im one stop centre-city hall of kuala lumpur
TRANSCRIPT
One Stop Centre
City Hall of Kuala Lumpur
Dr Ibrahim MohdUniversity of Malaya
Outline of Presentation
•Background•Background
•Why the need for an OSC
•What is an OSC, functions and value proposition
•Diffusing the OSC concept
•OSC processes•OSC processes
•Effectiveness of OSC
•Key Actors
Background
•Building/Planning approvals - a •Building/Planning approvals - a
legal requirement in all states of
Malaysia (Act 172; Act 267);
•Defines who can submit
applica&ons (Act 133);
•Such approvals have been •Such approvals have been
criticized for being very slow
Processing Applications: Why we
need a new approach
Deficiencies of existing processDeficiencies of existing process
Stage process
Delays in
approval (lead to
increase in
development
Weak tracking
of applications development
costs)
Responding to the situation
Ministry of Housing and Local Government Ministry of Housing and Local Government
initiated efforts to address this perennial
problem. Idea of one stop centre emerged
Idea was discussed with all relevant parties
– local authorities, State governments,
developers and professional bodies –developers and professional bodies –
before Cabinet approval was obtained in
2004
What is a One Stop Centre
Provision of dedicated
services involving
multiple agencies
through a single centre
Models of successful one stop centres
through a single centre
Why the One Stop Centre is an
Innovation
Old System
• The old system allows
New System
• All related authorities • The old system allows
all authorities related to
land development to
exercise their duties
and to take their own
timeframes individually.
• All related authorities
are being coordinated
and closely monitored
by an appointed agency
though they continue to
exercise their timeframes individually. exercise their
prerogative powers
individually.
OSC Function
• To coordinate the applications
for: OSC for for:
- planning permissions,
-building plan approvals and,
-Land Conversion, Subdivision
and Amalgamation;
with the main objective of
OSC for building approvals different from OSC for paying bills
with the main objective of
reducing time consumed in
approval process.
Value Proposition of OSC
Overcoming
Delays Reduction in
Development Costs
Sense of
OwnershipDelays
• Planning Permission
• Land matters: amalgamation, subdivisions, change of category or conditions
• Less transactions
Ownership
• All agencies feel responsible for processing of applications
conditions
• Building plan and Earth Works
Key Actors in Building approvals
Federal Govt (5 yr
Plans)
Ministries
State Govt
Local Authority
Technical
Agencies
Housing
Developer
Diffusing the OSC concept
• The first establishment of OSC secretariat was • The first establishment of OSC secretariat was
in Ampang Jaya Municipal Council in Selangor,
• MHLG monitored the performance of the OSC
and presented report to Cabinet in 2007,
• Since then, all local authorities in Peninsular • Since then, all local authorities in Peninsular
Malaysia have established the OSC
Implementing the Innovation:
OSC Process
• All the three applications must be submitted to
OSCOSC
• OSC distributes applications to respective
technical departments and monitoring the
progress of that department concerned. Technical
departments are given 14 days to deliver their
comments to applications located within an area comments to applications located within an area
of having a local plan and 40 days for applications
within areas of not having local plans
The Approval Process
• Submission– The OSC will only a complete submission – based on its checklist
• Comments• Comments– The OSC will distribute the copies of plans and related documents to technical
bodies including related ‘in-house’ departments and monitor the respective application
• Site Visit– Site visit will be arranged to investigate the characteristics of the site to ensure
that the requirements are complied or can be complied.
• Consideration– The OSC will table the application to the OSC meeting when all the technical
comments were ready. The technical department representatives are also comments were ready. The technical department representatives are also sitting in the meeting.
• Approval– Decisions from the OSC meeting will be released to the applicant with or
without conditions.
4 Months Process
6 months process
Concurrent Application
• Alterna&ve 1
– 4 applica&ons: land maAers, DO, Bldg Plan, – 4 applica&ons: land maAers, DO, Bldg Plan, Earthwork
• Alterna&ve 2
– 3 applica&ons: land maAers, DO, Bldg Plan or
– 3 applica&ons: DO, Bldg Plan, Earthwork
• Alterna&ve 3• Alterna&ve 3
– 2 applica&ons: combina&on of two among the above plans
Effectiveness of OSC
Time Taken Percent Time Taken Percent
Less than 4 months
(16 weeks)65
More than 4 months
(16 weeks)35
(16 weeks)
Total 100.0
Key Actors
• Applicants (Developers, Land Owners or their
Agents)Agents)
• The OSC Officers
• Technical Department officers
• Decision Makers (Lord Mayors)
• MHLG - officers• MHLG - officers
Dr Saffiah will elaborate on the e-submission