improving performance
TRANSCRIPT
www.neimagazine.com May2014
ImprovingperformanceInside WANO peer reviews (below) page 23
Rajasthan 5 tops 2013 full-year load factors league tables page 26
Dealing with primary-circuit cracks and leaks page 20
NewneutrontransportsimulationsUsing Monte Carlo to estimate extent of reactor activation page 13
Going pin-by-pin in AP1000 first core page 33
NU
CLE
AR
EN
GIN
EE
RIN
G IN
TER
NATIO
NA
L MAY
2014
001nei0514cover.indd 2 14/04/2014 14:51
Decontamination & decommissioning
NUCLEAR ENGINEERING INTERNATIONAL | www.neimagazine.com May 201416
Aqueous, in situ primary circuit decontaminationA technology that removes activity and corrosion products from inner pipe and vessel surfaces yielded overall decontamination factors of 80-90 at Unterweser and Neckarwestheim 1, and factors as high as 150 for steam generator tubing. By Christian Topf, Luis Sempere-Belda, Kai Tscheschlok and Klaus Reuschle
Germany was confronted with
the decontamination and
decommissioning (D&D) issue when
the 13th amendment to the German Atomic
Energy Act was passed in the backlash
following the Fukushima accident. With it,
Germany’s nuclear programme reversed
almost overnight from life extension to
immediate and permanent shut down. This
caused a major overhaul in the utilities’
operational and financial strategies, forcing
them to re-examine the cost-effectiveness
of their D&D programmes.
All existing decommissioning strategies
were considered, but immediate
decommissioning after the operational
phase soon emerged as the favoured
option for all the country’s utilities. The
experience accumulated in D&D in Europe
over the last few decades, especially in
Germany, has established full system
decontamination (FSD) – simultaneous
decontamination of the complete primary
circuit and auxiliary systems – as the key
element of immediate decommissioning.
It is considered to be state-of-the-art
best practice. It has been used in recent
decommissioning projects and is planned
for projects in preparation.
Over the last few decades AREVA has
performed FSD for return-to-service and
decommissioning at 18 reactors worldwide
– some immediately or several years after
final shutdown. The complexity of such
FSD projects always requires a flexible
approach regarding process chemistry and
control to achieve the best possible result.
The multi-cycle CORD concept (chemical-
oxidation-reduction-decontamination), with
its dynamic process control and flexible
application times, makes best use of the
chemicals employed, helping minimise the
waste generated during decontamination.
FSDs at Unterweser in 2012 and
Neckarwestheim 1 in 2013 were the first
such applications in Germany in the
aftermath of the Fukushima event and the
German decision to phase out nuclear.
Engineering and chemistry conceptThe key to a successful FSD application is
symbiosis between system operation and
the chemical concept.
The first and vital step is to clearly
define the main systems in the
decontamination area. To achieve the best
possible decontamination the area should
include all the systems that are in contact
with primary coolant during normal plant
operation. A variety of auxiliary systems
(for example reactor coolant storage
system, waste water treatment system and
the nuclear exhaust system) support the
application.
For PWRs the typical decontamination
area is the primary circuit, including the
RPV with internals, pressurising system,
residual heat removal system (RHR),
chemical volume control system (CVCS),
and reactor water clean-up system. For
BWRs, it includes the reactor vessel,
recirculation system (depending on the
design of the plant), RHR system, and
reactor water clean-up (RWCU) system.
To make sure the decontamination
solution reaches all parts of the system,
the number of dead legs (runs of piping
ending in a termination) are minimised by
making temporary connections to them
with hoses and pipes. A flushing/rinsing
programme at the end of decontamination
helps to flush the remaining dead legs.
Figure 2 shows the schematic drawings
of the decontamination area of the FSDs
per-formed recently at Unterweser (2012,
left side) and Neckarwestheim 1 (2013,
right side).
The detailed engineering approach
for these plants was designed in close
collaboration between AREVA and the
utilities. The basic technical data of the
plants are listed in Table 1.
The system was adapted and the
technical modes of operation were
substantially developed and configured by
experienced plant operational personnel
in cooperation with AREVA engineering
and chemical personnel. Plant operators
controlled the plant systems during the
FSD.
Top: Inspection of a post-FSD pump (Neckarwestheim). Bottom: Pressurizer spray valves (left) and DN 50 valve after FSD, revealing clean surfaces (Unterweser)
016_018nei0514fsd.indd 16 14/04/2014 14:56
Decontamination & decommissioning
www.neimagazine.com | NUCLEAR ENGINEERING INTERNATIONALMay 2014 17
The main reactor coolant pumps
and the RHR system pumps were
used to recirculate the solution in the
decontamination area, and the thermal
energy liberated by operating them
supplied the necessary process heat.
The negative pressure suction head to
run the coolant pumps during FSD mode
was achieved by using one of the RHR
accumulators as a pressurizer. Based on
the different main coolant pump designs
(see Table 3) the operational pressure
during FSD differed from around 21
bar (~300 psi) to 26 bar (~375 psi). The
plant pressurizer was operated in solid
mode to obtain the highest possible
decontamination on the complete
surface. To ensure exchange of the
decontamination solution the main and
auxiliary spray lines were operated either
in parallel or alternately during the FSD.
Different approaches used the plants’
RHR systems for process temperature
control. At Unterweser temperature was
regulated using all four RHR redundancies.
At Neckarwestheim 1 RHR system 30 was
excluded from the decontamination area.
Within the regulatory framework RHR
system 30 had to stand by under normal
conditions at any time because it provides
redundancy for the spent fuel pool cooling
system, so temperature was regulated using
only the two other RHR 10/20 systems.
For both applications proprietary
decontamination equipment Automated
Modular Decontamination Appliance
(AMDA®) was used with the plant´s own
systems during FSD. This allowed AREVA’s
radwaste volume-reducing technologies
to be applied, such as UV decomposition
of the decontamination chemicals. AMDA
was also used for sampling during
the application, for detailed process
control and mechanical filtration of
the decontamination solution. AMDA
equipment, which can include pumps,
heaters, ion exchange columns, filters, UV
reactors, sampling modules, monitoring
systems, automation and remote controls
and chemical injection equipment, was
connected in each case to two different
RHR systems (see Figure 3).
The CVCS and RWCU systems in
Neckarwestheim were part of the
decontamination area and were operated
under normal operating conditions and
temperature restrictions. In Unterweser
the sensitive centrifugal charging pumps
in the CVCS were replaced by an external
pump to ensure undisturbed operation
during FSD application but remaining in
standby mode for redundancy. In contrast
to Neckarwestheim, the Unterweser RWCU
system supported the clean-up of the
decontamination solution during certain
phases of the application. The increase in
the cleaning rate reduced treatment time
and supported process control during the
FSD operation.
To have maximum decontamination
effect at minimum material impact, a
five-cycle chemical oxidation reduction
decontamination (CORD) UV chemical
decontamination concept using
permanganic acid (HP) was developed
by AREVA and the plants. Generally
speaking, the formulation is adjusted to
the characteristics of the oxide present.
Table 1: Basic technical data
Unterweser Neckarwestheim 1
Reactor type PWR, 4 loop, 1410 MWe PWR, 3 loop, 840 MWe
Decontamination areaPrimary circuit / 4 RHR systems
/ CVC systemPrimary circuit / 2 RHR systems / CVC system / RWCU system
Auxiliary systems RCS / WWTS / NES / RWCU RCS / WWTS / NES / RWCU
Total surface area 22,500 m2 (~ 278,000 ft²) 18,000 m2 (~ 194,000 ft²)
Total system volume 540 m3 (~ 142,000 gal) 360 m3 (~ 95,100 gal)
Reactor coolant pump supplier KSB Andritz
Operational pressure ~ 21 bar (~ 300 psi) ~ 26 bar (~ 375 psi)
Operational temperature 60 - 95 °C (140-200 °F) 60 - 95 °C (140-200 °F)
AMDA connection points RHR 30 / 40 RHR 10 / 20
Application time 35 days 25 days
Collective radiation exposure for on-site activities
70 mSv 61 mSv
Loop20
Loop10
Loop30 Loop
30
Loop10
Loop20
Loop40
AMDA AMDA
RHR 20
RHR 20
RHR 30
RHR 10
RWCU
RHR 10 RHR 40
RPV
CVCS
RWCU
CVCS
RHR 24
RHR 30
Spent fuelpool
RPV
Primary circuit Residual heat removal system Chemical volume control system
Pressurizing system Reactor water clean up system AREVAs decontamination equipment AMDA
Figure 2: Schematic Drawings of the decontamination area at Unterweser (left) and Neckarwestheim 1 (right)
NPP-Systemlow dose-rate
Demineralizedwater
ActivityCorrosion productsMn**Ion exchange resins
Demineralizedwater
Metallicallyclean surface
ActivityCorrosion productsMn**Ion exchange resins
NPP-Systemlow dose-rate
Demineralizedwater
Demineralizedwater
Metallicallyclean surface
CORD UV Cydes OxidationReductionDecontaminationDecomposition
CORD UV Cydes OxidationReductionDecontaminationDecomposition
Carbondioxide
CORDchemicals
Carbondioxide
CORDchemicals
ActivityCorrosion products
ActivityCorrosion products
NPP-Systemhigh dose-rateNPP-System
high dose-rate
Figure 3: Logistics of the HP CORD UV process
016_018nei0514fsd.indd 17 14/04/2014 14:56
Decontamination & decommissioning
NUCLEAR ENGINEERING INTERNATIONAL | www.neimagazine.com May 201418
The main process variables are volume,
surface, construction materials, oxide
characteristics, operating history, process
temperature, ion exchange rate and
chemical concentration.
The entire process takes just one fill of
water. Each cycle is divided into the following
steps:
■ Oxidation with HP
■ Reduction of HP with decontamination
chemical
■ Decontamination
■ UV decomposition of decontamination
chemicals and clean-up.
Oxidation prepares the oxide layers for
their removal, but does not mobilize large
amounts of activity and corrosion products
itself. The mobilization of activity and
oxide dissolution take place during the
decontamination step. The water is not
flushed. The dissolved corrosion products
and activity are removed via ion exchangers
and the water is reused in the next cycle.
Bypass purification is performed during
the decontamination step to fix the
dissolved activity and corrosion products
on ion exchange resins (Co-60 is the
dominant nuclide in recently shut-down
plants, and the main cause of dose).
After the decontamination step the
ultraviolet decomposition of the remaining
decontamination chemicals takes place
in-situ. The decontamination chemicals are
decomposed to water and carbon dioxide
while the remaining activity and corrosion
products are being purified. Through this
procedure, the system water reaches a
purity that is close to demineralised water
at the end of each cycle, so the water can
be reused in the next cycle.
The HP CORD UV process does not
require a predetermined number of cycles
to be performed. The number of cycles is
varied depending on the decontamination
tasks and targets.
The cycle duration depends on the speed
of dissolution of deposits, the total amount
of deposits present, and the speed of
removal of dissolved species from solution.
During application the decontamination
solution is analysed in the hot lab and
the progress of the process is determined
through analyses of corrosion products and
radionuclides in solution.
ResultsThe decontamination targets for
Unterweser and Neckarwestheim
assumed immediate decommissioning, but
maintained the possibility of a return to
service. They were:
■ Minimizing the total activity inventory
■ Reducing dose rates at plant systems,
especially the primary circuit with its
heavy components, to facilitate further
handling
■ Minimizing ambient dose rates to lower
future personnel doses (ALARA)
■ Avoiding a significant shift of the
gamma-to-alpha ratio (which can
have consequences in later stages
of decommissioning operations,
particularly concerning health physics
and radiation protection monitoring).
Based on these targets, five HP CORD UV
cycles were applied in both PWRs. During
on-site application AREVA’s chemical
experts provided 24-hour supervision.
Table 2 summarises the results. The
decontamination factors are the ratio of the
contact dose rates before and after FSD at
specific measuring points.
Based on these results and the total
surface of the decontamination area, the
average oxide layer removed is 4.3 µm.
Considering the amount of corrosion
products removed and the total surface
of the decontamination area, the average
oxide layer in Unterweser is 4.9 µm.
During the commissioning phase and
in the course of the FSD applications at
Unterweser and Neckarwestheim the
primary coolant was permanently filtered.
In the Unterweser plant 9x1012 Bq of
activity (Co-60) was additionally removed
by filtration.
A number of measuring points were
identified in the decontamination area to
determine the average decontamination
factor. In Unterweser (a four-loop PWR)
83 measuring points were used, and in
Neckarwestheim (a three-loop PWR) 66
were used. Before FSD, at Unterweser
100% of the points in the decontamination
area had dose rates above 0.5 mSv/h (0.05
Rem), while at in Neckarwestheim the
distribution was about 90%. The initial
dose rates in the primary systems differed
significantly, from an average of 5 mSv/h
(0.5 Rem) in Unterweser to 630 µSv/h
(0.063 Rem) in GKN 1.
The contact dose rates in the primary
systems after FSD were significantly lower,
even in the area of plugged tubes. They
averaged 30 µSv/h (0.003 Rem) in both
plants. The distribution of dose rates in
the decontamination area of both plants
shifted significantly, with 90% of the
measuring points lower than 0.1 mSv/h
(0.01 Rem).
AREVA’s HP CORD UV concept, adjusted
to the needs of these plants, resulted
in a very high decontamination while
keeping all systems operational. Extensive
inspection programmes after treatment
revealed no detrimental effects on the
material. Technically, the plants could
return to operation.
Performing the decontamination right
after the operational phase proved to be a
great advantage. The key to success was
involving the plant’s own personnel during
all phases of the decontamination. Their
detailed system knowledge, expertise, and
extended operational experience, together
with the close and open cooperation with
AREVA’s decontamination personnel,
produced the best result. ■
References
Dr. Christian Topf ([email protected]), Luis Sempere-Belda ([email protected]), AREVA GmbH, Abteilung Chemistry Services, Paul-Gossen-Str. 100, 91054 Erlangen; Kai Tscheschlok ([email protected]), E.ON Kernkraft GmbH, Kernkraftwerk Unterweser, Abteilung TMT, Dedesdorfer Str. 2, 26935 Stadland. Klaus Reuschle ([email protected]), EnBW Kernkraft GmbH, Kernkraftwerk Neckarwestheim, Im Steinbruch, 74382 Neckarwestheim, Germany
Table 2: Full-scope decontamination applications
Unterweser (KKU)
Neckarwestheim-1 (GKN1)
Activity & corrosion products removed
Corrosion products (Fe, Cr, Ni) 459 kg 260 kg
Total activity removed (> 99% Co-60) 9.1 x1013 Bq (2,460 Ci) 1.1x1013 Bq (297 Ci)
Decontamination factors (DF) achieved
DF overall 94.5 (83 MP) 81 (66 MP)
DF of primary circuit (loop & pressurizer) 158 (26 MP) 31 (20 MP)
DF of steam generator tubing area 147 (16 MP) 224 (15 MP)
DF of auxiliary systems (RHR / CVCS) 35 (41 MP) 44 (31 MP)
Waste
Ion exchange resins 21 m³ (planned 23 m³) 11 m³ (planned 15 m³)
MP = measuring point
016_018nei0514fsd.indd 18 14/04/2014 14:56