Page 1: Installation & Instruction ManualLocal agent Gyeongnam & Daegu - Korea PME Room # 103, shopping area in Samsung Buckinggham APT, 148-3, Yangdeok 2-dong, Hoewon-gu, Masan, Gyeongnam

Daekyung Tech & Tester Mfg. Co., Ltd.

Technical Instruction Manual : DKTD-902 (DTR-300N)

Technical Instruction Manual : DKTD-903 (DTR-200N)

Rockwell Hardness TesterInstallation & Instruction Manual

Ver.1005/ROCKWELL

MODEL NUMBER : DTR-300N / DTR-200N

DTR‐300N DTR‐200N

Ver.1005/ROCKWELL

Page 2: Installation & Instruction ManualLocal agent Gyeongnam & Daegu - Korea PME Room # 103, shopping area in Samsung Buckinggham APT, 148-3, Yangdeok 2-dong, Hoewon-gu, Masan, Gyeongnam

Contents

Ver.1005/ROCKWELL Technical Instruction Manual

section

Contents

About us ---------------------------------------------------- 1

Safety precautions --------------------------------------- 2

Technical manual ---------------------------------------- 3

Installation manual -------------------------------------- 4

How to use --------------------------------------- 5

Electrical manual ----------------------------------------- 6

MAINTENANCE ----------------------------------- 7

Certificate and calibration report ------------------- 8

FAQ------------------------------------------------ 9

10Quality warranty and request for repair service

Ver.1005/ROCKWELL Technical Instruction Manual

Page 3: Installation & Instruction ManualLocal agent Gyeongnam & Daegu - Korea PME Room # 103, shopping area in Samsung Buckinggham APT, 148-3, Yangdeok 2-dong, Hoewon-gu, Masan, Gyeongnam

About usSection - 1

Greetings!

Ver.1005/ROCKWELL Technical Instruction Manual

Greetings!

First of all, we thank you for purchasing a product of Daekyung.

Since the foundation in 1991, Daekyung Tech & Tester Mfg always does our best to produce the best testing machines.

Daekyung Tech & Tester Mfg is the best testing machine brand that supplies our products not only to local market, but also to about 20 countries.

W ill tt ti t t ' d i d t dWe will pay attention to our customer's needs in order to produce better products.

Thank you.

Daekyung Tech & Tester Mfg. Co., Ltd.

Ver.1005/ROCKWELL Technical Instruction Manual

Page 4: Installation & Instruction ManualLocal agent Gyeongnam & Daegu - Korea PME Room # 103, shopping area in Samsung Buckinggham APT, 148-3, Yangdeok 2-dong, Hoewon-gu, Masan, Gyeongnam

About usSection - 1

Company Name Daekyung Tech & Tester Mfg. Co., Ltd

Ver.1005/ROCKWELL Technical Instruction Manual

Company Name Daekyung Tech & Tester Mfg. Co., Ltd

Address 1st Factory and Office

118B-10L, 688-10 Gojan-dong, Namdong-gu, Incheon Zip: 405 820Tel : 82 32 822 5511Tel : 82 32 822 5511 Fax : 82 32 821 4580Website : www.idtnt.comE-mail : [email protected] / [email protected] (overseas call)

Calibration Dept. and Hardness Dept.

117B-9L, Building B Room# 108, Namdong Woori Town, 686-7 Gojan-dong, Namdong-gu, Incheon Zip: 405 820

Tel : 82 32 822 5511Fax : 82 32 822 1798

Extension Sales Dept. : 222Design Dept. : 600Control Dept. (A/S) : 555Calibration Dept. : 777Hardness Dept. : 750pOverseas Sales Dept. : 201

Local agent Gyeongnam & Daegu - Korea PMERoom # 103, shopping area in Samsung Buckinggham APT, 148-3, Yangdeok 2-dong, Hoewon-gu, Masan, GyeongnamTel : 055 297 0838Tel : 055 297 0838Fax : 055 294 3197

Ulsan - Sein instrument

67-1 Seo-dong, Jung-gu, UlsanTel : 052 294 5530Tel : 052 294 5530Fax : 052 294 5527

Ver.1005/ROCKWELL Technical Instruction Manual

Page 5: Installation & Instruction ManualLocal agent Gyeongnam & Daegu - Korea PME Room # 103, shopping area in Samsung Buckinggham APT, 148-3, Yangdeok 2-dong, Hoewon-gu, Masan, Gyeongnam

About usSection - 1

Ver.1005/ROCKWELL Technical Instruction Manual

Overseas Agent China - Daekyung Tech & Tester Mfg. Co., Ltd. Beijing branch北京市顺义区北小营镇府西路4号 Zip101305电话: +86(0)10 8698 8444

China - FOUNDRAX ASIA LIMITED BEIJING OFFICERoom 1206 Jintaiguoyi Building Chaoyang Bei Lu Chaoyang DistrictRoom 1206, Jintaiguoyi Building, Chaoyang Bei Lu, Chaoyang DistrictBeijing, China. 100025Tel: 86 10 5202 6505

Malaysia - LESO instruments (M) Sdn BhdNo. 12A, Jalan Gitar 33/3, Elite Industrial Estate, Seksyen 33, 40350Sh h Al S lShah Alam, Selangor.Tel: 60 3 5121 2673

Indonesia - PT. Uni Metrika UtamaJl, Agung Timur 8, Komplek Prima Sunter Blok D Kav, No.7Jakarta Utara - Indonesia 14350.Tel: 62 21 6530 4111

Thailand - Trong kamol Co., Ltd.24/708 Moo7 Soi Lasalle75 Sukhumvit 105 Rd, Bangna Bangna Bankok 10260 Thailand.Tel: 66 0 2361 8889

Egypt - Technology Vision.2C Misr El-Gadida Bidgs (Behind Shams Club) Heliopolis Cairo EgyptTel: 202 2620 2705

Pakistan - Chemtech International (Pvt) LimitedPakistan - Chemtech International (Pvt) LimitedC-13 Block 17 Gulsahn-e Iqbal Karachi Pakistan.Tel: 92 21 3452 8415

Iran - Payesh Karan Amin CompanyFlat No.1, 6th Floor, Javaneh Building, Next to Sahrayi Str., SatrahanTehran 145744163 IranTehran 145744163, Iran.Tel: 98 21 4421 9458

Ver.1005/ROCKWELL Technical Instruction Manual

Page 6: Installation & Instruction ManualLocal agent Gyeongnam & Daegu - Korea PME Room # 103, shopping area in Samsung Buckinggham APT, 148-3, Yangdeok 2-dong, Hoewon-gu, Masan, Gyeongnam

Safety precautionsSection - 2

List

Ver.1005/ROCKWELL Technical Instruction Manual 1

page

Introduction ------------------------------------------------------------------------ 2

During transporting the machine ------------------------------------- 3

List

Risky parts of the machine and operational precautions ----------- 4

- Diamond/ ball indenter ---------------------------------------------------------- 4

S f t k 5Safety mark ------------------------------------------------------------- 5

How to take emergency measures ----------------------------------- 5

Safety inspection ------------------------------------------------------- 6

Ver.1005/ROCKWELL Technical Instruction Manual 1

Page 7: Installation & Instruction ManualLocal agent Gyeongnam & Daegu - Korea PME Room # 103, shopping area in Samsung Buckinggham APT, 148-3, Yangdeok 2-dong, Hoewon-gu, Masan, Gyeongnam

Safety precautionsSection - 2

Introduction

Ver.1005/ROCKWELL Technical Instruction Manual 2

Introduction

The product is for tensile strength, compression, and bending test of various test sample. Since some parts of the machine can be dangerous to operators or other people around the machine, please fully be aware of the descriptions in Section - 2 for safe operation of the product.

Especially, in case of too big sized test sample that exceeds machine capacity, please pay special attention to it.To test those test samples, please contact Daekyung in advance to check if it is possible.

Additi ll i th i ht f th d t i b t 140k th d tAdditionally, since the weight of the product is about 140kg, the product must be located on a flat place to prevent fall and two persons are required for transporting.

This product is designed for 220V, 1 A, 1ph, 50~60 Hz.Please re-check your power before operating the machine.

Ver.1005/ROCKWELL Technical Instruction Manual 2

Page 8: Installation & Instruction ManualLocal agent Gyeongnam & Daegu - Korea PME Room # 103, shopping area in Samsung Buckinggham APT, 148-3, Yangdeok 2-dong, Hoewon-gu, Masan, Gyeongnam

Safety precautionsSection - 2

Transporting the machine

Ver.1005/ROCKWELL Technical Instruction Manual 3

Transporting the machine

To transport the machine, use the transporting pole and two persons To transport the machine, use the transporting pole and two persons are required for transporting.

In addition, please wear safety shoes before transporting the product.

Since the weight of the product is 90kg, carelessness can cause severe injury.

Ver.1005/ROCKWELL Technical Instruction Manual 3

Page 9: Installation & Instruction ManualLocal agent Gyeongnam & Daegu - Korea PME Room # 103, shopping area in Samsung Buckinggham APT, 148-3, Yangdeok 2-dong, Hoewon-gu, Masan, Gyeongnam

Safety precautionsSection - 2

Risky parts of the machine and operational precautions

Ver.1005/ROCKWELL Technical Instruction Manual 4

Risky parts of the machine and operational precautions

- Diamond/ball indenter

Pay attention not to insert your fingers between the indenter and a test sample.

Please pay full attention before and during a test.

Ver.1005/ROCKWELL Technical Instruction Manual 4

Page 10: Installation & Instruction ManualLocal agent Gyeongnam & Daegu - Korea PME Room # 103, shopping area in Samsung Buckinggham APT, 148-3, Yangdeok 2-dong, Hoewon-gu, Masan, Gyeongnam

Safety precautionsSection - 2

Safety mark

Ver.1005/ROCKWELL Technical Instruction Manual 5

Safety mark

Any part with the above sign is an electric connection. Pay attention to the sign.

How to take emergency measures

www.idtnt.com

1 경도기는 먼지나 습기 진동이 없는 장소에 설치한다

설치 시 주의사항

www.idtnt.com

NOTICE1 INSTALL IN THE PLACE FREE OF HUMIDITY

www.idtnt.com

1. 경도기는 먼지나 습기, 진동이 없는 장소에 설치한다.

2. 설치 시 지급된 공구로 수평은 반듯이 맞춘다.

3. 다이아몬드 콘은 충격에 취약하니 주의 하여야 한다.

4. 초 하중 가압 시 핸들은 부드럽게 조작한다.

원인 확인 해결

설치 시 주의사항

응급조치 요령1. 경도 값 오차발생시

www.idtnt.com

NOTICE

Before you call to DT&T !

1. INSTALL IN THE PLACE FREE OF HUMIDITY, VIBRATION AND HEAVY DUST2. MAKE A LEVEL BY MEANS OF TOOLS SUPPLIED3. BE CARE THE DAMAGE OF DIAMOND CONE4. HANDLE SMOOTHLY FOR INITIAL LOADING

1. Discrepancy of hardness value

www.idtnt.com

1. 경도기는 먼지나 습기, 진동이 없는 장소에 설치한다.

2. 설치 시 지급된 공구로 수평은 반듯이 맞춘다.

3. 다이아몬드 콘은 충격에 취약하니 주의 하여야 한다.

4. 초 하중 가압 시 핸들은 부드럽게 조작한다.

원인 확인 해결

공구현미경으로 확인

유리나 거울표면에 콘을

긁어 흠집이 나면 콘 불량

스틸볼 마모 편 마모 확인 스틸볼 교체

평면시료에 곡면보정 기

능 오류(DTR-300N)"Φ" 기능 스위치 확인 "D"나 "R"에 "0.00" 확인

전면 게이지 움직임 불량 상부커버 분해, 텐션확인 윤활제(WD-40) 도포

장비이동 재 설치 후 하중 추 센터링 확인 레벨볼트 조정

스쿠류커버 상부 돌출 앤빌밑면과 커버접촉확인 5 mm이상 간격유지

설치 시 주의사항

응급조치 요령

콘 교환다이아몬드 콘 파손

1. 경도 값 오차발생시

www.idtnt.com

Reason Check Solution

Abrasion of steel ball Chage steel ball

Function of compensation "Ø" function Set "0.00"

Trouble of dial gauge Lube oil

Change of the tester Leveling Leveling

f h k b f il

Change diamond coneCheck by microscope

NOTICE

Before you call to DT&T !

1. INSTALL IN THE PLACE FREE OF HUMIDITY, VIBRATION AND HEAVY DUST2. MAKE A LEVEL BY MEANS OF TOOLS SUPPLIED3. BE CARE THE DAMAGE OF DIAMOND CONE4. HANDLE SMOOTHLY FOR INITIAL LOADING

1. Discrepancy of hardness value

Damage of diamond cone

www.idtnt.com

1. 경도기는 먼지나 습기, 진동이 없는 장소에 설치한다.

2. 설치 시 지급된 공구로 수평은 반듯이 맞춘다.

3. 다이아몬드 콘은 충격에 취약하니 주의 하여야 한다.

4. 초 하중 가압 시 핸들은 부드럽게 조작한다.

원인 확인 해결

공구현미경으로 확인

유리나 거울표면에 콘을

긁어 흠집이 나면 콘 불량

스틸볼 마모 편 마모 확인 스틸볼 교체

평면시료에 곡면보정 기

능 오류(DTR-300N)"Φ" 기능 스위치 확인 "D"나 "R"에 "0.00" 확인

전면 게이지 움직임 불량 상부커버 분해, 텐션확인 윤활제(WD-40) 도포

장비이동 재 설치 후 하중 추 센터링 확인 레벨볼트 조정

스쿠류커버 상부 돌출 앤빌밑면과 커버접촉확인 5 mm이상 간격유지

원인 확인 해결

다이얼게이지 소 침 불량 DTR-200일 경우 전원 OFF / ON

스쿠류는 돌아가는데

">>>>" 증가가 안됨DTR-300N일 경우

상부커버 분리, 게이지 축

을 움직인다.

스쿠류 돌지 않고 ">>>>"

증가가 안됨DTR-300N일 경우 전원 OFF / ON

원인 확인 해결

3. 스쿠류 작동불량

설치 시 주의사항

응급조치 요령

콘 교환다이아몬드 콘 파손

1. 경도 값 오차발생시

2. 초 하중 부하 시 작동불량

www.idtnt.com

Reason Check Solution

Abrasion of steel ball Chage steel ball

Function of compensation "Ø" function Set "0.00"

Trouble of dial gauge Lube oil

Change of the tester Leveling Leveling

Contact of screw cover Check bottom of anvil

Reason Check SolutionTrouble of small hand DTR-200 Reboot

No signal of">>>>" whilehandle works well DTR-300N Lease top cover & push

pivot of digital gauge

No signal of ">>>>" andbad works of handle DTR-300N Reboot

R Ch k S l ti

Change diamond cone

2. Trouble during initial loading

Check by microscope

NOTICE

Before you call to DT&T !

3. Trouble of screw handle

1. INSTALL IN THE PLACE FREE OF HUMIDITY, VIBRATION AND HEAVY DUST2. MAKE A LEVEL BY MEANS OF TOOLS SUPPLIED3. BE CARE THE DAMAGE OF DIAMOND CONE4. HANDLE SMOOTHLY FOR INITIAL LOADING

1. Discrepancy of hardness value

Damage of diamond cone

www.idtnt.com

1. 경도기는 먼지나 습기, 진동이 없는 장소에 설치한다.

2. 설치 시 지급된 공구로 수평은 반듯이 맞춘다.

3. 다이아몬드 콘은 충격에 취약하니 주의 하여야 한다.

4. 초 하중 가압 시 핸들은 부드럽게 조작한다.

원인 확인 해결

공구현미경으로 확인

유리나 거울표면에 콘을

긁어 흠집이 나면 콘 불량

스틸볼 마모 편 마모 확인 스틸볼 교체

평면시료에 곡면보정 기

능 오류(DTR-300N)"Φ" 기능 스위치 확인 "D"나 "R"에 "0.00" 확인

전면 게이지 움직임 불량 상부커버 분해, 텐션확인 윤활제(WD-40) 도포

장비이동 재 설치 후 하중 추 센터링 확인 레벨볼트 조정

스쿠류커버 상부 돌출 앤빌밑면과 커버접촉확인 5 mm이상 간격유지

원인 확인 해결

다이얼게이지 소 침 불량 DTR-200일 경우 전원 OFF / ON

스쿠류는 돌아가는데

">>>>" 증가가 안됨DTR-300N일 경우

상부커버 분리, 게이지 축

을 움직인다.

스쿠류 돌지 않고 ">>>>"

증가가 안됨DTR-300N일 경우 전원 OFF / ON

원인 확인 해결

스쿠류너트 최저점(100

mm) 밑으로 과다 회전

테이블과 스쿠류밑면 접

촉 확인

테이블에 홀(Φ80~)가공

하거나 스쿠류 조정

* 설치 및 응급조치 요령 입니다.

3. 스쿠류 작동불량

설치 시 주의사항

응급조치 요령

콘 교환다이아몬드 콘 파손

1. 경도 값 오차발생시

2. 초 하중 부하 시 작동불량

www.idtnt.com

Reason Check Solution

Abrasion of steel ball Chage steel ball

Function of compensation "Ø" function Set "0.00"

Trouble of dial gauge Lube oil

Change of the tester Leveling Leveling

Contact of screw cover Check bottom of anvil

Reason Check SolutionTrouble of small hand DTR-200 Reboot

No signal of">>>>" whilehandle works well DTR-300N Lease top cover & push

pivot of digital gauge

No signal of ">>>>" andbad works of handle DTR-300N Reboot

Reason Check SolutionOver works of screw handleto the bottom

Check the bottom ofmachine

Make a hole for screw onthe table (Ø80~)

Change diamond cone

2. Trouble during initial loading

Check by microscope

NOTICE

Before you call to DT&T !

3. Trouble of screw handle

1. INSTALL IN THE PLACE FREE OF HUMIDITY, VIBRATION AND HEAVY DUST2. MAKE A LEVEL BY MEANS OF TOOLS SUPPLIED3. BE CARE THE DAMAGE OF DIAMOND CONE4. HANDLE SMOOTHLY FOR INITIAL LOADING

1. Discrepancy of hardness value

Damage of diamond cone

Ver.1005/ROCKWELL Technical Instruction Manual 5

Page 11: Installation & Instruction ManualLocal agent Gyeongnam & Daegu - Korea PME Room # 103, shopping area in Samsung Buckinggham APT, 148-3, Yangdeok 2-dong, Hoewon-gu, Masan, Gyeongnam

Safety precautionsSection - 2

Safety inspection

Ver.1005/ROCKWELL Technical Instruction Manual 6

Safety inspection

To ensure safety, please conduct an inspection for the followings.

◈ Check for any shaking of the product. ◈ Check if there is any liquid on the machine.◈ Workers must fully pay attention to tests ◈ Workers must fully pay attention to tests. ◈ Workers must check their clothing prior to tests. ◈ In case of cleaning the inside of the machine, be sure to shut all power off. ◈ Be sure to shut all power off after completing tests. ◈ Only well experienced people are allowed for tests.

Ver.1005/ROCKWELL Technical Instruction Manual 6

Page 12: Installation & Instruction ManualLocal agent Gyeongnam & Daegu - Korea PME Room # 103, shopping area in Samsung Buckinggham APT, 148-3, Yangdeok 2-dong, Hoewon-gu, Masan, Gyeongnam

Technical ManualSection - 3

Listpage

Identifying nameplate ---------------------------------------------------- 2

Machine parts ------------------------------------------------------------- 3

List

- Product drawing ---------------------------------------------------------------------- 3 - Technical data (Part list and spec.) ----------------------------------------------- 5 - Diamond indenter - Ball indenter - Error of measurement

Operating conditions ----------------------------------------------------- 7

Ver.1005/ROCKWELL Technical Instruction Manual 1

Page 13: Installation & Instruction ManualLocal agent Gyeongnam & Daegu - Korea PME Room # 103, shopping area in Samsung Buckinggham APT, 148-3, Yangdeok 2-dong, Hoewon-gu, Masan, Gyeongnam

Technical ManualSection - 3

Identifying nameplateIdentifying nameplate

MODEL : DTR 300NMODEL : DTR - 300N

S / N : 10 - K1467

DATE : 2010. 01 / 1Y

POWER : 220V. AC / 50~60Hz

CURRENT : 1 Amps

MODEL : DTR - 300N

S / N : 10 - K1467

DATE : 2010. 01 / 1Y

POWER : 220V. AC / 50~60Hz

CURRENT : 1 Amps

Made in Korea.

www. idtnt.com Tel : 82 32 822 5511

◈ The above name plated is on the rear. Please put down S/N when you request for repair for quicker service.

- Model No. : model number of your product.

- S/N : serial number of the relevant product.

- DATE : calibration date at the factory - DATE : calibration date at the factory.

- POWER : electrical specification.

- CURRENT : ampere (fuse) is stipulated.

MODEL : DTR - 300N

S / N : 10 - K1467

DATE : 2010. 01 / 1Y

POWER : 220V. AC / 50~60Hz

CURRENT : 1 Amps

Made in Korea.

www. idtnt.com Tel : 82 32 822 5511

Ver.1005/ROCKWELL Technical Instruction Manual 2

Page 14: Installation & Instruction ManualLocal agent Gyeongnam & Daegu - Korea PME Room # 103, shopping area in Samsung Buckinggham APT, 148-3, Yangdeok 2-dong, Hoewon-gu, Masan, Gyeongnam

Technical ManualSection - 3

Machine partsMachine parts

- Product drawing (DTR-200N)

Ver.1005/ROCKWELL Technical Instruction Manual 3

Page 15: Installation & Instruction ManualLocal agent Gyeongnam & Daegu - Korea PME Room # 103, shopping area in Samsung Buckinggham APT, 148-3, Yangdeok 2-dong, Hoewon-gu, Masan, Gyeongnam

Technical ManualSection - 3

- Product drawing (DTR-300N) Product drawing (DTR 300N)

Ver.1005/ROCKWELL Technical Instruction Manual 4

Page 16: Installation & Instruction ManualLocal agent Gyeongnam & Daegu - Korea PME Room # 103, shopping area in Samsung Buckinggham APT, 148-3, Yangdeok 2-dong, Hoewon-gu, Masan, Gyeongnam

Technical ManualSection - 3

- Product spec. (DTR-200N) Product spec. (DTR 200N)

- Load : preload 10 kgf / test load (60,100,150) kgf - Max test height : 200 mm (When there is a hole on the table) - Max diameter of test sample : Ø250 - Dimension / Weight : (210 X 450 X 680) mm / 81 kg

- Load error : within ± 0 7 % - Load error : within ± 0.7 % - Error of hardness measure: HRC (20~40) : within ± 0.5 %

(40~60) : within ± 0.5 %(60~ ) : within ± 0.5 %

HRBW (30~50) : within ± 0.5 %(50~70) : within ± 0.5 %(70 ) ithi ± 0 5 %(70~ ) : within ± 0.5 %

- Name of each part

Upper cover

Dial gauge to indicate load

LightIndenter connecting partIndenter connecting part

Anvil

Handle to change test loadScrew handle

Sta t b ttonStart button

Level adjusting bolt

Ver.1005/ROCKWELL Technical Instruction Manual 5

Page 17: Installation & Instruction ManualLocal agent Gyeongnam & Daegu - Korea PME Room # 103, shopping area in Samsung Buckinggham APT, 148-3, Yangdeok 2-dong, Hoewon-gu, Masan, Gyeongnam

Technical ManualSection - 3

- Product spec. (DTR-300N) Product spec. (DTR 300N)

- Load : preload 10 kgf / test load (60,100,150) kgf - Max test height : 200 mm (When there is a hole on the table) - Max diameter of test sample : Ø250 - Dimension / Weight : (210 X 450 X 680) mm / 81 kg

- Load error : within ± 0 7 % - Load error : within ± 0.7 % - Error of hardness measure: HRC (20~40) : within ± 0.5 %

(40~60) : within ± 0.5 %(60~ ) : within ± 0.5 %

HRBW (30~50) : within ± 0.5 %(50~70) : within ± 0.5 %(70 ) ithi ± 0 5 %(70~ ) : within ± 0.5 %

- Name of each part

Upper cover

Operating part

LightIndenter connecting partIndenter connecting part

Anvil

Handle to change test load Screw handle

Level adjusting bolt

Ver.1005/ROCKWELL Technical Instruction Manual 6

Page 18: Installation & Instruction ManualLocal agent Gyeongnam & Daegu - Korea PME Room # 103, shopping area in Samsung Buckinggham APT, 148-3, Yangdeok 2-dong, Hoewon-gu, Masan, Gyeongnam

Technical ManualSection - 3

Operating conditionsOperating conditions

◈ This product can be used in the range of general indoor temperature. If the tolerance of voltage and current is exceeded, it can cause defect.

A di l l b th f ll i t t d f t Accordingly, please observe the followings to prevent defect.

- Operating temperature : 10 ℃ ~ 40 ℃ - Operating humidity

- Voltage : ≤ ±10% (within 10% of stipulated voltage): within 50 % R.H. (High humid can cause defect.)

- Current : ± 1 % (within 1% of stipulated current) - Place with no humidity - Place with no dust - Place with no direct rays of sunlight and place with good ventilation - Place with no corrosive substance - Place with no combustible materials Place with no combustible materials - Place for easier maintenance and inspection. - Install on a strong table with no vibration.

Ver.1005/ROCKWELL Technical Instruction Manual 7

Page 19: Installation & Instruction ManualLocal agent Gyeongnam & Daegu - Korea PME Room # 103, shopping area in Samsung Buckinggham APT, 148-3, Yangdeok 2-dong, Hoewon-gu, Masan, Gyeongnam

Installation ManualSection - 4

page

Tool required for installation ------------------------------------------ 2

Transporting product --------------------------------------------------- 2

Weight installation and leveling -------------------------------------- 3

Place for product installation ------------------------------------------ 4

Turning power ON ------------------------------------------------------ 4

Precautions during installation ---------------------------------------- 5

Power and earthing work ---------------------------------------------- 5

List

Ver.1005/ROCKWELL Technical Instruction Manual 1Ver.1005/ROCKWELL Technical Instruction Manual 1

Page 20: Installation & Instruction ManualLocal agent Gyeongnam & Daegu - Korea PME Room # 103, shopping area in Samsung Buckinggham APT, 148-3, Yangdeok 2-dong, Hoewon-gu, Masan, Gyeongnam

Installation ManualSection - 4

Tool required for installation

These tools are in the tool box that is supplied with the product.

Transporting the product

Ver.1005/ROCKWELL Technical Instruction Manual 2

Two persons are required for transporting.

( moving handle is inside of tool box )

Ver.1005/ROCKWELL Technical Instruction Manual 2

Page 21: Installation & Instruction ManualLocal agent Gyeongnam & Daegu - Korea PME Room # 103, shopping area in Samsung Buckinggham APT, 148-3, Yangdeok 2-dong, Hoewon-gu, Masan, Gyeongnam

Installation ManualSection - 4

Weight installation and leveling

① Remove rear cover. ② Connect the weight to inner ring

Ver.1005/ROCKWELL Technical Instruction Manual 3

③ Turn legs to adjust level ④ Check for verticality and horizontality by

turning the lever. (Adjust horizontality for

reach of weight in good condition on prop)

A

B

CWeight prop

Ver.1005/ROCKWELL Technical Instruction Manual 3

Page 22: Installation & Instruction ManualLocal agent Gyeongnam & Daegu - Korea PME Room # 103, shopping area in Samsung Buckinggham APT, 148-3, Yangdeok 2-dong, Hoewon-gu, Masan, Gyeongnam

Installation ManualSection - 4

Place for product installation Secure a space that is similar with the figure as below (optional).

500 mm

550 mm

650 mm

Φ 100 mm

Ver.1005/ROCKWELL Technical Instruction Manual 4

Turning power ON: Power switch is on the rear panel.

500 mm

550 mm

650 mm

Φ 100 mm

Ver.1005/ROCKWELL Technical Instruction Manual 4

Page 23: Installation & Instruction ManualLocal agent Gyeongnam & Daegu - Korea PME Room # 103, shopping area in Samsung Buckinggham APT, 148-3, Yangdeok 2-dong, Hoewon-gu, Masan, Gyeongnam

Installation ManualSection - 4

Precautions during installation

1) Ensure to check power supply in the installation place! - This product is designed for AC 220V, 1 A, 1ph, 50/60 Hz. - If power voltage is wrong, over current may cause a damage of the machine. - If you have different power voltage, please contact us.

2) Check the status of power earthing. - Earthing work can prevent electrical shock.

3) Check input power cable. - If it is possible, use exclusive power cable for the machine. - If the thickness of power cable in the input part does not match the capacity, it can cause a fire owing to over load.

4) Install the machine on a flat place. - This product is precise machine. - Never install the product on a slope or uneven place.

Ver.1005/ROCKWELL Technical Instruction Manual 5

- Please maintain level.

Power and earthing work

1) Power work - AC 220V, 1 A, 1ph, 50/60 Hz

2) Earthing work [Caution] - This product is designed for single phase 3 wire system based on standard of electric equipment. Be sure to connect the power cable to the plug with earthing. - If there is no earthing, it can damage electric and electronic parts owing to thunderbolt, etc. - In addition, it may cause electric shock.

Ver.1005/ROCKWELL Technical Instruction Manual 5

Page 24: Installation & Instruction ManualLocal agent Gyeongnam & Daegu - Korea PME Room # 103, shopping area in Samsung Buckinggham APT, 148-3, Yangdeok 2-dong, Hoewon-gu, Masan, Gyeongnam

How to use

Section - 5

page

How to test (DTR-200N) ------------------------------------------------------- 2

How to test (DTR-300N) ------------------------------------------------------- 3

Functions on digital display (DTR-300N) ------------------------------------- 6

Precautions during test -------------------------------------------------------- 9

Standard accessories ----------------------------------------------------------- 9

Reference ------------------------------------------------------------------------ 10

1) Reference Table 1 - Rockwell hardness scale

2) Reference Table Ⅱ. Correction value when cylinder type test sample

is tested with C,A,D scale

3) Reference Table Ⅲ. Correction value when Cylinder-type test sample

List

Ver.1005/ROCKWELL Technical Instruction Manual 1

is tested with B,F,G scale

Ver.1005/ROCKWELL Technical Instruction Manual 1

Page 25: Installation & Instruction ManualLocal agent Gyeongnam & Daegu - Korea PME Room # 103, shopping area in Samsung Buckinggham APT, 148-3, Yangdeok 2-dong, Hoewon-gu, Masan, Gyeongnam

How to use

Section - 5

① Tester must be installed on a place with no dust, humidity, or vibration.

② Install the machine a strong support, drill a hole on the prop on the lower part of the

SCREW about 90mm diameter and 160mm deep to allow lowering of the SCREW.

③ Install the machine a support, open the packing and then adjust horizontality.

To adjust horizontality, adjust horizontality to make test weight and test weight prop

is a straight line using horizontality adjusting screw.

④ Clean contacting surface on the lower part of ANVIL to sure that Anvil is free of filth

and/or oil.

⑤ Select a scale (Reference TableⅠ) suitable for a test sample, insert diamond cone or

steel ball indenter suitable for scale and then set test weight according to the scale by

turning test weight adjusting HANDLE.

⑥ Turn MAIN switch ON and check if the LAMP is ON.

If the Lamp is not ON, automatically move back to test position.

How to test (DTR‐200N)

Ver.1005/ROCKWELL Technical Instruction Manual 2

⑦ Place a test sample on ANVIL and turn SCREW HANDLE clockwise to let short needle be

located at the middle of red point after the needle of the indicating GAUGE rotates 3 times.

⑧ Press START BUTTON to start operating. LAMP will be flickering and turned OFF.

At this point load will be applied and returned automatically. When a test is completed,

the LAMP will be ON.

⑨ When the needle of indicating GAUGE stops and LAMP is ON, a test is completed.

In case of diamond cone, read black number, and in case of steel ball indenter,

read red value as hardness value.

⑩ Turn SCREW HANDLE counterclockwise to remove test sample.

How to test (DTR‐200N)

Ver.1005/ROCKWELL Technical Instruction Manual 2

Page 26: Installation & Instruction ManualLocal agent Gyeongnam & Daegu - Korea PME Room # 103, shopping area in Samsung Buckinggham APT, 148-3, Yangdeok 2-dong, Hoewon-gu, Masan, Gyeongnam

How to use

Section - 5

INDENTER

Test sample

How to test (DTR‐300N)

① Locate a test sample on Anvil.

② Turn the handle clockwise to raise the Anvil.

③ When a test sample and indenter are met, the following screen will be displayed.

④ By turning the handle, the gauge number and ">>>>>" mark keeps progressing.

(Stage in which 10 kgf of preload is applied.)

How to test (DTR‐300N)

Ver.1005/ROCKWELL Technical Instruction Manual 3

Page 27: Installation & Instruction ManualLocal agent Gyeongnam & Daegu - Korea PME Room # 103, shopping area in Samsung Buckinggham APT, 148-3, Yangdeok 2-dong, Hoewon-gu, Masan, Gyeongnam

How to use

Section - 5

⑤ Keeps turning the handle slowly until ">>>" mark reaches the end of the screen and

you hear 'beep' sound.

DAEKYUNG TECHHTTP://WWW.IDTNT.COM

MENU Ø RESET ENTER

ROCKWELL HARDNESS TESTER

150kgf Install

HRC Diamond Cone

Gauge 0.017 mm

>>>

Ver.1005/ROCKWELL Technical Instruction Manual 4

⑥ When you hear 'Beep' sound, stop turning handle and wait for about 6 seconds

to see the test result.

DAEKYUNG TECHHTTP://WWW.IDTNT.COM

MENU Ø RESET ENTER

ROCKWELL HARDNESS TESTER

150kgf Install

HRC Diamond Cone

Gauge 0.017 mm

>>>

DAEKYUNG TECHHTTP://WWW.IDTNT.COM

MENU Ø RESET ENTER

ROCKWELL HARDNESS TESTER

150kgf Install

HRC Diamond Cone

Gauge 0.059 mm

>>>>>>>>>>>>>>>>>>>>Beep~!

Ver.1005/ROCKWELL Technical Instruction Manual 4

Page 28: Installation & Instruction ManualLocal agent Gyeongnam & Daegu - Korea PME Room # 103, shopping area in Samsung Buckinggham APT, 148-3, Yangdeok 2-dong, Hoewon-gu, Masan, Gyeongnam

How to use

Section - 5

⑦ Press Up/Down arrow (▲,▼) in the above result output screen to calculate

the result by another unit.

DAEKYUNG TECHHTTP://WWW.IDTNT.COM

MENU Ø RESET ENTER

ROCKWELL HARDNESS TESTER

HRC 62.6 Add on

AvrS.D

62.6 NumFUL

15

U / D Unit Change

J HRA 60K

Ver.1005/ROCKWELL Technical Instruction Manual 5

* Example Unit value

HRC = 62.6

SHORE = 86.2

HV 10K = 759

HRD = 72.6

DAEKYUNG TECHHTTP://WWW.IDTNT.COM

MENU Ø RESET ENTER

ROCKWELL HARDNESS TESTER

HRC 62.6 Add on

AvrS.D

62.6 NumFUL

15

U / D Unit Change

J HRA 60K

Ver.1005/ROCKWELL Technical Instruction Manual 5

Page 29: Installation & Instruction ManualLocal agent Gyeongnam & Daegu - Korea PME Room # 103, shopping area in Samsung Buckinggham APT, 148-3, Yangdeok 2-dong, Hoewon-gu, Masan, Gyeongnam

How to use

Section - 5

Functions on digital display

DAEKYUNG TECHHTTP://WWW.IDTNT.COM

MENU Ø RESET ENTER

ROCKWELL HARDNESS TESTER

150kgf Normal selection

HRC Diamond Cone

Gauge 0.000

Normal. Standby

Ver.1005/ROCKWELL Technical Instruction Manual 6

- MENU : Function to display whole menu

- Ø : Enter diameter during measuring a test sample of cylinder or

globular shape to compensate value.

- RESET : Reset the machine when Gauge in the main screen does not come to 0.

- ENTER : Eenter changed detail.

- SCALE : Set hardness unit (scale) to be tested.

Select one of the scales (Unit) below using arrows.

MENU

HRC HRA HRB HRD

HRE HRF HRG HRH

HRK HRL HRM HRP

HRR HRS HRV

DAEKYUNG TECHHTTP://WWW.IDTNT.COM

MENU Ø RESET ENTER

ROCKWELL HARDNESS TESTER

150kgf Normal selection

HRC Diamond Cone

Gauge 0.000

Normal. Standby

Ver.1005/ROCKWELL Technical Instruction Manual 6

Page 30: Installation & Instruction ManualLocal agent Gyeongnam & Daegu - Korea PME Room # 103, shopping area in Samsung Buckinggham APT, 148-3, Yangdeok 2-dong, Hoewon-gu, Masan, Gyeongnam

How to use

Section - 5

- Load maintain : to apply main load

- add or subtract by 1 second using Up/down arrows (▲,▼).

- Read standby : Set standby time before reading.

- add or subtract by 1 second using Up/down arrows (▲,▼).

- Min HRC : Estimated minimum available value -> when it is below this value,

Error message will be displayed.

- Set it using Up/down/right/left arrows (▲,▼,◀,▶)

- Max HRC : Estimated maximum available value -> when it is above this value,

Error message will be displayed.

- Set it using Up/down/right/left arrows (▲,▼,◀,▶)

- Consecutive time: Maximum number of test times that can be stored (initial value = 0)

- Max 200 tests can be stored and the average and deviation for 200 tests

will be displayed.

- result view : Check stored average value and deviation.

- data initialization: Delete stored data.

Ver.1005/ROCKWELL Technical Instruction Manual 7

- Language : Function to convert Korean/English

- Load unit : Convert load symbol to kgf / N.

- Serial print : Change printer settings (off / OnK / OnA).

- When it is OFF, can not print serial number. Currently,

OnK and OnA are same.

① Press Right arrow (▶) to print currently displayed hardness value (1 time).

2008-02-27 09:55:17

Test Number : (Input test No manually.)

Test Date : (Input test date manually.)

Operator : (Input a person who conducted test manu

Specimen : (Input test sample manually.)

Remarks :

001 : HRC 027.20 (Test times: print hardness value)

Ver.1005/ROCKWELL Technical Instruction Manual 7

Page 31: Installation & Instruction ManualLocal agent Gyeongnam & Daegu - Korea PME Room # 103, shopping area in Samsung Buckinggham APT, 148-3, Yangdeok 2-dong, Hoewon-gu, Masan, Gyeongnam

How to use

Section - 5

② Press Left arrow(◀) to print hardness values measured so far

2008-02-27 09:55:17

Test Number : (Input test No manually.)

Test Date : (Input test date manually.)

Operator : (Input a person who conducted test manu

Specimen : (Input test sample manually.)

Remarks : (Input remarks manually.)

001 : HRC45 (test times: print hardness value)

Total No : 001 (print test times so far)

Avr Value : 027.20 (Print average hardness value so far.)

S.D Value : 000.00 (Print average hardness so far.)

- Backlight : Set lighting time (Can set up to 200 seconds - power saving mode)

- correction mode : Setting for off / C-1 / C-2 correction.

- This menu is for correction. Users use it in OFF condition.

Ver.1005/ROCKWELL Technical Instruction Manual 8

- C-1 is used for indirect correction using standard test sample.

- C-2 is used for direct correction using load cell.

- Debug mode : Do not change basic value of 'NON'

- Conversion mode: Display JIS / ASTM standard.

- End : Finish the settings

- Press Right arrow to move to End key in any MENU.

- R. Cylindrical : In case of cylinder type test sample, input radius (R) value.

- After finishing cylinder-form test sample, be sure to restore it to

initial setting (0.00mm).

- Available range is 0.00 ~ 19.99mm. (Based on ASTM)

- D. Spherical : In case of globular form test sample, input D (diameter) value.

- After finishing globular form test sample, be sure to restore it to

initial setting (0.00mm).

- Available range is 0.00 ~ 25.99mm. (Based on ASTM)

- Exit End the program

Ø

Ver.1005/ROCKWELL Technical Instruction Manual 8

Page 32: Installation & Instruction ManualLocal agent Gyeongnam & Daegu - Korea PME Room # 103, shopping area in Samsung Buckinggham APT, 148-3, Yangdeok 2-dong, Hoewon-gu, Masan, Gyeongnam

How to use

Section - 5

Precautions during test

- Roughly process contacting surface between test sample and ANVIL until it becomes

flat surface for tests.

- Vertically install test sample and indenter and ensure that mark surface is not too coarse.

- To select a scale suitable for a test sample, please see Reference Table Ⅰ.

- Selecting Anvil

Round pipe : V ANVIL (Ø40, big one)

Small pins : V ANVIL (Ø10, small one)

Anvil's contacting surface step shape: SPOT ANVIL

In case of big test sample : Ø 200 mm PLANE ANVIL - optional

- Ensure that you do not give impact on diamond cone during replacing ANVIL or a test sample.

- In case of cylinder type test sample, please refer to Reference Table Ⅱ,Ⅲ.

Standard accessories (Optional items can be change upon user's request.)

Ver.1005/ROCKWELL Technical Instruction Manual 9

- Standard hardness test sample HRC S : 1 ea

- Standard hardness test sample HRBW : 1 ea

- Load weight (60, 100, 150)kg : 1 set

- Diamond cone : 1 ea

- Steel ball indenter (1/16") : 1 ea (tungsten ball)

- Spare indenter (1/16") : 1 ea (tungsten ball)

- SPOT ANVIL (Ø10) : 1 ea

- PLANE ANVIL (Ø63) : 1 ea

- PLANE ANVIL (Ø200) : 1 ea

- V ANVIL (Ø40, big one) : 1 ea

- V ANVIL (Ø10, small one) : 1 ea

-Tester COVER : 1 ea

- P.P box (Tool BOX) : 1 ea (including wrench, spanner, spare bulb)

- Manual : 1 copy

- Test report : 1 copy

- Printer for DTR-300N : optional

- Program for DTR-300N : optional

- Test Table : optional

Ver.1005/ROCKWELL Technical Instruction Manual 9

Page 33: Installation & Instruction ManualLocal agent Gyeongnam & Daegu - Korea PME Room # 103, shopping area in Samsung Buckinggham APT, 148-3, Yangdeok 2-dong, Hoewon-gu, Masan, Gyeongnam

How to use

Section - 5

Reference

1) Reference Table 1 - Rockwell hardness scale

2) Reference Table Ⅱ. Correction value when a cylinder-form test sample is tested with C,A,D scale

Ver.1005/ROCKWELL Technical Instruction Manual 10Ver.1005/ROCKWELL Technical Instruction Manual 10

Page 34: Installation & Instruction ManualLocal agent Gyeongnam & Daegu - Korea PME Room # 103, shopping area in Samsung Buckinggham APT, 148-3, Yangdeok 2-dong, Hoewon-gu, Masan, Gyeongnam

How to use

Section - 5

3) Reference Table Ⅲ. Correction value when a cylinder-form test sample is tested with B,F,G scale

Ver.1005/ROCKWELL Technical Instruction Manual 11Ver.1005/ROCKWELL Technical Instruction Manual 11

Page 35: Installation & Instruction ManualLocal agent Gyeongnam & Daegu - Korea PME Room # 103, shopping area in Samsung Buckinggham APT, 148-3, Yangdeok 2-dong, Hoewon-gu, Masan, Gyeongnam

Electrical ManualSection - 6

page

Circuit drawings -------------------------------------------------------- 2

Parts list ----------------------------------------------------------------- 3~5

List

Ver.1005/ROCKWELL Technical Instruction Manual 1Ver.1005/ROCKWELL Technical Instruction Manual 1

Page 36: Installation & Instruction ManualLocal agent Gyeongnam & Daegu - Korea PME Room # 103, shopping area in Samsung Buckinggham APT, 148-3, Yangdeok 2-dong, Hoewon-gu, Masan, Gyeongnam

Electrical ManualSection - 6

Ver.1005/ROCKWELL Technical Instruction Manual 2Ver.1005/ROCKWELL Technical Instruction Manual 2

Page 37: Installation & Instruction ManualLocal agent Gyeongnam & Daegu - Korea PME Room # 103, shopping area in Samsung Buckinggham APT, 148-3, Yangdeok 2-dong, Hoewon-gu, Masan, Gyeongnam

Electrical ManualSection - 6

Parts list

SEQ Div. Q'TY

1 I.C. 1

2 I.C. 1

3 I.C. 1

4 I.C. 1

5 I.C. 1

6 I.C. 3

7 I.C. 3

8 I.C. 1

9 I.C. 1

10 I.C. 1

11 I.C. 1

12 I.C. 1

13 I.C. 6

14 I.C. 4

15 TR 3

U14

U5

U6

U12

ATmega134

74HC4059

ATmega132

74HC4058

ATmega133

U10

U2

U3

U4

U13

U11

ATmega131

74HC4057 U9

ATmega128

74HC4053

74HC4054

ATmega129

74HC4055

U1

ATmega130

74HC4056

U15

U7

U8

REMARK

74HC4060

Item

Ver.1005/ROCKWELL Technical Instruction Manual 3

16 SSR 1

17 POWER 1

18 POWER 1

19 POWER 1

20 POWER 1

21 OSC 1

22 Resonator 1

24 Resistor 3

25 Resistor 1

26 Resistor 60

27 Resistor 1

ATmega137

U22

33 Ohm, 0805 Size

Resistor23

74HC4061

14

U16

U17

R3, R85, R88

U21

U18

U19

U20

ATmega138

R3, R85, R8936 Ohm, 0805 Size

ATmega136

74HC4062

R10, R44, R54 R80,R84,R87, R93, R111,R118, JP1, SW4, SW9,

SW20, SW21

R3, R85, R86

0 Ohm, 0805 Size

34 Ohm, 0805 Size R3, R85, R87

74HC4063

ATmega135

35 Ohm, 0805 Size

Ver.1005/ROCKWELL Technical Instruction Manual 3

Page 38: Installation & Instruction ManualLocal agent Gyeongnam & Daegu - Korea PME Room # 103, shopping area in Samsung Buckinggham APT, 148-3, Yangdeok 2-dong, Hoewon-gu, Masan, Gyeongnam

Electrical ManualSection - 6

Parts list

28 Resistor 1

30 Resistor 4

31 Resistor 1

32 Resistor 2

33 Array 3

34 Capacitor 2

35 Capacitor 23

29 Resistor4.7 KOhm, 0805

Size15

R94

R12, R14, R15, R16,R17,R18, R19, R20, R21,

R39, R49, R78, R96,R199, R212

R121, R198

RN1, RN2, RN3

C2, C4

C6, C7, C8, C9, C10,C11, C12, C13, C32,C33, C24 CP1, CP2,CP3, CP4, CP5, CP6,CP7, CP8, CP9, CP10,

CP11, BP1

R13, R45, R56, R98100 KOhm, 0805

SiR92

2.2 KOhm, 0805Si

33 Ohm, 1206 Size

1 KOhm, Array-4EA

30pF, 0805 Size

0.1uF, 0805 Size

10 KOhm, 0805Si

Ver.1005/ROCKWELL Technical Instruction Manual 4

36 Capacitor 9

37 Capacitor 4 C34, C35, C36, C37

41 FET 2

42 Connector 3

43 Connector 1

44 Connector 2

45 Connector 1

46 Connector 1

47 Connector 1

48 Connector 1

C3, C5, C22, C23, C25,C26, C27, C28, C29

JP7, JP14

P4

D3, D4

SW1, SW2, SW3

47uF/16V SMD,electrolytic condenser

BOX CONNECTOR10X2 2.54mm R /A

P3

P5

JP7, JP16

10uF/16V Tantal, BSize-SMD

JP7, JP15

HEADER 3X1 S/T,2.54mm

HEADER 6X1 S/T,2.54mm

Outer connector2X1 R/A, 5mm

BOX CONNECTOR5X2 2.54mm R/A

BOX CONNECTOR8X2 2.54mm R/A

BOX CONNECTOR15X2 2.54mm R/A

SI9953DY

Ver.1005/ROCKWELL Technical Instruction Manual 4

Page 39: Installation & Instruction ManualLocal agent Gyeongnam & Daegu - Korea PME Room # 103, shopping area in Samsung Buckinggham APT, 148-3, Yangdeok 2-dong, Hoewon-gu, Masan, Gyeongnam

Electrical ManualSection - 6

Parts list

49Connecto

r1

50 Switch 1

51 variable resistance 1

52 BUZZER 1

53 Socket 6

54Jumper

Pin3

55 MOTOR 1

56INLETFI-

LTER1

2.54mm JumperPin

P6

JP7, JP17

JP7, JP18

P7

S6R06GXCE

IQ-06220H2

8-pin DIP

Cylinder type-DIP

10KOhm-VR

Keypad 10x1,2.5mm

2-pole TACT switch

Ver.1005/ROCKWELL Technical Instruction Manual 5Ver.1005/ROCKWELL Technical Instruction Manual 5

Page 40: Installation & Instruction ManualLocal agent Gyeongnam & Daegu - Korea PME Room # 103, shopping area in Samsung Buckinggham APT, 148-3, Yangdeok 2-dong, Hoewon-gu, Masan, Gyeongnam

MAINTENANCESection - 7

Ver.1005/ROCKWELL Technical Instruction Manual 1

page

Before test -------------------------------------------------------------- 2

List

After test ---------------------------------------------------------------- 2

Weekly Maintenance ----------------------------------------------------------- 2

Monthly Maintenance ----------------------------------------------------------- 2

Yearly Maintenance -------------------------------------------------------------- 2

How to take emergency measures ----------------------------------- 3

Ver.1005/ROCKWELL Technical Instruction Manual 1

Page 41: Installation & Instruction ManualLocal agent Gyeongnam & Daegu - Korea PME Room # 103, shopping area in Samsung Buckinggham APT, 148-3, Yangdeok 2-dong, Hoewon-gu, Masan, Gyeongnam

MAINTENANCESection - 7

Ver.1005/ROCKWELL Technical Instruction Manual 2

Before test

- Check if the indenter and load is correct according to the scale.

- During inserting or taking out diamond indenter, be careful that the indenter does not bump into the Anvil on the lower part. Diamond indenter is relatively sensitive to impact.

- Check if the product is not shaking prior to any test.h l h l h l f f When a test sample is heavy, please pay attention to the sample for safety.

- Any person who conduct the test must wear gloves. If you touch Anvil with bare hand, it will get rusty easily and give small effect to hardness value.

After test

- During taking out an indenter after test, be careful that the indenter does not bump into the Anvil on the lower part.

- Replace the product cover after each test.

Weekly Maintenance

- Remove dust near and on the screw and clean the machine - Remove dust near and on the screw and clean the machine.

- Wipe each Anvil with oil to prevent rust.

Monthly Maintenance

R d t d th d l l b i t - Remove dust near and on the screw and apply new lubricant.

Yearly Maintenance

- To ensure the normal operation of the product, please conduct periodic calibration inspection every year.

Ver.1005/ROCKWELL Technical Instruction Manual 2

Page 42: Installation & Instruction ManualLocal agent Gyeongnam & Daegu - Korea PME Room # 103, shopping area in Samsung Buckinggham APT, 148-3, Yangdeok 2-dong, Hoewon-gu, Masan, Gyeongnam

MAINTENANCESection - 7

Ver.1005/ROCKWELL Technical Instruction Manual 3

* How to take emergency measures.

www.idtnt.com

NOTICE1 INSTALL IN THE PLACE FREE OF HUMIDITY

Before you call to DT&T !

1. INSTALL IN THE PLACE FREE OF HUMIDITY, VIBRATION AND HEAVY DUST2. MAKE A LEVEL BY MEANS OF TOOLS SUPPLIED3. BE CARE THE DAMAGE OF DIAMOND CONE4. HANDLE SMOOTHLY FOR INITIAL LOADING

Reason Check Solution

Abrasion of steel ball Chage steel ball

Change diamond coneCheck by microscope

y1. Discrepancy of hardness value

Damage of diamond cone

Abrasion of steel ball Chage steel ball

Function of compensation "Ø" function Set "0.00"

Trouble of dial gauge Lube oil

Change of the tester Leveling Leveling

Contact of screw cover Check bottom of anvil

2 Trouble during initial loadingReason Check Solution

Trouble of small hand DTR-200 Reboot

No signal of">>>>" whilehandle works well DTR-300N Lease top cover & push

pivot of digital gauge

No signal of ">>>>" andbad works of handle DTR-300N Reboot

2. Trouble during initial loading

bad works of handle

Reason Check SolutionOver works of screw handleto the bottom

Check the bottom ofmachine

Make a hole for screw onthe table (Ø80~)

3. Trouble of screw handle

Ver.1005/ROCKWELL Technical Instruction Manual 3

Page 43: Installation & Instruction ManualLocal agent Gyeongnam & Daegu - Korea PME Room # 103, shopping area in Samsung Buckinggham APT, 148-3, Yangdeok 2-dong, Hoewon-gu, Masan, Gyeongnam

Certificate and calibration reportSection - 8

List

Ver.1005/ROCKWELL Technical Instruction Manual 1

page

Calibration report ------------------------------------------------------ attached

ISO 9001 certificate ------------------------------------------------------------- 2

List

CE certificate ----------------------------------------------------------------------- 3

International calibration Institute's certificate, KOLAS ------------ 5

International test Institute's certificate, KOLAS -------------------- 6

Corporate R&D Institute certificate ---------------------------------------- 7

Certificate of Patent ---------------------------------------------------- 8

Excellent Service Quality ---------------------------------------------- 9

Ver.1005/ROCKWELL Technical Instruction Manual 1

Page 44: Installation & Instruction ManualLocal agent Gyeongnam & Daegu - Korea PME Room # 103, shopping area in Samsung Buckinggham APT, 148-3, Yangdeok 2-dong, Hoewon-gu, Masan, Gyeongnam

Certificate and calibration reportSection - 8

Ver.1005/ROCKWELL Technical Instruction Manual 2Ver.1005/ROCKWELL Technical Instruction Manual 2

Page 45: Installation & Instruction ManualLocal agent Gyeongnam & Daegu - Korea PME Room # 103, shopping area in Samsung Buckinggham APT, 148-3, Yangdeok 2-dong, Hoewon-gu, Masan, Gyeongnam

Certificate and calibration reportSection - 8

Ver.1005/ROCKWELL Technical Instruction Manual 3Ver.1005/ROCKWELL Technical Instruction Manual 3

Page 46: Installation & Instruction ManualLocal agent Gyeongnam & Daegu - Korea PME Room # 103, shopping area in Samsung Buckinggham APT, 148-3, Yangdeok 2-dong, Hoewon-gu, Masan, Gyeongnam

Certificate and calibration reportSection - 8

Ver.1005/ROCKWELL Technical Instruction Manual 4Ver.1005/ROCKWELL Technical Instruction Manual 4

Page 47: Installation & Instruction ManualLocal agent Gyeongnam & Daegu - Korea PME Room # 103, shopping area in Samsung Buckinggham APT, 148-3, Yangdeok 2-dong, Hoewon-gu, Masan, Gyeongnam

Certificate and calibration reportSection - 8

Ver.1005/ROCKWELL Technical Instruction Manual 5Ver.1005/ROCKWELL Technical Instruction Manual 5

Page 48: Installation & Instruction ManualLocal agent Gyeongnam & Daegu - Korea PME Room # 103, shopping area in Samsung Buckinggham APT, 148-3, Yangdeok 2-dong, Hoewon-gu, Masan, Gyeongnam

Certificate and calibration reportSection - 8

Ver.1005/ROCKWELL Technical Instruction Manual 6Ver.1005/ROCKWELL Technical Instruction Manual 6

Page 49: Installation & Instruction ManualLocal agent Gyeongnam & Daegu - Korea PME Room # 103, shopping area in Samsung Buckinggham APT, 148-3, Yangdeok 2-dong, Hoewon-gu, Masan, Gyeongnam

Certificate and calibration reportSection - 8

Ver.1005/ROCKWELL Technical Instruction Manual 7Ver.1005/ROCKWELL Technical Instruction Manual 7

Page 50: Installation & Instruction ManualLocal agent Gyeongnam & Daegu - Korea PME Room # 103, shopping area in Samsung Buckinggham APT, 148-3, Yangdeok 2-dong, Hoewon-gu, Masan, Gyeongnam

Certificate and calibration reportSection - 8

Ver.1005/ROCKWELL Technical Instruction Manual 8Ver.1005/ROCKWELL Technical Instruction Manual 8

Page 51: Installation & Instruction ManualLocal agent Gyeongnam & Daegu - Korea PME Room # 103, shopping area in Samsung Buckinggham APT, 148-3, Yangdeok 2-dong, Hoewon-gu, Masan, Gyeongnam

FAQSection - 9

List

Ver.1005/ROCKWELL Technical Instruction Manual 1

page

Error of hardness value. ----------------------------------------------- 2~3

Error during applying preload. ---------------------------------------- 4

List

Screw does not turn. --------------------------------------------------- 5

Product power won't be ON. ------------------------------------------ 6

Ver.1005/ROCKWELL Technical Instruction Manual 1

Page 52: Installation & Instruction ManualLocal agent Gyeongnam & Daegu - Korea PME Room # 103, shopping area in Samsung Buckinggham APT, 148-3, Yangdeok 2-dong, Hoewon-gu, Masan, Gyeongnam

FAQSection - 9

Error of hardness value.

Occurrence of an error of hardness value is caused by various reasonsOccurrence of an error of hardness value is caused by various reasons.Check for the error observing the following orders.

1. Damage of diamond indenter (in case of HRC measurement)

If k i d i i HRC l fi t f ll - If an error keeps occurring during measuring HRC scale, first of all, check for the damage on the diamond indenter.

- How to measure : 1) Check with tool microscope: 2) Scratch glass if there is any mark

- Measures : replace diamond indenter

2. Wear or bent of steel ball (in case of HRB measurement)

- If an error keeps occurring during measuring HRBW scale, it probably If an error keeps occurring during measuring HRBW scale, it probably because of bent or wear of steel ball.

- Measures : replace the ball

3. When you use a function of curved surface compensation for a flat test sample (DTR-300N model) for a flat test sample (DTR-300N model)

- In case of DTR-300N model, if there is big difference of value, check if there is any value for the function of curved surface compensation. (See 'How to use', page 8.)

- Measures : set both of D, R value to 0.

Ver.1005/ROCKWELL Technical Instruction Manual 2

Page 53: Installation & Instruction ManualLocal agent Gyeongnam & Daegu - Korea PME Room # 103, shopping area in Samsung Buckinggham APT, 148-3, Yangdeok 2-dong, Hoewon-gu, Masan, Gyeongnam

FAQSection - 9

Error of hardness value.

Occurrence of an error of hardness value is caused by various reasonsOccurrence of an error of hardness value is caused by various reasons.Check for the error observing the following orders.

4. Transport and re-installation of the product.

If h d th d t t di ti th l l t i - If you have moved the product at you discretion, the level or centering of a weight of for load pressurization is twisted causing an error.

- Measures : Open rear cover, adjust and centering of a weight for load pressurization to the centering of a support.

5. Upper part of screw cover is projected.

- You can remove screw cover according to test sample. Sometimes, screw cover has been raised to touch the Anvil Sometimes, screw cover has been raised to touch the Anvil causing big effect to a test.

- Measures : Turn screw cover to secure gap between Anvil and a test sample.

Maintain regular gapMaintain regular gap

Ver.1005/ROCKWELL Technical Instruction Manual 3

Page 54: Installation & Instruction ManualLocal agent Gyeongnam & Daegu - Korea PME Room # 103, shopping area in Samsung Buckinggham APT, 148-3, Yangdeok 2-dong, Hoewon-gu, Masan, Gyeongnam

FAQSection - 9

Error during applying preload.

Check for errors observing the following orders.

1. In case of DTR-200N, when the small needle on the dial gauge does not move.

M Sh t OFF f b t 30 d d - Measures : Shut power OFF for about 30 seconds and turn back it ON.

2. In case of DTR-300N, when '>>>>>>' mark does not appear during applying preload. - Measures : 1) Shut power OFF for about 30 seconds and

turn back it ON.: 2) If it is not solved with the above measure, remove upper cover and then softly move the needle of digital gauge.

Remove upper front cover Softly press digital gauge rod

Ver.1005/ROCKWELL Technical Instruction Manual 4

Page 55: Installation & Instruction ManualLocal agent Gyeongnam & Daegu - Korea PME Room # 103, shopping area in Samsung Buckinggham APT, 148-3, Yangdeok 2-dong, Hoewon-gu, Masan, Gyeongnam

FAQSection - 9

Screw does not turn. (DTR-200N/300N)

In this case, Check for errors observing the following orders.

1. If there is no hole on the bottom of the product to allow the screw to be lowered, the end of the screw can contact the table.

- Measures : Lift up the product slightly and then raise the screw.

Ver.1005/ROCKWELL Technical Instruction Manual 5

Page 56: Installation & Instruction ManualLocal agent Gyeongnam & Daegu - Korea PME Room # 103, shopping area in Samsung Buckinggham APT, 148-3, Yangdeok 2-dong, Hoewon-gu, Masan, Gyeongnam

FAQSection - 9

Product power is won't ON.

When a fuse is melt off owing to over current or etcWhen a fuse is melt off owing to over current or etc, the power won't ON.Please replace the fuse observing the following order.

1 Sh t i OFF d h k f BOX it h t1. Shut main power OFF, and check fuse BOX on power switch part on the rear side of the machine.

2. The front side of the power switch box to find two fuses. fuse on the bottom is one that is currently used and thee is a spare fuse on the top. Replace the fuse on the bottom with new fuse on the top.

Ver.1005/ROCKWELL Technical Instruction Manual 6

Page 57: Installation & Instruction ManualLocal agent Gyeongnam & Daegu - Korea PME Room # 103, shopping area in Samsung Buckinggham APT, 148-3, Yangdeok 2-dong, Hoewon-gu, Masan, Gyeongnam

Quality warrantysection - 10

Ver.1005/ROCKWELL Technical Instruction Manual

1. The product went through quality control and inspection.

Quality warranty

2. For safe and proper use of this product, be sure to check the characteristics of the product and maintenance method described in the manual.

3. Free warranty term of this product is 1 year after installation date.

4 f f f4. In case of defect during warranty term under normal operation of the machine according to the precautions in instruction manual and nameplate, repair service will be provided free of charge.5. When free warranty term is over, actual expense will be invoiced for long distance trip.6. We provide customer service. In case of request for after sales service, basically we provide service within 24 hours. However, in case of unavoidable situation, we sincerely request you for your cooperation.7. This warranty is only for domestic customers. For foreign customers, we will make a separate contract. 8. In case of the following situations, service charge will be basically invoiced.

① Defect caused by carelessness or improper repair or renovation ② When somebody besides A/S staff of Daekyung Tech & Tester Mfg disassemble the product or replace any part ③ In case of defect and/or damage owing to fire, earthquake, flood,

abnormal supply voltage and natural disaster

Product Name Delivery Date

Model Name warranty term

Installed by Received by

CEO Ju, chung-geunDaekyung Tech & Tester Mfg. Co., Ltd.

Ver.1005/ROCKWELL Technical Instruction Manual

Page 58: Installation & Instruction ManualLocal agent Gyeongnam & Daegu - Korea PME Room # 103, shopping area in Samsung Buckinggham APT, 148-3, Yangdeok 2-dong, Hoewon-gu, Masan, Gyeongnam

Date :To Customer Support Team, DT&T From

Tel/Fax 032-822-5511 / 032-821-4580 Staff CPAdd 118B-10L, 688-10, Gojan-dong, Namdong-gu, Incheon Add

Attention Mr. Song, Gi-man/Deputy Gnarl Mgr (extension 555) Tel/FaxMachine Model No. Capacity

Delivery Date Machine No. Desired A/S Date

Flaw Date Others■ Details of flaw or defect

☞ In case of After Sales Service;Any service due to user's obvious mistake within the term of guarantee(1 year) and service after termination of the term of guarantee or separate contract will be charged.In case of service with charge, trip cost and labor cost will be charged, replacement of a part or a product will be additionally charged.

☞ In case of repair;We will decide if we can repair the product requested by a customer. The processing order is 'Cost estimation -> Approval -> Repair'.

Requestor's Check

■ We do not receive any request by telephone. Please send us this 'Request form'. Please put down full details because all information provided by you will be very valuable data to manufacture better products.

Repair Details

Request for □ A/S / □ Repair

/