iffco phulpur project

27
155 First Prize Fertilizers INDIAN FARMERS FERTILISER COOPERATIVE LIMITED Phulpur Unit-II, Distt. Allahabad (Uttar Pradesh) Unit Profile Indian Farmers Fertiliser Cooperative Limited (IFFCO), globally acclaimed cooperative in fertiliser production and marketing has been striving for socio-economic upliftment of the rural population of India since inception. To ensure timely availability of quality fertilizers to the farmers, IFFCO came into being on 3rd November, 1967. Initially, IFFCO commissioned Kalol and Kandla plants in Gujarat in early 1975. Due to increasing demand-supply gap of Urea in the country, Govt. of India has given approval for expansion project at Phulpur site since basic infrastructure facilities were available at Phulpur. The unit Phulpur-II was commissioned in December 1997 and consists of 1520 MTPD Ammonia Plant based on M/s. HTAS, Denmark technology and 2620 MTPD Urea Plant based on M/s. Snamprogetti, Italy Technology.

Upload: rajeshkumare

Post on 17-Sep-2015

158 views

Category:

Documents


13 download

DESCRIPTION

iffcopp

TRANSCRIPT

  • 155

    First Prize Fertilizers

    INDIAN FARMERS FERTILISER

    COOPERATIVE LIMITED

    Phulpur Unit-II, Distt. Allahabad (Uttar Pradesh)

    Unit Profile

    Indian Farmers Fertiliser Cooperative Limited (IFFCO), globally acclaimed cooperative

    in fertiliser production and marketing has been striving for socio-economic upliftment

    of the rural population of India since inception. To ensure timely availability of

    quality fertilizers to the farmers, IFFCO came into being on 3rd November, 1967.

    Initially, IFFCO commissioned Kalol and Kandla plants in Gujarat in early 1975.

    Due to increasing demand-supply gap of Urea in the country, Govt. of India has

    given approval for expansion project at Phulpur site since basic infrastructure facilities

    were available at Phulpur. The unit Phulpur-II was commissioned in December

    1997 and consists of 1520 MTPD Ammonia Plant based on M/s. HTAS, Denmark

    technology and 2620 MTPD Urea Plant based on M/s. Snamprogetti, Italy Technology.

  • 156

    Energy Consumption

    Ammonia & Urea manufacturing is highly energy intensive and it contributes more

    than 80% of the total cost of production Urea. Therefore, a slight change in energy

    consumptions affects the cost of production in a big way. Apart from cost of

    production reduction in energy saves the valuable fast depleting natural resources

    such as Naphtha , Natural Gas, LSHS & Coal. Therefore, the Energy conservation is

    a major corporate objective at IFFCO and it is a continuous process at its units.

    IFFCO-Phulpur complex has become one of the lowest energy consuming units

    amongst fertilizer plants in India. It has substantially reduced its energy consumption

    during last three years. The details are highlighted below :

    Plant 2006-07 2007-08 2008-09 2009-10 %Reduction

    Over 2006-10

    Ammonia-II 7.986 7.926 8.116 7.619 4.60

    Urea - II 5.792 5.824 5.980 5.658 2.31

    All figures are in Million kCal/MT

    Performance At A Glance

    Pro

    du

    ctio

    n(M

    T)

    700000

    800000

    900000

    1000000

    2006 -07 2007 -08 2008 -09 2009 -10

    882600

    924223

    840584

    1000085

    YEAR

    UREA -II PRODUCTION

    400000

    500000

    600000

    2006 -07 2007 -08 2008 -09 2009 -10

    506172

    519949

    475913

    583507

    YEAR

    AMMONIA - II PRODUCTION

    Pro

    du

    ctio

    n(M

    T)

    5.795.82

    5.98

    5.66

    5.50

    5.70

    5.90

    6.10

    2006-07 2007-08 2008-09 2009-10

    YEAR

    UREA- II ENERGY CONSUMPTION

    2.2 % reduction over 2006-10

    7.997.93

    8.12

    7.62

    7.50

    7.70

    7.90

    8.10

    8.30

    2006-07 2007-08 2008-09 2009-10

    YEAR

    AMM - II ENERGY CONSUMPTION

    4.6%reduction over 2006 -10

    Ov

    era

    llE

    ner

    gy

    (G

    Ca

    l/M

    T)

    Ov

    era

    llE

    ner

    gy

    (G

    Ca

    l/M

    T)

  • 157

    Energy Conservation Commitment, Policy & Set-Up

    IFFCO Phulpur Unit is playing a vital role in the national economy by providing

    chemical fertiliser Urea to the Indian Farmers for prosperity and growth.

    Manufacturing Process of Urea Complex is highly energy intensive and energy

    contributes more than 80% of cost of production. Therefore, energy conservation

    receives top priority at IFFCO Phulpur. IFFCO Phulpur Unit is committed to produce

    good quality product with a mission to reduce the specific energy consumption 1%

    every year.

    IFFCO Phulpur is the first in fertilizer sector to receive Energy Management

    Certification EN -16001.

    Energy Conservation Achievements

    Phulpur unit has always been a leader in adopting new developments in the field of

    fertilizer production and number of modifications / revamp have been carried out

    over the years which have resulted in substantial improvement in energy

    consumption.

    Major Projects Implemented during the Year 2009-2010

    1 Higher Load Operation, Maximization of on-stream days & optimization

    of Process Parameters

    Specific Feed, Fuel and Steam Consumption is monitored on daily basis. Based

    on design data corrective measures are taken on day to day basis to run the

    plant at optimum efficiency.

    Other important parameters like, Turbine & Compressor Efficiency, proper

    utilization of Turbine condensate, furnace stack temperature and Turbine exhaust

    pressure are monitored to achieve the lowest overall plant energy. Due to

    these measures, 5% reduction in the overall energy per MT of Urea has been

    realized.

    Yearly Saving (MTOE) : 23108.99

    Yearly Saving (Rs. Lakhs) : 3471.22

    Investment (Rs. Lakhs) : NIL

    2 Monitoring & Rectification of steam traps and leakages

    Steam traps are installed in the steam lines to remove condensate from the

    system. It is required to remove Condensate from the steam system, to avoid

    heat loss and hammering in the line.

    A survey was conducted to study the faulty traps and it was recommended to

    replace those traps with new ones. Accordingly, all the faulty traps were changed.

    Overall savings of 2 MT/Hr of HP steam has been realized with this measure.

  • 158

    Yearly Saving (MTOE) : 1337.48

    Yearly Saving (Rs. Lakhs) : 193.86

    Investment (Rs. Lakhs) : 6.00

    3 Absorber temperature improvement in Carbon Dioxide Recovery Plant

    (CDR)

    Carbon Dioxide Recovery Plant (CDR) has been installed to recover CO2 from

    the Flue Gas of Primary Reformer of Ammonia-II Plant. CDR Plant mainly consists

    of Wash Column, Absorber and Regenerator. Due to lesser CW supply pressure

    to the coolers of Absorber, the design value of top temperature could not be

    achieved. Due to higher temperature, low pressure (LP) steam consumption in

    the Regenerator was more.

    In order to increase the CW flow and bring down the absorber temperature to

    design range, CW return line has been connected to the Mist Cooling water

    sump. As Mist Cooling sump is located at ground level, due to pressure

    differential CW flow increased, resulting in better performance of the Absorber.

    Due to lesser temperature, LP steam savings in the regenerator section has

    been achieved.

    Yearly Saving (MTOE) : 91.72

    Yearly Saving (Rs. Lakhs) : 13.29

    Investment (Rs. Lakhs) : 8.00

    Schematic Dig. of the Scheme

    4 Bypass of Adiabatic Pre Reformer

    Pre-Reformer was installed by the Process Licensor Haldor Topsoe at the time

    of commissioning for the Naphtha feed. Pre-reformer adiabatically breaks the

    higher hydrocarbons to lower hydrocarbons. After RLNG Conversion, in-house

    study was conducted and it was decided to bypass Adiabatic Pre Reformer.

    After by-passing Pre Reformer, pressure drop at the front-end reduced by 1.7

  • 159

    5 Installation of Liquid Nitrogen Tank

    Syn Gas is highly flammable mixture. Before doing any hot job, purging of Syn

    loop is a must. During catalyst loading also N2 atmosphere is a must for Reduced

    Fe catalyst. Total time required for purging and catalyst loading with existing

    facilities like N2 Blower, Inert Gas Plant was atleast 3 days. Liquid N2 Tank has

    been installed for storing the N2 brought through the tankers. With the help of

    the stored N2 in the tank, purging and catalyst loading job was completed in

    1.5 Days. Thus saving 1.5 Days shutdown time. Steam has been saved, as

    steaming of Primary Reformer has been reduced by 1.5 Days.

    Yearly Saving (MTOE) : 312.15

    Yearly Saving (Rs. Lakhs) : 45.24

    Investment (Rs. Lakhs) : 45.00

    3 D view of Liquid Nitrogen Tank

    kg/cm2. Due to lesser pressure drop, Syn Gas Compressor suction pressure

    increased by 1.7 kg/cm2 resulting in lower steam consumption in the Syn

    Turbine.

    Yearly Saving (MTOE) : 5445.93

    Yearly Saving (Rs. Lakhs) : 793.63

    Investment (Rs. Lakhs) : NIL

    Schematic Dig. of the bypass of Adiabatic Pre Reformer

  • 160

    7 Stoppage of Service Water Pump

    Water requirement of Phulpur Unit is full-filled by borewell water. Earlier, borewell

    water was stored in the raw water storage and water for Softening Plant was

    transferred by Service Water Pump.

    Now, the feed water for Softening Plant is taken directly from the borewell

    header, resulting in stoppage of 122 KW service water pump.

    Yearly Saving (Lakh kWh) : 10.69

    Yearly Saving (Rs. Lakhs) : 117.56

    Investment (Rs. Lakhs) : NIL

    Sketch before modification Sketch after modification

    6 CO2 Ejectors to prevent Seal losses

    CO2 compressor is installed in the Urea Plant to compress the CO2 from the

    Ammonia Plant from 0.5 kg/cm2 to 160 kg/cm2, before entering Urea Reactor.

    CO2 from the seals of compressor escapes to the atmosphere. An ejector

    system has been installed in the compressor. These ejectors were available in

    Urea-II as discarded. The CO2 escaped from the system is trapped by the

    ejector and sent back to the compressor suction. Total savings of 300 NM3 of

    CO2 has been estimated. Earlier, this amount of CO2 was produced in the

    Carbon Dioxide Recovery (CDR) Plant to keep up with the Urea Production.

    With this scheme, load of CDR Plant has been reduced. Lower CDR Plant load

    resulted in lesser low pressure steam consumed in the regenerator system.

    Yearly Saving (MTOE) : 275.16

    Yearly Saving (Rs. Lakhs) : 39.88

    Investment (Rs. Lakhs) : NIL

    Sketch before modification Sketch after modification

  • 161

    8 Stoppage of RO Feed Water Pump

    Reverse Osmosis Plant has been installed to treat effluent water. Earlier effluent

    water from the plant was stored in a Feed Tank and transferred to the RO feed

    with the help of RO Feed water pump.

    As a energy saving initiation, effluent water is fed directly to the RO feed. This

    has resulted in the stoppage of 45 KW feed water pump.

    Yearly Saving (Lakh kWh) : 3.94

    Yearly Saving (Rs. Lakhs) : 43.36

    Investment (Rs. Lakhs) : NIL

    Sketch before modification Sketch after modification

    9 Installation of Solar Power Pack

    A Solar Photo Voltaic Power Plant of 1.5 kW has been installed at R&D building

    in plant premises. The power generated is being utilized for fan and lighting

    application of the R&D building.

    There are total 20 Nos. of Solar Photo Voltaic modules of 75 W each. The

    energy generated by these Solar Photo Voltaic modules is stored in rechargeable

    batteries and this energy is consumed as per the desired application.

    Yearly Saving ( kWh) : 1460

    Yearly Saving (Rs. Lakhs) : 0.16

    Investment (Rs. Lakhs) : 5.23

    Picture / Sketch of Solar Power Pack

  • 162

    10 Installation of Solar Street Lights

    6 Nos. of 22 W stand alone Solar Street Lights have been installed in the

    premises.

    Each system contains, 2 CFL bulbs of 11 W each, Solar Photo Voltaic modules

    of 100 W, rechargeable batteries. The energy is saved in the batteries during

    day time and consumed during night. The CFL gets ON automatically during

    darkness.

    Yearly Saving ( kWh) : 385

    Yearly Saving (Rs. Lakhs) : 0.04

    Investment (Rs. Lakhs) : 2.50

    Picture of Solar Street Lights

    11 Output Voltage Reduction of Lighting Transformer

    Power saving by reducing the supply voltage in lighting system has been carried

    out by lowering the tap of the lighting transformer. Supply voltage has been

    reduced from 414 V (3 phase) to 404 V (3 phase). Total power reduction is

    13.9 KW.

    Yearly Saving ( kWh) : 60882

    Yearly Saving (Rs. Lakhs) : 6.70

    Investment (Rs. Lakhs) : NIL

  • 163

  • 164

    Environment and Safety

    IFFCO Phulpur Unit is totally committed for maintaining an eco-friendly environment.

    For controlling air pollution, plants have been provided with Bag Filters, Electro

    Static Precipitators, Dust Extraction Systems, etc. A lush green belt with about 3

    lakh trees has been developed all around the factory premises which is a natural

    means of air purification. To overcome the problem of fly ash disposal, generated

    in the Captive Power plant, a dense phase dry fly ash disposal plant has been

    installed which directly fills the fly ash in closed tankers for transportation of the

    ash to the cement plants manufacturing Portland Pozzolana cement.

    Phulpur Unit has always put its best efforts for conserving water. The effluent

    generated in the plant is recycled back after purification in Reverse Osmosis Plant.

    Even the sewage water generated in the township is reused in the plant after

    treatment in sewage treatment plant. The plant is running on zero effluent discharge

    and total recycle basis. The present specific water consumption is the lowest among

    the fertiliser industry in the country. Plant and its township have ISO 14001

    certification which speaks volumes about its environmental commitment.

  • 165

    Second Prize Fertilizers

    RASHTRIYA CHEMICALS AND

    FERTILIZERS LTD.

    Trombay Unit, Mumbai (Maharashtra)

    Unit Profile

    Rashtriya Chemicals and Fertilizers Limited, Trombay, a Govt. of India Undertaking

    is one of the largest integrated Fertilizer and Industrial chemicals complexes in the

    country. It was incorporated on 6th March'1978 during reorganization of the erstwhile

    Fertilizer Corporation of India Ltd. into Hindustan Fertillizer Corporation Ltd., and

    National Fertilizers Limited. It has two industrial complexes located at :

    Q Trombay in Mumbai

    Q Thal in Raigad district of Maharashtra

  • 166

    Trombay Unit manufactures a vast range of products ranging from Complex Fertilizers

    to Industrial Chemicals. These plants were installed phase wise under various

    schemes such as expansion, de-bottlenecking, revamping etc.

    Energy Consumption

    Year Electrical Energy consumed Thermal energy consumed

    Lakhs kWh Lakh SM3

    2008-2009 2097.20 1949.17

    2009-2010 2713.98 2996.84

    Energy Conservation Commitment, Policy & Set-Up

    Considerable efforts have been made to reduce energy consumption of age-old

    plants making use of latest technology.

    An Energy Cell with an Energy Manager and qualified engineers has been set up to

    analyze the day to day energy consumption levels in various process plants in the

    factory. Energy Conservation Opportunities are identified based on energy audits,

    case histories of successful conservation measures implemented by other plants

    and through suggestions received from the operating and technical personnel etc.

    Major Projects Implemented during the Year 2009-2010

    1. Provision of capacitor banks on 11KV system fed from

    Ammonia-1

    After provision of capacitor banks on 11 KV system fed the power factor has improved

    to the tune of 0.999. Thus reducing the losses in electrical network and saving

    almost Rs. 90 Lakhs in electricity bill.

    Energy cost savings = Rs. 90.01 Lakhs

    Total investment = Rs. 35.00 Lakhs

    2. Scheme to use Benfield condensate in place of DM water in

    Ammonia-V plant

    The above scheme of using Benefield Condensate in place of DM water for purpose

    of sealing in Benefield solution pump has lead to saving in electrical power as one

    DM water pump (P313) is stopped. The Benefield condensate is connected at

    discharge line of DM water pump (P313).

    Energy cost savings = Rs. 4.78 Lakhs

    Total investment = Rs. 4.00 Lakhs

  • 167

    3. Conventional 125 Watt HMPV light fittings have been replaced

    with 70 Watt Metal halide light fittings

    Total 100 no. of Conventional 125 Watt HMPV light fittings have been replaced with

    70 Watt Metal halide light fittings leading in electrical energy saving of 0.5 lakh

    kWh.

    Energy cost savings = Rs. 2.51 Lakhs

    Total investment = Rs. 4.50 Lakhs

    4. Installation of new modified SL Saturator in ANP Plant

    The above scheme has lead to savings in steam of 0.5 MT/hr due to stopping of

    steam leakage. Thus leading to reduction in fuel consumption.

    Energy cost savings = Rs. 7.16 Lakhs

    Total investment = Rs. 17.30 Lakhs

    5. Installation of new AN surface condenser in ANP plant

    The above scheme has lead to Saving of electrical energy due to stoppage of 2 no.

    Vacuum pump motors (140 kW) which were earlier required to operate with the

    old surface condenser.

    Energy cost savings = Rs. 29.38 Lakhs

    Total investment = Rs. 53.40 Lakhs

    6. Replacement of 240 Nos of old A/Cs by new energy efficient

    A/cs

    Replacement of 240 Nos of old A/Cs by new energy efficient A/Cs leading to saving

    of electrical energy

    Energy cost savings = Rs. 9.52 Lakhs

    Total investment = Rs. 27.10 Lakhs

    7. Installation of Fan less cooling tower in Sulphuric acid plant

    Fan less cooling tower is installed in place of two induced draft cooling towers in

    Sulphuric acid plant.

    Reduction of power consumption:

    Energy cost savings = Rs. 15.50 Lakhs

    Total investment = Rs. 14.05 Lakhs

  • 168

    8. Installation of Capacitor Banks in Sulphuric Acid Plant

    Installation of Capacitor Banks in Sulphuric Acid Plant has lead to reduction in

    electrical energy consumption.

    Energy cost savings = Rs. 6.29 Lakhs

    Total investment = Rs. 7.00 Lakhs

    9. Installation of Air Handling Unit for SAP-CNA Control Room

    Installation of Air Handling Unit in Sulphuric Acid Plant leading to saving of electrical

    energy by stopping Air Conditioners in Control room.

    Energy cost savings = Rs. 1.68 Lakhs

    Total investment = Rs. 6.50 Lakhs

    10. Provision VFD for 2 No. of aerator motors in Sewage Treatment

    Plant

    Installation of VFD in for 2 no. aerator motors leading to saving of electrical energy.

    The operation of VFD is linked with online Dissolved Oxygen measurement. By

    monitoring the DO value the speed of aerators can be controlled, thus leading to

    saving of electricity.

    Energy cost savings = Rs. 6.24 Lakhs

    Total investment = Rs. 4.35 Lakhs

    11.Solar water heater for providing 6000 liter per day of hot water

    (70 0C) Sewage Treatment Plant

    Installation of Solar water heater for providing 6000 liter per day of hot water (70

    0C) Sewage Treatment Plant. This has lead to stopping of two electric heaters (24

    kW each) and thus reducing power consumption

    Energy cost savings = Rs. 6.83 Lakhs

    Total investment = Rs. 9.88 Lakhs

  • 169

    12.Provision of High Capacity C.W. Pump

    for Methylamine Plant

    Provision of High Capacity C.W. Pump for MAP has

    resulted in saving of electrical energy (25 kWh).

    Earlier two less capacity pumps were operated. These

    pumps are now stopped and new high capacity pump

    is installed leading to stoppage of two lesser capacity

    pumps.

    Energy cost savings = Rs. 7.33 Lakhs

    Total investment = Rs. 2.00 Lakhs

    Environment and Safety

    In line with motto of sustainability, The plant is Environment Management System

    (EMS) ISO-14001:2004 compliant.

  • 170

    Certificate of Merit Fertilizers

    GUJARAT STATE FERTILIZERS &

    CHEMICALS LIMITED

    Vadodara Unit, Distt. Vadodara (Gujarat)

    Unit Profile

    Gujarat State Fertilizers & Chemicals Ltd. (GSFC), a unit promoted by the

    Government of Gujarat is leading manufacturers of fertilizers & chemicals. GSFC is

    spread over 648 hectare with 220 (34%) hectare of green belt.

    On February 15th 1962, GSFC was incorporated as Joint Sector Company with

    determination of the Government of Gujarat to offer quality products and services

    to the farmers. The first latency of GSFC's fertilizer rolled out of its production unit

    in 1967.

    During the years 1974 to 1982 with serene policies of alteration, GSFC turned into

    manufacturing of Caprolactam, Nylon-6, Melamine and Argon. Subsequently,

    capacities were enhanced in Caprolactam and Melamine. Initially all the power was

    drawn from state grid. GSFC installed three nos. of Cogeneration plants in phase

    wise manner.

  • 171

    Manufacturing facilities / products range

    Installed capacity / Actual production / Capacity utilization for the last three years

    are presented below:

    Product Unit Installed Actual production / (Capacity utilization %)

    capacity

    2007-08 2008-09 2009-10

    Urea MT 367200 277008 280500 326300

    (75.44%) (76.39%) (88.86%)

    Ammonium MT 196000 292935 265710 271580

    sulphate (AS) (149.46%) (135.57%) (138.56%)

    Diammonium MT 108000 79300 43770 00

    sulphate (DAP)

    APS MT 120120 207500 293600

    Caprolactam MT 70000 79716 70913 81151

    (113.88%) (101.3%) (115.93%)

    Melamine MT 15000 14741 13655 13735

    (98.27%) (91.03%) (91.57%)

    Nylon-6 MT 8000 8638 8751 8688

    (107.98%) (109.39%) (108.6%)

    MEKO MT 4450 4083 3400 2780

    (91.75%) (76.4%) (62.47%)

    Energy Consumption

    Energy consumption at GSFC is monitored on regular basis during day to day

    production meeting, fortnightly Operation division meeting (ODC) and monthly

    Technical Monitoring Committee (TMC) meetings.

    Consumption of NG, power and LSHS for last three years is as given below:

    YEAR NG Power - Power LSHS MT Total

    own generation purchased energy

    units * 1000 units * 1000 consumed

    Gcal

    2007-08 153265 169056 424786 4088 3044065

    2008-09 145039 162029 392605 5412 2875911

    2009-10 551946 140989 446118 6916 3201640

  • 172

    Total Energy consumption at GSFC

    2000000

    2200000

    2400000

    2600000

    2800000

    3000000

    3200000

    3400000

    2007-08 2008-09 2009-10

    Year

    En

    erg

    y,G

    cal

    Energy Gcal

    Energy Conservation Commitment, Policy and Set-Up

    GSFC has energy conservation as major corporate objective. General Manager

    (also designated Energy Manager) coordinated the activities of energy conservation

    and cost reduction. GSFC has dedicated energy cell comprising members from

    Operation, Electrical, Maintenance and Technical Services. Energy conservation

    ideas are also received from all employees in form of suggestion through Suggestion

    Appraisal Committee. Also a dedicated Energy management team comprising of

    16 members is formed to discuss, evaluate and encourage energy conservation

    ideas from each plants and departments.

    GSFC has also implemented Energy Management system BS - EN-16001 to have

    energy conservation approach in systematic, uniform and continuously monitored

    parameter by one and all, including higher management. Various energy

    conservation schemes are initiated under the Energy management system adopted

    and targets set for implementation of the same at faster rate. Special attention is

    given for purchase of energy efficient items.

    Major Projects Implemented during the Year 2009-2010

    GSFC implemented following schemes at Vadodara unit.

    1. Installation of small capacity Make up water pump at Co-Generation -III plant.

    Due to low load operation requirement, make up water pump was operating

    at low capacity. Small capacity, low head pump installed in place of high

    capacity, high head pump to reduce power consumption by 2.4 lacs

  • 173

    equivalent to Rs. 6.03 lacs/Yr. Cost of installation of small capacity small head

    pump is Rs. 3.17 lacs/Yr with payback period of about 7 months.

    2. Power saving by stopping continuous operation of high capacity Caustic pump

    (P-1046) in Capro-II plant. A high capacity caustic pump common for

    continuous and occasional consumers is provided which runs on continuous

    basis. Small capacity pump for continuous supply to consumers, installed. It

    resulted in to stoppage of higher capacity pump except for occasional running.

    It resulted in to annual power saving by 0.48 lacs units/Yr, equivalent to Rs.

    1.81 lacs/Yr. Cost of installation of small capacity pump is Rs. 1.65 lacs/Yr

    with payback period of less than a year.

  • 174

    3. Changing of CT fan blade from Aluminium to FRP-Hollow blades at Ammonia

    storage plant. Existing Aluminium blades replaced by hollow FRP blades to

    reduce power consumption. It resulted in to annual power saving by 0.32 lacs

    units/Yr, equivalent to Rs. 1.21 lacs/Yr. Cost of installation of is Rs. 1.0 lacs/Yr

    with payback period of 10 months.

    Savings and payback period for Energy conservation schemes atGSFC.

    0

    2

    4

    6

    8

    10

    12

    1 2 3

    NO. of SchemesEletricity conservation, Lacs/kWh Savings, Rs. (lacs/Yr)

    Cost of Implementation, Rs. (lacs) Payback period, months

  • 175

    Environment and Safety

  • 176

    Certificate of Merit Fertilizers

    INDIAN FARMERS FERTILISER

    COOPERATIVE LIMITED - PARADEEP UNIT

    Distt. Jagatsinghpur (Orissa)

    Unit Profile

    Indian Farmers Fertiliser Cooperative Limited (IFFCO) took over OCFL's Phosphatic

    Fertiliser Complex at Paradeep in October 2005

    The plant consists of two streams of Sulphuric Acid Plant, one stream of Phosphoric

    Acid plant and three streams of Complex fertilizer plant. In addition to these various

    offsite and utilities facilities are also present inside the complex to fulfill various

    requirements.

  • 177

    Energy Consumption

    Production Performance

    During the financial year 2009-10, IFFCO Paradeep unit have produced 15.00 lakhs

    metric tonnes (MT) of complex fertilisers, 14.28 lakhs MT of Sulphuric Acid and

    4.62 lakh MT of Phosphoric Acid (as 100% P2O5).

    0

    0.2

    0.4

    0.6

    0.8

    1

    1.2

    Sp

    .C

    on

    s.

    (Gc

    al/

    MT

    )

    2006-07 2007-08 2008-09 2009-10

    Year

    Specific consumption of Energy

    0.000

    0.100

    0.200

    0.300

    0.400

    0.500

    0.600

    0.700

    0.800

    0.900

    1.000

    Sp

    .C

    on

    s.(

    MW

    H/M

    T)

    2006-07 2007-08 2008-09 2009-10

    Year

    Specific consumption of Power

  • 178

    Energy Conservation: Commitment, Policy & Set-Up

  • 179

    Major Projects Implemented during the Year 2009-2010

    1. Replacement of cooling tower fan blades: The cooling tower blades of

    Energy Center cooling tower & Sulphuric Acid Plant (SAP) cooling tower were

    replaced with energy efficient FRP hollow blades as an energy savings scheme

    measure. The modification led to savings of 15kWh per fan.

    Investment in SAP cooling tower : Rs. 21,00,000 /-

    Savings in energy due to replacement SAP cooling tower blades with hollow

    FRP blades :Rs.246600/year

    Investment in TG cooling tower : Rs. 30,00,000 /-Savings in energy due to

    replacement TG cooling tower blades with hollow FRP blades : Rs.65,26,000

    per year

    2. Trimming of filter water pumps: The filter water pumps are used to pump

    process water to different plants inside the complex. Each of the three pumps

    was designed to give a flow of 1800 m3

    /hr at a discharge pressure of 6.9 kg/

    cm2

    . After an in-house study as per the requirement of the plant it was observed

    that the impeller of one pump can be trimmed for lower flow without any

    change in the discharge pressure. The impeller dia. of the pump was trimmed

    form 520 mm to 490 mm. After the trimming the performance of the pump

    was observed and tabulated below.

    3. Use of Liquid ammonia instead of vapor ammonia: In the DAP/NP plant it

    was designed to use vapor Ammonia to react with Phosphoric acid to produce

    the complex fertiliser (DAP/NP). So steam was used to vaporize liquid ammonia

    as the ammonia is received and stored in the liquid state. After an in-house

    study it was considered to use liquid ammonia in place of vapor ammonia

    which saves energy in terms of steam being used for vaporization.

    Description Before trimming After Trimming

    Dia. of the Impeller 520 mm 490 mm

    Flow of the pump 1800 m3

    /hr 1500 m3

    /hr

    Discharge Pressure 6.9 kg/cm2

    6.9 kg/cm2

    Current 42 amp 36 amp

    Power consumption 411 kW 338 kW

    Savings - 73 Kw

    Monetary Savings - 17.96 Lakh rupees

    Investment - NIL

  • 180

    A. Savings of energy in DAP/NP plant due to liquid ammonia feeding

    I. Energy savings from Steam pre-heater

    Consumption of steam in Preheater = 2360 kg/hr

    2.360 MT/hr

    Heat content of the LP steam = 661.300 Kcal/kg

    Energy savings per hour = 1.561 Gcal

    Total energy savings for 2009-10 for three trains = 29462.291 Gcal

    (considering stream hours for three trains 18878 Hrs)

    II. Energy savings from ammonia vaporiser

    Steam requirement during the start up = 10.250 MT/startup

    Heat requirement per startup = 6.778 Gcal

    Assuming one startup each day (330 days) 2236.847 Gcal

    energy savings for three trains due to ammonia vaporiser = 6710.542 Gcal

    Total savings per year (I + II) = 36172.832 Gcal

    Steam savings per year = 44879.444 MT

    (converting to HP steam, 805.9 Kcal/kg)

    Price of steam per MT = 500.00 INR

    Total savings per year = 22439722 INR

    Coal savings per year = 13598.472 MT

    (considering sp. Cons. Of 0.3030 per MT of steam)

    B. Investment: Rs. 30,00,000 /-

    C. Payback period: 0.133 Yrs

    4. Reduction of MP steam pressure in DAP/NP Complex fertiliser Plant:

    2 MT of Medium Pressure steam at 15 kg/cm2

    g was being used in combustion

    chamber of Dryer for atomization of furnace oil, flushing of slurry pumps and

    slurry lines. After an in-house study it was observed that MP steam at 10 kg/

    cm2

    g can be used for the above purpose. Accordingly the pressure was reduced

    as per requirement and the savings are as following.

  • 181

    A. Investment: NIL

    B. Savings due to reduction of pressure in MP steam

    Quantity of MP steam used in DAP = 2 TPH

    Enthalpy of steam at 15kg/cm2g, 220 OC = 679.9 Kcal/kg

    Enthalpy of steam at 10kg/cm2g, 200 OC = 674.1 Kcal/kg

    Savings in energy per hour = 11600 Kcal/Hr

    Savings in energy per year = 218984800 Kcal/Yr

    Enthalpy of HP steam (61 Kg/cm2g, 480 OC) = 805.4 Kcal/kg

    Savings in terms of HP steam per year = 272 MT

    Cost of HP steam = 500 INR

    Monetary savings = 135948 INR

    Coal savings per year = 82 MT

    Energy savings in Coal Handling Plant (CHP): In the old CHP total eleven nos.

    of conveyors were present for conveying coal inside the plant. When it was planned

    to construct the new present CHP it was considered to reduce the no. of the belts

    which in turn reduces the energy consumption as the no of drives were reduced.