informetrica limited april 2002 ahpp summary 1 alaska highway pipeline project (ahpp) summary of...

51
April 2002 AHPP Summary 1 Informetric a Limited Alaska Highway Pipeline Project (AHPP) Summary of Findings Informetrica Limited May 3, 2002

Upload: lynne-terry

Post on 23-Dec-2015

214 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Informetrica Limited April 2002 AHPP Summary 1 Alaska Highway Pipeline Project (AHPP) Summary of Findings Informetrica Limited May 3, 2002

April 2002 AHPP Summary 1

Informetrica

Limited

Alaska Highway Pipeline Project (AHPP)

Summary of Findings

Informetrica Limited

May 3, 2002

Page 2: Informetrica Limited April 2002 AHPP Summary 1 Alaska Highway Pipeline Project (AHPP) Summary of Findings Informetrica Limited May 3, 2002

April 2002 AHPP Summary 2

Informetrica

Limited

The Future Demand for Natural Gas

• Gas demand in the North American economy is rising, with projections of 38.5 tcf per year by 2020

• The real price of NG is expected to rise• Alaska supplies are competitive, if delivered

through an efficient transportation system• Incremental supplies of 1.4 tcf per year available

from North Slope

Page 3: Informetrica Limited April 2002 AHPP Summary 1 Alaska Highway Pipeline Project (AHPP) Summary of Findings Informetrica Limited May 3, 2002

April 2002 AHPP Summary 3

Informetrica

Limited

Page 4: Informetrica Limited April 2002 AHPP Summary 1 Alaska Highway Pipeline Project (AHPP) Summary of Findings Informetrica Limited May 3, 2002

April 2002 AHPP Summary 4

Informetrica

Limited

B.C.

Alberta

N.W.T.Yukon

Alaska

FortSimpson

FortNelson

Whitehorse

FortSt.John

PrudhoeBay

Inuvik

Fort GoodHope

BoundaryLake

MackenzieDeltaStandAlone

MackenzieDeltaStandAlone

Northern RouteNorthern Route

AlaskaHighwayRoute

AlaskaHighwayRoute

Figure 3 – Proposed Pipeline Routes

Page 5: Informetrica Limited April 2002 AHPP Summary 1 Alaska Highway Pipeline Project (AHPP) Summary of Findings Informetrica Limited May 3, 2002

April 2002 AHPP Summary 5

Informetrica

Limited

Project Characteristics

• Length – 2, 810 km (1,746 miles)

• Pipe – 42”, 0.75” wall, X80

• Tons of steel pipe – 1,381,000

• Construction Costs – $13.6 B (US$9.1 B)

• Real Tariff – $1.57 /mcf (US$1.05)

• Volume – 2.5 bcfd rising to 4 bcfd

• Compressors - 40

Page 6: Informetrica Limited April 2002 AHPP Summary 1 Alaska Highway Pipeline Project (AHPP) Summary of Findings Informetrica Limited May 3, 2002

April 2002 AHPP Summary 6

Informetrica

Limited

Alaska

• Length – 1,193 km (741 miles)

• Pipe – 42”, 0.75” wall, X80

• Tons of steel pipe – 586,000

• Construction Costs – $6.6 B (US$4.4 B) 49%

• Real Tariff – $0.766 /mcf (US$0.51)

• Volume – 2.5 bcfd to 4 bcfd

• Compressors - 16

Page 7: Informetrica Limited April 2002 AHPP Summary 1 Alaska Highway Pipeline Project (AHPP) Summary of Findings Informetrica Limited May 3, 2002

April 2002 AHPP Summary 7

Informetrica

Limited

Yukon

• Length – 832 km (517 miles)

• Pipe – 42”, 0.75” wall, X80

• Tons of steel pipe – 409,000

• Construction Costs – $3.8 B (US$2.5 B) 54%

• Real Tariff – $0.435 /mcf (US$0.29)

• Volume – 2.5 bcfd to 4 bcfd

• Compressors – 10

Page 8: Informetrica Limited April 2002 AHPP Summary 1 Alaska Highway Pipeline Project (AHPP) Summary of Findings Informetrica Limited May 3, 2002

April 2002 AHPP Summary 8

Informetrica

Limited

British Columbia

• Length – 721 km (448 miles)

• Pipe – 42”, 0.75” wall, X80

• Tons of steel pipe – 355,000

• Construction Costs – $3.0 B (US$2.0 B) 43%

• Real Tariff – $0.348 /mcf (US$0.232)

• Volume – 2.5 bcfd to 4 bcfd

• Compressors - 14

Page 9: Informetrica Limited April 2002 AHPP Summary 1 Alaska Highway Pipeline Project (AHPP) Summary of Findings Informetrica Limited May 3, 2002

April 2002 AHPP Summary 9

Informetrica

Limited

Alberta

• Length – 64 km (40 miles)

• Pipe – 42”, 0.75” wall, X80

• Tons of steel pipe – 32,000

• Construction Costs – $0.2 B (US$0.12 B) 3%

• Real Tariff – $0.023 /mcf (US$0.015)

• Volume – 2.5 bcfd to 4 bcfd

• Compressors - 0

Page 10: Informetrica Limited April 2002 AHPP Summary 1 Alaska Highway Pipeline Project (AHPP) Summary of Findings Informetrica Limited May 3, 2002

April 2002 AHPP Summary 10

Informetrica

Limited

Comparison to TAPS

Cost (2000$)

Length

BTU Throughput per day

Tons of pipe

Employment

TAPS• US$11.3 B• 800 miles• 8.4 trillion • 450,000• 70,000

AHPP• US$9.1 B• 1750 miles• 4.1 trillion • 1,381,000• 59,000

Page 11: Informetrica Limited April 2002 AHPP Summary 1 Alaska Highway Pipeline Project (AHPP) Summary of Findings Informetrica Limited May 3, 2002

April 2002 AHPP Summary 11

Informetrica

Limited

Volumes of Gas

0

0.5

1

1.5

2

2.5

3

3.5

4

4.5

2005 2010 2015

bill

ion

cu

bic

fe

et

pe

r d

ay

Page 12: Informetrica Limited April 2002 AHPP Summary 1 Alaska Highway Pipeline Project (AHPP) Summary of Findings Informetrica Limited May 3, 2002

April 2002 AHPP Summary 12

Informetrica

Limited

Tariffs

1.00

1.50

2.00

2.50

3.00

2001 2006 2011 2016 2021 2026 2031Year

Tarif

f (C

dn$/

mcf

)

Levelized Nominal Escalated Nominal Levelized Real

Page 13: Informetrica Limited April 2002 AHPP Summary 1 Alaska Highway Pipeline Project (AHPP) Summary of Findings Informetrica Limited May 3, 2002

April 2002 AHPP Summary 13

Informetrica

Limited

Tariff Analysis

• A nominal tariff of $2.05 per mcf (Canadian $) , or

• A real tariff that starts at $1.57 per mcf in 2001, escalated by CPI will produce equivalent incomes

• Alaska (C$0.766), Canada (C$0.805)• Yukon (C$0.435), BC (C$0.348), Alberta

(C$0.023)

Page 14: Informetrica Limited April 2002 AHPP Summary 1 Alaska Highway Pipeline Project (AHPP) Summary of Findings Informetrica Limited May 3, 2002

April 2002 AHPP Summary 14

Informetrica

Limited

Types of analysis for this project

• Benefit-Cost Analysis

• National Economic Impact

• Provincial/Territorial Economic Impact

• Regional-Urban Model

• Local Area Model

• Occupational Impact

• YTG Revenue and Expenditure Model

Page 15: Informetrica Limited April 2002 AHPP Summary 1 Alaska Highway Pipeline Project (AHPP) Summary of Findings Informetrica Limited May 3, 2002

April 2002 AHPP Summary 15

Informetrica

Limited

Benefit-cost Analysis• Positive Net Benefits

• Net gains mainly in Alaska and lower 48

• Regulation of pipeline rate of return minimizes Canadian gains

• Increased government revenues in Canada

Page 16: Informetrica Limited April 2002 AHPP Summary 1 Alaska Highway Pipeline Project (AHPP) Summary of Findings Informetrica Limited May 3, 2002

April 2002 AHPP Summary 16

Informetrica

LimitedNPV of Net BenefitsB$, Canadian 0% 7% 10% 15%

Production, US 32.4 8.0 4.6 1.9

Transmission, US 15.4 2.3 0.6 -0.8

Transmission, Cdn 13.8 1.6 0.1 -1.1

Government, US 50.0 13.6 8.5 4.2

Government, Cdn 12.5 3.7 2.4 1.3

Federal 6.2 1.8 1.2 0.6

Provincial 6.3 1.9 1.2 0.7

Total 124.1 29.2 16.0 5.5

Page 17: Informetrica Limited April 2002 AHPP Summary 1 Alaska Highway Pipeline Project (AHPP) Summary of Findings Informetrica Limited May 3, 2002

April 2002 AHPP Summary 17

Informetrica

Limited

Implications of Benefit-cost

• Financing from US sources or normal financial markets

• Canadian interest hinges on federal & provincial revenue

• Yukon interest areas:– Jobs– Energy options– Minimizing adverse effects

Page 18: Informetrica Limited April 2002 AHPP Summary 1 Alaska Highway Pipeline Project (AHPP) Summary of Findings Informetrica Limited May 3, 2002

April 2002 AHPP Summary 18

Informetrica

Limited

Economic Impact Analysis

• Uses statistical/econometric methods to develop a mathematical model of the economy (the “Base Case”)

• Adds the project parameters (“Injection”) to the “Base Case” model to estimate Direct, Indirect and Induced Effects on a number of economic variables (e.g., GDP, employment, tax revenues)

Page 19: Informetrica Limited April 2002 AHPP Summary 1 Alaska Highway Pipeline Project (AHPP) Summary of Findings Informetrica Limited May 3, 2002

April 2002 AHPP Summary 19

Informetrica

Limited

Two Scenarios

• Scenario I – Governments retain all balance improvements, choosing to reduce outstanding debt

• Scenario 2 – Federal government recycles improved balances through:– Corporate tax reductions– Personal income tax reductions– Reduced EI contributions

Page 20: Informetrica Limited April 2002 AHPP Summary 1 Alaska Highway Pipeline Project (AHPP) Summary of Findings Informetrica Limited May 3, 2002

April 2002 AHPP Summary 20

Informetrica

Limited

Key Impacts

• Investment• GDP• Employment• Unemployment• Inflation• Fiscal Balances (Taxes, Govt. Spending, Debt)• Current Account Balances

Page 21: Informetrica Limited April 2002 AHPP Summary 1 Alaska Highway Pipeline Project (AHPP) Summary of Findings Informetrica Limited May 3, 2002

April 2002 AHPP Summary 21

Informetrica

Limited

Construction Period Impacts, 2002-12

GDP,Millions 2000$)

Employment(person-years)

Investment - Canada 6,990 30,440

Yukon 3,369 12,114

Scenario 1-Canada 9,762 72,799

Yukon 3,736 19,448

Scenario 2 - Canada 14,497 194,396

Yukon 5,082 28,585

Page 22: Informetrica Limited April 2002 AHPP Summary 1 Alaska Highway Pipeline Project (AHPP) Summary of Findings Informetrica Limited May 3, 2002

April 2002 AHPP Summary 22

Informetrica

Limited

Operations Period Impacts, 2013-25

GDP,Millions 2000$)

Employment(person-years)

Revenue- Canada 15,288 4,253 (327)

Yukon 8,252 2,220 (171)

Scenario 1-Canada 16,678 34,921

Yukon 7,775 13,029

Scenario 2 - Canada 16,906 182,678

Yukon 8,911 21,998

Page 23: Informetrica Limited April 2002 AHPP Summary 1 Alaska Highway Pipeline Project (AHPP) Summary of Findings Informetrica Limited May 3, 2002

April 2002 AHPP Summary 23

Informetrica

Limited

Investment

-$500

$0

$500

$1,000

$1,500

$2,000

2002 2005 2008 2011 2014 2017 2020 2023

mill

ion

s o

f c

on

sta

nt

20

00

$

Structures (direct) Machinery & Equipment (direct)

Total Induced (Scenario 1) Total Induced Scenario 2)

Page 24: Informetrica Limited April 2002 AHPP Summary 1 Alaska Highway Pipeline Project (AHPP) Summary of Findings Informetrica Limited May 3, 2002

April 2002 AHPP Summary 24

Informetrica

Limited

GDP

0

0.05

0.1

0.15

0.2

0.25

0.3

2002 2007 2012 2017 2022

% Im

pa

ct

Scenario 1 Scenario 2

Page 25: Informetrica Limited April 2002 AHPP Summary 1 Alaska Highway Pipeline Project (AHPP) Summary of Findings Informetrica Limited May 3, 2002

April 2002 AHPP Summary 25

Informetrica

Limited

Employment

-10

0

10

20

30

40

50

2002 2007 2012 2017 2022

Em

plo

ym

en

t (0

00

s)

Scenario 1 Scenario 2

Page 26: Informetrica Limited April 2002 AHPP Summary 1 Alaska Highway Pipeline Project (AHPP) Summary of Findings Informetrica Limited May 3, 2002

April 2002 AHPP Summary 26

Informetrica

Limited

Fiscal Balances – Scenario 1(millions of dollars)

$0

$500

$1,000

$1,500

$2,000

$2,500

2002 2007 2012 2017 2022

Imp

act

(No

min

al $

)

Federal Provincial-Local-Hospital CPP & QPP

Page 27: Informetrica Limited April 2002 AHPP Summary 1 Alaska Highway Pipeline Project (AHPP) Summary of Findings Informetrica Limited May 3, 2002

April 2002 AHPP Summary 27

Informetrica

Limited

Fiscal Balances – Scenario 2(millions of dollars)

-$500

$0

$500

$1,000

$1,500

2002 2007 2012 2017 2022

Imp

act

(No

min

al $

)

Federal Provincial-Local-Hospital CPP & QPP

Page 28: Informetrica Limited April 2002 AHPP Summary 1 Alaska Highway Pipeline Project (AHPP) Summary of Findings Informetrica Limited May 3, 2002

April 2002 AHPP Summary 28

Informetrica

Limited

National Findings

• No stresses on macro economy

• Procurement effects important to steel and turbines

• Additional investment may be needed in Alberta

• Larger impacts if governments recycle their “fiscal dividend”

Page 29: Informetrica Limited April 2002 AHPP Summary 1 Alaska Highway Pipeline Project (AHPP) Summary of Findings Informetrica Limited May 3, 2002

April 2002 AHPP Summary 29

Informetrica

Limited

Regional Impacts

• Direct spending on construction & operations determined by location of pipeline

• Indirect spending (commodity content of direct spending) determined by the location of suppliers and their suppliers

• Induced spending depends on distribution of wage income and sources of supply of consumer goods and services

Page 30: Informetrica Limited April 2002 AHPP Summary 1 Alaska Highway Pipeline Project (AHPP) Summary of Findings Informetrica Limited May 3, 2002

April 2002 AHPP Summary 30

Informetrica

Limited

Territories(effects concentrated in Yukon)

0

2

4

6

8

10

12

2002 2005 2008 2011 2014 2017 2020 2023

% Im

pac

t GD

P

0

2

4

6

8

10

2002 2005 2008 2011 2014 2017 2020 2023

Em

plo

ymen

t (00

0s)

Scenario I Scenario II

Page 31: Informetrica Limited April 2002 AHPP Summary 1 Alaska Highway Pipeline Project (AHPP) Summary of Findings Informetrica Limited May 3, 2002

April 2002 AHPP Summary 31

Informetrica

Limited

British Columbia

0

0.1

0.2

0.3

0.4

0.5

2002 2005 2008 2011 2014 2017 2020 2023

% I

mp

act

GD

P

0

500

1000

1500

2000

2002

mill

ions

of c

onst

ant 2

000$

#REF! #REF!0

0.2

0.4

0.6

0.8

1

1.2

2002

% Im

pact

(bar

s)

0

0.2

0.4

0.6

0.8

1

1.2

% Im

pact

(lin

es)

#REF! #REF! #REF! #REF! #REF! #REF!

-2

0

2

4

6

8

10

12

2002 2005 2008 2011 2014 2017 2020 2023

Em

plo

ymen

t (0

00s)

Scenario I Scenario II

Page 32: Informetrica Limited April 2002 AHPP Summary 1 Alaska Highway Pipeline Project (AHPP) Summary of Findings Informetrica Limited May 3, 2002

April 2002 AHPP Summary 32

Informetrica

Limited

Alberta

0

0.05

0.1

0.15

0.2

2002 2005 2008 2011 2014 2017 2020 2023

% Im

pac

t G

DP

-1

0

1

2

3

4

5

2002 2005 2008 2011 2014 2017 2020 2023

Em

plo

ymen

t (0

00s)

Scenario I Scenario II

Page 33: Informetrica Limited April 2002 AHPP Summary 1 Alaska Highway Pipeline Project (AHPP) Summary of Findings Informetrica Limited May 3, 2002

April 2002 AHPP Summary 33

Informetrica

Limited

Rest-of-Canada

-0.05

0

0.05

0.1

0.15

0.2

2002 2005 2008 2011 2014 2017 2020 2023

% I

mp

act

GD

P

-10

-5

0

5

10

15

20

25

2002 2005 2008 2011 2014 2017 2020 2023

Em

plo

ymen

t (0

00s)

Scenario I Scenario II

Page 34: Informetrica Limited April 2002 AHPP Summary 1 Alaska Highway Pipeline Project (AHPP) Summary of Findings Informetrica Limited May 3, 2002

April 2002 AHPP Summary 34

Informetrica

Limited

Regional Findings

• The impacts on the provinces are modest• Impacts on Yukon are large• Procurement has been directed to increase

impact and test industrial capacities• Distinction between residence of workers

and place of work important• Assumption that 80% of construction

workers come from outside Yukon

Page 35: Informetrica Limited April 2002 AHPP Summary 1 Alaska Highway Pipeline Project (AHPP) Summary of Findings Informetrica Limited May 3, 2002

April 2002 AHPP Summary 35

Informetrica

Limited

Yukon Impacts

• Yukon economy identified separately• Base Case View• Impacts from RIM on Yukon Base• Focus on:

– Employment– Wage Bill– Disposable Income

• Direct and Indirect +Induced

Page 36: Informetrica Limited April 2002 AHPP Summary 1 Alaska Highway Pipeline Project (AHPP) Summary of Findings Informetrica Limited May 3, 2002

April 2002 AHPP Summary 36

Informetrica

Limited

Yukon GDP Impact

0

10

20

30

40

2002 2004 2006 2008 2010 2012 2014 2016 2018 2020 2022 2024

% I

mp

act

Scenario 1 Scenario 2

Page 37: Informetrica Limited April 2002 AHPP Summary 1 Alaska Highway Pipeline Project (AHPP) Summary of Findings Informetrica Limited May 3, 2002

April 2002 AHPP Summary 37

Informetrica

Limited

Yukon Employment

0

2

4

6

8

10

2002 2004 2006 2008 2010 2012 2014 2016 2018 2020 2022 2024

Lev

els

Scenario 1 Scenario 2

Page 38: Informetrica Limited April 2002 AHPP Summary 1 Alaska Highway Pipeline Project (AHPP) Summary of Findings Informetrica Limited May 3, 2002

April 2002 AHPP Summary 38

Informetrica

Limited

Yukon Wage Bill

0

5

10

15

20

25

30

35

2002 2004 2006 2008 2010 2012 2014 2016 2018 2020 2022 2024

% I

mp

act

Scenario I Scenario II

Page 39: Informetrica Limited April 2002 AHPP Summary 1 Alaska Highway Pipeline Project (AHPP) Summary of Findings Informetrica Limited May 3, 2002

April 2002 AHPP Summary 39

Informetrica

Limited

Yukon Real Disposable Income

05

1015202530

2002 2004 2006 2008 2010 2012 2014 2016 2018 2020 2022 2024

Scenario 1 Scenario 2

Page 40: Informetrica Limited April 2002 AHPP Summary 1 Alaska Highway Pipeline Project (AHPP) Summary of Findings Informetrica Limited May 3, 2002

April 2002 AHPP Summary 40

Informetrica

Limited

Key Industry Impacts - YukonTop 10 industry impacts during construction period

1. Construction 6. Telecommunications

2. Professional Services to Business 7. Other Personal Services

3. Accommodation and Food 8. Retail Trade

4. Personal Finance 9. Air Transportation

5. Motor Transportation 10. Printing and Publishing

Employment Impacts Scenario 1 Scenario 2

Peak Employment 6930 8250

Average Employment 2005-07 4723 5900

Page 41: Informetrica Limited April 2002 AHPP Summary 1 Alaska Highway Pipeline Project (AHPP) Summary of Findings Informetrica Limited May 3, 2002

April 2002 AHPP Summary 41

Informetrica

Limited

Yukon Fiscal ImpactsScenario I

-15

-10

-5

0

5

10

15

20

25

30

2001/02 2002/03 2003/04 2004/05 2005/06 2006/07 2007/08 2008/09 2009/10

Imp

ac

t le

ss

Ba

se

($

mil)

Own-Source Revenue Fiscal Grant

Page 42: Informetrica Limited April 2002 AHPP Summary 1 Alaska Highway Pipeline Project (AHPP) Summary of Findings Informetrica Limited May 3, 2002

April 2002 AHPP Summary 42

Informetrica

Limited

Yukon Fiscal ImpactsScenario II

-15

-10

-5

0

5

10

15

20

25

30

35

2001/02 2002/03 2003/04 2004/05 2005/06 2006/07 2007/08 2008/09 2009/10

Imp

ac

t le

ss

Ba

se

($

mil)

Own-Source Revenue Fiscal Grant

Page 43: Informetrica Limited April 2002 AHPP Summary 1 Alaska Highway Pipeline Project (AHPP) Summary of Findings Informetrica Limited May 3, 2002

April 2002 AHPP Summary 43

Informetrica

Limited

Findings from Fiscal Model

• Own revenue increases from activity are offset by federal transfer reductions

• Expenditure increases will worsen Territorial Balance, unless financing arrangement made or territorial tax rates increased

• Revenue consequences of pipeline construction are modest at Territorial level

• Federal government is major beneficiary

Page 44: Informetrica Limited April 2002 AHPP Summary 1 Alaska Highway Pipeline Project (AHPP) Summary of Findings Informetrica Limited May 3, 2002

April 2002 AHPP Summary 44

Informetrica

Limited

Local Impacts

• Employment Effects

• Local supply

• Spending by non-residents

• Bidding up Local Wages

Page 45: Informetrica Limited April 2002 AHPP Summary 1 Alaska Highway Pipeline Project (AHPP) Summary of Findings Informetrica Limited May 3, 2002

April 2002 AHPP Summary 45

Informetrica

Limited

Occupational Impacts, Yukon

1. Construction (1128)

2. Clerical (432)

3. Services (370)

4. Managerial & Administration (366)

5. Sales (199)

6. Fabricating, Assembly (157)

7. Natural Sciences (132)

8. Transportation & Eqpt. Ops (104)

9. Farming (70)

10. Machining (55)

Page 46: Informetrica Limited April 2002 AHPP Summary 1 Alaska Highway Pipeline Project (AHPP) Summary of Findings Informetrica Limited May 3, 2002

April 2002 AHPP Summary 46

Informetrica

Limited

Tough Questions

• Construction costs determine tariff and wellhead prices: can costs be controlled?

• Problems on any segment can hurt project economics. How to coordinate and avoid difficulties?

• Will escalating tariff be acceptable?• Need commitments to use the pipeline for some

defined amount for twenty-five years in order to finance it. Who guarantees performance?

Page 47: Informetrica Limited April 2002 AHPP Summary 1 Alaska Highway Pipeline Project (AHPP) Summary of Findings Informetrica Limited May 3, 2002

April 2002 AHPP Summary 47

Informetrica

Limited

Yukon Development

• Expansion Opportunities – see industry forecasts

• New areas – not supplied by Yukon now What can be done here?

• Ancillary and Post-pipeline Opportunities

• When to start?

Page 48: Informetrica Limited April 2002 AHPP Summary 1 Alaska Highway Pipeline Project (AHPP) Summary of Findings Informetrica Limited May 3, 2002

April 2002 AHPP Summary 48

Informetrica

Limited

Comparison to Other Studies

• 2000 Federal Study– Longer Pipeline, including Alberta and Sask.– Pipe imported– Fiscal policy like Scenario 1– Construction costs per mile lower– Less Throughput– Total tariff larger (US$2.83 vs US$2.63 from

Prudhoe Bay to Chicago)

Page 49: Informetrica Limited April 2002 AHPP Summary 1 Alaska Highway Pipeline Project (AHPP) Summary of Findings Informetrica Limited May 3, 2002

April 2002 AHPP Summary 49

Informetrica

Limited

Next Steps

• Final Route Definition

• Define total direct HR requirements

• Review occupational requirements against supplies

• Contingency for low NG prices– Indexed bonds?– Long-tem contracts?

Page 50: Informetrica Limited April 2002 AHPP Summary 1 Alaska Highway Pipeline Project (AHPP) Summary of Findings Informetrica Limited May 3, 2002

April 2002 AHPP Summary 50

Informetrica

Limited

Steps after “Go”

• Procurement Plans• ROW use• Training of Yukoners• Yukon business mobilization• Federal-territorial agreements• Agreements with Alaska and BC about

people, goods and services, supply, regulatory, and information

Page 51: Informetrica Limited April 2002 AHPP Summary 1 Alaska Highway Pipeline Project (AHPP) Summary of Findings Informetrica Limited May 3, 2002

April 2002 AHPP Summary 51

Informetrica

Limited

AHPP – Will it Go?

• Cost effective – Alaska field costs are sunk and Alberta south has been pre-built

• Least-cost option for delivering Prudhoe Bay gas

• Most regulatory hurdles already jumped• No insurmountable bottlenecks identified• Do US consumers want the gas? Are

producers ready to sell?