ilembe district municipality - sahris
TRANSCRIPT
ILEMBE DISTRICT MUNICIPALITY
ILembe House, 59/61 Mahatma Ghandi Road, KwaDukuza, South Africa, 4450
12 Haysom Road, Ilembe District Municipality, KwaDukuza, South Africa, 4450
Tel: +27 (0)32 551 8776
Cell:+27(0)83 950 0770
www.ilembe.gov.za
LOWER THUKELA BULK WATER
SUPPLY SCHEME OFFTAKES 7 & 8
CONSTRUCTION METHOD
STATEMENT
|Office 1B Deodant Building |10 Payne Street, Pinetown, 3600 |
|Tel: (031) 701 1038 | Fax: (031) 701 0963|
|E-mail : [email protected] | Website : www.vumesa.co.za|
DESIGN REPORT
Project No. TBC “LOWER THUKELA BULK WATER SUPPLY SCHEME OFFTAKES 7 & 8
Page 1 of 8
Prepared by
VUMESA (PTY) LTD
Office 1B Deodant Building,10 Payne Street Pinetown, 3600
Prepared for
ILEMBE DISTRICT MUNICIPALITY
12 Haysom Road, Ilembe District Municipality,
KwaDukuza, South Africa, 4450
Issue/revision Issue 1 Revision
Remarks CONSTRUCTION METHODOLOGY
Date 09 OCTOBER 2017
Prepared by SENZIWE MNGADI
Contact 031 701 1038
Signature
Date
Checked by SABELO XHAKAZA
Signature
Date
Authorised by MELUSI NDLOVU
Signature
Date
Project number
File reference LOWER THUKELA BULK WATER SUPPLY SCHEME
OFFTAKES 7 & 8
DESIGN REPORT
Project No. TBC “LOWER THUKELA BULK WATER SUPPLY SCHEME OFFTAKES 7 & 8
Page 2 of 8
EXECUTIVE SUMMARY
A reliable supply of clean and safe water is the first and most critical municipal service that people require, Ilembe
District Municipality.
The success in land acquisition from privately owned properties will assist in the success of the project.
The projects has been divided into three projects as follows:
Project 1: Construction of Offtake 7 which consist of (450mmØ pipeline and 5Ml concrete reservoir)
Project 2: Construction of Offtake 8e, 2 Ml concrete reservoir and Pump station ( Offtake 8f (350mmØ)
Project 3 : Construction of Offtake 8f and 9 ( Offtake 8f 350mmØ and 250mmØ and offtake 9 350mmØ)
The total cost for the project is R 129 336 202.46
DESIGN REPORT
Project No. TBC “LOWER THUKELA BULK WATER SUPPLY SCHEME OFFTAKES 7 & 8
Page 3 of 8
ABBREVIATIONS
IDM : Ilembe District Municipality
LTBWSS : Lower Thukela Bulk Water Supply Scheme
NCSS : North Coast Supply System
DWS : Department of Water and Sanitation
EPWP : Expanded Public Work Programme
DWS : Department of Water & Sanitation
CLO : Community Liaison Officer
COGTA : Department of Corporate Governance & Traditional Affairs
DOT : Department of Transport
DOE : Department of Energy
DOH : Department of Health
DPW : Department t of Public Works
SANRAL : South African National Roads Agency Limited
WSA : Water Services Authority
WSP : Water Services Provider
MIG : Municipal Infrastructure Grant
RBIG : Regional Bulk Infrastructure Grant
SCM : Supply Chain Management
SLA : Service Level Agreement
IDP : Integrated Development Plan
WSDP : Water Services Development Plan
WULA : Water Utilisation Licence Application
ROD : Record of Decision
EMP : Environmental Management Plan
EIA : Environmental Impact Assessment
PMU : Project Management Unit
ISD : Institutional Social Development
MHS : Manager Health & Safety
Pr Tech Eng : Professional Technologist: Engineering
Pr Eng : Professional Engineer
SG : Surveyor General
PSC : Project Steering Committee
OHS : Occupational Health & Safety
O&M : Operations & Maintenance
Vumesa : Vumesa (Pty) Ltd
DESIGN REPORT
Project No. TBC “LOWER THUKELA BULK WATER SUPPLY SCHEME OFFTAKES 7 & 8
Page 4 of 8
Table of Contents EXECUTIVE SUMMARY .............................................................................................................................................. 2
ABBREVIATIONS .......................................................................................................................................................... 3
1. Introduction ........................................................................................................................................................... 5
2. Planning of Pipelines ........................................................................................................................................... 5
3. Planning of River/Stream and Wetland Crossings ...................................................................................... 7
4. Construction Methodology ................................................................................................................................ 7
5. Conclusion .............................................................................................................................................................. 8
DESIGN REPORT
Project No. TBC “LOWER THUKELA BULK WATER SUPPLY SCHEME OFFTAKES 7 & 8
Page 5 of 8
1. Introduction
This report note covers the generic design and construction considerations and parameters for
project Lower Thukela Bulk Water Supply Scheme Offtakes 7 & 8. The project consist
construction of:
New 450mm Diamater Class 12 to 16 oPVC 3.1km Long Gravity Main Pipeline (Offtake
7).
New 250mm Diameter Class 12 to 16 uPVC 2.2km Long Bulk Portable Water Gravity
Pipeline to New Guilderland.
New Bulk Portable Water Storage, 5ML Steel Reinforced 35Mpa Concrete Reservoir in
Blythdale West
New 350mm Diamater Class 12 to 16 uPVC 4km Long Gravity Main Pipeline
(Offtake 8e). New Bulk Portable Water Storage, 2ML Steel Reinforced 35Mpa Concrete Reservoir in
Groutville, Ethembeni
15ML Brick and Reinforced Concrete Pump Station at the existing 2 and 2.5ML (4,5ML)
UMvoti Balancing Reservoirs
New 300mm Diamater Class 12 to 16 uPVC 1.5km Long Gravity Main Pipeline (Offtake
8f).
New 250mm Diamater Class 12 to 16 uPVC 0.8km Long Gravity Main Pipeline (Offtake
8f)
New 350mm Diamater Class 12 to 16 uPVC 1.5km Long Gravity Main Pipeline (Offtake
9)
All pipes will be laid, as far as is possible, in the existing pipeline servitudes, road reserves and
also in privately owned land where omnibus servitudes have been provided and on property
boundaries.
Pipelines will be laid in trenches and backfilled to natural ground level except in the stream
crossing. The overall layout is as shown in Annexure A.
2. Planning of Pipelines
In the planning for the design phase of the pipelines, cognisance was taken of the following
reference documents;
I. Red Book – Guidelines for Human Settlement Planning and Design;
II. SABS 1200 – Standardised Specification for Civil Engineering Construction;
III. Ilembe District Municipality standards.
When planning or designing the pipelines, a holistic approach that adheres to all the tenets of
the reference or policy documents listed above was adopted. The environmental sensitivity of
wetland and sensitive areas was acknowledged, and designs took full cognisance of the proposed
impact to these areas.
DESIGN REPORT
Project No. TBC “LOWER THUKELA BULK WATER SUPPLY SCHEME OFFTAKES 7 & 8
Page 6 of 8
The approach to design and construction will encompass the following;
Appropriate and adequate protection of existing manmade and natural structures such
as buildings, fences, river banks, etc. in the vicinity of the pipelines will be incorporated
into the design.
Existing fences will be maintained as far as is possible, but if not possible will be
temporarily removed and reinstated to the same or better condition. The time taken
will be kept to a minimum and where necessary temporary fencing will be erected to
maintain the level of security to the effected properties.
Where crossing or running alongside river or stream courses, the existing river/stream
bank structure will be maintained to reduce disturbance to the river flow.
Where the pipeline crosses stormwater channels it has been designed to have no
impact on normal stormwater flow in that all pipes and concrete casing will be buried
at least 500mm below natural channel level in the case of soft material, and level with
reno- mattress in the case of hard rock material.
In the case of sewer and stormwater pipelines, manholes will be provided at all
changes in grade and direction and at intervals not exceeding 80m to facilitate
maintenance during the lifetime of the pipelines.
DESIGN REPORT
Project No. TBC “LOWER THUKELA BULK WATER SUPPLY SCHEME OFFTAKES 7 & 8
Page 7 of 8
3. Planning of River/Stream and Wetland Crossings
In the planning for the design phase of the pipe crossing, cognisance is taken of the
following reference documents;
Red Book – Guidelines for Human Settlement Planning and Design;
SABS 1200 – Standardised Specification for Civil Engineering Construction;
Local municipal standards.
When planning or designing the pipe crossing, a holistic approach that adheres to all the
tenets of the reference or policy documents listed above will be adopted. The
environmental sensitivity of wetland areas is acknowledged and designs undertaken will
take full cognisance of the proposed impact to these areas.
This includes the impact on all, or any, matters relating to water quality, flooding,
agricultural drainage, erosion, flora and fauna and any adjacent topographical features.
The approach to design and construction will encompass the following;
Appropriate and adequate protection of the river/stream/wetland banks in the
vicinity of the pipeline will be incorporated into the design.
The existing river/stream bank structure will be maintained to reduce disturbance
to the river/stream flow.
Wherever possible, the pipelines will cross river/stream and wetlands within a
road prism.
The pipe crossings have been designed to have no impact on normal river/stream
flow.
Where pipes are laid through a flood plain (1 : 100 year flood line), a minimum
cover level of 1 metre will be maintained.
4. Construction Methodology
Construction methodology will differ slightly depending on the nature of the river/stream
or wetland being crossed. Perennial streams will require the temporary diversion of water
flow during construction, whereas non-perennial streams may not require flow diversion
depending on the season.
4.1 A typical construction sequence is summarised hereunder:
Conduct a competent site investigation to build up an informed picture of the
task.
Conduct a topographical survey of the pipeline route.
Adequate design of all the stages of construction.
All Environmental and Health and Safety requirements and good practice to be
adhered to.
DESIGN REPORT
Project No. TBC “LOWER THUKELA BULK WATER SUPPLY SCHEME OFFTAKES 7 & 8
Page 8 of 8
4.2 Plant and Resources required for the Construction may include, inter alia:
Excavators;
Crane of sufficient lifting capacity and reach for pipe laying (if required);
Tipper trucks for the delivery of bedding material;
Compaction equipment;
Pneumatic breakers (if required);
On-site concrete batching plant (if required);
Concrete delivery vehicles for wet concrete;
Formwork, reinforcing steel and the necessary equipment and tools for assembly;
Equipment for the construction of concrete ring manholes and concrete
encasement of pipes.
4.3 Construction Method for Pipes laid in Trenches:
This method will be used where pipes are conventionally laid in trenches and backfilled to
natural ground level.
Remove topsoil and stockpile for later use.
Excavate trench for pipeline to the design level.
If the material is firm normal excavation techniques will apply. In soft material
shoring of the trench sides may be required. In hard rock material trench
excavation may require the use of pneumatic breakers or blasting.
Install temporary dewatering pumps to keep the excavation dry (if required due
to groundwater ingress).
Construct stormwater diversion berms where required.
Place concrete to encasement if required. The top level will be determined by the
stormwater channel level.
Place bedding, lay pipe, place and compact selected fill over the pipeline.
Construct manholes, where required. Manholes will be constructed along the
pipeline route at changes in grade and direction.
Backfill to specification.
Dress backfill, topsoil and re-vegetate all exposed areas.
5. 5. Conclusion All design and construction work will be carried out in accordance with the relevant
construction
specifications and in compliance with the Construction Health and Safety Specifications as
well as
the Construction Environmental Management Plan. Internal surface joints in the floor and
wall are to be sealed using the bandage system Roof joints (top and sides) are to be sealed
using self-adhesive aluminium foil strips and ferrule holes sealed with an approved latex
compound).