impact identification, assessment and mitigation · pdf fileproposed natural gas pipeline to...

59
PROPOSED NATURAL GAS PIPELINE TO SERVE THE SEATON LAND DEVELOPMENT: ENVIRONMENTAL REPORT Impact Identification, Assessment and Mitigation March 8, 2016 4.0 IMPACT IDENTIFICATION, ASSESSMENT AND MITIGATION 4.1 METHODOLOGY The potential effects and impacts of the Project on physical, biophysical and socio-economic features have been assessed along the preferred pipeline route. With an understanding of pipeline construction and operation activities (see Sections 4.1.1 and 4.1.2), the assessment: Describes the environmental and socio-economic setting along the preferred pipeline route; Predicts the effects and associated impacts of construction and operation activities; Recommends supplemental studies, mitigation and protective measures (including construction methods and timing, site-specific mitigation, environmental protection measures, and compensation measures); and Outlines the net impacts that are likely to remain. Environmental and socio-economic effects have been avoided or reduced to the extent feasible through the route selection process, or will be addressed through the methods listed above. Predicting effects and impacts, and determining supplemental studies, mitigation and protective measures, takes into account concerns expressed through the consultation program, published information available from literature, maps and digital data, mitigation guidance documents, field assessments, and the previous pipeline development experience of Enbridge. By necessity, the analysis, integration and synthesis of the data are an iterative process since information becomes available at various stages of the study and at different mapping scales. The level of detail of data and mapping increases as the study moves from analysis of the routing Study Area, to analysis of alternate routes, and, finally, to a site-specific survey of features along the preferred pipeline route. The data available at the current stage of the environmental study were appropriate for selecting a preferred pipeline route, identifying effects, and developing mitigation and protective measures. There are instances where field investigations are recommended along the preferred pipeline route before construction. Given the experience of Stantec in providing environmental services for hydrocarbon pipelines, and the knowledge gained of the Project location from Enbridge, these supplemental studies are not anticipated to change the conclusions regarding potential adverse residual impacts identified in Sections 4.2-4.4 of the ER. The environmental and socio-economic information presented in Sections 4.2-4.4 of the ER is based on available information cited throughout. 4.1

Upload: dinhbao

Post on 06-Mar-2018

216 views

Category:

Documents


2 download

TRANSCRIPT

PROPOSED NATURAL GAS PIPELINE TO SERVE THE SEATON LAND DEVELOPMENT: ENVIRONMENTAL REPORT

Impact Identification, Assessment and Mitigation March 8, 2016

4.0 IMPACT IDENTIFICATION, ASSESSMENT AND MITIGATION

4.1 METHODOLOGY

The potential effects and impacts of the Project on physical, biophysical and socio-economic features have been assessed along the preferred pipeline route. With an understanding of pipeline construction and operation activities (see Sections 4.1.1 and 4.1.2), the assessment:

• Describes the environmental and socio-economic setting along the preferred pipeline route;

• Predicts the effects and associated impacts of construction and operation activities;

• Recommends supplemental studies, mitigation and protective measures (including construction methods and timing, site-specific mitigation, environmental protection measures, and compensation measures); and

• Outlines the net impacts that are likely to remain.

Environmental and socio-economic effects have been avoided or reduced to the extent feasible through the route selection process, or will be addressed through the methods listed above.

Predicting effects and impacts, and determining supplemental studies, mitigation and protective measures, takes into account concerns expressed through the consultation program, published information available from literature, maps and digital data, mitigation guidance documents, field assessments, and the previous pipeline development experience of Enbridge. By necessity, the analysis, integration and synthesis of the data are an iterative process since information becomes available at various stages of the study and at different mapping scales. The level of detail of data and mapping increases as the study moves from analysis of the routing Study Area, to analysis of alternate routes, and, finally, to a site-specific survey of features along the preferred pipeline route. The data available at the current stage of the environmental study were appropriate for selecting a preferred pipeline route, identifying effects, and developing mitigation and protective measures.

There are instances where field investigations are recommended along the preferred pipeline route before construction. Given the experience of Stantec in providing environmental services for hydrocarbon pipelines, and the knowledge gained of the Project location from Enbridge, these supplemental studies are not anticipated to change the conclusions regarding potential adverse residual impacts identified in Sections 4.2-4.4 of the ER. The environmental and socio-economic information presented in Sections 4.2-4.4 of the ER is based on available information cited throughout.

4.1

PROPOSED NATURAL GAS PIPELINE TO SERVE THE SEATON LAND DEVELOPMENT: ENVIRONMENTAL REPORT

Impact Identification, Assessment and Mitigation March 8, 2016

4.1.1 Construction

The pipeline construction process includes various activities as described below and will be undertaken in accordance with Enbridge’s Construction and Maintenance Manual, 2015 or the applicable construction and maintenance manual in effect at the time construction commences. :

1. Site Preparation: The first crew to enter the construction site is typically the survey and staking crew who delineate the boundaries of the road allowance. Safety fence is installed at the edge of the construction road allowance where public safety considerations are required, and aspects of the traffic management plan are implemented (i.e., signs, vehicle access);

2. Clearing: The clearing crew clears brush and other vegetation on the road allowance (including the TWE) to permit construction of the pipeline;

3. Grading and Stripping: Next, the grading crew prepares the road allowance for access by construction equipment. At this stage, the topsoil (on agricultural lands) or the duff layer (on natural lands) is stripped by bulldozers and graders then segregated so it will not be mixed with the subsoil later removed from the trench. Existing landscaping is also removed and dewatering undertaken, where necessary;

4. Stringing: The stringing crew lays pipe on wooden skids adjacent to the trench area;

5. Trenching: Once the road allowance has been graded, a hydraulic hoe will excavate the trench for the installation of the new pipeline. Laneways and trails are left over the trench as long as feasible where requested by the landowner;

6. Pipe Fabrication and Lowering: Next, the pipe is bent as required and the welding crew welds the pipe into continuous lengths. The pipe welds are x-rayed and coated then inspected before the pipeline is lowered into the trench. Crews also install pipes under obstacles such as roads or watercourses by directional drilling. The welds are global positioning system located with locations identified on the weld map along with the identification of each pipe section for future identification;

7. Backfilling: The backfilling crew backfills the originally excavated subsoil over the pipe in the trench. In shallow water table areas the pipeline may be weighted to provide negative buoyancy. Surplus backfill material will be removed from the road allowance. The trench line will be crowned to allow for soil settlement;

8. Hydrostatic Test: The pipeline is then tested hydrostatically according to procedures outlined in Enbridge’s Construction and Maintenance Manual, 2015 (Section 23.6, Mains, Hydrostatic Tests). Water is drawn from a suitable local source based on discussions with the appropriate authorities and will be disposed of appropriately (e.g., discharged to land or sanitary sewer, or removed by an Enbridge approved waste disposal provider). Upon completion of the hydrostatic testing, the pipeline is dried, purged of air and prepared for delivery of the product; and

9. Clean-Up and Restoration: The clean-up crew is responsible for the restoration of the RoW and other work areas. In natural areas the clean-up crew undertakes restoration including re-seeding of the RoW and restoring ditch banks, watercourse crossings and wetland areas, and removing erosion and sediment controls. In developed areas the clean-up crew undertakes landscaping plans developed for site restoration.

4.2

PROPOSED NATURAL GAS PIPELINE TO SERVE THE SEATON LAND DEVELOPMENT: ENVIRONMENTAL REPORT

Impact Identification, Assessment and Mitigation March 8, 2016

4.1.2 Operation and Maintenance

Upon completion of the Project, the Project components will be transferred to Enbridge’s operations for inclusion in the existing Pipeline Integrity Program. Enbridge has procedures in place to inspect and maintain the pipeline, including RoW inspection. Enbridge’s’ Pipeline Integrity team has extensive technical, operational, and industry knowledge, and whose members remain current with industry practices. Detailed procedures and programs will be modified to include the new pipeline and to ensure the operation and maintenance activities for the Project comply with applicable provincial and federal legislation, regulations and guidelines.

Pipeline operation consists of monitoring and regulating the gas flowing through or being stored in the pipeline. Valves will serve to shut off and isolate the pipeline for maintenance and security purposes. Above-ground facilities at the tie in point will include a district station that will regulate the pressure of the pipeline.

4.2 PHYSICAL FEATURES

4.2.1 Bedrock Geology and Drift Thickness

The Paleozoic geography of the Study Area indicates that the bedrock underlying the Study Area is from the Blue Mountain Formation (MNDM, 2007). The Blue Mountain formation is comprised of dark blue-grey to brown to black shale, with thin interbeds of limestone or calcareous siltstone. Drift thickness is generally between 10-50 m below grade in the area with some isolated areas of shallower bedrock. Bedrock is not anticipated to be encountered during construction of the preferred pipeline.

Potential Impacts

The current path of the HDD under Ganatsekiagon and Urfé Creeks indicates that the drill will pass through silt and silty sand at a depth of approximately 10 m (Stantec, 2015) and any excavations required for the project (tie-ins etc.) will typically be less than 5 m deep. Contact with bedrock is not expected; therefore, impacts relating to the bedrock are not expected. No significant impacts to bedrock resources are anticipated.

Mitigative/Protective Measures

No impacts related to bedrock are anticipated. Mitigation measures to protect bedrock are not required.

4.3

PROPOSED NATURAL GAS PIPELINE TO SERVE THE SEATON LAND DEVELOPMENT: ENVIRONMENTAL REPORT

Impact Identification, Assessment and Mitigation March 8, 2016

4.2.2 Physiography & Surficial Geology

The Study Area is located in a transition area between the Iroquois Plain and South Slope physiographic regions of Southern Ontario (Chapman and Putnam, 1984). This area consists of a drumlinized till plain consisting of clay silty to sandy silt tills transitioning to the southeast into glaciolacustrine deposits consisting of sand, gravelly sand and gravel; near shore and beach deposits (Barnett et al., 1991). The topography is undulating with steep slopes in some locations. As discussed in Section 4.2.1, overburden deposits in the area are generally 10 to 50 m thick.

Potential Impacts

Due to the undulating topography and presence of coarser textured soils, there are potential erosion impacts to surficial geology.

Mitigative/Protective Measures

Slope stabilization and erosion controls for slopes will be required on the Project area, particularly in those areas proximal to watercourses and other drainage features. In addition to mitigation measures outlined in Enbridge’s Construction and Maintenance Manual, 2015 (Sections 8.0, Excavating) standard erosion and sediment control measures are discussed in Section 4.2.5 and erosion and sediment controls specific to protecting watercourses, etc. from sedimentation resulting from rainfall events during construction are discussed in Section 4.3.1.

Net Impacts

With the implementation of the above mitigation and protective measures, no significant adverse residual impacts on or from physiography and surficial geology are anticipated.

4.2.3 Groundwater

According to TRCA’s Watershed Plan for Duffins Creek and Carruthers Creek (2003), the Study Area is located in the Duffins watershed which includes the physiographic regions referred to by Chapman and Putnam (1984) as the Oak Ridges Moraine, the South Slope and the Lake Iroquois shoreline. The preferred pipeline route is situated approximately 7 km south of the Oak Ridges Moraine at the borderline between the South Slope and Lake Iroquois. It is characterized by upper, middle, and lower aquifer systems in overburden material overlying shale bedrock of the Georgian Bay Formation. The overburden is mainly composed of glaciolacustrine deposits consisting of sand, gravelly sand and gravel; near shore and beach deposits (Barnett et al., 1991).

A review of the Watershed Plan for Duffins Creek and Carruthers Creek (TRCA, 2003) suggests that the bedrock groundwater quality is of poor quality with elevated levels of sodium and sulphate. The overburden groundwater quality is of relatively good quality for domestic use with

4.4

PROPOSED NATURAL GAS PIPELINE TO SERVE THE SEATON LAND DEVELOPMENT: ENVIRONMENTAL REPORT

Impact Identification, Assessment and Mitigation March 8, 2016

minor occurrences of naturally high hardness and iron concentrations and some localized elevated levels above drinking water criteria for nitrates and chloride.

The municipal water system for Pickering obtains its water supply from Lake Ontario. As a result, no Well Head Protection Areas (WHPAs) are mapped in the vicinity of the Study Area. The closest WHPA is located in Whitchurch-Stouffville, approximately 14 km north west of the preferred pipeline. The nearest Intake Protection Zone (IPZ) is located in Ajax, approximately 10 km south of the preferred pipeline and it does not extend to the Study Area. As such, there are no concerns with respect to WHPAs or IPZs due to the proposed Project.

Aquifer vulnerability in the Study Area was mapped by the TRCA as medium to high (TRCA, 2009). Significant groundwater recharge in the Duffins Creek watershed occurs through most of the area including south of the Oak Ridges Moraine (TRCA, 2003).

MOECC water well records (WWRs) were reviewed within 500 m of the preferred pipeline route to get a better understanding of the hydrogeology of the Study Area. The review indicates that there are a total of fifty five (55) wells within the Study Area. Nineteen (19) of the fifty five (55) wells are domestic supply wells, and four (4) wells are used for commercial, industrial, public and irrigation purposes. The remaining wells are either identified as abandoned, observation wells, test holes, recharge wells or unknown.

Installation details of the private wells were available from the MOECC WWRs for two (2) of the nineteen (19) domestic water supply wells. Well records indicate that these private wells were screened within confined sand material at depths of 20 m and 50 m below ground surface (BGS), with thick clay confining units.

Given that well installation details were available for only two (2) of the nineteen (19) private wells, a private well survey may be conducted to identify potential private wells within 100 m of the preferred pipeline route that could be affected by the construction activities.

Hydrostatic Testing and Dewatering/Sand-pointing

A hydrostatic test will be undertaken for the NPS 6 XHP section of the pipeline before commissioning. Water required for the test will be obtained from a suitable local source based on discussions with the appropriate authorities. When the hydrostatic test is complete, the water will be will be disposed of appropriately (e.g., discharged to land or sanitary sewer, or removed by an Enbridge approved waste disposal provider).

Where trenches encounter shallow groundwater conditions or following a large precipitation event, removing water from the trench (known as dewatering) may be necessary.

During trench dewatering, discharge water will potentially be released to the environment. An uncontrolled discharge of water could cause downstream flooding, erosion, sedimentation or contamination.

4.5

PROPOSED NATURAL GAS PIPELINE TO SERVE THE SEATON LAND DEVELOPMENT: ENVIRONMENTAL REPORT

Impact Identification, Assessment and Mitigation March 8, 2016

Private Water Supply

Nineteen (19) private wells within 500 m of the proposed pipeline were identified based on the MOECC WWRs. The installation details and current status of many of these wells are not known. Groundwater quality and quantity may be impacted by construction activities affecting water supply to residents if their wells are nearby, shallow and installed within a recharge zone.

Municipal Water Supply

There are no municipal groundwater supply wells in the vicinity of the preferred pipeline route. The Study Area does not extend through any WHPA or IPZ. No mitigation measures are required with respect to municipal supply.

Mitigation and Protective Measures

Hydrostatic Testing and Dewatering/Sand-pointing

A Permit to Take Water (PTTW) will be required from the MOECC should the volume withdrawn from a natural source exceed 50,000 L/day. The initial application would include an assessment of the capacity of the source to provide the required water without impacting the ecosystem. Recommendations for mitigation measures such as screened water intakes to limit intake of debris and organisms would also be considered.

To reduce the potential for erosion and scouring at discharge locations, energy dissipation techniques should be used. Discharge piping should be free of leaks and should be properly anchored to prevent bouncing or snaking during surging. Protective measures may include dewatering at low velocities, dissipating water energy by discharging into a filter bag or equivalent, and utilizing protective riprap or equivalent. If energy dissipation measures are found to be inadequate, the rate of dewatering should be reduced or dewatering discontinued until satisfactory mitigation measures are in place. Discharge should be monitored to make sure that no erosion or flooding occurs.

To assess the potential for introduction of contaminated water to soils or bodies of water, testing of hydrostatic discharge water and trench dewatering should be considered. Testing requirements can be influenced by the nature and quality of the source water used, any additives to the test water, the nature of the pipeline and pipeline contents. An environmental consultant should be consulted to determine what testing is necessary for the discharge water.

4.6

PROPOSED NATURAL GAS PIPELINE TO SERVE THE SEATON LAND DEVELOPMENT: ENVIRONMENTAL REPORT

Impact Identification, Assessment and Mitigation March 8, 2016

Private Water Wells

A private well survey should take place to assess domestic groundwater use within 100 m of the preferred pipeline and a private well monitoring program may be recommended for residents who rely on groundwater supply for domestic use.

Net Impacts

With the implementation of the above mitigation and protective measures, no significant adverse residual impacts on groundwater are anticipated.

4.2.4 Extractive Resources

Correspondence from the MNDM (dated December 16, 2015, see Appendix B5) indicated that based on a review of their databases there are no known mineral occurrences within 1 km of the Study Area and no assessment files for any reported mineral exploration activity in the Study Area. Additionally, it was determined that there is low metallic mineral potential for the Study Area (with maximum value of 18.6).

The City of Pickering Official Plan (2010) does not identify any significant mineral aggregate resources within the Study Area. Commercial construction and rock crushing operations are located north of Taunton Road and west of Sideline 16 and east of Sideline 16 south of Concession Road 5.

Aggregate resources, which may be required during construction of the preferred pipeline, are available from sand and gravel operators that supply aggregate in the area.

Potential Impacts

Due to the absence of significant extractive resources in the Study Area no impacts are anticipated.

Mitigative/Protective Measures

No impacts related to extractive resources are anticipated. Given the distance of the commercial construction/rock crushing operations from the road no impacts to these operations is anticipated. Mitigation measures to protect extractive resources are not required.

4.7

PROPOSED NATURAL GAS PIPELINE TO SERVE THE SEATON LAND DEVELOPMENT: ENVIRONMENTAL REPORT

Impact Identification, Assessment and Mitigation March 8, 2016

4.2.5 Soil and Soil Capability

The northwest portion of the Study Area consists of Milliken and Woburn loam soils derived from till parent material. The south east portion of the Study Area is dominated by the coarser textured shallow glaciolacustrine Brighton and Tecumseh sandy loams. Bottom land alluvial soils are found along and adjacent to the watercourses (Soil Survey of Durham County, 1946). In the Study Area, the Milliken and Woburn soils have a CLI rating of 1 and the Brighton and Tecumseh soils a CLI rating of 2. The stony phase of the Brighton soil has a CLI rating of 3. Bottom land soils have a CLI rating of 5.

Potential Impacts

The Project will be largely confined to an existing road allowance where the preferred pipeline will be installed. Though the proposed infrastructure will impact a very limited amount of agricultural land, there is the potential to impact agricultural soils as a result of the need to accommodate a 5 m wide TWE. Excessive heavy equipment traffic can damage topsoil to the point of greatly diminished productivity. Soil characteristics relating to the potential for damage include: moisture content, texture, organic matter content.

Soils can be susceptible to rutting and compaction which can severely reduce agricultural productivity. An increase in moisture levels in these soils further increases the susceptibility to compaction damage.

Additionally, careless topsoil stripping, topsoil storage and topsoil replacement can result in unnecessary mixing of topsoil and subsoil that can also reduce soil productivity.

During construction, soils with no vegetative cover are more prone to erode. This can result in soil erosion from water and wind. Soil susceptibility to water erosion depends on a number of variables, including: intensity and duration of rainfall events, antecedent soil moisture, surface soil cover, slope, soil texture, soil structure and organic matter content. Similarly, the susceptibility of soils to wind erosion depends on wind speed, surface soil cover, soil texture, soil structure and organic matter levels. Water and wind erosion both can result in a significant loss of topsoil.

Mitigative/Protective Measures

In addition to the soil erosion mitigation measures outlined in Enbridge’s Construction and Maintenance Manual, 2015 (Section 8.3, Topsoil Handling) the following measures are recommended:

• To avoid loss of soil, topsoil from lands directly affected by construction of the pipeline should be stripped. That topsoil should be stripped during dry soil conditions and stockpiled for use during clean-up and rehabilitation. Identification of the topsoil and subsoil interface should be carefully monitored to ensure that all topsoil with limited subsoil is stripped from the easement. To reduce construction impacts associated with wet climatic conditions, the

4.8

PROPOSED NATURAL GAS PIPELINE TO SERVE THE SEATON LAND DEVELOPMENT: ENVIRONMENTAL REPORT

Impact Identification, Assessment and Mitigation March 8, 2016

other components of the construction are recommended to occur during dry soil conditions. If construction cannot be completed during the drier summer months when evapotranspiration is greatest, strict adherence to an Environmental Protection Plan is recommended;

• As an initial stage of construction, standard erosion and sediment control methods should be implemented on all active areas. Erosion and sediment control features should be regularly inspected and maintained. Additionally, erosion and sediment control features should be improved or added to in areas requiring more protection. In locations prone to erosion, soil stockpiles should be protected with silt fencing. Soil piles should be separated by at least 1 m to avoid mixing topsoil with subsoil. On agricultural lands, subsoil should be stored on lands stripped of topsoil (subsoil on subsoil);

• Following periods of excessive rainfall or saturated soil conditions, construction activities on agricultural lands should be suspended. During wet soil conditions heavy tracked and rubber-tired vehicles should be restricted from movement on agricultural soils. Usually, construction may continue from gravel or existing roadside work surfaces during wet soil conditions;

• To the extent feasible, construction activities should occur during drier times of the year. Lands affected by heavy rainfall events and wet soil conditions should be monitored, to avoid the potential for topsoil and subsoil mixing. Construction activities should be temporarily halted on lands where excessively wet soil conditions are encountered. Enbridge’s on-site inspection team should determine when construction activities may be resumed;

• If a situation develops that necessitates construction during wet soil conditions, soil protection measures should be implemented, such as: confining construction activity to the narrowest area practical, installing surface protection measures, and using wide tracked or low ground pressure vehicles;

• During construction activities, weather should be monitored to identify the potential onset of high wind conditions which can cause wind erosion. In the event that high winds occur, protective measures such as the following will be implemented:

− suspend earth moving operations;

− apply dust suppressants; and

− protect soil stockpiles with a cover, barrier or windscreen.

• In conjunction with the above measures, all required materials and equipment should be readily accessible and available for use as required;

• Topsoil stripping on the RoW should be sufficiently wide to ensure that topsoil will be stockpiled on topsoil and subsoil will be stockpiled on subsoil. Inspection staff should ensure separation between topsoil storage piles and subsoil storage piles is maintained to reduce potential for soil mixing. If topsoil is required to be imported it should be tested for soybean cyst nematode to ensure that it is not contaminated (see Section 4.2.6);

• Where agricultural land adjacent to the RoW is typically accessed by crossing the RoW alternate access to the fields will be provided for the farm operator for the short period of time during construction that access across the RoW is not possible; and

4.9

PROPOSED NATURAL GAS PIPELINE TO SERVE THE SEATON LAND DEVELOPMENT: ENVIRONMENTAL REPORT

Impact Identification, Assessment and Mitigation March 8, 2016

• If clean-up is not practical during the construction year, it should be undertaken in the year following construction, starting in May or June once the soils have sufficiently dried. Interim soil protection measures should be undertaken in sensitive areas to stabilize the RoW for over-wintering.

Net impacts

With adherence to the best construction practices discussed in this report, no significant adverse impacts to the capability of the soils along the pipeline route are anticipated.

4.2.6 Soybean Cyst Nematode (SCN)

Soybean cyst nematode (SCN) is a soil borne parasite that can significantly impact soybean yields. It may be present in some fields in the Study Area.

Potential Impacts

On agricultural fields, the potential exists for SCN to be spread from an impacted field to a non-impacted field by contaminated machinery, wind, contaminated boots, water erosion, etc. In order to minimize the risk of spreading SCN to non-impacted fields, mitigative/protective measures have been established. Since the construction will impact very little agricultural soil, the potential for the spread of SCN onto adjacent fields is negligible.

Mitigative/Protective Measures

Soil sampling for SCN is required where construction activity in the TWE is planned on agricultural lands adjacent to the existing municipal road allowance. If a field is identified as having SCN, the following mitigation measures should be considered:

• Ensure construction activity is restricted to the non-agricultural pipeline construction area;

• In the event that the pipeline route or an adjacent farm field has SCN advise the farm operator to remove soil from equipment before moving to the area that has not been impacted by SCN. This may involve thorough washing of equipment before moving equipment from an impacted field to non- impacted field;

• All properties impacted with SCN should be recorded and communicated to the Contractor. Stantec will help develop best practices protocol to handle SCN; and

• Any topsoil imported for clean-up activities should be analyzed for SCN by collecting a composite sample, sending it to a lab for analysis and reviewing results before any imported topsoil is placed on the easement. Imported suitable fill (not containing topsoil) or granular materials do not need to be tested for SCN.

4.10

PROPOSED NATURAL GAS PIPELINE TO SERVE THE SEATON LAND DEVELOPMENT: ENVIRONMENTAL REPORT

Impact Identification, Assessment and Mitigation March 8, 2016

4.2.7 Agricultural Tile Drains

Artificial tile drainage is commonly implemented to achieve maximum agricultural productivity on fields. There are no properties adjacent to the preferred pipeline route that has random or systematic agricultural tile drains.

Potential Impacts

As the proposed construction Project will not cross any locations of agricultural tile drainage, impacts are not anticipated.

Mitigative/Protective Measures

No impacts related to agricultural tile drains are anticipated. Mitigation measures to protect agricultural tile drains are not required.

4.2.8 Natural Hazards

Natural hazards are elements of the physical environment that have the potential to affect a project in an adverse manner. Potential natural hazards along the preferred pipeline route are limited. Natural hazards that may occur are seismic activity and flooding. The preferred route traverses flood line areas. A map of TRCA’s regulation limit (i.e., flood line) is located in Appendix C, Figure No. 3.

The preferred pipeline route lies within the southern Great Lakes Seismic Zone (NRCan, 2013). This zone has a low to moderate level of seismicity when compared to the more active seismic zones to the east, along the Ottawa River and in Quebec.

Over the past 30 years, on average, 2 to 3 magnitude 2.5 or larger earthquakes have been recorded in the southern Great Lakes region. By comparison, over the same time period, the smaller region of Western Quebec experienced 15 magnitude 2.5 or greater earthquakes per year.

Three moderate sized (magnitude 5) events have occurred in the 250 years of European settlement of this region, all of them in the United States - 1929, Attica, New York, 1986, near Cleveland, Ohio, and 1998, near the Pennsylvania/Ohio border. All three of these earthquakes were widely felt in southern Ontario but caused no damage in Ontario.

Potential Impacts

The probability of significant seismic activity in the area traversed by the preferred pipeline is low; therefore, no potential effects are anticipated.

4.11

PROPOSED NATURAL GAS PIPELINE TO SERVE THE SEATON LAND DEVELOPMENT: ENVIRONMENTAL REPORT

Impact Identification, Assessment and Mitigation March 8, 2016

The likelihood of a flooding event interfering with pipeline construction is reduced by construction occurring outside of the spring freshet. A flooding event during construction could result in construction delays, sedimentation, and construction equipment entering a watercourse. The nature of these impacts would depend on the spatial extent, duration, and magnitude of the flooding event.

Mitigation and Protective Measures

If flooding necessitates a change in the construction schedule, affected landowners and regulatory agencies should be notified and construction should continue at non-affected locations. Workspaces, unless necessary for watercourse crossings, should be located above the floodplain to the extent practical. All work in the floodplains will be subject to a permit under Ontario Regulation 166/06 from the TRCA. Mitigation measures for wet soil shutdown and high winds are provided in Section 4.2.5.

Net Impacts

With the implementation of the above mitigation and protective measures, no significant adverse residual impacts from natural hazards are anticipated.

4.3 BIOPHYSICAL FEATURES

4.3.1 Aquatic Species and Habitat

The MNRF’s Land Information Ontario (LIO) digital mapping (LIO, 2015) indicates the presence of four watercourses within the Study Area (Appendix C, Figure No. 3). All four watercourses are tributaries of Duffins Creek. The Duffins Creek watershed is characterized as a coldwater system that supports a diversity of fish species including Brook Trout (Salvelinus fontinalis), Rainbow Trout (Oncorhynchus mykiss) Darter sp. (Percina sp.) and Sculpin sp. (Cottoidea sp.) (TRCA, 2004).

According to the Department of Fisheries and Oceans Canada’s (DFO) aquatic Species at Risk (SAR) mapping (DFO, 2015) and the Natural Heritage Information Centre online database (MNRF, 2015a), Urfé Creek and Ganatsekiagon Creek support Redside Dace (Clinostomus elongatus). Redside Dace are provincially endangered and the species and its habitat are protected by Ontario’s Endangered Species Act (ESA), 2007. Federally, Redside Dace is a Special Concern species with no protection under the federal Species at Risk Act (SARA).

A site investigation was conducted on October 29, 2015 at the proposed crossing locations to confirm the presence of mapped watercourses and identify crossings that may not have been in the LIO database. Field investigation confirmed the presence of potential habitat for Redside Dace in Urfé Creek and Ganatsekiagon Creek, both of which are crossed by the preferred pipeline route. Both watercourses are permanently flowing streams with conditions suitable to support the species. The remaining two watercourses mapped in the Study Area (Appendix C,

4.12

PROPOSED NATURAL GAS PIPELINE TO SERVE THE SEATON LAND DEVELOPMENT: ENVIRONMENTAL REPORT

Impact Identification, Assessment and Mitigation March 8, 2016

Figure No. 3, WC-3 and WC-4) do not cross the preferred pipeline route. The mapped watercourse at WC-3 is parallel to Taunton Road, north of the hydro poles. It is seasonal in nature, likely flowing in spring or during heavy precipitation events. The mapped watercourse at WC-4 does not extend north of the CP rail tracks and therefore is not crossed by the preferred pipeline route.

Potential Impacts

Construction has the potential to affect fish through impacts on water quality (erosion, sedimentation, and accidental spills) and disruption/harassment (vibration and noise). These potential effects may occur due to construction of the pipeline using HDD crossing methods.

Watercourses will be crossed using HDD methods therefore no in-water work will be required. Setback distances for the drill entry and exits pits should be established at least 30 m from the bank full width of Urfé Creek and Ganatsekiagon Creek, both of which support Redside Dace (Clinostomus elongatus). With the successful implementation of mitigation measures, HDD crossings reduce the risk of impacts on sensitive habitats and sedimentation in a watercourse and reduce disturbance to the streambed and banks within the riparian zone. Fish passage and stream flow are also maintained.

In the event that open cut crossings may be required at some locations, other potential impacts may include restrictions to habitat use and fish passage, changes to habitat such as substrate composition, increased erosion potential, loss of in stream cover and riparian shading. Excessive sediment introduced into a watercourse can adversely impact fisheries via clogging gills, sedimentation of spawning beds and alteration of habitat. If an open cut is required for either Urfé Creek or Ganatsekiagon Creek, additional ESA permitting will be required.

Mitigation and Protective Measures

In addition to the mitigation measures outlined in Enbridge’s Construction and Maintenance Manual, 2015 (Section 15.0, River and Creek Crossings), the following general mitigation measures, or equivalent, are recommended at watercourse crossings along the preferred pipeline route. Some of the following general measures may not be applicable to HDD crossing methods but are included in the event an open cut crossing is required. Additional measures related to specific crossing methods are provided below.

General Mitigation Measures

• The following timing window is applicable to in-water activities at the watercourses along the preliminary preferred route:

• Coldwater: In-water work for non-Redside Dace Regulated Habitat permitted from July 1 to September 15 (no work from September 16 to June 30).

4.13

PROPOSED NATURAL GAS PIPELINE TO SERVE THE SEATON LAND DEVELOPMENT: ENVIRONMENTAL REPORT

Impact Identification, Assessment and Mitigation March 8, 2016

• Watercourses should not be obstructed in a way that impedes the free movement of water and fish;

• Prior to removal of the vegetation cover, effective mitigation techniques for erosion and sediment should be in place to protect water quality. Disturbance to the area during construction should be limited and grubbing activities should be delayed until immediately prior to grading operations;

• Soil exposure should be minimized prior to commencing construction, and the period of time that soil remains exposed for grading should be limited. Exposed soils surrounding all watercourses should be seeded immediately following construction;

• Temporary erosion and sediment control measures should be maintained and kept in place until all work within or near a watercourse has been completed and stabilized. Temporary sediment control measures should be removed at the completion of the work but not until permanent erosion control measures have been established;

• Construction material, excess material, construction debris and empty containers should be stored away from watercourses and watercourse banks;

• All activities, including equipment maintenance and refueling, should be controlled to prevent entry of petroleum products or other deleterious substances, including any debris, waste, rubble or concrete material, into a watercourse, unless otherwise specified in the contract. These should be >100 m from the watercourse at all times. Any such material that inadvertently enters a watercourse should be removed in a manner satisfactory to the environmental inspector;

• In the unlikely event of a spill, spills containment and clean-up procedures should be implemented immediately. Enbridge will contact the MOECC Spills Action Centre. The MOECC Spills Action Centre is the first point of contact for spills at the provincial and federal level;

• Conditions of water crossing permit(s), if applicable, will be adhered to; and

• Additional supplies should be maintained on-site, in a readily accessible location, for maintenance and contingency purposes. Prior to construction, adequate quantities of the materials listed below, or comparable substitutions, should be on site in order to control erosion and sediment deposition:

− Sediment control fencing;

− Straw bales;

− Wooden stakes;

− Sand bags;

− Water energy dissipater;

− Filter cloth;

− Water pumps (including stand-by pumps and sufficient lengths of hose); and

− Culvert.

4.14

PROPOSED NATURAL GAS PIPELINE TO SERVE THE SEATON LAND DEVELOPMENT: ENVIRONMENTAL REPORT

Impact Identification, Assessment and Mitigation March 8, 2016

Horizontal Direction Drill Mitigation Measures

HDD construction methods for pipeline water crossings will not require DFO review or Authorization under the Fisheries Act provided measures to avoid causing serious harm to fish and fish habitat are followed during construction. These measures include locating entry and exit points at sufficient distance to avoid disturbance to the bed and banks, locating the drill path at an appropriate depth below the channel and installation of appropriate sediment and erosion control measures (i.e., silt fencing around disturbed areas, development of a contingency plan, etc.). If these measures are followed, a project of this nature is considered to be low risk to fish and fish habitat and can proceed without DFO review.

Specific mitigation measures as they relate to employing the HDD method are as follows:

• Standard erosion and sediment control measures should be implemented around drill and pipe staging areas;

• Prior to initiating a HDD, appropriate geotechnical data should be obtained to assist in determining the drill path;

• Drilling equipment (e.g., drill rig, support equipment, sump) should be set up a minimum of 30 m from the edge of watercourses;

• Clearing of vegetation or grading of watercourse banks should not occur within 30 m from the edge of watercourses, if possible;

• A drilling mud release contingency plan should be prepared and kept on-site;

• Environmental inspectors should be present to during the crossing of Urfé Creek and Ganatsekiagon Creek since they are Redside Dace regulated watercourses. The Environmental inspectors will be present to monitor for accidental mud release into these watercourses during HDD activities;

• Bentonite-based drilling mud should be used without the use of additives (except with approval from appropriate regulatory authorities);

• Suitable drilling mud tanks or sumps should be installed to prevent contamination of watercourses;

• Berms or check dams should be installed downslope from drill entry and anticipated exit points to contain the release of any drilling mud; and

• Drilling mud should be disposed of in accordance with the appropriate regulatory authority requirements.

Bore Path Collapse Mitigation Measures

The following mitigation measures should be applied to prevent HDD borehole collapse from occurring in susceptible soils. These measures should be informed by geotechnical studies:

• Fluid volumes, annular pressure and cutting returns should be strictly monitored to ensure bore hole plugging and fluid losses are detected and addressed immediately;

4.15

PROPOSED NATURAL GAS PIPELINE TO SERVE THE SEATON LAND DEVELOPMENT: ENVIRONMENTAL REPORT

Impact Identification, Assessment and Mitigation March 8, 2016

• Alternative drill paths should be evaluated to minimize exposure to challenging soil materials; and

• Drilling mud should be maintained in the borehole at all times. This can be facilitated by positioning the entry and exit points in areas with cohesion less soils (e.g., silt-sand zones).

Drilling Mud Release (Inadvertent Returns) Mitigation Measures

The following mitigation measures should be employed to reduce the risk of lost drilling mud circulation:

• Appropriate berms, silt fencing and secondary containment measures (i.e., plastic tarp) should be installed around drilling and drilling mud management equipment at both bore entry and bore exit locations to contain operational spills;

• Operational spills should be cleaned-up daily to prevent mobilization of drilling mud off site during rain events;

• The directional drill should be designed so that drilling slurry pressure is minimized and the drilling rate is reduced in porous materials to minimize the chance of loss of circulation of the drilling slurry;

• Smooth operation of the drilling string and slurry pumping systems should be maintained to avoid pressure surges;

• Slurry viscosity through appropriate filtering of drilled material should be minimized to reduce the pressure gradient along the drill path due to frictional effects;

• Slurry volumes should be continually monitored to enable a quick response to any indications of lost circulation; and

• Any drilling mud that escapes onto land should be immediately contained and transferred into an on-site containment system.

The following materials should be on hand during drilling operations and prepared to employ them in the event of a drilling mud spill or inadvertent return: sand bags, straw bales, silt fencing and a hydrovac truck.

Additional Measures

The contingency method for HDD crossings is an open cut crossing. The following measures are applicable to open cut crossings.

Flow Diversion/Dewatering

If in-water works are required, the work area will be isolated from the remainder of the surface water feature. Downstream flows will be maintained using dam and pump techniques. Dewatering operations will be managed to prevent erosion and/or release of sediment laden or contaminated water to the waterbody (e.g. settling basin, filter bag, energy dispersion measures). An isolation/contamination plan will be designed and implemented to isolate

4.16

PROPOSED NATURAL GAS PIPELINE TO SERVE THE SEATON LAND DEVELOPMENT: ENVIRONMENTAL REPORT

Impact Identification, Assessment and Mitigation March 8, 2016

temporary in-water work zones and maintain flow around the work zone at all times. Maintenance of downstream flow will avoid potential upstream flooding and desiccation of downstream aquatic habitat and organisms.

Fish Rescue Plan

Fish in the construction area will be collected and moved using capture, handling, and release techniques to minimize harm and stress. The intakes of pumping hoses will be equipped with an appropriate device to avoid entraining and impinging fish (see Measures to Avoid Causing Harm to Fish and Fish Habitat (2013) at the following DFO website http://www.dfo-mpo.gc.ca/pnw-ppe/measures-mesures/measures-mesures-eng.html). Rescue plans will be developed on a site specific basis and implemented by qualified professionals with the appropriate permitting in place (i.e. MNRF Licence to Collect Fish for Scientific Purposes).

Site Restoration and Riparian Planting

Following construction, the bed and banks of the crossing locations will be restored to pre-construction conditions to the extent possible in accordance with Enbridge’s Construction and Maintenance Manual, 2015 (Section 15.8: Site Restoration). Bank slopes will be restored to match existing grades; however, alterations may be made to maintain slope stability and limit future erosion. Exposed banks will be re-vegetated with native shrubs and grasses to provide riparian cover and aid in erosion and sediment control. Stream beds will be restored to maintain slopes and tie in with existing grades. Bed material will be replaced to match pre-construction conditions.

Permitting

The proposed pipeline will be located within the regulated boundary of TRCA. Permits under Ontario Regulation 166/06 will be required prior to construction activities in the regulated boundary. Due to the presence of Redside Dace in Urfé Creek and Ganatsekiagon Creek, the HDD drill entry and exit pits must be located at least 30 m from bank full width. The MNRF must be notified to determine if a Notice of Activity is required for the HDD crossing. If activities are required within 30 m of the bank full width and will disturb more than 300 m2, then the MNRF must be contacted to determine if an ESA Permit is required.

Net Impacts

With the implementation of the HDD construction method and the above mitigation and protective measures, no significant adverse residual impacts on aquatic species or habitat are anticipated.

4.17

PROPOSED NATURAL GAS PIPELINE TO SERVE THE SEATON LAND DEVELOPMENT: ENVIRONMENTAL REPORT

Impact Identification, Assessment and Mitigation March 8, 2016

4.3.2 Designated Natural Areas and Vegetation

Known and potential designated natural areas within 120 m of the preferred pipeline route are wetlands and significant woodlands. A map of designated natural areas within 120 m of preferred pipeline route and within the Study Area is located in Appendix C, Figure No. 2.

Wetlands

The Ontario Wetland Evaluation System is used to identify Provincially Significant Wetlands. An evaluated wetland may be one contiguous unit or may be a series of smaller wetlands functioning as a whole. Evaluated wetlands that do not qualify as provincially significant may be designated locally significant and may be protected through local planning and policy measures. There may also be unevaluated wetlands in an area.

A review of MNRF Land Information Ontario (LIO) mapping (LIO, 2015) did identify eleven unevaluated wetland features within the Study Area. There is no overlap of wetland features with road allowance along Taunton Road, however, portion of the TWE on the north side Taunton Road does overlap with some wetland features. Field studies conducted in 2015 by Stantec also identified a number of treed wetlands within the Study Area and along the preferred pipeline route.

Significant Woodlands

A woodland is defined as a treed area, woodlot or forested area. The Natural Heritage Reference Manual notes that the local planning authority has a responsibility for designating significant woodlands, using criteria that include size, ecological function, uncommon characteristics and economic and social functional values (MNRF, 2010).

In the Region of Durham, significant woodlots are defined under the Provincial Policy Statement, which includes any contiguous forested areas larger than 20 hectares in municipalities that have 16-30% woodland cover (Riley and Mohr, 1994). The preferred pipeline route and the TWE do not cross within woodlands that meet the size criterion for significance.

Areas of Interest

On November 23, 2015, the TRCA provided information on Areas of Interest located in the vicinity of the preferred pipeline route. These areas of interest include regulated areas (regulation limit, crest of slope, meander belt, regulatory flood plain, wetlands and watercourses), program and policy areas (conservation lands, environmentally significant areas, terrestrial natural heritage system strategy and terrestrial species and habitat), and provincial program areas (greenbelt). Areas of interest located along the preferred pipeline route are shown in Appendix C, Figure Nos. 2 and 3.

4.18

PROPOSED NATURAL GAS PIPELINE TO SERVE THE SEATON LAND DEVELOPMENT: ENVIRONMENTAL REPORT

Impact Identification, Assessment and Mitigation March 8, 2016

Summary

A total of seven vegetation community types were identified within 120 m of the preferred route and are shown in Appendix C, Figure No. 2. Vegetation communities present within the preferred route include forest, swamp and thicket communities. Vegetation communities adjacent to the road allowance were relatively disturbed as the Taunton Road experiences high amounts of traffic and disturbance. Additional land use within 120 m of the preferred route includes agricultural (row) crops, active aggregate pit (extraction), rural and low-density residential.

Potential Impacts

A Field survey in 2015 identified that the preferred pipeline route falls within an existing road allowance that passes near but not within unevaluated wetlands; further review for the TWE was addressed through a desktop exercise. As noted above in Section 4.3.3, these wetlands were not identified by MNRF in their LIO mapping and are currently not designated as provincially or locally significant. Ecological Land Classification (ELC) and botanical surveys were conducted in fall 2015 to assess the significance and boundaries of vegetation communities, woodlands and to identify vascular plant species. Given the intent to construct the pipeline largely within the road allowance significant tree removal is not anticipated for the construction of this Project including in the TWE area. Where there is natural vegetation within or adjacent to the preferred pipeline route, potential impacts include the removal of native vegetation from within the road allowance, introduction or spread of invasive species, and indirect effects such as dust, erosion, and accidental spills. In addition, trees removed from the City of Pickering Tree Protection Zones (adjacent to watercourses and in designated greenspaces) that are greater than 25 mm in diameter at 1.5 above surface grade, are protected and would require a Tree Permit.

Mitigation and Protective Measures

Mitigation and protective measures are outlined in Section 4.2.5 for dust and erosion, and Section 4.3.1 for accidental spills.

Environmental mitigation and protective measures during construction will include the following:

• Minimize clearing and disturbance to natural areas to the extent possible, including sensitive areas such as unstable soils, wetlands, and areas of significant groundwater recharge or discharge;

• Construction activities with the potential to remove migratory bird habitat, such as vegetation clearing, should be avoided to the extent possible during the breeding season which is generally from April 1- August 31 in southern Ontario (Environment Canada, 2014). In instances where vegetation clearing within the window is unavoidable, a nest search of the area to be cleared can be undertaken to identify nests of species protected under the MBCA. Nest searches in trees, shrubs and ground vegetation on and adjacent to the RoW will be conducted by a qualified wildlife biologist a maximum of 7 days before clearing

4.19

PROPOSED NATURAL GAS PIPELINE TO SERVE THE SEATON LAND DEVELOPMENT: ENVIRONMENTAL REPORT

Impact Identification, Assessment and Mitigation March 8, 2016

activities commence. The results of the survey will be reported to the Environmental Inspector. In the event that an active nest is observed on or off the RoW, a species specific setback distance to vegetation clearing will be recommended and adhered to.;

• Clearing should be done during frozen or dry soil conditions to the extent practical to limit disturbance to vegetation and terrain;

• Tree cutting should be done in consideration of the Durham Region Tree Conservation Bylaw (#31-2012). Please note that this by-law only applies to Woodlands within the Region that are one hectare (2.5 acres) in size and greater. No woodlands of this size exist along the Preferred Route;

• Tree removal in a protected area within the City should be done in accordance with the City of Pickering Tree Protection By-law 6108/03. Protected areas usually run through and adjacent to watercourses and green spaces. A permit is required for trees located in a designated protected area;

• The limits of the construction footprint should be identified in the field, to allow for the protection of off-site natural areas and vegetation;

• An invasive species management plan should be developed by Enbridge, as measures (e.g., equipment washing before site access) may be necessary to mitigate the spread of invasive species;

• A screening field program of wetlands and riparian areas should be undertaken prior to construction. The following recommendations for work within wetlands are recommended:

− Remove vegetation at ground level, leaving existing root systems. Limit tree stump removal and grading activities;

− Install water control swales, as required, to facilitate cross easement water movements;

− Establish travel areas by installing swamp mats;

− Strip the top 0.15 – 0.30 m of topsoil/muck separately from the subsoil in the area disturbed by trenching;

− Regularly inspect the off-easement water regime, monitoring for possible off-easement ponding;

− Storage areas for hazardous materials, chemicals, fuels and lubricating oils should be located at least 100 m outside of wetland boundaries and should be situated in designated contained areas;

− Construction equipment should be refueled at least 50 m outside of wetland boundaries;

− Construction equipment traffic in wetland areas should be kept to the minimum necessary to complete the pipeline construction; and,

− Post-construction, replace any small ephemeral ponds and seasonal depressions.

• A re-vegetation program appropriate to the land use should be initiated for all work areas disturbed during construction (refer to Section 27.0 of Enbridge’s Construction and Maintenance Manual);

4.20

PROPOSED NATURAL GAS PIPELINE TO SERVE THE SEATON LAND DEVELOPMENT: ENVIRONMENTAL REPORT

Impact Identification, Assessment and Mitigation March 8, 2016

• In the event that trees are required to be removed, a tree replacement program should be undertaken, satisfactory to the landowner, and consistent with any municipal requirements; and

• One year following construction, planted vegetation should be inspected for survival, in areas of severe dieback, dead or diseased planted vegetation should be replaced.

Net Impacts

With the implementation of the above mitigation and protective measures, no significant adverse residual impacts on designated natural areas and vegetation are anticipated.

4.3.3 Wildlife and Wildlife Habitat

Significant Wildlife Habitat

Wildlife habitat is defined as an area where plants, animals and other organisms live, including areas where species concentrate at a vulnerable point in their life cycle, and areas that are important to migratory and non-migratory species (MNRF, 2000). Significant wildlife habitats are grouped into four categories:

1. Seasonal concentration areas;

2. Animal movement corridors;

3. Rare vegetation communities or specialized habitats; and

4. Habitats of species of conservation concern.

Seasonal Concentration Areas

Seasonal concentration areas are those sites where large numbers of a species gather together at one time of the year, or where several species congregate. No seasonal concentration areas have been identified in MNRF mapping (MNRF, 2015a) within 120 m of the proposed pipeline route.

The existing road allowance for Taunton Road experiences high amounts of road traffic. Vegetation communities located within 120 m of the preferred route consisted of treed (forest and swamp) and thicket communities. Based on the results of habitat assessments conducted in 2015 seasonal concentration areas within the Study Area were not identified.

Animal Movement Corridors

Animal movement corridors are elongated, naturally vegetated parts of the landscape used by animals to move from one habitat to another (MNRF, 2000). In Ecoregion 6E, amphibian and deer movement corridors can be considered significant wildlife habitats (MNRF, 2015b). Corridors should have at a minimum 15 m of vegetation on either side of a waterway or be up to 200 m wide of woodland habitat, and should contain native vegetation and not be broken by roads or waterways. A review of aerial photography indicates the presence of linear hedgerows;

4.21

PROPOSED NATURAL GAS PIPELINE TO SERVE THE SEATON LAND DEVELOPMENT: ENVIRONMENTAL REPORT

Impact Identification, Assessment and Mitigation March 8, 2016

however, any vegetated corridor is broken by Taunton Road and does not meet the criteria for significance.

Based on the background information, habitat assessments and incidental wildlife observations from 2015, habitat supporting animal movement corridors was not identified. It is not expected that the existing road allowance along the preferred pipeline route and adjacent wooded habitat are providing corridor functions.

Rare Vegetation Communities or Specialized Habitats

Rare or specialized habitats are two separate components. Rare habitats are those with vegetation communities that are considered rare in the province. SRANKS are rarity rankings applied to species at the provincial level and are part of a system developed under the auspices of the Nature Conservancy. Generally, community types with SRANKS of S1 to S3 (i.e., extremely rare to rare – uncommon in Ontario), as defined by the NHIC, could qualify. It is assumed that these habitats are at risk and that they are also likely to support additional wildlife species that are considered significant.

Specialized habitats are microhabitats that are critical to some wildlife species. The 6E Ecoregion Criteria (MNRF, 2015b) identifies seven potential specialized habitats (cliffs and talus slopes, sand barren, alvar, old growth forest, savannah, tallgrass prairie, other rare vegetation communities) associated within Ecoregion 6E of Ontario, where the proposed pipeline route is located.

None of these communities were identified along the preferred pipeline route during site investigations in 2015.

Habitat for Species of Conservation Concern

There are four types of species of conservation concern: those which are rare, those whose populations are significantly declining, those which have been identified as being at risk from certain common activities and those with relatively large populations in Ontario compared to the remainder of the globe.

Rare species are considered at five levels: globally rare, federally rare (with designations by COSEWIC), provincially rare (with designations by COSSARO), regionally rare (at the Site Region level), and locally rare (in the municipality or Site District). This is also the order of priority that should be assigned to the importance of maintaining species. Some species have been identified as being susceptible to certain practices, and their presence may result in an area being designated significant wildlife habitat. Examples include species vulnerable to habitat loss and species such as woodland raptors that may be vulnerable to forest management or human disturbance. The final group of species of conservation concern includes species that have a high proportion of their global population in Ontario. Although they may be common in Ontario, they are found in low numbers in other jurisdictions.

The NHIC database was searched to obtain historic records of species of conservation concern (SOCC) in the vicinity of the proposed pipeline route. The Ontario Breeding Bird Atlas was also consulted for bird records in the Study Area (Region 12, square 17PJ45) which (Cadman et al.,

4.22

PROPOSED NATURAL GAS PIPELINE TO SERVE THE SEATON LAND DEVELOPMENT: ENVIRONMENTAL REPORT

Impact Identification, Assessment and Mitigation March 8, 2016

2007), as well as the Ontario Reptile and Amphibian Atlas (Ontario Nature, 2013) and the Ontario Mammal Atlas (Dobbyn, 1994). In addition to these records, SOCC recorders were provided to Stantec from MNRF on November 23, 2015. Based on a review of background information, 8 species of conservation concern are known to occur in the vicinity of the Study Area, as shown in Table 4.1.

Exact location of species occurrences are not available from these atlases and, instead, are recorded within 1 x 1 km or 10 x 10 km squares. The potential for species to be present will be limited by habitat suitability and availability. Therefore, the identified species recorded from these databases may not occur in the Study Area.

Table 4.1: Terrestrial Species of Conservation Concern

Common Name Scientific Name SRANK Provincial

Status (COSSARO)

National Status

(COSEWIC) Source

PLANTS

Eastern Burning Bush Euonymus atropurpureus S3 - - NHIC

REPTILES

Eastern Ribbonsnake Thamnophis sauritus S3 SC SC NHIC

Snapping Turtle Chelydra serpentina S3 SC SC RAO

BIRDS

Canada Warbler Wilsonia canadensis S4B SC THR OBBA

Common Nighthawk Chordeiles minor S4B SC THR OBBA

Eastern Wood-Pewee Contopus virens S4B SC SC OBBA, MNRF

Wood Thrush Hylocichla mustelina S4B SC THR-NS OBBA, MNRF

MAMMALS

Tri-coloured Bat Perimyotis subflavus S3? END COSEWIC*

NOTES: NHIC: Natural Heritage Information Centre OBBA: Ontario Breeding Bird Atlas RAO: Reptiles and Amphibians of Ontario COSSARO: Committee on the Status of Species at Risk in Ontario COSEWIC: Committee on the Status of Endangered Wildlife in Canada *2013 COSEWIC Assessment and Status Report on the Little Brown Myotis, Northern Myotis, and Tri-colored Bat in Canada THR: Threatened - a species that is at risk of becoming endangered END - Endangered - a species facing imminent extinction or extirpation

SC: Special Concern - a species with characteristics that make it sensitive to human activities or natural events S1:Critically Imperiled - Critically imperiled in the province (often 5 or fewer occurrences) S2: Imperiled - Imperiled in the province, few populations (often 20 or fewer) S3: Vulnerable - Vulnerable in the province, relatively few populations (often 80 or fewer) S4: Apparently Secure - Uncommon but not rare S? indicates uncertainty in the assigned rank S#B: Breeding status rank NS: No schedule – not yet on a SARA schedule

4.23

PROPOSED NATURAL GAS PIPELINE TO SERVE THE SEATON LAND DEVELOPMENT: ENVIRONMENTAL REPORT

Impact Identification, Assessment and Mitigation March 8, 2016

Potential Impacts

Potential impacts on wildlife and wildlife habitat from construction include direct mortality from construction vehicles, limited habitat destruction through vegetation removal, habitat degradation through spills and sensory disturbance of wildlife during construction.

Mitigation and Protective Measures

Mitigation and protective measures are outlined in Section 4.3.2 for vegetation removal and Section 4.3.1 for accidental spills.

Environmental mitigation and protective measures during construction include the following:

• Detailed design of the pipeline should be reviewed to avoid and minimize impact upon wildlife habitat and vegetated areas to the extent possible;

• Construction activities with the potential to remove migratory bird habitat, such as vegetation clearing, should be avoided to the extent possible during the breeding season which is generally from April 1- August 31 in southern Ontario (Environment Canada, 2014). In instances where vegetation clearing within the window is unavoidable, a nest search of the area to be cleared can be undertaken to identify nests of species protected under the MBCA. Nest searches in trees, shrubs and ground vegetation on and adjacent to the road allowance will be conducted by a qualified wildlife biologist a maximum of 7 days before clearing activities commence. The results of the survey will be reported to the Environmental Inspector. In the event that an active nest is observed on or off the road allowance, a species specific setback distance to vegetation clearing will be recommended and adhered to.;

• Trench construction should be limited in duration and followed as closely as practical with backfill operations, to facilitate the minor occurrences of wildlife movement across the trench;

• Construction personnel will not to threaten, harass or injure wildlife;

• Where practical avoid construction within 20 m of wetland communities during the amphibian breeding season (March 1 – June 30);

• All brush and trees felled should be removed immediately from the Project footprint to discourage use of these features by snakes; and

• Precautionary mitigation measures to be implemented in the unlikely event that a wildlife encounter occurs include:

• Equipment and vehicles are to yield the right-of-way to wildlife; and

• If wildlife are encountered during construction, personnel are required to move away from the animal and wait for the animal to move off the construction site.

Net Impacts

With the implementation of the above mitigation and protective measures, no significant adverse residual impacts on wildlife and wildlife habitat are anticipated.

4.24

PROPOSED NATURAL GAS PIPELINE TO SERVE THE SEATON LAND DEVELOPMENT: ENVIRONMENTAL REPORT

Impact Identification, Assessment and Mitigation March 8, 2016

4.3.4 Species at Risk (SAR)

SAR are identified as endangered or threatened by federal (COSEWIC) and/or provincial legislation (COSSARO).

The NHIC database was searched to obtain historic records of Species at Risk in the vicinity of the proposed pipeline route. The Ontario Breeding Bird Atlas was also consulted for bird records (Region 12, square 17PJ45) (Cadman et al., 2007), as well as the Ontario Reptile and Amphibian Atlas (Ontario Nature, 2013) and the Ontario Mammal Atlas (Dobbyn, 1994). In addition to these records, SAR recorders were provided to Stantec from MNRF on November 23, 2015. Based on a review of background information, Species at Risk are known to occur in the vicinity of the Study Area.

Exact location of species occurrences are not available from these atlases and, instead, are recorded within 1 x 1 km or 10 x 10 km squares. The potential for species to be present will be limited by habitat suitability and availability. Therefore the identified species recorded from these databases may not occur in the Study Area. Based on a review of background information, 10 Species at Risk are known to occur in the vicinity of the Study Area, as shown in Table 4.2.

Table 4.2: Terrestrial Species at Risk

Common Name Scientific Name SRANK Provincial

Status (COSSARO)

National Status

(COSEWIC) Source

PLANTS

Butternut Juglans cinerea S3? END END NHIC, MNRF

BIRDS

Acadian Flycatcher Empidonax virescens S2, S3B END END NHIC

Bank Swallow Riparia riparia S4B THR THR-NS OBBA

Barn Swallow Hirundo rustica S4B THR THR-NS OBBA, MNRF

Bobolink Dolichonyx oryzivorus S4B THR THR-NS NHIC, MNRF

Chimney Swift Chaetura pelagica S4B, S4N THR THR OBBA

Eastern Meadowlark Sturnella magna S4B THR THR-NS OBBA, NHIC, MNRF

Least Bittern Ixobrychus exilis S4B THR THR OBBA

4.25

PROPOSED NATURAL GAS PIPELINE TO SERVE THE SEATON LAND DEVELOPMENT: ENVIRONMENTAL REPORT

Impact Identification, Assessment and Mitigation March 8, 2016

Table 4.2: Terrestrial Species at Risk

Common Name Scientific Name SRANK Provincial

Status (COSSARO)

National Status

(COSEWIC) Source

MAMMALS

Little Brown Myotis Myotis lucifugus S5 END END COSEWIC*

Northern Myotis Myotis septentrionalis S3? END END COSEWIC*

NOTES: NHIC: Natural Heritage Information Centre OBBA: Ontario Breeding Bird Atlas RAO: Reptiles and Amphibians of Ontario COSSARO: Committee on the Status of Species at Risk in Ontario COSEWIC: Committee on the Status of Endangered Wildlife in Canada *2013 COSEWIC Assessment and Status Report on the Little Brown Myotis, Northern Myotis, and Tri-colored Bat in Canada END: Endangered - a species facing imminent extinction or extirpation THR: Threatened - a species that is at risk of becoming endangered SC: Special Concern - a species with characteristics that make it sensitive to human activities or natural events

S1: Critically Imperiled - Critically imperiled in the province (often 5 or fewer occurrences) S2: Imperiled - Imperiled in the province, few populations (often 20 or fewer) S3: Vulnerable - Vulnerable in the province, relatively few populations (often 80 or fewer) S4: Apparently Secure - Uncommon but not rare S5: Secure - Common, widespread, and abundant in the province S?: indicates uncertainty in the assigned rank S#N – Non-breeding status rank S#B: Breeding status rank NS: No schedule – not yet on a SARA schedule

One plant species at risk was identified as potentially occurring within the Study Area: Butternut. This medium-sized tree species is commonly found in a variety of habitats throughout Southern Ontario, including woodlands and hedgerows ideal habitat includes rich, moist, and well-drained soils often found along streams, but may also be found on well-drained gravel sites, particularly those made of limestone (COSEWIC, 2003). Butternut is intolerant of shade and occurs singly or in small groups with a variety of associates (Farrar, 1995). Although potential habitat for this species may occur in the Study Area (i.e., woodlands and hedgerows), no Butternut was observed within the road allowance during the ELC surveys completed along the preferred pipeline route. At the time of the field surveys, access to the off road allowance was not available and there is a potential that Butternut may be present with the TWE.

Seven bird species at risk were identified as potentially occurring within the Study Area: Acadian Flycatcher, Bank Swallow, Barn Swallow, Bobolink, Chimney Swift, Common Nighthawk, Eastern Meadowlark, and Least Bittern.

The preferred breeding habitat of Acadian Flycatchers generally consists of large mature forests and deeply wooded ravines (Friesen and Stabb, 2001). A minimum of thirty hectares of suitable habitat are required. Acadian Flycatchers generally prefer large tracts of undisturbed forest and in Ontario, the species often breeds in black ash swamps (Whitehead and Taylor, 2002). Due to its area sensitive nature, suitable habitat is limited in Ontario as forest cover within its breeding

4.26

PROPOSED NATURAL GAS PIPELINE TO SERVE THE SEATON LAND DEVELOPMENT: ENVIRONMENTAL REPORT

Impact Identification, Assessment and Mitigation March 8, 2016

range is low and occurs as small, isolated patches. Other limiting factors include logging practices, invasive species, and encroachment on habitat by agriculture, residential development and utility corridors (COSEWIC, 2010a). No large tracts of undisturbed forest were found along the preferred pipeline route; therefore, this species is unlikely to be found in the Study Area.

The Bank Swallow excavate nests in exposed earth banks along watercourses and lakeshores, roadsides, stockpiles of soil, and the sides of sand and gravel pits. Single nests may occur, although colonies are typical and range from two to several thousand. Adjacent grasslands and watercourses are used for foraging habitat (Cadman et al., 2007). No cliffs or banks were found along the preferred pipeline route; therefore, this species will not be impacted by the Project.

Barn Swallows nest on walls or ledges of barns as well as on other human-made structures such as bridges, culverts or other buildings (Cadman et al., 2007). Where suitable nesting structures occur, Barn Swallow often form small colonies, sometimes mixed with Cliff Swallows. Barns Swallows feed on aerial insects while foraging in open habitat (COSEWIC, 2011). Barn Swallows are generally considered grassland species, foraging over meadows, hay, pasture or even mown lawn. They will also frequently forage in woodland clearings, over wetland habitats or open water where insect prey is abundant. No barns or other anthropogenic structures will be removed for this Project; therefore, this species will not be impacted by the Project.

The Bobolink is generally referred to as a grassland species. It nests primarily in forage crops with a mixture of grasses and broad-leaved forbs, predominantly hayfields and pastures. Preferred ground cover species include grasses such as Timothy and Kentucky bluegrass and forbs such as clover and dandelion (COSEWIC, 2010b). Bobolink is an area-sensitive species, with reported lower reproductive success in small habitat fragments (Kuehl and Clark, 2002; Winter et al., 2004). Grassland habitat assessments during surveys in 2015 did not identify suitable habitat along the preferred pipeline route; therefore, this species will not be impacted by the Project.

Chimney Swift use chimneys for roosting and breeding, as well as walls, rafters, or gables of buildings and, less frequently, natural structures such as hollow trees, tree cavities and cracks in cliffs (Cadman et al., 2007). The main limiting factor contributing to the species’ decline is the reduction of suitable breeding and roosting habitat through logging, removal of abandoned buildings and particularly the reduction in use of traditional chimneys; poor weather conditions during breeding season, pesticide use, chimney sweeping during breeding season and intolerance of some building owners are also contributing factors (COSEWIC, 2007a). No chimneys or other anthropogenic structures will be removed for this Project; therefore, this species will not be impacted by the Project.

The Common Nighthawk is an aerial insectivore and forages at dawn and dusk. Common Nighthawks nest on the ground in open habitats preferably with rocky or graveled substrate. Nighthawks will even nest on gravel roofs in the city. The regeneration or succession of forest clearings and the destruction of grassland habitats appear to play a major role in this species’

4.27

PROPOSED NATURAL GAS PIPELINE TO SERVE THE SEATON LAND DEVELOPMENT: ENVIRONMENTAL REPORT

Impact Identification, Assessment and Mitigation March 8, 2016

decline along with the non-selective spraying for mosquitoes (Cadman et al., 2007). Other potential limiting factors include an increase in predators such as domestic cats, Striped Skunks, Raccoons, American Crows and Common Ravens, as well as road-associated mortality (COSEWIC, 2007b). No open habitats with gravel substrate were found along the preferred pipeline route; therefore, this species will not be impacted by the Project.

Eastern Meadowlarks are ground nesting birds (Harrison, 1975), which are often associated with human-modified habitats where they sing from prominent perches such as roadside wires, trees, and fenceposts. As a grassland species the Eastern Meadowlark typically occurs in meadows, hayfields and pastures. However, it will utilize a wider range of habitat than most grassland species, including mown lawn (e.g. golf course, parks), wooded city ravines, young conifer plantations and orchards (Peck and James, 1983). The Eastern Meadowlark is generally tolerant of habitat with early succession of trees or shrubs. As with other grassland species, current threats are primarily the result of expanding urbanization and intensive farming practices (Cadman et al., 2007). Grassland habitat assessments during surveys in 2015 did not identify suitable habitat along the preferred pipeline route; therefore, this species will not be impacted by the Project.

The Least Bittern is a relatively small bird that nests in freshwater marshes where dense aquatic vegetation occurs with woody vegetation and open water. They are found most commonly in marshes greater than 5 ha in size (Gibbs et al., 1992). The Canadian population of Least Bitterns is estimated at less than 1000 pairs. The majority of Least Bitterns that breed in Canada are found in Ontario. The species is designated threatened due to its very small and declining population that depends on high quality marsh habitats that are being lost and degraded across the species' range (NHIC, 2007). The Least Bittern is protected under the SARA, the Canada/United States Migratory Birds Convention and the Migratory Bird Treaty between the United States and Mexico. No large freshwater marshes were found along the preferred pipeline route; therefore, this species will not be impacted by the Project.

Two mammal species at risk were identified as potentially occurring within the Study Area: Little Brown Myotis and Northern Myotis. Until recently, these species were considered common, and the recent change in status is due to significant declines in recent years attributed to a condition referred to as White-nose Syndrome. The Little Brown Myotis is a bat species commonly found near waterbodies in buildings, attics, roof crevices and loose bark on trees or under bridges (Eder, 2002). The Northern Myotis is a resident bat of upland forests, typically foraging for aerial insects in the forest understory. Maternity roosts are located under bark or in buildings with young born in June and July while hibernating colonies typically reside in cave crevices (Reid, 2006). No chimneys or other anthropogenic structures will be removed for this Project and tree removal is restricted to the road allowance along the preferred pipeline route and TWE; therefore, this species will not be impacted by the Project.

Potential Impacts

Construction activities have the potential to harm butternut trees within the TWE area.

4.28

PROPOSED NATURAL GAS PIPELINE TO SERVE THE SEATON LAND DEVELOPMENT: ENVIRONMENTAL REPORT

Impact Identification, Assessment and Mitigation March 8, 2016

Mitigation and Protective Measures

Prior to any tree removals it is recommended that a Butternut Survey be completed to confirm the presence or absence of this species in (or within 25 m of) the work area, in particular within the TWE. In the event that Butternut is found, a Butternut Health Assessment can be conducted and, if required, ESA authorization obtained.

Net Impacts

With the implementation of the above mitigation and protective measures, no significant adverse residual impacts on species at risk are anticipated.

4.4 SOCIO-ECONOMIC ENVIRONMENT

4.4.1 Residents and Businesses

The Study Area and preferred pipeline route are located east of the community of Whitevale, south of Highway 407 and north of the planned Seaton Developments. Several scattered rural residences including aggregate operations are located north (along Whitevale Road and Concession Road 5), south (along Taunton Road), and east (along Brock Road and Sideline 16) within the Study Area. The only known non-aggregate businesses within the Study Area are The Vinyl Connection located at the north east corner of Sideline 16 and Concession Road 5, Mike’s Music Machine along Brock Road, and AgriChill located south of Taunton Road, west of Concession Road 4.

Potential Impacts

Residential and business properties may experience noise, dust and equipment exhaust associated with construction activity. Construction activities will temporarily affect the aesthetic landscape of the construction area, and could impede property access. Potential safety concerns also exist at locations where properties, residents and vehicles come in proximity to construction activities.

Mitigation and Protective Measures

During construction, motorized construction equipment should be equipped with mufflers and silencers as available. Company and construction personnel should avoid idling of vehicles; vehicles or equipment should be turned off when not in use unless required for operation of the vehicle or equipment. To the greatest extent practical activities that could create noise should be restricted to daylight hours and adhere to local noise by-laws. Sources of continuous noise, such as portable generators, should be shielded or located so as to reduce disturbance to residents and businesses. Where pipeline installation will take an extended time period to complete, such as watercourse and road crossings, an assessment should be undertaken to

4.29

PROPOSED NATURAL GAS PIPELINE TO SERVE THE SEATON LAND DEVELOPMENT: ENVIRONMENTAL REPORT

Impact Identification, Assessment and Mitigation March 8, 2016

determine the suitability and effectiveness of temporary noise barriers adjacent to residential or business properties.

Site practices during construction should be implemented that are in line with the Environment Canada document ‘Best Practices for the Reduction of Air Emissions from Construction and Demolition Activities’ (Environment Canada, 2005), which may include:

• Maintaining equipment in compliance with regulatory requirements;

• Protecting stockpiles of friable material with a barrier or windscreen in the event of dry conditions and dust;

• Dust suppression of source areas; and

• Covering loads of friable materials during transport.

Watering for dust control must not result in the formation of puddles, rutting by equipment or vehicles, the tracking of mud onto roads or the siltation of watercourses.

Additional consultation with residents and businesses adjacent to the preferred pipeline route will be held in advance of construction commencement. Contact information for a designated Enbridge representative will be available prior to and during construction to address questions and concerns.

While pipeline construction activities and machinery have the potential to temporarily affect the local viewscape, restoration of the construction area will leave little evidence that a pipeline exists. Construction should be conducted as expeditiously as possible, to reduce duration of activities. Vegetative buffers at watercourse and road crossings should be restored where feasible.

Access to residential properties should be maintained at all times.

Safety fence should be installed at the edge of the construction RoW where public safety considerations are required. A traffic management plan should be implemented for all roads affected by construction, which at a minimum outlines measures to:

• Control the movement of materials and personnel to and from the construction site;

• Post signs to warn oncoming motorists of construction activity;

• Control traffic at road crossings;

• Reduce on-road disturbance and land closures;

• Store equipment as far from the edge of the road as practical; and

• Install construction barricades at road crossings.

4.30

PROPOSED NATURAL GAS PIPELINE TO SERVE THE SEATON LAND DEVELOPMENT: ENVIRONMENTAL REPORT

Impact Identification, Assessment and Mitigation March 8, 2016

Net Impacts

With the implementation of the above mitigation and protective measures, no significant adverse residual impacts on residents or businesses are anticipated.

4.4.2 Institutional Services & Facilities

No libraries, schools, police services, fire services, or places of worship are located along the preferred pipeline route. The closest health facilities (i.e., Westney Heights Medical Centre, Pickering Urgent Care Medi-Centre and Pickering Medical Centre) are located outside of the Study Area, approximately 5 km south of the preferred pipeline route. Additionally, the preferred pipeline route is located approximately 4 km south of the nearest emergency services (i.e., Fire Hall No. 6 and Durham Regional Police (25th Division)), outside of the Study Area.

Potential Impacts

Since there are no institutional services present within the vicinity of the preferred pipeline route, no impacts are expected.

Mitigation and Protective Measures

No impacts to institutional services and facilities are anticipated; therefore, no mitigation and protective measures are recommended.

4.4.3 Culture, Tourism & Recreation Facilities

A review of the Durham Region Ontario Genealogical Society mapping identified three cemeteries within the Study Area, along Whitevale Road/Concession Road 5; Hastings Cemetery is situated north of Whitevale Road, west of Brock Road, Lamoreux Cemetery is located south of Whitevale Road, west of Brock Road and Bethel Church Burial Ground is located at the south east corner of Sideline 16 and Concession Road 5. However, no known cultural, tourism, or recreational facilities located along the preferred pipeline route. Outside of the Study Area to the west, the Seaton Trail follows the West Duffins Creek, west of Sideline 26. This trail is home to a number of historic hunting and fishing routes along the creek, used for centuries by aboriginal people. The Trans Canada Trail follows the East Duffins Creek to Rossland Road (east of Sideline 16) on the east side of the Study Area. The trail is primarily used for hiking, road biking and walking and is accessible year-round.

4.31

PROPOSED NATURAL GAS PIPELINE TO SERVE THE SEATON LAND DEVELOPMENT: ENVIRONMENTAL REPORT

Impact Identification, Assessment and Mitigation March 8, 2016

Potential Impacts

There are no known cultural, tourism, or recreational facilities present within the vicinity of the preferred pipeline route; therefore, no impacts are expected.

Mitigation and Protective Measures

No impacts to cultural, tourism, or recreational facilities are anticipated; therefore, no mitigation and protective measures are recommended.

4.4.4 Economy & Employment

The most recent economy and employment statistics are provided in the 2011 National Household Survey released by Statistics Canada. Table 4.3 summarizes the unemployment rate, percentage of work force (over the age of 15) employed at the time of the census and median income of persons over the age of 15 (Statistics Canada, 2013a; Statistics Canada, 2013b, Statistics, Canada 2013c). Unemployment and the percentage of work force employed are very similar across Pickering, Durham Region and Ontario. Median income in Pickering and Durham Region is over 10% higher compared to Ontario.

Table 4.3: Economy and Employment Statistics

Unemployment Rate % in labour force > 15 years

Median Income for persons > 15

years

City of Pickering 8.4% 69.8% $34,548

Region of Durham 8.6% 69.2% $34,996

Ontario 8.3% 65.5% $30,526

Figure 4.1 shows the percentage of the employed population by industry in 2011 as released by Statistics Canada (2013a; 2013b; 2013c). Both Pickering and Durham Regional have higher employment in the utilities industry compared to Ontario. Employment in the finance and insurance industry is much higher in Pickering compared to Durham region and Ontario.

4.32

PROPOSED NATURAL GAS PIPELINE TO SERVE THE SEATON LAND DEVELOPMENT: ENVIRONMENTAL REPORT

Impact Identification, Assessment and Mitigation March 8, 2016

Figure 4.1: Distribution of Workforce by Percentage

Potential Impacts

The construction and operation of the preferred pipeline route will result in direct and indirect business and employment income, and an increase in tax revenues.

Mitigation and Protective Measures

Enbridge should make all reasonable efforts where practicable to procure services and materials from local suppliers, where services or materials are available in required quantity and at competitive prices.

Net Impacts

With the implementation of the Project and local procurement of services and materials where reasonable, positive residual impacts on the economy and employment are anticipated.

0

2

4

6

8

10

12

City of Pickering

Durham Region

Ontario

Statistics Canada, 2013a; Statistics Canada, 2013b; Statistics Canada, 2013c

4.33

PROPOSED NATURAL GAS PIPELINE TO SERVE THE SEATON LAND DEVELOPMENT: ENVIRONMENTAL REPORT

Impact Identification, Assessment and Mitigation March 8, 2016

4.4.5 Contaminated Sites

Landfills

The location of active and former landfill sites in the Study Area were identified by reviewing the MOECC’s Waste Disposal Inventory (MOECC, 1991), the City of Pickering Official Plan maps and the MOECC’s Landfill Inventory Management Ontario document on the MOECC’s website (MOECC, 2015a).

Two former landfills are located less than 2 km from the Study Area: (1) Brock West Landfill and (2) Brock South Landfill. The Brock West Landfill site is located west of Brock Road, north of Concession 3 Road in the City of Pickering. It covers an area of approximately 123 hectares (304 acres). According to the Brock Lands Master Plan Background Report prepared by the Toronto and Region Conservation Authority in 2011, the Brock West Landfill operated as a landfill until 1997, during which time more than 18 million tonnes of primarily municipal solid waste, but also some activated sludge, were deposited on the site. In 1991 Eastern Power started operating a gas power plant at the Brock West site in 1990 by utilizing methane gas generated from the landfill waste. The Brock South Landfill site is located south of Concession 5 Road, west of Sideline 16 Road. No municipal waste was disposed of on the Brock South site (TRCA, 2011).

Contaminated Sites and Former Industrial Sites

The location of contaminated sites in the Study Area were identified by reviewing the Region of Durham and City of Pickering Official Plan maps, the MOECC Brownfield’s Environmental Site Registry (MOECC, 2015b), the Federal Contaminated Sites Inventory accessed through the Treasury Board of Canada Secretariat’s website (Treasury Board, 2015) and the MOECC Waste Disposal Inventory (1991), including the Inventory for Industrial Sites Producing and Using Coal Tar and Related Tars in Ontario. These resources did not identify potentially contaminated sites in the Study Area or along the preferred pipeline route. However, the search identified five records of site condition outside of the Study Area; the closest site is approximately 150 m south of Taunton Road (see Appendix C, Figure No. 2). In addition, the preferred pipeline route crosses a TNPI petroleum products pipeline along Taunton Road.

Potential Effects

The preferred pipeline route will cross a TNPI petroleum products pipeline, which may be associated with potentially contaminated lands.

Mitigation and Protective Measures

Should contaminated soils be encountered during construction, Enbridge should implement their Suspect Soils Program (see Section 8.13 of Enbridge’s Construction and Maintenance Manual, 2015 for further details).

4.34

PROPOSED NATURAL GAS PIPELINE TO SERVE THE SEATON LAND DEVELOPMENT: ENVIRONMENTAL REPORT

Impact Identification, Assessment and Mitigation March 8, 2016

Net Effects

With the implementation of the above mitigation and protective measures, no significant adverse residual effects from contaminated sites are anticipated.

4.4.6 Waste Management

Potential Impacts

Improper disposal of waste material generated during construction may result in contamination to soil, groundwater, and/or surface water resources on and off the construction road allowance. Litter generated during construction may also become a nuisance to adjacent properties if not contained.

Mitigation and Protective Measures

All construction wastes should be disposed of in accordance with Enbridge’s Construction and Maintenance Manual, 2015. Additionally, Enbridge should undertake responsible management of excess fill. When details on excess fill volumes are known, disposal locations should be determined and appropriate permitting obtained.

A site-specific waste collection and disposal management plan should be implemented, which may include:

• Waste materials, sanitary waste and recycling transported off-site by private waste contractors licensed by the MOECC;

• Contractors required to remove their excess materials from the site;

• Labelling and storage of hazardous and liquid wastes in a secure area that would contain material in the event of a spill; and

• Implementation of a waste management program consisting of reduction, reuse, and recycling of materials.

Net Impacts

With the implementation of the above mitigation and protective measures, no significant adverse residual impacts from waste management are anticipated.

4.35

PROPOSED NATURAL GAS PIPELINE TO SERVE THE SEATON LAND DEVELOPMENT: ENVIRONMENTAL REPORT

Impact Identification, Assessment and Mitigation March 8, 2016

4.4.7 Land Use

The Study Area and preferred pipeline route are located in land uses designated by the Region of Durham and the City of Pickering.

Region of Durham

The Region of Durham Official Plan identifies the Study Area as within Special Policy Area “A”, which contains lands within Central Pickering and they shall be developed in accordance with the Central Pickering Development Plan. Therefore, the land use designation and policies are governed by the City of Pickering.

City of Pickering

The preferred pipeline route within the City of Pickering Official Plan crosses the Seaton Urban Study Area and Natural Area designations. The City and Region are undertaking a Detailed Community Planning Exercise for the development of the area known as the Seaton Lands with the objective of planning an “innovative, compact urban community”. Policy 2.13 of the Official Plan indicates that for the Seaton Urban Study Area, City Council supports the ultimate development of an urban community of up to 61,000 people and 30,500 jobs by 2031 and 70,000 people and 35,000 jobs through longer term intensification.

The preferred pipeline route within the Central Pickering Development Plan crosses the Mixed Corridor and Natural Heritage System designations. Section 4.1 Natural Heritage Designation permits the following use:

Infrastructure where required to serve the new urban community, where the location is logical or no reasonable alternative exists. Efforts are too be made to minimize the footprint of the use, to the extent possible, and to ensure no significant negative impacts on the Natural Heritage System or natural features and functions occur. Infrastructure includes: sewage and water systems, electric power generation and transmission including renewable energy systems, communications/telecommunications, transit and transportation corridors and facilities, oil and gas pipelines and associated facilities.

In addition Section 4.6 outlines Servicing Policies, which indicates that utilities should avoid Natural Heritage Systems, where possible and that utilities should be coordinate to accommodate private and public utilities, roads, etc. to avoid disruptions to the community and natural heritage systems.

4.36

PROPOSED NATURAL GAS PIPELINE TO SERVE THE SEATON LAND DEVELOPMENT: ENVIRONMENTAL REPORT

Impact Identification, Assessment and Mitigation March 8, 2016

The Seaton Zoning By-law 7364-14, Section 2.5 Linear Utilities Permitted in All Zones states that:

a) Notwithstanding anything else in this By-law, a utility company including Veridian, Bell, Rogers, Telus, Hydro One, Enbridge and other similar utility company may use any land or erect or use any building or structure in any zone for the purpose of a linear utility subject to the building or structure being in compliance with the most restrictive regulations contained in such zone for the use and the parking requirements of Section 3 of this By-law, for such use. Any building or structure erected or used in a Residential Zone under the provisions of this Section, shall be designed so as not to intrude into the residential character of the area.

b) This exemption for use in any zone shall not apply to:

i. permit buildings or structures in the Natural Heritage System (NHS) Zone except for structures directly related to the linear utility and uses otherwise permitted in the NHS Zone;

ii. permit any outdoor storage or works/maintenance yards; or,

iii. permit any land or building to be used for administrative offices, retail purposes, or vehicular or equipment maintenance

Potential Impacts

The preferred pipeline route is a linear corridor and is permitted in the Natural Heritage System designation within any zone. However, it must be demonstrated that there are no feasible alternative routes where the proposed route crossed the Natural Heritage System. This was undertaken through the route evaluation process for the Project as per the OEB guidelines (Section 2.0) and compliance of this ER.

Potential impacts of the Project on natural areas and mitigation and protective measures are outlined in Section 4.3.2.

Mitigation and Protective Measures

Section 4.3.2 of this report, the design, construction, site restoration and maintenance will be carried out in accordance with relevant environmental guidelines and best practices as outlined in this report.

Consultation will be undertaken with landowners along and adjacent to the proposed pipeline route, where applicable.

Municipal by-law and permits may be applicable such as tree cutting by-laws, Conservation Authority permits, MOECC D-guidelines, etc., and these are outlined in Section 1.2.5.

4.37

PROPOSED NATURAL GAS PIPELINE TO SERVE THE SEATON LAND DEVELOPMENT: ENVIRONMENTAL REPORT

Impact Identification, Assessment and Mitigation March 8, 2016

Net Impacts

With the implementation of the above mitigation and protective measures, no significant adverse residual impacts on land use are anticipated. It must be demonstrated to the municipality that no feasible alternatives are available where the proposed route crosses the Natural Heritage System designation in the Official Plan.

4.4.8 Archaeological Resources

A Stage 1 AA has been conducted for the proposed Project and the 5 m wide TWE. Copies of the Stage 1 Archaeological Assessments are located in Appendix E.

Potential Impacts

The study determined that the preferred route does not retain potential for the identification or recovery of archaeological resources and archaeological potential. However, portion of the TWE on the north side of Taunton Road does retain potential for the identification or recovery of archaeological resources and has archaeological potential. Therefore, a further Stage 2 AA is required for this area (see Appendix E).

Mitigation and Protective Measures

The findings of the Stage 2 AA, and any further necessary stages of archaeological assessment, will implement recommendations for archaeological resources. Wherever possible, archaeological sites that are determined to have cultural heritage value and interest should be mitigated in whole or in part by avoidance and preservation. If it should evolve that avoidance and preservation is not feasible, the site or sites should be mitigated by the implementation of Stage 4 salvage excavations. For any sensitive First Nation sites that could be subject to impact by the Project, the Stage 3 and 4 options will be evaluated in discussions with the appropriate First Nations.

Should previously unknown archaeological resources be uncovered or suspected of being uncovered during construction, ground disturbance in the find location should cease immediately. MTCS and an archaeologist licensed in the Province of Ontario should be notified immediately. A site-specific response plan should then be employed following further investigation of the specific find. The response plan would indicate under which conditions the ground disturbance activity in the find location may resume.

In the event that human remains are uncovered or suspected of being uncovered during ground disturbance, the above measures should be implemented along with notifying local police, the coroner’s office and the Cemeteries Regulation Unit of the Ontario Ministry of Government and Consumer Services (1-800-889-9768).

4.38

PROPOSED NATURAL GAS PIPELINE TO SERVE THE SEATON LAND DEVELOPMENT: ENVIRONMENTAL REPORT

Impact Identification, Assessment and Mitigation March 8, 2016

Net Effects

By continuing the above assessment, and implementing resulting mitigation measures and any necessary contingency plans, no significant adverse residual impacts on archaeological resources are anticipated.

4.4.9 Heritage Resources and Cultural Heritage Landscapes

A Heritage Overview has been undertaken along the preferred pipeline route through agency consultation and review of historic mapping (Appendix E). The Heritage Overview identified protected and previously identified heritage resources. A map of these resources crossed by the preferred pipeline route and within the Study Area is located in Appendix C, Figure No. 1.

Potential Impacts

The Project has the potential to directly impact two heritage resources during construction.

A Heritage Assessment will be undertaken prior to construction. Within the Report, the potential heritage resources will be assessed, the relationship of each heritage resource to the Project described, and the impacts of the proposed undertaking on each heritage resource analyzed. While describing the impacts of the proposed pipeline route on heritage resources, the Report will also provide recommendations pertaining to the mitigation of negative impacts to safeguard these resources during the construction and operation phases of the Project.

Mitigation and Protective Measures

Prior to construction, the above-referenced Heritage Assessment will be undertaken and submitted to the MTCS for their review and comment. The Report will contain mitigation measures for potential impacts, if required.

Net Impacts

With the implementation of the above mitigation and protective measures, no significant adverse residual impacts on heritage resources or cultural heritage landscapes are anticipated.

4.4.10 First Nations and Métis Nation Interests

The Study Area is within the boundary of the Williams Treaties (1923) (AANDC, 2015).The Project does not intersect any First Nation reserve land; however correspondence from CLFN (dated February 23) confirmed that the Project is located within their Traditional Territory, which is incorporated within the Williams Treaties Territory and is subject of a claim under Canada’s Specific Claims Policy. CLFN is also interested in any archaeological findings, as well as if any potential negative environmental impacts and potential impacts on their Aboriginal and Treaty

4.39

PROPOSED NATURAL GAS PIPELINE TO SERVE THE SEATON LAND DEVELOPMENT: ENVIRONMENTAL REPORT

Impact Identification, Assessment and Mitigation March 8, 2016

rights should occur as a result of new or unforeseen issues. Hiawatha First Nation and Mississaugas of Scugog Island First Nation also expressed interest in the archaeological assessment.

Potential Impacts

The proposed Project may impact CLFN Traditional Territory and/or rights.

Mitigation and Protective Measures

Enbridge has sought First Nations and MNO input into the Project (see Section 3.5.6). No other information has been obtained by Enbridge or provided by First Nations or the MNO with regards to traditional land and resource use. Enbridge will continue engaging with First Nation communities and the MNO as the Project moves forward.

Mitigation and protective measures for archaeology are discussed in Section 4.4.8.

Net Impacts

By continuing the above engagement, no significant adverse residual impacts on First Nations and Métis Nation interests are anticipated.

4.4.11 Infrastructure

Infrastructure identified for the purpose of this Project includes roads, hydrocarbon facilities, other buried pipelines, railways and other utilities. A map of infrastructure developed from existing databases is shown in Appendix C, Figure No. 1. Other utilities such as water and communication lines that may exist along road allowances are not illustrated on the map.

4.4.11.1 Roads

The proposed Project is located south of a controlled-access highway; Highway 407 Express Toll Route (407 ETR). The Study Area is traversed by several roads including Whitevale Road, Concession Road 5, Sideline 16, Brock Road, Mulberry Lane, Taunton Road, Sideline 22, Concession Road 4, Sideline 24, William Jackson Drive and Forbrock Street. The preferred pipeline route traverses Brock Road, Sideline 22 and Concession Road 4.

Hydrocarbon Facilities and Buried Pipelines

The preferred pipeline route traverses a high pressure petroleum products pipeline owned and operated by TNPI, between Sideline 22 and Concession Road 4. According to the Ontario Oil, gas and Salt Resources Library there are no oil and gas wells within the Study Area.

4.40

PROPOSED NATURAL GAS PIPELINE TO SERVE THE SEATON LAND DEVELOPMENT: ENVIRONMENTAL REPORT

Impact Identification, Assessment and Mitigation March 8, 2016

Railways

Outside of the Study Area, an active rail line owned by CPR runs along an Enbridge pipeline, south of Taunton Road. An abandoned rail line parallel to Sideline 16 is located east of the Study Area.

Utilities

The preferred pipeline route crosses an electric transmission line owned by Hydro One that runs along TNPI’s pipeline, between Sideline 22 and Concession Road 4.

A variety of buried and overhead utilities (e.g., telephone, low-voltage hydroelectric, fiber optic, watermains) are located in road allowance. Enbridge will locate buried and overhead utilities prior to construction.

Potential Impacts

The preferred pipeline route has the potential to interact with roads, hydrocarbon facilities and buried and overhead utilities. Potential impacts include damage and service interruptions to the infrastructure and safety harm to personnel.

Mitigation and Protective Measures

Consultation has been initiated, and will continue, with municipal personnel to obtain road crossing permits. Where roads will be crossed, a traffic management plan will be developed to ensure the safety of road users during the crossing (see Section 4.4.1).

It is anticipated that all utility crossings will be completed using the HDD technique.

Existing pipelines and utilities on lands which will be affected by trench excavation will be located and exposed. Machine operators will be informed where electrical transmission lines are present overhead. Lines that may interfere with the operation of construction equipment will be identified with warning poles strung together with rope and suspended red flags. In addition, crossing agreements and the conditions required with utilities, including Hydro one and TNPI, will be procured prior to the onset of construction activities and conditions adhered to. Measures to migrate induced voltage effects should be followed and are outlined in Enbridge’s Construction and Maintenance Manual, 2015 (Section 14.8).

Net Impacts

With the implementation of the above mitigation and protective measures, no significant adverse residual impacts on infrastructure are anticipated.

4.41

PROPOSED NATURAL GAS PIPELINE TO SERVE THE SEATON LAND DEVELOPMENT: ENVIRONMENTAL REPORT

Impact Identification, Assessment and Mitigation March 8, 2016

4.5 SUMMARY OF RECOMMENDATIONS

Table 4.4 provides a summary of the recommended supplemental studies, mitigation and protective measures identified in Sections 4.2-4.4.

4.42

PROPOSED NATURAL GAS PIPELINE TO SERVE THE SEATON LAND DEVELOPMENT: ENVIRONMENTAL REPORT

Impact Identification, Assessment and Mitigation March 8, 2016

Table 4.4: Summary of Potential Effects and Recommended Mitigation and Protective Measures

Environmental Feature(s) Potential Effect(s) Mitigation and Protective Measures

PHYSICAL FEATURES

Bedrock Geology and Drift Thickness Section 4.2.1

• No effects anticipated • N/A

Physiography & Surficial Geology Section 4.2.2

• Soil erosion • Slope stabilization and erosion controls for slopes will be required on the Project area, particularly in those areas proximal to watercourses and other drainage features. In addition to mitigation measures outlined in Enbridge’s Construction and Maintenance Manual, 2015 (Sections 8.0, Excavating) standard erosion and sediment control measures are discussed in Section 4.2.5 and erosion and sediment controls specific to protecting watercourses, etc. from sedimentation resulting from rainfall events during construction are discussed in Section 4.3.1.

Groundwater Section 4.2.3

Hydrostatic Testing and Dewatering/Sand-pointing • Downstream flooding,

erosion, sedimentation or contamination may result from uncontrolled discharges of water

Private Water Wells • Reduced water quality and quantity

may result from construction activities

Municipal Water Wells • No effects anticipated

Hydrostatic Testing and Dewatering/Sand-pointing • A Permit to Take Water will be required from the MOECC, should the volume

withdrawn from a natural source exceed 50,000 L/day. • To reduce the potential for erosion and scouring at dewatering points,

energy dissipation techniques should be used. Discharge piping should be free of leaks and properly anchored to prevent bouncing or snaking during surging. Discharge should be monitored to make sure that no erosion or flooding occurs.

• Protective measures may include dewatering at low velocities, dissipating water energy by discharging into a filter bag or equivalent, and utilizing protective riprap or equivalent.

• If energy dissipation measures are found to be inadequate, the rate of dewatering should be reduced or dewatering discontinued until satisfactory mitigation measures are in place. Discharge should be monitored to make sure that no erosion or flooding occurs.

• To assess the potential for introduction of contaminated water to soils or bodies of water, testing of hydrostatic discharge water and trench dewatering should be considered. An environmental consultant should be

4.43

PROPOSED NATURAL GAS PIPELINE TO SERVE THE SEATON LAND DEVELOPMENT: ENVIRONMENTAL REPORT

Impact Identification, Assessment and Mitigation March 8, 2016

Table 4.4: Summary of Potential Effects and Recommended Mitigation and Protective Measures

Environmental Feature(s) Potential Effect(s) Mitigation and Protective Measures

consulted to determine what testing is necessary for the discharge water.

Private Water Wells • A private well survey should take place to assess domestic groundwater use

within 100 m of the proposed pipeline and a private well monitoring program may be recommended for residents who rely on groundwater supply for domestic use.

Extractive Resources: Aggregates Section 4.2.4

• No effects anticipated • N/A

Soil and Soil Capability Section 4.2.5

• Damage to topsoil from excessive passes with heavy equipment

• Rutting and compaction of soils, as well as mixing of topsoil and subsoil may result from the movement of heavy machinery on wet soil

• Erosion of exposed soil may result from the loss of vegetative cover

• In addition to the soil erosion mitigation measures outlined in Enbridge’s Construction and Maintenance Manual, 2015 (Section 8.3, Topsoil Handling) the following measures are recommended:

o Topsoil should be stripped during dry soil conditions and stockpiled for use during cleanup and rehabilitation.

o Identification of the topsoil and subsoil interface should be carefully monitored to ensure that all topsoil with limited subsoil is stripped from the easement.

o To reduce construction impacts associated with wet climatic conditions, the other components of the construction are recommended to occur during dry soil conditions. If construction cannot be completed during the drier summer months when evapotranspiration is greatest, strict adherence to an Environmental Protection Plan is recommended.

o As an initial stage of construction, standard erosion and sediment control methods should be implemented on all active areas. Erosion and sediment control features should be regularly inspected and maintained. Additionally, erosion and sediment control features should be improved or added to in areas requiring more protection.

o In locations prone to erosion, soil stockpiles should be protected with silt fencing. Soil piles should be separated by at least 1 m to avoid

4.44

PROPOSED NATURAL GAS PIPELINE TO SERVE THE SEATON LAND DEVELOPMENT: ENVIRONMENTAL REPORT

Impact Identification, Assessment and Mitigation March 8, 2016

Table 4.4: Summary of Potential Effects and Recommended Mitigation and Protective Measures

Environmental Feature(s) Potential Effect(s) Mitigation and Protective Measures

mixing topsoil with subsoil. o On agricultural lands, subsoil should be stored on lands stripped of

topsoil (subsoil on subsoil). o Following periods of excessive rainfall or saturated soil conditions,

construction activities on agricultural lands should be suspended. During wet soil conditions heavy tracked and rubber-tired vehicles should be restricted from movement on agricultural soils. Usually, construction may continue from gravel work surfaces during wet soil conditions.

o To the extent feasible, construction activities should occur during drier times of the year. Lands affected by heavy rainfall events and wet soil conditions should be monitored, to avoid the potential for topsoil and subsoil mixing. Construction activities should be temporarily halted on lands where excessively wet soil conditions are encountered. Enbridge’s on-site inspection team should determine when construction activities may be resumed.

o If a situation develops that necessitates construction during wet soil conditions, soil protection measures should be implemented, such as: confining construction activity to the narrowest area practical, installing surface protection measures, and using wide tracked or low ground pressure vehicles.

o During construction activities, weather should be monitored to identify the potential onset of high wind conditions which can cause wind erosion. In the event that high winds occur, protective measures such as the following will be implemented:

suspend earth moving operations ; apply dust suppressants; and protect soil stockpiles with a cover, barrier or windscreen.

o In conjunction with the above measures, all required materials and equipment should be readily accessible and available for use as required.

4.45

PROPOSED NATURAL GAS PIPELINE TO SERVE THE SEATON LAND DEVELOPMENT: ENVIRONMENTAL REPORT

Impact Identification, Assessment and Mitigation March 8, 2016

Table 4.4: Summary of Potential Effects and Recommended Mitigation and Protective Measures

Environmental Feature(s) Potential Effect(s) Mitigation and Protective Measures

o Topsoil stripping on the RoW should be sufficiently wide to ensure that topsoil will be stockpiled on topsoil and subsoil will be stockpiled on subsoil. Inspection staff should ensure separation between topsoil storage piles and subsoil storage piles is maintained to reduce potential for soil mixing. If topsoil is required to be imported it should be tested for soybean cyst nematode to ensure that it is not contaminated (see Section 4.2.7).

o Where agricultural land adjacent to the RoW is typically accessed by crossing the RoW alternate access to the fields will be provided for the farm operator for the short period of time during construction that access across the RoW is not possible.

o If clean-up is not practical during the construction year, it should be undertaken in the year following construction, starting in May or June once the soils have sufficiently dried. Interim soil protection measures should be undertaken in sensitive areas to stabilize the RoW for over-wintering.

Soybean Cyst Nematode Section 4.2.6

• SCN may be spread from an impacted field to a non-impacted field by contaminated machinery, wind, contaminated boots, water erosion etc.

• If a field is identified as having SCN, the following mitigation measures should be considered for farm equipment travel from one field to another across the proposed pipeline route: o Ensure construction activity is restricted to the non-agricultural pipeline

construction area o In the event that the pipeline route or an adjacent farm field is known to

have SCN, advise the farm operator to remove soil from equipment before moving to the area that has not been impacted by SCN. This may involve thorough washing of equipment before moving equipment from an impacted field to non- impacted field;

o All properties impacted with SCN should be recorded and communicated to the Contractor.

o Any topsoil imported for cleanup activities should be analyzed for SCN by collecting a composite sample, sending it to a lab for analysis and reviewing results before any imported topsoil is placed on the easement. Imported suitable fill (not containing topsoil) or granular materials do not

4.46

PROPOSED NATURAL GAS PIPELINE TO SERVE THE SEATON LAND DEVELOPMENT: ENVIRONMENTAL REPORT

Impact Identification, Assessment and Mitigation March 8, 2016

Table 4.4: Summary of Potential Effects and Recommended Mitigation and Protective Measures

Environmental Feature(s) Potential Effect(s) Mitigation and Protective Measures

need to be tested for SCN.

Agricultural Tile Drains Section 4.2.7

• No effects anticipated • N/A

Natural Hazards Section 4.2.8

• Construction delays, sedimentation, and construction equipment entering a watercourse may result from flooding

• If flooding necessitates a change in the construction schedule, affected landowners and regulatory agencies should be notified and construction should continue at non-affected locations.

• Workspaces, unless necessary for watercourse crossings, should be located above the floodplain to the extent practical.

• A permit will be obtained from Toronto and Region Conservation Authority under Ontario Regulation 166/06.

BIOPHYSICAL FEATURES

Aquatic Species and Habitat Section 4.3.1

• Potential impacts may include decreased water quality (erosion, sedimentation, and accidental spills), disruption/harassment (vibration and noise) and loss of habitat

• Other impacts may include restrictions to habitat use and fish passage, changes to habitat such as substrate, increased erosion potential, loss of in stream cover and riparian shading

General Mitigation Measures • In addition to the mitigation measures outlined in Enbridge’s Construction

and Maintenance Manual, 2015 (Section 15.0, River and Creek Crossings), the following general mitigation measures, or equivalent, are recommended: o The following timing windows are applicable to in-water activities (if

required) at watercourses along the preliminary preferred route, with timing dependent on the thermal regime of each watercourse. Any in-water works within Urfé Creek and Ganatsekiagon Creek will require an ESA permit: Coldwater: In-water work permitted from July 1 to September 15 (no

work from September 16 to June 30); o Watercourses should not be obstructed in a way that impedes the free

movement of water and fish; o Prior to removal of the vegetation cover, effective mitigation techniques

for erosion and sediment should be in place to protect water quality. Disturbance to the area during construction should be limited and grubbing activities should be delayed until immediately prior to grading operations;

o Soil exposure should be minimized prior to commencing construction, and

4.47

PROPOSED NATURAL GAS PIPELINE TO SERVE THE SEATON LAND DEVELOPMENT: ENVIRONMENTAL REPORT

Impact Identification, Assessment and Mitigation March 8, 2016

Table 4.4: Summary of Potential Effects and Recommended Mitigation and Protective Measures

Environmental Feature(s) Potential Effect(s) Mitigation and Protective Measures

the period of time that soil remains exposed for grading should be limited. Exposed soils surrounding all watercourses should be seeded immediately following construction;

o Temporary erosion and sediment control measures should be maintained and kept in place until all work within or near a watercourse has been completed and stabilized. Temporary sediment control measures should be removed at the completion of the work but not until permanent erosion control measures have been established;

o Construction material, excess material, construction debris and empty containers should be stored away from watercourses and watercourse banks;

o All activities, including equipment maintenance and refueling, should be controlled to prevent entry of petroleum products or other deleterious substances, including any debris, waste, rubble or concrete material, into a watercourse, unless otherwise specified in the contract. These should be >100 m from the watercourse at all times. Any such material that inadvertently enters a watercourse should be removed by in a manner satisfactory to the environmental inspector;

o In the unlikely event of a spill, spills containment and clean-up procedures should be implemented immediately. Enbridge will contact the MOECC Spills Action Centre. The MOECC Spills Action Centre is the first point of contact for spills at the provincial and federal level;

o Conditions of water crossing permit(s), if applicable, will be adhered to; and

o Additional supplies should be maintained on-site, in a readily accessible location, for maintenance and contingency purposes. Prior to construction, adequate quantities of the materials listed below, or comparable substitutions, must be obtained in order to control erosion and sediment deposition: Sediment control fencing; Straw bales;

4.48

PROPOSED NATURAL GAS PIPELINE TO SERVE THE SEATON LAND DEVELOPMENT: ENVIRONMENTAL REPORT

Impact Identification, Assessment and Mitigation March 8, 2016

Table 4.4: Summary of Potential Effects and Recommended Mitigation and Protective Measures

Environmental Feature(s) Potential Effect(s) Mitigation and Protective Measures

Wooden stakes; Sand bags; Water energy dissipater; Filter cloth; Water pumps (including stand-by pumps and sufficient lengths of

hose); and Culvert.

Horizontal Direction Drill Mitigation Measures • Standard erosion and sediment control measures should be implemented

around drill and pipe staging areas; • Prior to initiating a HDD, appropriate geotechnical data should be obtained

to assist in determining the drill path; • Drilling equipment (e.g., drill rig, support equipment, sump) should be set up a

minimum of 30 m from the bank full width of the watercourses; • Clearing of vegetation or grading of watercourse banks should not occur

within 30 m from the bank full width of the watercourses, if possible; • A drilling mud release contingency plan should be prepared and kept on-

site; • Environmental inspectors should be present to watch for accidental mud

release into watercourses during HDD of watercourse crossings; • Bentonite-based drilling mud should be used without the use of additives

(except with approval from appropriate regulatory authorities); • Suitable drilling mud tanks or sumps should be installed to prevent

contamination of watercourses; • Berms or check dams should be installed downslope from drill entry and

anticipated exit points to contain the release of any drilling mud; and • Drilling mud should be disposed of in accordance with the appropriate

regulatory authority requirements. Bore Path Collapse Mitigation Measures • Fluid volumes, annular pressure and cutting returns should be strictly

4.49

PROPOSED NATURAL GAS PIPELINE TO SERVE THE SEATON LAND DEVELOPMENT: ENVIRONMENTAL REPORT

Impact Identification, Assessment and Mitigation March 8, 2016

Table 4.4: Summary of Potential Effects and Recommended Mitigation and Protective Measures

Environmental Feature(s) Potential Effect(s) Mitigation and Protective Measures

monitored to ensure bore hole plugging and fluid losses are detected and addressed immediately;

• Alternative drill paths should be evaluated to minimize exposure to challenging soil materials; and

• Drilling mud should be maintained in the borehole at all times. This can be facilitated by positioning the entry and exit points in areas with cohesion less soils (e.g., silt-sand zones).

Drilling Mud Release (Inadvertent Returns) Mitigation Measures • Appropriate berms, silt fencing and secondary containment measures (i.e.,

plastic tarp) should be installed around drilling and drilling mud management equipment at both bore entry and bore exit locations to contain operational spills;

• Operational spills should be cleaned-up daily to prevent mobilization of drilling mud off site during rain events;

• The directional drill should be designed so that drilling slurry pressure is minimized and the drilling rate is reduced in porous materials to minimize the chance of loss of circulation of the drilling slurry;

• Smooth operation of the drilling string and slurry pumping systems should be maintained to avoid pressure surges;

• Slurry viscosity through appropriate filtering of drilled material should be minimized to reduce the pressure gradient along the drill path due to frictional effects;

• Slurry volumes should be continually monitored to enable a quick response to any indications of lost circulation; and

• Any drilling mud that escapes onto land should be immediately contained and transferred into an on-site containment system.

Open Cut Crossing Mitigation Measures Flow Diversion/Dewatering • Wherever in-water works are required, the work area will be isolated from the

remainder of the surface water feature. Maintenance of downstream flow

4.50

PROPOSED NATURAL GAS PIPELINE TO SERVE THE SEATON LAND DEVELOPMENT: ENVIRONMENTAL REPORT

Impact Identification, Assessment and Mitigation March 8, 2016

Table 4.4: Summary of Potential Effects and Recommended Mitigation and Protective Measures

Environmental Feature(s) Potential Effect(s) Mitigation and Protective Measures

will avoid potential upstream flooding and desiccation of downstream aquatic habitat and organisms.

• Downstream flows will be maintained at crossing locations using damp and pump techniques.

• All dewatering operations will be managed to prevent erosion and/or release of sediment laden or contaminated water to the waterbody (e.g. settling basin, filter bag, energy dispersion measures).

• An isolation/contamination plan will be designed and implemented to isolate temporary in-water work zones to maintain clean flow to downstream/around the work zone at all times.

Fish rescue plan • Any fish in the work area will be transferred away from the construction area

using capture, handling, and release techniques to minimize harm and stress. The intakes of pumping hoses will be equipped with an appropriate device to avoid entraining and impinging fish (see Measures to Avoid Causing Harm to Fish and Fish Habitat (2013) at the following DFO website http://www.dfo-mpo.gc.ca/pnw-ppe/measures-mesures/measures-mesures-eng.html).

• Plans will be developed on a site specific basis and implemented by qualified professionals with the appropriate permitting in place.

Site restoration and Riparian Planting • Following construction, the bed and banks of the crossing locations will be

restored to pre-construction conditions to the extent possible in accordance with Enbridge’s Construction and Maintenance Manual, 2015 (Section 15.8: Site Restoration). Bank slopes will be restored to match existing grades, however alterations may be made to maintain slope stability and limit future erosion.

• Exposed banks will be re-vegetated with native shrubs and grasses to provide riparian cover and aid in sediment and erosion control. Stream beds will be restored to maintain slopes and tie in with existing grades. Bed material will be replaced to match pre-construction conditions.

Permitting

4.51

PROPOSED NATURAL GAS PIPELINE TO SERVE THE SEATON LAND DEVELOPMENT: ENVIRONMENTAL REPORT

Impact Identification, Assessment and Mitigation March 8, 2016

Table 4.4: Summary of Potential Effects and Recommended Mitigation and Protective Measures

Environmental Feature(s) Potential Effect(s) Mitigation and Protective Measures

• Permits under Ontario Regulation 166/06 will be required prior to construction activities in the regulated boundary.

• Due to the presence of Redside Dace in Urfé Creek and Ganatsekiagon Creek, the HDD drill entry and exit pits all construction activity must remain at least 30 m from the bank full width of the watercourses.

• The MNRF must be notified to determine if a Notice of Activity or Information Gathering Form is required for the HDD crossings.

• If activities are required within 30 m of the bank full width and will disturb more than 300 m2, then the MNRF must be contacted to determine if an ESA Permit is required.

Designated Natural Areas and Vegetation Section 4.3.2

• Removal of native vegetation • Introduction or spread of invasive

species • Indirect impacts may include dust,

erosion, and accidental spills

• Mitigation and protective measures are outlined in Section 4.2.5 for dust and erosion, and Section 4.3.1 for accidental spills.

• Environmental mitigation and protective measures during construction will include the following: o Minimize clearing and disturbance to natural areas to the extent possible,

including sensitive areas such as unstable soils, wetlands, and areas of significant groundwater recharge or discharge;

o Construction activities with the potential to remove migratory bird habitat, such as vegetation clearing, should be avoided to the extent possible during the breeding season which is generally from April 1- August 31 in southern Ontario (Environment Canada, 2014). Should vegetation clearing activities be unavoidable during this window, a program should be implemented to reduce and avoid impacts to migratory birds and their nests. This program should include preventative and mitigation measures but may also include avoidance of clearing during key sensitive periods and in key locations;

o The limits of clearing should be surveyed and staked in the field; o Clearing should be done during frozen or dry soil conditions to the extent

practical to limit disturbance to vegetation and terrain; o Tree cutting should be done in consideration of the Durham Region Tree

4.52

PROPOSED NATURAL GAS PIPELINE TO SERVE THE SEATON LAND DEVELOPMENT: ENVIRONMENTAL REPORT

Impact Identification, Assessment and Mitigation March 8, 2016

Table 4.4: Summary of Potential Effects and Recommended Mitigation and Protective Measures

Environmental Feature(s) Potential Effect(s) Mitigation and Protective Measures

Conservation Bylaw (#31-2012) and the City of Pickering Tree Protection By-Law;

o Tree removal in a protected area in the City should be done in accordance with the City of Pickering Tree Protection By-law 6108/03. Protected areas usually run through and adjacent to watercourses and green spaces. A permit is required for trees located in a designated protected area;

o The limits of the construction footprint should be identified in the field, to allow for the protection of off-site natural areas and vegetation;

o An invasive species management plan should be developed by Enbridge, as measures (e.g., equipment washing before site access) may be necessary to mitigate the spread of invasive species;

o A screening field program of wetlands and riparian areas should be undertaken prior to construction. The following recommendations for work within wetlands are recommended: Remove vegetation at ground level, leaving existing root systems.

Limit tree stump removal and grading activities; Install water control swales, as required, to facilitate cross easement

water movements; Establish travel areas by installing swamp mats; Strip the top 0.15 – 0.30 m of topsoil/muck separately from the subsoil

in the area disturbed by trenching; Regularly inspect the off-easement water regime, monitoring for

possible off-easement ponding; Storage areas for hazardous materials, chemicals, fuels and

lubricating oils should be located at least 100 m outside of wetland boundaries and should be situated in designated contained areas;

Construction equipment should be refueled at least 50 m outside of wetland boundaries;

Construction equipment traffic in wetland areas should be kept to the minimum necessary to complete the pipeline construction; and

4.53

PROPOSED NATURAL GAS PIPELINE TO SERVE THE SEATON LAND DEVELOPMENT: ENVIRONMENTAL REPORT

Impact Identification, Assessment and Mitigation March 8, 2016

Table 4.4: Summary of Potential Effects and Recommended Mitigation and Protective Measures

Environmental Feature(s) Potential Effect(s) Mitigation and Protective Measures

Post-construction, replace any small ephemeral ponds and seasonal depressions.

o A re-vegetation program appropriate to the land use should be initiated for all work areas disturbed during construction(refer to Section 27.0 of Enbridge’s Construction and Maintenance Manual);

o In the event that trees are required to be removed, a tree replacement program should be undertaken, satisfactory to the landowner, and consistent with any municipal requirements; and

o One year following construction, planted vegetation should be inspected for survival, in areas of severe dieback, dead or diseased planted vegetation should be replaced.

Wildlife and Wildlife Habitat Section 4.3.3

• Direct mortality may result from construction vehicles

• Habitat degradation or destruction may result from vegetation removal and/or accidental spills

• Sensory disturbance of wildlife during construction

• Mitigation and protective measures are outlined in Section 4.3.2 for vegetation removal and Section 4.3.1 for accidental spills.

• Environmental mitigation and protective measures during construction include the following: o Detailed design of the pipeline should be reviewed to avoid and minimize

impact upon wildlife habitat and vegetated areas to the extent possible; o Construction activities with the potential to remove migratory bird habitat,

such as vegetation clearing, should be avoided to the extent possible during the breeding season which is generally from April 1- August 31 in southern Ontario (Environment Canada, 2014). Should vegetation clearing activities be unavoidable during this window, a program should be implemented to reduce and avoid impacts to migratory birds and their nests. This program should include preventative and mitigation measures but may also include avoidance of clearing during key sensitive periods and in key locations;

o Trench construction should be limited in duration and followed as closely as practical with backfill operations, to facilitate the minor occurrences of wildlife movement across the trench;

o The contractor should inform their personnel not to threaten, harass or injure wildlife;

4.54

PROPOSED NATURAL GAS PIPELINE TO SERVE THE SEATON LAND DEVELOPMENT: ENVIRONMENTAL REPORT

Impact Identification, Assessment and Mitigation March 8, 2016

Table 4.4: Summary of Potential Effects and Recommended Mitigation and Protective Measures

Environmental Feature(s) Potential Effect(s) Mitigation and Protective Measures

o Where practical avoid construction within 20 m of wetland communities during the amphibian breeding season (March 1 – June 30);

o All brush and trees felled should be removed immediately from the Project footprint to discourage use of these features by snakes; and

o Precautionary mitigation measures to be implemented in the unlikely event that a wildlife encounter occurs include: Equipment and vehicles are to yield the right-of-way to wildlife; and If wildlife are encountered during construction, personnel are required

to move away from the animal and wait for the animal to move off the construction site.

Species at Risk Section 4.3.4

• Impact to potential Butternuts. • Prior to any tree removals it is recommended that a Butternut Survey be completed to confirm the presence or absence of this species in (or within 25 m of) the work area, in particular within the TWE. In the event that Butternut is found, a Butternut Health Assessment can be conducted and, if required, ESA authorization obtained.

SOCIO-ECONOMIC ENVIRONMENT

Residents and Businesses Section 4.4.1

• Noise, dust and equipment exhaust may result from construction activity

• Temporary traffic and dust emissions from trucks during construction

• Aesthetics of the landscape will be temporarily affected

• Access to property may be temporary impeded

• Potential safety concerns exist where properties, residents and vehicles come in proximity to construction activities

• During construction, motorized construction equipment should be equipped with mufflers and silencers.

• Company and construction personnel should avoid idling of vehicles; vehicles or equipment should be turned off when not in use, unless required.

• Activities that create noise should be restricted to daylight hours when possible, and adhere to local noise by-laws; sources of continuous noise, such as portable generators, should be shielded or located so as to reduce disturbance to residents and businesses.

• Where pipeline installation will take an extended time period to complete, such as watercourse and road crossings, an assessment should be undertaken to determine the suitability and effectiveness of temporary noise barriers adjacent to residential or business properties.

• Site practices during construction should be implemented that are in line with the Environment Canada document ‘Best Practices for the Reduction of Air

4.55

PROPOSED NATURAL GAS PIPELINE TO SERVE THE SEATON LAND DEVELOPMENT: ENVIRONMENTAL REPORT

Impact Identification, Assessment and Mitigation March 8, 2016

Table 4.4: Summary of Potential Effects and Recommended Mitigation and Protective Measures

Environmental Feature(s) Potential Effect(s) Mitigation and Protective Measures

Emissions from Construction and Demolition Activities’ (Environment Canada, 2005), which may include: o Maintaining equipment in compliance with regulatory requirements; o Protecting stockpiles of friable material with a barrier or windscreen in the

event of dry conditions and dust; o Dust suppression of source areas; and o Covering loads of friable materials during transport.

• Additional consultation with residents and businesses will be held before construction commences. With respect to local viewscapes, restoration of the construction area will leave little evidence that a pipeline exists.

• Construction should be conducted as expeditiously as possible, to reduce duration of activities.

• Access to residential properties should be maintained at all times. • The contractor should implement a traffic management plan for all roads

affected by construction, which at a minimum outlines measures to: o Control the movement of materials and personnel to and from the

construction site; o Post signs to warn oncoming motorists of construction activity o Control traffic at road crossings; o Reduce on-road disturbance and land closures; o Store equipment as far from the edge of the road as practical; and o Install construction barricades at road crossings.

Institutional Services and Facilities Section 4.4.2

• No effects anticipated • N/A

Culture, Tourism & Recreational Facilities Section 4.4.3

• No effects anticipated • N/A

4.56

PROPOSED NATURAL GAS PIPELINE TO SERVE THE SEATON LAND DEVELOPMENT: ENVIRONMENTAL REPORT

Impact Identification, Assessment and Mitigation March 8, 2016

Table 4.4: Summary of Potential Effects and Recommended Mitigation and Protective Measures

Environmental Feature(s) Potential Effect(s) Mitigation and Protective Measures

Economy & Employment Section 4.4.4

• Direct and indirect business income and employment income

• An increase in tax revenues

• Enbridge should make all reasonable efforts where practicable to procure services and materials from local suppliers, where services or materials are available in required quantity and at competitive prices.

Contaminated Sites Section 4.4.5

• Potential to encounter contaminated lands.

• Should contaminated soils be encountered during construction, Enbridge should implement their Suspect Soils Program (see Section 8.13 of Enbridge’s Construction and Maintenance Manual, the ECMM for2015 for further details).

Waste Management Section 4.4.6

• Potential soil, groundwater, and/or surface water contamination may result from improper disposal of waste material generated during construction

• Nuisance to adjacent properties may result from uncontained litter generated during construction

• All construction wastes should be disposed of in accordance with Enbridge’s Construction and Maintenance Manual, 2015.

• Enbridge should undertake responsible management of excess fill. When details on excess fill volumes are known, disposal locations should be determined and appropriate permitting obtained.

• A site-specific waste collection and disposal management plan should be implemented, which may include: o Waste materials, sanitary waste and recycling transported off-site by

private waste contractors licensed by the MOECC; o Contractors required to remove their excess materials from the site; o Labelling and storage of hazardous and liquid wastes in a secure area

that would contain material in the event of a spill; and o Implementation of a waste management program consisting of

reduction, reuse, and recycling of materials. Land Use Section 4.4.7

• The proposed pipeline is permitted in the Natural Heritage designation and any zone, therefore no potential impacts are anticipated

• Potential impacts on natural areas, are outlined in Sections 4.3.2

• Section 4.3.2 of this report, the design, construction, site restoration and maintenance will be carried out in accordance with relevant environmental guidelines and best practices as outlined in this report.

• Consultation will be undertaken with landowners along and adjacent to the proposed pipeline route, where applicable.

• Municipal by-law and permits may be applicable such as tree cutting by-laws, Conservation Authority permits, MOECC D-guidelines, etc., and these are outlined in Section 1.2.5.

4.57

PROPOSED NATURAL GAS PIPELINE TO SERVE THE SEATON LAND DEVELOPMENT: ENVIRONMENTAL REPORT

Impact Identification, Assessment and Mitigation March 8, 2016

Table 4.4: Summary of Potential Effects and Recommended Mitigation and Protective Measures

Environmental Feature(s) Potential Effect(s) Mitigation and Protective Measures

Archaeological Resources Section 4.4.8

• Damage or destruction of archaeological resources may result from excavation and construction

• The findings of the Stage 2 Archaeological Assessment and any further necessary stages of archaeological assessment, will implement recommendations for archaeological resources.

• Wherever possible, archaeological sites that are determined to have cultural heritage value and interest should be mitigated in whole or in part by avoidance and preservation. If it should evolve that avoidance and preservation is not feasible, the site or sites should be mitigated by the implementation of Stage 4 salvage excavations.

• For any sensitive First Nation sites that could be subject to impact by the Project, the Stage 3 and 4 options will be evaluated in discussions with the appropriate First Nations.

• Should previously unknown archaeological resources be uncovered or suspected of being uncovered during construction, ground disturbance in the find location should cease immediately. MTCS and an archaeologist licensed in the Province of Ontario should be notified immediately. A site-specific response plan should then be employed following further investigation of the specific find. The response plan would indicate under which conditions the ground disturbance activity in the find location may resume.

• In the event that human remains are uncovered or suspected of being uncovered during ground disturbance, the above measures should be implemented along with notifying local police, the coroner’s office and the Cemeteries Regulation Unit of the Ontario Ministry of Government and Consumer Services (1-800-889-9768).

Heritage Resources and Cultural Heritage Landscapes Section 4.4.9

• Destruction, alteration, direct or indirect obstruction, a change in land use, shadows that alter the appearance of a heritage attribute or change the viability of a natural feature, and land disturbances (i.e. a change in grade that alters soils and drainage patterns) may result

• Prior to construction, a Heritage Assessment will be prepared and submitted to the MTCS for their review and comment. The Report will contain mitigation measures for potential impacts, if required.

4.58

PROPOSED NATURAL GAS PIPELINE TO SERVE THE SEATON LAND DEVELOPMENT: ENVIRONMENTAL REPORT

Impact Identification, Assessment and Mitigation March 8, 2016

Table 4.4: Summary of Potential Effects and Recommended Mitigation and Protective Measures

Environmental Feature(s) Potential Effect(s) Mitigation and Protective Measures

from excavation and construction.

First Nations and Métis Nation Interests Section 4.4.10

• Potential to affect CLFN Traditional Territory and/or rights

• Enbridge has sought First Nations and MNO input into the Project (see Section 3.5.6). Engagement will continue as the Project moves forward.

• Mitigation and protective measures for archaeology are discussed in Section 4.4.8.

Infrastructure Section 4.4.11

• Potential to damage and service interruptions to infrastructure and compromise the safety of workers and surrounding residents may result from interactions with roads, hydrocarbon facilities and buried and overhead utilities during construction

• Consultation has been initiated, and will continue, with municipal personnel to obtain road crossing permits. Where roads will be crossed, a traffic management plan will be developed to ensure the safety of road users during the crossing (see Section 4.4.1).

• It is anticipated that all utility crossings will be completed using the HDD technique.

• Existing pipelines and utilities on lands which will be affected by trench excavation will be located and exposed.

• Machine operators will be informed where electrical transmission lines are present overhead. Lines that may interfere with the operation of construction equipment will be identified with warning poles strung together with rope and suspended red flags. In addition, crossing agreements and the conditions required with utilities, including Hydro one and TNPI, will be procured prior to the onset of construction activities and conditions adhered to.

• Measures to migrate induced voltage effects should be followed and are outlined in Enbridge’s Construction and Maintenance Manual, 2015 (Section 14.8).

4.59