Harris Stratex Networks Eclipse Terminal Installation and Commissioning Forms Rev 3 June 07 Introduction Purpose is to provide: A prompt for preparing data for new installations. A datapack for installers. A data entry form to capture additional as-built data. An as-built record with sign-off. Associated forms included in this file are: Installation Inspection Form Customer Acceptance Form Remedial Action Form Navigation: The Master Site Data column lists entries required. Click on a ‘+’ tab at the far left of the screen to open up required data entry rows. Click ‘–’ tab to close. The Build / As-Built Data column is for data entry. Build data is data to be entered at the planning (datapack prep) stage. As- built data is data to be entered at site, mostly from Portal. The Portal column highlights the data to be entered into Portal and data to be entered from Portal. The Comments column is to capture any additional data. See the Example Form for additional guidance. Forms can be printed. Important! Please provide feedback on the use of these forms. Feedback is needed to provide guidance on what improvements should be made to assist the application and usability of these forms. Please send feedback to: Director Installation Practices Director of Services, Americas Global Technical Support manager Eclipse Terminal Forms: V1.1 June06 Commercial-In-Confidence 1

Upload: mymothman69

Post on 23-Apr-2017

215 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Installation and Commissioning Forms - Eclipse Terminal

Harris Stratex Networks

Eclipse Terminal Installation and Commissioning FormsRev 3 June 07

Introduction

Purpose is to provide:

A prompt for preparing data for new installations.

A datapack for installers.

A data entry form to capture additional as-built data.

An as-built record with sign-off.

Associated forms included in this file are:

Installation Inspection Form

Customer Acceptance Form

Remedial Action Form

Navigation:

The Master Site Data column lists entries required. Click on a

‘+’ tab at the far left of the screen to open up required data

entry rows. Click ‘–’ tab to close.

The Build / As-Built Data column is for data entry. Build data

is data to be entered at the planning (datapack prep) stage. As-

built data is data to be entered at site, mostly from Portal.

The Portal column highlights the data to be entered into Portal

and data to be entered from Portal.

The Comments column is to capture any additional data.

See the Example Form for additional guidance.

Forms can be printed.

Important! Please provide feedback on the use of these forms.

Feedback is needed to provide guidance on what improvements should

be made to assist the application and usability of these forms. Please

send feedback to:

Director Installation Practices

Director of Services, Americas

Global Technical Support manager

Eclipse Terminal Forms: V1.1 June06 Commercial-In-Confidence 1

Page 2: Installation and Commissioning Forms - Eclipse Terminal

Harris Stratex Networks

Eclipse Terminal Installation and Configuration Form For Site:

Installer:

Installer Contact Details:

Scheduled Start Date:

Scheduled Completion Date:

New or Existing Site:

Electrical Supply OK yes/no:

Site Grounding OK yes/no:

Antenna Mounts OK yes/no:

Site Security OK yes/no:

Site Plans Included yes/no:

Master Site Data Build / As-Built Data Portal

Entry To

Comments

Terminal

IDU type To

ODU type

Terminal name To

Site name To

Site grid reference To

Tech services contact details To

NOC contact details

Site location

Site access See attached map

Rack number/name

IDU location in rack

Chassis serial number (All serial numbers begin with three letters)

-48Vdc power supply connection

Networking

Terminal IP address To

Subnet mask To

Static or dynamic routing To

Static routing data

DHCP yes/no; address range To

Trap destinations To

Link/Radio

Link name/number To

Remote end site name To

Remote end terminal/node name To

Local antenna type

Local antenna diameter

Antenna serial number

Height on tower / pole mount ID `

Initial pointing (compass/map ref)

Polarization

ODU direct mounting, yes/no

ODU serial number

ODU cable length required

Protected yes/no To

Link protection type To

Trib protection type (TT or TA) To

Tx frequency To

Rx frequency To

T/R spacing To

Tx power To

Detected forward power From

Capacity To

Modulation

ATPC yes/no To

ATPC data

Expected RSL

Indicated RSL From

Expected RSSI

Indicated RSSI From

Expected fade margin

Measured fade margin From

G.826 link check From

Alarms check From

Performance check From

E1 Tributaries

General Instructions:

To = Enter into Portal

From = Enter from Portal

Terminal I+C Form: V1.1 June06 Commercial-In-Confidence 2

Page 3: Installation and Commissioning Forms - Eclipse Terminal

Harris Stratex Networks

DS1 Tributaries

STM1/OC3 Tributary

Ethernet Ports

AUX

Auxiliary port

Type, port settings, name To

Circuit name To

Alarm I/O

Alarm actions

Date/Time

(Specify Date/Time setting) To

BER Circuit Checks

Trib-trib BER check

(Specify the trib[s] and period)

From

Alarms exit check

Active alarms yes/no From

Ground checks

Single point bldg ground y/n

Master Ground Bar resistance

Rack to MGB resistance

-48V PSU to MGB resistance

Tower ground resistance(s)

Other resistance readings

Meter used

Site Inspection Report completed

yes/no

Hardware Installation completed

Name:

Signature:

Date:

Node Installation & Tests completed

Name:

Signature:

Date:

Completion Comments

Terminal I+C Form: V1.1 June06 Commercial-In-Confidence 3

Page 4: Installation and Commissioning Forms - Eclipse Terminal

Harris Stratex Networks

Eclipse Terminal Installation and Configuration Form For Site: Plaza

Installer: Joeseph Brown

Installer Contact Details: 021 362 700

Scheduled Start Date: 15-Sep-05

Scheduled Completion Date: 18-Sep-05

New or Existing Site: Existing

Electrical Supply OK yes/no: Yes

Site Grounding OK yes/no: Yes

Antenna Mounts OK yes/no: Yes

Site Security OK yes/no: Intruder alarm has been disabled

Site Plans Included yes/no: Yes

Master Site Data Build / As-Built Data Portal

Entry To

Comments

Terminal

IDU type IDU 20x

ODU type ODU 300hp

Terminal name E116 To

Site name Plaza To

Site grid reference Eastxxx Southxxx To

Tech services contact details 021 362 701 To

NOC contact details 021 362 702 To

Site location 10km East of Masterton

Site access Off Murrays Road See attached map

Rack number/name 1A

IDU location in rack Directly under terminal E10

Chassis serial number LES00934567 (All serial numbers begin with three letters)

-48Vdc power supply connection Provide and install 5A Cct Breaker on supply

panel at top of rack

Networking

Terminal IP address 192.168.11.1 To

Subnet mask 225.225.255.0. To

Static or dynamic routing RIP 2 To

Static routing data N/A

DHCP yes/no; address range Yes, 192.168.11.2 to 192.168.11.10 To

Trap destinations N/A To

Link/Radio

Link name/number Plaza-Weston To

Remote end site name Weston To

Remote end terminal/node name E109 To

Local antenna type VHLP2-180-EX

Local antenna diameter 0.6M

Antenna serial number AN35239

Height on tower / pole mount ID 28M `

Initial pointing (compass/map ref) 183 degrees

Polarization Vertical

ODU direct mounting, yes/no Yes

ODU serial number SNA7687988

ODU cable length required 40m

Protected yes/no No To

Link protection type N/A To

Trib protection type (TT or TA) N/A To

Tx frequency 17.85 GHz To

Rx frequency 18.25 GHz To

T/R spacing 400 MHz To

Tx power 17 dBm To

Detected forward power 17.1 dBm From

Capacity 20xE1 To

Modulation 16 QAM To

ATPC yes/no No To

ATPC data

Expected RSL -51 dBm

Indicated RSL -50 dBm From

Expected RSSI 1.25

Indicated RSSI 1.27 From

Expected fade margin 35 dB

Measured fade margin 37 dB From

G.826 link check Zero errors over 14 hours From

Alarms check No active alarms From

Performance check All indications normal From

E1 Tributaries

General Instructions: 4-wheel drive access only. This time of the year the track will be wet and slippery. Please do a battery check and run the back-up diesel generator for about 30 mins and check associated panel lights. Should all be green.

To = Enter into Portal

From = Enter from Portal

Terminal I+C Form V1.1 June06 Commercial-In-Confidence 4

Page 5: Installation and Commissioning Forms - Eclipse Terminal

Harris Stratex Networks

Master Site Data Build / As-Built Data Portal

Entry To

Comments

Bal or Unbal Unbal To

No. tribs req. 18 To

Trib names Pla/Wes 1 - 18 To

Circuit names Pla/Wes 1 - 18

Connect to Rack BNC panel: ports 1 to 18

E1 Tributaries

DS1 Tributaries

STM1/OC3 Tributary

Ethernet Ports

AUX

Auxiliary port

Type, port settings, name Sync, default, Aux Plaza/Weston To

Circuit name Bel/Lak To

Alarm I/O

Input 1, active condition Digital input, active high To Wire to intruder alarm: alarm is active when circuit

is broken.

Input 2, active condition To

Output 1, active condition To

Output 2, active condition To

Output 3, active condition To

Output 4, active condition To

Alarm I/O

Alarm actions

Destination IP address, slot, and output.

Trigger(s).

192.168.2.1, slot 4, output 2.

AUX alarm input 1.

To At commissioning check that the destination

output (bell) at Belmont activates when the

intruder alarm is activated. Also check that the

alarm event is raised at the NOC.

Destination IP address, slot, and output.

Trigger(s).

To

Destination IP address, slot, and output.

Trigger(s).

To

Destination IP address, slot, and output.

Trigger(s).

To

Destination IP address, slot, and output.

Trigger(s).

To

Alarm actions

Date/Time

(Specify Date/Time setting) Sync to Portal PC Date/Time To

BER Circuit Checks

Trib-trib BER check

(Specify the trib[s] and period)

BER check completed on trib 2 to Weston. No

errors over 12 hours.

From

Alarms exit check

Active alarms yes/no No active alarms From

Ground checks

Single point bldg ground y/n Yes

Master Ground Bar resistance 0.62 ohms

Rack to MGB resistance 0.15 ohms

-48V PSU to MGB resistance 0.27 ohms

Tower ground resistance(s) Not possible to measure. Cannot get meter jaws

around the ground straps.

Other resistance readings

Meter used Prova clamp-on, model DX Serial number 00458

Hardware Installation completed

Name: Joe Brown

Signature:

Date: 18 September 2005

Node Installation & Tests completed

Name: Joesphine Brown

Signature:

Date: 18 September 2005

Completion Comments Road access is OK.

Terminal I+C Form V1.1 June06 Commercial-In-Confidence 5

Page 6: Installation and Commissioning Forms - Eclipse Terminal

Harris Stratex Networks

Master Site Data Build / As-Built Data Portal

Entry To

Comments

Shelter door hinges very corroded.

Checked diesel generator & all OK

Terminal I+C Form V1.1 June06 Commercial-In-Confidence 6

Page 7: Installation and Commissioning Forms - Eclipse Terminal

Harris Stratex Networks

Eclipse Terminal Installation Inspection Report For Site:

Check for correct and complete installation of:

Item Pass Fail Comments

Antenna Mounting

Antenna side support (if used)

ODU fastening

ODU grounding

ODU connector weatherproofing

ODU cable fastening

ODU cable grounding

Lightning surge suppressor(s)

IDU location in rack

IDU is labelled (if required)

IDU grounding

IDU power supply wiring

Trib cables are correctly and neatly installed

Trib cables are numbered (if required)

Alarms all-clear

Site left clean and tidy

Site photos taken (if required)

Site ground measurements (if required)

Checked by:

Name:

Signature:

Date:

Additional Comments:

Terminal Inst. Insp. Report: V1.0 Mar04 Commercial-In-Confidence 7

Page 8: Installation and Commissioning Forms - Eclipse Terminal

Harris Stratex Networks

Eclipse Terminal Customer Acceptance Form

Site Name:

Eclipse Terminal Name:

Related documents Received Yes/No

Eclipse Installation and Commissioning Form:

Eclipse Installation Inspection Report:

Acceptance Category* Category

Accepted / Conditionally Accepted / Not Accepted:

*If conditionally accepted or not accepted, the action required to

achieve acceptance must be detailed in a Remedial Action Form

Signed By:

Customer

Name:

Signature:

Title:

Date:

Harris Stratex Networks

Name:

Signature:

Title:

Date:

Terminal Acceptance Form V.1.0 Mar04 Commercial-In-Confidence 8