initial environmental examination - adb

260
Initial Environmental Examination Document stage: Draft Project Number: 42486-016 December 2018 IND: Madhya Pradesh Urban Services Improvement Program Subproject of Sewerage Improvement in Anjad Town Package No: MPUSIP-2F Prepared by Project Management Consultant, Madhya Pradesh Urban Development Company, Government of Madhya Pradesh for the Asian Development Bank. This draft initial environmental examination is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, management, or staff, and may be preliminary in nature. Your attention is directed to the ‘terms of use’ section on ADB’s website. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

Upload: others

Post on 20-Oct-2021

9 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Initial Environmental Examination - ADB

Initial Environmental Examination Document stage: Draft Project Number: 42486-016 December 2018

IND: Madhya Pradesh Urban Services Improvement Program – Subproject of Sewerage Improvement in Anjad Town

Package No: MPUSIP-2F

Prepared by Project Management Consultant, Madhya Pradesh Urban Development Company, Government of Madhya Pradesh for the Asian Development Bank. This draft initial environmental examination is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, management, or staff, and may be preliminary in nature. Your attention is directed to the ‘terms of use’ section on ADB’s website. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

Page 2: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

1

Draft Initial Environmental Examination

December 2018

IND: Madhya Pradesh Urban Services Improvement Program–Subproject of Sewerage Improvement in Anjad Town

Prepared by Project Management Consultant, Madhya Pradesh Urban Development Company, Government of Madhya Pradesh for the Asian Development Bank

Page 3: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

2

CURRENCY EQUIVALENTS

(as of 27 Septmber2018)

Currency unit – Conversion INR1.00 = $.0.015

$1.00 = INR66.00

Abbreviations

AC – Asbestos Cement ADB – Asian Development Bank ANP - Anjad Nagar Parishad ASI – Archeological Survey of India ASO – Assistant Safeguards Officer CFE – Consent for Establishment CFO – Consent for Operation CPCB Central Pollution Control Board EA – Executing Agency EAC – Expert Appraisal Committee EC – Environmental Clearance EHS – Environmental Health & Safety EIA – Environmental Impact Assessment EMP – Environmental Management Plan; ESR – Elevated Service Reservoir GOI – Government of India GOMP – Government of Madhya Pradesh IA – Implementing Agency IEE – Initial Environmental Examination; LPCD – Liters per Capita per Day MLD – Million Liters per Day MOEF – Ministry of Environment and Forest MPPCB – Madhya Pradesh Pollution Control Board MPUDC – Madhya Pradesh Urban Development Company MPS – Main Pumping Station NOC – No Objection Certificate PE – Polyethylene PHED – Public Health Engineering Department PIU – Project Implementation Unit; PMC – Project Management Consultant PMU – Project Management Unit PO – Project Officer PPTA – Project Preparatory Technical Assistance PWD – Public Works Department REA – Rapid Environmental Assessment Checklist RoW – Right of Way SEIAA – State Environmental Impact Assessment Authority SPS – Safeguard Policy Statement, 2009 UDED – Urban Development & Environment Department ULB – Urban Local Body WHO – World Health Organization STP – SewageTreatment Plant

SBR – Sequence Batch Reactor

Page 4: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

3

WEIGHTS AND MEASURES S Degree Celsius

km kilometre lpcd litres per capita per day mm millimeter m metre MLD million litres per day mm millimetre Nos. Numbers sq.km Square Kilometer

Page 5: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

4

TABLE OF CONTENTS

I. EXECUTIVE SUMMARY .............................................................................................................. 10

II. INTRODUCTION ............................................................................................................................ 16

A. Background ....................................................................................................................................... 16

C. Report Structure ............................................................................................................................... 17

III. DESCRIPTION OF THE PROJECT ............................................................................................ 18

A. Project Area ...................................................................................................................................... 18

B. Existing Water Supply, Sewerage and Storm Water DrainageSystem ................................... 19

C. Proposed Project ............................................................................................................................... 24

IV. POLICY, LEGAL AND ADMINISTRATIVE FRAMEWORK ..................................................... 59

A. ADB Policy ........................................................................................................................................ 59

B. National Environmental Laws ......................................................................................................... 59

V. DESCRIPTION OF THE ENVIRONMENT ................................................................................. 67

A. Methodology Used for Baseline Study .......................................................................................... 67

B. Physical Resources ......................................................................................................................... 67

C. Ecological Resources ...................................................................................................................... 80

D. Economic Development .................................................................................................................. 82

E. Socio Cultural Resources ............................................................................................................... 84

F. Subproject Site Environmental Features ...................................................................................... 86

VI. ANTICIPATED ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES .................. 97

A. Pre-Construction Impacts – Design & Location ......................................................................... 98

B. Construction Impacts ..................................................................................................................... 105

B. Operation and Maintenance Impacts ........................................................................................ 117

VII. PUBLIC CONSULTATION AND INFORMATION DISCLOSURE ......................................... 122

A. Overview .......................................................................................................................................... 122

B. Public Consultation ........................................................................................................................ 123

C. Information Disclosure ................................................................................................................. 135

VIII. GRIEVANCE REDRESS MECHANISM ................................................................................... 136

A. Project Specific Grievance Redress Mechanism .................................................................... 136

B. Purpose of the GRM Manual: ..................................................................................................... 136

C. Principles: ...................................................................................................................................... 136

(a) Accessibility ................................................................................................................................... 136

Page 6: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

5

(b) Predictability .................................................................................................................................. 136

(c) Transparency ................................................................................................................................ 137

(d) Credibility ....................................................................................................................................... 137

(e) Fairness ......................................................................................................................................... 137

(f) Feedback ....................................................................................................................................... 137

D. Nature and scope of Grievance Redress Mechanism under MPUSIP ................................ 137

E. Structure of GRM and its Functions .......................................................................................... 137

F. Process of Grievance Redress Mechanism ............................................................................. 141

G. Monitoring and Evaluation systems of GRM ............................................................................ 144

H. Action Plan for the formation of the GRM................................................................................. 145

IX. ENVIRONMENTAL MANAGEMENT PLAN ............................................................................... 146

A. Environmental Management Plan ............................................................................................... 146

B. Implementation Arrangements ..................................................................................................... 182

C. Training Needs ............................................................................................................................... 185

D. Monitoring and Reporting ............................................................................................................. 186

E. EMP Implementation Cost ............................................................................................................ 186

X. CONCLUSION AND RECOMMENDATIONS .......................................................................... 191

List of Tables

Table 1: Ward Wise Source & Water Supply................................................................................. 21

Table 2: Proposed Components in New Water Supply Scheme ............................................. 21

Table 3: Existing Status of Wastewater Management ................................................................ 23

Table 4: Present status of the toilets .............................................................................................. 24

Table 5: Details of Sewage Zones ................................................................................................... 28

Table 6: Population Projection For each Zones .......................................................................... 28

Table 7: Sewage Generation ............................................................................................................. 29

Table 8: Maximum Depth (m) of Sewer from Ground Level Zone Wise ............................... 29

Table 9: Proposed Discharge Standards recommended for Disposal from STP ............... 29

Table 10: Proposed Sewerage Subproject Components in Anjad Town ............................... 32

Table 11: Details of Manhole, Numbers, Sizes Types & Materials .......................................... 36

Table 12: Width of Road with respect to Manhole No. along with Dia and Depth of Sewer

and Trench Width for Sewer Main Trunk Line .............................................................................. 37

Page 7: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

6

Table 13: Details of Depth Wise Length of sewer ........................................................................ 39

Table 14: Details of Diameter Wise Depth & Trench Excavation Width of Sewer............... 39

Table 15: Applicable Environmental Regulations ........................................................................ 60

Table 16: Effluent Disposal Standards of STPs Applicable to All Modes of Disposal ...... 62

Table 17: Standards for Sludge Reuse as Manure ...................................................................... 64

Table 18:-WHO Ambient Air Quality Guidelines ........................................................................... 65

Table 19:-World Bank Group’s EHS Noise Level Guidelines .................................................. 66

Table 20: Water Quality of the River Narmada ............................................................................. 74

Table 21: Wastewater Quality of the Bhongli Nala ...................................................................... 75

Table 22 : Hydrology ........................................................................................................................... 76

Table 23: Quality of Ground Water of Barwani District.............................................................. 77

Table 24:-Site Environmental Features- Anjad ............................................................................ 86

Table 25: Proposed Design Effluent Values for STP and Discharge Standards of

MoEFCC ................................................................................................................................................ 117

Table 26: Summary of Consultation ............................................................................................. 123

Table 27:-Design Stage Environmental Management Plan ..................................................... 147

Table 28:- Environmental Management Plan of Anticipated Impacts during Pre-

Construction ....................................................................................................................................... 152

Table 29:- Environmental Management Plan of Anticipated Impacts during Construction

................................................................................................................................................................ 156

Table 30:- Environmental Management Plan of Anticipated Impacts during Operation ... 176

Table 31:-Environmental Monitoring Plan – Pre Constrction and Construction ................ 178

Table 32:-Environmental Monitoring Plan of Anticipated Impacts during Operation ....... 180

Table 33:-Outline Capacity Building Programon EMP Implementation ............................... 185

Table 34:- Cost Estimats to Implement the EMP ........................................................................ 188

List of Figures Figure 1: Ward Map Anjad Town ...................................................................................................... 18

Figure 2: Location of Anjad Town in MP ....................................................................................... 18

Figure 3: Existing Water Supply Map Anjad Town ..................................................................... 20

Figure 4: Water Intake and STP Discharge Location on Rivr Narmada For Anjad town Shown in Google Map ........................................................................................................................................ 20

Figure 5: Steps for Planning Septage Management in Zone-3, Anjad Town ....................... 28

Page 8: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

7

Figure 6: Location Map of Subproject Town in Barwani District, Madhya Pradesh .......... 31

Figure 7: Roads & Transpotation Map of Anjad Town ............................................................... 36

Figure 8: Type & Width of Trench .................................................................................................. 40

Figure 9: Proposed Zone Map for Anjad Town & Outfall of STP into drain ......................... 42

Figure 10: Proposed Sewer Network Map of Zone-1 for Anjad Town .................................... 43

Figure 11: Proposed Sewer Network Map of Zone-2 & Proposed Alignment of Pumping

Main for Anjad Town ........................................................................................................................... 45

Figure 12: Details of Proposed IPS for Anjad Town ................................................................... 46

Figure 13: Details of Proposed MPS in Anjad town .................................................................... 47

Figure 14: Layout Plan of STP for Anjad Town (Based on SBR Technology) ..................... 48

Figure 15:- Process Flow Diagram of STP at Anjad (SBR Technology) ................................ 49

Figure 16: GA Drawing of 3.66 MLD STP- Anjad (SBR Technology) ...................................... 50

Figure 17: Sludge Sump of 3.66 MLD- Anjad Town .................................................................... 51

Figure 18: - Gravity Sludge Thickener of 3.66 MLD in Anjad ................................................... 51

Figure 19: Thickened Sludge Sump of 3.66 MLD in Anjad town ............................................. 52

Figure 20:- Details of Septic Tanks & Soak Pits for Zone-3...................................................... 53

Figure 21:- Septic Tanks for Zone-3 ................................................................................................ 54

Figure 22: Google Map for the Location of IPS, MPS, STP & Treated Sewage Disposal

Point in Anjad Town ............................................................................................................................ 55

Figure 23: Tentative Green Buffer Area around Proposed IPS At Anjad .............................. 56

Figure 24: Tentative Green Buffer Area Around Proposed MPS ............................................. 57

Figure 25:Tentative Green Buffer Area Around Proposed STP ............................................... 58

Figure 26: Existing Drainage Map Anjad ...................................................................................... 68

Figure 27: Showing Anjad Town in Google Earth Map ........................................................... 69

Figure 28: Bhongli Nala / Bhongli River ....................................................................................... 72

Figure 29: Showing Google earth Map of Anjad Town Upto Narmada River ............................... 73

Figure 30: The weekly market operated along the Bhongli Nala ........................................... 73

Figure 31: Hydro geological Map, District Barwani (M.P.) ............................................................ 78

Figure 32: Depth of Water Level (Pre-Monsoon Season) .......................................................... 79

Figure 33: Depth of Water Level (Post-Monsoon Season) ........................................................ 79

Figure 34: Existing Landuse Map- Anjad Showing Forest Area ............................................ 81

Page 9: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

8

Figure 35:Proposed Landuse Map- Anjad Showing Forest Area .......................................... 81

Figure 36: Proposed STP Site with Area around 50, 100, 200, 250 & 500m circle along

with habitationShown in Google Map............................................................................................. 93

Figure 37: Proposed MPS Site with Area around within 50,100, & 200m circle alongwith

habitationShown in Google Map ...................................................................................................... 94

Figure 38: Proposed IPS Site with Area around within 50,100, & 200m circle alongwith

habitationShown in Google Map ...................................................................................................... 95

Figure 39: Proposed STP Outfall Nearby Local Nala Which Joins Bhongli Nala & Then to

Narmada River after travelling a Distance of approx. 15km Shown in Google Map .......... 96

Figure 40: Work Flow Diagram on GRM....................................................................................... 140

Figure 41: Structure and Process of GRC ................................................................................... 144

List of Appendices

Appendix 1: REA Checklist Sewerage and Sanitation ............................................................. 194

Appendix 2:National Ambient Air Quality Standards................................................................ 198

Appendix 3: Vehicle Exhaust Emission Norms ......................................................................... 198

Appendix 4: National Ambient Air Quality Standards in Respect of Noise ........................ 198

Appendix 5: EXTRACT FROM CONSTRUCTION & DEMOLITION MANAGEMENT ......... 199

APPENDIX 6: Salient Features of Major Labor Laws Applicable to Establishments

Engaged in Construction of Civil Works ..................................................................................... 205

Appendix 7: General Standards for Discharge of Environmental Pollutants

(Wastewater) ....................................................................................................................................... 207

Appendix 8:Sample Grievance Registration Form .................................................................... 210

Appendix 9: Sample Outline Spoils (construction waste) Management Plan .................... 212

Appendix 10: Sample Outline Traffic Management Plan ......................................................... 213

Appendix 11: SAMPLE ENVIRONMENTAL SITE INSPECTION REPORT ............................ 220

Appendix 12: Quarterly Reporting Format for Assistant Safeguards Officer .................... 223

Appendix 13: Summary of Consultation with Stakeholders ................................................................. 229

Appendix 13A - Photographs and List of Participants ............................................................ 237

Appendix 13B: Photographs of Consultation with local resident at IPS Site- Anjad ....................... 245

Appendix 13C:Consultaion Nearby MPS Site in Ward No.4 at Patel Nagar on 25.04.2018 & List of

Participant .............................................................................................................................................. 248

Appendix 13D: Consultation Photographs with Local People At Proposed STP Site- Anjad ........... 251

Appendix 14: Sample Location for Surface Water (River Narmada-U/S & D/S) & Bhongli

Nala Water ........................................................................................................................................... 256

Page 10: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

9

Appendix 15: Water Quality Results of River Narmada-U/S & D/S) ...................................... 257

Appendix 16: Water Quality Results of Bhongli Nala ............................................................... 259

Page 11: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

10

I. EXECUTIVE SUMMARY

1. Government of Madhya Pradesh with loan funding from Asian Development Bank (ADB)

has proposed to implement Madhya Pradesh Urban Services Improvement Project

(MPUSIP), herein after referred as the “Project”. Madhya Pradesh Urban Development

Company Limited (MPUDC) shall be the Implementing Agency and the State Urban

Development and Housing Department (UDHD) shall be the executing agency for the

Project.

2. The Program envisages to deliver:

(i) Continuous, pressurized, safe and sustainable drinking water through private

household metered connections in 64 tier II towns in the State; (ii) Sewage and storm water collection and treatment system in ten identified

towns, Khajuraho, Rajnagar, Barwaha, Dhamnod, Sanchi, Jabalpur, Maihar Anjad, Saikheda and Sanawad; and

(iii) Non-physical investments comprising of establishing GIS system, capacity building of participating urban local bodies in contract management, Improving local operators ’capability through global partnership and building capacity of the implementing agency, urban local bodies and services utilities for ensuring long term sustainability of services.

3. Anjad is located in the district of Barwani in the south-western part of Madhya Pradesh

state. Anjad is a small and class III town which was established as Nagar Panchayat on

1908. Presently the town has a population of about 26492 (census 2011 provisional figure)

which is divided into 15 wards. Nagar Parishad is situated along the main road connecting

Anjad with SH-26. The town is situated 17 km. from Barwani. Provision of sewerage

system in Anjad is one of the subprojects proposed under MPUSIP. At present, there is no

sewerage system in Anjad; about 52.77% of residents use septic tanks or soak pit for

sewage disposal, and rest of the houses dispose the wastewater directly into roadside

open drains. Most of the houses do not have in-built toilets.

4. The Subproject. The objective of this subproject is to develop sewerage management

services to the residents in Anjad Nagar Parishad (ANP). The subproject envisages

providing 100% coverage of population with sewage collection network and treatment

services, and includes civil works, project implementation and management, and non-

physical investments. The physical investment includes the following: (i) 23 km of sewer

network of diameter 100 mm to 400 mm (ii) manholes - 774 No.s (iii) Sewage Treatment

Plant (STP) of 3.66 million liters per day (MLD) capacity (iv) sewage pumping stations – 02

Nos – (a) intermediate pumping station (IPS) of 0.58 MLD capacity in Zone 1, and (b) Main

pumping station(MPS) in Zone 2 of capacity 3.66 MLD; (v) sewage main pipelines – (a)

pumping main of length 340 m and 100 mm diameter from IPS to MPS, (b) pumping main

of 2000 m length and 300 mm diameter from MPS to STP, (v) house sewer connections –

5,560 Nos, and, (vi). Outfall Sewer from STP to nearby available natura drain- 580 m

length of 400mm diameter Pipe. This subproject package is proposed for implementation

under a single Design-Build-Operate (DBO) contract package.

5. Implementation Arrangements: Urban Development and Housing Department (UDHD)

Page 12: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

11

of Government of Madhya Pradesh is the Executing Agency. Implementing Agency is the

Madhya Pradesh Urban Development Company (MPUDC), A central Project Management

Unit (PMU) attached to MPUDC is responsible for implementing the MPUSIP. The PMU

supported by Program Implementation Units (PIUs). A Program Management Consultant

(PMC) centrally located in PMU and with field teams in PIUs, supports PMU and PIUs in

implementation. Infrastructure will be designed, built, and operated (DBO) by contractor

for 10 years after which it will be transferred to the ULB. Project Officer (Environment) at

PMU and Assistant Safeguard Officer (ASO) at each of the PIU is responsible for

environment safeguards tasks, and supported by Environment Specialist of PMC Team.

Contractor personnel will include an Environment, Health and Safety (EHS) supervisor.

6. Screening and assessment of potential impacts: ADB requires the consideration of

environmental issues in all aspects of the Bank’s operations, and the requirements for

environmental assessment are described in ADB’s Safeguard Policy Statement (SPS),

2009. The potential environmental impacts of the subproject have been assessed using

ADB Rapid Environmental Assessment Checklist for Sewerage. Then potential negative

impacts were identified in relation to pre-construction, construction and operation of the

improved infrastructure.

7. Categorization: Based on results of the assessment and ADB SPS, the subproject is

classified as environmental Category B, i.e., the subproject is judged to be unlikely to have

significant adverse environmental impacts. An initial environmental examination (IEE) is

required to determine whether significant environmental impacts warranting an

environmental impact assessment are likely.

8. This IEE aims to (i) provide critical facts, significant finding, and recommended

actions; (ii) present the national and local legal and institutional framework within which the

environmental assessment has been carried out; (iii) provide information on existing

geographic, ecological, social and temporal context including associated facilities within

the subproject’s area of influence; (iv) assess the subproject’s likely positive and negative

direct and indirect impacts to physical, biological, socioeconomic, and physical cultural

resources in the subproject’s area of influence; (v) identify mitigation measures and

any residual negative impacts that cannot be mitigated; (vi) describe the process

undertaken during project design to engage stakeholders and the planned information

disclosure measures and the process for carrying out consultation with affected people

and facilitating their participation during project implementation; (vii) describe the

subproject’s grievance redress mechanism for resolving complaints about environmental

performance; (viii) present the set of mitigation measures to be undertaken to avoid,

reduce, mitigate, or compensate for adverse environmental impacts; (ix) to describe the

monitoring measures and reporting procedures to ensure early detection of conditions that

necessitate particular mitigation measures; and (x) identify indicative costs and who is

responsible for carrying out the mitigation and monitoring measures.

9. Description of the Environment: The subproject components locations are in Anjad

town. The proposed STP and sewage pumping stations are located within the limit of

Municipal boundary of the town. The immediate surroundings were converted into urban

use for many years ago, and there is no natural habitat left at the subproject sites. There

Page 13: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

12

are no protected areas, forests and archaeological sites in the Anjad town. Nearest

protected area is Ralamandal Sanctuary, about 140 km from the Anjad town. Mandu,

located at about 85 km from Anjad, is an important historical and architectural town in MP,

and it is a world heritage site listed by GoI. There are several ASI monuments,

archaeological site like Rani Roopmati Mahal, Jahaz Mahal, Jama Masjid etc. All the

locations of the STP, IPS and MPS are government-owned vacant and barren lands with

no notable tree cover. No tree cutting will be required as the trees are on the periphery of

the site, which will not be removed for IPS, MPS and STP construction. Proposed IPS site

is located near Susad Mohalla in between ward No. 5 and 6, and on the bank of Susad

river, at least 50m away from habitation and surrounded by agricultural land, Susad River

and residential area. A temple, government middle school and community hall is located at

about 50 m from the proposed site of IPS, and site is on the back side of the built up area.

Proposed MPS site is located near Army hotel (It is a food restaurant) on the bank of

Bhongli nala along the main road when moves towards Chota Bardha village about 50m

away from habitation on the outskirts of town Anjad. Anjad town is in between the

Narmada River and proposed STP site. The site selected for STP is located on the

outskirts of Anjad town atleast 500m away from habitation. Site is surrounded by

agricultural lands; some brick kiln works is going on within 200-500 from STP site. Final

discharge point of treated sewage from STP is nearby natura drain at a distance 580m

from prposed STP site, which joins Bhongli Nala after travelling a distance of approx. 1.60

km and then final disposal into Narmada about 15 km from the site. There is water intake

for Anjad town on upstream side, about 11 km away from treated effluent discharge point

on Narmada river. There are no forests in or near project sites. Construction activities will

be confined to the identified sites. The soil in the project area generally falls under the

broad group of deep alluvial soils. The project area is surrounded by agricultural areas and

no industries are found. The ground water availability in these areas comes under Safe

Zone as per Central Ground Water Board report.

10. Potential Environmental Impacts. The subproject is unlikely to cause significant adverse

impacts because: (i) the components will involve straightforward construction and

operation, so impacts will be mainly localized; (ii) there are no significant sensitive

environmental features in the project sites and (iii) predicted impacts are site-specific and

likely to be associated with the construction process and are produced because the

process is invasive, involving excavation and earth movements. Sewerage system

performs a crucial function of safely collecting, transporting, treating and disposing

domestic wastewater, including, human excreta. Subproject is likely to have numerous

positive impacts on the environment and public health. Planning principles and design

considerations have been reviewed and incorporated into the site planning and design

process wherever possible; thus, environmental impacts as being due to the project design

or location were not significant. Locations and siting of the proposed infrastructures were

considered to further reduce impacts. These include (i) locating sewage pumping stations

and STP away from the inhabited areas, (ii) locating facilities on government-owned land

to avoid the need for land acquisition and relocation of people; and (iii) laying of sewer

pipes in RoW alongside main/access roads, to reduce acquisition of land and impacts on

livelihoods specifically in densely populated areas of the town.

11. Sewage pumping stations, which collect sewage to further pump to a higher elevation

Page 14: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

13

manhole, are likely to generate odour. Utmost care is taken to locate these away from the

houses, and also included various design and operaion measures to minimize the odour

generation. Site selected for IPS is located on the bank of Susad River near Susad

Mohalla. Although, a temple, government middle school and community hall is reported in

the proximity of Susad Mohalla but proposed site of IPS is away from these receptors. It is

about 50m away and as well as back side of the built up area. As mentioned ealier that

proposed site is located on bank of the river and agricultural fields are reported in and

around the site. As per the land records there is large piece of land in the proposed Khasra

but during site visit, it was found that a large built up area along with temple and school

has been developed but away from river side. It is pertinent to mention here that

requiredland for IPS is available which is reported vacant in state. Proposed MPS site is

located near Army hotel (a food restaurant) on the bank of Bhongli nala along the main

road when moves towards Chota Bardha village at least 50m away from habitation. There

is no notable development within 50m of MPS site boundary. It is proposed developed 20-

30 m buffer around the IPS/MPS within the proposed site boundary, so the buffer between

MPS/IPS and temple/school and residential area will be about 70-80 m. Providing proper

boundary for the site, especially high compound wall towards temple and school. Layout

plan of IPS & MPS shall be devised in such a way that it will be farthest from habitation,

temple & school with low odour and low noise, so there are no impacts envisaged. Another

impact is that of STP operation: from malfunction or decrease in treatment efficiency and

sludge handling and disposal. This will result in release of untreated or partially treated

wastewater that will pollute environment and cause public health issues. Accumulation of

silt in sewers in areas of low over time, overflows, blockages, power outages, harmful

working conditions for the workers cleaning sewers etc. may create nuisance, unhealthy

and hazardous conditions. Various measures are suggested to minimize these impacts.

12. The site selected for STP is located on the outskirts of Anjad town atleast 500m away from

habitation. Site is located on higher elevation/upstream side of Bhongli Nala. It is because

of non-availability of goverment land on the downstream side. Efforts have been made to

conceptualize scheme along slop, but high fertile agricultural fields are reported towards

slope side. These agricultural fields are private lands. No government land is reported

towards slope or Narmada river side. Site is surrounded by agricultural lands, and there

are no notable developments within 500 m of the site boundary. All the development is

away from 500-700 meters from its premises. Some brick kiln works is going on within 200-

500 from STP site by local people. It is proposed developed 20-30 m buffer around the

plant with in the STP boundary, so the buffer between STP components and habitation

area act as a barrier for noise & air pollution to residents from bad odor & insect nuisance

due to operation of STP. This will act as a visual screen around the STP and surrounding

area and will improve the aesthetic appearance of the surrounding environment and given

the proposed SBR technology with low odour and low noise, there are no impacts

envisaged and the treated effluent will be discharged into nearby natural drain already

available at a distance 580m from proposed STP site, which joins Bhongli Nala after

travelling a distance of approx. 1.60 km and then final disposal into Narmada about 13.4

km from the Bhongli Nala. There is water intake for Anjad town on upstream side near

Dattwada village on Narmada river. STP discharge point into Narmada is in the

downstream about 11 km away from intake, so there will be no impact on intake due to

STP discharge. As the River Narmada is perennial river and flow in the river is adequate to

Page 15: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

14

dilute the discharge. There are no water intakes / dams in the downstream river course

upto 5-10 km stretch.

13. During the construction phase, impacts mainly arise from the need to excavate large areas

which can result to increase in dust and noise levels, disturbance to residents and

businesses along the delivery routes, and traffic and the need to dispose moderate

quantities of waste soil during construction phase.

14. Environmental Management Plan (EMP). An EMP has been developed to provide

mitigation measures to reduce all negative impacts to acceptable levels. The EMP

includes design measures such as (i) design of treatment process to meet discharge

parameters more stringent than discharge stadnards of MoEFCC (ii) sludge management,

(iii) planning and design measures to control odour from SPS, (iv) green buffer zones

around SPS and STP, (v) alternative power suppy (back-up) arrangements for

uninturrupted working of SPS and STP. During construction, the EMP includes mitigation

measures such as (i) implementation of traffic management plan in coordination with local

traffic police to minimize traffic impacts; (ii) awareness campaigns and consultations to

inform residents and businesses of potential disturbances; (iii) provision of walkways and

planks over trenches to ensure access will not be impeded; (iv) appropriate scheduling of

works to avoid peak tourist season in important places; (v) use of noise-dampening

measures in areas with sensitive receptors such as hospitals, schools, places of worships

and other silence-zones; (vi) use of dust-suppression methods such as watering and/or

covering of stockpiles; and (vii) finding beneficial use of excavated materials to extent

possible to reduce the quantity that will be disposed off. As for the O and M phase,

facilities will need to be repaired from time to time, but environmental impacts will be much

less than those of the construction period as the work will be infrequent, affecting small

areas only. The EMP includes mitigation measures and monitoring plan to ensure

compliance to environmental standards during O and M phase.

15. The EMP will guide the environmentally-sound construction of the subproject and ensure

efficient lines of communication between MPUDC, PMU, PIU, consultants and contractors.

The EMP will (i) ensure that the activities are undertaken in a responsible non-detrimental

manner; (i) provide a pro-active, feasible and practical working tool to enable the

measurement and monitoring of environmental performance on site; (ii) guide and control

the implementation of findings and recommendations of the environmental assessment

conducted for the subproject; (iii) detail specific actions deemed necessary to assist in

mitigating the environmental impact of the subproject; and (iv) ensure that safety

recommendations are complied with. The EMP includes a monitoring program to measure

the environmental condition and effectiveness of implementation of the mitigation

measures. It will include observations on- and off-site, document checks, and interviews

with workers and beneficiaries.

16. The contractor will be required to submit to PMU, for review and approval, a site

environmental plan (SEP) including (i) proposed sites/locations for construction work

camps, storage areas, hauling roads, lay down areas, disposal areas for solid and

hazardous wastes; (ii) Specific mitigation measures following the approved EMP; (iii)

monitoring program as per SEP; and (iv) budget for SEP implementation. No works are

allowed to commence prior to approval of SEP.

Page 16: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

15

17. A copy of the EMP/approved SEP will be kept on site during the construction period at all

times. The EMP included in the bid and contract documents. Non-compliance with, or any

deviation from, the conditions set out in this document constitutes a failure in compliance.

18. Consultation, Disclosure and Grievance Redress Mechanism: Consultations have

been conducted with different types of stackeholders at various levels i.e. at town level

with CMO & elected representatives and people were consulted at several places in the

town including at STP and pumping stations (IPS & MPS) sites (Refer Appendix 13). The

stakeholders were involved in developing the IEE through discussions on-site and public

consultation at several places in the town, after which views expressed were incorporated

into the IEE and in the planning and development of the project. The IEE will be made

available at public locations and will be disclosed to a wider audience via the ADB,

MPUDC and PMU websites. The consultation process will be continued and expanded

during project implementation to ensure that stakeholders are fully engaged in the project

and have the opportunity to participate in its development and implementation. A grievance

redress mechanism is described within the IEE to ensure any public grievances are

addressed quickly.

19. Monitoring and Reporting: Mitigation will be assured by a program of environmental

monitoring to be conducted during construction and operation stages. The environmental

monitoring program will ensure that all measures are implemented, and will determine

whether the environment is protected as intended. It will include observations on- and off-

site, document checks, and interviews with workers and beneficiaries. Any requirements

for remedial action will be reported to the PMU. The PIU, PMDC and PMU will be

responsible for monitoring. The PMDC will submit quarterly and semi-annual monitoring

reports to PMU, and the PMU will review and send the semi-annual monitoring reports to

ADB. ADB will post the environmental monitoring reports on its website.

20. The citizens of the Anjad Nagar Parishad will be the main beneficiaries of the sewerage

scheme, as they will be provided with sewerage system to collect, covnvey, treat and

dispose the sewage safely. This will improve the over-all health condition of the town as

water borne diseases will be reduced, so people should spend less on healthcare and lose

fewer working days due to illness, so their economic status should also improve, as well as

their overall health. This should also improve the environment of these areas, should

deliver major improvements in individual and community health and well- being.

21. Conclusions and Recommendations: The subproject is therefore unlikely to cause

significant adverse impacts. The potential impacts that are associated with design,

construction and operation can be mitigated to standard levels without difficulty through

proper engineering design and the incorporation or application of recommended mitigation

measures and procedures. Based on the findings of the IEE, there are no significant

impacts and the classification of the project as Category “B” is confirmed. No further special study or detailed environmental impact assessment (EIA) needs to be undertaken

to comply with ADB SPS (2009) or GoI EIA Notification (2006). Project will require

following government permission/approvals: (i) consent for establishment and consent for

operation for STP from Madhya Pradesh Pollution Control Board. These

Page 17: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

16

permissions/approvals shall be obtained. This IEE will be updated during the detailed

design stage by the DBO contractor to reflect any changes, amendments and will be

reviewed and approved by PMU.

II. INTRODUCTION

A. Background 1. Government of Madhya Pradesh with loan funding from Asian Development Bank (ADB)

has proposed to implement Madhya Pradesh Urban Services Improvement Project (MPUSIP), herein after referred as „the Project‟. Madhya Pradesh Urban Development Company Limited (MPUDC) shall be the Implementing Agency and the State Urban Development and Environment Department (UDED) shall be the executing agency for the Project.A project management unit (PMU) created under MPUDC is implementing MPUSIP.

2. MPUSIP’s physical components include (a) improvements to water in 62 project towns, and (b) sewage and storm water collection and treatment services proposed in seven (7) identified towns namely Sanchi, Maihar, Saikheda, Sanawad, Anjad, Badwah and Dhamnod under tranche II. The project also includes an institutional strengthening component and a project management and administrative support component.:

3. At present there is no sewerage system for collection, conveyance, treatment and safe disposal of sewage in Anjad Town. The households are having septic tanks and overflow of septic tank and household waste water is being directly discharged into storm water drains without treatment. This leads to deterioration of environment and health hazards. It causes lot of unhealthy conditions to the people in general and hence it is essential to provide underground drainage scheme for the town.

4. The water supply improvement project is under process of sanction in Anjad town and

water supply rate per capita is 135 lpcd in the water supply project and therefore there is

immediate need for sewerage system for collection, conveyance and treatment of sewage.

5. Hence there is need of the project to improve service levels in sewerage system in Anjad

Nagar Parishad conforming to National Service Level Benchmarks.

6. The Government has appointed the consultant for preparation of underground drainage

scheme of the Town. Consultant has deployed team as part of the Program development.

The Consultant team conducted series of investigations and developed this conceptual

plan for improving the sewerage in Anjad town.

7. The subproject town of Anjad area is located in the district of Barwani in the south-western

part Madhya Pradesh state. Providing sewerage system in Anjad is one of the subprojects

proposed under MPUSIP. The objective of this subproject is to develop sewerage

management services to the residents in Anjad Nagar Parishad (ANP) conforming to

National Service Level Benchmarks in sewerage services. The subproject envisages

providing 100% coverage of population with sewage collection network and treatment

services. A detailed description of the components is provided in Section III. This

subproject package is proposed for implementation under a single Design-Build-Operate

(DBO) contract package.

Page 18: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

17

B. Purpose of this IEE Report

8. ADB requires the consideration of environmental issues in all aspects of the Bank’s

operations, and the requirements for environmental assessment are described in ADB‟s Safeguard Policy Statement (SPS), 2009. The potential environmental impacts of the

subproject have been assessed using ADB Rapid Environmental Assessment Checklist for

Sewage and Sanitation (Appendix 1). Then potential negative impacts were identified in

relation to pre-construction, construction and operation of the improved infrastructure, and

results of the assessment show that the subproject is unlikely to cause significant adverse

impacts. Thus, this initial environmental examination (IEE) has been prepared in

accordance with ADB SPS requirements for environment category B projects.

9. This IEE is based on the detailed engineering report prepared by the PMC team and will

be finalized during implementation stage by DBO contractor to reflect any changes and

latest subproject designs. The IEE was based mainly on field reconnaissance surveys and

secondary sources of information. No field monitoring (environmental) survey was

conducted however, the environmental monitoring program developed as part of the

environmental management plan (EMP) will require the contractors to establish the

baseline environmental conditions prior to commencement of civil works. The results will

be reported as part of the environmental monitoring report and will be the basis to ensure

no degradation will happen during subproject implementation. Stakeholder consultation

was an integral part of the IEE.

C. Report Structure

10. This Report contains thefollowing nine (9) sections:

(i) Executive summary; (ii) Introduction (iii) Description of the project (iv) Policy, legal and administrative framework (v) Descriptionof the environment; (vi) Anticipated environmental impacts and mitigation measures; (vii) Public consultation and information disclosure; (viii) Grievance redress mechanism; (ix) Environmental managementplan, and, (x) Conclusion and recommendation.

Page 19: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

18

III. DESCRIPTION OF THE PROJECT

A. Project Area

11. Subproject town Anjad is located in Barwani district in the south-western part of Madhya

Pradesh. Anjad is a small and class III town which was established as Nagar Panchayat

on 1908. The Municipal area of the town is approximately 15.54 Sq. Km. Presently city

holds the population of 26492 as per the 2011population census data and it has 15 wards.

Project area is situated at about 318 km south-west of state capital Bhopal and is

connected with highways, railways and airport. Following is the map showing ward

boundaries of all 15 wards.

Figure 1: Ward Map Anjad Town

Figure 2: Location of Anjad Town in MP

Page 20: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

19

12. The subproject components locations are in Anjad town. The proposed sewage treatment

plant (STP) and sewage pumping sations will be located within the municipal boundary of

the town. The immediate surroundings were converted into urban use for many years ago,

and there is no natural habitat left at the subproject sites. All the locations of the STP and

SPS are government-owned barren land with no notable tree cover.

B. Existing Water Supply, Sewerage and Storm Water DrainageSystem

13. Existing water Supply System: It shall be ensured that the existing water supply or under

execution, has the potential to meet the water demand of the projected design population

at the rate of 135 LPCD specified. ULB is committed to ensure desired water supply rate of

135 LPCD in all sewerage districts/all municipal wards of Anjad town. The town of Anjad

gets raw water supply from Narmada River which is about 5 km from the city. Town

receives water from both surface and ground water. Around 1.2 MLD per day water

receives from river Narmada. In ground source, for supplying drinking water in the town

there are 6 tube wells and 10 Hand pumps which are located in the various parts of the

town. From ground sources, 0.3MLD water is being supplied. There are 330 Stand posts in

the town. The distribution network is having length of 16.81 km approx. This covers about

53%HHs of the town. Water is distributed for 45 min. every alternate day in the town.

Distribution and transmission losses currently amount to 10% of supply. Direct Pumping is

being done at Dattwada in River Narmada. It is around 7 kms away from the town. There

are three Over-Head Tanks with a total installed storage capacity of 17 (Lac Liter) in the

town. There is one treatment plant is at Dattwada. It is around 7 kms away from the town.

Only primary treatment facility is available. Water Quality monitoring is done to check

turbidity and pH levels. Existing situation of water supply on map is shown below.

Page 21: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

20

Figure 3: Existing Water Supply Map Anjad Town

Figure 4: Water Intake and STP Discharge Location on Rivr Narmada For Anjad town Shown in Google Map

Intake Point

STP Discharge

Point into

Narmada

WTP Location

at Dattwada

Page 22: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

21

Table 1: Ward Wise Source & Water Supply

S.

No.

Ward

No.

Ward Name W.S. through 2011

Population

Actual Water

Supply (MLD)

LPCD

Hand

Pump

Tube

Well

Line

1 1 Narmada

Sagar ward

0.000 0.000 0.127 2786 0.113 41

2 2 DhanMandi

Ward

0.006 0.000 0.067 1466 0.065 44

3 3 Ambika Ward

0.000 0.043 0.069 1520 0.100 66

4 4 Sardar Patel

Ward

0.000 0.000 0.086 1877 0.076 41

5 5 Savarkar Ward

0.003 0.042 0.107 2335 0.135 58

6 6 Mukharji Ward

0.014 0.000 0.089 1947 0.092 47

7 7 Subhash Ward

0.000 0.000 0.058 1262 0.051 41

8 8 Jawahar Ward

0.000 0.050 0.080 1756 0.116 66

9 9 RanaPratap

Ward

0.000 0.000 0.063 1376 0.057 41

10 10 Azad Ward

0.000 0.000 0.055 1202 0.049 41

11 11 Ghandhi Ward

0.003 0.039 0.060 1316 0.090 69

12 12 Vivekanand

Ward

0.005 0.044 0.108 2366 0.140 59

13 13 Dr. Amabedkar

Ward

0.004 0.047 0.078 1713 0.115 67

14 14 Prajapati Ward

0.000 0.000 0.064 1400 0.058 41

15 15 Nagari Mata

Ward

0.000 0.000 0.090 1967 0.089 45

25 All Ward 0.035 0.265 1.200 26289 1.35 Avg.=51

Source: Analysis by the Consultant

14. Proposals for Augmentation of Water Supply System: Anjad municipal council has

prepared water supply augmentation scheme to augment existing water supply. The same

is executed and new water supply scheme has been commissioned at the end of

December 2017. After implementation of the scheme the rate of supply has been

enhanced from existing 51 LPCD to 135 LPCD. The details of the proposed components of

new water supply scheme are as follows: -

Table 2: Proposed Components in New Water Supply Scheme

SN Name of the components Unit/Capacity Remark

Page 23: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

22

1 Raw water pump and Intake well 2 no./ 42 HP /37 lps/60.0 m head

2 Raw water pumping main 200 mm Dia. K9 800 m length

3 Water Treatment Plant 4.00 MLD

4 Clear water pumps 2 no. /72 HP/351 lps/125 m head

5 Clear water pump house at WTP 2.8 MLD Intermediate phase

6 Clear water pumping/Gravity main

200 mm K9 6000 m Length, 200 mm K7 1748 m, 150 mm K7 3406 m in length

Storage Reservoirs 450 KL GSR and 400 KL OHT 600 KL Existing

7 Distribution net work 110 mm to 280 mm total 49707 m

15. Existing Sewerage and Drainage System: The town does not have underground

sewerage system. The existing condition of sewerage and storm water drainage system is

in very bad shape. There are two rivers passing from the town, one passing from centre of

the town namely Bhongli or Bhagwat river (Initially Bongli Nala was the Bhagwati river or

Bhongli river, later due to the encroachment and pollution it got converted into the Bhongli

Nala) and another major river which is passing from western side of the town namely

Susad river. As mentioned above Bhongli Nala & Susad River (it also got converted into

main drain) these are two major drain in the town. Bhongli Nala passes from centre of the

town and flows from ward no. 5, 6, 14 and 15, carries about 70% of city’s storm water and drainage out of the town. The road has been built along the both sides of the Nala by the

nagar parishad and the Nala has been almost pakka. The sewerage from the houses is

directly dumped into the Bhongli Nala through the pipes. The weekly market is operated

from the roads which are constructed along the Nala, the waste of the weekly market is

also dumped in the Nala and in many places the solid waste is collected along the nala by

the workers of nagar parishad. The other major drain is Susad River passes from western

side of town and flows from ward no. 5, 6 and 7, the drainage of slums are directly meet to

the Susad river. and finally meets Narmada river in northerns side after travelling a

distance of about 10 km from anjad town. Thre is no separate network for sewerage, both

sewerage and storm water passess through the same drains. As such whole sewage and

storm water of the area is flows through the road side drains and discharged to Bhongli

nallahs and Susad River and then ultimately to the river Narmada. At about 3.62 km

distance Susad and Bhongli river are confluence and after that they fall into the Narmada

River at a distance of 6 km.

16. There is no any waste water treatment system exists in the town. Anjad has an onsite

sewage disposal (OSD) disposal system. The waste water is usually being disposed of

through septic tanks and soak pits. There is no provision of waste water or sludge

treatment system for the town. Grey water/sullage is disposed off into the open field or

road side drains in front of the house. These drains then dispose the sullage into the

nearby nallahs at various locations in the town without any treatment. Also there is no

Page 24: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

23

separate sewerage and storm water network in the town. Drains are used to dispose off

effluents from septic tanks and pit latrines.

17. In some cases, direct raw sewage is also being let out in open drains. The overflow of

septic tanks together with the grey water is disposed of in open drains and subsequently

into open areas/nalla. Also being uncovered, they always get clogged due to mixing of

garbage and polythenes or plastic waste littering around. The untreated effluent over

flowing from soak pits and draining into the town’s drainage system pollute surface and ground water source considerably apart from emanating foul smell into the atmosphere.

Since most of the drains/nalla are open and easily accessible, especially in the slum area,

there is large scale indiscriminate dumping of organic wastes in the nallah. Finally, in the

form of nallas the sewage is discharges into Narmada River. There is no organized

sewerage system in existence and hence utilization of existing sewerage system does not

arise.

Table 3: Existing Status of Wastewater Management

Sewerage system Anjad lacks in proper underground sewerage system for conveyance of household wastewater.

Sewerage Districts At present municipal area is not categorized by sewerage district wise.

Sewerage Districts Area and number of drains in the districts

The existing open drainage system functions as open sewers and thus contributes to the pollution of the Narmada, where most of the effluent ultimately finds its way. There is one major nalla (Bhonglinalla) in the town which is taking about 90% sewage/sullage of the town and then flows towards North direction of the town and finally it discharges into Narmada River. Remaining 10% of sewage/sullage from the households is carried by Susad river which ultimately discharge into River Narmada after joining of bhonglinalla.

Sewerage Districts covered with sewers and STP

Nil

Sewerage Districts Not Covered With Sewer and STP

As per census 2011, total 52.77% HHs of total HHs are having latrine facility within the premises. From which waste water of 0.04% of the is discharged in to Open drains, wastewater of 42.07% HH are conveyed into septic tanks and discharging into open drains, Wastewater of 3.21% HH conveyed through Pit latrine and the rest 7.45% is by other system. Remaining 47.23% HHs which are not having latrine facility within the premises, they either use public latrine or defecate in open area.

As per City Sanitation Plan, there are 19 Community toilet, 6 Public Urinal and one public toilet exist in the town. 3 community toilets are not in working condition. The waste water of public/community toilets is conveyed into septic tanks and discharged into open drains.

Source: Analysis by the Consultant, census 2011 data and City Sanitation Plan

18. Toilets: At present sanitary system of whole city is based on either individual house hold

Page 25: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

24

having septic tank or twin pit latrine system. There are 3 Community toilet blocks and 2

Public toilets exits in the city. As per the door to door survey conducted in the city the detail

of household toilet in the area where septage management, non-conventional system i.e.

SBS and conventional sewer system has been proposed are as follows: -

Table 4: Present status of the toilets

Area Total

Property

Septic

Tank

Twin

Pit

No

system

SBS (Small Bore Sewer System) 690 160 125 405

Conventional (Conventional Sewer

System) 4545 480 1652 2413

Septage 518 124 86 308

Total 5753 764 1863 3126

19. ANP has identified 308 Houses in the septage management area where household does

not have septic tank. The construction of twin pit toilet is proposed under Swatch Bharat

Mission. All the houses within its limits which do not have individual toilets and has taken

up the responsibility of constructing toilets for such families at individual household level.

ANP envisaged a scheme under the State owned ‘Mukhya Mantri Shahri Swachhata Mission’ which later on was merged with the National Level Mission "Swachchh Bharat

Mission". ANP has already started constructing individual toilets and aims to have

Individual toilets at each HH level; by the end of the Year 2017.

20. At present as there is no proper Sewerage system, the sewage is directly disposed in to

the nearby drain without any treatment. Anjad does not have an under ground sewerage

system. Also there is no separate sewerage and storm water network in the city. The

existing condition of sewerage system is in very bad shape. The area completely lacks in

underground sewrage system for conveyance of household wastewater. Also there is no

treatment facility in the form of STP in the town. The prevelant sewerage systems

generally practiced by the people in town is individual septic tanks privately maintained by

the respective households. Filty nallahs/drains run across almost whole length and breadth

of the town, thus contributing to unhygienic living conditions. It causes lot of unhealthy

conditions to the people in general and hence it is essential to provide Sewerage scheme

for the town. Also, due to increase in water needs for the growing population, and the

expected increase in supply, will lead to generation of more wastewater, which needs to be

safely managed. The Government has therefore appointed the consultant for preparation

of sewerage scheme of the Town. The objective of the sewerage system is to ensure that

sewage discharged from communities is properly collected, transported and treated to the

required degree and disposed off / reused without causing any health or environmental

problems.

C. Proposed Project

21. Coverage of Sewerage System: The character of Anjad town is a mix of urban and rural

areas. As such it is proposed to provide sewerage system in the core area of the town.

Page 26: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

25

The Project area covered under the scheme is 7.83 sq.km. It is proposed to lay down

scheme consisting of three separate zones. As per topography, the zones are classified by

considering the location of the proposed pumping stations and pipe network layout. The

proposed scheme shall be determined following the path of the developed or to be

developed roads in the town as per the town-planning scheme. Details of the classified

area covered by each zone and the projected dry weather flow (DWF) to be served by the

respective pumping stations are given in Table 6 and 7.

22. Anjad town is proposed to cover by centralised sewerage system considering the

topography of the town by way of dividing into three sewerage zones. Sewerage zone I

covers whole western part of the town. The slop of whole zone is from West to East i.e.

towards Susad River. Sewerage zone 2 covers main town area east side of the Susad

River. The slope of the whole zone is towards Bhonglinalla which is passing from center of

the town. Around 90% population of the total population is covered by this district. Only a

few pockets are felt necessary to have techno-economic proposition for covering all

households of the town under organized sewerage system. One sewage treatment plant is

proposed to cover 95% of the population and hardly 5% proposed to be covered by septic

tank with arrangement of safe effluent disposal.

23. As Anjad is proposed with a centralized sewerage system. Only Gravity network has been

considered. The Sewerage zone boundaries are defined based on the topography

(Considering depth of cut). Sewer collection network is planned for the project area

keeping in consideration of minimise the crossings of major barriers like National highway,

Railways, Rivers, Canals. Main Sewers are laid along the natural drainage line to minimize

the depth of excavation. The design of sewer network is as per the design criteria of

CPHEEO Manual. The town is divided into 03 zones. Zone I & II is gravitated to single

sewage treatment plant based on SBR Technology. The treated effluent from STP is

proposed to be disposed off to a nearby available drain which joins Bhongli Nala by a

gravity pipe line. Zone III will be covered by septic tank with arrangement of safe effluent

disposal.

24. In centralized Sewerage System approach, one IPS near Susad River in zone I and one

MPS near Bhongli Nala in Zone II is required to pump the sewage of ward no. 5 and 6,

from IPS Zone I to MPS in zone II and then from MPS to STP at Zone II through pumping

main, hence the sewage of whole town can be treated by two SPS and one Sewage

treatment plant.

25. All the wards mentioned in the city Development plan has been taken in the proposal. The

proposed sewage collection system will include house service connections with aim to

collect sewage at location of its generation. This will also avoid intermixing of sewage and

storm water run off

26. Proposed Sewerage System: The conventional sewage system of laterals, branch and

main sewers are proposed. The network is planned in such a way that sewage will be

collected from households from all streets and roads within ULB area by gravity and will be

conveyed to STP location. The manholes are proposed at 30m interval, at change of

direction and diameters of sewers for inspection and cleaning of sewers. The proposed

Page 27: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

26

sewer manholes are brick masonry manholes. The street manholes will be circular in

shape with concentric cone depending on the depth and diameter of sewers. The minimum

size of sewer considered as 100 mm and minimum soil cover of 1m. Till the house sewers

connections are made by individuals, the existing septic tanks will be in operation.

27. The sewage flow is considered 80% of rate of water supply that is 135 lpcd. The sewage

flows are calculated for present, intermediate and ultimate years. The efforts are made to

maintain minimum self-cleaning velocity in sewers. In initial stretches of sewers, the

minimum self-cleaning velocities are not achieved so flushing will be required. The sewer

cleaning equipment are proposed in the project for cleaning of sewers. House connection

chambers are proposed for connection of household sewer pipe to this chamber. The

hydraulic designing of sewers is done using SewerCAD software. The proposed sewage

treatement facility is for 3.66 MLD of sewage flow.

28. Community Septic Tanks & Soak Pits: For rural villages and slum areas in Anjad Town,

majority of the population residing in the slums faces severe problem of improper drainage.

Individual houses / community do not have septic tanks and laying of conventional sewers

are not feasible due to scattered houses, away from the main city area, per capita waste

water generation is very low due to less populated area and water consumption rate is low.

It is proposed to have community septic tanks for these villages and to improve the service

levels for sewage treatment and preventing untreated sewage flowing to drain / open area.

The community wise toilets will be constructed by MP Govt. under Swachh Bharat

Abhiyan. The local committee will carry out O&M of community septic tanks and

community toilets.

29. Septage Management: Due to topography of the area and uneven slope of the wards and

for ease of maintenance, they are proposed to be covered by septage management. There

are approximately 192 households in Anjad Municipal council area which are proposed

under septage management under Zone 3 and some houses which do not come under the

sewer network are also proposed under septage management by constructing septic tanks

and soak pits for household in zone 3. Collection of sludge from the septic tank,

disposal to treatment. Construction of the septic tank in the house does not have

septic tankhas been included as BOQ item in project cost, thereby making people

dependent on septic tanks (one of the most common forms of urban sanitation facilities

with the Swachh Bharat Mission’s aim to make India an open defecation free country by 2019. This will certainly help in reducing open defecation in he proposed zone 3 area but

without proper collection, transportation and treatment processes, faecal waste from these

additional toilets will only amplify the current problem. This is clearly an area that needs

urgent attention. For this septage management has been proposed. Septage management

is a process and requires attention at every stage of the sanitation chain for collection,

transportation and treatment of septage (See Figure 5: Steps for planning septage

management). Safe disposal or end use in a scientific manner is the main goal of septage

management. Though cleaning interval of septic tank varies from 2 to 5 years or even

more depending upon the capacity of the tank,

30. The following are the key components of a Septage Management Plan

Page 28: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

27

31. Collection and Transportation: Proper collection and transportation of septage is one of the most important components of septage management. As per the CPHEEO Manual on Sewerage and Sewage Treatment, 2013 “yearly desludging of septic tanks is desirable, but if it is not feasible or economical, then septic tanks should be cleaned at least once in two - three years, provided the tank is not overloaded due to use by more than the number of persons for which it is designed.”This septic tank will be required to clean in every two years.Assuming on average one machine can clean three tanks per day; hence total 1 vehicle / machine will be needed. No machine is available with Anjad Municipal council. It is proposed that one machine will be tractor mounted tanker fitted with diesel pump and one jetting cum suction machine having capacity 8.0 KL with 140 HP motor and will fulfill the demand of the septage management.

32. Under the Prohibition of Employment as Manual Scavengers and their Rehabilitation Act,

2013 desludging / emptying of septic tanks is to be undertaken by mechanical devices like

suction emptier trucks / vacuum tankers. These desludging trucks collect septage at the

household level and transport it to treatment or disposal sites. ULBs need to assess the

following aspects of septic tank emptying (UDD, 2016);

• The number of septic tanks required to be emptied annually as per CPHEEO norm versus the number that are emptied in a year

• The number of vaccum emptying trucks/ capacity of trucks that are required if number of septic tank emptied as per CPHEEO norm versus the number of trucks that are available/working with capacities of emptier trucks

• Cost assessment per emptying visit • Method of register maintenance for septic tank emptying services database

etc.

33. It will be ensured that the septage transportation vehicle operators (whether from the ULB or private sector) are well trained and equipped with protective safety gears (such as gloves, boots, hat, face mask, Davy’s lamp), uniforms, tools and proper vacuum trucks, for safe handling of septage (UDD, 2016). Also, all septage transporters need to maintain a collection and transport receipt system that needs to be duly filled by the private / ULB service provider and submitted to ULB office (UDD, 2016).

34. Treatment & Disoposal: Septage collected from various points in the zone 4 will be disposed of at STP site in compliance with the Environment (Protection) Act, 1986 and the Water (Prevention and Control of Pollution) Act, 1974.Once collected, the septage will be treated as per the CPCB and MPPCB norms before disposal. Septage has constituents similar to municipal wastewater, which make the co-treatment of septage along with sewage feasible.

35. Reuse: Reusing refers to the act of returning the products to the environment as either useful resources or reduced-risk materials (UDD, 2016). The treated septage can be used as a soil enricher or as filling material at construction sites (UDD, 2016). Properly treated sludge can be reused in the following ways (CEPT, 2015):

• Soil Conditioner- It can be applied on parched land as a soil conditioner, or as a fertilizer in agriculture. Crops which could be safely grown are corn, fodder, cotton, trees including fruit trees, eucalyptus and poplar.

• Aquaculture- Settled septage effluent can be applied to freshwater where it is possible to achieve dilution to ensure dissolved oxygen is above 4 mg /l. Fish species of tilapia and carp are preferred since they tolerate low dissolved oxygen.

Page 29: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

28

Figure 5: Steps for Planning Septage Management in Zone-3, Anjad Town

Table 5: Details of Sewage Zones

Sewerage Zone

Ward Covered Existing Population covered

Contributing Area (Ha)

Area Covered

Zone 1 Ward No. 5 and 6 (Both Partially)

3328 238.86 Guybheda area, Krishi Upaj Mandi

Zone 2 Ward No. 1, 2 (Part), 3, 4, 5 and 6 (Both Partially) 3 to 15 whole wards)

22081 470.30 Nagar Parishad, Futla talab, Bus stand area, MG road Market, Sabjimandi, Hospital Chowk, Mukharjimarg, Dhanmandi chowk

Zone 3 Ward No. 2 962 74 Anjan Datwada Road

Table 6: Population Projection For each Zones

S. No.

Sewerage Zone

Ward covered Initial Design Population

2018

Intermediate Design

Population 2033

Ultimate Design

Population 2048

1 Zone I Part 5 and 6 3642 4439 5409

2 Zone II 1, 2 (Part), 3, 4, (5 & 6 Part), 7 to 15 24160 29452 35888

Page 30: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

29

3 Zone III 2 Part 962 1173 1430

3 Total 28764 35065 42727

Source: Analysis by the Consultant

Table 7: Sewage Generation

S. No.

Sewerage Zone

Waste water flow (in MLD) i/c infiltration Treatment process 2018 2033 2048

1 Zone I 0.39 0.48 0.58 SPS

2 Zone II 2.61 3.18 3.88 MPS & (STP/SBR)

3 Zone III 0.10 0.13 0.15 Septage

Source: Analysis by the Consultant

Table 8: Maximum Depth (m) of Sewer from Ground Level Zone Wise

Maximum Depth (m) of Sewer from ground Level Zone Wise

Zone 1 – 4.66m

Zone 2 – 6.99 m

36. The town is divided into 03 zones and zone 3, are considered to be provided with onsite

facilities by constructing septic tanks. Both zone 1 & zone 2, the zone is gravitated to single sewage treatment plant based on SBR Technology (3.66 MLD capacity). On the basis of Life Cycle Costing (LCC) Technique, the most feasible technological option for STP for town is ‘Sequencing Batch Reactors (SBR). This option is cost-effective, land required is less and result is very good. STP is to be designed for ultimate design year capacity, but the phase wise operation will be followed (i.e. first phase will be comprising of the construction of STP for first 15 years’ capacity) year 2033. The proposed SBR technology will achieve effluent discharge standards of Central Pollution Control Board (CPCB).

Table 9: Proposed Discharge Standards recommended for Disposal from STP

S. No

Parameter Concentration (SBR)

1. pH 6.5-9.0

2. Biochemical Oxygen Demand (BOD), mg/l

<10

3. Chemical Oxygen Demand (COD), mg/l

<20

4. Total Suspended Solids (TSS), mg/l

<10

Sulphates mg/l 2

7. Fecal Coliform, MPN <100

37. Table 10 shows the nature and size of the various components of the subproject. The

three main elements are: (i) provision of a network to collect sewage from different parts of the town; (ii) construction of a trunk sewer to transport waste to the STP; (ii) STP to treat sewage to Indian standards. (iii) Final disposal will be nearby existing natural drain which

Page 31: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

30

joins Bhongli Nallah and then into Narmada river. The descriptions shown in Table 10 are based on the present proposals, which are expected to be substantially correct, although certain details may change as development of the subproject progresses. Location of subproject components and conceptual layout plans are shown in Figure 6 to Figure 25.

Page 32: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

31

Figure 6: Location Map of Subproject Town in Barwani District, Madhya Pradesh

Page 33: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

32

Table 10: Proposed Sewerage Subproject Components in Anjad Town

S. No.

Infrastructure

Function Description Location

1. Sewer network

Collect wastewater from houses and convey by gravity to nearest sewage pumping station for further conveyance to STP for treatment and disposal

23,055 m, diameter 100 - 3400 mm

Diameter (mm)

Length

(m)

Material

% (Total

) 100 2980 DWC 12.93 135 17754 DWC 77.01 170 1155 DWC 5.01 250 987 DWC 4.28 400 179 DWC 0.78

Total 23055 100

Sewers will be laid underground along the all the roads and and streets in Anjad town area comprising two sewerage zones. Sewers will be laid in the earthen shoulder along the roads, and where there is no place, sewers will be located within the carriage way.

2. Manholes For maintainance and cleaning of sewers

774 Nos.

Material Nos. Diameter (mm)

Brick 272 900 Brick 259 1200 Brick 253 1500 Total 784

• Average spacing - 30 m • Brick masonry manholes; drop

arrangement for sewer juctions of >0.6 m level difference; circular in shape with concentric cone depending on depth and sewer diameter

The manholes are proposed at 30m interval, at change of direction and diameters of sewers for inspection and cleaning of sewers.

3. Sewage Pumping Main

Transfer sewage from pumping stations to STP

2,340 m – 100-300 mm diameter DI pipes

• 340 m length 100 mm diameter pumping main from IPS to MPS

• 2000 m length 300 mm diameter pumping main from MPS to inlet chamber of STP.

From Zone 1 to Zone 2 (Susad River to Bhongli Nala) along the road within the ROW In Zone 2 (from MPS to STP along the road within ROW

4. Sewage pumping stations (SPS)

Collect sewage by pump to

Intermediate pumping station (IPS) - Capacity 0.58 MLD - Components - wet well of diameter 5m

IPS is located in Zone-1 near Susad River at

Page 34: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

33

higher level for further transfer and treatment

and depth 5.5 m and pumping station Main pumping station (MPS) - Capacity (4.46 MLD ) - Components: (wet well of diameter 5m and depth 4.9 m and pumping station)

relatively low-lying area for collecting sewage from collection area; total land area required is 0.022 Ha & available land is (0.360 Hectare (Khasra No. 71 owned by GoMP. Proposed IPS site is located near Susad Mohalla Nearby ward No. 5 & 6. On the bank of Susad river at least 50m away from habitation surrounded by agricultural land, susad river & residential area. Although a temple, community hall named as Mangli Bhawan and government middle school in the proximity of IPS site approximately 50m away from the proposed site as well as on the back side has been reported. (Refer Fig-38) MPS site near Bhongli Nala; total land area required is 0.03 Ha & available land is (0.20 Hectare at (Khasra No. 370) owned by

Page 35: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

34

GoMP. Proposed MPS site is located near Army hotel (It is a food restaurant) (at a distance of about 50m away from site) on the bank of Bhongli nala along the main road when moves towards Chota Bardha village at least 50m away from nearby habitation. Site is surrounded by, Agriculrural land and residential area. (Refer Fig-37)

5. Sewage Treatment Plant (STP)

For treatment of raw sewage for final discharge

3.66 MLD capacity Treatment technology: SBR STP Components: Following are indicative, and actual design will be firmed up by DBO Contractor - Raw Sewage Pumping Station - Pre-treatment works (inlet chamber, fine Screen channels, de-gritting Tanks, flow measuring channel and flow distribution box) List main treatment components (Anoxic Basin/Selector zone, SBR Basin, Chlorin Contact Tank, Gravity Sludge Thickener, Sludge Dewatering-Centrifuge, Sludge Drying Beds and Fitlrate pump house etc.).

STP Located at upstream of the Bhogli Nala i.e. south of the Anjad Town approximately 500m away from habitations Total land area required is 0.5 Ha & available land is 13.86 Hec. (plot no. 526, Village-anjad Halka- Anjad, RI-Anjad and Tehsil- Anjad) owned by GoMP. (STP Distance from nearest houses/property is more than 500m. Some brick kiln works is going on within 200-500

Page 36: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

35

from STP site by local people.

6. Outfall sewer Dispose treated wastewater from STP to final disposal location

580 m length 400 mm dia RCC NP3 pipe

Pipeline will be laid along existing road from STP outlet to Nearby available drain which joins Bhongli drain; pipeline will be laid along existing road within ROW. STP discharge point is nearby available natural drain at a distance 580m from prposed STP site, which joins Bhongli Nala after travelling a distance of approx. 1.60 km and then final disposal into Narmada is about 13.4 km from the Bhongli Nala and 15 km away from the STP site.

7. House sewer connections

Collect sewage from individual houses and convey into network

5,560 Nos.

Sewage delivery pipe will be connected to sewer lines at each house with a chamber

8 Mobile tanker To collect septage from septic tanks and convey

1 no,s - Tractor mounted tanker fitted with diesel pump and one jetting cum suction machine of capacity 8.0 KL with 140 HP motor and pump

Mobile tanker

Page 37: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

36

to STP 38. Details of Manholes: Manholes are proposed at every 30m interval in the straight line, at

intersections and turns on the roads, at changes in grade and size of sewers. The drop arrangement has been proposed where one sewer pipe meets another sewer pipe at different level (where level difference is more than 0.6m). The proposed sewer manholes are brick masonry. The street manholes will be circular in shape with concentric cone depending on the depth and diameter of sewers.

Table 11: Details of Manhole, Numbers, Sizes Types & Materials

Material Nos. Diameter (mm)

Brick 272 900

Brick 254 1200

Brick 248 1500

Total 774

39. Road Width: Width of road varies section to section wise. For more details, Refer Table 12 as given below.

Figure 7: Roads & Transpotation Map of Anjad Town

Page 38: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

37

Table 12: Width of Road with respect to Manhole No. along with Dia and Depth of

Sewer and Trench Width for Sewer Main Trunk Line

Zone-1

Manhole to Manhole

Width of Road in Meter

Dia of Sewer (mm)

Avg. Depth of Sewer (m)

Avg. Trench

Width (m)

Zone-1 829-830 6.86 135 2.55 1.35

Zone-1 830-831 6.6 135 2.55 1.35

Zone-1 831-832 6.77 135 1.05 1.35

Zone-1 832-833 7.18 135 1.10 1.35

Zone-1 833-834 7.19 135 1.16 1.35

Zone-1 834-835 7.16 135 1.28 1.35

Zone-1 835-836 7.05 135 1.37 1.35

Zone-1 836-837 7.06 135 1.42 1.35

Zone-1 837-838 7.08 135 1.45 1.35

Zone-1 838-839 7.06 135 1.38 1.35

Zone-1 839-840 6.99 135 1.91 1.35

Zone-1 840-841 6.9 135 2.60 1.40

Zone-1 841-842 6.9 135 2.84 1.40

Zone-1 842-843 6.94 135 3.05 1.40

Zone-1 843-844 7.05 135 3.02 1.40

Zone-1 844-845 6.96 135 3.01 1.40

Zone-1 845-846 6.9 135 2.96 1.40

Zone-1 846-847 6.96 135 2.89 1.40

Zone-1 847-848 6.98 135 2.98 1.40

Zone-1 848-849 6.99 135 3.10 1.70

Zone-1 849-850 7.12 135 3.45 1.70

Zone-1 850-851 7.12 135 3.83 1.70

Zone-1 851-852 7.06 135 4.01 1.70

Zone-1 852-853 7.09 135 3.74 1.70

Zone-1 853-854 7.05 135 3.52 1.70

Page 39: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

38

Zone-1 854-855 6.82 135 3.39 1.70

Zone-1 855-856 6.8 135 3.27 1.70

Zone-1

Manhole to Manhole

Width of Road in Meter

Dia of Sewer (mm)

Avg. Depth of Sewer (m)

Avg. Trench

Width (m)

Zone-1 856-857 7.04 135 3.36 1.70

Zone-1 857-858 7.01 135 3.29 1.70

Zone-1 858-859 7.02 135 3.23 1.70

Zone-1 859-860 7.03 135 3.15 1.70

Zone-1 860-861 6.93 135 3.17 1.70

Zone-1 861-862 6.8 135 3.25 1.70

Zone-1 862-863 6.59 135 3.18 1.70

Zone-1 863-864 6.58 135 3.07 1.70

Zone-1 864-1068 6.91 135 2.95 1.35

Zone-1 1068-865 6.54 135 2.86 1.35

Zone-1 865-866 6.45 135 2.70 1.35

Zone-1 866-867 6.72 135 2.65 1.40

Zone-1 867-869 6.57 135 2.49 1.40

Zone-1 869-870 6.41 135 3.01 1.70

Zone-1 870-871 6.25 135 4.10 1.70

Zone-1 871-872 6.48 135 4.80 1.70

Zone-1 872-926 15.29 135 3.11 1.70

Zone-1 826-927 3.03 135 1.34 1.35

Zone-1 927-1057 3.48 135 1.33 1.35

Zone-1 1060-1061 2.07 135 1.23 1.35

Zone-1 1061-1062 2.29 135 1.05 1.35

Zone-1 1062-926 3.06 135 1.71 1.35

Zone-1 883-884 2.03 135 1.71 1.35

Zone-1 884-885 2.39 135 1.84 1.35

Zone-1 885-886 1.97 135 2.67 1.35

Zone-1 886-887 2.28 135 2.86 1.40

Zone-1 887-888 2.08 135 3.05 1.40

Page 40: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

39

40. Sewer Construction works: Civil works in the project include linear excavation for laying sewer pipes along the roads, placing sewer pipes in the trench and refilling with the excavated soil. Subsequent to completion of works, road reinstatement will be undertaken by the contractor as part of the civil works. The roads in the core city area are very narrow and congested with pedestrians and vehicles, while the roads in outer areas are wide. Details of propsed sewer construction are given below. Minimum depth will be 1.0 m and maximum will be 6.99 m. Trench width will range from 1.10 m to 1.50 m. 35% of sewers will be with laid within depth of 1.5 m below ground, and only about 13% of sewers will be laid more than 3.5 m deep. Maximum depth of sewer to be laid is 7.0m. Trenches for sewer-work will be dug by backhoe or manually in narrow, and swers will be brought to site on trucks, off loaded and placed into each trench manually, after which soil will be replaced to cover the trench. Manholes will be either constructed in-situ or precast manholes will be fixed depending on site conditions.

Table 13: Details of Depth Wise Length of sewer

Length of Sewer (m) Depth

8069 1 - 1.5 m

5764 1.5 – 2 m

3458 2 – 2. 5

2766 2.5 - 3.5 m

1614 3.5 – 4.5 m

923 4.5 – 5.5 m

691 5.5- 7.00 m

23055 Total 41. Trench Excavation Width: With reference to the width of trench for pipe laying in Anjad,

depending on the soil condition at site and depth of the sewer, method of pipe laying will be decided and accordingly trench width also (Figure No. 8).

Table 14: Details of Diameter Wise Depth & Trench Excavation Width of Sewer

Pipe

Diameter

(mm)

Length of

Sewer (m)

Min. Depth

(m)

Max. Depth

(m)

Min. Trench

Width (m)

Max. Trench

Width (m)

Zone 1

135 68024 1.0 4.76 1.0 3.0

Zone 2

100 2976.9 1.0 5.41 1.0 3.346

135 10942.8 1.0 6.145 1.0 3.82

170 1154.4 1.0 6.74 1.0 4.2

250 986.2 2.29 6.99 1.7 4.45

Page 41: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

40

400 178.6 3.35 5.06 2.5 3.5

Figure 8: Type & Width of Trench

42. Other construction works. Other civil works in the subproject include construction of sewage pumping stations, and STP (pre-treatment works like inlet chamber, fine Screen Channels De Gritting Tanks Flow Measuring Channel and Flow distribution box, main treatment units, treated effluent disposal works), at the identified sites. These works will be confined to sites, and construction will include general activities like excavation for foundation, construction of foundations, columns, walls and roof in cement concrete and masonry, and fixing of mechanical and electrical fixtures, etc. Although the site is fairly small the construction will be straightforward, involving mainly simple excavation. The ground will be dug by backhoe diggers and bulldozers, and soil will be transferred into trucks for offsite disposal. Most of the construction works will be of concrete mortar, which will be prepared mechanically at site in concrete mixtures. Foundations for the small pump houses will be dug by backhoe or manually, and concrete and aggregate will be tipped in to create the foundations and floor. The brick sides will then be built manually by masons and pumps will be brought in on trucks and placed inside the pump house by crane. The roof material will then be attached by hand. Once the work is over, the temporary structure will be removed.

43. Project Benefits: The subproject aims to achieve sustainable wastewater management in both the towns and where the sewage generated is collected at the household level,

Page 42: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

41

transported, treated and safely disposed and at the same time improving the storm water drainage infrastructure to minimise or avoid flooding and water logging both in terms of services to customers, cost recovery, Provisions is made in proposed system for construction of new septic tanks in both towns to meet 100% sewer connection. Besides achieving progressively increasing cost recovery by expanding the coverage and increasing operating efficiency, the subproject will improve the overall environmental quality of the town. It will reduce the reduced time and costs of households and will lead to better public health particularly reduction in waterborne and infectious diseases.

44. The benefits of the project after implementation are:

• Prevention of ground water and soil pollution due to infiltration of untreated liquid waste

• Prevention of discharge of untreated sewage into lakes / river • Improvement in water quality of lakes • Improvement in environmental sanitation health and reduction in associated health

hazards • Improvement in quality of life, human dignity and increased productivity • Prevention of storm drains carrying sanitary sullage or dry weather flow • Treated sewage shall be available for irrigating agricultural fields leading to more

production of agricultural products

D. ImplementationSchedule 45. After the approval of the detailed project report, bid will be prepared and tenders are likely to

be invited by April 2018, and the contract will be awarded by June 2018. Construction is likely to start in July 2018, and will take about 28 months (including monsoon period).

Page 43: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

42

Figure 9: Proposed Zone Map for Anjad Town & Outfall of STP into drain

Page 44: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

43

Figure 10: Proposed Sewer Network Map of Zone-1 for Anjad Town

Page 45: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

44

Page 46: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

45

Figure 11: Proposed Sewer Network Map of Zone-2 & Proposed Alignment of Pumping Main for Anjad Town

Page 47: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

46

Figure 12: Details of Proposed IPS for Anjad Town

Page 48: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

47

Figure 13: Details of Proposed MPS in Anjad town

Page 49: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

48

Figure 14: Layout Plan of STP for Anjad Town (Based on SBR Technology)

Page 50: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

49

Figure 15:- Process Flow Diagram of STP at Anjad (SBR Technology)

Proposed Treated

Sewage Storage Tank

for Irrigation Purpose

for Sourrounding

Agricutural Fields

Page 51: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

50

Figure 16: GA Drawing of 3.66 MLD STP- Anjad (SBR Technology)

Page 52: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

51

Figure 17: Sludge Sump of 3.66 MLD- Anjad Town

Figure 18: - Gravity Sludge Thickener of 3.66 MLD in Anjad

Page 53: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

52

Figure 19: Thickened Sludge Sump of 3.66 MLD in Anjad town

Page 54: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

53

Figure 20:- Details of Septic Tanks & Soak Pits for Zone-3

Page 55: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

54

Figure 21:- Septic Tanks for Zone-3

Page 56: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

55

Figure 22: Google Map for the Location of IPS, MPS, STP & Treated Sewage Disposal Point in Anjad Town

Natural Drain for Final Disposal of Treated

Sewage

Page 57: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

56

Figure 23: Tentative Green Buffer Area around Proposed IPS At Anjad

Page 58: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

57

Figure 24: Tentative Green Buffer Area Around Proposed MPS

Page 59: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

58

Figure 25:Tentative Green Buffer Area Around Proposed STP

Page 60: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

59

IV. POLICY, LEGAL AND ADMINISTRATIVE FRAMEWORK

A. ADB Policy

46. ADB requires the consideration of environmental issues in all aspects of

ADB’soperations, and the requirements for environmental assessment are described in ADB SPS,2009. This states that ADB requires environmental assessment of all ADB investments.

47. Screening and Categorization: The nature of the environmental assessment required for a project depends on the significance of its environmental impacts, which are related to the type and location of the project; the sensitivity, scale, nature, and magnitude of its potential impacts; and the availability of cost-effective mitigation measures. Projects are screened for their expected environmental impacts, and are assigned to one of the following four categories:

(i) Category A: Projects could have significant adverse environmental impacts.

An EIA is required to address significant impacts. (ii) Category B: Projects could have some adverse environmental impacts, but

of lesser degree or significance than those in category A. An IEE is required to determine whether significant environmental impacts warranting an EIA are likely. If an EIA is not needed, the IEE is regarded as the final environmental assessment report.

(iii) CategoryC: Projects are unlikely to have adverse environmental impacts. No EIA or IEE is required, although environmental implications are reviewed.

48. Environmental Management Plan: An EMP, which addresses the potential impacts and

risks identified by the environmental assessment, shall be prepared. The level of detail and complexity of the EMP and the priority of the identified measures and actions will be commensurate with the project’s impact and risks.

49. Public Disclosure: ADB will post the safeguard documents on its website as well as

disclose relevant information in accessible manner in local communities:

(i) For environmental category A projects, draft EIA report at least 120 days before Board consideration;

(ii) Final or updated EIA and / or IEE upon receipt; and (iii) Environmental monitoring reports submitted by the implementing agency during

project implementation upon receipt.

B. National Environmental Laws

50. Environmental Assessment: The GoI EIA Notification of 2006 (replacing the EIA

Notification of 1994), sets out the requirement for Environmental Assessment in India. This states that Environmental Clearance (EC) is required for specified activities/projects, and this must be obtained before any construction work or land preparation (except land acquisition) may commence. Projects are categorized as A or B depending on the scale of the project and the nature of its impacts.

51. Categories A projects require EC from the central Ministry of Environment and Forests

(MoEF). The proponent is required to provide preliminary details of the project in the prescribed manner with all requisite details, after which an Expert Appraisal Committee(EAC) of the MoEF prepares comprehensive Terms of Reference (ToR) for the EIA study. On completion of the study and review of the report by the EAC, MoEF considers the recommendation of the EAC and provides the EC if appropriate.

Page 61: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

60

52. Category B projects require environmental clearance from the State Environment Impact Assessment Authority (SEIAA). The State level EAC categorizes the project as either B1 (requiring EIA study) or B2 (no EIA study), and prepares ToR for B1 projects within 60 days. On completion of the study and review of the report by the EAC, the SEIAA issues the EC based on the EAC recommendation. The Notification also provides that any project or activity classified as category B will be treated as category A if it is located in whole or in part within 10 km from the boundary of protected areas, notified areas or inter-state or international boundaries.

53. None of the components of this sewage improvement subproject in Anjad falls under the

ambit of the EIA Notification 2006, and, therefore EC is thus not required for the subproject.

54. Applicable Environmental Regulations: Besides EIA Notification 2006, there are

various other acts, rules, policies and regulations currently in force in India that deal with environmental issues that could apply to infrastructure development. The specific regulatory compliance requirements of the subproject are shown in Table 15.

Table 15: Applicable Environmental Regulations

Law Descriptio Requirement

The EIA notification, 2006 (and its subsequent amendments in 2009) provides for categorization of projects into category A and B, based on extent of impact

This states that Environmental Clearance (EC) is required for specified activities/projects, and this must be obtained before any construction work or land preparation (except land acquisition) may commence. Projects are categorized as A or B depending on the scale of the project and the nature of its impacts. Categories A projects require Environmental Clearance from the National Ministry of Environment and Forests (MoEF). Category B projects require environmental clearance from the State Environment Impact Assessment Authority (SEIAA).

Not applicable. The sub-project is not included in schedule of environmental impact assessment notification 2006 and its subsequent amendments till date, so it is not categories as either Category A or Category B. As a result, environmental clearance is not required, either from the state or the central Government.

Page 62: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

61

Water (Prevention And Controlof Pollution) Act of 1974, Rules of 1975, and amendments

Act was enacted to provide for the Prevention and control of water pollution and the maintaining or restoring of wholesomeness of water, by Central and State Pollution Control Boards and for conferring on and assigning to CPCB/SPCBs powers and functions relating to water pollution control. Control of water pollution is achieved through administering conditions imposed in consent issued under to this Act. These conditions regulate the quantity and quality of effluent, the location of discharge and the frequency of monitoring of effluents. Any component of the subproject having the potential to generate sewage or trade effluent will come under its purview. Such projects have to obtain Consent For Establish (CFE) under Section 25 of the Act from Madhya Pradesh Pollution Control Board (MPPCB) before starting implementation and Consent For Operate (CFO) before commissioning.

STP requires CFE and CFOfrom MPPCB.

Application has to be submitted online at http://www.mppcb.nic.in/xgn.html

Environment (Protection) Act, 1986 and CPCB Environmental Standards.

Emissions and discharges from the Facilities to be created or refurbished or augmented shall comply with the notified standards

Appendix 2 provides applicable standards for ambient air quality. Appendix 3 provides vehicular emission norms

NoisePollution (Regulation and Control) Rules, 2000 amended up to 2010.

Rule 3 of the Act specifies ambient air quality standards in respect of noise for different areas/zones.

Appendix 4 provides applicable noise standards.

Solid Wastes Management Rules,2016

Rules to manage municipal solid waste generated; provides rules for segregation, storage, collection, processing and disposal.

Solid waste generated at proposed facilities shall be managed and disposed in accordance with the MSWM Rules

Construction & Demolition Waste Management Rules, 2016

Rules to manage construction & to wasteresulting from construction, remodeling, repair and demolition of any civil structure. Rules define C&D waste as waste comprising of building materials, debris resulting from construction, re- modeling, repair and demolition of any civil structure.

Construction & demolitionwaste generated from the project construction shall be managed and disposed as per the rules (Appendix5)

Page 63: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

62

LaborLaws The contractor shall not makeemployment decisions based upon personal characteristics unrelated to job requirements. The contractor shall base the employment relationship upon equal opportunityand fair treatment, and shall not discriminate with respect to aspects of the employment relationship, including recruitment and hiring, compensation (including wages and benefits), working conditions and terms of employment or retirement, and discipline. The contractor shall provide equal wages and benefits to men and women for work of equal value or type.

Appendix 6 provides applicable Labor laws including amendments issued from time to time applicable to establishments engaged in construction of civil works.

Table 16: Effluent Disposal Standards of STPs Applicable to All Modes of Disposal

S. No. Parameter Standard

Location Concentration

not to exceed

1 pH. Anywhere in the country 6.5 - 9.0

2 Bio-Chemical Oxygen Demand (BOD)

Metro Cities*, all State Capitals except in the State of Arunachal Pradesh, Assam, Manipur, Meghalaya Mizoram, Nagaland, Tripura Sikkim, Himachal Pradesh, Uttarakhand, Jammu and Kashmir, and Union territory of Andaman and Nicobar Islands, Dadar and Nagar Haveli Daman and Diu and Lakshadweep

20

Areas/regions other than mentioned above 30

3 Total Suspended Solids (TSS)

Metro Cities*, all State Capitals except in the State of Arunachal Pradesh, Assam, Manipur, Meghalaya Mizoram, Nagaland, Tripura Sikkim, Himachal Pradesh, Uttarakhand, Jammu and Kashmir, and Union territory of Andaman and Nicobar Islands, Dadar and Nagar Haveli Daman and Diu and Lakshadweep

<50

Areas/regions other than mentioned above <100

4 Fecal Coliform (FC) (Most Probable Number per 100 milliliter,

Any where in the country <1000

Page 64: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

63

MPN/100ml

*Metro Cities are Mumbai, Delhi, Kolkata, Chennai, Bengaluru, Hyderabad, Ahmedabad and Pune.

Note:

(i) All values in mg/l except for pH and Fecal Coliform.

(ii) These standards shall be applicable for discharge into water bodies as well as for land disposal/applications.

(iii) The standards for Fecal Coliform shall not apply in respect of use of treated effluent for industrial purposes.

(iv) These Standards shall apply to all STPs to be commissioned on or after the 1st June, 2019 and the old/existing STPs shall achieve these standards within a period of five years from date of publication of this notification in the Official Gazette.

(v) In case of discharge of treated effluent into sea, it shall be through proper marine outfall and the existing shore discharge shall be converted to marine outfalls, and in cases where the marine outfall provides a minimum initial dilution of 150 times at the point of discharge and a minimum dilution of 1500 times at a point 100 meters away from discharge point, then, the existing norms shall apply as specified in the general discharge standards.

(vi) Reuse/Recycling of treated effluent shall be encouraged and in cases where part of the treated effluent is reused and recycled involving possibility of human contact, standards as specified above shall apply.

(vii) Central Pollution Control Board/State Pollution Control Boards/Pollution Control Committees may issue more stringent norms taking account to local condition under section 5 of the Environment (Protection) Act, 1986”.

Page 65: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

64

Table 17: Standards for Sludge Reuse as Manure

Standards for Composting. As there are no specific standards notified for sludge reuse, the compost quality standards notified under the Solid Waste Management Rules, 2016 (Schedule II A, Standards for Composting) have been adopted here. According to the standards “In order to ensure safe application of compost, the following specifications for compost quality shall be met, namely: -

Parameters Units Organic Compost

(FCO 2009)

Phosphate Rich

Organic Manure

(FCO 2013)

Arsenic mg/kg 10 10

Cadmium mg/kg 5 5

Chromium 50 50

Copper 300 300

Lead 100 100

Mercury 0.15 0.15

Nickel 50 50

Zinc 1000 1000

C/N ratio <20 <20:1

PH 6.5 – 7.5 (1:5 solution) maximum 6.7

Moisture, percent by weight, maximum

15.0 – 25.0 25.0

Bulk density (g/cm3)

<1 Less than 1.6

Total Organic Carbon, per cent by weight, minimum

12 7.9

Total Nitrogen (as N), per cent by weight, minimum

percent by weight

0.8 0.4

Total Phosphate (as P205) percent by weight, minimum

percent by weight

0.4 10.4

Total Potassium (as K20), percent by weight, minimum

percent by weight

0.4 -

Page 66: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

65

Standards for Composting. As there are no specific standards notified for sludge reuse, the compost quality standards notified under the Solid Waste Management Rules, 2016 (Schedule II A, Standards for Composting) have been adopted here. According to the standards “In order to ensure safe application of compost, the following specifications for compost quality shall be met, namely: -

Parameters Units Organic Compost

(FCO 2009)

Phosphate Rich

Organic Manure

(FCO 2013)

Colour

Odour Absence of foul Odor

Particle size minimum 90% material should pass through 4.0 mm is sieve

minimum 90% material should pass through 4.0 mm is sieve

Conductivity, not more than

dsm-1 4 8.2

* compost (final product) exceeding the above stated concentration limits shall not be used for food crops. however, it may be utilized for purposes other than growing food crops.

55. ADB SPS Requirements: During the design, construction, and operation of the project

the PMU and PIUs will apply pollution prevention and control technologies and practices consistent with international good practice, as reflected in internationally recognized standards such as the World Bank Group’s Environment, Health and Safety Guidelines. (IFC’s General EHS Guidelines1 and Sector Specific (Water and Sanitation) Guidelines2). These standards contain performance levels and measures that are normally acceptable and applicable to projects. When Government of India regulations differ from these levels and measures, the PMU and PIUs will achieve whichever is more stringent. If less stringent levels or measures are appropriate in view of specific project circumstances, the PMU and PIUs will provide full and detailed justification for any proposed alternatives that are consistent with the requirements presented in ADB SPS.

Table 18:-WHO Ambient Air Quality Guidelines

1https://www.ifc.org/wps/wcm/connect/554e8d80488658e4b76af76a6515bb18/Final%2B-

%2BGeneral%2BEHS%2BGuidelines.pdf?MOD=AJPERES 2 https://www.ifc.org/wps/wcm/connect/e22c050048855ae0875cd76a6515bb18/Final%2B-

%2BWater%2Band%2BSanitation.pdf?MOD=AJPERES

Page 67: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

66

Table 19:-World Bank Group’s EHS Noise Level Guidelines

Page 68: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

67

V. DESCRIPTION OF THE ENVIRONMENT

A. Methodology Used for Baseline Study

56. Data collection and stakeholder consultations. Data for this study has been primarily

collected through comprehensive literature survey, discussion with stakeholder agencies, and field visits to the proposed subproject sites.

57. The literature survey broadly covered the following:

(i) Project details, reports, maps, and other documents prepared by technical expert of design consultant team

(ii) Discussions with Technical experts of the design consultant team, municipal authorities, relevant government agencies etc.

(iii) Secondary data from previous project reports and published articles, and (iv) Literature on landuse, soil, geology, hydrology, climate, socioeconomic profiles,

and other planning documents collected from Government agencies and websites.

58. Ocular inspection: During IEE preparation to assess the existing environment (physical,

biological, and socioeconomic) and gather information with regard to the proposed sites and scale of the proposed project. A separate socioeconomic study was conducted to determine the demographic information, existing service levels, stakeholder needs and priorities.

B. Physical Resources

1. Location, Area & Connectivity

59. Geographically, the project area is located in the Narmada valley at 22.03° N latitude and

75.05° E longitude. It has an average elevation of 151 metres (495 feet). It is a tehsil in Barwani district of Madhya Pradesh state. The project area comprises the adjoining town of Anjad, administratively in Barwani District of the state. It is located at about 318 km south – west of the state capital Bhopal, and its distance from Barwani is 16 km and130 km from Indore. It is situated along the main road connecting Anjad with SH-26. The town is situated 17 km. from Barwani. The great Narmada River flows through Barwani (just 5 km from city). A river flows through it named Bhagwati Nadi, today known as Bhongli nadi. The district is bordered by Maharashtra state to the south, Gujarat state to the west, Dhar District to the north and Khargone District to the east.

60. Anjad Nagar Parishad (Anjad Municipal Council) extends to an area of about 15.54 sq. km

characterized by a mix of urban and few rural settlements. Anjad is a class III town which was established as Nagar Panchayat on 1908. Presently the town has a population of about 26492 (census 2011 provisional figure). Anjad is a small town and Nagar Parishad situated in the District Anjad of M.P The town is divided into 15 municipal wards, which includes villages of Awali, Badgaon, Bjaha and Banjari etc

Page 69: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

68

2. Topography, Soils and Geology

61. The topography of Anjad town is governed by two major water bodies. Namely Susad River

and Bhongli nalla, Susad River and Bhongli nalla flow from South direction to North direction. Both of them meet near Chhota Barda village and then adjoin into River Narmada. The drainage system of Anjad is shown below.

Figure 26: Existing Drainage Map Anjad

62. The soil in the region is mostly black cotton but has a rocky terrain. No rock cutting/blasting will be required during sewer laying, however detailed investigation will be done during detailed design phase by DBO Contractor.The soil in the Nimar region is less productive in comparison to nearby region like Malwa region. The district as previously supposed to be unsuitable for the tube-well development programme since it is a hard rock formation area. However, the results of Geo hydrological survey and drilling of tube wells in the district are encouraging. The primary geo hydrological investigation in the entire district has been completed

3. Seismology 63. As per the seismic zoning map of India, project area falls under Zone II, which is the lowest

earthquake risk zone in India. This zone is termed as “low damage risk zone”.

Page 70: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

69

4. Rainfall and Climatic Conditions

64. The climate of the district on the whole is tropical and dry, except during south west

monsoon season (middle of June to September). The year may be divided into four seasons. Winter Season is between November to February. Summer season starts from March and ends by June. The months of October and November constitute the post-monsoon or transition season. The climate of the district is hot; the temperature varies between 420C to 480C, making it the hottest place in India. Relative humidity is maximum in the monsoon season and is very low in dry months. It is as low as 10% in dry months and as high as 94% in the monsoon season. The place stays very hot in summer and moderately cold in winter; hence, the ideal time to visit is between the months of August and March. The months of May and June are very hot while the month of December and January are cold with the temperature going down to 100C. July and August are rainy season. The rain may occur from the months of June to October. Average wind speed is 9 km per hour. Maximum wind speed is during May – June and minimum wind speed is during December – January.

65. Rainfall: The district is influenced by South-West Monsoon which extends from June to September. The mean annual rainfall is 842 mm. The most rainfalls occur in July. There is very little rainfall in the winter season. The monsoon rainfall accounts for 80% - 85% of the annual rainfall.

66. There is little rainfall throughout the year. The driest month is February. There is 0 mm of

precipitation in February. The most precipitation falls in July. With an average of 34.5 °C, May is the warmest month. January has the lowest average temperature of the year. It is 20.9 °C.

58. Project Areas & Environs: Project components locations are shown in below map.

Figure 27: Showing Anjad Town in Google Earth Map

Page 71: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

70

5. Surface Water

Page 72: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

71

59. There is lake located in the town is situated in the south eastern side of the town namely Foota Talab. The water body has a surface area of 2.10 Hectares. There are two rivers passing from the town, one is passing from the centre of the town namely Bhongli Nallah and another major river which is passing from western side of the town namely Susad river. The whole sewage and storm water of the area is flows through the road side drains and finally joins Bhongli Nala. Initially Bongli Nala was the Bhagwati river or Bhongli river, later due to the encroachment and pollution it got converted into the Bhongli Nala. The Bhongli Nala passess from the centre of the town and carries about 70% of city’s storm water and drainage out of the town. The road has been built along the both sides of the Nala by the nagar parishad and the Nala has been almost pakka. The sewerage from the houses is directly dumped into the Bhongli Nala through the pipes. The weekly market is operated from the roads which are constructed along the Nala, the waste of the weekly market is also dumped in the Nala and in many places the solid waste is collected along the nala by the workers of nagar parishad. Similarly, the Susad river is also passes from the city, the drainage of slums are directly meet to the river. At some distance Susad and Bhongli river are confluence and after that they fall into the Narmada River at a distance of 5 km.

Page 73: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

72

Figure 28: Bhongli Nala / Bhongli River

Page 74: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

73

Figure 29: Showing Google earth Map of Anjad Town Upto Narmada River

Figure 30: The weekly market operated along the Bhongli Nala

Page 75: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

74

60. Barwani district falls under the Narmada drainage system which forms the northern boundary of the district. The tributaries of Narmada are Goi and Deb which are formed by small streams.

61. About 88% of the district lies in Narmada Basin and 12% in Tapti Basin. The major tributaries of Narmada are Deb and Goi. No major tributary of Tapti flows in the district. The surface water availability at 75% dependability for both the Basins is 966.70 MCM of which 921.95 MCM is from Narmada Basin and 44.75 MCM from Tapti Basin. The district area is drained mainly by the Narmada river and its tributaries like Goi and Deb. All of these tributaries flow from south to north and join Narmada. Similarly, tributaries like Tori, Churi, Dudhikheda etc. flow from north to south. Major rivers are perennial to semi-perennial.

62. Goi: Goi is a long river rising from the southern slope of the Bijagarh foot hill and cutting its channel through the Satpura. It meanders for over 120.75 Km. to the north-west and joins Narmada south of Nisarpur which is on the opposite northern bank covering Sendhwa and Silawad places of the district.

63. Deb: Deb originates from the village Dhanori and flows with its meanders for about 100 Kms to the north and joins Narmada. Deb has eleven springs; six of the springs in the Deb drainage area are near the villages of Bada, Salai, Singui, Ghusgaon, Achhaldevi, Sitapuri and Sadla while there is one to the north-east of Bharvada and other four in the Dhaba forest.

64. The great Narmada River flows through Barwani (just 5 km from city). A river flows through project town named Bhagwati Nadi, today known as Bhongli nadi. The town of Anjad gets raw water supply from Narmada River which is about 5 km from the city. Town receives water from both surface and ground water. Around 1.2 MLD per day water receives from river Narmada. In ground source, for supplying drinking water in the town there are 6 tube wells and 10 Hand pumps which are located in the various parts of the town. From ground sources, 0.3MLD water is being supplied. Yield of these tube considerably during summer.

65. Water Quality of River U/S & D/S of the Anjad Town: Chemical quality of water of Narmada River at u/s and d/s of the town is tested by Regional Laboratory, M.P. Pollution Control Board Indore on dated 30/6/2014. The samples were collected on dated 26/6/2014 at Dattwada (u/s of the town) and near Chhota Barda (d/s of the town). From the results, it is revealed that untreated sewage discharge coming out from the Anjad town joins Narmada River. The detailed results are given in Appendix-15 .

Table 20: Water Quality of the River Narmada

Parameters U/S of town D/S of town Standards for River

Water Quality

pH 8.27 8.18 6.5 to 8.5

BOD (mg/l) 1.1 1.6 3 (mg/l) or less

DO (mg/l) 8 7.9 5 mg/l or more

Page 76: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

75

Fecal coliform (MPN/100 ml)

<1.8 <1.8 Desireable-500 (MPN/100

ml)

Maxm. Permissible =2500

(MPN/100 ml)

Source: DPR Consultant (Test undertaken by MPPCB Regional Laboratory, Indore on

30/6/2014)

66. The sewage characteristics of Bhonglinalla got tested from Regional Laboratory, MP

Pollution Control Board Indore. As per characteristic of sewage, it is cleared that the nalla is carrying only Domestic Waste. The detail of main parameters is given below and in detail is given in Appendix 16.

Table 21: Wastewater Quality of the Bhongli Nala

Parameters BhongliNalla

BOD (mg/l) 84

COD (mg/l) 180

TDS (mg/l) 764

Fecal coliform (MPN/100

ml)

540

Source: Test undertaken by MPPCB Regional Laboratory,

Indore on 30/6/2014

67. Surface Water Quality: Surface water quality monitoring will be done during detailed

design phase and surface water quality monitoring has been include in monitoring plan. Refer EMP Table- 31.

6. Ground Water

68. The occurrence and movement of ground water is governed and conditioned by geomorphic configuration of the place and water bearing properties of the litho units like porosity, permeability etc.

69. Barwani district is underlain by, Basaltic lava flows of Deccan trap. Dynamic ground water resources of the district have been estimated for base year-2010/11, on block-wise basis. Out of 5,42,200 ha of geographical area, 3,66,831 (68%) ha is ground water recharge worthy area and 1,75,369 ha (32%) is hilly area. There are seven number of assessment units (block) in the district which fall under which fall under non-command sub-unit. Barwani, Niwali, Pati and Sendhwa blocks of the district are categorized as safe blocks, Rajpur and Thikri as semi critical and Pansemal as over exploited with highest stage of ground water development which is computed as 115 %. The net ground water availability in the district is 41,301 ham and ground water draft for all uses is 29,819 ham, making Stage of Ground water development 72 % (72 % in 2004/09) as a whole for district. After making allocation for future domestic and industrial supply for next 25 years, balance

Page 77: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

76

available ground water for future irrigation would be 9,457 ham.

Table 22 : Hydrology

Items Statics Major Water Bearing Formation

Alluvium & Deccan Trap

Pre-monsoon depth to water level during 2012

3 - 21 mbgl

Post-monsoon depth to water level during 2012

3 - 8 mbgl

Long Term water level trend in 10 years (2003-2012) in m/yr

Rising Trend

0.0031 – 0.2093

70. Ground Water Quality of Barwani District: As per chemical analysis data of pre-

monsoon, 2011, ground water in the area is generally alkaline in nature and the pH values are within acceptable limits. The Chloride concentration in the area is below 250 mg/l. The higher chloride values generally coincide with areas having high EC thus indicating that the salinity in ground water is mainly due to chloride. Concentration of magnesium and calcium in Barwani district are within permissible limits. The nitrate concentration in the district ranges between 2.5 – 68 mg/l with only Sendhwa having a value of 68 mg/l. The fluoride concentration in the district ranges between 0.14 to 0.61 mg/l. The total hardness in the district ranges between 65 to 530 mg/l falling within permissible limit. The plot of the Piper diagram indicates that alkaline water is found at Baru phatak, Julwania, Niwali and Rajpur. At Sendhwa, ground water is of alkaline earth sulphate and chlorite type, having permanent hardness, which can be removed by ion-exchange method. At Palsud, the water is alkali sulphate and chloride type

71. Ground Water Quality & Depth of Water Level: Ground water quality data of Anjad town is not available at this stage; however, ground water quality of the town is potable. The ground water availability in these areas comes under Safe Zone as per Central Ground Water Board (CGWB) report. Ground water quality monitoring will be done during detailed design phase by DBO Contractor. However, as per District Ground Water Information has been annexed in Table- 23 as given below.

Page 78: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

77

Table 23: Quality of Ground Water of Barwani District

Source: Barwani District Ground Water Information Booklet

Page 79: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

78

Figure 31: Hydro geological Map, District Barwani (M.P.)

Page 80: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

79

Figure 32: Depth of Water Level (Pre-Monsoon Season)

Figure 33: Depth of Water Level (Post-Monsoon Season)

Page 81: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

80

7. Air Quality 72. No air quality data available, however, there are no air pollution sources, except the dust,

which is mainly due to dry weather, activities like traffic movement. There is no data on ambient air quality in Anjad Town, which are not subject to monitoring by the Madhya Pradesh Pollution Control Board (MPPCB) as there are no major industries. Traffic is the only significant pollutant, so levels of oxides of sulphur and nitrogen are likely to be well within the National Ambient Air Quality Standards (NAAQS). In addition, following factors also contribute largely to the problem;

• Increased in the number of vehicular traffic, • Poor road condition • Construction of buldings

73. No field monitoring (environmental) survey was conducted however, the environmental

monitoring program developed as part of the environmental management plan (EMP) will require the contractors to establish the baseline environmental conditions prior to commencementof civil works. The results will be reported as part of the environmental monitoring report and will be the basis to ensure no degradation will happen during subproject implementation.

C. Ecological Resources

74. Project area mostly comprises urban areas, agricultural areas of Anjad, which are

converted to human use many years back. Majority of the area in the municipal boundary is in residential and commercial. There are no ecologically sensitive features in the project area. Flora and fauna found in the area is of local species. There are no forest areas within municipal limits, but forest areas exist around Anjad as shown in Fig-34-35. Extent of forest areas around Anjad is very limited and none of the project components are located in the forest areas. The forest areas are confined to low forested hilly areas around the town. None of the subproject components are located in these forests. Forests are mostly covered with teak and mixed tree cover. The district lies in the southwestern corner of Madhya Pradesh; the Narmada River forms its northern boundary. The Satpura Range lies to its south.

Page 82: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

81

Figure 34: Existing Landuse Map- Anjad Showing Forest Area

Figure 35:Proposed Landuse Map- Anjad Showing Forest Area

Page 83: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

82

75. Barwani district area covered with vegetation is managed by the Forest department. Due to less rainfall and land, nature provides the scattered and unmanageable greenery which remain under the forest area protected and un-classed forests. Mixed type of forests is found in the district. These forests are spread in Sendhwa, Pansemal ranges and also in parts of Barwani ranges. The trees found in the forests are teak, moyen, dhovan, haldu, ledia, neem, palash, amla, tensa, belawar and behda etc. The main teak associate floras are; anjain, salai, jhingan, while saj, tendu and mahuwa etc. are found in low-lying moist area. Other main species found in the canopy are phansi, bija, mokha, kaim, kari, bijasal, rohan, arjunshisham, kalasiris, chichwa, pangrachirolgamari and semal.

76. The wild animals found within the district do not differ remarkably from those found in other districts. Of the animals of the carnivorous order, tiger and panthers are very rarely seen in the interior areas of dense forests. Senkutta, lomdi, and jararc (hyena) are the other roaming carnivorous animals. Sloth bear, wild bear, nilgai, sambhar, chital, chinkara and monkeys are found in Pati ranges. Rabbits and mangoose are the mammals found in the district. Among birds, wild owl, peacock, titar, bater,dove and pigeon can be seen everywhere. Nearest protected area is Ralamandal Sanctuary, about 140 km from the Anjad town.

D. Economic Development

1. Landuse

77. As per the existing land use pattern, the commercial activity is observed to be the second

largest activity after the transportation activity may be mainly due to the tourist inflow. Present development shows a clustered settlement pattern spread over 15.54 sq.km area, comprising both urban and rural settlements. Most of the area is predominantly undeveloped and is under the agricultural use. The urbanized area is only about 15% of the total municipal areas. In the historical context, Barwani district is described as a rich and fertile land due to Narmada basin. District and its headquarters share the same name. Carved out of Khargone (West-Nimar) district Barwani was formed on 25th May 1998. In 2006 the Ministry of Panchayati Raj named Barwani one of the country's 250 most backward districts (out of a total of 640). It is one of the 24 districts in Madhya Pradesh currently receiving funds from the Backward Regions Grant Fund Programme (BRGF).

78. Spread over 15.54 sq. km area Anjad is comparatively a smaller town and is traditionally

an agriculture-based economy. It is a local center for agricultural marketing dealing in agriculture produce, inland fisheries and forest produce. Large part of the municipal area is still under agriculture.

79. Residential areas share about 41.00% of the total area in Anjad; while, Agriculture Land / Forest Cover areas shares about 28.00%, Special areas shares about 13.00%, Public & Semi Public areas shares about 6.00%, Vacant Land areas shares about 5.00%, Water Bodies areas shares about 3.00%, Roads & Transportation areas shares about 2.00%, Commercial areas shares about 2.00%, The following analysis with respect to land use can be drawn for the case of Anjad:

Existing and Proposed land use in Anjad

Page 84: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

83

Land use Category Area (in Hec.)

Land use %

Residential 637.14 41.00% Agriculture Land / Forest Cover

435.12 28.00%

Special Areas 202.02 13.00% Public & Semi Public 93.24 6.00% Vacant Land 77.70 5.00% Water Bodies 46.62 3.00% Roads & Transportation 31.08 2.00% Commercial 31.08 2.00% Total 1554.00 100% Source: Urban local Body *Hec. Hectare

2. Industry & Agriculture

80. The economy of Barwani district is based on cultivation. Agriculture is the main source of

livelihood of the people of the district. 84.9% of the people depend upon agriculture in the district, out of which 44.0% are cultivators and 40.9% are agricultural labourers.

81. Economically Anjad is entirely dependent on agriculture, with several other small industries developing in the area. Anjad town is mainly known for Cotton, Soybean, Corn, Vegetables and Chilly cultivation. Along with many cotton factories which gives employee to the thousands of local people, Sanjay Cotton Fiber is the most famous and largest Cotton Factory of the region. Majority of the population is engaged in trading and agriculture related activities. The economy is mostly dependent on agriculture and agricultural based activities. Cotton industries are located within municipal limits. They have there own treatment plants As per EARF EMP Table, no industrial wastewater shall be allowed to dispose into municipal sewers

82. The main Economic base of Anjad town is mainly depends upon the Agriculture. Agriculture is the only component after trading that from the backbone of the economy. Anjad sits in rich agriculture region, though lack of proper irrigation facility and modern agriculture practice are reducing the actual potential. Techniques are largely nominal, with the majority of the farmers still relying on traditional methods of farming. The main crops produced in the district include Maize, Rice, Kutki and Oil seed Ramtilla. Kharif and rabi are the main crop seasons in the project area.

83. Commercial Aspects: Anjad is one of the small towns of Badwani district. It could be develop as a major commercial city because of good connectivity to major cities. The city mostly relies on Badwani and Thikri for commercial activities. The major commercial activities of the town are operated from ward 5, 7, 9, 10, and 11. 3. Infrastructure

84. Sewerage: There is no sewerage collection and treatment system in the Anjad town.

Households mainly depend on individual sanitation systems like pit latrines, septic tanks etc. Open defecation is also prevalent in the project area. There is no treatment plant established thus, the raw water sewage with drainage water is directly disposed in the

Page 85: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

84

agricultural fields. There are no public toilet facilities available in the town. A sewerage and drainage system needs to be improved in the towns to meet the increased wastewater generation due to improvement in water supply.

85. Solid Waste Management: There is no proper solid waste management system in the

towns. Respective municipal councils are responsible for SWM services their areas. Waste generated in the towns are collected and disposed by crude open dumping method in the outskirts of the towns.

86. Storm Water Drainage: Open drainage system is provided in towns for collection and

conveyance of rain water from the town. Due to lack of sewerage system, the drains are presently carrying wastewater including sewage. Since rains are confined only to a short duration in monsoon, the drains mostly carry wastewater. Indiscriminate disposal of solid waste into drains is common, due to which drains are often chocked, creating unhygienic conditions.

87. Power Supply: Thermal power is the main source of energy in Madhya Pradesh,

contributing nearly 90% of the electricity, compared to hydropower, which produces the remainder.

88. Transport: The areas of Anjad town are characterized by very narrow roads that are

frequently congested with traffic and pedestrians. In contrast the remainder of the town has a relatively good road system, particularly in the outer areas, where streets are wide and not heavily used by traffic. Roads are surface either with bitumen or concrete, and roads in the outer areas are mostly unpaved. Most of the roads are maintained by respective municipal councils except the main roads connecting other towns and villages, which are maintained by the Public Works Department (PWD). Road the condition is generally poor, with many roads in need of repairs and resurfacing. Anjad Nagar Parishad is currently improving some of the important roads in the town.

E. Socio Cultural Resources

1. Demography

89. According to the census, the population of Anjad was 26,289 in 2011, increased from

22,882 in 2001, which shows an increase of 14.89 % over the decade. The previous decade of 1991-2001 experienced comparatively higher growth of 17.81%. Overall literacy is 59%, which is lower than the national average of 59.5% with 58% for males and 42% for females, literacy in the state as a whole. 16% of the population is under 6 years of age. With an area of 15.54 sq. km under the municipal limits, gross population density is very low (2275 persons/km), but this varies across the area, as most of this area is undeveloped, and in the core area of the town, population is dense. About 2% of the population are scheduled tribes (ST), but these are part of the mainstream population, and about 16% belong to scheduled castes (SC). Main language spoken the project areas is Hindi.

90. Socio-Economic Status: The overall involvement of main workers in the town is close to both district and state average whereas involvement of marginal workers is lower than the district and state average figures. The % of Non-Workers population in Anjad is 64% which includes students, housewives, dependent such as infants or very elderly people,

Page 86: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

85

pensioner’s those who are drawing pension after retirement and are not engaged in any economic activity etc. The total workers in Anjad can be classified into 4 categories based on their occupation as Cultivators, Agricultural Labourers, Household Industry Workers and Other Workers. Out of total workers (main+marginal) Cultivators and Agricultural Labourers constitute 10.7% and 36.8% respectively. The overall literacy rate of the town (excluding out growths) is higher than the district average (urban) but much lesser than the state level data. Comparison of literacy among males and females shows that more percentage of male are literate than females. 2. History, Culture and Tourism

91. Anjad is popular for its ancient and beautiful “Nagari Mata Temple”, located on top of the

valley in right corner and centr of the town, the Deity of this temple is considered as Tutelary Diety of Rajput community. Religious temple like Nagri Mata temple are places where people spend their time for recreation. There are two other temples, namely Gayatri Temple and Saibaba Temple (Chota shirdi). Anjad is also famous for its cotton factory, an employment source for thousands of locals.

92. The Pancha Mukhi Hanuman Temple in Anjad, brings devotees together from all over the region for offering prayers. The place is surrounded by many nearby tourist places such as Mandu, which is at a distance of about 85 km, Omkareshwar is about 132 km, Nandurbar is approx. 154 km and Toranmal is about 135 km away from Anjad town. Mandu, also known as Mandavgarh, is an ancient town established by the Muslim ruler, AlauddinKhilji. The town is renowned for its two fortified enclosures meant for protecting the royal enclave and the royal palace of Baz.

93. There are no protected areas / archeonologica sites in Anjad. Nearest town Mandu, which

is at a distance of about 85 km from Anjad town.is an important historical and architeural town in M.P. and is a world heritage site listed by GOI. There are several ASI monuments, archeological sites such as the 15th century Jahaz Mahal, built in the Afghan style of architecture, is a major part of the royal enclave and attracts many people. Other popular attractions of this place are Alamgir, Jehangir Gate, Rampol Darwaza, Bhangi and Tarapur Gate, Rani Roopmati Mahal, Jama Masjid etc. Another prominent pilgrimage centre near Anjad, at a distance of 132 km is the Omkareshwar Temple located in Khandwa District, which is counted among the 12 Jyotirlinga shrines of Lord Shiva.

94. Culture Activities: As such there is no prominent recreational area or tourist place in

Anjad town and hence the town doesn’t have any remarkable tourism activity. At present there are very limited socio-cultural facilities available in the town such as community halls, dharamshalas, parks, playgrounds etc. Even the facilities which are present are not in good condition and lack maintenance. Apart from that, some areas can be developed as Regional tourism or recreational areas which have a potential to attract people from other towns. The areas which are identified for the development as tourism centre is: Nagari Mata Mandir.

95. Religious Activities: Bawangaja (Chool Giri) is an important Jain pilgrimage centre. It is 6 Kms from district headquarter Anjad. There are 11 temples on the hill and they belong to 15th century. It has world's tallest statue of Lord Adinathji. Jain saints Kumbhakarna and Indrajeet were said to attain Nirvaan from this place only. Beejasan is situated on the Agra-Mumbai national highway, 20 Kms from Sendhawa towards Maharashtra. It is

Page 87: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

86

famous for the temple of Godess Beejasani (Durga).

96. Tourism: Anjad is also popular for the nearby small hill station called Toranmal. Toranmal houses tourist sites such as Yashavant Lake, Lotus Lake, Gorakhnath Temple and Nagarjun Temple. Main tourist season starts in the month of August and continues up March. December-January is considered as peak tourist season.

97. Barwani is surrounded by the great hills of Satpura and in the raining days it becomes one of the most beautiful places in central India. The city is also called the Paris of Nimar. Nimar region is split into East Nimar and West Nimar. Nimar, in local terms, means "area beyond thetdhgn Neem Trees". Barwani lies in West Nimar. Barwani is famous for its Papitas and Bawangaja (a Jain holy place 8 km from Barwani).

F. Subproject Site Environmental Features

98. Features of the selected subproject sites are presented in the following table below.

Table 24:-Site Environmental Features- Anjad

Infrastructure

Location & Environment Feature Site Photograph

Sewage Treatment Plant

The proposed STP site is located on south-eastern side and on outskirts of the town, away from human settlement on the right hand side of existing road and proposed STP site is at least 500 m away from the habitation There is no notable development within 500m of site boundary. Some brick kiln works is going on within 200-500m from its premises by local people. (Refer map annexed as Fig-36). There are no trees on the proposed site. There are no notable sensitive features and the site is currently vacant and barren land and surrounded by agricultural lands, which belongs to Revenue Department, GoMP. Total land area required is 0.5 Hectare and available land is 13.86 hectare (Khasra No. 526.) Proposed STP site is located on undulating terrain and most part of the site is surrounded by agricultural land and some part is surrounded by hilly areas and approx. 300m away from phoota talab. The STP site not comes under flood prone area/ low lying areas, however site is surrounded by foothill. It is not a defiened drainage channel. But for general water

Page 88: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

87

accumulation during monsoon, it will be ensured that STP site is not obstructing natural drainage, all the mitigative measures will be take into consideration such as proper drainage system will be provided to channel off the upstream flow into downstream near by available natural drains, which joins Bhongli Nala and then finally into Narmada to avoid flooding/water accumulation from up hill areas. Mitigative measures has been included in EMP. (Refer EMP Table-27 during design stage) The proposed site shall be provided with sufficient buffer zone with maximum extent as per availability of land at least 20-30 m width of buffer green area to avoid a site with significant inhabitated and residential areas down stream of prevailing wind. Providing proper boundary for the site, especially high compound wall towards Residential area. Distance from STP boundary to nearby property/houses is about 500m and with the proposed green buffer zone with trees of 30m width, the minimum distance from the STP units will be 530m and no odour generating potential units will be located towards habitation. Treated water will be disposed off into nearby available natural drain which joins Bhongli Nala and then to Narmada river. Treated wastewater will be disposed into nearby available natural drain, which is at a distance of 580m from STP site and then after traveling a distance of about 1.6km joins Bhongli Nala, after that it will finally disposed into Narmada after travelling a disatance of 13.4 km from Bhongli nala. Capacity of drain is adequate to take the load, as the drain is passing along agricultural fields connecting to STP site located near foothill of undulating land mass with a large catchment area as shown in google map (Refer Fig-

Page 89: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

88

39). This natural drain is only way to clear run-off water generated from hill catchment during rainy season. Treated effluent is of very small quantity with respect to run-off and as such capacity is adequate to discharge it through this natural drain all over the year.condition of the drain is not good, proper drainage system needs to be provided upto a stretch of 1.6km for proper disposal of treated sewage. Proposed STP site is located at the fringe area of subproject town and agricultural fields are reported in and around of STP site, therefore treated water will be utilized mostly by local farmers for irrigation purpose for agricultural land which will be lifted by them from their owned pumps as a sump is proposed for temporary storage at WTP site. During monsoon season, effluent will move through natural drain which further meets at Bhongli Nalla and then into Narmada river.

Intermediate Pumping Station (IPS)

Site selected for IPS is located on the bank of Susad River near Susad Mohalla. Although, a temple, government middle school and community hall is reported in the proximity of Susad Mohalla but proposed site of IPS is away from these receptors. It is about 50m away and as well as back side of the built up area. As mentioned above that proposed site is located on bank of the river and agricultural fields are reported in and around the site. As per the land records there is large piece of land in the proposed Khasra but during site visit, it was found that a large built up area along with temple and school has been developed but away from river side. It is pertinent to mention here that required land for IPS is available which is reported vacant in state. Site is currently vacant & barren land and is owned by GoMP. As per revenue

Page 90: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

89

record total land area available is 0.36 Hectare & required land area is 0.022 Hect (Khasra No. 71). No tree cutting will be required as the trees are on the periphery of the site, which will not be removed for IPS construction. It is proposed developed 20-30 m buffer around the IPS within the proposed site boundary, so the buffer between IPS and temple/school and residential area will be about 70-80 m. Providing proper boundary for the site, especially high compound wall towards temple, school and residential areas. Layout plan of IPS shall be devised in such a way that it will be farthest from temple, school and habitation, so there will be no impacts envisaged due to odour to the nearby residents. (Refer Fig-38) As the site comes under flood prone area due to proximity of Susad river. Structures should be constructed above HFL to avoid pollution of floodwaters and flood damage to infrastructures and to minimize the earthworks and associated construction costs. As per local people no flooding occurred during last 05 years’ period.

Main Pumping Station (MPS)

Proposed MPS site is located near Army hotel (a food restaurant) on the bank of Bhongli nala along the main road when moves towards Chota Bardha village at least 50m away from habitation. There is no notable development within 50m of MPS site boundary. (Refer Fig-37) HFL of the proposed site is road level. As per local people no flooding occurred during last 10 years’ period. The site is currently vacant and barren land. A community toilet exists on the proposed site which is currently not in use and is delipated structure. Electrical line is passing along the road in between proposed MPS site and main access road, which will not make

Page 91: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

90

any impact during implementation. Trees are on the periphery of the site, which will not be removed for MPS construction. Site is located outside the town. Adequate land is in possession of ULB. Site is currently vacant, and is owned by GoMP. Total land area available is 0.2 Hectare & required land area is 0.03 Hec. (Khasra No. 370) The proposed site shall be provided with sufficient buffer zone with maximum extent as per availability of land at least 20-130 m width of buffer green zone to avoid a site with significant inhabitated and residential areas down stream of prevailing wind. Providing proper boundary for the site, especially high compound wall towards Residential area. Distance from MPS boundary to nearby property/houses is about 50m and with the proposed green buffer zone with trees of 20-30m, the minimum distance from the MPS will be 70-80m and layout MPS shall be devised in such a way no impact will be envisaged due to odour to the nearby residents.

Pumping Main

Pipelines will be mostly laid along the main roads. Pipes will be laid underground. There are no trees along the roads and no tree cutting will be required along the road. Locating main sewer in the ROW alongside the Road, to avoid acquiring agricultural land and affecting the livelihoods of farmers and farm workers.

Page 92: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

91

Main Sewer line

Pipelines will be mostly laid in the middle of the main roads. Pipes will be laid underground

Photograph of Road Proposed forMain Sewer Line

Photograph of Road Proposed forMain Sewer Line

Sewer Networks

Pipes will be laid along the roads/streets in the towns within the road right of way (ROW). In wider roads pipes/sewers will be laid in the road shoulder, and in narrow roads, where there is no space, pipes/sewers will be laid in the road carriage. Roads in the old part of the town are quite narrow (~3m), and in the rest of the town roads are wider. Roads are lines both sides with open drains. There are no trees along the roads, except in some new colonies in the outer areas. In old town areas pipes will be laid in the middle of the

Page 93: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

92

road, which may affect the traffic. However, laying of pipeline in centre

of the road or sides etc. will be

decided after utility surver during

detailed design phase by DBO

contractor.

Community Septic Tanks & Soak Pits

The proposed location for 0.15 MLD Septic Tanks & Soak Pits for Zone- 3 This location is favourable because of Majority of the population residing in the slums faces severe problem of improper drainage. Individual houses / community do not have septic tanks and laying of conventional sewers are not feasible due to scattered houses,

Page 94: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

93

Figure 36: Proposed STP Site with Area around 50, 100, 200, 250 & 500m circle along with habitationShown in Google Map

Page 95: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

94

Figure 37: Proposed MPS Site with Area around within 50,100, & 200m circle alongwith habitationShown in Google Map

Page 96: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

95

Figure 38: Proposed IPS Site with Area around within 50,100, & 200m circle alongwith habitationShown in Google Map

Page 97: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

96

Figure 39: Proposed STP Outfall Nearby Local Nala Which Joins Bhongli Nala & Then to Narmada River after travelling a Distance of approx. 15km Shown in Google Map

Page 98: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

97

VI. ANTICIPATED ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES

99. Potential environmental impacts of the proposed infrastructure components are presented in this section. Mitigation measures to minimize/mitigate negative impacts, if any, are recommended along with the agency responsible for implementation. Monitoring actions to be conducted during the implementation phase is also recommended to reduce the impact.

100. Screening of potential environmental impacts are categorized into four categories

considering subproject phases: location impacts and design impacts (pre-construction phase), construction phase impacts and operations and maintenance phase impacts.

a. Location impacts; include impacts associated with site selection and include loss of

on-site bio physical array and encroachment either directly or indirectly on adjacent environments. It also includes impacts on people who will lose their lively hood or any other structures by the development of that site.

b. Design impacts; include impacts arising from Investment Program design, including technology used, scale of operation/throughout, waste production, discharge specifications, pollution sources and ancillary services.

c. Construction impacts; include impacts caused by site clearing, earthworks, machinery, vehicles and workers. Construction site impacts include erosion, dust, noise, traffic congestion and waste production.

d. O&M impacts; include impacts arising from the operation and maintenance activities of the infrastructure facility. These include routine management of operational waste streams, and occupational health and safety issues.

101. Screening of environmental impacts has been based on the impact magnitude

(negligible/moderate/severe – in the order of increasing degree) and impact duration (temporary/permanent).

102. This section of the IEE reviews possible project-related impacts, in order to identify

issues requiring further attention and screen out issues of no relevance. ADB SPS (2009) require that impacts and risks will be analyzed during pre-construction, construction, and operational stages in the context of the project’s area of influence.

103. The ADB Rapid Environmental AssessmentChecklist in

http://www.adb.org/documents/guidelines/environmental_assessment/eaguidelines002.asph as been used to screen the project for environmental impacts and to determine the scope of the IEE.

104. In the case of this project (i) most of the individual elements are relatively small and

involve straightforward construction and operation, so impacts will be mainly localized and not greatly significant; (ii) most of the predicted impacts are associated with the construction process, and are produced because that process is invasive, involving excavation and earth movements; and some works are located in the reservoir and (iii) being mostly located in an urban area, will not cause direct impact on biodiversity values. The project will be in properties held by the local government and access to the project location is through public rights-of-way and existing roads hence, land acquisition and encroachment on private property will not occur.

Page 99: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

98

A. Pre-Construction Impacts – Design & Location

105. ADB Environmental Assessment Guidelines require that an IEE should evaluate impacts due to the location, design, construction and operation of the project. Construction and operation are the two activities in which the project interacts physically with the environment, so they are the two activities during which the environmental impacts occur. In assessing the effects of these processes therefore, all potential impacts of the project are identified, and mitigation is devised for any negative impacts.

106. In many environmental assessments there are certain effects that, although they will

occur during either the construction or operation stage, should be considered as impacts primarily of the location or design of the project, as they would not occur if an alternative location or design was chosen.

107. The main impact from location and design may arise for pipe laying and STP and SPS

(IPS & MPS) sites. Most of the impacts for pipe laying are already mitigated during design by changing the pipe laying sites to less impact areas after detail survey. Also, trenchless method is adopted for major nallah crossings to reduce impact. Advance NOC needs to be taken for laying the pipes through roads, highways and through lands of other Government departments. Both IPS and MPS site is located 50m away from habitation. Although, a temple, government middle school and community hall is reported in the proximity of proposed IPS, which is away from these receptors. It is about 50m away and as well as back side of the built up area. To reduce impact of foul smell plantation in 2-3 rows on the periphery of IPS & MPS land has been proposed to develop 20-30 m buffer around the MPS & IPS, so the buffer between MPS/IPS and temple, school and residential area will be about 70-80 m. STP design was modified and SBR technology was adopted so as the available free land will be sufficient for the construction of desired STP for Anjad (STP –3.66 MLD). Though there is no habitation near STP site, Habitation is approximately at a distance of 500 from STP site. STP is outside of the town. To reduce impact of foul smell plantation in 2-3 rows on the periphery of STP land shall be done.

108. Design of the Proposed Components: Technical design of the (i) SewageTreatment

Plant; (iii) Pumping mains, (iv) Pumping station, (v), Sewer Network; connections and other items, follows the relevant national planning and design guidelines, focusing on providing a robust system which is easy to operate, sustainable, efficient and economically viable.

109. Design of Sewage Treatment Plant. An SBR based STP of 3.66 MLD capacity is proposed to be constructed at the identified site on the outskirts of Anjad town to treat the sewage generated from Anjad Town. Septage from septic tanks collected via mobile suction tanker will be discharged into inlet of STP for treatment along the sewage collected via sewer network. It is proposed that the treated wastewater will be disposed into nearby natural drain which joins Bhongli Nala and then final disposal into Narmada river. As per existing situation; besides wastewater, solid waste is dumped into Bongli nalla. There are also weekly markets held along the nala, and market waste is dumped into this nallah. To avoid and reduce the impacts of solid waste dumped into the Bhongli Nala, provision for installation of screens as barrier nets to avoid dumping of waste into Bhongli Nala is included in EMP (Refer EMP Table 27 & Table 32 in IEE Report). Subproject is proposed for implementation under design-build-operate mode of contract, and therefore detailed design of STP will be carried out by the DBO contractor to meet the following prefixed treatment standards, which are more stringent than those of MoEFCC

Page 100: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

99

effluent disposal standards from STP (Table 16). SBR technology is already finalized during feasibility stage, and contractor will adopt this technology and design the facility.

S. No

Parameter Concentration

1. pH 6.5-9.0

2. Biochemical Oxygen Demand (BOD), mg/l <10

3. Chemical Oxygen Demand (COD), mg/l <50

4. Total Suspended Solids (TSS), mg/l <10

Sulphates mg/l 2

7. Fecal Coliform , MPN <100

110. Sewage Treatment Plant: An SBR based STP is recommended since SBR

technology requires comparatively much less land area with same efficient results as that of extended aeration. The main advantage of the SBR plant is that the effluent shall be of high quality.

111. The major components of the STP are i) Inlet chamber, ii) Fine Screen Channel, iii) Grit Chamber, iii) SBR units (SBR basin, Decanting Device, aeration system, Return sludge and excess sludge pumps, automation and control), iv) Disinfection unit, sludge dewatering unit, Sludge holding area

112. The SBR treatment (for the STP) process consists of the following stages: ➢ Inlet works with mechanical screens, grit removal, flow measurement & flow splitter

box ➢ Four square batch reactors with individual inlet flow control & a fully automated

process ➢ Mechanical sludge dewatering ➢ Sludge holding area

113. The SBR based STP will require uninterrupted power supply for operation of all the

activities from inlet to treatment, and for sludge dewatering. Disruption in power supply will lead to process upset, may affect the efficiency of treatment, and result in treated effluent quality not meeting the disposal standards. Following measures are integrated into design and contracts to ensure efficient operation:

➢ Ensuring continuous uninterrupted power supply, including a back-up facility (such as

generator) ➢ Providing operating manual with all standard operating procedures (SOPs) for

operation and maintenance of the facility, this should include guidance on the follow up actions in case of process disruptions, inferior quality of treated water; etc.

➢ Necessary training (hands-on and class room / exposure visits) shall be provided to the ULB staff dealing with STP.

➢ Extended contract period for O & M, proper transfer of facility to ULB Anjad after compltetion of contract period with adequate technical know-how on O & M and hands-on training to ULB staff.

➢ Design should include online monitoring for at the minimum BOD, pH and Ammonia

Page 101: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

100

at the inlet and outlet of the plant. ➢ Design should include provision for automated shutdown in the incidence of high

BOD (above design capacity) entering the plant. ➢ Prohibit/prevent disposal of wastewater/effluent from industrial units in the sewers;

ensure regular checking to ensure no illegal entry of industrial wastewater into sewers

114. Proposed STP site is located away from the developed area of the town. Site is surrounded mostly by agricultural lands. The proposed STP site is located on outskirts of the town away from human settlement approximately about 500 m away from the habitation.

115. Site selected for IPS is located on the bank of Susad River near Susad Mohalla. Although, a temple, government middle school and community hall is reported in the proximity of Susad Mohalla but proposed site of IPS is away from these receptors. It is about 50m away and as well as back side of the built up area.

116. STP site selection and justification: There are many parameters which require careful and judicious selection before setting off for the actual design of STP. The STP has been proposed after due consideration to the existing landuse of the site. Issues has been investigated befor final selection include Govt. land availability, topography, drainage, surface/ground water, wind direction, power and water supply, accebility, disposal of effluent, ecosystem and local landuse. Site selected for STP is located on the outskirts of the Anjad town away from human settlement on the right hand side of existing road at a distance of 500 m away from habitation. There is no notable development within 500 m of STP site boundary. Some brick kiln works is going on within 200-500m from its premises by local people. Site is curently vacant, and is owned by Revenue Department, GoMP. Total land area required is 0.5 Hectare. Availbe land area is 13.86 hectare (khasra No. 526), which is sufficient for setting up of STP. STP is located on the higher elevation and on upstream side of Bhongli Nala. It is because of non-availability of govt. land. Efforts have been made to conceptualize scheme with STP towards north of town (between the Town and River Narmada), but there are highly fertile agricultural fields towards Narmada River. These agricultural fields are private lands andno government land available. Therefore, STP site is identified based on the government land availability on the south of the town, and scheme is designed accordingly. Proposed STP site is located on the outskirts of the town, about 500 m away from habitation and surrounded by agricultural fields. Treated wastewater from STP will be disposed into a local drain near STP that flows into Bhongli Nalla, which ultimately flows into Narmada river, about 15 km from the STP site..

117. Odour nuisance. SBR process being an aerobic process and conducted in a compacted and a closed system with automated operation, odour nuisance will be very minimal. However, limited bad odours will be generated from wet well, primary treatment units and sludge treatment. To mitigate this impact, development of physical separation and visual screen around the facility is recommended. Adequate green buffer zone in the form of landscaping and earth work shall be created around the STP. Besides operating the plant as per the standard operating procedures, which will further minimize the odour potential, the following measures are also included in the site planning and design:

➢ Providing a green buffer zone of all around the STP as per availability of land; atleast 20-30 m width of buffer zone with trees in multi-rows and landscaping. This will act as

Page 102: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

101

a visual screen around the facility and will improve the aesthetic appearance. ➢ Providing high compound wall around the STP ➢ Develop the STP layout plan such that STP units with maximum odour generating

potential are located farthest from the nearest development; in layout design, develop office or other such facilities towards the habitation.

118. Treaed wastewater disposal. From the STP treated wastewater will be discharged

into a drain which carries rain water during the monooon. This drain after traversing about 1.6 km joins Bongli Nalla. Bongli nala is a major storm water drain that primarily intended for carrying rain water, however, due to lack of sewerage system in the town, this nala is catering to untreated sewage and sullage from the town. At present this nala, except during monsoon, carries wastewater and joins River Narmada 12 km downstream of Anjad Town. The total distance of Narmada River discharge point from STP is about 15 km (drain / nala length). Provision of sewerage system including treatment facility will avoid disposal of untreated sewage into River Narmada. Given the SBR technology for treatment and stringent discharge standards, there are no significant impacts envisaged due to disposal of treated wastewater into Narmada. Treated wastewater discharges in to River Narmada after flowing for about 15 km from STP discharge point. Folllowing design measures are included: ➢ Proper drainage system shall be made as part of STP design to avoid flooding/water

accumulation from uphill areas, and to channel off the upstream flow into downstream drains without any hindrance

➢ Repair and rehabilitate the 1.6 km length drain, if required, to receive treated wastewater from STP and convey it to Bhongli Nala safely;

➢ Provision for installation of screens as barrier nets on Bhongli Nala to prevent solid waste disposal into nala

➢ Create awareness in the town on to prevent dumping of solid waste into drains

119. Sewage sludge generally consists of organic matter, pathogens, metals and micro pollutants. The concentration of parameters such as metals can be influenced by input to the sewers system from industry. Since no industrial wastewater is allowed into sewers, it is unlikely that sludge contains heavy metals. The sludge from reactors will be collected in sludge sump and conveyed to centrifuge for dewatering. The sludge in the form of a wet cake will be further air-dried in the sludge drying beds. The treatment and drying processes kill enteric bacteria and pathogens, and because of its high content of nitrates, phosphates and other plant nutrients the sludge is an excellent organic ferti lizer for application to the land. Adequate drying is however necessary to ensure maximum kill of enteric bacteria. To achieve adequate drying minimum drying period (15 days) shall be ensured. The drying period, which will be varying depending on the season will be determined during operation and be followed. A sludge management plan will be developed by the DBO Contractor. Sludge shall be periodically tested for presence of heavy metals. Proper sludge handling methods should be employed. Personal Protection Equipment should be provided to the workers.

120. Dried and properly composted sludge can be used as soil conditioner. Periodic testing of dried sludge will be conducted to ensure that it does not contain heavy metals that make it unsuitable for food crops. Tests will be conducted to confirm the concentrations below the following standards. As there are no specific standards notified for sludge reuse, the compost quality standards notified under the Solid Waste Management Rules,

Page 103: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

102

2016 have been adopted here. Rules stipulate that “In order to ensure safe app lication of compost, the following specifications for compost quality shall be met”. Refer Table-17.

121. Sewage Pumping stations. It is proposed to construct 2 sewage pumping stations i.e IPS & MPS, which will receive sewage from the catchment area and pump to STP. IPS and MPS are located at lowest point where the sewage from catchment area can be collected by gravity, and then pumped to a higher level, and ultimately to the STP. SPS will consists of inlet chamber with screen; a sewage sump or wet well of dia 5 m and 4.9 m to 5.5 m deep, to receive sewage; pump room. A generator set will also be provided at each SPS as standy power.

122. SPS operation involves accumulation of incoming sewage wey well, and then pumping

out as the sewage level reaches the designed pumping depth. Water level in the well rises before the pumping cycle starts, and as the pumping is performed the water level goes down, registering its lowest depth at the end of pumping cycle. This cycle of rising and lowering will continue throughout the day and night, however, the duration between successive pumping cycles will significantly vary depending on the sewage generation. During morning and evening peak hours, sewage will accumulate quickly, and pumping frequency will be high. The sewage retention time in the suction well therefore varies throughout the day, with very high retention periods during the nights and mid-days.

123. Odour from pump stations. In the suction wells, the sewage emits gases, which

accumulated in the air above water surface. The gas may include odourous compounds like hydrogen sulphides (H2S), amines, fatty acids, aldehydes, ketones and other volatile organic compounds (VOCs). As the water level rises before the pumping cycle, it physically displaces the air, along with the odourous gas compounds. H2S is the most dominant odour causing compound, and therefore can cause nuisance to nearby households. When sewage becomes stagnant, H2S is generated in the anaerobic conditions. The quantum of H2S generation depend on quantity of accumulated sewage and sewage retention time that create anaerobic conditions. Both increase in quantity of sewage accumulation and retention time will increase the H2S generation. Design considerations will be included to minimize the both as much as possible. The retention time will be kept to its lowest possible so that there is no stagnation of sewage for long time which could create anaerobic conditions.

124. Sites for pumping stations were identified based on the technical suitability and

availability of government owned land parcels to avoid land acquisition. As far as possible sites away from inhabited areas are selected. Site selected for IPS is located on the bank of Susad River near Susad Mohalla. A temple, government middle school and community hall located at about 50m away from IPS site and as well as back side of the built up area. Maximum buffer towards temple and school should be maintained utilized the available land, and by planning of IPS units away from school and temple. There is no notable development within 50m of MPS site boundary. Following mesures needs to be included in the layout design of the SPS to minimize nuisance to surrounding areas:

Layout planning related measures

➢ Locate wet wells within the identified site at an internal location as far as possible from

nearest development; ➢ Providing 20-30 m wide green buffer zone around the IPS and MPS (with maximum

Page 104: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

103

towards temple and school) with a combination of tall and densely growing trees in multi rows as per the land availability to control odour and also act as visual shield and improve aesthetical appearance.

➢ Layout plan of IPS/MPS shall be devised in such a way that it will be farthest from temple, school and habitation, so there will be no impacts envisaged due to odour to the nearby residents; ensure that maximum available distance is maintained to sump /wet well (Temple and school in case of IPS); this will increase the buffer distance of sump /wet well to nearby schook / temple from the existing 50 m from the boundary.

➢ Provide high compound wall around pumping stations

Design related measures to prevent and control odour

➢ Submersible sewage pumps of suitable rating, minimum submergence requirements ➢ Position of the submersible pumps and design of the wet well floor by providing

necessary side benching / sloped flooring to allow for higher submergence during low flow shall be made to ensure regular pump operation and avoid sewage stagnation beyond the permissible limit.

➢ Diesel Generators shall be provided as standby power supply ➢ Develop standard operating procedures / operational manual for operation and

maintenance SPS; this shall include emergency measures ➢ Provide training to the staff in SOPs and emergency procedures

125. Noise from pumping operations. Operation of pumps and motors and diesel

generators is a major source of noise. Noise generated from lifting/pump stations can have continuous negative impacts on the surrounding population. Pumping stations are located within the town but on the outer area of the town. Although STP is located outside the Town, noise control measures are necessary. High inside noise levels can affect the health of operators and staff at the facilities, and therefore, noise levels needs to be maintained within and outside the facilities at acceptable levels. Internal noise level in a room measured at a distance of 1m from these pump sources typically will be in the range from 80 dB(A) to 100 dB(A).

➢ Procure good quality latest technology high pressure pumps that guarantee controlled

noise at a level of around 80 dB(A) at a distance of 1 m ➢ Use appropriate building materials and construction techniques for pump houses which

can absorb sound rather than reflect noise ➢ Use acoustic enclosures – manufacturer specified, for all pumps, motors ➢ Procure only CPCB approved generators with low emission and low noise fitted with

acoustic enclosures ➢ Provide sound mufflers for ventilators in the plant rooms; and sound proof doors ➢ Provide ear plugs to workers

126. Energy Efficiency. Project area is mostly plain and gently sloping ground, it is therefore

not technically feasible or economical to design a completely gravity system to collect sewage from individual houses and transfer the same the STP on the outskirts of the town. It necessitated provision of pumping stations, which are optimized to the extent possible to minimize the overall pumping. In the current design, sewage will be collected from the houses via sewer network and conveyed by gravity to the pumping stations. To optimize the power consumption, the hydraulic design shall follow optimal approach, and the following

Page 105: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

104

also to be considered in design and selection of pumping systems. According to Manual for the Development of Municipal Energy Efficiency Projects in India (jointly developed by Beaurau of Energey Efficiency (BEE) and International Finance Corporation in 2008), energy savings, at minimum, of 25% to 40% is possible with appropriate measures. The following measures shall be considered and incorporated into the subproject designs:

➢ Using low-noise and energy efficient pumping systems ➢ Efficient Pumping system operation ➢ Installation of Variable Frequency Drives (VFDs)

127. Sewer network. Following design considerations are to be included in sewer network planning and design: ➢ Limit the sewer depth where possible. ➢ Sewers shall be laid away from water supply lines and drains (at least 1 m, wherever

possible); ➢ In all cases, the sewer line should be laid deeper than the water pipeline (the

difference between top of the sewer and bottom of water pipeline should be atleast 300mm)

➢ In unavoidable, where sewers are to be laid close to storm water drains or canals or natural streams, appropriate pipe material shall be selected (stoneware pipes shall be avoided)

➢ For shallower sewers, use small inspection chambers in lieu of manholes; ➢ Design manhole covers to withstand anticipated loads & ensure that the covers can

be readily replace if broken to minimize silt/garbage entry ➢ Ensure sufficient hydraulic capacity to accommodate peak flows & adequate slope in

gravity mains to prevent buildup of solids and hydrogen sulfide generation ➢ Equip pumping stations with a backup power supply, such as a diesel generator, to

ensure uninterrupted operation during power outages, and conduct regular maintenance to minimize service interruptions. Consider redundant pump capacity in critical areas

128. Utilities: Telephone lines, electric poles and wires, water lines within the proposed

project locations may require to be shifted in few cases. To mitigate the adverse impacts due to relocation of the utilities, the contractor, in collaboration with ULB will (i) identify the locations and operators of these utilities to prevent unnecessary disruption of services during construction phase; and (ii) instruct construction contractors to prepare a contingency plan to include actions to be done in case of unintentional interruption of services.

129. Site selection of construction work camps, stockpile areas, storage areas, and

disposal areas: Priority is to locate these near the project location. However, if it is deemed necessary to locate elsewhere, sites to be considered will not promote instability and result in destruction of property, vegetation, irrigation, and drinking water supply systems. Residential areas will not be considered for setting up construction camps to protect the human environment (i.e., to curb accident risks, health risks due to air and water pollution and dust, and noise, and to prevent social conflicts, shortages of amenities, and crime). Extreme care will be taken to avoid disposals near forest areas, water bodies, or in areas which will

130. Site selection of sources of materials: Significant quantities of coarse aggregate

Page 106: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

105

and fine aggregate will be required for construction works. Requirement of gravel is limited. Contractor should procure these materials only from the quarries permitted/licensed by Mines and Geology Department. Contractor should, to the maximum extent possible, procure material from existing quarries, and creation of new quarry areas should be avoided as far as possible. It will be the construction contractor ’s responsibility to verify the suitability of all material sources and to obtain the approval of Department of Mines & Geology and local revenue administration.

B. Construction Impacts

1. Construction Works

131. The works are spread over entire town, and therefore the implementation of the

project will affect a significant proportion of the town as branches of the new sewerage network will be built alongside almost all roads and streets. Areas outside the town will also be affected, by construction of the SPS and STP. However, it is not expected that the construction work will cause major negative impacts, mainly because:

• Sewer network will be built on unused ground alongside existing roads and can be

constructed without causing major disruption to road users and any adjacent houses, shops and other businesses;

• SPS and STP will be located on government-owned land that is not occupied or used for any other purpose;

• Most network construction will be conducted by small teams working on short lengths at a time so most impacts will be localized and short in duration; and

• The overall construction programme will be relatively short for a project of this nature, and is expected to be completed in 2 years.

132. STP Construction Works: STP will involve construction of:

• Raw Sewage Pumping Station • Pre-treatment works like inlet chamber, Fine Screen channels De gritting Tanks Flow

measuring Channel and Flow distribution box • Sewage Treatment Plant based on SBR Technology • Treated Effluent Disposal Works

133. SPS Construction Works: SPS will involve construction of:

• Inlet and screen chamber • Wet well • Pump room and diesel generator platform

134. The STP and SPS works will be confined to sites, and construction will include

general activities like excavation for foundation, construction of foundations, columns, walls and roof in cement concrete and masonry, and fixing of mechanical and electrical fixtures, etc. SBR technology STP will involve several mechanical and electrical components which will be brought to site, assembled and installed.

135. Sewer laying works: This works involves construction of following compoents:

Page 107: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

106

• 23055 m secondary and tertiary network; pipes will be of small diameter (100 to 400 mm); will be located in trenches along side roads (average width 1.10 to 1.350 m and depth 1.0 to 6.99 m)

• 2,340 m Pumping mains; pipes will be 100 mm to 300 mm in diameter; and will be located in trenches along side roads (average width 1.10 to 1.40 m and depth 1.350 to 1.50 m)

136. Most pipes will be buried in trenches immediately adjacent to roads, in the un-used

area within the ROW, alongside the edge of the tarmac. The main and secondary sewers will be located alongside main roads, where there is generally more than enough free space to accommodate the pipeline. However, in parts of the tertiary network where roads are narrow, this area is occupied by drains or the edges of shops and houses etc., so the trenches may have to be dug into the edge of the road.

137. Trenches will be dug by backhoe digger, supplemented by manual digging where

necessary. Excavated soil will be placed nearby, and the pipes (brought to site on trucks and stored on unused land nearby) will be placed in the trench by crane or using a small rig. After the pipes are joined, loose soil will be shoveled back into the trench, and the surface layer will be compacted by hand-operated compressor.

138. At intervals, manholes will be constructed to allow inspection and clearance of

blockages and sediment during operation. These will be excavated by backhoe or manually. Manholes will be constructed in brick masonry or RCC.

139. As noted above, some of the narrower roads are constructed of concrete and have no

available space at the edge because of the presence of drains, or shop- and house-fronts encroaching into the ROW. In these places it may be necessary to break open the surface of the road using hand-held pneumatic drills, after which the trench and pipeline will be constructed as described above. On completion, a concrete layer will be re-applied to the surface to repair the road.

140. Anticipated impacts during the construction phase are discussed below along with appropriate mitigation measures to avoid, minimize or mitigate those impacts to acceptable levels.

2. Construction Impacts

141. Sources of Materials. Significant amount of sand and coarse aggregate will be

required for this project, which will be sourced from quarries. Quarries inevitably cause extensive physical changes; as construction materials are excavated from the ground, leaving large cavities, or levelling hillsides, etc. The physical damage caused by quarries is controlled by allowing them to operate within specific limited areas only, so the damage is restricted in extent and not allowed to spread indiscriminately. New quarries are subject to a rigorous process of environmental assessment to ensure appropriate siting and adequate environmental controls on the operation. It will therefore be important to ensure that construction materials for this project are obtained from government approved licensed quarries only, to ensure these controls are in place. In Anjad, construction sand is normally obtained from Narmada river (about 5 km), and gravel and aggregate from Barwani or nearby quary site (about 17km). Contractor should avoid new borrow pits / quarries as far as possible, if necessary, all the permissions, including conduct of environmental

Page 108: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

107

assessment, and environmental clearance as necessary shall be obtained prior to start of quarrying activity. The contractor should also make a concerted effort to re-use as much excavated material from this project as possible. The construction contractor will be required to:

(i) Obtain construction materials only from government approved quarries with prior

approval of PIU (ii) PIU to review, and ensure that proposed quarry sources have all necessary

clearances/ permissions in place prior to approval (iii) Contractor to submit to PIU on a monthly basis documentation on material

obtained from each sources (quarry/ borrow pit) (iv) Avoid creation of new borrow areas, quarries etc., for the project; if unavoidable,

contractor to obtain all clearances and permissions as required under law, including Environmental Clearance (EC) prior to approval by PIU

142. Air Quality. Construction work, especially from earthwork activities, coupled with dry

and windy working conditions, material and debris transport, and works along the public roads carrying significant traffic, have high potential to generate dust. Significant quantities of earthwork will be conducted in the subproject, spread all over the project area. 95% of the excavated soil will be reused for filling the trenches. Also, emissions from construction vehicles, equipment, and machinery used for excavation and construction will induce impacts on the air quality. Anticipated impacts include dust and increase in concentration of vehicle-related pollutants such as carbon monoxide, sulfur oxides, particulate matter, nitrous oxides, and hydrocarbons. Dust generation from construction work in individual and confined work sites like STP, pumping stations etc., will be mainly during the initial construction phase of earth work, as the site is confined, dust can be effectively controlled with common measures. While pumping and lifting stations are located within residential neighbourhoods, STP is located outside the town, away from habitation area. Dust generation will be significant during sewer laying along the roads. Increase in dust/ particulate matter in ambient air is detrimental and may have adverse impacts on people and environment. To mitigate the impacts, construction contractors will be required to:

For all construction works

(i) Provide a dust screen around SPS and STP worksites (ii) Damp down the soil and any stockpiled material on site by water sprinkling; (iii) Stabilize surface soils where loaders, support equipment and vehicles will operate

by using water and maintain surface soils in a stabilized condition (iv) Apply water prior to levelling or any other earth moving activity to keep the soil

moist throughout the process (v) Cover the soil stocked at the sites with tarpaulins (vi) Control access to work area, prevent unnecessary movement of vehicle, public

trespassing into work areas; limiting soil disturbance will minimize dust generation (vii) Use tarpaulins to cover the loose material (soil, sand, aggregate etc.,) when

transported by open trucks; (viii) Control dust generation while unloading the loose material (particularly aggregate,

sand, soil) at the site by sprinkling water and unloading inside the barricaded area (ix) Clean wheels and undercarriage of haul trucks prior to leaving construction site

Page 109: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

108

(x) Ensure that all the construction equipment, machinery are fitted with pollution control devises, which are operating correctly, and have a valid pollution under control (PUC) certificate

For sewer works

(i) Barricade the construction area using hard barricades (ii) Initiate site clearance and excavation work only after barricading of the site is done (iii) Confine all the material, excavated soil, debris, equipment, machinery (excavators,

cranes etc.,), to the barricaded area (iv) Limit the stocking of excavated material at the site; remove the excess soil from

the site immediately to the designated disposal area (v) Undertake the work section wise; and conduct work sequentially - excavation,

sewer laying, backfilling; testing section-wise (for a minimum length as possible) so that backfilling, stabilization of soil can be done.

(vi) Remove the excavated soil of first section to the disposal site (vii) Backfilled trench at any completed section after removal of barricading will be the

main source of dust pollution. The traffic, pedestrian movement and wind will generate dust from backfilled section. Road restoration shall be undertaken immediately.

143. Surface Water Quality. Run-off from stockpiled materials and chemicals from fuels and

lubricants during construction works can contaminate water quality of the receiving water bodies and streams/rivers. There are ponds and two rivers in the project area, which mostly drains into the Foota Talab, Bhongli Nala (initially Bongli Nala was the Bhagwati river or Bhongli river, later due to the encroachment and pollution it got converted into the Bhongli Nala) and into Susad River. it is important that runoff from the construction areas, which may contain silt and chemical traces do not enter the river and the water bodies. Impact will be temporary, and but needs to be mitigated. Construction contractor will be required to:

(i) All earthworks be conducted during the dry season to prevent the problem of

soil/silt run-off during rains (ii) Avoid stockpiling of earth fill especially during the monsoon season unless

covered by tarpaulins or plastic sheets; (iii) Prioritize re-use of excess spoils and materials in the construction works. If spoils

will be disposed, only designated disposal areas shall be used; (iv) Install temporary silt traps or sedimentation basins along the drainage leading to

the water bodies; (v) Place storage areas for fuels and lubricants away from any drainage leading to

water bodies; (vi) Store fuel, construction chemicals etc., on an impervious floor, also avoid spillage

by careful handling; provide spill collection sets for effective spill management (vii) Dispose any wastes generated by construction activities in designated sites; and (viii) Conduct surface quality inspection according to the Environmental Management

Plan (EMP). 144. Surface and Groundwater Quality. Another physical impact that is often associated

with excavation is the effect on drainage and the local water table if groundwater and surface water collect in the voids. In the project area, groundwater table is much deeper than the anticipated excavation depth and therefore this impact is not envisaged. However,

Page 110: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

109

during the rains, water will be collected in open pits and trenches. The water collected in excavated pits will contain silt and disposal of this in drainage channels lead to silting. To avoid this the contractor needs to be implement the following measures:

(i) As far as possible control the entry of runoff from upper areas into the excavated

pits, and work area by creation of temporary drains or bunds around the periphery of work area

(ii) Pump out the water collected in the pits / excavations to a temporary sedimentation pond; dispose off only clarified water into drainage channels/streams after sedimentation in the temporary ponds

(iii) Consider safety aspects related to pit collapse due to accumulation of water 145. Generation of Construction Wastes. Solid wastes generated from the construction

activities are excess excavated earth (spoils), discarded construction materials, cement bags, wood, steel, oils, fuels and other similar items. Domestic solid wastes may also be generated from the workers’ camp. Improper waste management could cause odor and vermin problems, pollution and flow obstruction of nearby watercourses and could negatively impact the landscape. 95% of the excavated soil will be reused, and the remaining soil needs to be disposed safely. The following mitigation measures to minimize impacts from waste generation shall be implemented by the contractor:

(i) Prepare and implement a Construction Waste (Spoils) Management Plan (ii) As far as possible utilize the debris and excess soil in construction purpose, for

example for raising the ground level or construction of access roads etc., (iii) Avoid stockpiling any excess spoils at the site for long time. Excess excavated

soils should be disposed off to approved designated areas immediately (iv) If disposal is required, the site shall be selected preferably from barren, infertile

lands; sites should have located away from residential areas, forests, water bodies and any other sensitive land uses

(v) Domestic solid wastes should be properly segregated in biodegradable and non-biodegradable for collection and disposal to designated solid waste disposal site; create a compost pit at worker’s camp sites for disposal of biodegradable waste; non-biodegradable / recyclable material shall be collected separately and sold in the local recycling material market

(vi) Residual and hazardous wastes such as oils, fuels, and lubricants shall be disposed off in disposal sites approved by MPPCB;

(vii) Prohibit burning of construction and/or domestic waste; (viii) Ensure that wastes are not haphazardly thrown in and around the project site;

provide proper collection bins, and create awareness to use the dust bins. (ix) Conduct site clearance and restoration to original condition after the completion

of construction work; PIU to ensure that site is properly restored prior to issuing of construction completion certificate

146. Noise and Vibration Levels. Components are located within urban area, where there are houses, schools and hospitals, religious places and businesses in the surrounding area. The sensitive receptors are the general population in these areas. Increase in noise level may be caused by excavation, particularly breaking of cement concrete or bitumen roads for laying of sewers, operation of construction equipment, and the transportation of equipment, materials, and people. Vibration generated from construction activity, for instance from the use of pneumatic drills, will have impact on nearby buildings. This impact

Page 111: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

110

is negative short-term, and reversible by mitigation measures. The construction contractor will be required to:

(i) Plan activities in consultation with PIU so that activities with the greatest potential

to generate noise are conducted during periods of the day which will result in least disturbance;

(ii) Minimize noise from construction equipment by using vehicle silencers, fitting jackhammers with noise-reducing mufflers, and use portable street barriers to minimise sound impact to surrounding sensitive receptor; and

(iii) Maintain maximum sound levels not exceeding 80 decibels (dBA) when measured at a distance of 10 m or more from the vehicle/s.

(iv) Identify any buildings at risk from vibration damage and avoiding any use of pneumatic drills or heavy vehicles in the vicinity;

(v) Horns should not be used unless it is necessary to warn other road users or animals of the vehicle’s approach;

(vi) Consult local communities in advance of the work to identify and address key issues, and avoid working at sensitive times, such as religious and cultural festivals.

147. Accessibility and Traffic Disruptions. Excavation along the roads for laying of

sewers, hauling of construction materials and operation of equipment on-site will cause traffic problems. Main roads carrying traffic in the subproject area include the following:

• List road names that carry significant traffic in town is SH-26: Refer Drawing given below for road Network.

• Hospital Chauraha • Bus Stand • Library Chauraha • Sarafa Market • Jata Shankar Churaha • Shri Krishna Chauraha

Road Surface & Problematic Area

Page 112: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

111

Details of Diameter Wise Proposed Trench Width & Depth

Pipe

Diameter

Length of

Sewer (m)

Min. Depth

(m)

Max. Depth

(m)

Min. Trench

Width (m)

Max. Trench

Width (m)

Zone 1

135 68024 1.0 4.76 1.0 3.0

Zone 2

100 2976.9 1.0 5.41 1.0 3.346

135 10942.8 1.0 6.145 1.0 3.82

170 1154.4 1.0 6.74 1.0 4.2

250 986.2 2.29 6.99 1.7 4.45

400 178.6 3.35 5.06 2.5 3.5

148. Internal roads in the town are very narrow. Traffic movement will be mostly disrupted.

Works related to all the remaining components (pumping stations and STP) will be confined to the selected sites, therefore there is no direct interference of these works with the traffic

Page 113: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

112

and accessibility. Hauling of construction material, equipment, construction waste, etc., to and from the work site may increase the road traffic on local roads. This will further inconvenience the local community and road users. Potential impact is negative but short term and reversible by mitigation measures. The construction contractor will be required to:

Sewer works

(i) Prepare a sewer work implementation; ensure that for each road where the work is being undertaken there is an alternative road for the traffic movement; take up the work in sequential way so that public inconvenience is minimal

(ii) Provide temporary diversions, where necessary and effectively communicate with general public

(iii) Undertake the work section wise (iv) Confine work areas in the road carriageway to the minimum possible extent; all

the activities, including material and waste/surplus soil stocking should be confined to this area.

(v) Proper barricading should be provided; avoid material/surplus soil stocking in congested areas – immediately removed from site/ or brought to the as and when required

(vi) Limit the width of trench excavation as much as possible by adopting best construction practices; adopt vertical cutting approach with proper shoring and bracing; this is especially to be practiced in narrow roads and deeper sewers; if the deep trenches are excavated with slopes, the roads may render completely unusable during the construction period

(vii) Leave spaces for access between mounds of soil to maintain access to the houses / properties; access to any house or property shall not be blocked completely; alternative arrangements, at least to maintain pedestrian access at all times to be provided

(viii) Provide pedestrian access in all the locations; provide wooden/metal planks over the open trenches at each house to maintain the access.

(ix) Inform the affected local population 1-week in advance about the work schedule (x) Plan and execute the work in such a way that the period of disturbance/ loss of

access is minimum. (xi) Keep the site free from all unnecessary obstructions; (xii) Notify affected public by public information notices, providing sign boards

informing nature and duration of construction works and contact numbers for concerns/complaints. Provide information to the public through media – newspapers and local cable television (TV) services

(xiii) At work site, public information/caution boards shall be provided including contact for public complaints

Hauling (material, waste/debris and equipment) activities

(i) Plan transportation routes so that heavy vehicles do not use narrow local roads,

except in the immediate vicinity of delivery sites (ii) Schedule transport and hauling activities during non-peak hours; (iii) Drive vehicles in a considerate manner (iv) Notify affected public by public information notices, providing sign boards

informing nature and duration of construction works and contact numbers for concerns/complaints.

Page 114: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

113

149. Socio-Economic – Income. Sites for all projects components are carefully selected in

government owned vacant lands and therefore there is no requirement for land acquisition or any resettlement. Blocking of access to the business / livelihood activities, especially during pipeline laying along the roads, may impact the income of households. Some shops and other premises along the roads may lose business income if the access will be impeded by excavation of trenches. Access disruption to socio cultural places will inconvenience public. Implementation of the following best construction measures will avoid the disturbance reduce the inconvenience and disturbance to the public. Resettlement and social issues are being studied in a parallel resettlement planning study of this subproject.

(i) Inform all businesses and residents about the nature and duration of any work

well in advance so that they can make necessary preparations; (ii) Do not block any access; leave spaces for access between barricades/mounds

of excavated soil and other stored materials and machinery, and providing footbridges so that people can crossover open trenches

(iii) Barricade the construction area and regulate movement of people and vehicles in the vicinity, and maintain the surroundings safely with proper direction boards, lighting and security personnel – people should feel safe to move around

(iv) Control dust generation (v) Immediately consolidate the backfilled soil and restore the road surface; this will

also avoid any business loss due to dust and access inconvenience of construction work.

(vi) Employee best construction practices, speed up construction work with better equipment, increase workforce, etc., in the areas with predominantly commercial, and with sensitive features like hospitals, and schools;

(vii) Consult businesses regarding operating hours and factoring this in work schedules; and

(viii) Provide sign boards for pedestrians to inform nature and duration of construction works and contact numbers for concerns/complaints.

150. Socio-Economic – Employment. Manpower will be required during the 24-months

construction stage. This can result in generation of temporary employment and increase in local revenue. Thus, potential impact is positive and long-term. The construction contractor will be required to:

(i) Employ local labour force as far as possible

151. Occupational Health and Safety. Workers need to be mindful of the occupational

hazards which can arise from working in confined areas such as trenches, working at heights, near the heavy equipment operating areas etc., Deep trenches will be excavated for laying sewers (maximum depth 6.9 m), given narrow roads and works in urban area, these confirned spaces will be pose considerable safety risk to workers and as well as the surrounding structures and community. Potential impacts are negative and long-term but reversible by mitigation measures. The construction contractor will be required to:

(i) Comply with all national, state and local labour laws (see Appendix 6);

Page 115: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

114

(ii) IFC’s General EHS Guidelines3 and Sector Specific (Water and Sanitation) Guidelines4

(iii) Develop and implement site-specific Occupational Health and Safety (OHS) Plan which shall include measures such as: (a) safe and documented construction procedures to be followed for all site activities; (b) ensuring all workers are provided with and use personal protective equipment; (c) OHS Training5 for all site personnel, (d) excluding public from the work sites; and (e) documentation of work-related accidents; Follow International Standards such as the World Bank Group’s Environment, Health and Safety Guidelines6.

(iv) Ensure proper safety measures during trench excavation; provide bracing / shoring in all trenches of more than 1.5 m deep; no overburden soil, material, equipment etc., shall be placed along the deep trenches; safety training shall be provided to workers; where required provide supports anchors or suitable arrangement to nearby building to avoid any safety risk

(v) Ensure that qualified first-aid is provided at all times. (vi) Secure all installations from unauthorized intrusion and accident risks (vii) Provide health and safety orientation training to all new workers to ensure that

they are apprised of the basic site rules of work at the site, personal protective protection, and preventing injuring to fellow workers;

(viii) Ensure the visibility of workers through their use of high visibility vests when working in or walking through heavy equipment operating areas;

(ix) Ensure moving equipment is outfitted with audible back-up alarms; (x) Mark and provide sign boards for hazardous areas such as energized electrical

devices and lines, service rooms housing high voltage equipment, and areas for storage and disposal. Signage shall be in accordance with international standards and be well known to, and easily understood by workers, visitors, and the general public as appropriate; and

(xi) Disallow worker exposure to noise level greater than 85 dBA for duration of more than 8 hours per day without hearing protection. The use of hearing protection shall be enforced actively.

(xii) Provide supplies of potable drinking water; (xiii) Provide clean eating areas where workers are not exposed to hazardous or

noxious substances

3https://www.ifc.org/wps/wcm/connect/554e8d80488658e4b76af76a6515bb18/Final%2B-

%2BGeneral%2BEHS%2BGuidelines.pdf?MOD=AJPERES 4 https://www.ifc.org/wps/wcm/connect/e22c050048855ae0875cd76a6515bb18/Final%2B-

%2BWater%2Band%2BSanitation.pdf?MOD=AJPERES

5 Some of the key areas that may be covered during training as they relate to the primary causes of accidents

include (i) slips, trips and falls; (ii) personal protective equipment; (iii) ergonomics, repetitive motion, and

manual handling; (iv) workplace transport; and (v) legislation and responsibilities. Training can provide the

foundations of competence but it does not necessarily result in a competent worker. Therefore, it is essential to

assess staff competence to ensure that the training provided is relevant and effective. Supervision and

monitoring arrangements shall be in place to ensure that training has been effective and the worker is

competent at their job. The level of supervision and monitoring required is a management decision that shall be

based on the risks associated with the job, the level of competence required, the experience of the individual

and whether the worker works as part of a team or is a lone worker. 6 http://www.ifc.org/wps/wcm/connect/a99ab8804365b27aa60fb6d3e9bda932/EHS-Guidelines+101-

Webinar.pdf?MOD=AJPERES

Page 116: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

115

152. Community Health and Safety. Sewers works and deep excavations along the roads

and narrow streets and hauling of equipment and vehicles have potential to create safety risks to the community. Deep excavations without any proper protection may endanger the close by buildings. Hazards posed to the public, specifically in high-pedestrian areas may include traffic accidents and vehicle collision with pedestrians. A temple and Govt. Middle school is located close (50 m) from the IPS work site. Proper precautions needs to be taken to confirne the workers operations to the site, so that there is no disturbance or safety risk to the students/childrens.

153. Potential impact is negative but short-term and reversible by mitigation measures. The construction contractor will be required to:

(i) Ensure proper safety measures during trench excavation; provide bracing /

shoring in all trenches of more than 1.5 m deep; no overburden soil, material, equipment etc., shall be placed along the deep trenches; safety training shall be provided to workers; where required provide supports anchors or suitable arrangement to nearby building to avoid any safety risk

(ii) Confine work areas; prevent public access to all areas where construction works are on-going through the use of barricading and security personnel

(iii) Attach warning signs, blinkers to the barricading to caution the public about the hazards associated with the works, and presence of deep excavation

(iv) Contractor shall create awareness and no activities shall be extended outside the site, especially towards the temple & school; enfore strict site rules so that there is no disturbance or safety risk

(v) Minimize the duration of time when the sewer trench is left open through careful planning; plan the work properly from excavation to refilling and road relaying

(vi) Control dust pollution – implement dust control measures as suggested under air quality section

(vii) Ensure appropriate and safe passage for pedestrians along the work sites (viii) Provide road signs and flag persons to warn of on-going trenching activities. (ix) Restrict construction vehicle movements to defined access roads and

demarcated working areas (unless in the event of an emergency) (x) Enforce strict speed limit (20 kmph) for plying on unpaved roads, construction

tracks (xi) At sensitive locations particularly where there are schools and markets close to

the road, awareness of safety issues will be raised through neighbourhood awareness meetings

(xii) All drivers and equipment operators will undergo safety training (xiii) Maintain regularly the construction equipment and vehicles; use manufacturer-

approved parts to minimize potentially serious accidents caused by equipment malfunction or premature failure.

(xiv) Overall, the contractor should comply with IFS EHS Guidelines Community Health and Safety (this can be downloaded from http://www1.ifc.org/wps/wcm/connect/dd673400488559ae83c4d36a6515bb18/3%2Bcommunity%2Bhealth%2Band%2Bsafety.pdf?MOD=AJPERES)

154. Construction Camps. Contractor may require to set up construction camps – for temporary storage of construction material (sewer, cement, steel, fixtures, fuel, lubricants etc.,), and stocking of surplus soil, and may also include separate living areas for migrant

Page 117: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

116

workers. The contractor will however be encouraged to engage local workers as much as possible. Operation of work camps can cause temporary air, noise and water pollution, and may become a source of conflicts, and unhealthy environment if not operated properly. Potential impacts are negative but short-term and reversible by mitigation measures. Provision of proper living facilities and basic amenities (water, sanitation, fire safety, health and safety, etc) shall be ensured.

155. The construction contractor will be required to comply with the following. Overall, the contract should follow the IFC EHS guidelines specific to workers accommodation (this can be downloaded from http://www1.ifc.org/wps/wcm/connect/topics_ext_content/ifc_external_corporate_site/ifc+sustai

n ability/publications/publications_gpn_workersaccommodation).

(i) Consult PIU before locating project offices, sheds, and construction plants; (ii) Select a camp site away from residential areas (at least 100 m buffer shall be

maintained) or locate the camp site within the existing facilities of City Corporation

(iii) Avoid tree cutting for setting up camp facilities (iv) Provide a proper fencing/compound wall for camp sites (v) Camp site shall not be located near (100 m) water bodies, flood plains flood

prone/low lying areas, or any ecologically, socially, archeologically sensitive areas

(vi) Separate the workers living areas and material storage areas clearly with a fencing and separate entry and exit

(vii) Ensure conditions of liveability at work camps are maintained at the highest standards possible at all times; living quarters and construction camps shall be provided with standard materials (as far as possible to use portable ready to fit-in reusable cabins with proper ventilation); thatched huts, and facilities constructed with materials like GI sheets, tarpaulins, etc., shall not be used as accommodation for workers

(viii) Camps shall be provided with proper drainage, there shall not be any water accumulation

(ix) Provide drinking water, water for other uses, and sanitation facilities for employees

(x) Prohibit employees from cutting of trees for firewood; contractor should provide cooking fuel (cooking gas); fire wood not allowed

(xi) Train employees in the storage and handling of materials which can potentially cause soil contamination

(xii) Wastewater from the camps shall be disposed properly either into sewer system; if sewer system is not available, provide on-site sanitation with septic tank and soak pit arrangements

(xiii) Recover used oil and lubricants and reuse or remove from the site; (xiv) Manage solid waste according to the following preference hierarchy: reuse,

recycling and disposal to designated areas; provide a compost pit for bio degradable waste, and non-biodegradable / recyclable waste shall be collected and sold in local market

(xv) Remove all wreckage, rubbish, or temporary structures which are no longer required; and

Page 118: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

117

(xvi) At the completion of work, camp area shall be cleaned and restored to pre-project conditions, and submit report to PIU; PIU to review and approve camp clearance and closure of work site

B. Operation and Maintenance Impacts

156. Operation and Maintenance of the sewerage system will be carried out by DBO

operation for a duration of 10 years, and after which it will be transferred to Anjad Nagar Parishad During the system design life (15/30 years for mechanical/civil components) it shall not require major repairs or refurbishments and should operate with little maintenance beyond routine actions required to keep the equipment in working order. The stability and integrity of the system will be monitored periodically to detect any problems and allow remedial action if required. Any repairs will be small-scale involving manual, temporary, and short-term works involving regular checking and recording of performance for signs of deterioration, servicing and replacement of parts.

157. Operation and Maintenance of Improved Sewerage System: The new sewerage

system will collect and treat all domestic wastewater sewage produced in Anjad town. Septage collected from septic tanks via mobile suction tanked will also treated in the STP along with the sewage collected via sewer network.The treatment technology (SBR) is approved by the Central Public Health and Environmental Engineering Organization (CPHEEO). The proposed design discharge values of SBR based STP treated effluent is much stringent than the standards specificed by the Ministry of Environment, Forest and Climate Change (MOEFCC) for discharge from STPs (Notification dated 13th October 2017 for the discharge of treated sewage from STPs). Comparative values are given in the following table.

Table 25: Proposed Design Effluent Values for STP and Discharge Standards

of MoEFCC S. No. Parameters Design Value for

Anjad SBR STP MoEFCC STP

Discharge Standard 1. Biochemical Oxygen Demand

(BOD5 at 200C) < 10 mg/L 30 mg/L

2. Total Suspended Solis (TSS) < 10 mg/L < 100 mg/L

3. Chemical Oxygen Demand (COD) < 50 mg/L < 50 mg/L

4. Total Nitrogen as N < 10 mg/L < 10 mg/L

5. Ammonical Nitrogen as N < 5 mg/L < 5 mg/L

6. Phosphorous as P < 2 mg/L < 2 mg/L

7. Fecal coliform < 230 MPN/100 ml <1000 MPN/100 ml

158. In SBR technology the odour will be minimal and development of greenbelts in and

around the STP will further minimize the effect. The financial provision has been considered for development of greenbelt.

159. Sewage Treatment Process: An SBR based STP is recommended since SBR technology requires comparatively much less land area with same efficient results as that of extended aeration. The main advantage of the SBR plant is that the effluent shall be of

Page 119: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

118

high quality.

160. Location of Discharge Point and Disposal Method: Treated sewage from STP will be discharged into nearby l drain through outfall sewer pipeline having 580m length of dia 400mm RCC NP3 pipe by gravity system. Drain is at a distance of 580m from proposed STP site, which joins Bhongli Nala after travelling a distance of 1.60 km and then Bhogli Nala after traveling a distance of about 13.4 km joins Narmada river and the final disposal is into Narmada. There is one water intake for Anjad town on upstream side near Dattwada village on Narmada river. STP discharge point into Narmada is in the downstream about 11 km away from intake, (Refer Map annexed as Fig-4 & Fig-29), so there will be no impact on intake due to STP discharge as the discharge point is on on d/s from intake. As the River Narmada is perennial river and flow in the river is adequate to dilute the discharge. There are no water intakes / dams in the downstream river course upto 5-10 km stretch. Water quality of River Narmada is good and is considered as the A grade river. Water samples were collected by the officials of the pollution control board and tested at MPPCB Indore regional office. (Refer Appendix-15).

161. Capacity of natural drain is adequate to take the load, this natural drain passing along agricultural fields connecting to STP site located near foothill of undulating land mass with a large catchment area as shown in google map (Refer Fig-39). Treated effluent is of very small quantity with respect to run-off and as such capacity is adequate to discharge it through this natural drain all over the year. But condition of drain is not very good, proper improvement needs to be carried out upto a stretch of 1.6 km. So, it will be able to transfer treated water to major drain of Anjad town i.e. Bhongli Nala and then to Narmada safely without any flooding or overflowing problem. initially Bongli Nala was the Bhagwati river / Bhongli river, later due to the encroachment and pollution it got converted into the Bhongli Nala. As per existing situation; besides wastewater, solid waste is dumped into Bongla nalla. There are also weekly markets held along the nala, and market waste is dumped into this nallah. To avoid and reduce the impacts of solid waste dumped into the Bhongli Nala, provision for installation of screen as barrier nets to prevent dumping of solid waste is included in EMP (Refer EMP Table 27 & Table 32 in IEE Report). Besides, awareness programs also will be conducted. There will be no environmental concerns, this project will not deteriote the environment, it will further improve the environment. Given the high-quality treatment process SBR based treatment plant & output quality more stringent than the STP disposal standards and flowing for 15 km prior to meeting river, there is no impacts envisaged on River Narmada. Regular monitoring will be conducted to check the treatment quality. Baseline water quality of Bhongli Nala will be established during the detailed design stage by DBO Contractor. Proposed STP site is located at the fringe area of subproject town and agricultural fields are reported in and around of STP site, therefore treated water may be utilized by local farmers . Treated water can not be used for food crops that eaten raw or uncooked. It is pertinent to mention that it is a tentative one and it has to be finalized based on detailed investigation by DBO contractor once contract will be awarded. Accordingly, IEE and EMP will be further modified and finalized.

162. Sludge Management (Collection, Treatment and Disposal /Reuse): Sewage sludge generally consists of organic matter, pathogens, metals and micro pollutants. The concentration of parameters such as metals can be influenced by input to the sewers system from industry. However, there are no industries with problematic wastewater discharges in the catchment area of the proposed wastewater treatment plant. Most importantly, as provided above, no industrial discharges are allowed into municipal sewer

Page 120: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

119

system.

163. At the STP sewage sludge will need to be removed from the active treatment plant periodically. This is a simple process that which require a Sludge Management Plan. Calculations conducted by the design engineers show that 796 kg/day of dry sludge is to be generated. Sludge will be allowed to dry out naturally and the solid sludge is removed by mechanical digging.

164. Sludge Dewatering System: Sludge Dewatering System shall consist of the following: • Sludge Sump and Thickener Feed Pump House

• Sludge Thickener (Gravity)

• Thickened Sludge Sump and Centrifuge Feed pumps

• Centrifuge & Polyelectrolyte Dosing System

165. Excess Sludge from SBR Basins shall be withdrawn through Sludge Withdrawal System and collected in the Sludge Sump. A Sludge Sump and Pump House shall be provided for collection and transfer of sludge from SBR Reactors to sludge thickener. The thickener shall be provided to thicken sludge (solids concentration to 4%). The thickened sludge shall be collected in a sump from where it shall be pumped to centrifuge for dewatering using positive displacement type Screw Pumps. Dewatering Polyelectrolyte Dosing System comprising one Solution Preparation tank and One Solution Dosing Tank with agitators equipped with slow speed Mixers and mechanically actuated diaphragm type Metering Pumps shall be provided to enhance the dewatering efficiency of centrifuge and to dose Dewatering Polyelectrolyte Solution online. The dewatered sludge in the form of wet cake from Centrifuges shall be collected and transported by trucks for disposal off to sanitary landfills site in Anjad or for use as manure on agricultural land. whereas Concentrate shall be collected into a Concentrate Tank and recycled to the Inlet Chamber. Drying of sludge inside the STP premises in Sludge storage platform.

166. The sludge from SBR basins will be collected into sludge sump and conveyed to centrifuge unit for dewatering the same. The necessary centrifuge feed pumps & centrifuge will be provided. The sludge in the form of a wet cake will be further air-dried in the sludge drying beds and disposed off at sanitary landfill site in Anjad town. The treatment and drying processes kill enteric bacteria and pathogens, and because of its high content of nitrates, phosphates and other plant nutrients the sludge is an excellent organic fertilizer and farmers are normally allowed to remove the dry material for application to their land. Adequate drying is however necessary to ensure maximum kill of enteric bacteria. To achieve adequate drying minimum drying period (days) shall be ensured. The drying period, which will be varying depending on the season, shall be determined during detailed design. The sludge is allowed to settle until clear water is on the top 20 to 30 percent of the tank contents. This ensures about 95% removal of E –Coli and other harmful bacteria from the effluent and sludge which can later be used for as manure.

167. Drying of sludge will be done inside the STP premises in Sludge storage platform. Dried sludge will be used as soil conditioner as manure and mixing with compost at compost yard. Periodic testing of dried sludge will be conducted to ensure that it does not contain heavy metals that make it unsuitable for food crops. Tests will be conducted to confirm the concentrations below the standards as mentioned in Table 17. As there are no specific standards notified for sludge reuse, the compost quality standards notified under the

Page 121: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

120

Municipal Solid Waste Management & Handling Rules, 2000 and Solid Waste Management Rule 2016 have been adopted here. The MSWMH Rules stipulate that “In order to ensure safe application of compost, the following specifications for compost quality shall be met, Table 17 above.

168. Sludge shall be periodically tested for presence of heavy metals. Proper sludge handling methods should be employed to mitigate pollution due to improper sludge disposal methods. Personal Protection Equipment should be provided to the workers. A proper sludge management plan shall be prepared/developed by the STP DBO contractor.

169. Sludge Treatment: Sludge shall be treated/composted prior to use as manure.

Appropriate sludge treatment technology will be provided for reuse of sludge for agriculture purpose. The technology is kept open as the project will be firmed up during detailed design phase by DBO contractor.

170. As STP is proposed under design-build-operate contract modality, the following measures will be implemented during the detailed design of the STP:

(i) SBR process design to meet the following effluent discharge values

Biochemical Oxygen Demand (BOD5 at 200C)

<10 mg/l

Total Suspended Solis (TSS) < 10 mg/l

Chemical Oxygen Demand (COD) <50 mg/l

Total Nitrogen as N < 10 mg/L

Ammonical Nitrogen as N < 5 mg/L

Phosphorous as P < 2 mg/L

Fecal coli form < 230 MPN/100 ml

(ii) Regular monitoring system to ensure that treated wastewater always meets the

design disposal standards (iii) Sludge management to collect, treat and dispose the accumulated sludge safely;

sludge will be treated in a mechanical centrifuge which will thicken the sludge by separating the liquid, thicken sludge will be further dried, and dried sludge will be used as a soil conditioner in fields; Sludge will be tested periodically for heavy metal concentration.

(iv) Provision of appropriate personal protection equipment to the workers and staff (v) Conduct detailed water quality assessment of Bhonli Nala at d/s of proposed

discharge point- pre and post monsoon (vi) Conduct sediment quality assessment of existing rainy drain and Bhongli Nala at

discharge point. 171. Following measures are to be implemented during the operation phase, and should be

appropriately included in the project design and operation manuals:

(i) Prior to handing over STP to ULB after the DBO contract period, ensure proper knowledge transfer, hands-on training to municipal staff engaged in STP

Page 122: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

121

operation by DBO Contractor (ii) Ensure continuous uninterrupted power supply (iii) Operate and maintain the facility following standard operating procedures of

operational manual (iv) Undertake preventive and periodic maintenance activities as required (v) Maintain the mechanical / electrical parts as per the maintenance plan to avoid

any hazards (vi) Conduct periodic training to workers (vii) Ensure all safety apparatus at STP including personal protection equipment (viii) Implement sludge management plan (ix) Conduct regular wastewater quality monitoring (at inlet and at outlet of STP) to

ensure that the treated effluent quality complies with STP design values (x) Conduct periodic testing of dried sludge/compost to check presence of heavy

metals and confirming the following concentrations to use as compost. It shall not be used for food crops.

172. Sewer network. The sewer pipes will not function without maintenance, as silt

inevitably collects in areas of low flow over time. The project contractor will therefore provide equipment for cleaning the sewers, including buckets and winches to remove silt via the inspection manholes, diesel-fuelled pumps to remove blockages, and tankers to transport the waste hygienically to the STP.

173. Piped sewers are not 100% watertight and leaks can occur at joints. Any repairs will

be conducted by sealing off the affected sewer and pumping the contents into tankers, after which the faulty section will be exposed and repaired following the same basic procedure as when the sewer was built. Trenches will be dug around the faulty section and the leaking joint will be resealed, or the pipe will be removed and replaced.

174. There are certain environmental risks from the operating system, most notably from leaking sewer pipes as untreated faecal material can damage human health and contaminate both soil and groundwater. It will be imperative therefore that the the agency operating the sewerage system establishes a procedure to routinely check the operation and integrity of the sewers, and to implement rapid and effective repairs where necessary.

There is an occupation health risk to workers engaged in sewer maintenance activities. Following measures should be followed:

(i) Establish regular maintenance program, including:

• Regular cleaning of grit chambers and sewer lines to remove grease, grit, and other debris that may lead to sewer backups. Cleaning should be conducted more frequently for problem areas

• Inspection of the condition of sanitary sewer structures and identifying areas that need repair or maintenance. Items to note may include cracked/deteriorating pipes; leaking joints or seals at manhole; frequent line blockages; lines that generally flow at or near capacity; and suspected infiltration or exfiltration; and

• Monitoring of sewer flow to identify potential inflows and outflows

• Conduct repairs on priority based on the nature and severity of the problem. Immediate clearing of blockage or repair is warranted where an overflow is currently occurring or for urgent problems that may cause an imminent overflow (e.g. pump station failures, sewer line mentales, or sewer line

Page 123: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

122

blockages); (ii) Maintain records; review previous sewer maintenance records to help identify

“hot spots” or areas with frequent maintenance problems and locations of potential system failure, and conduct preventative maintenance, rehabilitation, or replacement of lines as needed;

(iii) When a spill, leak, and/or overflow occurs, keep sewage from entering the storm drain system by covering or blocking storm drain inlets or by containing and diverting the sewage away from open channels and other storm drain facilities (using sandbags, inflatable dams, etc.). Remove the sewage using vacuum equipment or use other measures to divert it back to the sanitary sewer system.

(iv) Provide necessary health and safety training to the staff in sewer cleaning and maintenance

(v) Provide all necessary personnel protection equipment (vi) Do not conduct manual cleaning of sewers; for personnel engaged sewer

maintenance work, there is a risk due to oxygen deficiency and harmful gaseous emissions (hydrogen sulphide, methane, etc.); provide for adequate equipment (including oxygen masks) for emergency use

175. Septage Collection and Treatment. Due to techno economic reasons, some households are not covered with sewer network. To cater to these households, septage management system is provided. Wastewater will be disoposed by households ino individual septic tanks, and periodically (once in 2 two 3 years), accumulated septage will be collected via mobile suction tankers and discharged into STP inlet for safe treatment along with the sewage. Necessary training, apparatus and personnel protection equipment will be provided to the septage management staff to avoid any health and environmental risks in handling.

176. The citizens of the Anjad Nagar Parishad will be the major beneficiaries of the

improved sewerage system. The project will improve the over-all health condition of the town as water borne diseases will be reduced, so people should spend less on healthcare and lose fewer working days due to illness, so their economic status should also improve, as well as their overall health. This should also improve the environment of these areas, should deliver major improvements in individual and community health and well- being.

VII. PUBLIC CONSULTATION AND INFORMATION DISCLOSURE

A. Overview

177. The active participation of stakeholders including local community, NGOs/CBOs, and

the media in all stages of project preparation and implementation is essential for successful implementation of the project. It will ensure that the subprojects are designed, constructed, and operated with utmost consideration to local needs, ensures community acceptance, and will bring maximum benefits to the people. Public consultation and information disclosure is a must as per the ADB policy.

178. Most of the main stakeholders have already been identified and consulted during

preparation of this IEE, and any others that are identified during project implementation will be brought into the process in the future. Primary stakeholders of the subproject are: residents, shopkeepers and businesspeople who live and work alongside the roads in which network improvements will be provided and near sites where facilities will be built

Page 124: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

123

(STP), and government and utility agencies responsible for provision of services in Anjad, Forest Department and MadhyaPradesh Pollution Control Board. Secondary stakeholder are: NGOs and CBOs working in the area, community representatives, beneficiary community in general, government agencies, the executing and implementing agencies (MPUDC, PMU and PIUs), Government of India and the ADB.

B. Public Consultation

179. The public consultation and disclosure program is a continuous process throughout

the project implementation, including project planning, design and construction.

1. Consultation during Project Preparation

Table 26: Summary of Consultation

S.N. Location Participants (M/F)

Topic Discussed Issues Raised and Key Mitigation Measures

1. At Nagar Parishad Conference Hall on 25th April 2018

Town level Consultation with elected representatives locally called Ward Parshad and other prominent persons of town along including, President, Vice President, MLA Representative and CMO-Anjad

Explained in details about the Sewerage Project, Background, its components, locations, provisions, timeline, est. cost and also their roles in the project. Environmental, Social, traffic safety issue and benefit from the project were explained to the Stakeholders. The adverse effect of flowing sewer into the open nallahs of city. Connection of existing toilets with the sewer line will be a basic problem for the residents. Current status of sewage, Need of the Subproject and objectives, Potential positive and negative impacts and specific measures taken for odour and noise control (modelling, odour

Following main concerns were raised by the participants during • The project should

be completed within the stipulated time period.

• Work Plan of contractor should be shared with them so that they may start their road development work in the areas where laying gets done.

• Looking into the narrow streets and ongoing Water supply work, digging should not be like such as to block the whole passage for a prolonged period.

• What about storm water and the existing nalis

• The excavation work should not damage the newly laid/old water supply pipelines.

Page 125: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

124

S.N. Location Participants (M/F)

Topic Discussed Issues Raised and Key Mitigation Measures

capture etc.) were also explained to stakeholders.

Willingness to pay

• For ensuring quality work, subletting to local contractor should not be permitted.

They were contented with the provisions of project and said they are looking forward for the same. Shown their willingness to support / agreed to take the subproject. Asked about methods for sewage treatment and what type of technology is proposed. Possible interruption in commercial activity, breakage of other utility line, safety for pedestrian etc. Improvement in environment, health and hygiene etc. Operation and maintenance is covered under the subproject and ensure community participation Assured full support during execution. During excavation for dust and traffic management assurance given to the business community Shown their interest to pay tariff and full participation to motivate others Prior information is required before start of the civil works in the respective ward More attention is

Page 126: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

125

S.N. Location Participants (M/F)

Topic Discussed Issues Raised and Key Mitigation Measures required on safety as a supervisor is required to observe and enforce safety measures For Safety of Local traffic and pedestrian in Built-up Zone, fencing should be provided. Adequate provision for minimizing the Dust and Noise Pollution during construction and during operation phase specific measures taken for odour and noise control (modelling, odour capture etc.)

2. Ward No. 14 Shivalya Mohalla, Anjad

Local Inhabitants (Female-7 and Male-11)

The Sewerage Project Background, Environmental, Social, traffic safety issue and benefit from the project were explained to the Stakeholders.

• The adverse effect of flowing sewer into the open nallahs of city.

• Connection of existing toilets with the sewer line will be a basic problem for the residents

i) Prevailing status of sewage

ii) Need of the Subproject iii) Briefing on subproject

objectives iv) Potential positive and

negative impacts due to project implementation

v) If impact on livelihood. vi) Inconvenience to

public vii) Willingness to pay

viii) Local residents have shown their willingness to support / agreed to take the subproject.

ix) Improvement in environment, health and hygiene etc.

x) Suggested if noticed during construction, then should be compensated as per RF

xi) Public notice to be circulated, construction should be completed in the given time, debris

xii) Shown their interest to pay tariff and full participation to motivate others

For Safety of Local traffic and pedestrian in Built-up Zone, fencing should be provided. Adequate provision for minimizing the Dust and Noise Pollution during construction

Page 127: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

126

S.N. Location Participants (M/F)

Topic Discussed Issues Raised and Key Mitigation Measures Peoples also demanded for proper traffic signage for speed limits for minimizing the accident

3. Ward No. 5 & 6

Khosar Falya and

Gai Bachhada,

Anjad (Near IPS

Site)

Local residents (Female-20)

The Sewerage Project Background, Environmental, Social, traffic safety issue and benefit from the project were explained to the Stakeholders.

• The adverse effect of flowing sewer into the open nallahs of city.

• Connection of existing toilets with the sewer line will be a basic problem for the residents

xiii) Prevailing status of

sewage xiv) Need of the Subproject xv) Briefing on subproject

objectives xvi) Potential positive and

negative impacts due to project implementation

xvii) If impact on livelihood.

xviii) Inconvenience to

i) All the females have shown their willingness to support / welcome the subproject.

ii) Improvement in environment, health and hygiene etc.

iii) Suggested if noticed during construction, then should be compensated as per RF

iv) Public notice to be circulated, construction should be completed in the given time, debris

v) Assured full support during execution.

vi) Shown their interest to pay tariff and full participation to motivate others

Page 128: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

127

S.N. Location Participants (M/F)

Topic Discussed Issues Raised and Key Mitigation Measures

public xix) Willingness to pay

4. Ward No. 2 Main

Road Hospital

Chauraha, Anjad

Local Inhabitants (Male-10 including Ward Parshad)

The Sewerage Project Background, Environmental, Social, traffic safety issue and benefit from the project were explained to the Stakeholders.

i) Prevailing status of

sewage ii) Need of the Subproject iii) Briefing on subproject

objectives iv) Potential positive and

negative impacts due to project implementation

v) If impact on livelihood. vi) Inconvenience to

public vii) Willingness to pay

i) Local inhabitants have shown their willingness to support / welcome the subproject.

ii) Local inhabitant generally prefer to construct Pit Toilet, hardly construct septic tank in their house.

iii) Shown their interest to pay low tariff and full participation to motivate others.

iv) Temporary impacts: possible interruption in commercial activity, breakage of other utility line, safety for pedestrian etc.

v) Improvement in environment, health and hygiene etc.

vi) Suggested if noticed during construction, then should be compensated as per RF

vii) Local inhabitants preferably defecate in the open areas away from habitation

viii) Public notice to be circulated, construction should be completed in the given time, debris

5. Ward No. 5 Navalpura, Anjad

Elected representatives locally called Ward Parshad and Local Inhabitants

viii) Prevailing status of sewage

ix) Need of the Subproject x) Briefing on subproject

objectives xi) Potential positive and

i) Ward Parshad along with local inhabitants have shown interest.

ii) Temporary impacts: possible interruption in the movement,

Page 129: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

128

S.N. Location Participants (M/F)

Topic Discussed Issues Raised and Key Mitigation Measures

(Female-06 and Male-10)

negative impacts due to project implementation

xii) If impact on livelihood. i) Inconvenience to

public xiii) Willingness to pay

safety for pedestrian etc.

iii) Improvement in environment, health and hygiene etc.

iv) What are the common methods for sewage treatment and what type of technology is proposed.

v) Temporary impacts: possible interruption in commercial activity, breakage of other utility line, safety for pedestrian etc.

vi) Suggested if noticed during construction, then should be compensated as per RF

vii) Public notice to be circulated, construction should be completed in the given time, debris

viii) Shown their interest to pay low tariff and full participation to motivate others.

6. Consultation with Squatters (commercial) reported within RoW of road at Anjad to Thikri road

4-5 squatters xiv) Prevailing status of sewage

xv) Need of the Subproject xvi) Briefing on subproject

objectives xvii) Potential positive

and negative impacts due to project implementation

xviii) If impact on livelihood.

xix) Inconvenience to public

xx) Willingness to pay

i) Squatters losing temporarily loss of livelihood have shown their willingness to support / agreed to take up the subproject.

ii) Temporary impacts: possible interruption in commercial activity, breakage of other utility line, safety for pedestrian etc.

Page 130: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

129

S.N. Location Participants (M/F)

Topic Discussed Issues Raised and Key Mitigation Measures

iii) Suggested if noticed during construction, then should be compensated as per RF

iv) During excavation for dust and traffic management assurance given to the business community

v) Suggested if noticed during construction, then should be compensated as per RF

7. Near Proposed Location of IPS on 27th November 2017

Local Resident (Male-09)

The Sewerage Project Background, Environmental, Social, traffic safety issue and benefit from the project were explained to the Stakeholders. Current status of sewage, Need of the Subproject and objectives, Potential positive and negative impacts, Willingness to pay

Shown their willingness to support / agreed to take the Asked about methods for sewage treatment and what type of technology is proposed. Improvement in environment, health and hygiene etc. Operation and maintenance is covered under the subproject and ensure community participation Assured full support during execution. Excavated trench should be properly barricaded and restore as soon as possible in market area. Shown their interest to pay tariff and full participation to motivate others Prior information is

required before start of the civil

works in the respective ward through public

Page 131: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

130

S.N. Location Participants (M/F)

Topic Discussed Issues Raised and Key Mitigation Measures

address system

Near Proposed Location of IPS on 25th April 2018

Local Resident (Male-10)

The Sewerage Project Background, Environmental, Social, traffic safety issue and benefit from the project were explained to the Stakeholders. Current status of sewage, Need of the Subproject and objectives, Potential positive and negative impacts, Willingness to pay

Shown their willingness to support / agreed to take the Asked about methods for sewage treatment and what type of technology is proposed. Improvement in environment, health and hygiene etc. Operation and maintenance is covered under the subproject and ensure community participation Assured full support during execution. Excavated trench should be properly barricaded and restore as soon as possible in market area. Shown their interest to pay tariff and full participation to motivate others Prior information

isrequired before start of the civil

works in the respective ward through public address

system 8. Near

Proposed Location of MPS on 27th November 2017

Local Resident (Male-04)

The Sewerage Project Background, Environmental, Social, traffic safety issue and benefit from the project were explained to the Stakeholders. Current status of sewage, Need of the Subproject and objectives, Potential positive and

Shown their willingness to support / agreed to take the Asked about methods for sewage treatment and what type of technology is proposed. Improvement in environment, health and hygiene etc. Operation and maintenance is covered

Page 132: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

131

S.N. Location Participants (M/F)

Topic Discussed Issues Raised and Key Mitigation Measures

negative impacts, Willingness to pay

under the subproject and ensure community participation Assured full support during execution. Excavated trench should be properly barricaded and restore as soon as possible in market area. Shown their interest to pay tariff and full participation to motivate others Prior information is

required before start of the civil

works in the respective ward through public address

system Near

Proposed Location of MPS on 25th April 2018

Local Resident (Male-04, Female-08)- Total 12 Participants

The Sewerage Project Background, Environmental, Social, traffic safety issue and benefit from the project were explained to the Stakeholders. Current status of sewage, Need of the Subproject and objectives, Potential positive and negative impacts, Willingness to pay

Shown their willingness to support / agreed to take the Asked about methods for sewage treatment and what type of technology is proposed. Improvement in environment, health and hygiene etc. Operation and maintenance is covered under the subproject and ensure community participation Assured full support during execution. Excavated trench should be properly barricaded and restore as soon as possible in market area. Shown their interest to pay tariff and full participation to motivate others

Page 133: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

132

S.N. Location Participants (M/F)

Topic Discussed Issues Raised and Key Mitigation Measures Prior information is

required before start of the civil

works in the respective ward through public address

system 9. Near

Proposed Location of STP on 27th November 2017

Local Residents (Male-03)

The Sewerage Project Background, Environmental, Social, traffic safety issue and benefit from the project were explained to the Stakeholders.

• The adverse effect of flowing sewer into the open nallahs of city.

• Connection of existing toilets with the sewer line will be a basic problem for the residents

Current status of sewage, Need of the Subproject and objectives, Potential positive and negative impacts, Willingness to pay

Shown their willingness to support / agreed to take the subproject as some inhabitant defecate on the proposed STP site Asked about methods for sewage treatment and what type of technology is proposed. Improvement in environment, health and hygiene etc. Operation and maintenance is covered under the subproject and ensure community participation Assured full support during execution. During excavation for dust and traffic management assurance given to local residents. Excavated trench should be properly barricaded and restore as soon as possible in & around STP area. Shown their interest to pay tariff and full participation to motivate others Prior information is required before start of the civil works in the respective ward through public address system

Page 134: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

133

S.N. Location Participants (M/F)

Topic Discussed Issues Raised and Key Mitigation Measures

Near Proposed Location of STP on 25th April 2018

Local Residents Near Aspatal Chowk Total Participant-13

The Sewerage Project Background, Environmental, Social, traffic safety issue and benefit from the project were explained to the Stakeholders.

• The adverse effect of flowing sewer into the open nallahs of city.

• Connection of existing toilets with the sewer line will be a basic problem for the residents

Current status of sewage, Need of the Subproject and objectives, Willingness to pay Potential positive and negative impacts and specific measures taken for odour and noise control (modelling, odour capture etc.) were also explained to stakeholders

Shown their willingness to support / agreed to take the subproject as some inhabitant defecate on the proposed STP site Asked about methods for sewage treatment and what type of technology is proposed. Improvement in environment, health and hygiene etc. Operation and maintenance is covered under the subproject and ensure community participation Assured full support during execution. During excavation for dust and traffic management assurance given to local residents. Excavated trench should be properly barricaded and restore as soon as possible in & around STP area. Shown their interest to pay tariff and full participation to motivate others Prior information is required before start of the civil works in the respective ward through public address system Adequate provision for minimizing the Dust and Noise Pollution during construction and during operation phase specific measures taken for odour and noise control measures

Page 135: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

134

S.N. Location Participants (M/F)

Topic Discussed Issues Raised and Key Mitigation Measures (modelling, odour capture etc.)

180. Formal and informal consultations have been carried out with different type of

stakeholders right from the planning of the subproject. The subproject proposal is formulated in consultation with office of the Nagar parishad Anjad. (Refer Appendix 13 (13A to Appendix 13D)).

172. Town level consultation has been conducted on 25th April 2018 with elected

representatives of new Parishad in Anjad at Nagar Parishad Conference Hall. Total 18

participants including President, Vice President, Councillors, MLA representative

and CMO were explained in details about the project, its components, locations,

provisions, timeline, est. cost and also their roles in the project and later on their queries were replied. Besides this, Public consultation at STP, MPS and IPS sites were also

conducted for disseminating the information and taking their views on 25th April 2018.

and also consultation with peoples residing near IPS-1, MPS-2 & STP and in different wards has been conducted in Anjad Town during the project preparation in which representatives of primary and secondary stakeholders has been invited as mentioned in Table given above. The feedback and concerns of the stakeholders has been taken into consideration

173. It was observed that people are willing to extend their cooperation as the proposed activities are proposed to enhance the infrastructure service levels and the living standard of the public. The public expressed their concern regarding the nuisance and disturbance (dust, road closure and traffic management activities) during the construction stage which can have impact on their day to day activities. Public demanded for advance notice before construction and proper warning signs along the construction area to avoid accidents and inconvenience. Public opined that an appropriate operation and maintenance system should be in place, for sewerage system, for its best functioning and to have the maximum health and aesthetic benefits. • Local people have appreciated the waste water management proposal of the

government and they have ensured that they will cooperate with the Executing Agency during project implementation

• All the stakeholders were supportive of the project and indicated their willingness to participate in the project to make it successful.

• Stakeholders were of the view that these subprojects provide benefits to all the people by improving sewerage.

• Stakeholders are concerned about the pollution of water bodies due to entry of wastewater. It was explained that this subproject will mitigate this problem by effectively collecting, treating the sewage.

174. Stakeholders suggested that (i) Local people should be employed by the contractor during construction work; (ii) Adequate safety measures should be taken during

Page 136: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

135

construction work; (iii) utility shifting should be properly planned before execution of the work; (iv) Road restoration should be carried out properly; (v) Proposed waste water management project should ensure proper hygienic disposal of sewerage water in all wards of city.

2. Consultation during construction

175. Prior to start of construction, ULB and PIU with the assistance of PDMC will conduct

information dissemination sessions at various places and solicit the help of the local community, leaders/prominent for the project work. At each ward/neighborhood level, focus group meetings will be conducted to discuss and plan construction work with local communities to reduce disturbance and other impacts.

176. A constant communication will be established with the affected communities to

redress the environmental issues likely to surface during construction phases and also regarding the grievance redress mechanism ULB/PIU and PDMC will organize public meetings and will appraise the communities about the progress on the implementation of EMP. Meeting will also be organized at the potential hotspots/sensitive locations before and during the construction. Contractor will provide prior public information (in Hindi) about the construction work in the area, once 7 days prior to the start of work and again a day before the start of work via pamphlets. At the work sites, public information boards will also be provided to disseminate project related information.

C. Information Disclosure

177. Executive summary of the IEE will be translated in Hindi and made available at the

offices of PMU, PIU, Nagar Parishad offices, and also displayed on their notice boards Hard copies of the IEE will be accessible to citizens as a means to disclose the document and at the same time creating wider public awareness. Electronic version of the IEE in English and Executive Summary in Hindi will be placed in the official website of the MPUDC, PMU after approval of the IEE by Government and ADB. Stakeholders will also be made aware of grievance register and redress mechanism.

178. Public information campaigns to explain the project details to a wider population will be conducted. Public disclosure meetings will be conducted at key project stages to inform the public of progress and future plans. Prior to start of construction, the PMU/PIU will issue Notification on the start date of implementation in local newspapers A board showing the details of the project will be displayed at the construction site for the information of general public.

179. Local communities will be continuously consulted regarding location of construction camps, access and hauling routes and other likely disturbances during construction. The road closure together with the proposed detours will be communicated via advertising, pamphlets, radio broadcasts, road signage, etc.

Page 137: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

136

VIII. GRIEVANCE REDRESS MECHANISM

A. Project Specific Grievance Redress Mechanism

180. Grievance Redress Mechanism (GRM) is a part of project management that is likely to increase accountability and responsiveness among service providers and provide a friendly environment to the beneficiaries of the project. GRM is considered a tool to measure efficiency and effectiveness of the project as it provides important feedback on the project management. Effectively addressing public grievances is a core component of managing risks under Asian Development Bank (ADB) projects according to the Safeguard Policy Statement (Safeguard Requirement 2: Involuntary Resettlement, Pages 49-50, June 2009) – “The borrower/client will establish a mechanism to receive and facilitate the resolution of affected persons’ concerns and grievances about physical and economic displacement and other project impacts, paying particular attention to the impacts on vulnerable groups. The grievance redress mechanism should be scaled to the risks and adverse impacts of the project. It should address affected persons’ concerns and complaints promptly, using an understandable and transparent process that is gender responsive, culturally appropriate, and readily accessible to the affected persons at no costs and without retribution. The mechanism should not impede access to the country ’s judicial or administrative remedies. The borrower/client will inform affected persons about the mechanism”. The statement allows the formation of grievance redress committee in the project areas to facilitate the concerns of affected people under the project areas.

B. Purpose of the GRM Manual:

181. This document describes the procedure that shall be followed by the Madhya Pradesh Urban Development Company Limited (MPUDCL) under Madhya Pradesh Urban Services Improvement project (MPUSIP) to address complaints or concerns shared by people affected due to project related interventions.

182. The present document intends to provide clarity to project stakeholders on the grievance redress mechanism procedures to be followed under the project. The document provides clarity on how the complaint shall be received, registered, sorted, assessed, resolved and monitored under MPUSIP. This also includes action plans to be followed for effective implementation.

C. Principles:

183. The GRM is based on the following principles and the same shall be used to assess the GRM performance: (a) Accessibility

The GRM shall be accessible to all people residing in the project area. It shall be available and provide assistance to all project affected people irrespective of language, literacy level, or cost. Project affected people shall access the GRM without fear of reprisal. Information on the GRM will be disseminated using various means to ensure people know about GRC, its members and procedures. (b) Predictability

The GRM shall offer clear procedures with time frames for each stage and clarity on the

Page 138: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

137

type of results it can and cannot deliver. (c) Transparency

The GRM shall operate in such a way that it is easy for others to see what actions are being performed. This will be undertaken through disclosure of all information to the public and affected people. (d) Credibility

The performance of the GRM shall enable affected people to accept and believe that the mechanism works, delivers results and is trustworthy. (e) Fairness

The GRM procedures shall be perceived as fair, especially in terms of access to information, and opportunities for meaningful participation in the final decision. Its outcome should be consistent with applicable national standards and should not restrict access to other redress mechanisms. (f) Feedback

The GRM shall serve as a means to channel citizen feedback to improve project outcomes for the people. It is difficult to avoid Grievances totally but much can be done to minimize and manage complaints in order to reduce impacts.

D. Nature and scope of Grievance Redress Mechanism under MPUSIP

184. GRM aims to address complaints of local affected people because of project interventions in the selected towns (64 towns) of MPUSIP during the project period.

185. MPUSIP predicts public complaints because of the nature of the project during the design, implementation and operation & maintenance stage of the project. In the design phase, people are expected to raise inconveniences with regards to land acquisition, compensation amount, compensation procedure and environmental issues. During project implementation, grievances may come from individuals or a particular group of people in relation to construction related inconveniences such as dust, noise, blocking drainage, damage roads, walls/boundaries of property and its impact on their daily lives in addition to land acquisition, and compensation. Issues related to corruption shall not be considered by the Grievance Redress Committee (GRC). Corruption related issues shall be forwarded to the State GRC (PMU) directly by the Chairperson of town level GRC at the time of sorting of grievances. The structure, functions of GRC, monitoring & evaluation systems and action plan of its implementation is described below:

E. Structure of GRM and its Functions

186. The GRM will have a three- tier decision making process. The first tier which is at the town level aims to resolve all construction related grievances which require quick and efficient action. The second tier which is at the project implementation unit (PIU) will handle complaints that could not be resolved by the first- tier level and/or grievances related to land acquisition and compensation. The third tier which is at the project management unit (PMU) or state level will handle complaints which are over and above the scope for the first and second tier and/or complaints which could not be resolved by the first and second tier levels.

Page 139: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

138

187. Contact numbers of GRC Chair-person and members, CDO and contractor’s focal person will be placed at appropriate locations like construction sites, ULB office etc.

188. The three-tier Grievance Redress Mechanism under MPUSIP is described below:

1st tier (At Town Level):

composition of the Grievance Redress Committee (GRC):

• A representative of Chief Municipal Officer associated with Urban Local Body,

Chairperson;

• CDO of ULB designated/nominated by ULB.

• Field Engineer of Project Management Consultants;

• Focal person (GRC Person) of DBO contractor of respective town;

• Field Engineer of concerned ULB designated by the respective PIU, Secretary;

Major Functions: The major functions of town level GRC is as follows:

• Registration of Grievances by the Local person (GRC Person) of DBO contractor

of respective town Sorting of Grievances by Focal person (GRC Person) of DBO

contractor of respective town and Chairperson;

• Forwarding grievances to concerned authorities i.e. Site Engineer for resolution;

• Information to the complainant on the decision taken to address registered

complaint and expected time to resolve issue;

• Resolution of issues emerged due to construction;

• Feedback to the complainant on action completed against registered complaint

and seeking complainant feedback on level of satisfaction;

• Closure of grievances by CDO-ULB or forwarding of complaint to PIU GRC if

grievance remains unresolved.

2nd Tier {At PIU Level}:

Composition of the PIU level GRC:

• Project Manager, associated with Project Implementation Unit (PIU) of Madhya

Pradesh

• Urban Development Company Limited - Chairperson

• An elected member nominated by Mayor in Council/ President in Council of

associated

• Urban Local Body (ULB).

• A Social Worker nominated by Mayor in Council/ President in Council of

associated Urban

• Local Body

• Commissioner of associated Urban Local Body/Chief Municipal Officer or

Community

Page 140: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

139

• Development Officer/Community Organizer of Urban Local Body.

• Community Development Officer CDO-PIU - Secretary

Major Functions: The following functions will be performed by the PIU level GRC:

• Registration of complaints by CDO-PIU from the 1st tier GRC and/or affected

people;

• Eligibility assessment of grievances by the GRC Chairperson;

• Information to the complainant about eligibility of the complaint;

• Grievance Redress Committee meetings to discuss grievances and action

required;

• Ensuring collection of detailed information about the eligible complaint;

• Assessment of complaint, draw conclusion from discussions and make

recommendations;

• Develop action plan outlining activities required to implement the

recommendations;

• Ensuring implementation of recommendations by stakeholders or concerned

authorities;

• Monitoring actions of the recommendations in view of timeline;

• Feedback to the complainant on action completed against registered complaint

and seeking complainant feedback on level of satisfaction;

• Closure of grievances by CDO-PIU or forwarding of complaint to PMU GRC if

grievance remains unresolved.

3rd Tier {At PMU-State Level}

Composition of State Level GRC:

• Engineer in Chief, MPUDC – Chairperson

• Deputy Project Director (T)

• Deputy Project Director (A) (Secretary)

• Project Officer

• Community Development Officer CDO-PMU

• PMC TL or representative Advisor

Major Functions: The state level GRC will be responsible to perform the following functions:

• Registration of complaints received from GRC PIU and/or affected people;

• Information to the complainant about eligibility of the complaint;

• Eligibility assessment of grievances by the GRC PMU chairperson with support

of the

• Secretary of state GRC- – whether grievance is eligible for consideration or not

at the state level;

• Ensuring collection of required information about the eligible complaint;

• Assessment of complaint to draw conclusion from discussions and make

recommendations;

Page 141: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

140

• Develop action plan outlining activities required to implement the

recommendations;

• Ensuring implementation of recommendations by stakeholders or concerned

authorities;

• Monitoring actions of the recommendations in view of timeline;

• Closing complaint after all actions taken as per recommendations and feedback

to the complainant.

• Advise to complainants about approach /appeal to the concerned department in

case the complainant is not satisfied or complaint is beyond the scope of the

GRC PMU.

Figure 40: Work Flow Diagram on GRM

Grievance

Redress Mechanism

Step 1: Receiving Grievances /

Complaints and its Registration at

town level (24 hours)

Step 2: Review of

Grievances,

Sorting,

Information and

Forwarding (1

Ste

p 3

: E

lig

ibil

ity

an

d P

rep

ara

tio

n f

or

GR

C M

ee

tin

g (

3 D

ay

s)

Step 4: Assessment of the Grievance,

Meeting and Plan of Action (7 Days)

Step 5: Implementation of

Action

Ste

p 6

: M

on

ito

rin

g a

nd

Re

po

rtin

g

(Mo

nth

ly)

Ste

p 7

: C

losu

re o

f th

e

Co

mp

lain

t

Step 8: Appeal to the

State Level GRC

Page 142: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

141

F. Process of Grievance Redress Mechanism

189. The following process shall be adopted for receiving complaints and addressing received complaints: Step 1: Receiving Grievances/ Complaints and its Registration at town Level

• All grievances, complaints, concerns shall be submitted verbally or in writing

to CDO contractor’s focal person or any GRC members – by filling the

Complaint Registration Slip and putting into the complaint box placed at

construction sites or ULB office.

• Received complaints shall be recorded, compiled and Registered

(Grievance Number) in a register (database) placed at the ULB by CDO with

support of the contractor’s focal person on a daily basis (24 hours). Each

grievance shall be given a number to track status.

Step 2: Review of Grievances, Sorting, Information and Forwarding (24 hours)

• Registered grievances shall be reviewed by the CDO with support of the

contractor’s focal person. • Based on type of grievances, CDO shall sort out grievances with support of

the contractor’s focal person. • CDO (ULB) shall inform the GRC Chairperson about all grievances either by

phone or in writing. At that time, CDO may suggest grievances can be

managed by the site engineer to the GRC Chairperson;

• GRC Chairperson will determine eligibility of the complaints. Inconveniences

caused by minor construction related issues shall be referred to the site

engineer to resolve immediately or within 24 hours. For example -site

engineer shall be instructed to resolve grievances associated with

construction at the town such as restoration of road, obstruction in accessing

house/shop or any place due to dumping of construction materials, dust etc.

Site engineer will be responsible to respond to the complaints immediately.

On the other hand, issues which cannot be resolved by the site engineer and

if it is complex in nature shall be referred to GRC.

• CDO shall receive acknowledgement from concerned authorities (site

engineer) on receipt of the grievances shared with them. CDO shall inform

complainants regarding eligibility of their complaint and action to be taken by

the concerned authority (site engineer/ GRC) within (24 hours). If the

grievance is ineligible, complainants should be informed of the reasons;

Step 3: Eligibility and Preparation for GRC meeting (3 days)

• GRC Chairperson shall receive eligible complaints (copy of written complaint

document or verbally recorded messages) from the CDO (ULB) and review

details; GRC Chairperson may ask to collect baseline information about the

grievances registered, if required.

• GRC Chairperson shall share list of documents with the GRC Secretary to

collect baseline information on selected grievances to be addressed.

Page 143: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

142

• The GRC Secretary shall arrange all documents with the help of CDO-ULB,

CDO-PIU or the contractor’s focal person in a proper way to present in front of GRC.

• GRC Chairperson shall call a meeting as per convenient date and time of the

committee members.

Step 4: Assessment of the Grievance, Meeting and Plan of Action (7 days)

• If necessary, the GRC shall consult and seek relevant information about

complaint from the concerned parties.

• On basis of the collected evidences, GRC shall draw conclusions and make

recommendations for a solution.

• GRC Secretary shall keep record of the proceedings and decisions taken by

GRC members to further track the status as per decided time line.

• The GRC shall agree on the action plan required to be implemented

according to the recommendations made. The action plan shall include

detailed activities along with timeline.

• GRC Secretary shall inform to the complainant about the decisions taken by

the committee members and expected date of resolution of the grievance.

• If the complaint is complex, the GRC may request for additional time and

resolution after proper assessment or refer the complaint to the GRC-PMU

Level.

Step 5: Implementation of Action (30 days)

• The concerned parties shall be responsible to implement action plan

according to recommendations of the GRC.

• The GRC members may arrange field trip and interact with the concerned

persons, if needed before reaching the conclusion.

Step 6: Monitoring and Reporting (Monthly)

• CDO (ULB) shall be responsible to track and record status of all complaints -

whether forwarded to site engineer or GRC in the database as follows –

Grievance registered, Grievance in process to be resolved, Grievance

addressed and closed, and Grievance forwarded to concerned authorities.

• CDO (ULB) shall be responsible to report/inform status of the complaints

(received, addressed and forwarded) to the contractor for further reporting to

respective PIU.

• Overall GRC chairperson shall be responsible for effective management of

complaints at the town level.

Step 7: Closure of the Complaint

• GRC Secretary shall prepare a summary of the findings and share with GRC

members.

• On agreement of all GRC members, GRC Secretary shall provide

information to the complainant about decisions taken in writing/verbal on the

Page 144: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

143

registered complaint and seek feedback of the complainant about the

decisions taken. A copy of the letter shall be kept as record with GRC

Secretary and CDO (ULB).

• Complaint shall be considered closed if all actions have been taken and the

complainant satisfied with the resolution.

• GRC Secretary shall prepare a closure report of the grievances handled by

GRC members and the closure shall be documented by the CDO (ULB) in

his register.

Step 8: Appeal to the State level GRC

• In the event that GRC PIU cannot make a decision on how to resolve the

complaint, or if a complainant is not satisfied with the actions taken to

resolve the complaint by the GRC (PIU), an appeal can be made to state

level GRC (PMU) either by the GRC Chairperson (PIU) or complainant

directly.

• GRC Chairperson (PIU) or complainant shall submit an appeal in writing to

the state level GRC established at PMU.

• The state GRC Secretary shall register the case in consultation with

Chairperson and provide a number of the grievances to be tracked.

• The state GRC Secretary shall acknowledge the registration of the grievance

to the complainant in writing.

• The Secretary of the GRC shall review the registered grievances and collect

required evidences from relevant parties to present case to the GRC.

• The state GRC Chairperson shall call a GRC meeting to review the

complaint. GRC members shall get information about the meeting in

advance to ensure their availability in the meeting.

• The state GRC shall draw conclusions and recommendations based on the

evidence in the meeting. At the same time an action plan shall be developed

for implementation with a timeline.

• The state GRC Secretary shall communicate decisions of the State GRC to

the complainant in writing. The copy of the communication shall be kept with

the state GRC Secretary as record.

• The recommendations shall be implemented immediately

• Upon completion of the recommended actions, the state GRC Secretary

shall prepare a report on the closure of the complaint which will be signed by

the complainant and state GRC Chairperson. A copy of the same shall be

kept for record.

The structure and process of GRM is presented below for detailed understanding

Page 145: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

144

Figure 41: Structure and Process of GRC

G. Monitoring and Evaluation systems of GRM

All grievances, concerns and complaints received shall be recorded by concerned authorities to be tracked. The status of the grievances shall be discussed in the review meetings organized at PIU and PMU level. The following indicators shall be monitored and recorded

- Number and type of complaints received;

- Number and % of complaints that have been resolved;

- Number and % of complaints that are unresolved;

The State GRC shall review grievance related data on monthly basis to evaluate the functionality of the system, as well as to note the followings:

• Failures to follow GRM procedures;

• Delays in complaint resolution, particularly those that can affect project

construction;

• Most frequent types of grievances and complaints;

• Location(s) producing the most grievances and complaints;

Page 146: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

145

H. Action Plan for the formation of the GRM

S. No Action Plan Time Line

A Action required at PMU/PMC

A1 Letter for formation of GRC and follow up Pre -construction

A2 Development of GRM Manual Pre -construction

A3 Orientation of GRC members by integrating with training/workshops/meetings

Construction

A4 Integration of GRC topic in BCC – like availability of GRC and its procedure

Construction

A5 Review of functioning of GRC by integrating with meetings and visits

Construction

B Action at Town level

B1 Formation of GRC at town level and inform to the PMU/PMC Pre -construction

B2 Information to All ULB Officials/Public about existence of

GRC, its committee members and their function

Construction

B3 Orientation of all GRC members during visit of PMU and PMC officials

Construction

B4 Tracking of complaint registered and its status Construction

B5 Sharing status of grievances with PIUs with the help of GRC person

Construction

B6 Training of selected women to maintain grievances at customer service center (Educated Prerak (Motivator) may be considered)

Construction

B7 Complaint management Operation and maintenance phase

Page 147: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

146

IX. ENVIRONMENTAL MANAGEMENT PLAN

A. Environmental Management Plan

190. An environmental management plan (EMP) has been developed to provide mitigation

measures to reduce all negative impacts to acceptable levels. 191. The EMP will guide the environmentally-sound construction of the subproject and

ensure efficient lines of communication between MPUDC, project management unit (P MU), project implementing unit (PIU), consultants and contractors. The EMP will (i) ensure that the activities are undertaken in a responsible non-detrimental manner; (i) provide a pro-active, feasible and practical working tool to enable the measurement and monitoring of environmental performance on site; (ii) guide and control the implementation of findings and recommendations of the environmental assessment conducted for the subproject; (iii) detail specific actions deemed necessary to assist in mitigating the environmental impact of the subproject; and (iv) ensure that safety recommendations are complied with. The EMP includes a monitoring program to measure the environmental condition and effectiveness of implementation of the mitigation measures. It will include observations on- and off-site, document checks, and interviews with workers and beneficiaries.

192. The contractor will be required to submit to PIU, for review and approval, a site

environmental plan (SEP) including (i) proposed sites/locations for construction work camps, storage areas, hauling roads, lay down areas, disposal areas for solid and hazardous wastes; (ii) specific mitigation measures following the approved EMP; (iii) monitoring program as per SEP; and (iv) budget for SEP implementation. No works are allowed to commence prior to approval of SEP.

193. A copy of the EMP/approved SEP will be kept on site during the construction period

at all times. The EMP included in the bid and contract documents. Non-compliance with, or any deviation from, the conditions set out in this document constitutes a failure in compliance.

194. For civil works, the contractor will be required to (i) carry out all of the mitigation and

monitoring measures set forth in the approved SEP; and (ii) implement any corrective or preventative actions set out in safeguards monitoring reports that the employer will prepare from time to time to monitor implementation of this IEE and SEP. The contractor shall allocate budget for compliance with these SEP measures, requirements and actions.

195. The following tables show the potential environmental impacts, proposed mitigation

measures and responsible agencies for implementation and monitoring. .

Page 148: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

147

Table 27:-Design Stage Environmental Management Plan

Field Anticipated Impact Mitigation Measures Responsible for Implementation/

Cost and Source of Funds

Design of sewageTreatment Plant

Nuisance to local people due to bad odor from STP

• Select a treatment process that is compact, aesthetically good, and generates no or fewer odours

• Providing a green buffer zone of all around the STP as per availability of land; atleast 20-30 m width of buffer zone with trees in multi-rows and landscaping. This will act as a visual screen around the facility and will improve the aesthetic appearance.

• Providing high compound wall around the STP • Develop the STP layout plan such that STP units with maximum

odour generating potential are located farthest from the nearest development; in layout design, develop office or other such facilities towards the habitation.

PIU/PMU Project Costs

Treated effluent not meeting the disposal standards and associated impactson receiving environment

• STP to be designed to meet the following treated effluent parameters: : o BOD: less than 10 mg/l o TSS: less than 10mg/l o COD: less than 50 mg/l o Faecalcoliform less than: 100/100 ml

DBOContractor/ PMU

Project Costs

Page 149: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

148

Provision of drainage system in and around STP site and from existing drain to Bhongli Nala to transfer treated sewage/ storm water into d/s drain without anyflooding / overflowing problems

• Proper drainage system shall be made as part of STP design to avoid flooding/water accumulation from uphill areas, and to channel off the upstream flow into downstream drains without any hindrance

• Repair and rehabilitate the 1.6 km length drain, if required, to receive treated wastewater from STP and convey it to Bhongli Nala safely;

DBO Contractor/PIU & PMU and respective Nagar parishad

Project Costs

Solid waste dumping into Bongli nala

• Provision of screen as barrier nets to prevent solid waste dumping into Bhongli Nala

• Create awareness in the town on to prevent dumping of solid waste into drains

DBO Contractor/PIU & PMU and respective Nagar parishad

Project Costs

Impacts monitoring on receiving water body

• Conduct baseline water quality monitoring of Bhongli nala & Narmada River

DBO Contractor

Project Costs

Improper sludge management

• Prepare sludge management plan (collection, treatment, drying, disposal and periodic testing) and integrate into design, construction and operation

Decline in treatment efficiency due to power supply disruptions and poor O&M practices

• Ensure continuous uninterrupted power supply, including a back-up facility (such as generator)

• Provide backup power facilities for continuous and uninterrupted operation

• Provide operating manual with all standard operating procedures (SOPs) for operation and maintenance of the facility

• Necessary training to ULB staff dealing with STP • Extended contract period for O & M, proper transfer of facility to

ULB after compltetion of contract period with adequate technical know-how on O & M and hands-on training to ULB staff

Page 150: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

149

Sewage Pumping Station (SPS)

Odor and insect nuisancedue to operation of SPS

Layout planning related measures • Locate wet wells within the identified site at an internal location as

far as possible from nearest development; • Providing 20-30 m wide green buffer zone around the IPS and

MPS (with maximum towards temple and school) with a combination of tall and densely growing trees in multi rows as per the land availability to control odour and also act as visual shield and improve aesthetical appearance.

• Layout plan of IPS/MPS shall be devised in such a way that it will be farthest from temple, school and habitation, so there will be no impacts envisaged due to odour to the nearby residents; ensure that maximum available distance is maintained to sump /wet well (Temple and school in case of IPS); this will increase the buffer distance of sump /wet well to nearby schook / temple from the existing 50 m from the boundary.

• Provide high compound wall around pumping stations

Design related measures to prevent and control odour

• Submersible sewage pumps of suitable rating, minimum submergence requirements

• Position of the submersible pumps and design of the wet well floor by providing necessary side benching / sloped flooring to allow for higher submergence during low flow shall be made to ensure regular pump operation and avoid sewage stagnation beyond the permissible limit.

• Diesel Generators shall be provided as standby power supply • Develop standard operating procedures / operational manual for

DBO Contractor/PMU

Project Costs

Page 151: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

150

STP and SPS operations

Noise from pumps and motor operations

• Procure good quality latest technology high pressure pumps that guarantee controlled noise at a level of around 80 dB(A) at a distance of 1 m

• Use appropriate building materials and construction techniques for pump houses which can absorb sound rather than reflect noise

• Use acoustic enclosures – manufacturer specified, for all pumps, motors

• Procure only CPCB approved generators with low emission and low noise fitted with acoustic enclosures

• Provide sound mufflers for ventilators in the plant rooms; and sound proof doors

• Provide ear plugs to workers

DBO Contractor/PMU

Project Costs

Energey consumption • Provide energy efficient design; • Using low-noise and energy efficient pumping systems • Efficient Pumping system operation • Installation of Variable Frequency Drives (VFDs)

DBO Contractor/PMU

Project Costs

Sewer Network Measures to minimize Impacts during construction and operation of sewer network

• Limit the sewer depth where possible. • Sewers shall be laid away from water supply lines and drains (at

least 1 m, wherever possible); • In all cases, the sewer line should be laid deeper than the water

pipeline (the difference between top of the sewer and bottom of water pipeline should be at least 300 mm)

• In unavoidable, where sewers are to be laid close to storm water drains or canals or natural streams, appropriate pipe material shall be selected (stoneware pipes shall be avoided)

• For shallower sewers, use small inspection chambers in lieu of manholes;

• Design manhole covers to withstand anticipated loads & ensure that the covers can be readily replace if broken to minimize silt/garbage entry

• Ensure sufficient hydraulic capacity to accommodate peak flows & adequate slope in gravity mains to prevent buildup of solids and hydrogen sulfide generation

DBO Contractor/PMU

Project Costs

Page 152: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

151

Application of Internationally approved guidelines

Pollution control, environmental, health and safety during design, construction, and operation

• During the design, construction, and operation of the project, apply pollution prevention and control technologies and practices consistent with international good practice, as reflected in internationally recognized standards such as the World Bank Group’s Environment, Health and Safety Guidelines (IFC’s General EHS Guidelines7 and Sector Specific (Water and Sanitation) Guidelines8).

DBO Contractor / PMU

Project Costs

7https://www.ifc.org/wps/wcm/connect/554e8d80488658e4b76af76a6515bb18/Final%2B-%2BGeneral%2BEHS%2BGuidelines.pdf?MOD=AJPERES 8 https://www.ifc.org/wps/wcm/connect/e22c050048855ae0875cd76a6515bb18/Final%2B-%2BWater%2Band%2BSanitation.pdf?MOD=AJPERES

Page 153: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

152

Table 28:- Environmental Management Plan of Anticipated Impacts during Pre-Construction

Field Anticipated Impact Mitigation Measures Responsible for Implementation

Monitoring of

Mitigation

Cost and Source of Funds

Utilities Telephone l i n e s , electric poles and wires, water lines within proposed project area

(i) Identify and include locations and operators of these utilities in the detailed design documents to prevent unnecessary disruption of services during construction phase; and (ii) Require Construction contractors to prepare a contingency plan to include actions to be taken in case of unintentional interruption of services.

(iii) Require contractors to prepare spoils (waste) management p l an (Appendix 9 ) and traffic management plan (Appendix 10)

DBO Contractor in collaboration with PIU and with approval o f PMU

(i) List of affected utilities and operators;

(ii) Bid document to include requirement f o r a contingency plan for service interruptions (example provision of water if disruption is more than 24 hours), waste management plan and traffic management p l an

- Project Costs

Construction work camps, stockpile areas, storage areas,

Conflicts with local community; disruption to traffic flow and

(i) Prioritize areas within or nearest possible vacant space in the project location;

DBO Contractor to finalize locations in consultation and

(i) List of selected sites for construction work camps, hot mix

-

Page 154: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

153

and disposal areas. sensitive receptors (ii) If it is deemed necessary to locate elsewhere, consider sites that will not promote instability and result in destruction of property, vegetation,

irrigation, and drinking water supply systems;

(iii) Do not consider residential areas; (iv) Take extreme care in selecting sites to avoid direct disposal to water body which will inconvenience t h e

community. (v) For excess spoil disposal, ensure (a) site shall be selected preferably f rom barren, infertile lands. In case agricultural land needs to be selected, written consent from landowners (not lessees) will be obtained; (b) debris disposal site shall be at least 200 m away from surface water bodies; (c) no residential areas shall be located within 50 m

approval o f PIU plants, stockpile areas, storage areas, and disposal areas.

(ii) Written consent of landowner’s (not lessee/s)

Page 155: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

154

downwind side of the site; and (d) site is minimum 250 m away from sensitive locations like settlements, ponds / lakes or other water bodies.

Sources of Materials Extraction of materials

can disrupt natural land contours and vegetation resulting in accelerated erosion, disturbance in natural drainage patterns, ponding and water logging, and water pollution.

(i) Obtain construction materials only from government approved quarries with prior approval of PIU

(ii)PIU to review, and ensure that proposed quarry sources have all necessary clearances/ permissions in place prior to approval

(iii)Contractor to submit to PIU on a monthly basis documentation on material obtained from each source (quarry/ borrow pit)

(iv) Avoid creation of new borrow areas, quarries etc., for the project; if unavoidable, contractor to obtain all clearances and permissions as

DBO Contractor t o prepare list of approved quarry sites and sources of materials with the approval o f PIU

(i) List of approved qu ar r ies

sites and sources of materials;

-

Page 156: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

155

required under law, including Environmental Clearance (EC) prior to approval by PIU

Consents, permits, clearances, NOCs, etc.

Failure to obtain necessary consents, permits, NOCs, etc. can result to design revisions and/or stoppage of works

(i) Obtain all necessary consents, permits, clearance, NOCs, etc. prior to award of civil works. (ii) Ensure that all necessary approvals for construction to be

obtained by contractor are in place before start of construction (iii) Acknowledge in writing and provide report on compliance all obtained consents, permits, clearance, NOCs, etc.

(iv) Include in detailed design drawings and documents all conditions and provisions i f necessary

PIU and PMC Incorporated i n final design and communicated to contractors.

No cost required. Cost of obtaining all consents, permits, clearance, NOCs, etc. prior to start of civil works responsibility of

PIU.

Asbestos Cement Pipes

Health risk due to exposure to asbestos materials

(i) Obtain details from

PHED/NPs on location of underground A C pipes (ii) Locate the new pipe/sewer carefully

DBO Contractor in

coordination with PIU and PMC

(i) Detailed construction

drawings showing alignment of AC pipes

No cost

required.

Mitigation measures are part of TOR of PIU and PMDSC

Page 157: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

156

to avoid encountering AC pipes

(ii) Leave the AC pipes undisturbed in the ground.

Table 29:- Environmental Management Plan of Anticipated Impacts during Construction

Field Anticipated

Impact Mitigation Measures Responsible for Mitigation Monitoring of

Mitigation

Cost and

Source of

Funds

EMP Implementation Training

Irreversible impact to the environment, workers, and community

(i) Project manager and all key workers will be required to undergo training on EMP implementation including spoils/waste management, Standard operating procedures (SOP) for construction works; occupational health and safety (OH&S), core labor laws, applicable environmental laws, etc.

DBO Contractor (i) Certificate of Completion (Safeguards Compliance Orientation)

(iii) Posting of EMP at

worksites

Cost of EMP Implementation Orientation Training to contractor is responsibility of PMU.

Other costs responsibility of contractor.

Air Quality Emissions from construction vehicles, equipment, and machinery used for installation of pipelines resulting to dusts and

For All Construction Works;

(ii) Provide a dust screen around STP worksite

(iii) Damp down the soil and any stockpiled material on site by water sprinkling;

(iv) Stabilize surface soils where loaders, support equipment and vehicles will operate by using water and maintain surface soils in a stabilized condition

(v) Apply water prior to levelling or any

DBO Contractor (i) Location of stockpiles;

(ii) Complaints from sensitive receptors;

(iii) Heavy equipment and machinery with air pollution control devices;

Cost for implementation of mitigation measures responsibility of

contractor.

Page 158: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

157

increase

in concentration of vehicle-related pollutants such as carbon monoxide, sulphur oxides, particulate matter, nitrous oxides, and hydrocarbons.

other earth moving activity to keep the soil moist throughout the process

(vi) Cover the soil stocked at the sites with tarpaulins

(vii) Control access to work area, prevent unnecessary movement of vehicle, public trespassing into work areas; limiting soil disturbance will minimize dust generation

(viii) Use tarpaulins to cover the loose material (soil, sand, aggregate etc.,) when transported by open trucks;

(ix) Control dust generation while unloading the loose material (particularly aggregate, sand, soil) at the site by sprinkling water and unloading inside the barricaded area

(x) Clean wheels and undercarriage of haul trucks prior to leaving construction site

(xi) Ensure that all the construction equipment, machinery are fitted with pollution control devises, which are operating correctly, and have a valid pollution under control (PUC) certificate

(iv) Pollution under control certificate

For Sewer Works;

(i) Barricade the construction area using hard barricades

(ii) Initiate site clearance and excavation work only after barricading of the site is done

(iii) Confine all the material, excavated soil, debris, equipment, machinery (excavators, cranes etc.,), to the

Page 159: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

158

barricaded area (iv) Limit the stocking of excavated

material at the site; remove the excess soil from the site immediately to the designated disposal area

(v) Undertake the work section wise; and conduct work sequentially - excavation, sewer laying, backfilling; testing section-wise (for a minimum length as possible) so that backfilling, stabilization of soil can be done.

(vi) Remove the excavated soil of first section to the disposal site

(vii) Backfilled trench at any completed section after removal of barricading will be the main source of dust pollution. The traffic, pedestrian movement and wind will generate dust from backfilled section. Road restoration shall be undertaken immediately.

Surface Water Quality

Mobilization of

settled silt materials, and chemical contamination from fuels and lubricants during installation of pipelines can contaminate

(i) All earthworks be conducted during the dry season to prevent the problem of soil/silt run-off during rains

(ii) Avoid stockpiling of earth fill especially during the monsoon season unless covered by tarpaulins or plastic sheets;

(iii) Prioritize re-use of excess spoils and materials in the construction works. If spoils will be disposed, only designated disposal areas shall be used;

(iv) Install temporary silt traps or sedimentation basins along the drainage leading to the water

DBO

Contractor

(i) Areas for stockpiles, storage of fuels and lubricants and waste materials;

(ii) Records of surface water quality inspection;

(iii) Effectiveness of water management measures;

Cost for implementation of mitigation measures responsibility of

contractor.

Page 160: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

159

nearby surface water quality

bodies; (v) Place storage areas for fuels and

lubricants away from any drainage leading to water bodies;

(vi) Store fuel, construction chemicals etc., on an impervious floor, also avoid spillage by careful handling; provide spill collection sets for effective spill management

(vii) Dispose any wastes generated by construction activities in designated sites; and

Conduct surface quality inspection according to the Environmental Management Plan (EMP).

(iv) No visible degradation to nearby drainages, nallahs or water bodies due to civil works

Surface and Ground Water Quality

Mobilization of

settled silt materials, and chemical contamination from fuels and lubricants during installation of pipelines can contaminate nearby surface water quality

(i) As far as possible control the entry of runoff from upper areas into the excavated pits, and work area by creation of temporary drains or bunds around the periphery of work area

(ii) Pump out the water collected in the pits / excavations to a temporary sedimentation pond; dispose off only clarified water into drainage channels/streams after sedimentation in the temporary ponds

(iii) Consider safety aspects related to pit collapse due to accumulation of water

DBO

Contractor

(v) Areas for stockpiles, storage of fuels and lubricants and waste materials;

(vi) Records of surface water quality inspection;

(vii) Effectiveness of water management measures;

(viii) No visible degradation to nearby drainages, nallahs or water bodies due to civil

Cost for implementation of mitigation measures responsibility of

contractor.

Page 161: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

160

works Noise and Vibration Levels

Increase in noise level due to earth- moving and excavation equipment, and the transportation of equipment, materials, and people

(i) Plan activities in consultation with PIU so that activities with the greatest potential to generate noise are conducted during periods of the day which will result in least disturbance;

(ii) Minimize noise from construction equipment by using vehicle silencers, fitting jackhammers with noise-reducing mufflers, and use portable street barriers to minimise sound impact to surrounding sensitive receptor; and

(iii) Maintain maximum sound levels not exceeding 80 decibels (dBA) when measured at a distance of 10 m or more from the vehicle/s.

(iv) Identify any buildings at risk from vibration damage and avoiding any use of pneumatic drills or heavy vehicles in the vicinity;

(v) Horns should not be used unless it is necessary to warn other road users or animals of the vehicle’s approach;

(vi) Consult local communities in advance of the work to identify and address key issues, and avoid working at sensitive times, such as religious and cultural festivals.

DBO Contractor (ix) Complaints from sensitive receptors;

(x) Use of silencers in noise-producing equipment and sound barriers;

(xi) Equivalent day and night time noise levels

Cost for implementation of mitigation measures responsibility of

contractor.

Generation of Construction wastes

Impacts due to excess excavated earth, excess construction materials, and solid

(i) Prepare and implement a Construction Waste (Spoils) Management Plan

(ii) As far as possible utilize the debris and excess soil in construction purpose, for example for raising the ground level or construction of access roads etc.,

DBO Contractor (i) Complaints from sensitive receptors;

(ii) Worksite clear of hazardous wastes such as

Cost for implementation of mitigation measures responsibility of contractor.

Page 162: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

161

waste such as removed conc re te , wood, packaging materials, empty containers, spoils, oils, lubricants, and other similar items

(iii) Avoid stockpiling any excess spoils at the site for long time. Excess excavated soils should be disposed off to approved designated areas immediately

(iv) If disposal is required, the site shall be selected preferably from barren, infertile lands; sites should have located away from residential areas, forests, water bodies and any other sensitive land uses

(v) Domestic solid wastes should be properly segregated in biodegradable and non-biodegradable for collection and disposal to designated solid waste disposal site; create a compost pit at worker’s camp sites for disposal of biodegradable waste; non-biodegradable / recyclable material shall be collected separately and sold in the local recycling material market

(vi) Residual and hazardous wastes such as oils, fuels, and lubricants shall be disposed off in disposal sites approved by TNPCB;

(vii) Prohibit burning of construction and/or domestic waste;

(viii) Ensure that wastes are not haphazardly thrown in and around the project site; provide proper collection bins, and create awareness to use the dust bins.

(ix) Conduct site clearance and restoration to original condition after the completion of construction work; PIU to ensure that site is properly restored prior to issuing of construction completion certificate

oil/fuel

(iiv) Worksite clear of

any excess excavated earth, excess construction materials, and solid waste such as removed concrete, wood, packaging materials, empty containers

Page 163: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

162

Existing Infrastructure and Facilities

Disruption of service and damage to existing infrastructure at specified project location

(i) Obtain from PIU the list of affected utilities and operators if any;

(ii) Prepare a contingency plan to include actions to be done in case of unintentional interruption of service

DBO Contractor

Existing Utilities Contingency Plan

Cost for implementation of mitigation measures responsibility of contractor.

Ecological Resources –

Terrestrial

Loss of vegetation

and tree cover

(i) Minimize removal of vegetation and disallow cutting of trees; (ii) If tree-removal w i l l be required, obtain tree-cutting permit and (iii) Plant 5 native trees for every one that is removed.

DBO Contractor PIU to report in writing the no of trees cut and planted.

Cost for implementation of mitigation measures responsibility of contractor.

Land use Environmental

Issues due to land use change

The impact due to change in land use will be negligible due to this project.

Not applicable Not applicable Not applicable

Accessibility and Traffic Disruption

Traffic problems and conflicts near project locations and haul road

For Sewer Works;

(i) Prepare a sewer work implementation; ensure that for each road where the work is being undertaken there is an alternative road for the traffic movement; take up the work in sequential way so that public inconvenience is minimal

(ii) Provide temporary diversions, where necessary and effectively communicate with general public

(iii) Undertake the work section wise (iv) Confine work areas in the road

carriageway to the minimum possible extent; all the activities, including material and

DBO

Contractor

(i) Traffic route during construction works including number of permanent signages, barricades and flagmen on worksite (Appendix 10);

(ii) Complaints from

sensitive receptors; (iii)

Cost for implementation of mitigation measures responsibility of contractor.

Page 164: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

163

waste/surplus soil stocking should be confined to this area.

(v) Proper barricading should be provided; avoid material/surplus soil stocking in congested areas – immediately removed from site/ or brought to the as and when required

(vi) Limit the width of trench excavation as much as possible by adopting best construction practices; adopt vertical cutting approach with proper shoring and bracing; this is especially to be practiced in narrow roads and deeper sewers; if the deep trenches are excavated with slopes, the roads may render completely unusable during the construction period

(vii) Leave spaces for access between mounds of soil to maintain access to the houses / properties; access to any house or property shall not be blocked completely; alternative arrangements, at least to maintain pedestrian access at all times to be provided

(viii) Provide pedestrian access in all the locations; provide wooden/metal planks over the open trenches at each house to maintain the access.

(ix) Inform the affected local population 1-week in advance about the work schedule

(x) Plan and execute the work in such a way that the period of disturbance/ loss of access is minimum.

(xi) Keep the site free from all

Number of signages placed at project location.

Page 165: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

164

unnecessary obstructions; (xii) Notify affected public by public

information notices, providing sign boards informing nature and duration of construction works and contact numbers for concerns/complaints. Provide information to the public through media – newspapers and local cable television (TV) services

(xiii) At work site, public information/caution boards shall be provided including contact for public complaints

Hauling

(material,

waste/debris

and

equipment)

activities

Traffic problems and conflicts near project locations and haul road

(i) Plan transportation routes so that heavy vehicles do not use narrow local roads, except in the immediate vicinity of delivery sites

(ii) Schedule transport and hauling activities during non-peak hours;

(iii) Drive vehicles in a considerate manner Notify affected public by public information notices, providing sign boards informing nature and duration of construction works and contact numbers for concerns/complaints.

DBO

Contractor

(i) Traffic route during construction works including number of permanent signages, barricades and flagmen on worksite (Appendix 10);

(ii) Complaints from

sensitive receptors; (iii) Number of signages placed at project location.

Cost for implementation of mitigation measures responsibility of contractor.

Socio-

Economic –

Impede the access

(i) Inform all businesses and residents about the nature and duration of

DBO (i) Complaints from

sensitive

Cost for

implementatio

Page 166: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

165

Income of residents and customers to nearby shops

any work well in advance so that they can make necessary preparations;

(ii) Do not block any access; leave spaces for access between barricades/mounds of excavated soil and other stored materials and machinery, and providing footbridges so that people can crossover open trenches

(iii) Barricade the construction area and regulate movement of people and vehicles in the vicinity, and maintain the surroundings safely with proper direction boards, lighting and security personnel – people should feel safe to move around

(iv) Control dust generation (v) Immediately consolidate the

backfilled soil and restore the road surface; this will also avoid any business loss due to dust and access inconvenience of construction work.

(vi) Employee best construction practices, speed up construction work with better equipment, increase workforce, etc., in the areas with predominantly commercial, and with sensitive features like hospitals, and schools;

(vii) Consult businesses regarding operating hours and factoring this in work schedules; and Provide sign boards for pedestrians to inform nature and duration of construction works and

Contractor receptors;

(ii) Spoils management plan

(iii) Number of walkways, signages, and metal sheets placed at project location.

n of mitigation measures responsibility of contractor.

Page 167: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

166

contact numbers for concerns/complaints.

Socio-

Economic –

Employment

Generation of temporary employment and increase in local revenue

Employ local labour force as far as possible

DBO Contractor (i)Employment records;

(iii) Compliance to

labor laws (see Appendix 6 of this

IEE)

Cost for implementation of mitigation measures responsibility of contractor

Occupationa

l Health and

Safety

Occupational hazards which can arise during work

(i) Comply with all national, state and local labour laws; (see Appendix 6 of this IEE)

(ii) Following internationally recognized health and safety standards such as the World Bank Group’s Environment, Health and Safety Guidelines (IFC’s General EHS Guidelines9 and Sector Specific (Water and Sanitation) Guidelines10).

(iii) Develop and implement site-specific Occupational Health and Safety (OHS) Plan which shall include measures such as: (a) safe and documented construction procedures to be followed for all site activities; (b) ensuring all workers are provided with and use personal protective equipment; (c) OHS Training11 for all site

DBO Contractor (i) Site-specific OH&S Plan;

(ii) Equipped

first-aid stations;

(iii) Medical insurance

coverage for workers; (iv) Number of accidents;

(v) Supplies of potable

drinking water;

(vi) Clean eating areas where

Cost for implementation of mitigation measures responsibility of contractor.

9https://www.ifc.org/wps/wcm/connect/554e8d80488658e4b76af76a6515bb18/Final%2B-%2BGeneral%2BEHS%2BGuidelines.pdf?MOD=AJPERES 10 https://www.ifc.org/wps/wcm/connect/e22c050048855ae0875cd76a6515bb18/Final%2B-%2BWater%2Band%2BSanitation.pdf?MOD=AJPERES

Page 168: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

167

personnel, (d) excluding public from the work sites; and (e) documentation of work-related accidents; Follow International Standards such as the World Bank Group’s Environment, Health and Safety Guidelines12.

(iv) Ensure proper safety measures during trench excavation; provide bracing / shoring in all trenches of more than 1.5 m deep; no overburden soil, material, equipment etc., shall be placed along the deep trenches; safety training shall be provided to workers; where required provide supports anchors or suitable arrangement to nearby building to avoid any safety risk

(v) Ensure that qualified first-aid is provided at all times.

(i) Secure all installations from unauthorized intrusion and accident risks

(ii) Provide health and safety orientation training to all new workers to ensure that they are apprised of the basic site rules of work at the site, personal protective protection, and preventing injuring to fellow workers;

(iii) Ensure the visibility of workers through their use of high visibility vests when working in or walking

workers are not exposed to hazardous or noxious substances; (vii) record of H&S orientation trainings

(viii) personal

protective equipment; (ix) % of moving equipment outfitted with audible back-up alarms;

(xi) permanent s ign

boards for hazardous areas such as energized electrical devices and lines, service rooms housing high voltage

equipment, and areas

for storage

Page 169: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

168

through heavy equipment operating areas;

(iv) Ensure moving equipment is outfitted with audible back-up alarms;

(v) Mark and provide sign boards for hazardous areas such as energized electrical devices and lines, service rooms housing high voltage equipment, and areas for storage and disposal. Signage shall be in accordance with international standards and be well known to, and easily understood by workers, visitors, and the general public as appropriate; and

(vi) Disallow worker exposure to noise level greater than 85 dBA for duration of more than 8 hours per day without hearing protection. The use of hearing protection shall be enforced actively.

(vii) Provide supplies of potable drinking water;

(viii) Provide clean eating areas where workers are not exposed to hazardous or noxious substances

and disposal.

(xii) Compliance to core labor laws (see Appendix 6 of this IEE

Page 170: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

169

Community

Health and

Safety

Traffic accidents and vehicle collision with pedestrians during material and waste transportation

(i) Ensure proper safety measures during trench excavation; provide bracing / shoring in all trenches of more than 1.5 m deep; no overburden soil, material, equipment etc., shall be placed along the deep trenches; safety training shall be provided to workers; where required provide supports anchors or suitable arrangement to nearby building to avoid any safety risk

(ii) Confine work areas; prevent public access to all areas where construction works are on-going through the use of barricading and security personnel

(iii) Attach warning signs, blinkers to the barricading to caution the public about the hazards associated with the works, and presence of deep excavation

(iv) Provide proper boundary for the site, especially high compound wall towards temple and school residential area

(v) Contractor shall create awareness and no activities shall be extended outside the site, especially towards the temple and school (in case of IPS); enfore strict site rules so that there is no disturbance or safety risk

(vi) Minimize the duration of time when the sewer trench is left open through careful planning; plan the work properly from excavation to refilling and road relaying

(vii) Control dust pollution – implement dust control measures as

DBO

Contractor

(i) Traffic Management

Plan;

(ii) Complaints from sensitive receptors

Cost for

implementation of mitigation measures responsibility of contractor.

Page 171: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

170

suggested under air quality section (viii) Ensure appropriate and safe

passage for pedestrians along the work sites

(ix) Provide road signs and flag persons to warn of on-going trenching activities.

(x) Restrict construction vehicle movements to defined access roads and demarcated working areas (unless in the event of an emergency)

(xi) Enforce strict speed limit (20 kmph) for plying on unpaved roads, construction tracks

(xii) At sensitive locations particularly where there are schools and markets close to the road, awareness of safety issues will be raised through neighbourhood awareness meetings

(xiii) All drivers and equipment operators will undergo safety training

(xiv) Maintain regularly the construction equipment and vehicles; use manufacturer-approved parts to minimize potentially serious accidents caused by equipment malfunction or premature failure.

(xv) Overall, the contractor should comply with IFC EHS Guidelines Community Health and Safety (this can be downloaded from http://www1.ifc.org/wps/wcm/connect/dd67

(xvi) 3400488559ae83c4d36a6515bb18/3%2BCo

(xvii) mmunity%2BHealth%2Band%2BS

Page 172: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

171

afety.pdf?MOD=AJPERES xviii)

Safety of sensitive groups (children, elders etc.) and others pedestrians in narrow

Trench excavation in in narrow streets will pose high risk to children

(i) Provide prior information to the local people about the nature and duration of work

(ii) Conduct awareness program on safety during the construction work

(iii) Undertake the construction work stretch-wise; excavation, pipe laying and trench refilling should be

DBO Contractor Complaints from neighbourhood a n d monitoring of accidents

Cost for implementation of mitigation measures responsibility of contractor.

Page 173: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

172

streets and elders

in the locality

completed on the same day (iv) Provide barricades, and

deploy security personnel to ensure safe movement of people and also to prevent unnecessary entry and to avoid accidental fall into open trenches

Constructio

n Camps Temporary a i r and noise pollution from machine operation, water pollution from storage and use of fuels, oils, solvents, and lubricants

Unsanitary and poor living conditions for workers

(i) The contractor should establish and operate the temporary worker camps in compliance with IFC EHS Guidelines specific to worker’s accommodation ((this can be downloaded from http://www1.ifc.org/wps/wcm/connect/topics_ext_content/ifc_external_corporate_site/ifc+sustainability/publications/publications_gpn_work ersaccommodation), including the following:

(ii) Consult PIU before locating project offices, sheds, and construction plants;

(iii) Select a camp site away from residential areas (at least 100 m buffer shall be maintained) or locate the camp site within the existing facilities of City Corporation

(iv) Avoid tree cutting for setting up camp facilities

(v) Provide a proper fencing/compound wall for camp sites

(vi) Camp site shall not be located near (100 m) water bodies, flood plains flood prone/low lying areas, or any ecologically, socially,

DBO Contractor (i) Complaints from sensitive receptors;

(ii) Drinking water and sanitation facilities for employees

Cost for implementation of mitigation measures responsibility of contractor.

Page 174: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

173

archeologically sensitive areas (vii) Separate the workers living areas

and material storage areas clearly with a fencing and separate entry and exit

(viii) Ensure conditions of liveability at work camps are maintained at the highest standards possible at all times; living quarters and construction camps shall be provided with standard materials (as far as possible to use portable ready to fit-in reusable cabins with proper ventilation); thatched huts, and facilities constructed with materials like GI sheets, tarpaulins, etc., shall not be used as accommodation for workers

(ix) Camps shall be provided with proper drainage, there shall not be any water accumulation

(x) Provide drinking water, water for other uses, and sanitation facilities for employees

(xi) Prohibit employees from cutting of trees for firewood; contractor should provide cooking fuel (cooking gas); fire wood not allowed

(xii) Train employees in the storage and handling of materials which can potentially cause soil contamination

(xiii) Wastewater from the camps shall be disposed properly either into sewer system; if sewer system is not available, provide on-site sanitation with septic tank and soak pit arrangements

Page 175: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

174

(xiv) Recover used oil and lubricants and reuse or remove from the site;

(xv) Manage solid waste according to the following preference hierarchy: reuse, recycling and disposal to designated areas; provide a compost pit for bio degradable waste, and non-biodegradable / recyclable waste shall be collected and sold in local market

(xvi) Remove all wreckage, rubbish, or temporary structures which are no longer required; and

(xvii) At the completion of work, camp area shall be cleaned and restored to pre-project conditions, and submit report to PIU; PIU to review and approve camp clearance and closure of work site

Submission of EMP implementation report

Unsatisfactory compliance to EMP

(i) Appointment of (I) EHS Supervisor to ensure EMP implementation

(ii) Timely submission of monitoring reports including pictures

DBO

contractor

Availability and competency of appointed supervisor Monthly report

Cost for implementation of mitigation measures responsibility of contractor.

Post-construction clean-up

Damage due to debris, spoils, excess construction materials

(i) Remove all spoils wreckage, rubbish, or temporary structures (such as buildings, shelters, and latrines) which are no longer required; and

(ii) All excavated roads shall be reinstated to original condition. (iii) All disrupted utilities restored (iv) All affected structures rehabilitated/compensated

(iii) The area that previously housed the construction camp is to be checked for spills of substances

DBO Contractor PIU/PDMC report in writing that (i) worksite is restored to original conditions; (ii) camp has been vacated and restored to pre-project conditions; (iii) all

Cost for implementation of mitigation measures responsibility of contractor.

Page 176: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

175

such as oil, paint, etc. and these shall be cleaned up.

(iv) All hardened surfaces within the construction camp area shall be ripped, all imported materials removed, and the area shall be top soiled and regrassed using the guidelines set out in the revegetation specification that forms part of this document.

(v) The contractor must arrange the cancellation of all temporary services.

(vi) Request PIU to report in writing that worksites and camps have been vacated and restored to pre-project conditions before acceptance of work

construction related structures not relevant to O&M are removed; and (iv) worksite clean-up is satisfactory.

Page 177: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

176

Table 30:- Environmental Management Plan of Anticipated Impacts during Operation

Field AnticipatedImpact MitigationMeasures Responsiblefor

Mitigation Monitoring of Mitigation

Costand Sourceof Funds

Check for blockage and leakage and overflow problems in sewers

It may affect the sewer system, contaminate land, water and create public health issues

(i) Effective operation to avoid and/or immediate clearance of such leaks, blockages

(ii) Implementation of regular O&M schedules

DBO Contractor AnjadNagar Parishad

Project operating costs

Occupational Health & Safety:

Occupational health &safety: for personnel cleaning underground sewers there is a risk due to oxygen deficiency and harmful gaseous emissions (hydrogen sulphide, carbon monoxide, methane, etc.);

(i) Provide necessary health & safety training to the staff engaged sewer cleaning & maintenance; no manual cleaning should be carried out

(iii) provide appropriate personal protection equipment (including oxygen masks) to workers entering into sewage manhole for inspection/repairs

DBO Contractor AnjadNagar Parishad

Project operating costs

Page 178: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

177

STP operation – malfunction and effect on efficiency

Public health, safety and environmental impacts

(i) Ensure proper knowledge transfer, hands-on training to municipal staff engaged in STP operation has been provided by contractor prior to handover of facility (ii) Ensure continuous uninterrupted power supply (iii) Operate and maintain the facility following standard operating procedures of operational manual (iv) Undertake preventive and periodic maintenance activities as required (v) Maintain the mechanical / electrical parts as per the maintenance plan to avoid any hazards (vi) Conduct periodic training to workers (vii) Ensure that all safety apparatus at STP including personal protection equipment are in good condition all times; and are at easily accessible and identifiable place; periodically check the equipment, and conduct mock drills to deal with emergency situations (viii) Implement sludge management plan at the STP (x) Conduct regular wastewater quality monitoring (at inlet and at outlet of STP) to check compliance with design parameters (BOD < 10 mg/l, TSS < 100 mg/l, Faecal coliform < 100/100 ml (xi) Conduct periodic testing of dried sludge/compost to check presence of heavy metals and confirming stipulated concentrations to use as compost. It shall not be used for food crops. (xii)Safe sludge handling methods shall be employed. PPE shall be provided. Sludge shall be dried in drying beds before disposal

DBO Contractor Anjad Nagar Parishad / PMU

Project operating costs

Page 179: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

178

Operation of sewage pumpingstations

Odour nuisance (i) Strictly follow standard operating procedures / operational manual for operation and maintenance of lifting and pump stations

(ii) Ensure that operating staff is properly trained, and have clear understanding of odour issues vis-à-vis its related with operational practices

(iii) Ensure that pumping cycles are properly followed; and there is no buildup of sewage beyond design volume in the wells

DBO Contractor Anjad Nagar Parishad/PMU

Project operating costs

Generation of waste materials

Impacts on public health and environment

Collect solid wastes and dispose to approved disposal yards

DBO Contractor Anjad Nagar Parishad / PMU

Project Operating costs

Table 31:-Environmental Monitoring Plan – Pre Constrction and Construction

Monitoring field Monitoring location

Monitoring parameters Frequency Responsibility Cost & Source of Funds

Water quality of receiving water body – treated water discharge from STP

At the discharge location

pH, TDS, TSS, DO, BOD, COD, E-coli, Total coliform, Nitrate, Total Phosphates, Oil & grease, Total hardness, Sulphate, Fluoride, Chloride, Ammonia, Aluminum, Manganese, Iron, Zinc, Nickel, Magnesium, Chromium, Arsenic, Mercury, Cadmium, Lead,

Twice during design / prior to start of construction

(Pre-monsoon, if water is available in the drain and during monsoon)

DBO Contractor

Project costs

Page 180: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

179

Construction disturbances, nuisances, public & worker safety,

All work sites Implementation of dust control, noise control, traffic management, & safety measures. Site inspection checklist to review implementation is

appended at Appendix11

Weekly during construction

Supervising staff and safeguards specialists

No costs required

Ambient air quality 06 locations (01 STP site, 05 worksites)

PM10, PM2.5, NO2, SO2, CO

Once before start of construction Quarterly (yearly4-times) during construction (2 year) period considered)

DBO Contractor Cost for implementation of monitoring measures responsibility of contractor (54 samples x 5000 per sample = 2,70,000)

Ambient noise 06 locations (01 STP site, 05 worksites)

Day time and night time noise levels

Once before start of construction Quarterly (yearly4-times) during construction (2 year) period considered))

DBO Contractor Cost for implementation of monitoring measures responsibility of contractor (54 samples x 1500 per sample = 81,,000)

Surface water quality

1location (near STP construction site) (Rainy drain/Bhongli Nala)

pH, Oil & grease, Cl, F, NO3, TC, FC, Hardness, Turbidity BOD, COD, DO, Total Alkalinity

Once before start of construction Monthly during

Construction (12 months period considered)

DBO Contractor Cost for implementation of monitoring measures responsibility of contractor (13 samples x 4000 per sample = 52,000)

Page 181: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

180

Table 32:-Environmental Monitoring Plan of Anticipated Impacts during Operation

Monitoringfield Monitorin

g location Monitoringparameters Frequency Responsibility Cost& Source

Of Funds

Monitoring of quality of STP eff luent

At Inlet and Outlet • Parameters as specified by MPPCB in the consent.

• Concentration of various parameters in treated wastewater shall be within the specific limits by MPPCB,

• Concentrations must also be within the following STP design parameter

• BOD less than 10 mg/l • Suspended solids less than 100 mg/l • Faecal coliform less than 1000/100 ml

Monthly once

Operating agency (DBO Contractor /Anjad Nagar Parishad (ANP)

O&Mcosts

Water quality of receiving water body – Narmada River

Bingla nala

Upstream (50 m) and downstream (50 m) of proposed discharge location - pre & post monsoon

• pH, Cl, F, NO3, TC, FC, Hardness, Turbidity BOD, COD, DO, Total Alkalinity,

Yearly twice Operating agency (DBO Contractor /ANP)

O&Mcosts

Sediment quality Assessment of existing drain at discharge point.Bhongli Nala

At discharge point Assessment of sediment quality of existing drain & Bhongli nala at discharge point

Monthly once

Operating agency (DBO Contractor /ANP)

O&Mcosts

Sludge quality and suitability as manure

STP Analysis for concentration of heavy metals and confirm that value are within the following limits (see Table below)

Yearly once Operating agency (DBO Contractor /ANP)

O and M costs (testing to be done at an accredited external laboratory)

In order to ensure safe application of compost, the following specifications for compost quality shall be met, namely

Parameters Units Organic Compost

(FCO 2009)

Phosphate Rich Organic Manure

(FCO 2013)

Page 182: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

181

In order to ensure safe application of compost, the following specifications for compost quality shall be met, namely

Parameters Units Organic Compost

(FCO 2009)

Phosphate Rich Organic Manure

(FCO 2013) Arsenic mg/kg 10 10 Cadmium mg/kg 5 5 Chromium 50 50 Copper 300 300 Lead 100 100 Mercury 0.15 0.15 Nickel 50 50 Zinc 1000 1000 C/N ratio <20 <20:1 PH 6.5 – 7.5 (1:5 solution) maximum 6.7 Moisture, percent by weight, maximum

15.0 – 25.0 25.0

Bulk density (g/cm3) <1 Less than 1.6 Total Organic Carbon, per cent by weight, minimum

12 7.9

Total Nitrogen (as N), per cent by weight, minimum

percent by weight 0.8 0.4

Total Phosphate (as P205) percent by weight, minimum

percent by weight 0.4 10.4

Total Potassium (as K20), percent by weight, minimum

percent by weight 0.4 -

Colour Odour Absence of foul Odor

Particle size minimum 90% material should pass through 4.0 mm is sieve

minimum 90% material should pass through 4.0 mm is sieve

Conductivity, not more Than

dsm-1 4 8.2

* compost (final product) exceeding the above stated concentration limits shall not be used for food crops. however, it may be utilized for purposes other than growing food crops. Source: Standards for Composting, Schedule II A, Solid Waste Management Rules, 2016

Page 183: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

182

B. Implementation Arrangements

196. Urban Development and Environment Department (UDED) of Government of Madhya

Pradesh will be the Executing Agency for the Program, responsible for management, coordination and execution of all activities funded under the loan. Implementing Agency will be the recently established Madhya Pradesh Urban Development Company (MPUDC), a wholly owned subsidiary of GoMP. A central Project Management Unit (PMU) attached to MPUDC will be responsible for implementing the MPUSIP. The PMU will be supported by Program Implementation Units (PIUs) with a flexibility to redeployment depending upon the implementation requirements.

197. The PMU and PIUs will be supported by several teams of Design Consultants in

preparation of preliminary engineering designs.

198. Program Management Consultant (PMC) centrally located in PMU and with field teams located in PIUs shall be responsible for implementation of the Program. All infrastructure contracts will be procured through performance-based contracts (PBCs) and include build- operate (BO) framework. Based on the preliminary designs prepared by Design Consultants, the DBO (design-build-operate) Contractor will design, construct, commission and operate for10 years, after which it will be transferred to the respective ULB.

199. Two Committees - an Empowered Committee cum Executive Committee and a Technical

Clearance and Tender Committee have been constituted by the Government to be responsible for effective and timely implementation of the Program.

200. Safeguards Compliance Responsibilities: At PMU there will be two safeguard

specialists: (i) Project Officer (Environment) and (ii) Social & Gender Offer, who will responsible for compliance with the environmental and social safeguards in program implementation. PO (Environment) will have overall responsibility in implementation of the investment program as per the Environmental Assessment & Review Framework (EARF) agreed between ADB and the government. At individual subproject level, PO will ensure that environmental assessment is conducted, and a project-specific is prepared and implemented, and the compliance, and corrective actions, if any are reported as required.

201. PMU Responsibilities: PO (Environment) will be supported by PMC, which will be

staffed with an Environmental Specialist, and Environmental Coordinators. Key tasks and responsibilities of the PO (Environment) for this subproject include the following:

Biddingstage:

(i) Prior to invitation of bids for civil works contract, ensure that a. Consent for establishment(CFE) is obtained from MPPCB forSTPconstruction (ii) Ensure that EMP is included in bidding documents and civil works contracts (iii) Ensure that the bid/contract documents include specific provisions requiring

contractors to comply with all applicable labor laws and core labor standards including:

Page 184: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

183

a. Labour welfare measures and provision of amenities b. Prohibition of child labor as defined in national legislation for construction and

maintenance activities; c. Equal pay for equal work of equal value regardless of gender, ethnicity, or caste; d. elimination of forced labor; e. the requirement to disseminate information on sexually transmitted diseases,

including HIV/AIDS, to employees and local communities surrounding the project sites.

(iv) Ensure that staffrequired for implementation of EMP (EHS officer for Anjad) is included in the bid requirements

(v) Ensure that EMP cost is included in the project cost (vi) In the pre-bid meeting, provide insight into the EARF requirements, IEE update,

EMPmeasures, and overall compliancerequirements to the bidders

Constructionstage:

(i) Facilitate and ensure that all necessary environmental clearances/permissions, including that of contractor’s are in place prior to start of construction

(ii) Organize an induction course for the training of contractors, preparing them on EMP implementation, environmental monitoring, and on taking immediate action to remedy unexpected adverse impacts or ineffective mitigation measures found during the course of implementation.

(iii) Provide oversight on environmental management aspects of subprojects and ensureEMPs are implemented by PIU and contractors

(iv) Supervise and provide guidance to the PIUs to properly carry out the environmental monitoring as per the EMP

(v) Oversee grievance redress mechanism to address any grievances brought about in a timely manner; ensure that records are properly maintained

(vi) Consolidate monthly environmental monitoring reports from PIU and submit semi-annualmonitoring reports to ADB

(vii) Oversee site closures to ensure that all work / facility sites are restored properly prior to issuing work completion certificate to the contractor

Operationstage:

(i) Ensure and consent for operation (CFO) is obtained from MPPCB for STP prior to

start of operation 202. PIU Responsibilities: PIU will be headed by a Project Manager and supported by PMC.

An Assistant Project Manager of PIU will be given additional responsibilities of safeguard tasks and will be designated as Assistant Environmental Officer (ASO). ASO will be supported by PDMC Environmental Specialist and Environmental Coordinator. Key tasks and responsibilities of the ASO for this subproject include the following:

(i) Provide necessary support to PIU and Nagar Parishad in obtaining permission

fromMPPCB; liaison with PMU and regulatory agencies (ii) Oversee day-to-day implementation of EMPs by contractors, including compliance

with all government rules and regulations, take necessary action for obtaining rights of way

(iii) Oversee environmental monitoring by contractors (iv) Take corrective actions when necessary to ensure no environmental impacts

Page 185: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

184

(v) Submit monthly environmental monitoring reports to PMU (vi) Conduct continuous public consultation and awareness (vii) Address any grievances brought about through the grievance redress mechanism in

a timely manner as per the EMP 203. Contractor’s Responsibilities;

Biddingstage:

(i) Understand the EMP requirements and allocate necessary resources (budget, staff, etc.

(ii) Understand the regulatory compliance requirements related to labour welfare, safety, environment etc.,

Designstage:

(i) Review the IEE Report including the REA checklist, category and theEMP, and

conduct site visits to understand the environmental sensitivity of the project sites. (ii) Update the REA checklist, confirm the category, and update/revise the IEE Report

of the projectreflecting the changes /amendments /additions that areeffected in the project during the detailed design

(iii) Update/revise and finalize the EMP (iv) Provide all necessary technical assistance toPIU / ULB in obtaining regulatory

clearances/approvals. (v) Ensure that all design-related measures of theEMP, and conditions, if any, of

government regulatory agencies (like MPPCB consent conditions) are duly included in the final designs.

Constructionstage:

(i) Ensure that allregulatory clearances (both projectrelated and contractor related) are

in place before start of the construction work. (ii) MobilizeEHS officersupervisor prior to start of work (iii) Confirm withPIU availability of rights of way at all project sites prior to start of work. (iv) Prepare and submit: a. Construction waste management(CWM) plan b. Traffic management(TM) plan (v) Implement the mitigation measures as per the EMP including CWM& TM Plans (vi) Follow theEMP measures/guidelines for establishment of temporary construction

camps, construction waste disposal sites, and material borrow areas, etc. (vii) Implement EMP and ensure compliance with all the mitigation and enhancement

measures (viii) Conduct environmental monitoring (air, noise, water etc.,) as per the EMP (ix) Undertake immediate action as suggested byPIU/PMU/PMC toremedy unexpected

adverse impacts or ineffective mitigation measures found during the course of implementation

(x) Submit monthly compliancereports onEMP implementation (xi) Act promptly on public complaints and grievancesrelated to construction work and

redress ina timely manner in coordination with PIU (xii) Comply with applicable governmentrules and regulations

Page 186: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

185

Operationstage:

(i) Obtain CFO from MPPCB in coordination with the ULB, and comply with MPPCB

conditions, if any, during the operation phase (ii) Implement the operation phaseEMP including the monitoring plan (iii) Submit quarterlyEMP implementation report

C. Training Needs

204. The following Table 33 presents the outline of capacity building program to ensure EMP

implementation. The estimated cost is Rs.100,000 (excluding trainings of contractors which will be part of EMP implementation cost during construction) to be covered by the project ’s capacity building program. The detailed cost and specific modules will be customized for the available skill set after assessing the capabilities of the target participants and the requirements of the project by the ES of PDMC.

Table 33:-Outline Capacity Building Programon EMP Implementation

Description Target Participants& Venue

Estimate (INR)

Cost and Source of Funds

1. Introduction and Sensitization to Environmental I s s u e s (1 day)

- ADB Safeguards Po l i c y Statement - Government o f India and Madhya Pradesh applicable safeguard laws, regulations and policies including but not limited to core labor standards, OH&S, etc. - Incorporation o f EMP into the project design and contracts - Monitoring, reporting and corrective action planning

All staff and consultants involved i n

the project

At PMU, Bhopal (combined program for all subprojects)

- Included in the overall program cost

2. EMP implementation (1/2 day)

- EMP mitigation & monitoring measures -Roles and responsibilities - Public relations, - Consultations

- Grievance r e d r e s s - Monitoring and corrective action planning - Reporting and disclosure

- Construction site standard operating procedures (SOP) -- Chance find (archeological) p r o t o c o l

- AC pipe protocol - Traffic management plan - Waste management plan

- Site clean-up & restoration

All PIU staff,

contractor staff and consultants involved i n the Anjad subproject

At PIU

INR

100,000 (Lump sum)

Included in

subproject cost estimates

Page 187: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

186

3. Contractors Orientation to Workers (1/2 day) - Environment, h e a l t h and safety in project

construction

Once before start of work, and thereafter regular briefing every month once. Daily briefing on safety prior to start of work

All workers (including unskilled laborers)

- Contractors cost

D. Monitoring and Reporting

205. Immediately after mobilization and prior to commencement of the works, the contractor

will submit a compliance report to PIU that all identified pre-construction mitigation measures as detailed in the EMP are undertaken. Contractor should confirm that the staff for EMP implementation (EHS supervisor) is mobilized. PMU with the assistance of the PDMC will review the report and permit commencement of works.

206. During construction, results from internal monitoring by the contractor will be reflected in

their monthly EMP implementation reports to the PIU. ASO will review and advise contractors for corrective actions if necessary. Quarterly report summarizing compliance and corrective measures taken will be PMC field team at PIU and submitted to PMU (Appendix 12). During operation, the contractor will conduct management and monitoring actions as per the operation stage EMP, and submit to PMU and ULB a quarterly report on EMP implementation and compliance.

207. Based on monthly & quarterly reports and measurements, PMU will draft, review, and

submit to ADB, 6-monthly semi-annual Environmental Monitoring Report (EMR). Once concurrence from the ADB is received the report will be disclosed in the MPUDC and PMU websites.

208. ADB will review project performance against the MPUSIP commitments as agreed in the

legal documents. The extent of ADB’s monitoring and supervision activities will be commensurate with the project’s risks and impacts. Monitoring and supervising of social and environmental safeguards will be integrated into the project performance management system

E. EMP Implementation Cost

209. Most of the mitigation measures require the contractors to adopt good site practice, which

should be part of their normal procedures already, so there are unlikely to be major costs associated with compliance. The costs which are specific to EMP implementation and are not covered elsewhere in the projects are given below.

Page 188: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

187

Page 189: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

188

Table 34:- Cost Estimats to Implement the EMP

S. No. Particulars Stages Unit Total Number

Rate (INR)

Cost (INR)

Costs Covered By

A. Implementation Staff with DBO contractor

1 EHS Supervisor Construction Per month 24 50,000 1,200,000 DBO contract

Subtotal(A) 12,00,000

B. Mitigation Measures

1 Consent for establishments & consent for operation from MPPCB

Pre-& Post-construction

Lumpsum 200,000 Project costs

2 Provision for tree Cutting & compensatory plantation Measures

Construction

Per tree

100

1,000

100,000

DBO contract

3 Plantation of tree inmulti rows around STPand pumping stationssites and provision ofscreens along nala

Construction 10,00,000 DBO Contractor

4 Traffic management at worksites (Pavement Markings, Channelizing Devices, Arrow Panels and Warning Lights)

Construction Lump sum - - 200,000 DBO Contract

Page 190: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

189

Subtotal (B) 1500,000

C. Monitoring Measures

1 Air quality monitoring Construction Per sample 54 5,000 270,000 DBO Contract

2 Noise levels monitoring Construction Per sample 54 1,500 81,000 DBO Contract

3 Surface water Monitoring

Construction Per sample 13 4,000 104,000 DBO Contract

4 Effluent quality & sludge quality

Operation Lump sum / year

- - 200,000 DBO Contract

5 Odour, Noise Monitoring measures and (hand held- H2S measuring device)

Operation Lum sum - - 10,00,000 DBO Contract

Subtotal(C) 16,55,000

D. Capacity Building

1. Training on EMP implementation

Pre -construction Lumpsum 100,000 PMU

2 Preparation of plans and protocols (traffic management plan, waste(spoils) management plan etc., chance find protocol

Pre-construction Lump sum 50,000 DBO Contract

3. Contractors Orientation to Workers on EMP implementation

Prior to dispatch to work site

Lump sum 25,000 DBO Contract

Page 191: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

190

Subtotal(D) 175,000

Total (A+B+C+D) INR 45,30,000

Page 192: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

191

X. CONCLUSION AND RECOMMENDATIONS

210. The process described in this document has assessed the environmental impacts of all

elements of the infrastructure proposed under the Anjad Sewerage subproject. All potential impacts were identified in relation to pre-construction, construction, and operation phases. Planning principles and design considerations have been reviewed and incorporated into the site planning and design process wherever possible; thus, environmental impacts as being due to the project design or location were not significant.

211. Mitigation measures have been developed to reduce all negative impacts to acceptable levels. These were discussed with specialists responsible for the engineering aspects, and as a result some measures have already been included in the outline designs for the infrastructure. Various design related measures suggested for: for efficient treatment, odour control at pumping stations, uninterrupted power supply provision; standard operating procedures for operation and maintenance; and imparting necessary training for ULB staff; providing necessary safety, no manual cleaning of sewers, and personal protection equipment for workers (protection against oxygen deficiency, harmful gaseous emissions) and sludge handling, and development of green buffer zone around the IPS, MPS & STP.

212. The site selected for STP is located on the outskirts of Anjad Town. Site is surrounded by agricultural lands, and there are no notable developments within 500 m of the site boundary. It is proposed developed 20-30 m buffer around the plant with in the STP boundary. Given the proposed SBR technology with low odour and low noise, there are no impacts envisaged. STP is located on the upstream side of town. It is because of non-availability of land on the downstream side. Efforts have been made to conceptualize scheme in the north of the town (towards Narmada River), but due to high fertile agricultural fields towards river, and no availability government lands, the STP site is selected in the south of the town. With this sewage is pumped to higher elevation from SPS to STP, and then the treated water flows through the town in a nallah to Narmada River.

213. It is proposed that treated wastewater from the STP will be discharge into a drain which joins Bhongli Nala. Bhongli Nala flows down for about 13.4 km from Anjad and meets Narmada River, a large perennial river. Given the proposed treatment process of SBR, and output quality more stringent than the STP disposal standards, no impacts envisaged on receiving water body. Monitoring will be conducted during the operation.

214. Sewage pumping stations likely to generate odour and may cause nuisance to nearby areas. Various site planning, green buffer and design related measures are included in the project to prevent and control odour generation. Site selected for IPS is located on the bank of Susad River near Susad Mohalla. A temple, government middle school and community hall is located about 50m away. It is proposed to develop 20-30 m width of green buffer around the IPS within the proposed site boundary, so the buffer between IPS and temple/school and residential area will be about 70-80 m. MPS site is located near (50 m) Army hotel (a restaurant) on the bank of Bhongli nala along the main road when moves towards Chota Bardha village 50m away from habitation. There is no notable development within 50m of MPS site boundary. It is outskirts of town. It is proposed to develop 20-30 m buffer around the MPS within the proposed site boundary. High compound wall will be provided around pumping stations.. Layout plan of IPS & MPS shall be devised in such a way that it will be farthest from habitation, besides various design and operation measures are also suggested to avoid / minimize odour generation, therefore no notable impacts envisaged.

Page 193: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

192

215. All the project sites (STP and pumping stations) sites are situated on government owned

vacant land parcels, and sewers will be laid on the public roads. Therefore, subproject do not involve any private land acquisition.

216. STP malfunction or decrease in treatment efficiency will have adverse impacts. This will result in release of untreated or partially treated wastewater into river, and may cause public health issues. Besides measures to select an efficient treatment process to treat sewage, various measures are included in the design and operation phase to ensure that sewage system is operated and maintained with designed efficiency. Proper sludge management system to collect, treat and dispose safety will be developed and followed. Periodic monitoring of dried sludge to check suitability as a manure is suggested.

217. Except sewer works, all other construction activities will be confined to the selected sites, and the interference with the general public and community around is minimal. There will be temporary negative impacts, arising mainly from construction dust and noise, hauling of construction material, waste and equipment on local roads (traffic, dust, safety etc.,), mining of construction material, occupation health and safety aspects. Sewer line works will be conducted along public roads in the town with narrow and congested roads, subproject is likely to cause impacts during construction. Impacts mainly arise from the construction dust and noise; from the disturbance of residents, businesses, traffic by the construction work, safety risk to workers, public and nearby buildings due to deep trench excavations, especially in narrow roads, dust, access impediment to houses and business, disposal of large quantities of construction waste, etc. These are all general impacts of construction in urban areas, and there are well developed methods of mitigation that are suggested in the EMP.

218. Once the new system is operating, the facilities will operate with routine maintenance, which should not affect the environment. Improved system operation will comply with the operation and maintenance manual and standard operating procedures to be developed for all the activities.

219. Mitigation will be assured by a program of environmental monitoring conducted during construction and operation to ensure that all measures are implemented, and to determine whether the environment is protected as intended. This will include observations on- and off-site, document checks, and interviews with workers and beneficiaries, and any requirements for remedial action will be reported to the PMU.

220. Stakeholders were involved in developing the IEE through face-to-face discussions, on site meetings, which was conducted for larger public participation in the project. Views expressed by the stakeholders were incorporated into the IEE and the planning and development of the project. The IEE will be made available at public locations and will be disclosed to a wider audience via the MPUDC, and ADB websites. The consultation process will be continued during project implementation to ensure that stakeholders are engaged in the project and have the opportunity to participate in its development and implementation. The project’s grievance redress mechanism will provide the citizens with a platform for redress their grievances, and describes the informal and formal channels, time frame, and mechanisms for resolving complaints about environmental performance.

221. The EMP will assist the project agencies and contractor in mitigating the environmental impacts and guide them in the environmentally sound execution of the proposed project. A

Page 194: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

193

copy of the updated EMP/ SEP shall be kept on-site during the construction period at all times. The EMP shall be made binding on all contractors operating on the site and will be included in the contractual clauses. Non-compliance with, or any deviation from, the conditions set out in this document shall constitute a failure in compliance.

222. The citizens of Anjad will be the major beneficiaries of this subproject. The new sewerage system will remove the human waste from those areas served by the network rapidly and treated to an acceptable standard. In addition to improved environmental conditions, the subproject will improve the over-all public health in the project area. Diseases of poor sanitation, such as diarrhea and dysentery, should be reduced, so people should spend less on healthcare and lose fewer working days due to illness, so their economic status should also improve, as well as their overall health.

223. Therefore, as per ADB SPS, the project is classified as environmental category B and does not require further environmental impact assessment. However, to conform to government guidelines STP requires consent to establishment (CTE) and consent to operate (CTO) from Madhya Pradesh Pollution Control Board. CTE will be obtained prior to construction, as the detailed design of STP will be undertaken by contractor. Subproject is proposed under design-build-operate contract modality, and therefore various suggested measures will be included during the detailed design.

224. This IEE shall be updated by PMU during the detailed design phase to reflect any changes, amendments and will be reviewed and approved by ADB.

Page 195: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

194

Appendix 1: REA Checklist Sewerage and Sanitation

Instructions:

▪ This checklist is to be prepared to support the environmental classification of a project. It is to be attached to the environmental categorization form that is to be prepared and submitted to the Chief Compliance Officer of the Regional and Sustainable Development Department.

▪ This checklist is to be completed with the assistance of an Environment Specialist in a Regional Department.

▪ This checklist focuses on environmental issues and concerns. To ensure that social dimensions are adequately considered, refer also to ADB checklists and handbooks on (i) involuntary resettlement, (ii) indigenous peoples planning, (iii) poverty reduction, (iv) participation, and (v) gender and development.

▪ Answer the questions assuming the “without mitigation” case. The purpose is to identify potential impacts. Use the “remarks” section to discuss any anticipated mitigation measures.

Country / Project Title: India / Madhya Pradesh Urban Service Improvements Program -

Anjad Sewerage and Sanitation Subproject

Sector Division: Urban Development

SCREENING QUESTIONS Yes No REMARKS

Sewerage & Sanitation

A. Project Siting Is the project area…

▪ Densely populated? Subproject activities extend to the entire town including the densely populated areas . There are no major negative impacts envisaged, because sewer line will be located in unused government lands alongside the existing roads and can be constructed without causing disturbance to, houses , and commercial establishments. In narrow streets, disruption to road users is likely, and measure like bes t activity scheduling, alternative routes , prior information to road users , houses and s hops will minimize the impact to acceptable levels . The proposed STP site on the outskirts of the town and is away from human settlements approximately 400 meters from its premises. The proposed collector and mains alignment is similar to that of any small urban area and adequate provisions have been incorporated in to the project design to mitigate those are unavoidable. Also the proposed project will improve the environmental conditions and quality of life in that area.

▪ Heavy with development

activities ?

No

Page 196: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

195

▪ Adjacent to or withinany environmentallysensitive areas?

No

• Cultural heritage site

No

• Protected Area No

• Wetland No

• Mangrove No

• Es tuarine No

• Buffer zone of protected area

No

• Special area for protecting biodiversity

No

• Bay No

B. Potential EnvironmentalImpacts Will the Projectcause…

• Impairment of historical/cultural monuments /areas and loss /damage to thesesites?

No

• Interference with otherutilities and blocking ofaccess to buildings; nuisanceto neighbouring areas due tonoise, smell, and influx ofinsects, rodents, etc.?

The sewer pipeline alignment has been designed as aburied conduit and access across the ROW shall not bedisturbed after completion of the works. Where pipelaying activities shall affect existing access roads,alternative crossings shall be provided during theconstruction period. Existing access roads shall berestored to their existing or better condition followingcompletion of the pipeline operations.

• Dislocation or involuntary resettlement of people

There is no resettlement of people for projectimplementation.

• Impairment of downstream water quality due to inadequate sewage treatment or release of untreated sewage?

There may be possibility of pollution of downstreamwater if sewage not adequately treated as per requiredstandards. An adequate design criterion is adopted forthe proper disposal of treated sewage as perCPCB/MPPCB norms without causing any impairmentto the downstream water quality

• Overflows and flooding of neighbouring properties with raw sewage?

There are chances of overflowing or flooding of sewer manholes if not adequately designed. All sewer linesare designed for the year 2048 peak flow and howeverthe flow is mainly depending upon the number of houseservice connections. Hence chances for overflowinginto the neighbour properties are less.

• Environmental pollution due to inadequate sludge disposal or industrial waste discharges illegally disposed in sewers

The system is designed for the collection and treatmentof domestic sewage only. It can be monitoredperiodically to avoid any illegal disposal of industrialwaste into the system. The collected sludge from STPin form of sludge cakes can be disposed at thedesignated site or used as manure. Utmost care should be taken for legitimate disposal of sludge during operation of STP. The best use of sludge can be to useas manure in agriculture as there are a lot of agriculturalfields near the STP site. This can also be a means ofrevenue generation for ULB. It is recommended tocheck all the possibilities of sludge use and disposalbefore start of operation of STP.

Page 197: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

196

• Noise and vibration due to blasting and other civil works?

Blasting will not be done during excavation. Generationof noise during construction will not exceed normalemissions for general building construction activities. The contractor should ensure that there shall be nonoise problem to the residents. Nevertheless, thecontractor shall carry out noise measurements atfrequencies and locations to be agreed with theemployer’s representative and carryout measures to control it whenever and wherever needed.

• Discharge of hazardous materials into sewers, resulting in damage to sewer system and danger to works?

The sewer pipeline alignment has been designed as aburied conduit and hence chances for discharge ofhazardous materials into sewers are less. Also regularmonitoring programmes will be conducted.

• Inadequate buffer zone around pumping and treatment plants to alleviate

Adequate buffer zones as per guidelines will beprovided.

• Social conflicts between construction workers from other areas and community workers?

The contractor will be utilizing the local labour force asfar as possible; incase if it is unavoidabe, labour camps and facilities will be provided appropriately. No conflicts envisaged

• Road blocking and temporary flooding due to land excavation during the rainy season?

Access roads and alternative crossings should beprovided during the construction period.

• Noise and dust from construction activities

All the construction machineries employed will com ply with noise emission standards of Central Pollution Control Board. Dust suppression measures such as water sprinkling will be employed

• Traffic disturbances due to construction material transport and wastes?

There may be a moderate increase of traffic during the construction activities, which cannot be avoided. Also adequate measures will be taken to avoid traffic disturbances during the constructional phase.

• Temporary silt runoff due to construction

There is no considerable runoff could be caused during the constructional activities.

• Hazards to public health due to overflow flooding, and groundwater pollution due to failure of sewerage system?

Hydro testing will be carried out to all sewer lines and manholes as per CPHEEO manual.

• Deterioration of water quality due to inadequate sludge disposal or direct discharge of untreated sewage water?

Proper care should be taken before disposal of sludge. No direct discharge of untreated sewage should be done in to any water course. Sewage should be disposed after proper treatment as per CPHEEO Manual guidelines.

• Contamination of surface and ground waters due to sludge disposal on land?

Pre-study should be done before start of operation of STP for proper use/disposal of sludge. The collected sludge cakes can be disposed at the designated site as per MPPCB norms and also it can be used as manure.

Page 198: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

197

• Health and safety hazards to workers from toxic gases and hazardous materials which may be contained in sewage flow and exposure to pathogens in sewage and sludge

Ventilation shaft will be provided at the trunk main and adequate safety measures are incorporated in the system design.

Climate Change and Disaster Risk Questions The following questions are not for environmental categorization. They are included in this checklist to help identify potential climate and disaster risks.

Yes No Remarks

Is the Project area subject to hazards such as earthquakes, floods, landslides, tropical cyclone winds, storm s urges, tsunami or volcanic eruptions and climate changes?

√ Semi-arid zone, unreliable rainfall, les s vegetation cover. Promote more efficient us e of water by reducing losses and wastage to counter increased demands due to higher temperatures.

Could changes in temperature, precipitation, or extreme events patterns over the Project lifespan affect technical or financial sustainability (e.g., changes in rainfall patterns disrupt reliability of water supply; sea level rise creates salinity intrusion into proposed water supply source)?

√ Reduction in rainfall may affect the water availability from dam. Given the priority for drinking water supply, dead storage will be utilized in case of low rain fall years

Are there any demographic or socio-economic aspects of the Project area that are already vulnerable(e.g. high incidence of marginalized populations,rural-urban migrants, illegal settlements, ethnic minorities, women or children)?

√ No

Could the Project potentially increase the climate or disaster vulnerability of the surrounding area (e.g., by using water from a vulnerable source that is relied upon by m any user groups, or encouraging settlement in earthquake zones )?

√ No

Page 199: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

198

Appendix 2:National Ambient Air Quality Standards

SL NO:

Pollutants Time weighted average

Concentrationin ambientair Methodofmeasurement

Industrial, Residential, Rural &Other Areas

Ecologically Sensitive Areas

1 SulphurDioxide (SO2) µg/m3

Annual 24 hours

50 80

20 80

ImprovedWestandGeake- Ultravioletfluorescence

2 NitrogenDioxide (NO2)µg/m3

Annual 24 hours

40 80

30 80

Modified Jacob&Hochheiser (Na-Arsenite)

3 Particulate Matter (Sizeless than10 µm)orPM10µg/m3

Annual 24 hours

60 100

60 100

Gravimetric -TOEM -Beta attenuation

4 Particulate Matter (Sizeless than2.5 µm)orPM2.5µg/m3

Annual 24 hours

40 60

40 60

Gravimetric -TOEM -Beta attenuation

5 CarbonMonoxide (CO)mg/m3

8 hours 1 hours

02 04

02 04

NonDispersiveInfraRed (NDIR)Spectroscopy

1.PassengerCars Appendix 3: Vehicle Exhaust Emission Norms

Norms CO(g/km) HC+NOx(g/km) 1991Norms 14.3-27.1 2.0(OnlyHC) 1996Norms 8.68-12.40 3.00-4.36 1998Norms 4.34-6.20 1.50-2.18 Indiastage2000norms 2.72 0.97 Bharatstage-II 2.2 0.5 BharatStage-III 2.3 0.35(combined) BharatStage-IV 1.0 0.18(combined)

2.HeavyDiesel Vehicles Norms CO(g/kmhr) HC(g/kmhr) NOx (g/kmhr) PM(g/kmhr) 1991Norms 14 3.5 18 - 1996Norms 11.2 2.4 14.4 - Indiastage2000norms 4.5 1.1 8.0 0.36 Bharatstage-II 4.0 1.1 7.0 0.15 BharatStage-III 2.1 1.6 5.0 0.10 BharatStage-IV 1.5 0.96 3.5 0.02 Source: CentralPollutionControlBoard CO=Carbon Monixide;g/kmhr=gramsperkilometer-hour;HC=Hydrocarbons;NOx=oxidesof nitrogen;PM= ParticulatesMatter

Appendix 4: National Ambient Air Quality Standards in Respect of Noise

Area code Category ofarea/zone LimitindB

(A) Day time

Nighttime

A Industrial area 75 70 B Commercial area 65 55 C Residential area 55 45 D Silence zone 50 40

Page 200: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

199

Appendix 5: EXTRACT FROM CONSTRUCTION & DEMOLITION MANAGEMENT RULES, 2016

Page 201: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

200

Page 202: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

201

Page 203: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

202

Page 204: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

203

Page 205: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

204

Page 206: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

205

APPENDIX 6: Salient Features of Major Labor Laws Applicable to Establishments Engaged in Construction of Civil Works

(i) Workmen Compensation Act, 1923 - The Act provides for compensation in case of injury by accident arising out of and during the course of employment.

(ii) Payment of Gratuity Act, 1972 - Gratuity is payable to an employee under the Act on satisfaction of certain conditions on separation if an employee has completed 5 years’ service or more or on death at the rate of 15 days wages for every completed year of service. The Act is applicable to all establishments employing 10 or more employees.

(iii) Employees’ PF and Miscellaneous Provisions Act, 1952 - The Act provides for monthly contributions by the employer plus workers @10 % or 8.33 %. The benefits payable under the Act are: (a) Pension or family pension on retirement or death as the case may be; (b) deposit linked insurance on the death in harness of the worker; (c) payment of PF accumulation on retirement/death etc.

(iv) Maternity Benefit Act, 1951 - The Act provides for leave and some other benefits to women employees in case of confinement or miscarriage etc.

(v) Contract Labour (Regulation and Abolition) Act, 1970 - The Act provides for certain welfare measures to be provided by the Contractor to contract labor and in case the Contractor fails to provide, the same are required to be provided by the Principal Employer by Law. The principal employer is required to take Certificate of Registration and the Contractor is required to take a License from the designated Officer. The Act is applicable to the establishments or Contractor of principal employer if they employ 20 or more contract labor.

(vi) Minimum Wages Act, 1948 - The employer is supposed to pay not less than the Minimum Wages fixed by appropriate Government as per provisions of the Act if the employment is a scheduled employment. Construction of Buildings, Roads, Runways are scheduled employment.

(vii) Payment of Wages Act, 1936 - It lays down as to by what date the wages are to be paid, when it will be paid and what deductions can be made from the wages of the workers.

(viii) Equal Remuneration Act, 1979 - The Act provides for payment of equal wages for work of equal nature to Male and Female workers and not for making discrimination against Female employees in the matters of transfers, training and promotions etc.

(ix) Payment of Bonus Act, 1965 - The Act is applicable to all establishments employing 20 or more workmen. The Act provides for payments of annual bonus subject to a minimum of 8.33 % of wages and maximum of 20 % of wages to employees drawing Rs. 3,500/- per month or less. The bonus to be paid to employees getting Rs. 2,500/- per month or above up to Rs.3,500/- per month shall be worked out by taking wages as Rs.2,500/- per month only. The Act does not apply to certain establishments. The newly set up establishments are exempted for five years in certain circumstances. Some of the State Governments have reduced the employment size from 20 to 10 for the purpose of applicability of the Act.

(x) Industrial Disputes Act, 1947 - The Act lays down the machinery and procedure for resolution of industrial disputes, in what situations a strike or lock-out becomes illegal and what are the requirements for laying off or retrenching the employees or closing down the establishment.

(xi) Industrial Employment (Standing Orders) Act, 1946 - It is applicable to all establishments employing 100 or more workmen (employment size reduced by some of the States and Central Government to 50). The Act provides for laying down rules governing the conditions of employment by the employer on matters provided in the Act and get the same certified by the designated Authority.

Page 207: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

206

(xii) Trade Unions Act, 1926 - The Act lays down the procedure for registration of trade unions of workmen and employees. The trade unions registered under the Act have been given certain immunities from civil and criminal liabilities.

(xiii) Child Labor (Prohibition and Regulation) Act, 1986 - The Act prohibits employment of children below 14 years of age in certain occupations and processes and provides for regulation of employment of children in all other occupations and processes. Employment of child labor is prohibited in Building and Construction Industry.

(xiv) Inter-State Migrant Workmen's (Regulation of Employment and Conditions of Service) Act, 1979 - The Act is applicable to an establishment which employs 5 or more inter-state migrant workmen through an intermediary (who has recruited workmen in one state for employment in the establishment situated in another state). The inter-state migrant workmen, in an establishment to which this Act becomes applicable, are required to be provided certain facilities such as housing, medical aid, traveling expenses from home up to the establishment and back, etc

(xv) The Building and Other Construction Workers (Regulation of Employment and Conditions of Service) Act, 1996 and the Cess Act of 1996 - All the establishments who carry on any building or other construction work and employ 10 or more workers are covered under this Act. All such establishments are required to pay Cess at rate not exceeding 2% of the cost of construction as may be notified by the Government. The employer of the establishment is required to provide safety measures at the building or construction work and other welfare measures, such as canteens, first-aid facilities, ambulance, housing accommodation for workers near the workplace etc. The employer to whom the Act applies has to obtain a registration certificate from the Registering Officer appointed by the Government.

Page 208: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

207

Appendix 7: General Standards for Discharge of Environmental Pollutants (Wastewater)

S.

No. Parameter Standards

Inland surface

water Public sewers Land irrigation

1. Colour and odour remove as far as practicable

2. Suspended solids mg/l. max.

100 600 200

3. Particle size of suspended solids

shall pass 850 microns IS

Sieve

- -

4. pH value 5.5. to 9.0 5.5 to 9.0 5.5 to 9.0

5. Temperature shall not exceed 50C above the

receiving water temperature

- -

6. Oil and grease, mg./l, max.

10 20 10

7. Total residual chlorine, mg/l. max.

1.0 - -

8. Ammonical nitrogen (as N.) mg/l max

50 50 -

9. Total Kjeldahl Nitrogen (as NH3) mg/l. max

100 - -

10. Free ammonia (as NH3), mg/l.max

5.0 - -

11. Biochemical oxygen demand (3 days at 270C), mg/l. max.

30 350 100

12. Chemical oxygen demand, mg/l, max.

250 - -

13. Arsenic (as As) mg/l, max.

0.2 0.2 0.2

14. Mercury (As Hg), mg/l, 0.01 0.01 -

Page 209: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

208

S.

No. Parameter Standards

Inland surface

water Public sewers Land irrigation

max.

15. Lead (as Pb) mg/l, max 0.1 1.0 -

16. Cadmium (as Cd) mg/l. max

2.0 1.0 -

17. Hexavalent chro- mium (as Cr. +6). mg/l, max

0.1 2.0 -

18. Total Chromium (as Cr) mg/l, max

2.0 2.0 -

19. Copper (as Cu) mg/l, max 3.0 3.0 -

20. Zinc (as Zn) mg/l, max 5.0 15 -

21. Selenium (as Se) mg/l, max

0.05 0.05 -

22. Nickel (as Ni) mg/l, max 3.0 3.0 -

23. Cyanide (as CN) mg/l, max

0.2 2.0 0.2

24. Fluoride (as F) mg/l, max 2.0 15 -

25. Dissolved phosphates (as P) mg/l, max

5.0 - -

26. Sulfide (as S) mg/l, max 2.0 - -

27. Phenolic compounds (as C6H5OH) mg/l, max

1.0 5.0 -

Radioactive materials: (a) Alpha emitters microcurie mg/l, max. (b)Beta emitters micro curie mg/l

10-7

10-8

10-7

10-8

10-8

10-7

Bio-assay test 90% survival of fish after 96 hours in 100% effluent

90% survival of fish after 96 hours in 100% effluent

90% survival of fish after 96 hours in 100% effluent

Manganese 2 mg/l 2 mg/l -

Page 210: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

209

S.

No. Parameter Standards

Inland surface

water Public sewers Land irrigation

Iron (as Fe) 3mg/l 3mg/l -

Vanadium (as V) 0.2mg/l 0.2mg/l -

Nitrate Nitrogen 10 mg/l - -

Page 211: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

210

Appendix 8:Sample Grievance Registration Form

(To be available in Hindi and English)

The _____________________________________Project welcomes complaints, suggestions, queries, and comments regarding project implementation. We encourage persons with grievance to provide their name and contact information to enable us to get in touch with you for clarification and feedback.

Should you choose to include your personal details but want that information to remain confidential, please inform us by writing/typing *(CONFIDENTIAL)* above your name. Thank you.

Date Place of registration Project Town

Project:

Contact information/personal details

Name Gender * Male

* Female

Age

Home address

Place

Phone no.

E-mail

Complaint/suggestion/comment/question Please provide the details (who, what, where, and how) of your grievance below:

If included as attachment/note/letter, please tick here:

How do you want us to reach you for feedback or update on your comment/grievance?

Page 212: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

211

FOR OFFICIAL USE ONLY

Registered by: (Name of official registering grievance)

Mode of communication:

Note/letter

E-mail

Verbal/telephonic

Reviewed by: (Names/positions of officials reviewing grievance)

Action taken:

Whether action taken disclosed:

Yes

No

Means of disclosure:

Page 213: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

212

Appendix 9: Sample Outline Spoils (construction waste) Management Plan

• The Spoil Management Plan should be site specific and be part of the monthly Construction Management Plan.

• The contractor, in consultation with the PIU, has to find out appropriate location/s for the disposal of the excess soil generated. The spoils should be deposited only at these sites.

• Further precautions need to be taken in case of the contaminated spoils • The vehicle carrying the spoil should be covered properly. • The spoils generating from each site should be removed on the same day or immediately

after the work is complete. The site / road should be restored to the original condition. I. Spoils information The spoil information contains the details like a) The type / material, b) Potential contamination by that type, c) Expected volume (site / component specific), d) Spoil Classification etc. II. Spoils management The Spoil Management section gives the details of a) Transportation of spoil b) disposal site details c) Precautions taken d) Volume of contaminated spoil, if present, d) Suggested reuse of disposal of the spoil III. Documentation The volume of spoil generated (site specific, date wise), site disposed, reuse / disposal details should be documented properly.

Page 214: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

213

Appendix 10: Sample Outline Traffic Management Plan

A. Principles for TMP around the Water Pipes Construction Sites

1. One of the prime objectives of this TMP is to ensure the safety of all the road users along the work zone, and to address the following issues:

(i) the safety of pedestrians, bicyclists, and motorists travelling through the construction zone;

(ii) protection of work crews from hazards associated with moving traffic; (iii) mitigation of the adverse impact on road capacity and delays to the road users; (iv) maintenance of access to adjoining properties; and (v) Addressing issues that may delay the project.

B. Operating Policies for TMP

2. The following principles will help promote safe and efficient movement for all road users (motorists, bicyclists, and pedestrians, including persons with disabilities) through and around work zones while reasonably protecting workers and equipment.

(i) Make traffic safety and temporary traffic control an integral and high-priority element of project from planning through design, construction, and maintenance.

(ii) Inhibit traffic movement as little as possible. (iii) Provide clear and positive guidance to drivers, bicyclists, and pedestrians as

they approach and travel through the temporary traffic control zone. (iv) Inspect traffic control elements routinely, both day and night, and make

modifications when necessary. (v) Pay increased attention to roadside safety in the vicinity of temporary traffic

control zones. (vi) Train all persons that select, place, and maintain temporary traffic control

devices. (vii) Keep the public well informed. (viii) Make appropriate accommodation for abutting property owners, residents,

businesses, emergency services, railroads, commercial vehicles, and transit operations.

3. Figure A2 to Figure A12 illustrates the operating policy for TMP for the construction of water pipes and the sewers along various types of roads.

C. Analyze the impact due to street closure

4. Apart from the capacity analysis, a final decision to close a particular street and divert the traffic should involve the following steps:

(i) Approval from the ULB/Public Works Department (PWD) to use the local streets as detours;

(ii) Consultation with businesses, community members, traffic police, PWD, etc, regarding the mitigation measures necessary at the detours where the road is diverted during the construction;

Page 215: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

214

(iii) Determining of the maximum number of days allowed for road closure, and incorporation of such provisions into the contract documents;

(iv) Determining if additional traffic control or temporary improvements are needed along the detour route;

(v) Considering how access will be provided to the worksite; (vi) Contacting emergency service, school officials, and transit authorities to

determine if there are impacts to their operations; and (vii) Developing a notification program to the public so that the closure is not a

surprise. As part of this program, the public should be advised of alternate routes that commuters can take or will have to take as result of the traffic diversion.

5. If full road-closure of certain streets within the area is not feasible due to inadequate capacity of the detour street or public opposition, the full closure can be restricted to weekends with the construction commencing on Saturday night and ending on Monday morning prior to the morning peak period.

Figure A1: Policy Steps for the TMP

D. Public awareness and notifications

Page 216: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

215

6. As per discussions in the previous sections, there will be travel delays during the constructions, as is the case with most construction projects, albeit on a reduced scale if utilities and traffic management are properly coordinated. There are additional grounds for travel delays in the area, as most of the streets lack sufficient capacity to accommodate additional traffic from diverted traffic as a result of street closures to accommodate the works. 6. The awareness campaign and the prior notification for the public will be a continuous activity which the project will carry out to compensate for the above delays and minimize public claims as result of these problems. These activities will take place sufficiently in advance of the time when the roadblocks or traffic diversions take place at the particular streets. The reason for this is to allow sufficient time for the public and residents to understand the changes to their travel plans. The project will notify the public about the roadblocks and traffic diversion through public notices, ward level meetings and city level meeting with the elected representatives.

7. The PIU will also conduct an awareness campaign to educate the public about the following issues:

(i) Traffic control devices in place at the work zones (signs, traffic cones, barriers, etc.);

(ii) Defensive driving behaviour along the work zones; and (iii) Reduced speeds enforced at the work zones and traffic diversions.

8. It may be necessary to conduct the awareness programs/campaigns on road safety during construction.

9. The campaign will cater to all types of target groups i.e. children, adults, and drivers. Therefore, these campaigns will be conducted in schools and community centres. In addition, the project will publish a brochure for public information. These brochures will be widely circulated around the area and will also be available at the PIU, and the contractor's site office. The text of the brochure should be concise to be effective, with a lot of graphics. It will serve the following purpose:

(i) Explain why the brochure was prepared, along with a brief description of the project;

(ii) Advise the public to expect the unexpected; (iii) Educate the public about the various traffic control devices and safety

measures adopted at the work zones; (iv) Educate the public about the safe road user behaviour to emulate at the work

zones; (v) Tell the public how to stay informed or where to inquire about road safety

issues at the work zones (name, telephone, mobile number of the contact person; and

(vi) Indicate the office hours of relevant offices.

E. Install traffic control devices at the work zones and traffic diversion routes

10. The purpose of installing traffic control devices at the work zones is to delineate these areas to warn, inform, and direct the road users about a hazard ahead, and to protect them as well as the workers. As proper delineation is a key to achieve the above objective, it is

Page 217: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

216

important to install good traffic signs at the work zones. The following traffic control devices are used in work zones:

• Signs • Pavement Markings • Channelizing Devices • Arrow Panels • Warning Lights

11. Procedures for installing traffic control devices at any work zone vary, depending on road configuration, location of the work, construction activity, duration, traffic speed and volume, and pedestrian traffic. Work will take place along major roads, and the minor internal roads. As such, the traffic volume and road geometry vary. The main roads carry considerable traffic; internal roads in the new city areas are wide but in old city roads very narrow and carry considerable traffic. However, regardless of where the construction takes place, all the work zones should be cordoned off, and traffic shifted away at least with traffic cones, barricades, and temporary signs (temporary “STOP” and “GO”).

12. Figure A2 to Figure A6 illustrates a typical set-up for installing traffic control devices at the work zone of the area, depending on the location of work on the road way, and road geometrics:

• Work on shoulder or parking lane • Shoulder or parking lane closed on divided road • Work in Travel lane • Lane closure on road with low volume • Street closure with detour

13. The work zone should take into consideration the space required for a buffer zone between the workers and the traffic (lateral and longitudinal) and the transition space required for delineation, as applicable. For the works, a 30 cm clearance between the traffic and the temporary STOP and GO signs should be provided. In addition, at least 60 cm is necessary to install the temporary traffic signs and cones.

14. Traffic police should regulate traffic away from the work zone and enforce the traffic diversion result from full street closure in certain areas during construction. Flagggers/ personnel should be equipped with reflective jackets at all times and have traffic control batons (preferably the LED type) for regulating the traffic during night time.

16. In addition to the delineation devices, all the construction workers should wear fluorescent safety vests and helmets in order to be visible to the motorists at all times. There should be provision for lighting beacons and illumination for night constructions.

Page 218: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

217

Figure A2 & A3: Work on shoulder or parking lane & Shoulder or parking lane closed on divided road

Page 219: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

218

Figure A4 & A5: Work in Travel lane & Lane closure on road with low volume

Page 220: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

219

Figure A6: Street closure with detour

Page 221: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

220

Appendix 11: SAMPLE ENVIRONMENTAL SITE INSPECTION REPORT

Project Name

Contract Number

NAME: __________________________________ DATE: __________________________

TITLE: ___________________________________ DMA: ___________________________

LOCATION: _______________________________GROUP: ________________________

WEATHER:

Project Activity Stage

Survey

Design

Implementation

Pre-Commissioning

Guarantee Period

Monitoring Items Compliance

Compliance marked as Yes / No / Not applicable (NA) / Partially Implemented (PI)

EHS supervisor appointed by contractor and available on site

Archaeological Supervisor appointed by contractor and available on site

Construction site management plan (spoils, safety, schedule, equipment etc.,) prepared

Traffic management plan prepared

Dust is under control

Excavated soil properly placed within minimum space

Construction area is confined; no traffic/pedestrian entry observed

Surplus soil/debris/waste is disposed without delay

Construction material (sand/gravel/aggregate) brought to site as & when required only

Tarpaulins used to cover sand & other loose material when transported by vehicles

After unloading, wheels & undercarriage of vehicles cleaned prior to leaving the site

No AC pipes disturbed/removed during excavation

No chance finds encountered during excavation

Work is planned in consultation with traffic police

Work is not being conducted during heavy traffic

Work at a stretch is completed within a day (excavation, pipe laying & backfilling)

Page 222: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

221

Pipe trenches are not kept open unduly

Road is not completely closed; work is conducted on edge; at least one line is kept open

Road is closed; alternative route provided & public informed, information board provided

Pedestrian access to houses is not blocked due to pipe laying

Spaces left in between trenches for access

Wooden planks/metal sheets provided across trench for pedestrian

No public/unauthorized entry observed in work site

Children safety measures (barricades, security) in place at works in residential areas

Prior public information provided about the work, schedule and disturbances

Caution/warning board provided on site

Guards with red flag provided during work at busy roads

Workers using appropriate PPE (boots, gloves, helmets, ear muffs etc)

Workers conducting or near heavy noise work is provided with ear muffs

Contractor is following standard & safe construction practices

Deep excavation is conducted with land slip/protection measures

First aid facilities are available on site and workers informed

Drinking water provided at the site

Toilet facility provided at the site

Separate toilet facility is provided for women workers

Workers camps are maintained cleanly

Adequate toilet & bath facilities provided

Contractor employed local workers as far as possible

Workers camp set up with the permission of PIU

Adequate housing provided

Sufficient water provided for drinking/washing/bath

No noisy work is conducted in the nights

Local people informed of noisy work

No blasting activity conducted

Pneumatic drills or other equipment creating vibration is not used near old/risky buildings

Signature

Page 223: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

222

_______________________________________

Sign off

_______________________________ ________________________________

Name Name

Position Position

Page 224: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

223

Appendix 12: Quarterly Reporting Format for Assistant Safeguards Officer 1. Introduction

• Overall project description and objectives • Description of sub-projects • Environmental category of the sub-projects • Details of site personnel and/or consultants responsible for environmental monitoring • Overall project and sub-project progress and status

No. Sub-Project

Name

Status of Sub-Project List of

Works

Progress

of Works Design Pre-

Construction

Construction Operational

Phase

2. Compliance status with National/ State/ Local statutory environmental requirements

No. Sub-Project Name Statutory Environmental

Requirements

Status of

Compliance

Action Required

3. Compliance status with environmental loan covenants

No. (List schedule and

paragraph number of

Loan Agreement)

Covenant Status of Compliance Action Required

4. Compliance status with the environmental management and monitoring plan

• Provide the monitoring results as per the parameters outlined in the EMP. Append supporting documents where applicable, including Environmental Site Inspection Reports.

• There should be reporting on the following items which can be incorporated in the checklist of routine Environmental Site Inspection Report followed with a summary in the semi-annual

Page 225: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

224

report send to ADB. Visual assessment and review of relevant site documentation during routine site inspection needs to note and record the following:

o What are the dust suppression techniques followed for site and if any dust was noted to escape the site boundaries;

o If muddy water was escaping site boundaries or muddy tracks were seen on adjacent roads;

o adequacy of type of erosion and sediment control measures installed on site, condition of erosion and sediment control measures including if these were intact following heavy rain;

o Are their designated areas for concrete works, and refuelling; o Are their spill kits on site and if there are site procedure for handling emergencies; o Is there any chemical stored on site and what is the storage condition? o Is there any dewatering activities if yes, where is the water being discharged; o How are the stockpiles being managed; o How is solid and liquid waste being handled on site; o Review of the complaint management system; Checking if there are any activities being under taken out of working hours and how

that is being managed

Page 226: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

225

Summary Monitoring Table

Impacts (List

from IEE)

Mitigation

Measures (List

from IEE)

Parameters Monitored (As a

minimum those identified in the

IEE should be monitored)

Method of

Monitoring

Location of

Monitoring

Date of

Monitoring

Conducted

Name of Person

Who Conducted

the Monitoring

Design Phase

Pre-Construction Phase

Construction Phase

Operational Phase

Page 227: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

226

Overall Compliance with CEMP/ EMP

No. Sub-Project Name EMP/ CEMP Part of

Contract Documents

(Y/N)

CEMP/ EMP Being

Implemented (Y/N)

Status of Implementation (Excellent/

Satisfactory/ Partially Satisfactory/

Below Satisfactory)

Action Proposed and

Additional Measures

Required

5. Approach and methodology for environmental monitoring of the project

• Brief description on the approach and methodology used for environmental monitoring of each sub-project 6. Monitoring of environmental impacts on project surroundings (ambient air, water quality and noise levels)

• Brief discussion on the basis for monitoring • Indicate type and location of environmental parameters to be monitored • Indicate the method of monitoring and equipment to be used • Provide monitoring results and an analysis of results in relation to baseline data and statutory requirements

As a minimum the results should be presented as per the tables below.

Page 228: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

227

Air Quality Results

Site No. Date of Testing Site Location Parameters (Government Standards)

PM10 µg/m3 SO2 µg/m3 NO2 µg/m3

Site No. Date of Testing Site Location Parameters (Monitoring Results)

PM10 µg/m3 SO2 µg/m3 NO2 µg/m3

Water Quality Results

Site No. Date of Sampling Site Location

Parameters (Government Standards)

pH Conductivity

µS/cm

BOD

mg/L

TSS

mg/L

TN mg/L TP mg/L

Page 229: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

228

Site No. Date of Sampling Site Location

Parameters (Monitoring Results)

pH Conductivity

µS/cm

BOD

mg/L

TSS

mg/L

TN mg/L TP mg/L

Noise Quality Results

Site No. Date of Testing Site Location LAeq (dBA) (Government Standard)

Day Time Night Time

Site No. Date of Testing Site Location LAeq (dBA) (Monitoring Results)

Day Time Night Time

7. Summary of key issues and remedial actions

• Summary of follow up time-bound actions to be taken within a set timeframe. 8. Appendixes

• Photos • Summary of consultations • Copies of environmental clearances and permits • Sample of environmental site inspection report • Other

Page 230: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

229

Appendix 13: Summary of Consultation with Stakeholders

S.N. Location Participants (M/F)

Topic Discussed Issues Raised and Key Mitigation Measures

1 Ward No. 14 Shivalya Mohalla, Anjad

Local Inhabitants (Female-7 and Male-11)

i) Prevailing status of sewage

ii) Need of the Subproject

iii) Briefing on subproject objectives

iv) Potential positive and negative impacts due to project implementation

v) If impact on livelihood.

vi) Inconvenience to public

vii) Willingness to pay

i) Local residents have shown their willingness to support / agreed to take the subproject.

ii) Improvement in environment, health and hygiene etc.

iii) Suggested if noticed during construction, then should be compensated as per RF

iv) Public notice to be circulated, construction should be completed in the given time, debris

v) Shown their interest to pay tariff and full participation to motivate others

2. At Nagar Parishad Conference Hall on 25th April 2018

Town level Consultation with elected representatives locally called Ward Parshad and other prominent persons of town along including, President, Vice President, MLA Representative and CMO-Anjad

Explained in details about the Sewerage Project, Background, its components, locations, provisions, timeline, est. cost and also their roles in the project. Environmental, Social, traffic safety issue and benefit from the project were explained to the Stakeholders. The adverse effect of flowing sewer into the open nallahs of city.

Following main concerns were raised by the participants during • The project should be completed within the

stipulated time period. • Work Plan of contractor should be shared with them

so that they may start their road development work in the areas where laying gets done.

• Looking into the narrow streets and ongoing Water supply work, digging should not be like such as to block the whole passage for a prolonged period.

• What about storm water and the exiting nalis • The excavation work should not damage the newly

laid/old water supply pipelines. • For ensuring quality work, subletting to local

contractor should not be permitted. They were contented with the provisions of project and

Page 231: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

230

S.N. Location Participants (M/F)

Topic Discussed Issues Raised and Key Mitigation Measures

Connection of existing toilets with the sewer line will be a basic problem for the residents. Current status of sewage, Need of the Subproject and objectives,

Willingness to pay

Potential positive and negative impacts and specific measures taken for odour and noise control (modelling, odour capture etc.) were also explained to stakeholders

said they are looking forward for the same. Shown their willingness to support / agreed to take the subproject. Asked about methods for sewage treatment and what type of technology is proposed. Possible interruption in commercial activity, breakage of other utility line, safety for pedestrian etc. Improvement in environment, health and hygiene etc. Operation and maintenance is covered under the subproject and ensure community participation Assured full support during execution. During excavation for dust and traffic management assurance given to the business community Shown their interest to pay tariff and full participation to motivate others Prior information is required before start of the civil works in the respective ward More attention is required on safety as a supervisor is required to observe and enforce safety measures For Safety of Local traffic and pedestrian in Built-up Zone, fencing should be provided. Adequate provision for minimizing the Dust and Noise Pollution during construction and during operation with specific measures taken for odour and noise control (modelling, odour capture etc.) were also explained to stakeholders

3. Ward No. 5 & 6 Khosar

Falya and Gai Bachhada,

Anjad (Near IPS Site)

Local residents (Female-20)

i) Prevailing status of sewage

ii) Need of the Subproject

iii) Briefing on subproject objectives

iv) Potential positive and negative

vii) All the females have shown their willingness to support / welcome the subproject.

viii) Improvement in environment, health and hygiene etc.

ix) Suggested if noticed during construction, then should be compensated as per RF

x) Public notice to be circulated, construction should be completed in the given time, debris

Page 232: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

231

S.N. Location Participants (M/F)

Topic Discussed Issues Raised and Key Mitigation Measures

impacts due to project implementation

v) If impact on livelihood.

vi) Inconvenience to public

vii) Willingness to pay

xi) Assured full support during execution. xii) Shown their interest to pay tariff and full

participation to motivate others

4. Ward No. 2 Main Road

Hospital Chauraha, Anjad

Local Inhabitants (Male-10 including Ward Parshad)

i) Prevailing status of sewage

ii) Need of the Subproject

iii) Briefing on subproject objectives

iv) Potential positive and negative impacts due to project implementation

v) If impact on livelihood.

vi) Inconvenience to public

Willingness to pay

ix) Local inhabitants have shown their willingness to support / welcome the subproject.

x) Local inhabitant generally prefer to construct Pit Toilet, hardly construct septic tank in their house.

xi) Shown their interest to pay low tariff and full participation to motivate others.

xii) Temporary impacts: possible interruption in commercial activity, breakage of other utility line, safety for pedestrian etc.

xiii) Improvement in environment, health and hygiene etc.

xiv) Suggested if noticed during construction, then should be compensated as per RF

xv) Local inhabitants preferably defecate in the open areas away from habitation

xvi) Public notice to be circulated, construction should be completed in the given time, debris

5. Ward No. 5 Navalpura, Anjad near by IPS site

Elected representatives locally called Ward Parshad and Local Inhabitants (Female-06 and Male-10)

i) Prevailing status of sewage

ii) Need of the Subproject

iii) Briefing on subproject objectives

iv) Potential positive and negative

vi) Ward Parshad along with local inhabitants have shown interest.

vii) Temporary impacts: possible interruption in the movement, safety for pedestrian etc.

vi) Improvement in environment, health and hygiene etc.

vii) What are the common methods for sewage treatment and what type of technology is

Page 233: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

232

S.N. Location Participants (M/F)

Topic Discussed Issues Raised and Key Mitigation Measures

impacts due to project implementation

v) If impact on livelihood.

vi) Inconvenience to public

Willingness to pay

proposed. viii) Temporary impacts: possible interruption in

commercial activity, breakage of other utility line, safety for pedestrian etc.

viii) Suggested if noticed during construction, then should be compensated as per RF

xvii) Public notice to be circulated, construction should be completed in the given time, debris

ix) Shown their interest to pay low tariff and full participation to motivate others.

6. Consultation with Squatters (commercial) reported within RoW of road at Anjad to Thikri road

4-5 squatters i) Prevailing status of sewage

ii) Need of the Subproject

iii) Briefing on subproject objectives

iv) Potential positive and negative impacts due to project implementation

v) If impact on livelihood.

vi) Inconvenience to public

Willingness to pay

i) Squatters losing temporarily loss of livelihood have shown their willingness to support / agreed to take up the subproject.

ii) Temporary impacts: possible interruption in commercial activity, breakage of other utility line, safety for pedestrian etc.

iii) Suggested if noticed during construction, then should be compensated as per RF

iv) During excavation for dust and traffic management assurance given to the business community

v) Suggested if noticed during construction, then should be compensated as per RF

7. Near Proposed Location of IPS on 27th November 2017

Local Resident (Male-09)

Current status of sewage, Need of the Subproject and objectives, Potential positive and negative impacts, and specific measures taken for odour and noise control

Shown their willingness to support / agreed to take the Asked about methods for sewage treatment and what type of technology is proposed. Improvement in environment, health and hygiene etc. Operation and maintenance is covered under the subproject and ensure community participation Assured full support during execution.

Page 234: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

233

S.N. Location Participants (M/F)

Topic Discussed Issues Raised and Key Mitigation Measures

(modelling, odour capture etc.) were also explained to local residents Willingness to pay The adverse effect of flowing sewer into the open nallahs of city.

Excavated trench should be properly barricaded and restore as soon as possible in market area. Shown their interest to pay tariff and full participation to motivate others Prior information is required before start of the civil works in the respective ward through public address system

8 Near Proposed Location of IPS on 25th March 2018

Local Resident-Ward No.05 at Susal Faliya (Male-10)

Current status of sewage, Need of the Subproject and objectives, The adverse effect of flowing sewer into the open nallahs of city. Potential positive and negative impacts and specific measures taken for odour and noise control (modelling, odour capture etc.) were also explained to local residents Willingness to pay

Shown their willingness to support / agreed to take the Asked about methods for sewage treatment and what type of technology is proposed. Improvement in environment, health and hygiene etc. Operation and maintenance is covered under the subproject and ensure community participation Assured full support during execution. Excavated trench should be properly barricaded and restore as soon as possible in market area. Shown their interest to pay tariff and full participation to motivate others Prior information is required before start of the civil works in the respective ward through public address system

9 Near Proposed Location of MPS on 27th November 2017

Local Resident (Male-04)

Current status of sewage, Need of the Subproject and objectives, Potential positive and negative impacts, Willingness to pay

Shown their willingness to support / agreed to take the Asked about methods for sewage treatment and what type of technology is proposed. Improvement in environment, health and hygiene etc. Operation and maintenance is covered under the subproject and ensure community participation

Page 235: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

234

S.N. Location Participants (M/F)

Topic Discussed Issues Raised and Key Mitigation Measures

Assured full support during execution. Excavated trench should be properly barricaded and restore as soon as possible in market area. Shown their interest to pay tariff and full participation to motivate others Prior information is required before start of the civil works in the respective ward through public address system

Near Proposed Location of MPS on 25th April 2018

Local Resident in Ward No. 04 at Patel Nagar (Male-04+ Female-08)

Current status of sewage, The adverse effect of flowing sewer into the open nallahs of city. Need of the Subproject and objectives, Potential positive and negative impacts, and specific measures taken for odour and noise control (modelling, odour capture etc.) were also explained to local residents Willingness to pay

Shown their willingness to support / agreed to take the Asked about methods for sewage treatment and what type of technology is proposed. Improvement in environment, health and hygiene etc. Operation and maintenance is covered under the subproject and ensure community participation Assured full support during execution. Excavated trench should be properly barricaded and restore as soon as possible in market area. Shown their interest to pay tariff and full participation to motivate others Prior information is required before start of the civil works in the respective ward through public address system

10 Near Proposed Location of STP on 27th November 2017

Local Residents (Male-03)

Current status of sewage, The adverse effect of flowing sewer into the open nallahs of city.

Shown their willingness to support / agreed to take the subproject as some inhabitant defecate on the proposed STP site Asked about methods for sewage treatment and what type of technology is proposed.

Page 236: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

235

S.N. Location Participants (M/F)

Topic Discussed Issues Raised and Key Mitigation Measures

Need of the Subproject and objectives, Potential positive and negative impacts, and specific measures taken for odour and noise control (modelling, odour capture etc.) were also explained to local residents Willingness to pay

Improvement in environment, health and hygiene etc. Operation and maintenance is covered under the subproject and ensure community participation Assured full support during execution. During excavation for dust and traffic management assurance given to local residents. Excavated trench should be properly barricaded and restore as soon as possible in & around STP area. Shown their interest to pay tariff and full participation to motivate others Prior information is required before start of the civil works in the respective ward through public address system

11. Near Proposed Location of STP on 25th April 2018

Local Residents in Ward No. 12 & Ward No. 13 Near Hospital Chauraha (Total-13 Participant)

Current status of sewage, The adverse effect of flowing sewer into the open nallahs of city. Need of the Subproject and objectives, Willingness to pay Potential positive and negative impacts and specific measures taken for odour and noise control (modelling, odour capture etc.) were also explained to stakeholders

Shown their willingness to support / agreed to take the subproject as some inhabitant defecate on the proposed STP site Asked about methods for sewage treatment and what type of technology is proposed. Improvement in environment, health and hygiene etc. Operation and maintenance is covered under the subproject and ensure community participation Assured full support during execution. During excavation for dust and traffic management assurance given to local residents. Excavated trench should be properly barricaded and restore as soon as possible in & around STP area. Shown their interest to pay tariff and full participation to motivate others Prior information is required before start of the civil works in the respective ward through public address system Adequate provision for minimizing the Dust and Noise Pollution during construction and during operation

Page 237: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

236

S.N. Location Participants (M/F)

Topic Discussed Issues Raised and Key Mitigation Measures

specific measures taken for odour and noise control (modelling, odour capture etc.)

Page 238: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

237

Appendix 14 - Photographs and List of Participants

Town Level Consultation with President, Vice President, Ward Parshads, MLA Representative and CMO Anjad & List of

Participants on 25.04.2018

Page 239: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

238

Consultation With CMO Anjad Nagar Parishad

Page 240: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

239

Page 241: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

240

Consultation at Ward No. 14 Shivalya Mohalla, Anjad

Page 242: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

241

Consultation at Ward No. 5 & 6 Khosar Falya and Gai Bachhada, Anjad Near IPS Site

Page 243: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

242

Consultation at Ward No. 2 Main Road Hospital Chauraha, Anjad

Page 244: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

243

Consultation at Ward No. 5 Navalpura, Anjad

Page 245: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

244

Page 246: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

245

Appendix 15: Photographs of Consultation with local resident at IPS Site- Anjad

Page 247: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

246

Photographs of Consultation with local resident Near IPS Site, Ward No.5 in Susad Faliya Mohalla- Anjad on 25.04.2018 and

List of Participants

Page 248: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

247

Page 249: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

248

Appendix 16:Consultaion Nearby MPS Site in Ward No.4 at Patel Nagar on 25.04.2018 & List of Participant

Page 250: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

249

Page 251: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

250

On the Spot Consultation Near MPS Site

Page 252: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

251

Appendix 17: Consultation Photographs with Local People At Proposed STP Site- Anjad

Page 253: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

252

Consultation Photographs with Local People Nearby STP Site in ward No. 13 on 25.04.2018 & List of Participant

Page 254: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

253

Page 255: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

254

Consultation Photographs with Local People Nearby Proposed STP Site in Ward No. 12 at Hospital Chauraha on 25.04.2018

& List of Participant

Page 256: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

255

Page 257: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

256

Appendix 18: Sample Location for Surface Water (River Narmada-U/S & D/S) & Bhongli Nala Water

Page 258: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

257

Appendix 19: Water Quality Results of River Narmada-U/S & D/S)

Page 259: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

258

Page 260: Initial Environmental Examination - ADB

Initial Environmental Examination – Anjad Sewerage Scheme (Package – 2F)

259

Appendix 20: Water Quality Results of Bhongli Nala