installation issues and solutions - fieldbus · installation – issues and solutions ... mtl...

53
1 1 Successful Implementation & Improved Operation Installation Issues and Solutions Andreas Agostin Industrial Network Sales Specialist Asia Pacific MTL Instruments Singapore, part of Cooper Crouse-Hinds 22.02.2012 Kuala Lumpur

Upload: truongdang

Post on 25-Jul-2018

216 views

Category:

Documents


0 download

TRANSCRIPT

1 1 Successful Implementation & Improved Operation

Installation – Issues and Solutions

Andreas Agostin Industrial Network Sales Specialist Asia Pacific

MTL Instruments Singapore, part of Cooper Crouse-Hinds

22.02.2012 Kuala Lumpur

2 2 Successful Implementation & Improved Operation

Introduction

Fieldbus is in use since 19981, yet still new for

many customers today.

This presentation will look at the installation issues

and the “lessons learned”, so that you can

benefits from their experience.

1 Shell Malampaya is one of the early, larger projects. 1600 FF instruments are in use. The project produced first gas in

Oct 2001. Source: J. Seaver, Shell Philippines Exploration B.V., “Malampaya Deep Water Gas-to-Power Project:

Malampaya Subsea Development”, Offshore Technology Conference, 6 May-9 May 2002, Houston, Texas.

3 3 Successful Implementation & Improved Operation

Introduction

The pictures you will see are collected from “real”

projects; they are neither simulated nor “demo”.

We will look at – Control room: cabinet design and wiring

– Field: Wiring, field junction boxes, field device installation.

Processes typically involve explosion protection methods

“intrinsic safety” (I.S. / Ex i; energy limitation by a „barrier‟)

or “explosion proof” (Ex d; protection by explosionproof

enclosure).

Many examples use “IS” as this is a key product of my

company and that is where I get involved.

4 4 Successful Implementation & Improved Operation

Disclaimer

All products shown serve as EXAMPLE only.

In particular, problems shown in conjunction with a product

serve as example only.

The brand/make/model of the product serving as example

is IRRELEVANT.

Problems highlighted serve as example only, are do in no

way express problems with a particular product,

model or brand.

5 5 Successful Implementation & Improved Operation

The conventional system

6 6 Successful Implementation & Improved Operation

Control room – Conventional wiring

2nd level 1st level

junction box Marshalling

and barrier Control system

7 7 Successful Implementation & Improved Operation

Control room – Conventional wiring

Marshalling: to group AI / AO / DI / DO / etc

8 8 Successful Implementation & Improved Operation

Control room – Conventional wiring

9 9 Successful Implementation & Improved Operation

Control room – Conventional wiring

Long wires, standard length

Allows pre-fabrication of wire

(ferrules, mounting)

Conventional signals (4-20mA,

RTD, thermocouple, 0-

5V/10V/24V) – slow, hardware

filtered, length less important

10 10 Successful Implementation & Improved Operation

Field – Conventional wiring

Quality (material)

Safety

Location / access

Weight/size, …

10

11 11 Successful Implementation & Improved Operation

Fieldbus versus conventional

12 12 Successful Implementation & Improved Operation

Control room – DCS wiring EXAMPLES

Fieldbus

Conventional

13 13 Successful Implementation & Improved Operation

Control room – DCS wiring EXAMPLES

Installations do not have

to look messy. They

can be very nice, too.

Fieldbus

Conventional

14 14 Successful Implementation & Improved Operation

Control room – DCS wiring EXAMPLES Fieldbus Conventional

15 15 Successful Implementation & Improved Operation

Control room – DCS wiring EXAMPLES

Fieldbus Fieldbus

16 16 Successful Implementation & Improved Operation

Control room – DCS wiring

Important:

do not use individual wires to

wire cabinet. Use fieldbus cable

and shield properly.

Why?

Higher signal

frequency – protect

them against

disturbances.

Individual wires will

cause crosstalk from

one wire to another –

communication faults

can occur.

?

17 17 Successful Implementation & Improved Operation

Fieldbus Cable Recommended: Type A cable: Shielded twisted pair Other cable is possible, but there are limitations in terms of achievable cable distance and electromagnetic compatibility (EMC). Fieldbus is a digital “high speed” (31kBit/s) communication, a current modulated signal superimposed on the DC power.

18 18 Successful Implementation & Improved Operation

Fieldbus Cable

Shielded pair

principle

Foil

shield

Foil plus

braided

shield

SWA

SWA

Multi-pair

Multi-pair (multi-trunk)

19 19 Successful Implementation & Improved Operation

Please not this way

Images obscured – Brand is irrelevant.

20 20 Successful Implementation & Improved Operation

Control room – DCS wiring

21 21 Successful Implementation & Improved Operation

Fieldbus system – Field wiring

? • Parallel wiring

(terminals)

• special wiring

blocks

• (daisy chaining)

22 22 Successful Implementation & Improved Operation

Fieldbus system – Field junction boxes

Principle of wiring distribution in junction box:

all devices are in parallel

Source: FF AG 140 Rev. 1

23 23 Successful Implementation & Improved Operation

Fieldbus system – Field junction boxes

Please not this way

24 24 Successful Implementation & Improved Operation

24

Fieldbus system – Field junction boxes

Use dedicated

wiring blocks

with built-in

electronic

short circuit

protection.

LEDs: - built-in s/c protection

25 25 Successful Implementation & Improved Operation

Good Wiring Practices

Test segment wiring before connecting components Avoid damaging the wire when removing insulation Ground the cable shield only at one point (at the control

room end) Insulate the ungrounded end of the cable shield (at the

instrument) Ground armor on both sides (potential equalization) Use crimp ferrules

– Ferrule diameter must fit wire – Crimp tool must fit ferrule – Ferrule must fit terminals

Maintain polarity and associated color codes throughout the segment

26 26 Successful Implementation & Improved Operation

Good Wiring Practices

Lessons learned:

Torque screwdriver

Wire end ferrules

Right (!) wire strippers

Fieldbus tester

Harms

wire strands

Choose

right size

AWG ..

27 27 Successful Implementation & Improved Operation

Fieldbus Design Tools (Examples)

28 28 Successful Implementation & Improved Operation

Project Procedure

Best practice:

Bench test

Functional tests and interoperability test

FAT

SAT

29 29 Successful Implementation & Improved Operation

Installation Guidelines

Cable Tests – Experience has shown that new cable irregularities are

so infrequent that it is more efficient to check cable after installation

Cable Installation – Verify that cable is properly installed, bypassing impact

from wiring components Segment Checkout

– Check of proper wiring of wiring components Device installation

– Check of proper device installation Loop checkout

– Functional test

30 30 Successful Implementation & Improved Operation

Installation tools

Portable fieldbus diagnostic test equipment

(Handhelds)

Measures relevant fieldbus

parameters

Establish baseline

after commissioning

31 31 Successful Implementation & Improved Operation

Handheld diagnostic tools

Handheld

Diagnostic

Tool Device 1 Device 3 Device 2

T

Device Coupler

& Terminator

(non-IS) Spurs

FFPS

T

FF Power Supply

& Conditioner

&Terminator

24VDC

Host

Computer

H1 Interface

Connect at respective location to obtain accurate measurement.

32 32 Successful Implementation & Improved Operation

Handheld diagnostic tools

Handheld

Diagnostic

Tool

FFPS

T

FF Power Supply

& Conditioner

&Terminator

24VDC

Host

Computer

H1 Interface

Fieldbus

barrier

Device 1 Device 3 Device 2

Fieldbus barrier

& Terminator

Intrinsically

Safe Spurs

T

Fieldbus

barrier

To measure at fieldbus barrier/IS segments, Handheld needs to be Ex i approved.

Important since the galvanic isolation of fieldbus barrier impacts on measurement.

33 33 Successful Implementation & Improved Operation

Earthing/Grounding

Grounding in the control room

One point grounding only

Continuous shield from control room to the field

Shield not connected at the field instrument

Connect cable armor at both ends (potential

equalization)

34 34 Successful Implementation & Improved Operation

Earthing/Grounding

Device 1 Device 3 Device 2

T

Wiring Block

& Terminator FFPS

T

FF Power Supply

& Conditioner

&Terminator

24VDC

Host

Computer

H1 Interface

35 35 Successful Implementation & Improved Operation

Fieldbus

barrier

Device 1 Device 3 Device 2

Fieldbus barrier

& Terminator

Intrinsically

Safe Spurs

T

Fieldbus

barrier

Earthing/Grounding

FFPS

T

FF Power Supply

& Conditioner

&Terminator

24VDC

Host

Computer

H1 Interface

36 36 Successful Implementation & Improved Operation

Local field junction box for 4

instruments. Rust prevented

proper grounding, so that

separate ground connection

was required

37 37 Successful Implementation & Improved Operation

Field – Fieldbus wiring

Green: fieldbus

Red: Power (Motors, etc)

For easy maintenance

38 38 Successful Implementation & Improved Operation

Troubleshooting

39 39 Successful Implementation & Improved Operation

Daisy chaining – not recommended

40 40 Successful Implementation & Improved Operation

Troubleshooting

Electrical welding can generate significant surges

41 41 Successful Implementation & Improved Operation

Bend radius too tight, Upward facing gland risks water ingress

Two cables into one gland

prevents sealing of gland

42 42 Successful Implementation & Improved Operation

Water ingress caused corrosion of wire and terminals

43 43 Successful Implementation & Improved Operation

Cable jacket stripped back too far

Troubleshooting

44 44 Successful Implementation & Improved Operation

Wires coming out of ferrules

45 45 Successful Implementation & Improved Operation

Troubleshooting

Earth stud not connected – internal

surge protectors not working

46 46 Successful Implementation & Improved Operation

Troubleshooting

Ground not connected

47 47 Successful Implementation & Improved Operation

Troubleshooting

Poor cable (shield) quality

48 48 Successful Implementation & Improved Operation

Troubleshooting

Grounding concept failure-prone

49 49 Successful Implementation & Improved Operation

Troubleshooting

Water marks, fungus inside junction box

50 50 Successful Implementation & Improved Operation

Troubleshooting

Wire squeezed by enclosure lid – water ingress

51 51 Successful Implementation & Improved Operation

http://forums.fieldbus.org/showthread.php?t=1298

52 52 Successful Implementation & Improved Operation

Conclusion

Fieldbus is robust if the installation is adjusted to

the requirements of a digital communication line

Do not simply copy 4-20 methods

Use fieldbus smartly (e.g. eliminate marshalling)

Good wiring practices are more important than

on 4-20 due to bus structure

Train your installers on fieldbus practices

53 53 Successful Implementation & Improved Operation

Installation – Issues and Solutions

Andreas Agostin Industrial Network Sales Specialist Asia Pacific

MTL Instruments Singapore, part of Cooper Crouse-Hinds

22.02.2012 Kuala Lumpur

[email protected]

Ph: +65 97585161