the utility system that can damage utility or
customer equipment.
mailto:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected] -
8/4/2019 IEEE Application Guide
19/102
Application Guide for Distributed Generation Interconnection
The NRECA Guide to IEEE 1547 September 2001
15
problem. Grounding is accomplished on both sides of the transformer and the grounded DR energy
source can operate fully grounded with or without connection to the grounded utility service.
DR systems with converters that use three phase isolation transformers to interface with the Area EPS
present a variety of issues, all dependent on the configuration of the windings on either side of the
transformer. It is generally advisable that a power source be grounded at only one point, and the NEC isquite specific on this point. If multiple ground connections are created in the integration of the DR facility
to the existing ground system, neutral currents could flow in the ground system and compromise the
integrity of the protective grounding system.
If the DR is served by a dedicated isolation transformer, this permits the energy source of the DR to be
directly grounded either solidly or through an impedance. Certain static power converter networks
operate with a midpoint neutral. Alternatively the energy source may be grounded directly through the
converter at its midpoint. The transformer typically steps up the DR converter voltage to the level
required to match the ac utility interconnect voltage. It is at the transformer in particular that the
grounding connections must be controlled.
mailto:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected] -
8/4/2019 IEEE Application Guide
20/102
Application Guide for Distributed Generation Interconnection
The NRECA Guide to IEEE 1547 September 2001
16
SLIP AND SYNCHRONIZATION
The slip of a rotating ac machine isthe difference between its speed andthe synchronous speed, divided bythe synchronous speed. Slip isusually expressed as a percentage.It may be computed from themeasured speed of the machine andthe synchronous speed, but directmethods are more accurate.
Synchronization
P1547 Requirement (Section 4.1.3)
The DR unit shall synchronize with the Area EPS without causing a voltage fluctuation at the PCC
greater than 5% of operating voltage.
Application Guidance
BACKGROUND
In order to synchronize the distributed generator with the electric power system, the output of the
distributed generator and the input of electric power system must have the same voltage magnitude,frequency, phase rotation, and phase angle. Synchronization
is the act of checking that the four variables mentioned above
are within an acceptable range (or acceptable ranges). For
synchronism to occur, the output variables of the distributed
generator must match the input variables of the electric
power system. With polyphase machines, the direction of
phase rotation must also be the same. This is typically
checked at time of installation, the phases being connected to
the switches such that the phase rotation will always be
correct. Phase rotation is not usually checked again unless
wiring changes have been made on either the generator or
inverter, or the electric power system.
IMPACT OF DR
The testing provisions of IEEE 1547 require the test to demonstrate that the interconnection system, at
each point where synchronization is required, shall not connect the associated DR unit (or aggregation of
DR units) to an Area EPS except when all of the appropriate conditions are satisfied. If these conditions
are met, the DR will synchronize with the Area EPS with any voltage fluctuation limited to 5% of
nominal voltage.
The conditions for three types of DR follows.
A. Synchronous Generator to an EPS, or an Energized Local EPS to an Energized Area EPS.
Connection will be prevented when the DR (or the energized Local EPS) is operating outside of the
following limits relative to the Local EPS (or Area EPS).
mailto:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected] -
8/4/2019 IEEE Application Guide
21/102
Application Guide for Distributed Generation Interconnection
The NRECA Guide to IEEE 1547 September 2001
17
Aggregate Rating of
DR Units
(kVA)
Frequency
Difference
(f, Hz)
Voltage
Difference
(V, %)
Phase Angle
Difference
(, )
0 - 500 0.3 10 20
500 1,500 0.2 5 15
1,500 - 10,000 0.1 3 10
The test performed by the DR for the EPS will demonstrate that at the moment of paralleling-device
closure, all three parameters in the table above are within the stated ranges. This test shall also
demonstrate that if any of the parameters are outside of the ranges stated in the table, paralleling-device
closure will not be permitted.
B. Asynchronous (Induction) Generator to an EPS
In the case where the induction motor is acting as a generator, and the voltage drop is less than 5% at thePCC, the requirement is met.
Where the resulting voltage drop is greater than 5%, the analysis will proceed to consider the benefit of
accelerating the generator to near synchronous speed before connecting. If this produces less than 5%
voltage drop, then no additional testing is required and the requirement is met.
When the resulting voltage drop is still found to be unacceptable, the analysis will proceed to consider the
use of a static soft start unit that will provide a controlled rate of change of current.
The results of the analysis will be recorded and made available to the Area EPS Operator.
C. Static Inverter
A non-interactive inverter shall be treated as a synchronous generator of comparable size. A line
interactive inverter will be tested to establish the current that would be delivered to an EPS of zero
impedance. This will demonstrate the current control capacity of the inverter regulator.
The zero impedance current will be calculated from the value measured at two different impedances. Ifthe current is less than 120% of rated, the inverter will be considered to be in compliance at any rate. The
impedance values used for the test shall be as follows.
Z1 = 0.02*V*V/P
Z2 = 0.05*V*V/P
Where Z = impedance value
V = the DR unit rated line-to-line voltage, and
P = the DR unit rated power output.
The test will be carried out with a calibrated oscilloscope connected to measure the current in each phase.
The root mean square (rms) current shall be calculated for the first half of the cycle. From these results
the rms current to be delivered at an impedance level of zero shall be calculated by extrapolation.
mailto:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected] -
8/4/2019 IEEE Application Guide
22/102
Application Guide for Distributed Generation Interconnection
The NRECA Guide to IEEE 1547 September 2001
18
The test shall be carried out 10 times at each impedance value and the results maximized over these tests
when extrapolating to zero impedance.
TIPS, TECHNIQUES AND RULES OF THUMB
Out-of-Range Operation
Operation with phase angles out of phase between the distributed generator and the electric power system
may result in overheating of synchronous generator armature core ends with damage to the electric power
system and the distributed generator equipment.
When operating with a lower voltage magnitude, branch circuits may cause malfunctioning of motors and
controls. Semiconductors operation may also be impacted when voltage magnitude is allowed to slip
below desired levels. The semiconductors may malfunction and cause loss of control of distributed
generator devices. In addition, lower voltage may also extinguish mercury vapor type and fluorescent
lamps causing personnel safety to be compromised.
Operation at under frequency may result in synchronous generator hot spots and higher than normal
generator insulation temperatures.
Synchronization Techniques
Either manual or automatic synchronization devices may be used for synchronization of the distributed
generator with the electric power system. Considerations in the design and operation of both types are
discussed below.
Manual Synchronization
Manual synchronization equipment is normally used on smaller (less than 100 kW) distributed generatorequipment and as a backup to an automatic system on larger units. Manual synchronization equipment
varies with distributed generator size. The requirements for synchronization equipment for DGs
operating in parallel with the EPS and able to operate as an island are summarized in Table 1. For the
similar requirements for DGs with no ability to operate as an island, see Table 2.
For small single-phase systems (10 kW or less) which are electric power system connected only with no
islanding capabilities, only two volt meters are required.
For larger systems which are 10 kW and larger and have both electric power system operation and
islanding operation capabilities, the manual synchronization equipment will consist of two voltmeters,
Table 1. Synchronizing Requirements for Paralleled DG Units with Islanding
Capability
DR Size Volt Meters Freq MetersPhase Angle
MetersSync Scopes
>10 kW-500 kW 2 2 1 0
>500 kW-10 MW 2 2 1 1
>10 MW 2 2 1 1
mailto:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected] -
8/4/2019 IEEE Application Guide
23/102
Application Guide for Distributed Generation Interconnection
The NRECA Guide to IEEE 1547 September 2001
19
Synch-Check Relays
Synch-check relays are used to ensure thatbefore a machine can be paralleled, the voltageson both sides of the circuit breaker are nearly in
synchronism. That is, that the angle between thevoltages and the frequencies are sufficiently closetogether that the circuit breaker can be closedsuccessfully. If the limits are exceeded, thesynchro-check relay will prevent closure of thecircuit breaker.
two frequency meters, and a synchroscope.18 (See Table 1.) One voltmeter and one frequency meter
monitor the electric power system voltage and frequency. The other voltmeter and frequency meter
monitor the distributed generator voltage and frequency. A synchroscope pointer is used to indicate the
phase angle between the electric power system voltage and the distributed generator voltage. The straight
up or 12 oclock position indicates that the two voltages are in phase.
For a synchroscope, the connection between the electric power system and the distributed generator is
made when the synchroscope is rotating slowly in the clockwise direction and the pointer is about 11:30
position. When the pointer is rotating, it shows the frequencies of the electric power system and thedistributed generator are not exactly the same. Synchronization with the pointer rotating slowly clockwise
will ensure the connection between the two units is made along with a small outflow of power from the
distributed generator to prohibit the reverse power relay from tripping erroneously.
Automatic Synchronization
Many types of automatic synchronizers are
available to replace part or all of the manual
synchronizing functions mentioned above. Synch-
check relays, which are designed to check the
electric power system voltage and the distributed
generator voltages, close a contact when the twovoltages are within certain limits for certain length
of time. The synch-check relays are the least costly
and simplest to operate. The synch-check relaysmay also serve as signal devices for automatically
closing the breaker at the point of common
coupling.
Highly accurate and reliable automatic synchronizing relays and electronic transducer combinationpackages are avail