inner harbor navigation canal lock replacement · pdf fileother navigable waterways...
TRANSCRIPT
River and Harbor Act of 1956 -Authorized the construction of a new lock and connecting channel when economically justified by obsolescence or by increased traffic
WRDA 1986Re-authorized the project and established Cost Sharing requirements
WRDA 1996Authorized Community Impact Mitigation Plan
Cost shared50% Federal / 50% IWW Fund - shallow draft portion; 65% Federal / 35% Non-Federal - deep draft portion
SponsorPort of New Orleans
River and Harbor Act of 1956River and Harbor Act of 1956 --Authorized the construction of a new lock and connecting Authorized the construction of a new lock and connecting channel when economically justified by obsolescence or by channel when economically justified by obsolescence or by increased traffic increased traffic
WRDA 1986WRDA 1986ReRe--authorized the project and established Cost Sharing authorized the project and established Cost Sharing requirementsrequirements
WRDA 1996WRDA 1996Authorized Community Impact Mitigation Plan Authorized Community Impact Mitigation Plan
Cost sharedCost shared50% Federal / 50% IWW Fund 50% Federal / 50% IWW Fund -- shallow draft portion; shallow draft portion; 65% Federal / 35% Non65% Federal / 35% Non--Federal Federal -- deep draft portiondeep draft portion
SponsorSponsorPort of New OrleansPort of New Orleans
Inner Harbor Navigation Canal Lock Replacement
Facts
Inner Harbor Navigation Canal Inner Harbor Navigation Canal Lock Replacement Lock Replacement
FactsFacts
IHNC Lock (known locally as the Industrial Canal Lock) was completed in 1921
Target for replacement for over 40 years
Mississippi River SystemsMississippi River Systems
Other Navigable WaterwaysOther Navigable Waterways
MississippiRiver
Navigation System
IHNC Lock is a vital link between the Gulf
Intracoastal Waterway and the Mississippi River
MississippiMississippiRiverRiver
Navigation Navigation SystemSystem
IHNC Lock is a vital link between the Gulf
Intracoastal Waterway and the Mississippi River
MINNEAPOLIS
TULSA
MISSISSIPPI R
IVERM
ISSISSIPPI RIVER
ARKANSAS R.ARKANSAS R.
RED R.RED R.
ALEXANDRIA
SHREVEPORT
HOUSTON NEW ORLEANS
WHITE R.
WHITE R.
OU
AC
HITA
R.
OU
AC
HITA
R.
CHICAGO
PITTSBURGH
CINCINNATIOHIO R.
OHIO R.
GREEN R.
GREEN R.KNOXVILLE
TENNESSEE R
.
TENNESSEE R
.MEMPHIS
VICKSBURG
ILLINOIS R
.
ILLINOIS R
.
GIWWGIWW
MISSOUSI R.
MISSOUSI R.
SIOUX CITY
PEA
RL
R.
PEA
RL
R.
YAZO
O R
.YA
ZOO
R.
TOM
BIG
BEE
R.
TOM
BIG
BEE
R.
ST. LOUIS
GIWWGIWW
Reasons for the Project
Critical to Nation’s Commerce
Priority Replacement Lock in the Inland Waterway System
One of the most congested locks in the Inland System
Existing Lock is too small
Existing ConditionsExisting Conditions
Current Lock –
Placed in Service 1921
75 feet wide by 640 feet long by 31.5 feet deep
Average delay is 11 hrs, can be as much as 24-36 hrs
Current Lock Current Lock ––
Placed in Service 1921Placed in Service 1921
75 feet wide by 640 feet long 75 feet wide by 640 feet long by 31.5 feet deepby 31.5 feet deep
Average delay is 11 hrs, can Average delay is 11 hrs, can be as much as 24be as much as 24--36 hrs36 hrs
CONCEPTUAL VIEW OF COMPLETED PROJECT CONCEPTUAL VIEW OF COMPLETED PROJECT
Recommended Plan –
Deep Draft Lock
110 feet wide by 1200 feet long by 36 feet of draft
Cost - $804 million
Recommended Plan Recommended Plan ––
Deep Draft LockDeep Draft Lock
110 feet wide by 1200 feet 110 feet wide by 1200 feet long by 36 feet of draftlong by 36 feet of draft
Cost Cost -- $804 million$804 million
Project Cost SharingProject Cost Sharing
Total Cost $804,000,000IWW Trust Fund $324,611,500Corps RegularAppropriations $408,688,500 Non-Fed $ 70,700,000
Total Cost $804,000,000IWW Trust Fund $324,611,500Corps RegularAppropriations $408,688,500 Non-Fed $ 70,700,000
Community Impact Mitigation Plan
Community Impact Mitigation Plan
Plan is One of a KindSpecifically authorized by Congress (WRDA 96)
“The Secretary shall implement a comprehensive community impact mitigation plan…”
Estimated Dollars ($48.0 M)Implement up front as construction begins
Plan is One of a KindPlan is One of a KindSpecifically authorized by Congress (WRDA Specifically authorized by Congress (WRDA 96)96)
““The Secretary shall implement a The Secretary shall implement a comprehensive community impact comprehensive community impact mitigation planmitigation plan…”…”
Estimated Dollars ($48.0 M)Estimated Dollars ($48.0 M)Implement up front as construction beginsImplement up front as construction begins
Involving the CommunityInvolving the CommunityCommunityCommunity--Based Mitigation Based Mitigation Committee (CBMC) Concept:Committee (CBMC) Concept:•• A unique effort to build a broadA unique effort to build a broad--based based
community participation process to work in community participation process to work in tandem with the Corps throughout the IHNC tandem with the Corps throughout the IHNC Lock Replacement ProjectLock Replacement Project
Goal: Goal: •• Provide valuable input toward the Provide valuable input toward the
formulation and implementation of a formulation and implementation of a Community Impact Mitigation PlanCommunity Impact Mitigation Plan
Partnering with CBMCPartnering with CBMCObjective:Objective:-- A unique partnership effort between A unique partnership effort between
Community & the Corps of EngineersCommunity & the Corps of Engineers-- Chance to build a broadChance to build a broad--based community based community
participation processparticipation process
Benefits:Benefits:-- Enhanced trust and confidence between area Enhanced trust and confidence between area
residents and the Corpsresidents and the Corps-- Opportunity for urban revitalization through Opportunity for urban revitalization through
expenditure of mitigation fundsexpenditure of mitigation funds
In October 2006 the project was enjoined by order of Federal Court.
No work is to be done on the project until a Supplemental Environment Impact Statement (SEIS) is completed.
Construction Method Determination in August 2007
In October 2006 the project was enjoined In October 2006 the project was enjoined by order of Federal Court.by order of Federal Court.
No work is to be done on the project until No work is to be done on the project until a Supplemental Environment Impact a Supplemental Environment Impact Statement (SEIS) is completed. Statement (SEIS) is completed.
Construction Method Determination in Construction Method Determination in August 2007August 2007
Inner Harbor Navigation Canal Lock Replacement
Ongoing Work
Inner Harbor Navigation Canal Inner Harbor Navigation Canal Lock Replacement Lock Replacement
Ongoing WorkOngoing Work
FUNDINGFUNDING
33rdrd Supplemental FundingSupplemental Funding$12,500,000 (received)$12,500,000 (received)
FY 07 Funding FY 07 Funding ––$4,000,000 (received)$4,000,000 (received)
FY 08 PresidentFY 08 President’’s Budgets Budget$ 0 $ 0