in the united states court of appeals for the ninth...
TRANSCRIPT
IN THE UNITED STATES COURT OF APPEALS
FOR THE NINTH CIRCUIT
CENTER FOR COMMUNITY ACTION & ENVIRONMENTAL JUSTICE; et al.,
Petitioners,
v.
FEDERAL AVIATION ADMINISTRATION; et al.,
Respondents,
SAN BERNARDINO INTERNATIONAL AIRPORT AUTHORITY; EASTGATE BLDG 1, LLC,
Intervenors-Pending.
No. 20-70272
No. 20-70464
STATE OF CALIFORNIA, by and through Xavier Becerra, in his official capacity as Attorney General,
Petitioner,
v.
FEDERAL AVIATION ADMINISTRATION; et al.,
Respondents.
On Petition for Review of an Order By the Federal Aviation Administration
PETITIONER STATE OF CALIFORNIA’S OPENING BRIEF
XAVIER BECERRA Attorney General of California EDWARD H. OCHOA SENIOR ASSISTANT ATTORNEY GENERAL CHRISTIE VOSBURG Supervising Deputy Attorney General YUTING YVONNE CHI Deputy Attorney General State Bar No. 310177 Attorneys for State of California
1515 Clay Street, 20th Floor P.O. Box 70550 Oakland, CA 94612-0550
Telephone: (510) 879-3298 Fax: (510) 622-2270 Email: [email protected]
Case: 20-70272, 06/30/2020, ID: 11739107, DktEntry: 57-1, Page 1 of 47
TABLE OF CONTENTS
Page
i
INTRODUCTION ......................................................................................... 1 JURISDICTIONAL STATEMENT .............................................................. 3 STATEMENT OF ISSUES ........................................................................... 6 STATEMENT OF THE CASE ..................................................................... 7 STATEMENT OF THE FACTS ................................................................... 9
I. The Project ................................................................................ 9 II. Impacts on the Surrounding Communities and the
Environment ............................................................................ 10 III. Environmental Review ............................................................ 13 IV. Project Construction and Operations ...................................... 16 V. Relevant Procedural History ................................................... 18
SUMMARY OF ARGUMENT ................................................................... 18 STANDARD OF REVIEW ......................................................................... 20 ARGUMENT ............................................................................................... 21
I. The Order Must Be Set Aside Because the FAA Failed to Prepare an EIS as Required by NEPA and Failed to Articulate Why Findings of Significant Impact in the CEQA Analysis Did Not Trigger the Preparation of an EIS Under NEPA. ................................................................... 22
II. The FAA Order Must Be Set Aside Because the NEPA Analysis Failed to Discuss or Reconcile Factual Inconsistencies Before the Agencies, Insufficiently Justified Its Determinations, and Potentially Underestimated Project Mobile Source Emissions by 60 Percent. .................................................................................... 27 A. The FAA Failed to Discuss or Reconcile
Inconsistent and Inaccurate Truck Trip Estimates Used to Model Mobile Source Emissions and Failed to Justify Its Use of Those Estimates. ................ 28
Case: 20-70272, 06/30/2020, ID: 11739107, DktEntry: 57-1, Page 2 of 47
TABLE OF CONTENTS (continued)
Page
ii
B. The FAA’s Errors in Modeling Mobile Source Emissions Means that It Potentially Underestimated Mobile Source Emissions by 60 Percent, Rendering Flawed the EA’s Determination of “Significance.” ................................. 31
III. The FAA Order Must Be Set Aside Because It Fails to Consider California Greenhouse Gas Emissions Requirements Imposed to Protect the Environment. .............. 33
CONCLUSION AND REQUESTED RELIEF ........................................... 36
Case: 20-70272, 06/30/2020, ID: 11739107, DktEntry: 57-1, Page 3 of 47
TABLE OF AUTHORITIES
Page
iii
CASES
Bark v. U.S. Forest Serv. 958 F.3d 865 (9th Cir. 2020) ............................................................. 28, 33
Bennett v. Spear 520 U.S. 154 (1997)........................................................................... 20, 21
Blue Mountains Biodiversity Project v. Blackwood 161 F.3d 1208 (9th Cir. 1998) ..................................................... 20, 26, 35
Bob Marshall All. v. Hodel 852 F.2d 1223 (9th Cir. 1988) ............................................... 23, 26, 29, 35
California v. U.S. Dep’t of Transp. 260 F. Supp. 2d 969 (N.D. Cal. 2003) ..................................................... 24
Ctr. for Biological Diversity v. Nat’l Highway Traffic Safety Admin. 538 F.3d 1172 (9th Cir. 2008) ..................................................... 21, 23, 27
Earth Island Inst. v. U.S. Forest Serv. 351 F.3d 1291 (9th Cir. 2003) ................................................................. 21
Found. for N. Am. Wild Sheep v. U.S. Dep’t of Agric. 681 F.2d 1172 (9th Cir. 1982) ................................................................. 27
Marsh v. Or. Nat. Res. Council 490 U.S. 360 (1989)..................................................................... 28, 31, 33
Motor Vehicle Mfr. Ass’n v. State Farm Mutual 463 U.S. 29 (1983)............................................................................ passim
N. Idaho Cmty. Action Network v. U.S. Dep’t of Transp. 545 F.3d 1147 (9th Cir. 2008) ........................................................... 21, 23
Native Ecosystems Council v. Tidwell 599 F.3d 926 (9th Cir. 2010) ................................................. 20, 22, 25, 26
Case: 20-70272, 06/30/2020, ID: 11739107, DktEntry: 57-1, Page 4 of 47
TABLE OF AUTHORITIES (continued)
Page
iv
Ocean Advocates v. U.S. Army Corps. of Eng’rs 402 F.3d 846 (9th Cir. 2005) ............................................................. 27, 35
Or. Nat. Res. Council Fund v. Goodman 505 F.3d 884 (9th Cir. 2007) ................................................................... 20
Pac. Coast Fed’n of Fishermen’s Ass’ns v. Nat’l Marine Fisheries Serv. 265 F.3d 1028 (9th Cir. 2001) ..................................................... 21, 26, 30
Robertson v. Methow Valley Citizens Council 490 U.S. 332 (1989)................................................................................. 22
S. Fork Band Council of W. Shoshone of Nev. v. U.S. Dep’t of the Interior 588 F.3d 718 (9th Cir. 2009) ................................................................... 21
Sierra Club v. U.S. Forest Serv. 843 F.2d 1190 (9th Cir. 1988) ................................................................. 33
FEDERAL STATUTES
5 U.S.C. § 706 ......................................................................................... 20, 21
42 U.S.C. § 4332 ............................................................................... 14, 22, 27
42 U.S.C. § 4370m-6 .......................................................................................4
42 U.S.C. § 7506 ........................................................................................... 17
49 U.S.C. § 40101 ............................................................................................3
49 U.S.C. § 40103 ..................................................................................... 3, 14
49 U.S.C. § 40113 ............................................................................................3
49 U.S.C. § 44701 ............................................................................................3
49 U.S.C. § 44706 ............................................................................................3
Case: 20-70272, 06/30/2020, ID: 11739107, DktEntry: 57-1, Page 5 of 47
TABLE OF AUTHORITIES (continued)
Page
v
49 U.S.C. § 44718 ..................................................................................... 3, 14
49 U.S.C. § 46110 ................................................................................. 4, 6, 18
49 U.S.C. § 47101 ............................................................................................3
49 U.S.C. § 47107 ..................................................................................... 3, 14
CODE OF FEDERAL REGULATIONS
40 C.F.R. § 81.305 .................................................................................. 11, 32
40 C.F.R. § 93.153(b) ................................................................................... 17
40 C.F.R. § 1501.4 .................................................................................. 23, 29
40 C.F.R. § 1501.7 ........................................................................................ 23
40 C.F.R. § 1502.1 ........................................................................................ 22
40 C.F.R. § 1503.1 ........................................................................................ 23
40 C.F.R. § 1508.9 ............................................................................ 23, 27, 29
40 C.F.R. § 1508.27 ............................................................................... passim
FEDERAL REGISTER
70 Fed. Reg. 25,162 (May 12, 2005) ............................................................ 11
79 Fed. Reg. 52,526 (Sept. 3, 2014) ............................................................. 17
85 Fed. Reg. 160 (Jan. 2, 2020) .................................................................... 11
CALIFORNIA STATE AUTHORITIES
Assemb. B. 617, 2017 Reg. Sess. (Cal. 2017) .............................................. 12
Cal. Code Regs., Title 14, § 15002 ............................................................... 24
Case: 20-70272, 06/30/2020, ID: 11739107, DktEntry: 57-1, Page 6 of 47
TABLE OF AUTHORITIES (continued)
Page
vi
Cal. Code Regs., Title 14, § 15063 ............................................................... 24
Cal. Code Regs., Title 14, § 15070 ............................................................... 24
Cal. Const., Article V, § 13 .............................................................................5
Cal. Exec. Order No. S-3-05 (June 1, 2005) ........................................... 13, 34
Cal. Gov. Code § 12511...................................................................................5
Cal. Gov. Code § 12600...................................................................................5
Cal. Health & Safety Code § 38501 ............................................................. 34
Cal. Health & Safety Code § 38550 ....................................................... 13, 34
Cal. Health & Safety Code § 38566 ....................................................... 13, 34
Cal. Health & Safety Code § 39561 ............................................................. 34
COURT RULES
Fed. R. App. P. 15(a) .......................................................................................6
Fed. R. App. P. 28(f) ........................................................................................7
Ninth Circuit Rule 15-1 ...................................................................................6
Ninth Circuit Rule 28-2.7 ................................................................................7
OTHER AUTHORITIES
FAA Order 1015.1F ...................................................................................... 34
FAA Order 5050.4B ........................................................................................4
Case: 20-70272, 06/30/2020, ID: 11739107, DktEntry: 57-1, Page 7 of 47
GLOSSARY
vii
APA Administrative Procedure Act CEQ Council on Environmental Quality CEQA California Environmental Quality Act EA Environmental Assessment EIR Environmental Impact Report EIS Environmental Impact Statement EPA Environmental Protection Agency FAA Federal Aviation Administration FONSI Finding of No Significant Impact GHG Greenhouse Gas NEPA National Environmental Policy Act PER Petitioners’ Joint Excerpts of Record VOC Volatile Organic Compound
Case: 20-70272, 06/30/2020, ID: 11739107, DktEntry: 57-1, Page 8 of 47
1
INTRODUCTION
Petitioner the State of California, by and through Attorney General Xavier
Becerra, petitions this Court for review of Federal Aviation Administration (FAA)
Order issued on December 23, 2019 (Order), approving the Eastgate Air Cargo
Facility (Project) at the San Bernardino International Airport in San Bernardino,
California.
The Order is unlawful because Respondent the FAA approved the Project
with only a cursory environmental review, which undermines the purpose of the
National Environmental Policy Act (NEPA), 42 U.S.C. §§ 4321-4370m. NEPA
requires federal agencies to take a “hard look” at the environmental consequences
of a proposed project and perform a detailed analysis in an Environmental Impact
Statement (EIS) to foster informed decision-making and public participation before
approving a project that, like this one, may significantly impact the quality of the
human environment. The airport expansion Project would involve constructing a
658,500 square-foot air cargo warehouse that would generate at least 500 more
truck trips and 52 additional cargo aircraft takeoffs and landings daily at the
airport, in an air basin already designated by the United States Environmental
Protection Agency (EPA) as in “extreme” nonattainment for ozone and “serious”
nonattainment for diesel particulate matter. The Project is adjacent to
environmental justice communities burdened by high rates of asthma, including the
Case: 20-70272, 06/30/2020, ID: 11739107, DktEntry: 57-1, Page 9 of 47
2
San Bernardino-Muscoy community, which was selected by the California Air
Resources Board for the development of an emissions reduction program under
California Assembly Bill 617 because the community already bears heavy air
pollution.
In spite of public comments from California and others that the Project
would have significant environmental impacts, and a finding under the California
Environmental Quality Act (CEQA) one year earlier by Respondent San
Bernardino International Airport Authority that the Project would have significant
and unavoidable environmental impacts, the FAA approved the flawed NEPA
environmental review, and the developer, Respondent Eastgate Bldg 1, LLC,
began construction in early January 2020. Construction and construction-related
trucking has been occurring near communities that already experience some of the
worst pollution in the country. Respondents expect air cargo operations for the
Project to begin in December 2020 or January 2021, and estimate that more than
2,000 pounds of toxic air pollution from air cargo and trucking operations would
be emitted in the year that follows.
The Project harms California by increasing risks of death and serious
damage to the health of California residents, triggering and exacerbating heart
attacks and asthma attacks in communities that already suffer from high rates of
heart and lung diseases, and impeding California’s decades-long efforts to improve
Case: 20-70272, 06/30/2020, ID: 11739107, DktEntry: 57-1, Page 10 of 47
3
air quality, meet EPA-mandated emissions reduction targets, and meet California’s
own standards to reduce greenhouse gas emissions.
Accordingly, California asks this Court to require the FAA to prepare an
appropriate environmental analysis in a detailed EIS, as required under NEPA,
which would allow the public and the Respondents to fully consider the significant
impacts of this Project. California asks this Court to set aside the FAA Order and
vacate the Project’s ground lease until the FAA has complied with NEPA.
JURISDICTIONAL STATEMENT
On December 20, 2019, the FAA approved the NEPA environmental review
for the Project. Petitioners’ Joint Excerpts of Record (PER) (ECF Nos. 56-1 to 56-
4) at PER0030. And on December 23, 2019, the FAA memorialized this approval
in a Finding of No Significant Impact and Record of Decision, which together
constitute the Order that is the subject of this petition. PER0029. The FAA has
authority to issue the Order pursuant to 49 U.S.C. §§ 40101(d), 40103(b),
40113(a), 44701, 44706, 44718(b), 47101, and 47107(a)(16). Specifically, the
FAA has authority to “review and approve or disapprove” material changes to
airport layout plans. 49 U.S.C. § 47107(a)(16). Because the Project requires
material modifications to the airport layout plan at San Bernardino International
Airport, the Project could not move forward without the FAA’s approval of the
layout plan. See id. The FAA’s approval or disapproval of the plan “is a federal
Case: 20-70272, 06/30/2020, ID: 11739107, DktEntry: 57-1, Page 11 of 47
4
agency action subject to NEPA and other environmental laws.” See FAA Order
5050.4B, ¶ 9.g.(3), ¶ 202.b.
This Court has jurisdiction directly to review the Order pursuant to 42
U.S.C. § 4370m-6(a) and 49 U.S.C. § 46110(a). Section 4370m-6(a) provides:
[A] claim arising under Federal law seeking judicial review of any authorization issued by a Federal agency for a covered project shall be barred unless . . . (B) in the case of an action pertaining to an environmental review conducted under NEPA (i) the action is filed by a party that submitted a comment during the environmental review; and (ii) any commenter filed a sufficiently detailed comment so as to put the lead agency on notice of the issue on which the party seeks judicial review.
42 U.S.C. § 4370m-6(a). In addition, Section 46110(a) states:
[A] person disclosing a substantial interest in an order issued by . . . the Federal Aviation Administration with respect to . . . powers designated to be carried out by the Administrator of the Federal Aviation Administration . . . in whole or in part under this part, part B, or subsection (l) or (s) of section 114 may apply for review of the order by filing a petition for review in the United States Court of Appeals for the District of Columbia Circuit or in the court of appeals of the United States for the circuit in which the person resides or has its principle place of business. The petition must be filed not later than 60 days after the order is issued.
49 U.S.C. § 46110(a). California satisfies both statutory requirements. With regards to Section
4370m-6(a), California, by and through Attorney General Xavier Becerra,
submitted substantive comments regarding the inadequacy of the FAA’s NEPA
review process and Draft Environmental Assessment (Draft EA). PER0403-11.
Case: 20-70272, 06/30/2020, ID: 11739107, DktEntry: 57-1, Page 12 of 47
5
California and other commenters provided detailed comments during the
environmental review period that put the FAA on notice of the issues raised in this
brief. Specifically, comments raised the Draft EA’s failure to consider and explain
the significant and unavoidable impacts found through the CEQA process, see
PER0405-07, the inconsistencies in truck trip estimates between the EA and the
CEQA documents, see PER0407-08, and the EA’s deficient analysis of whether
the Project would threaten a violation of California’s greenhouse gas emissions
requirements, see PER0609-10.
California also satisfied Section 46110(a)’s jurisdictional requirements.
California has substantial interest in the FAA Order. Attorney General Xavier
Becerra is the chief law enforcement officer of the State and is authorized to file
actions to protect public rights and interests, including to protect the natural
resources of the State from pollution, impairment, or destruction. Cal. Gov. Code
§§ 12600-12612. This challenge is brought pursuant to the Attorney General’s
independent constitutional, common law, and statutory authority to represent the
public interest. See Cal. Const., art. V, § 13; Cal. Gov. Code §§ 12511, 12600-12.
The FAA’s approval of the Project without adequate environmental review
deprives California of its right to an adequate public review process essential to
NEPA. The Project is located in a part of California already burdened with
significant air pollution, and its development will directly harm California’s air
Case: 20-70272, 06/30/2020, ID: 11739107, DktEntry: 57-1, Page 13 of 47
6
quality and the health of California’s communities and residents. See ECF No. 31-
3 (declarations of residents in California communities harmed by Project).
Furthermore, California timely filed its petition for review within 60 days of the
entry of the FAA Order approving the NEPA review of the Project, in accordance
with 49 U.S.C. § 46110(a), the Federal Rule of Appellate Procedure 15(a) and
Circuit Rule 15-1. Compare 85 Fed. Reg. 160 (Jan. 2, 2020) (January 2, 2020
publication of Record of Decision in Federal Register), with ECF No. 1-5 (No. 20-
70464) (California Petition for Review filed February 20, 2020).
Accordingly, this Court has jurisdiction to review this case.
STATEMENT OF ISSUES
Whether the FAA action—issuing an Order to approve the environmental
review for the Project without preparing an EIS—was arbitrary, capricious, and
unlawful in violation of NEPA, where:
1. The FAA failed to articulate why findings of significant and unavoidable
impact in the CEQA environmental review did not trigger the preparation of an
EIS under NEPA;
2. The FAA potentially underestimated Project mobile source emissions by
60 percent after using truck trip estimates that are inconsistent with the estimates
used in the CEQA analysis and by using erroneous modeling inputs, and then
failed to explain its use of the inconsistent estimates and modeling inputs; and
Case: 20-70272, 06/30/2020, ID: 11739107, DktEntry: 57-1, Page 14 of 47
7
3. The FAA failed to analyze whether the Project’s greenhouse gas
emissions may violate California’s greenhouse gas emissions requirements.
Pursuant to Federal Rule of Appellate Procedure 28(f) and Circuit Rule 28-
2.7, all pertinent constitutional provisions, treaties, statutes, ordinances, regulations
or rules are set forth verbatim in the addendum to this brief.
STATEMENT OF THE CASE
California challenges the FAA Order approving the 658,500 square-foot
Eastgate Air Cargo Logistics Center currently under construction in San
Bernardino, California. PER0040; PER0046-47; PER0996. Following an
insufficient environmental review process under NEPA in which it prepared an
EA, the FAA determined that this Project will not have significant impacts on the
human environment, and failed to prepare an EIS to analyze and disclose in detail
the Project’s significant environmental impacts. PER0001-2. The Project will
result in additional flight operations and hundreds of additional truck trips at the
San Bernardino International Airport, and it will contribute 355.56 tons of air
pollution every year to the already pollution-burdened surrounding communities.
PER0047; PER0144.
Case: 20-70272, 06/30/2020, ID: 11739107, DktEntry: 57-1, Page 15 of 47
8
The FAA’s environmental review is flawed in three ways. First, the FAA
failed to articulate why findings of significant and unavoidable impact in the
Project’s CEQA environmental review did not trigger the preparation of an EIS
under NEPA. Second, the FAA potentially underestimated Project mobile source
emissions by 60 percent after using truck trip estimates that are inconsistent with
the estimates used in the CEQA analysis and by using erroneous modeling inputs,
and then failed to explain its use of the inconsistent estimates and modeling inputs.
Third, the FAA unlawfully violated its duty under NEPA to consider how the
Project will impact California’s greenhouse gas standards.
Therefore, California respectfully requests this Court to set aside the FAA
Order as arbitrary, capricious, and unsupported by the law. In addition, California
requests this Court to set aside the Final Environmental Assessment (Final EA)
approved by the FAA on December 20, 2019—which is the basis for the FAA’s
unlawful Order—as arbitrary, capricious, and unsupported by the law. California
further requests this Court to vacate the December 30, 2019 ground lease
agreement between the Airport Authority and Eastgate Bldg 1, LLC, which was
approved pursuant to the FAA’s unlawful Order. Finally, California requests this
Court to require the FAA to prepare an EIS for the Project in accordance with
NEPA.
Case: 20-70272, 06/30/2020, ID: 11739107, DktEntry: 57-1, Page 16 of 47
9
STATEMENT OF THE FACTS
I. The Project
The San Bernardino International Airport Authority, which owns and
operates the San Bernardino International Airport, and Eastgate Bldg 1, LLC, the
Project proponent, agreed in 2018 to develop the Eastgate Air Cargo Facility
within the airport boundaries to “satisfy an unmet need for large-scale air cargo
facilities in the San Bernardino area.” PER0044. The Project would develop a
package distribution center with an air cargo hub on approximately 100-acres on
the northern side of the airport, 150 feet from the nearest residences. PER0046;
PER0411. The proposed facilities would include a 658,500 square-foot
warehouse, an area for aircraft to taxi and park that would concurrently support 14
airplanes ranging from Boeing-737 to Boeing-767, 12 acres of ground support
equipment parking and operational support areas, two 25,000 square-foot
maintenance buildings, and more than 2,300 parking stalls. PER0046. The
facilities would operate seven days a week, adding 24 cargo aircraft takeoffs and
landings on opening day—which Respondents expect to be as early as December
2020—ramping up to 52 takeoffs and landings a day within five years. Decl. of
David Kessler, ECF No. 41-2 (Kessler Decl.) ¶ 7; Decl. of John Magness, ECF No.
42-2 (Magness Decl.) ¶ 3; PER0047. The projected average daily vehicle round
trips generated by the Project is about 3,500 on opening day, including at least 192
Case: 20-70272, 06/30/2020, ID: 11739107, DktEntry: 57-1, Page 17 of 47
10
by heavy duty trucks, more than doubling within five years to over 7,500 round
trips, including at least 500 by trucks. See PER0134.
In May 8, 2020, the Airport Authority announced that Amazon will be the
company operating out of the Project.1 See PER0996.
II. Impacts on the Surrounding Communities and the Environment
The communities adjacent to the Project already rank in the top 5 percent in
California for environmental pollution. PER0404. The South Coast Air Basin, in
which the Project is sited, is already severely polluted by ozone and particulate
matter. See PER0026. Ambient air in the Project area contains among the highest
background levels in the South Coast Air Basin of diesel particulate matter, a toxic
air contaminant generated by truck and aircraft engines that cause increased cancer
risks, heart disease, and lung disease. PER0404. The EPA has designated the air
basin as in “extreme” nonattainment for ozone and “serious” nonattainment for
particulate matter 2.5 (PM2.5, or particulate matter less than or equal to 2.5
microns in diameter). PER0299; PER0026. Ozone is the main ingredient of smog
and formed from volatile organic compounds (VOC) and nitrogen oxide—
chemicals generated by cars, trucks, and airplanes—reacting in the presence of
sunlight, and can cause premature deaths and cause and exacerbate asthma attacks.
1 “Amazon is landing at the San Bernardino Airport, officials say,” San Bernardino Sun (May 8, 2020), https://www.sbsun.com/2020/05/08/amazon-is-landing-at-san-bernardino-airport-officials-say/.
Case: 20-70272, 06/30/2020, ID: 11739107, DktEntry: 57-1, Page 18 of 47
11
See 40 C.F.R. § 81.305; 70 Fed. Reg. 25,162, 25,169 (May 12, 2005). PM2.5 can
include organic chemicals, dust, soot, and metals that come from cars, trucks, and
construction activities, and cause lung disease, heart disease, and asthma.
PER0384; PER0404.
The Project is sited close to sensitive receptors, including four elementary
schools and a high school nearby. PER0115. One elementary school, located less
than a mile from the airport’s runway, is directly beneath the flight paths of all
airport air traffic. Decl. of Martha Romero, ECF No. 30-2 at 472 (Romero Decl.) ¶
10. Local schools report high rates of asthma among their enrolled students. See
Romero Decl. ¶ 14. Furthermore, residents in the areas immediately adjacent to
the Project suffer from asthma at rates higher than 84 percent of California.
PER0404.
In addition, the Project is located just over a mile to the east of the San
Bernardino-Muscoy environmental justice community, which will be impacted by
pollution from the Project’s construction and operations. PER0404. The
California Legislature enacted Assembly Bill 617 to remedy the disproportionate
impact of air pollution in environmental justice communities, requiring local air
districts to help reduce air pollution and toxic air contaminants from commercial
and industrial sources, including by developing emissions reduction programs in
selected communities. Assemb. B. 617, 2017 Reg. Sess. (Cal. 2017). As a result
Case: 20-70272, 06/30/2020, ID: 11739107, DktEntry: 57-1, Page 19 of 47
12
of the San Bernardino-Muscoy community’s disproportionate exposure to
pollution and their vulnerability, in 2018, the California Air Resources Board
selected the San Bernardino-Muscoy community specifically to reduce air
emissions in the community under Assembly Bill 617. PER0405. In accordance
with that bill, San Bernardino-Muscoy has finalized a community emissions
reduction plan that calls for reducing truck traffic through the community.
PER0405.
Asthma rates in the San Bernardino-Muscoy community are among the
highest 2 percent in California. PER0404. Exposure to air pollution can cause
asthma, and the existing prevalence of asthma in a community can make the
community more vulnerable to exposure to air pollution. PER0404. The
community’s 90,000 residents identify as 13 percent African American and 73
percent Hispanic. PER0404. Furthermore, nearly 20 percent of the population are
children under the age of 10, a group particularly sensitive to the health effects of
air pollution. PER0404. In addition, more than 95 percent of the community live
below the poverty level2 and more than 75 percent are unemployed, thus limiting
the community’s access to healthcare. PER0404-05.
2 Poverty level as referenced here is defined as twice the federal poverty
threshold. PER0405.
Case: 20-70272, 06/30/2020, ID: 11739107, DktEntry: 57-1, Page 20 of 47
13
California has enacted laws and requirements for the protection of the
environment, specifically regarding greenhouse gas emissions levels. See
PER0609-10. These include, but are not limited to, the California Global Warming
Solutions Act of 2006, or Assembly Bill 32, which requires the California Air
Resources Board to adopt statewide rules and regulations that would achieve
greenhouse gas emissions equivalent to statewide levels in 1990 by 2020. Cal.
Health & Safety Code § 38550. In addition, Senate Bill 32, enacted in 2016, builds
on the Assembly Bill 32’s goal by requiring California to reduce statewide
greenhouse gas emissions to 40 percent below 1990 levels by 2030. Cal. Health &
Safety Code § 38566. Finally, Executive Order S-3-05 sets two statewide
greenhouse gas reduction targets: reducing emissions to 1990 levels by 2020, and
reducing emissions to 80 percent below 1990 levels by 2050. Cal. Exec. Order No.
S-3-05 (June 1, 2005).
III. Environmental Review
In 2018, the Airport Authority began an environmental review of the Project
under CEQA, California’s corollary to NEPA, publishing an Initial Study in July
2018 and a Draft Environmental Impact Report (Draft EIR) in August 2018.
PER0807. The Airport Authority published a Final Environmental Impact Report
(Final EIR) in October 2018, determining that the Project will have significant and
unavoidable air quality, climate, and noise impacts. PER0825-26; PER0788. The
Case: 20-70272, 06/30/2020, ID: 11739107, DktEntry: 57-1, Page 21 of 47
14
Final EIR concluded that construction and operational air emissions would exceed
regional thresholds of significance even after implementing all mitigation
measures. PER0825-26.
On December 18, 2018, Eastgate Bldg 1, LLC, entered into a lease
agreement for the Project site with the Airport Authority. See PER0049; ECF No.
1-12 at 11. But, because the proposed construction at the Project site also requires
the FAA approval of an airport layout plan, and such a federal agency action
requires compliance with NEPA, the Airport Authority began a NEPA review of
the Project in early 2019 and published a Draft EA in July 2019. PER0612; 42
U.S.C. § 4332(2)(C); 49 U.S.C. §§ 40103(b), 44718, 47107(a)(16); FAA Orders
1050.1F & 5050.4B. Despite having concluded in its Final EIR less than a year
prior that the Project would cause significant and unavoidable environmental
impacts, the Airport Authority found no significant impacts in its Draft EA, and
therefore it did not prepare an EIS required by NEPA. PER0612-0787. The
Airport Authority performed some of its NEPA analysis just three months after
concluding its analysis under CEQA. Compare PER1006, -13 tbl. 4.2, -22, -29 tbl.
4.2 (header dates indicating calculations for NEPA analyses were performed on
January 15, 2019), with PER0788-793 (Final EIR Errata published in October
2018). But the Draft EA did not discuss the CEQA analysis.
Case: 20-70272, 06/30/2020, ID: 11739107, DktEntry: 57-1, Page 22 of 47
15
More than 800 comments, including comments from California Attorney
General Xavier Becerra, were submitted to the Airport Authority identifying
deficiencies with the Draft EA. PER0002; PER0010; PER0403-11. Specifically,
the comments raised concerns that the EA does not consider or explain the
significant and unavoidable Project impacts what the CEQA review had found less
than a year prior to the NEPA review. PER0405-07. The comments also pointed
out inconsistencies and errors in the EA’s mobile source emissions modeling
analysis, which could have caused the EA to significantly underestimate the
Project’s mobile source emissions. PER0407-08. Furthermore, commenters
criticized the EA’s failure to demonstrate the Project’s compliance with
California’s greenhouse gas emissions standards. PER0609-10.
The FAA approved the Final EA without meaningfully addressing or
correcting any of these concerns. PER0412-16; PER0611. On December 20,
2019, and issued its Record of Decision and Finding of No Significant Impact
(FONSI) on December 23, 2019. PER0001-0029. The December 23, 2019 Record
of Decision and FONSI constitute the FAA Order that is the subject of this petition
for review. See ECF No. 1-5 (Case No. 20-70464). One week later, on December
30, the Airport Authority voted to approve the ground lease agreement between it
and Eastgate Bldg 1, LLC, for the Project site. ECF No. 1-12 at 3.
Case: 20-70272, 06/30/2020, ID: 11739107, DktEntry: 57-1, Page 23 of 47
16
IV. Project Construction and Operations
On January 6, 2020, Eastgate Bldg 1, LLC, began construction at the Project
site, and has been conducting land clearing, demolition, excavation, embankment,
and grading. Kessler Decl. ¶ 7; see PER0131. Project construction is generating
and will continue to generate emissions of VOC, nitrogen oxides, and PM.
PER0147-50. Trucks hauling construction debris regularly traverse the Project site
and drive through the nearby communities. Romero Decl. ¶ 13. The Final EA’s
mitigation measures specify that when transporting material from the construction
off-site, all material should be covered to limit dust emissions. PER0154-55.
However, residents near the construction have observed truck trips transporting
material out of the construction site with uncovered loads. Romero Decl. ¶ 13.
Debris and dust from uncovered trucks are escaping into the adjacent
neighborhoods. Romero Decl. ¶ 13. Residents near the Project construction site
have stated that they experience noxious smells from the construction activities and
bad headaches when walking past the site. Romero Decl. ¶¶ 7, 12.
Respondents anticipate Project operations to begin in December 2020 or
January 2021. Kessler Decl. ¶ 7; Magness Decl. ¶ 3. If the construction isn’t
completed by then, the EA estimates that Project construction and operations,
including air cargo flights and almost 200 daily truck trips, will add 214.05 tons of
air pollution in its first year of operations. PER0149-50. The EA anticipates that
Case: 20-70272, 06/30/2020, ID: 11739107, DktEntry: 57-1, Page 24 of 47
17
these emissions will exceed the de minimis emissions thresholds in the
nonattainment South Coast Air Basin set by the EPA under the Clean Air Act to
protect human health. See 42 U.S.C. § 7506(c)(1); 40 C.F.R. § 93.153(b);
PER0154-56. The EA further estimates that within five years, beginning in 2024,
Project operations will emit 355.56 tons of air pollution annually—or one ton of
pollution each day, due to additional daily air cargo flights and at least 500 truck
trips. PER0132; PER0134; PER0144.
The types of emissions that will occur during construction and operations are
harmful to human health. PER0384. Nitrogen oxide recombines with VOC to
form ground-level ozone, a gas that irritates and damages respiratory organs. 79
Fed. Reg. 52,526, 52,526 n.3 (Sept. 3, 2014); PER0404. Ozone exposure is
associated with increases in respiratory-related hospital admissions, respiratory
symptoms, and medication use by those who suffer from asthma. PER0404. PM
in diesel exhaust from car, truck, and airplane engines and from construction-
related activities is easily inhaled in the bronchial and alveolar regions of the lung,
children and the elderly are particularly vulnerable, and exposure is associated with
cardiovascular and respiratory hospitalizations, cancer, and early deaths.
PER0404.
Furthermore, the Project is anticipated to generate significant greenhouse
gas emissions, emitting 27,991 new metric tons of CO2 equivalent emissions in its
Case: 20-70272, 06/30/2020, ID: 11739107, DktEntry: 57-1, Page 25 of 47
18
first year of operations, and 55,842 metric tons of such emissions in 2024.
PER0165.
V. Relevant Procedural History
Following the FAA’s issuance of its final Order on December 23, 2019,
Center for Community Action & Environmental Justice, Sierra Club, Teamsters
Local 1932, Martha Romero, and Shana Saters on January 27, 2020, filed a petition
for review in this Court pursuant to 49 U.S.C. § 46110(a). Center for Community
Action & Environmental Justice v. FAA, No. 20-70272 (9th Cir. filed Jan. 27,
2020), ECF No. 1. California filed its petition for review of the FAA Order on
February 20, 2020. ECF No. 1 (No. 20-70464). On March 2, 2020, California
moved this Court to consolidate the two petitions, as they challenge the same FAA
Order. ECF No. 22. On March 11, 2020, the Court granted California’s
unopposed motion to consolidate the two petitions. ECF No. 25. On April 23,
2020, this Court denied Petitioners’ motion for a stay pending judicial review.
ECF No. 48.
SUMMARY OF ARGUMENT
The FAA’s December 23, 2019 Order must be set aside as arbitrary and
capricious under NEPA and the Administrative Procedure Act for three reasons.
First, the FAA Order is based on a flawed environmental analysis that fails
to discuss or even acknowledge substantial questions before the agency that the
Case: 20-70272, 06/30/2020, ID: 11739107, DktEntry: 57-1, Page 26 of 47
19
Project would have significant environmental impacts on air quality, climate, and
noise. These substantial questions are generated by the Project’s CEQA review, in
which the Airport Authority found significant and unavoidable impacts on those
environmental factors.
Second, the FAA Order is based on analysis that fails to discuss or reconcile
inconsistent and inaccurate data before the agency, thus potentially
underestimating Project mobile source emissions by 60 percent. The NEPA
analysis calculates mobile source emissions using truck trip estimates that are
substantially lower than the estimates used in the CEQA analysis, and does not
explain why the lower estimates are used. In addition, the NEPA analysis used
erroneous modeling inputs—half of the total truck trips—that lead to a significant
underestimate of mobile source emissions.
Third, the FAA Order is based on an analysis that failed to evaluate and
reconcile the Project’s greenhouse gas emissions with California’s binding
greenhouse gas emissions standards. NEPA and FAA’s own procedures require
the evaluation of whether a Project would “threaten the violation” of state law or
requirement implemented to protect the environment.
Therefore, the Court should set aside the FAA Order and require
Respondents to perform an environmental analysis and prepare an EIS that
thoroughly analyzes the Project’s environmental impacts as required by NEPA.
Case: 20-70272, 06/30/2020, ID: 11739107, DktEntry: 57-1, Page 27 of 47
20
STANDARD OF REVIEW
This Court reviews the FAA’s action for compliance with NEPA and the
Administrative Procedure Act (APA), 5 U.S.C. § 706(2)(A). Native Ecosystems
Council v. Tidwell, 599 F.3d 926, 932 (9th Cir. 2010). The Court must ensure that
the agency has taken a “hard look,” pursuant to NEPA, at the environmental
consequences of the proposed action. Blue Mountains Biodiversity Project v.
Blackwood, 161 F.3d 1208, 1211 (9th Cir. 1998).
Under the APA, a court must hold unlawful and set aside agency action,
findings, and conclusions found to be arbitrary, capricious, an abuse of discretion,
or otherwise not in accordance with law. See Bennett v. Spear, 520 U.S. 154, 174
(1997). The agency has an obligation to state a “rational connection” between the
facts found and the decision made. Native Ecosystems Council, 599 F.3d at 932.
An agency action is arbitrary and capricious if the agency has “entirely failed to
consider an important aspect of the problem, offered an explanation for its decision
that runs counter to the evidence before the agency, or is so implausible that it
could not be ascribed to a difference in view or the product of agency expertise.”
Motor Vehicle Mfr. Ass’n v. State Farm Mutual, 463 U.S. 29, 42 (1983). A final
agency action is arbitrary and capricious, and must be set aside, if it does not
“consider[] the relevant factors” and “articulate a rational connection between the
facts found and the choice made.” See Or. Nat. Res. Council Fund v. Goodman,
Case: 20-70272, 06/30/2020, ID: 11739107, DktEntry: 57-1, Page 28 of 47
21
505 F.3d 884, 889 (9th Cir. 2007); Pac. Coast Fed’n of Fishermen’s Ass’ns v.
Nat’l Marine Fisheries Serv., 265 F.3d 1028, 1034 (9th Cir. 2001). The reviewing
court may not supply a reasoned basis for the agency’s action that the agency itself
has not given. State Farm Mut. Auto. Ins. Co., 463 U.S. at 43.
ARGUMENT
The FAA Order violates NEPA and therefore must be set aside as “arbitrary,
capricious, . . . or not otherwise in accordance with law.” 5 U.S.C. § 706(2)(A);
Spear, 520 U.S. at 174. NEPA is a “basic national charter for the protection of the
environment.” Ctr. for Biological Diversity v. Nat’l Highway Traffic Safety
Admin., 538 F.3d 1172, 1185 (9th Cir. 2008) (quoting 40 C.F.R. § 1500.1(a)).
NEPA imposes procedural requirements that are intended to enforce NEPA’s
mandate that agencies will take a “hard look” at their actions’ environmental
consequences—by carefully considering detailed information on significant
environmental impacts and ensuring that the relevant information will be made
available to the public. Earth Island Inst. v. U.S. Forest Serv., 351 F.3d 1291,
1300 (9th Cir. 2003); see N. Idaho Cmty. Action Network v. U.S. Dep’t of Transp.,
545 F.3d 1147, 1153 (9th Cir. 2008). Congress enacted NEPA to protect the
public interest by requiring “careful consideration of environmental impacts before
major federal projects may go forward.” S. Fork Band Council of W. Shoshone of
Nev. v. U.S. Dep’t of the Interior, 588 F.3d 718, 728 (9th Cir. 2009) (emphasis
Case: 20-70272, 06/30/2020, ID: 11739107, DktEntry: 57-1, Page 29 of 47
22
added). This ensures that “important effects will not be overlooked or
underestimated only to be discovered after resources have been committed or the
die otherwise cast.” Robertson v. Methow Valley Citizens Council, 490 U.S. 332,
349 (1989).
I. The Order Must Be Set Aside Because the FAA Failed to Prepare an EIS as Required by NEPA and Failed to Articulate Why Findings of Significant Impact in the CEQA Analysis Did Not Trigger the Preparation of an EIS Under NEPA.
NEPA requires federal agencies to analyze in an EIS the potential
environmental impacts of any major federal action “significantly affecting the
quality of the human environment.” 42 U.S.C. § 4332(2)(C). The threshold for
determining whether an EIS is required is a low one—the agency must prepare an
EIS whenever “there are substantial questions about whether a project may cause
significant degradation of the human environment.” Native Ecosystems Council,
428 F.3d at 1239.
An EIS’s primary purpose is to be an “action-forcing tool” to ensure federal
government programs and actions meet NEPA’s goals and policies. 40 C.F.R.
§ 1502.1. To determine whether an EIS is necessary for a project, the agency may
prepare an EA, which should provide sufficient evidence and analysis to justify the
agency’s determination whether to prepare an EIS or make a finding of no
significant impact. 40 C.F.R. §§ 1501.4, 1508.9; see also Bob Marshall All. v.
Hodel, 852 F.2d 1223, 1225 (9th Cir. 1988).
Case: 20-70272, 06/30/2020, ID: 11739107, DktEntry: 57-1, Page 30 of 47
23
Indeed, giving detailed consideration of environmental impacts in an EIS
where substantial questions exist about whether a project may harm human and
environmental health is the exact type of procedural safeguard mandated by NEPA
to promote informed decision-making and public participation. See Ctr. for
Biological Diversity, 538 F.3d at 1194; N. Idaho Cmty. Action Network, 545 F.3d
at 1153.
In addition to fulfilling the agencies’ obligation under NEPA to fully
evaluate Project impacts, preparation of an EIS triggers a public participation
process in which the community can help determine the scope of issues that should
be addressed. See 40 C.F.R. § 1501.7. Furthermore, the EIS drafting process
requires agencies to request and address additional comments from the public. See
40 C.F.R. § 1503.1(a)(4). Thus, an EIS process would have enabled the FAA and
the Airport Authority to solicit input from the community and tailor improvements
to the Project based on community needs. In failing to prepare an EIS, the FAA
and the Airport Authority deprived the community of a public participation process
regarding a Project which disproportionately harms the community.
During the Airport Authority’s CEQA review in 2018, it prepared an EIR,
CEQA’s analog to the EIS, based on its finding that the Project may have
significant environmental impacts. PER0788; PER0825-26. Environmental
review under CEQA is akin to the process required by NEPA. Similar to NEPA,
Case: 20-70272, 06/30/2020, ID: 11739107, DktEntry: 57-1, Page 31 of 47
24
the “basic purposes of CEQA [is] to [i]nform governmental decision makers and
the public about the potential, significant environmental effects of proposed
activities.” Cal. Code Regs., tit. 14, § 15002(a)(1) (CEQA Guidelines). An EA
under NEPA is analogous to an initial study under CEQA. See id. § 15063.
Likewise, a FONSI under NEPA is analogous to a negative declaration under
CEQA. See id. § 15070. Preparing a negative declaration is appropriate under
CEQA only if, based on the whole record before the agency, there is no substantial
evidence the project may have significant environmental effects. See id. §
15070(a). Similarly, issuing a FONSI is appropriate under NEPA only if there is
no substantial question on whether the project may have significant environmental
effects. California v. U.S. Dep’t of Transp., 260 F. Supp. 2d 969, 972 (N.D. Cal.
2003).
The EIR prepared by the Airport Authority concluded that the Project would
have significant and unavoidable air quality, climate change, and noise impacts.
PER0825-26. For example, with respect to air quality impacts, the Final EIR
found that the construction of the Project would result in nitrogen oxides and PM
emissions that exceed applicable local regional air quality thresholds based on
additional mitigation, and that even after implementing recommended mitigation
measures, the Project’s emissions from operations would exceed regional
thresholds of significance for VOC, nitrogen oxides, carbon monoxide, and PM.
Case: 20-70272, 06/30/2020, ID: 11739107, DktEntry: 57-1, Page 32 of 47
25
PER0825-26. “No feasible mitigation measures have been identified that would
reduce these emission to levels that are less than significant.” PER0825-26;
PER0890, -901, -903, 0905, -914. Similarly for greenhouse gas impacts, the Final
EIR determined that emissions from Project operations would exceed local air
district thresholds, and that no feasible mitigation measures could reduce
greenhouse gas emissions to levels that are less than significant. PER0825.
Moreover, Project operations “would create a significant cumulative impact to
global climate change.” PER0825.
These findings—in an environmental review process closely approximating
NEPA—raises “substantial questions” in the NEPA review about whether this
Project may cause significant environmental effects, and thus triggers the FAA’s
NEPA obligation to prepare an EIS. See Native Ecosystems Council, 428 F.3d at
1239.
Perplexingly, the EA prepared by the Airport Authority and approved by the
FAA failed to discuss the CEQA process or the Airport Authority’s own
conclusion—just one year earlier—that the Project would have significant,
unavoidable impacts on air quality, climate change, and noise. Without even
mentioning the EIR, the EA disregarded the Airport Authority’s finding of
significant environmental impacts. A final agency action is arbitrary and
capricious, and must be set aside, if it does not “consider[] the relevant factors and
Case: 20-70272, 06/30/2020, ID: 11739107, DktEntry: 57-1, Page 33 of 47
26
articulate [] a rational connection between the facts found and the choice made.”
Pac. Coast Fed’n of Fishermen’s Ass’ns, 265 F.3d at 1034; Native Ecosystems
Council, 599 F.3d at 932. Respondents’ decision to approve the Project without an
EIS was arbitrary and capricious because they inexplicably concluded the Project
would not have significant environmental impacts, after coming to the opposite
conclusion in an analogous environmental review of the exact same Project.
Given the opportunity to publicly address questions regarding environmental
impacts found through the CEQA analysis, Respondents offered only conclusory
statements regarding the significance of those impacts in the Final EA. In the EA’s
response to California’s comment letter, for example, Respondents gave a short,
general statement that CEQA guidelines, methodologies, and significance
thresholds are different from those used by the FAA, that the “EIR is unrelated to
the federal EA.” PER0413. They provided no other analysis or explanation for
why the impacts determined to be significant and unavoidable under CEQA were
not significant under NEPA. This conclusory explanation is insufficient to provide
the public with the level of evidence and analysis required under NEPA. See Bob
Marshall All., 852 F.2d at 1225; Blue Mountains Biodiversity Project v.
Blackwood, 161 F.3d at 1212 (holding agency “must supply a convincing
statement of reasons to explain a Project’s impacts are insignificant” where it
decides not to prepare an EIS); Ocean Advocates v. U.S. Army Corps. of Eng’rs,
Case: 20-70272, 06/30/2020, ID: 11739107, DktEntry: 57-1, Page 34 of 47
27
402 F.3d 846, 864 (9th Cir. 2005) (holding agency “cannot avoid preparing an EIS
by making conclusory assertions that an activity will have only an insignificant
impact on the environment”).
By “entirely failing to consider an aspect of the problem,” the FAA Order is
arbitrary and capricious, and must be set aside. Motor Vehicle Mfr. Ass’n, 463
U.S. at 42.
II. The FAA Order Must Be Set Aside Because the NEPA Analysis Failed to Discuss or Reconcile Factual Inconsistencies Before the Agencies, Insufficiently Justified Its Determinations, and Potentially Underestimated Project Mobile Source Emissions by 60 Percent.
Federal agencies may prepare an EA first in order to determine whether a
project may have “a significant effect upon the human environment.” 40 C.F.R.
§ 1508.9; Found. for N. Am. Wild Sheep v. U.S. Dep’t of Agric., 681 F.2d 1172,
1178 (9th Cir. 1982). The EA must comply with requirements set forth in NEPA
and its implementing regulations, and must foster both informed decision-making
and informed public participation. See Ctr. for Biological Diversity, 538 F.3d at
1194; see, e.g., 42 U.S.C. § 4332(2)(C); 40 C.F.R. § 1508.27. The Council on
Environmental Quality (CEQ) regulations specify minimum requirements for the
agency’s analysis of a proposed action, mandating that agencies evaluate the
“context” and the “intensity” of the impacts when determining the impacts’
Case: 20-70272, 06/30/2020, ID: 11739107, DktEntry: 57-1, Page 35 of 47
28
“significance.” 40 C.F.R. § 1508.27. Marsh v. Or. Nat. Res. Council, 490 U.S.
360, 372 (1989).
If the agency fails to properly consider any one of the ten factors relating to
the significance of a project’s impacts on the environment, or “[w]hen one factor
alone raises ‘substantial questions’ about whether an agency action will have a
significant environmental effect,” the decision should be set aside and the agency
should prepare an EIS. Bark v. U.S. Forest Serv., 958 F.3d 865, 871 (9th Cir.
2020); Marsh, 490 U.S. at 372 (1989); see 40 C.F.R. §§ 1508.27(b)(1)-(10).
A. The FAA Failed to Discuss or Reconcile Inconsistent and Inaccurate Truck Trip Estimates Used to Model Mobile Source Emissions and Failed to Justify Its Use of Those Estimates.
The FAA Order is based on an EA that fails to explain inconsistent facts
before the agency and contains analysis based on inaccurate data, in violation of
NEPA. The EA underestimates mobile source emissions generated by the Project
in at least two ways. As a result, it underestimates the Project’s air quality and
climate change impacts. First, without explanation, the EA uses an estimate for
truck trips that is 23 percent lower than the estimate used for the Project’s CEQA
analysis. PER0407. The EA estimates that the Project would generate 192 truck
trips in its initial year of operation and 500 truck trips in full operation. PER0133-
34. However, according to the EIR from the CEQA process, the Project will
generate significantly more truck trips—248 truck trips in the initial year of
Case: 20-70272, 06/30/2020, ID: 11739107, DktEntry: 57-1, Page 36 of 47
29
operation and 652 truck trips in full operation. PER0795; PER0928. The EA fails
to offer any explanation for the discrepancies in estimates between the EIR and the
EA. The record shows that emissions calculations for the EA were performed just
three months after the EIR was developed. Compare PER1006, -13 tbl. 4.2, -22, -
29 tbl. 4.2 (header dates indicating calculations for NEPA analyses were performed
on January 15, 2019), with PER0788-793 (Final EIR Errata published in October
2018).
Respondents’ adoption of a new calculation that generated lower trip
estimates just three months after the Airport Authority itself concluded its CEQA
analysis evidences an inconsistent and arbitrary review process. The failure to
provide any explanation or basis for the reduced estimates, which California and
others raised in public comments, violates NEPA’s requirement that agencies
provide sufficient evidence and analysis to justify their final determinations. 40
C.F.R. §§ 1501.4, 1508.9; see also Bob Marshall All., 852 F.2d at 1225.
Furthermore, if the EIR’s higher estimates are accurate, the EA significantly
underestimates the emissions generated by the Project.
In addition, the EA appears to model only half of the mobile source
emissions because it counts each truck trip as a one-way trip, not a roundtrip. The
EA estimated emissions using CalEEMod, a program that models emissions of
one-way trips. PER0408. The truck trip estimates in the EIR, however, were
Case: 20-70272, 06/30/2020, ID: 11739107, DktEntry: 57-1, Page 37 of 47
30
roundtrips. PER0795. If the reduced truck trips considered in the EA were also
roundtrips, then the number of trips should be doubled before using CalEEMod to
estimate emissions. There is no evidence the EA did this. PER1013 tbl. 4.2;
PER1029 tbl. 4.2. The record shows that the EA’s emissions calculations were
based on the CalEEMod’s modeling inputs of only half of the total number of truck
trips. Compare PER1013 tbl. 4.2; PER1029 tbl. 4.2 (CalEEMod worksheets
indicating single-trip inputs of 192 and 500), with PER0795 (Final EIR Errata
indicating roundtrip inputs used). When California and others raised this oversight
in their comments, Respondents indicated that “further analysis was completed” to
calculate the total round trip truck traffic emissions, but pointed to no additional
analysis. PER0414.
Because the FAA Order has “entirely failed to consider an important aspect
of the problem” or articulate a “rational connection between the facts found and the
choice made,” it is arbitrary and capricious and must be set aside. See Motor
Vehicle Mfr. Ass’n, 463 U.S. at 42; Pac. Coast Fed’n of Fishermen’s Ass’ns, 265
F.3d at 1034.
Case: 20-70272, 06/30/2020, ID: 11739107, DktEntry: 57-1, Page 38 of 47
31
B. The FAA’s Errors in Modeling Mobile Source Emissions Means that It Potentially Underestimated Mobile Source Emissions by 60 Percent, Rendering Flawed the EA’s Determination of “Significance.”
The CEQ regulations specify that an action’s “significance” depends on
“both context and intensity.” 40 C.F.R. § 1508.27; see also id. § 1508.27(b)
(setting forth ten factors to “consider[] in evaluating intensity”); Marsh, 490 U.S.
at 372. “Context” requires the agency to analyze “the significance of an action” in
several contexts, including “society as a whole (human, national), the affected
region, the affected interests, and the locality.” 40 C.F.R. § 1508.27(a).
“Intensity” is simply the “the severity of impact.” 40 C.F.R. § 1508.27(b).
Because the EA underestimated the truck emissions in two ways, it failed to
account for a large amount of potential emissions in its air quality analysis,
underestimating the Project’s “intensity,” or “severity of impact.” For the initial
year of operation, if the EA mistakenly based its emissions estimates on the lower
estimate for the truck trips (192 truck trips) when it should have based estimates on
the higher trip number projected by the EIR (248 truck trips), and if it modeled the
lower single trip number in CalEEMod (192 trips) when it should have modeled
round trips by doubling the higher EIR trip number (496 trips), then the EA would
have modeled only 39 percent of the actual number of truck trips. Similarly, for
full operation, if the EA based emissions estimates on the lower truck trip number
(500 trips) rather than the trip number predicted by the EIR at full operation (652
Case: 20-70272, 06/30/2020, ID: 11739107, DktEntry: 57-1, Page 39 of 47
32
trips), and if the EA mistakenly modeled the lower trip number as single trips (500
trips) rather than doubling the higher EIR number to project emissions for round
trips (1,307 trips), the EA would have modeled only 38 percent of the actual truck
trips.
Together, these two errors—using a lower estimate of truck trips without
any explanation, and modeling emissions for only single trips—potentially
underestimated the Project’s mobile source emissions by more than 60 percent,
rendering flawed any determination of significant impacts based on those
emissions estimates, such as air quality and climate change impacts. By
underestimating the Project’s mobile source emissions, the FAA failed to properly
consider “the severity of impact” from the Project, thus failing to adequately
analyze the Project’s “intensity.” See 40 C.F.R. § 1508.27(b).
These mobile source emissions must also be considered in the “context” of
this Project. See 40 C.F.R. § 1508.27(a). The Project is located in the South Coast
Air Basin, which “continues to experience some of the worst air quality in the
nation” and suffers from some of the highest levels of smog-forming ozone
pollution in the country. See 40 C.F.R. § 81.305. In addition, the adjacent
communities already suffer from high rates of pollution-related illnesses, including
asthma, which could be caused and aggravated by such mobile source emissions.
PER0404. In this context, the intensity of Project impacts is heightened. Because
Case: 20-70272, 06/30/2020, ID: 11739107, DktEntry: 57-1, Page 40 of 47
33
the FAA underestimated mobile source emissions, it failed to adequately consider
the impact of additional emissions in this context. See 40 C.F.R. § 1508.27(b)(2)
(“The degree to which the proposed action affects public health or safety.”) &
(b)(5) (“The degree to which the possible effects on the human environment are
highly uncertain or involve unique or unknown risks.”).
The FAA Order must be set aside because the agency failed to adequately
analyze multiple factors relating to the context and intensity—the “significance”—
of the Project. See Bark, 958 F.3d at 871; Marsh, 490 U.S. at 372.
III. The FAA Order Must Be Set Aside Because It Fails to Consider California Greenhouse Gas Emissions Requirements Imposed to Protect the Environment.
During the EA review process, the agency has the affirmative duty to
consider whether the action “threatens a violation” of federal, state, or local law or
requirement “imposed for the protection of the environment. 40 C.F.R.
§ 1508.27(b)(10). This consideration contributes to the agency’s determination of
whether the agency action may have significant impacts on the environment. Id.
§ 1508.27. The Ninth Circuit has held unreasonable an agency’s failure to
consider these environmental laws in an EA and has required the agency to prepare
an EIS to redress this type of oversight. Sierra Club v. U.S. Forest Serv., 843 F.2d
1190, 1193, 1195 (9th Cir. 1988) (holding that “CEQ regulations, 40 C.F.R.
1508.27(b)(10), require the Forest Service to consider state requirements imposed
Case: 20-70272, 06/30/2020, ID: 11739107, DktEntry: 57-1, Page 41 of 47
34
for environmental protection to determine whether the action will have a
significant impact on the human environment” and that “an EIS should have been
prepared” because the EA failed to mention the state requirements). Furthermore,
the FAA’s own NEPA guidance requires the agency to identify and address any
“state and/or local air quality requirements that are applicable to a project.” FAA
Order 1015.1F § 1.1.2.
Recognizing the “serious threat” posed by greenhouse gases to “the
economic well-being, public health, natural resources, and the environment of
California,” California enacted various laws setting mandatory greenhouse gas
standards. See Cal. Health & Safety Code § 38501. These standards require the
California Air Resources Board to “reduce state emissions of greenhouse gases to
at least the 1990 emissions level by 2020,” “ensure that statewide greenhouse gas
emissions are reduced to at least 40 percent below the statewide greenhouse gas
emissions limit” by the end of 2030, and reduce statewide greenhouse gas levels to
80 percent below 1990 levels by 2050. See id. §§ 38550, 39561, 38566; Cal. Exec.
Order No. S-3-05.
However, nowhere does the FAA Order or the EA on which it is based
consider the Project’s impacts on the attainment of California’s greenhouse gases
standards. Given that the Project’s CEQA analysis found significant and
unavoidable impacts to climate change, and the EA estimated the Project would
Case: 20-70272, 06/30/2020, ID: 11739107, DktEntry: 57-1, Page 42 of 47
35
generate 27,991 new metric tons of CO2 equivalent within the first year of Project
operations, and 55,842 metric tons per year at full operation, Respondents should
have evaluated the Project’s impacts against these binding California greenhouse
gas emission requirements. PER0165. But the EA did not mention California’s
requirements, despite public comments urging Respondents to do so. PER0609-
10. In response to these comments, the FAA simply asserted that “FAA’s Orders
carry no requirement or obligation . . . to reconcile the [greenhouse gas] GHG
emissions generated by the Proposed Project with the State of California GHG
emissions goals,” then concluded without further explanation or analysis that the
Project will not result in significant greenhouse gas emissions. PER0611. NEPA
requires more than these conclusory statements. See Bob Marshall All., 852 F.2d
at 1225; Blue Mountains Biodiversity Project, 161 F.3d at 1212; Ocean Advocates,
402 F.3d at 864.
The Respondents’ failure to evaluate the Project’s conformity with
California’s greenhouse gases standards violates their obligation under NEPA to
consider whether the Project “threatens a violation” of state requirements. 40
C.F.R. § 1508.27(b)(10). Omitting such an evaluation renders the FAA Order
approving the Project arbitrary and capricious, because the agency has “entirely
failed to consider an important aspect of the problem.” Motor Vehicle Mfr. Ass’n,
463 U.S. at 42.
Case: 20-70272, 06/30/2020, ID: 11739107, DktEntry: 57-1, Page 43 of 47
36
CONCLUSION AND REQUESTED RELIEF
For these reasons, California respectfully requests this Court to set aside
FAA’s December 23, 2019 Order as unlawful, require the FAA to conduct a
thorough environmental review by producing a detailed EIS, vacate the ground
lease, and enjoin further construction and operations on the Project until
Respondents comply with NEPA.
Respectfully submitted this 30th day of June 2020.
XAVIER BECERRA Attorney General of California EDWARD H. OCHOA SENIOR ASSISTANT ATTORNEY GENERAL CHRISTIE VOSBURG Supervising Deputy Attorney General s/ Yuting Chi YUTING YVONNE CHI Deputy Attorney General Attorneys for State of California
Case: 20-70272, 06/30/2020, ID: 11739107, DktEntry: 57-1, Page 44 of 47
37
CERTIFICATE OF COMPLIANCE I hereby certify that PETITIONER STATE OF CALIFORNIA’S
OPENING BRIEF contains 7864 words and is 36 pages, excluding the items
exempted by Federal Rule of Appellate Procedure 32(f), and thus complies with
this Court’s type-volume and length requirements under Appellate Rules 28 and
32(g), and Circuit Rule 28.1-1(b). I further certify that this brief is proportionately
spaced and has a typeface of 14 points, and thus it complies with the typeface and
type-style requirements of Appellate Rules 32(a)(5) and (6).
Executed on June 30, 2020, in Oakland, California.
s/ Yuting Chi YUTING YVONNE CHI Attorney for Petitioner
Case: 20-70272, 06/30/2020, ID: 11739107, DktEntry: 57-1, Page 45 of 47
38
STATEMENT OF RELATED CASES
Pursuant to Rule 28-2.6, California states that it is unaware of any related
case.
Executed on June 30, 2020, in Oakland, California.
s/ Yuting Chi YUTING YVONNE CHI Attorney for Petitioner
Case: 20-70272, 06/30/2020, ID: 11739107, DktEntry: 57-1, Page 46 of 47
39
CERTIFICATE OF SERVICE
I hereby certify that on June 30, 2020, I electronically filed the foregoing
PETITIONER STATE OF CALIFORNIA’S OPENING BRIEF with the Clerk
of the Court for the United States Court of Appeals for the Ninth Circuit by using
the appellate CM/ECF system. Participants in the case who are registered
CM/ECF users will be served by the appellate CM/ECF system.
Executed on June 30, 2020, in Oakland, California.
s/ Yuting Chi YUTING YVONNE CHI Attorney for Petitioner
Case: 20-70272, 06/30/2020, ID: 11739107, DktEntry: 57-1, Page 47 of 47