ilc transport and installation
DESCRIPTION
ILC TRANSPORT AND INSTALLATION. Presentation to CES meeting 8 April 2009 ILC Beam he ight explanation, Transport implications of sloping access tunnels Discussion of buggy-type solution Info on CLIC module transport Acknowledgements: Jerry Leibfritz, FNAL Atsushi Enomoto , KEK - PowerPoint PPT PresentationTRANSCRIPT
![Page 1: ILC TRANSPORT AND INSTALLATION](https://reader036.vdocuments.net/reader036/viewer/2022081604/568161ba550346895dd18ef3/html5/thumbnails/1.jpg)
1
ILC TRANSPORT AND INSTALLATION
Presentation to CES meeting 8 April 2009
• ILC Beam height explanation,• Transport implications of sloping access tunnels• Discussion of buggy-type solution• Info on CLIC module transport
Acknowledgements: • Jerry Leibfritz, FNAL• Atsushi Enomoto, KEK• David Smekens, CERN• Caterina Bertone, CERN
Keith Kershaw, EN-HE CERN CES 08 April 2009
![Page 2: ILC TRANSPORT AND INSTALLATION](https://reader036.vdocuments.net/reader036/viewer/2022081604/568161ba550346895dd18ef3/html5/thumbnails/2.jpg)
2
Reason for the (relatively high ) height of the ILC cryomodules above the floor (1)
(860mm clearance underneath cryomodules)
Response from Jerry Leibfritz, FNAL (1)• This is what is used at DESY for FLASH and CMTS, and
also at the Fermilab ILCTA. • It is based on the large support girder that sits
underneath the first and last cryomodules of a string to counteract the large vacuum load and prevent movement of the cryomodule. The support stand sits on top of this girder.
Keith Kershaw, EN-HE CERN CES 08 April 2009
![Page 3: ILC TRANSPORT AND INSTALLATION](https://reader036.vdocuments.net/reader036/viewer/2022081604/568161ba550346895dd18ef3/html5/thumbnails/3.jpg)
3
Picture of the first cryomodule on its green support girders at Fermilab.
( cryogenic components not installed )
Keith Kershaw, EN-HE CERN CES 08 April 2009
![Page 4: ILC TRANSPORT AND INSTALLATION](https://reader036.vdocuments.net/reader036/viewer/2022081604/568161ba550346895dd18ef3/html5/thumbnails/4.jpg)
4
Beam tunnel and service tunnel
Keith Kershaw, EN-HE CERN CES 08 April 2009
![Page 5: ILC TRANSPORT AND INSTALLATION](https://reader036.vdocuments.net/reader036/viewer/2022081604/568161ba550346895dd18ef3/html5/thumbnails/5.jpg)
5
Reason for the (relatively high) height of the ILC cryomodules above the floor (2)
Response from Jerry Leibfritz, FNAL (continued)• The cryogenic feedbox and endcaps are designed for this elevation and it
would have been too expensive for us at Fermilab to redesign this, so we used basically the same design as DESY.
• When we were initially laying out the ILC tunnel, we tried to maximize the use of space, so we set the elevation of the cryomodule to be in the widest part of the diameter of the tunnel, allowing us to move it as close to the wall as possible.
• For a machine as big as the ILC, these components could be redesigned, so the cryomodule sits lower, but it would require some engineering effort.
TRANSPORT NOTE: THE CURRENT BEAM POSITION IS HIGH ENOUGH TO ALLOW THE USE OF TRANSPORT VEHICLES WHICH INCLUDE THEIR OWN TRANSFER CAPABILITY; IT IS THEREFORE INTERESTING TO LEAVE IT WHERE IT IS
Keith Kershaw, EN-HE CERN CES 08 April 2009
![Page 6: ILC TRANSPORT AND INSTALLATION](https://reader036.vdocuments.net/reader036/viewer/2022081604/568161ba550346895dd18ef3/html5/thumbnails/6.jpg)
6
LHC Buggies can move at 180 deg to transport direction
Keith Kershaw, EN-HE CERN CES 08 April 2009
![Page 7: ILC TRANSPORT AND INSTALLATION](https://reader036.vdocuments.net/reader036/viewer/2022081604/568161ba550346895dd18ef3/html5/thumbnails/7.jpg)
7
DESY Dwarsloeper During Transfer (height 1m)
Keith Kershaw, EN-HE CERN CES 08 April 2009
![Page 8: ILC TRANSPORT AND INSTALLATION](https://reader036.vdocuments.net/reader036/viewer/2022081604/568161ba550346895dd18ef3/html5/thumbnails/8.jpg)
8
Access ramps to tunnel
• CLIC• ILC Asian site
Keith Kershaw, EN-HE CERN CES 08 April 2009
![Page 9: ILC TRANSPORT AND INSTALLATION](https://reader036.vdocuments.net/reader036/viewer/2022081604/568161ba550346895dd18ef3/html5/thumbnails/9.jpg)
9
CLIC longitudinal section
Keith Kershaw, EN-HE CERN CES 08 April 2009
![Page 10: ILC TRANSPORT AND INSTALLATION](https://reader036.vdocuments.net/reader036/viewer/2022081604/568161ba550346895dd18ef3/html5/thumbnails/10.jpg)
10
CLIC access ramp tunnel summary
Figures based on CLIC Longitudinal section drawing data.
Access Point Number 11 5 3
upper height (m) 425 395 391
lower height (m) 358.7 350 350
delta h (m) 66.3 45 41
slope (%) 8 7 8
length (m) 829 643 513
Keith Kershaw, EN-HE CERN CES 08 April 2009
![Page 11: ILC TRANSPORT AND INSTALLATION](https://reader036.vdocuments.net/reader036/viewer/2022081604/568161ba550346895dd18ef3/html5/thumbnails/11.jpg)
11Keith Kershaw, EN-HE CERN CES 08 April 2009
![Page 12: ILC TRANSPORT AND INSTALLATION](https://reader036.vdocuments.net/reader036/viewer/2022081604/568161ba550346895dd18ef3/html5/thumbnails/12.jpg)
12Keith Kershaw, EN-HE CERN CES 08 April 2009
![Page 13: ILC TRANSPORT AND INSTALLATION](https://reader036.vdocuments.net/reader036/viewer/2022081604/568161ba550346895dd18ef3/html5/thumbnails/13.jpg)
13Keith Kershaw, EN-HE CERN CES 08 April 2009
![Page 14: ILC TRANSPORT AND INSTALLATION](https://reader036.vdocuments.net/reader036/viewer/2022081604/568161ba550346895dd18ef3/html5/thumbnails/14.jpg)
14
Transport implications of access ramps instead of shafts
Need to consider special vehicles (e.g. cryo-modules) and standard vehicles (e.g. services).
Effect of slope on vehicle design:• Need more traction force (more driven wheels)• Need more braking force (more braked wheels)• Cooling of motors (for long slopes)• Cooling of brakes / motors for braking→Bigger vehicle (integration)
Keith Kershaw, EN-HE CERN CES 08 April 2009
![Page 15: ILC TRANSPORT AND INSTALLATION](https://reader036.vdocuments.net/reader036/viewer/2022081604/568161ba550346895dd18ef3/html5/thumbnails/15.jpg)
15
Some notes on slope effects
Standard electric vehicles • Typically 1.5-2% slope for continuous use at full rated
loadwith increased slope the load capacity or the use factor reduces. (see performance chart)
Encyclopedie de la Manutention• “rampe ≥ 7% = problème délicate” (this is with
unbraked trailers)• Effect of 2% slope is to double traction force needed
compared with horizontal surface.
Keith Kershaw, EN-HE CERN CES 08 April 2009
![Page 16: ILC TRANSPORT AND INSTALLATION](https://reader036.vdocuments.net/reader036/viewer/2022081604/568161ba550346895dd18ef3/html5/thumbnails/16.jpg)
16Keith Kershaw, EN-HE CERN CES 08 April 2009
![Page 17: ILC TRANSPORT AND INSTALLATION](https://reader036.vdocuments.net/reader036/viewer/2022081604/568161ba550346895dd18ef3/html5/thumbnails/17.jpg)
17Keith Kershaw, EN-HE CERN CES 08 April 2009
![Page 18: ILC TRANSPORT AND INSTALLATION](https://reader036.vdocuments.net/reader036/viewer/2022081604/568161ba550346895dd18ef3/html5/thumbnails/18.jpg)
18
Example on effect of slope
• In the example a tractor with a nominal towing capacity of 20 tonnes can be used on a 10% slope to tow a 6 tonne trailer a maximum of 1600m in one hour.
Keith Kershaw, EN-HE CERN CES 08 April 2009
![Page 19: ILC TRANSPORT AND INSTALLATION](https://reader036.vdocuments.net/reader036/viewer/2022081604/568161ba550346895dd18ef3/html5/thumbnails/19.jpg)
19
Other transport/slope experience at CERN
Buggies for LHC warm magnet installation:• Designed for max slope 8%.• During testing on 7% slope (several passes)
overheated after approx 1hour.Special purpose fork lift:• Customized for 14% slope (needed continuous
forced ventilation for brakes and motors)• Difficult to find supplier willing to do this.
Keith Kershaw, EN-HE CERN CES 08 April 2009
![Page 20: ILC TRANSPORT AND INSTALLATION](https://reader036.vdocuments.net/reader036/viewer/2022081604/568161ba550346895dd18ef3/html5/thumbnails/20.jpg)
20
Slope general comments
at this stage:• 1.5 - 2% slope means can use standard vehicles (lowest cost
most reliable solution)• Up to 7 or 8% slope achievable by reducing standard vehicle
capacity to approx one third of nominal (space issues?).• Any steeper slopes will mean that it becomes more difficult
to use standard equipment –this will have cost and reliability implications.
• In any case equipment for installing cryomodules will be specially designed and built - but what about other equipment?
Keith Kershaw, EN-HE CERN CES 08 April 2009
![Page 21: ILC TRANSPORT AND INSTALLATION](https://reader036.vdocuments.net/reader036/viewer/2022081604/568161ba550346895dd18ef3/html5/thumbnails/21.jpg)
21
Discussion - Buggies• The 860mm clearance below cryomodules allows the use of a combined
transport and transfer vehicle such as the LHC buggies.• The LHC buggies were designed for slope of 8% but did overheat after
intensive use on slopes• The transfer using buggies is carried out by rotating the wheels through 90
degrees . The space between ends of LHC warm magnets when being installed is approx 7cm – longitudinal alignment relied on the operators’ skill and care.
• The space between the ends of ILC cryomodules is approx 2cm – this would lead to risk of damage using buggy –type solution relying on operator skill for large numbers (1600) modules unless some additional precise alignment is provided.
• The LHC buggies were used for transporting warm magnets – less delicate than cryomodules.
Keith Kershaw, EN-HE CERN CES 08 April 2009
![Page 22: ILC TRANSPORT AND INSTALLATION](https://reader036.vdocuments.net/reader036/viewer/2022081604/568161ba550346895dd18ef3/html5/thumbnails/22.jpg)
22
Buggy concept adaptation for ILC including access ramps
• The LHC buggies are 560mm high: for ILC the 860mm clearance underneath cryomodules will allow incorporation of cradles, load suspension, additional cooling and precise positioning tables to allow accurate longitudinal alignment during lateral transfer onto jacks.
• Buggy width closer to cryomodule width than outline vehicle shown in ILC cross section (slide 4)
Keith Kershaw, EN-HE CERN CES 08 April 2009
![Page 23: ILC TRANSPORT AND INSTALLATION](https://reader036.vdocuments.net/reader036/viewer/2022081604/568161ba550346895dd18ef3/html5/thumbnails/23.jpg)
23
Next steps
• Next step for CLIC at this stage was small amount of designer work to look into dimensions of vehicle integrated in tunnel and then consider transfer process, as well as vehicle entry into main tunnel .
Keith Kershaw, EN-HE CERN CES 08 April 2009
![Page 24: ILC TRANSPORT AND INSTALLATION](https://reader036.vdocuments.net/reader036/viewer/2022081604/568161ba550346895dd18ef3/html5/thumbnails/24.jpg)
24
CLIC transport
Slides from CLIC workshop in Oct 2008
Keith Kershaw, EN-HE CERN CES 08 April 2009
![Page 25: ILC TRANSPORT AND INSTALLATION](https://reader036.vdocuments.net/reader036/viewer/2022081604/568161ba550346895dd18ef3/html5/thumbnails/25.jpg)
25
Transport envelope in cyan – 1125 x 1150 x 2100Lifting points according to the worst case, i.e. on top of the transport envelope.Intergirder support acceptable assumption for the moment.
R. Nousiainen 04092008Keith Kershaw, EN-HE CERN CES 08 April 2009
![Page 26: ILC TRANSPORT AND INSTALLATION](https://reader036.vdocuments.net/reader036/viewer/2022081604/568161ba550346895dd18ef3/html5/thumbnails/26.jpg)
26Keith Kershaw, EN-HE CERN CES 08 April 2009
![Page 27: ILC TRANSPORT AND INSTALLATION](https://reader036.vdocuments.net/reader036/viewer/2022081604/568161ba550346895dd18ef3/html5/thumbnails/27.jpg)
27
3 cable trays 520mm
2 CV pipes 600mm
2 CV pipes 250mm
Drive beam
Drive beam
Main beam
Main beam
Safe passage
Transport train
Turnaround loop
RIGHT VIEWTYPICAL CROSS SECTION CLIC TUNNEL
Monorail
Keith Kershaw, EN-HE CERN CES 08 April 2009
![Page 28: ILC TRANSPORT AND INSTALLATION](https://reader036.vdocuments.net/reader036/viewer/2022081604/568161ba550346895dd18ef3/html5/thumbnails/28.jpg)
28
3 cable trays 520mm
2 CV pipes 600mm
2 CV pipes 250mm
Drive beam
Drive beam
Main beam
Main beam
Safe passage
Transport train
Turnaround loop
RIGHT VIEWTYPICAL CROSS SECTION CLIC TUNNEL
Monorail
Keith Kershaw, EN-HE CERN CES 08 April 2009
![Page 29: ILC TRANSPORT AND INSTALLATION](https://reader036.vdocuments.net/reader036/viewer/2022081604/568161ba550346895dd18ef3/html5/thumbnails/29.jpg)
29
3 cable trays 520mm
2 CV pipes 600mm
2 CV pipes 250mm
Drive beam
Drive beam
Main beam
Main beam
Safe passage
Transport train
Turnaround loop
RIGHT VIEWTYPICAL CROSS SECTION CLIC TUNNEL
Monorail
Keith Kershaw, EN-HE CERN CES 08 April 2009
![Page 30: ILC TRANSPORT AND INSTALLATION](https://reader036.vdocuments.net/reader036/viewer/2022081604/568161ba550346895dd18ef3/html5/thumbnails/30.jpg)
30
3 cable trays 520mm
2 CV pipes 600mm
2 CV pipes 250mm
Drive beam
Drive beam
Main beam
Main beam
Safe passage
Transport train
Turnaround loop
RIGHT VIEWTYPICAL CROSS SECTION CLIC TUNNEL
Monorail
Keith Kershaw, EN-HE CERN CES 08 April 2009
![Page 31: ILC TRANSPORT AND INSTALLATION](https://reader036.vdocuments.net/reader036/viewer/2022081604/568161ba550346895dd18ef3/html5/thumbnails/31.jpg)
31
3 cable trays 520mm
2 CV pipes 600mm
2 CV pipes 250mm
Drive beam
Drive beam
Main beam
Main beam
Safe passage
Transport train
Turnaround loop
RIGHT VIEWTYPICAL CROSS SECTION CLIC TUNNEL
Monorail
Keith Kershaw, EN-HE CERN CES 08 April 2009
![Page 32: ILC TRANSPORT AND INSTALLATION](https://reader036.vdocuments.net/reader036/viewer/2022081604/568161ba550346895dd18ef3/html5/thumbnails/32.jpg)
32
Shaft
Jonction chamberwith shielding
Loading area
Maintenance area
Services area
10t Crane
Based on Civil Engineering drawings prepared in 2007
Proposal for module lowering and tunnel access
Keith Kershaw, EN-HE CERN CES 08 April 2009
![Page 33: ILC TRANSPORT AND INSTALLATION](https://reader036.vdocuments.net/reader036/viewer/2022081604/568161ba550346895dd18ef3/html5/thumbnails/33.jpg)
33
Asian site
Keith Kershaw, EN-HE CERN CES 08 April 2009