institutional equity research india utilitiesbackoffice.phillipcapital.in/...utilities_sector... ·...

92
INSTITUTIONAL EQUITY RESEARCH Page | 1 | PHILLIPCAPITAL INDIA RESEARCH India Utilities Waiting for a new dawn INDIA | Utilities 28 April 2015 The Indian Power Utilities sector has underperformed the BSE Sensex 15%/2% during FY14 /FY15 as the sector grappled with fuel uncertainty and suppressed demand from loss making SEBs leading to lower utilization for generators. Post a series of reform measures initiated over the past few years, we are constructive on the transmission utilities and fuel suppliers while still cautious on the generation segment, pending distribution reforms. We initiate coverage with a BUY on Coal India, Power Grid, PTC India and a Neutral rating on NTPC. Slowdown in pace of capacity addition We believe India’s annual pace of capacity addition of ~ 1820GW (ex renewable) during past few years to slow down to 1214GW during FY1719E. We note limited near term ability of Coal India (CIL) to ramp up supply which coupled with distribution related issues would lead developers to delay commissioning. Note that Coal India has signed FSA’s with 78GW of plants commissioning till FY15 – there is little clarity on fuel supplies for power plants commissioning post FY15 and this would lead to delays in CoD. DemandSupply equilibrium by 2020 Based on our estimate of 86GW capacity addition during FY1520E (83GW in the XIIth plan), we expect supply growth at 8.5% CAGR. Supply would be driven by coal based generation at 9% CAGR. We expect utilization would pick up; however PLF will still continue to be sub optimal. Transmission constraints, limited availability of indigenous fuel and under utilization would continue, in our view. Thus, based on an 8% electricity demand growth, we expect India to attain equilibrium in electricity by FY20. However, we do note that for India to maintain this equilibrium in XIIIth and XIVth plan it is necessary to commence equipment ordering during FY1618E. Gradual ramp up in fuel supply – no quick fix solution possible We expect India will continue to be a net importer of coal unless India makes progress to improve domestic supply. Although new government has shown strong intent in speeding up construction of critical rail links for coal evacuation, benefits of these lines will accrue post FY18. Thus, we expect all India demand for coal to rise at 7% CAGR during FY1420E to 1.1bn tons driven by demand for power utilities and supply at 7.4% CAGR, implying 6% CAGR in import to 225mn tone by FY20. For utilities, we expect demand to grow 8% CAGR during FY1420E to 780mn tone and supply to grow to 681mn tone (8% CAGR) during same period leading to 7% CAGR growth in import. Distributionthe weakest link which remains unresolved Distribution remains the weakest link in the Indian power sector value chain as continued interference of state governments coupled with unremunerative tariffs has resulted in losses to the tune of Rs1060bn (FY13) to state discoms. Chronic under investment in distribution due to weak financial health of discoms ensures ~25% of power input in system remain unbilled. Although measures such as FRP (2003 and 2013) and feeder separation schemes have been initiated to mitigate losses, however implementation has been sketchy. Key stock recommendations We initiate coverage on PGCIL with Buy rating and target price of Rs 176 as we remain optimistic on transmission capex. We also initiate coverage on Coal India with target price of Rs 475 as we expect production and dispatches to improve driven by faster clearances. We initiate coverage on PTC India with target price of Rs 120 led by volume driven growth and strong performance of subsidiary driven by renewable capex. We initiate coverage on NTPC with Neutral rating and target price of Rs 160 as we expect stringent operational parameters under new tariff norms will result in subdued 4% CAGR during FY1517E. Companies Coal India Reco BUY CMP, Rs 376 Target Price, Rs 475 NTPC Reco Neutral CMP, Rs 153 Target Price, Rs 160 PGCIL Reco BUY CMP, Rs 150 Target Price, Rs 176 PTC India Reco BUY CMP, Rs 75 Target Price, Rs 120 Ankur Sharma(+ 9122 6667 9759) [email protected] Hrishikesh Bhagat(+ 9122 6667 9986) [email protected]

Upload: others

Post on 22-Sep-2020

0 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: INSTITUTIONAL EQUITY RESEARCH India Utilitiesbackoffice.phillipcapital.in/...Utilities_Sector... · post FY18. Thus, we expect all India demand for coal to rise at 7% CAGR during

INSTITUTIONAL EQUITY RESEARCH  

Page | 1 | PHILLIPCAPITAL INDIA RESEARCH 

India Utilities  Waiting for a new dawn  INDIA | Utilities 

 

  

28 April 2015 

The  Indian Power Utilities sector has underperformed the BSE Sensex 15%/2% during FY14 /FY15 as the sector grappled with fuel uncertainty and suppressed demand from loss making SEBs  leading to  lower utilization  for generators. Post a series of reform measures  initiated over the past few years, we are constructive on the transmission utilities and fuel suppliers while  still  cautious  on  the  generation  segment,  pending  distribution  reforms. We  initiate coverage with a BUY on Coal India, Power Grid, PTC India and a Neutral rating on NTPC.  Slowdown in pace of capacity addition We believe India’s annual pace of capacity addition of ~ 18‐20GW (ex renewable) during past few years to slow down to 12‐ 14GW during FY17‐19E.  We note limited near term ability of Coal India (CIL) to ramp up supply which coupled with distribution related issues would lead developers  to delay  commissioning. Note  that  Coal  India  has  signed  FSA’s with  78GW  of plants  commissioning  till  FY15  –  there  is  little  clarity  on  fuel  supplies  for  power  plants commissioning post FY15 and this would lead to delays in CoD.   Demand‐Supply equilibrium by 2020 Based on our estimate of 86GW capacity addition during FY15‐20E (83GW in the XIIth plan), we expect supply growth at 8.5% CAGR. Supply would be driven by coal based generation at 9% CAGR. We  expect utilization would pick up; however PLF will  still  continue  to be  sub optimal.  Transmission  constraints,  limited  availability  of  indigenous  fuel  and  under utilization would continue, in our view. Thus, based on an 8% electricity demand growth, we expect India to attain equilibrium in electricity by FY20. However, we do note that for India to maintain this equilibrium in XIIIth and XIVth plan it is necessary to commence equipment ordering during FY16‐18E.  Gradual ramp up in fuel supply – no quick fix solution possible We expect  India will continue to be a net  importer of coal unless  India makes progress to improve domestic supply. Although new government has shown strong  intent  in speeding up  construction of  critical  rail  links  for  coal evacuation, benefits of  these  lines will accrue post FY18. Thus, we expect all India demand for coal to rise at 7% CAGR during FY14‐20E to 1.1bn tons driven by demand for power utilities and supply at 7.4% CAGR, implying 6% CAGR in import to 225mn tone by FY20. For utilities, we expect demand to grow 8% CAGR during FY14‐20E to 780mn tone and supply to grow to 681mn tone  (8% CAGR) during same period leading to 7% CAGR growth in import.  Distribution‐ the weakest link which remains unresolved Distribution remains  the weakest  link  in  the  Indian power sector value chain as continued interference  of  state  governments  coupled  with  unremunerative  tariffs  has  resulted  in losses  to  the  tune  of  Rs1060bn  (FY13)  to  state  discoms.  Chronic  under  investment  in distribution due to weak financial health of discoms ensures ~25% of power input in system remain unbilled. Although measures  such  as  FRP  (2003 and  2013)  and  feeder  separation schemes have been initiated to mitigate losses, however implementation has been sketchy.   Key stock recommendations We  initiate  coverage  on  PGCIL with  Buy  rating  and  target  price  of  Rs  176  as we  remain optimistic on transmission capex. We also initiate coverage on Coal India with target price of Rs 475 as we expect production and dispatches to improve driven by faster clearances. We initiate coverage on PTC India with target price of Rs 120 led by volume driven growth and strong performance of subsidiary driven by renewable capex. We initiate coverage on NTPC with Neutral rating and target price of Rs 160 as we expect stringent operational parameters under new tariff norms will result in subdued 4% CAGR during FY15‐17E.     

Companies  Coal India Reco  BUY CMP, Rs  376 Target Price, Rs  475  NTPC Reco  Neutral CMP, Rs  153 Target Price, Rs  160  PGCIL Reco  BUY CMP, Rs  150 Target Price, Rs  176  PTC India Reco  BUY CMP, Rs  75 Target Price, Rs  120                   Ankur Sharma(+ 9122 6667 9759) [email protected]  Hrishikesh Bhagat(+ 9122 6667 9986) [email protected] 

  

Page 2: INSTITUTIONAL EQUITY RESEARCH India Utilitiesbackoffice.phillipcapital.in/...Utilities_Sector... · post FY18. Thus, we expect all India demand for coal to rise at 7% CAGR during

  

Page | 2 | PHILLIPCAPITAL INDIA RESEARCH 

UTILITIES SECTOR 

Valuation Table  Target  ___________ PE___________ ___________ PB ___________  __________ ROE __________

CMP  Price  Rating  FY15E  FY16E FY17E FY15E FY16E FY17E  FY15E  FY16E FY17E Coal India   376  475  BUY  15.8  12.9 11.3               5.7               4.8                4.1   36%  37% 36% NTPC   150  160  Neutral  15.0  13.3 12.3               1.5               1.4                1.3   11%  11% 11% PGCIL   150  176  BUY  15.1  12.1 10.3               2.1               1.9                1.7   14%  16% 17% PTC India   75  121  BUY  7.9  7.8 6.6               0.8               0.7                0.7   6%  7% 7%

Source: Phillip Capital India Research Estimates    Stock performance v/s Sensex 

 Source: Phillip Capital India Research Estimates        

‐10

10

30

50

70

90

110

130

150

1/1/2011 1/1/2012 1/1/2013 1/1/2014 1/1/2015

BSE Sensex PGCIL NTPC PTCIN Coal India

Page 3: INSTITUTIONAL EQUITY RESEARCH India Utilitiesbackoffice.phillipcapital.in/...Utilities_Sector... · post FY18. Thus, we expect all India demand for coal to rise at 7% CAGR during

  

Page | 3 | PHILLIPCAPITAL INDIA RESEARCH 

UTILITIES SECTOR 

Contents   

Big Opportunity clouded by weak execution  ‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐   4 

Generation‐ Private Sector leads the way  ‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐    7 

Mapping Demand and Supply    ‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐   11 

Fuel: Challenges to persist    ‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐   15 

Distribution ‐ Weak link in the value chain  ‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐   22 

Transmission‐ Bright Spot  ‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐   27 

 

Companies Section 

Coal India  ‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐   28 

NTPC ‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐   43 

Power Grid Corporation of India ‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐   61 

PTC India   ‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐   78      

   

Page 4: INSTITUTIONAL EQUITY RESEARCH India Utilitiesbackoffice.phillipcapital.in/...Utilities_Sector... · post FY18. Thus, we expect all India demand for coal to rise at 7% CAGR during

  

Page | 4 | PHILLIPCAPITAL INDIA RESEARCH 

UTILITIES SECTOR 

Big opportunity clouded by weak execution India has one of the  lowest per capita power consumption which represents a huge opportunity at macro  level; however  this has been clouded due  to weak execution. Note that chronic under investments, high power deficits coupled with rising demand during  the  last  decade  compelled  government  to  delicense  generation  (2003)  and introduce competitive based bidding  (2006)  to attract private players  in  the sector; however outcome has been relatively mixed. Although substantial focus was made on the generation segment of  the value chain, however such skewed approach  in past decade  led  to  inadequate  focus  on  fuel  and  transmission  segment,  the  impact  of which was felt during FY10‐14.  Per Capita Consumption 

 Source:WorldFactbook, Phillip Capital  Deficit Chart 

 Source: CEA  We  note  since  electricity  in  India  comes  under  concurrent  list  of  constitution, presence of State government particularly in distribution segment of value chain has significantly  impacted  the  sector  performance.  Although  government  in  India  had embarked upon ambitious project “Power for All by 2012”, the deadline for the same has been a moving  target. The government’s  (State as well as Central) halfhearted approach  towards  reforms  in  sector  has  kept  investors  largely  cautious.  The  ideal ratio  is Rs0.5  in transmission for every Re 1  invested  in generation. But the focus  in early plan period has largely been generation. We note capacity addition during FY07‐14 was a CAGR of 7% as against 4% witnessed during FY94‐04.  

498

3493

6017

11919

2286

4347

0

2000

4000

6000

8000

10000

12000

14000

India China Russia USA Brazil South Africa

Per Capita Power consumption (Kwh)

0

5

10

15

20

25

30

FY02 FY03 FY04 FY05 FY06 FY07 FY08 FY09 FY10 FY11 FY12 FY13 FY14 FY15

Base Deficit Peak Deficit

India has one of the lowest per capita consumption and elevated deficit  

Page 5: INSTITUTIONAL EQUITY RESEARCH India Utilitiesbackoffice.phillipcapital.in/...Utilities_Sector... · post FY18. Thus, we expect all India demand for coal to rise at 7% CAGR during

  

Page | 5 | PHILLIPCAPITAL INDIA RESEARCH 

UTILITIES SECTOR 

Installed Capacity 

   Source: CEA   Evolution of Indian Power Sector Year  Particular 1910  The Electricity Act 1910 created broad framework for electric supply 1948  The Electricity Act 1910 amended to create SEB to encourage electrification 1970‐1990  Creation of Central Utilities NTPC,NHPC, NEEPCO and transmission utilities 1991  The Electricity Act 19148 amended to allow private participation 1995  Introduction of Mega Power Policy, privatization of distribution initiated 1998  The Electricity Act (amendment) 1948 that promulgated creation of SERC and CERC and central and State transmission utility 2002  SEB restructuring 2003  Electricity Act 2003,  allowed for Open Access, performance based regulation, delicensing of power generation and introduction of power trading2006  Competitive bidding guidelines introduced, Rural Electrification Policy 2007  Electricity (act ) amended , clarity on cross subsidy 2008  Introduction of Power Exchanges 2009  LTOA regulation 2011  PoC charges 

Source: PhillipCapital India Research  

 

0

50,000

100,000

150,000

200,000

250,000Capacity addition (MW)

7%

4% Pace of capacity addition has picked up post 2008 with entry of private sector  

Page 6: INSTITUTIONAL EQUITY RESEARCH India Utilitiesbackoffice.phillipcapital.in/...Utilities_Sector... · post FY18. Thus, we expect all India demand for coal to rise at 7% CAGR during

  

Page | 6 | PHILLIPCAPITAL INDIA RESEARCH 

UTILITIES SECTOR 

Significant steps…..but mixed outcomes During past  two years,  sector has gone  through a  significant pain as  large  capacity additions  was  not  followed  up  with  much  needed  ramp  up  in  fuel  supply  and investment  in T&D. Despite SEB restructuring undertaken  in 2002, we note political intervention  coupled  with  unremunerative  tariffs  has  led  to  huge  losses  to distribution  companies  resulting  in  second  round  of  restructuring  (FRP)  in  2013. Higher losses impaired purchasing power leading to weak demand from SEB. Further lack of environmental clearances impacted CIL’s production, leading to fuel shortage.   We note  since 2012,  the government has  taken  series of  steps  to  revive  investors’ sentiment, however the outcomes of these steps has largely been mixed.  Steps Undertaken by the government to revive the power sector 1. CIL agreed to sign FSA for 78 GW (includes 8GW for tapering linkage). 2. PPA tariff revision for unremunerative PPA initiated by CERC and MERC. 3. Revised Case II SBD issued and revised Case I SBD expected in near term. 4. FRP  approved  for  debt  restructuring  of  discoms  and  working  capital  finance 

recommenced by banks and PFC & REC. 5. Pass through of imported coal cost in lieu of domestic shortage for linkage plants 

approved by CCEA subject to SERC’s approval 6. Removal of Go‐No Go policy by the MOEF. 7. Synchronisation of southern grid with national grid 8. Final  regulation for  MYT 2015‐19 issued by CERC 9. Deendayal Upadhyaya Gram Jyoti Yojana” for feeder separation  launched 10. Coal block auction policy issued post de allocation of mines by Supreme Court 11. Amendment  to  Electricity  Act  initiated  and  approved  by  the  Cabined  in 

December, 2014. This needs to be passed by the Parliament. 12. Land  acquisition  bill  amendment  approved  by  Cabinet  –  pending  clearance  in 

parliament. 13. Coal Swapping to reduce logistics cost for utilities  We  note  final  impact  of  these  steps  has  largely  been mixed  bag.  Although,  coal production  has  begun  to  improve  led  by  speedier  clearances,  however  imports continue  to  surge. On  distribution  front,  however  implementation  of  FRP  has  not been  in  its  true  spirit.    Although  demand  has  improved  in  key  states  driven  by disbursal, however  this has not been  followed up with  requisite measures  such  as tariff hike, implementation of “Model State Electricity Distribution Act”, reduction of T&D  by  states.  Further,  tariff  revision  initiated  by  electricity  commissions’  remain stuck in legal quagmire.  Power Index performance 

 Source: Bloomberg 

0

100

200

300

400

500

600

BSE Power

Entry of private players boost sentiments

Strong primary market activity from private players kept 

sentiment bouyant

Reality check as fuelshortage and weak SEB 

Reformmeasures and hopes of strong government boost 

Page 7: INSTITUTIONAL EQUITY RESEARCH India Utilitiesbackoffice.phillipcapital.in/...Utilities_Sector... · post FY18. Thus, we expect all India demand for coal to rise at 7% CAGR during

  

Page | 7 | PHILLIPCAPITAL INDIA RESEARCH 

UTILITIES SECTOR 

Generation ‐ Private Sector leads the way We acknowledge India’s effort towards increasing capacity addition. The government taking cognizance of rising deficit  in early decade allowed entry of private sector by delicensing  the  sector.  Post  the  aggressive  entry  of  private  sector  in  generation segment, pace  of  capacity  addition  gained  significant  traction.  Thus we  note  India added  59GW  during  FY12‐14,  and  to  put  that  into  perspective  it was  2x  capacity addition during FY08‐11.We note share of private sector in India’s generation sector gone up from 13% in FY07 to 26% in FY14.  Deficit 

 Source:  CEA   Capacity addition 

 Source: CEA  The  capacity  addition  from  private  sector  was  aided  by  a  favorable  policy environment led by tax holiday, easy financing and swift clearances.          

2.0 

4.0 

6.0 

8.0 

10.0 

12.0 

FY98 FY99 FY01 FY02 FY03 FY04 FY05 FY06 FY07 FY08 FY09 FY10 FY11 FY12 FY13 FY14 FY15

Base Deficit (%)

0

5,000

10,000

15,000

20,000

25,000 Capacity addition (MW)

Higher deficit ushered entry of private sector  

Capacity addition gained traction  

Page 8: INSTITUTIONAL EQUITY RESEARCH India Utilitiesbackoffice.phillipcapital.in/...Utilities_Sector... · post FY18. Thus, we expect all India demand for coal to rise at 7% CAGR during

  

Page | 8 | PHILLIPCAPITAL INDIA RESEARCH 

UTILITIES SECTOR 

……….however pace to slow down We expect pace of  capacity addition  to  slow down  in upcoming  years. We believe India’s annual capacity addition of ~ 18‐20GW during past few years to slow down to 12‐  14GW.  Thus,  in  XIIth plan we  expect  India  to  add  83GW  (54 GW  achieved  till Feb’15) capacity lower than CEA’s estimate of 88GW. At 83 GW the capacity addition will  be  equivalent  to  India’s  total  capacity  addition  during  Xth  and  XIth  plan. Also during FY18‐20E we expect capacity addition at 40 GW.  Capacity addition 

  Source: CEA        Our key arguments in favor of slowdown in capacity addition are:  1. CIL’s ability to meet FSA’s only to the extent of 78 GW for plants commissioned 

till  FY15.  This  would  continue  to  create  fuel  uncertainty  for  plants  to  be commissioned post FY15 and delay commissioning of such plants. 

2. Existing  issues  at  distribution  end  continue  to  remain  unresolved  thus suppressing demand and PLF’s. Further we believe during past FY11‐15e, India’s capacity addition was not commensurate to demand (105GW). Thus, as existing capacity gets absorbed in the system, and till utilization of existing capacity picks up developers would continue to delay CoD. 

3. Further we note equipment ordering has slowed down materially post euphoria witnessed  during  FY07‐10,  thus  raising  concerns  over  capacity  addition  during 13th plan. Also, a large segment of orders is being driven by state utilities that are prone  to delays. We believe  capacity  addition  in early part of 13th plan would largely  be  led  by  slippages  of  12th  plan,  and  state  utilities  to  drive  capacity addition in the 13th plan. 

 BTG ordering 

 Source: PhillipCapital India Research Estimate 

10 

12 

21  21 

18 

22 

13 

10 

16 

13 11 

10 

15 

20 

25  Capacity addition (GW)

Pace of capacity addition to slow down 

Page 9: INSTITUTIONAL EQUITY RESEARCH India Utilitiesbackoffice.phillipcapital.in/...Utilities_Sector... · post FY18. Thus, we expect all India demand for coal to rise at 7% CAGR during

  

Page | 9 | PHILLIPCAPITAL INDIA RESEARCH 

UTILITIES SECTOR 

4. Leverage  on  IPP’s  balance  sheet  continues  to  be  elevated  as  most  of  their existing  capacity  remains  stuck  in  unremunerative  tariff.  Unless  issues  on unremunerative  tariffs are addressed  through  legal solution, balance sheet and cash  flow  strain will  continue  for  IPP’s which  in  turn will  impact new  capacity addition. 

 Leverage of various players (graphs) 

 Source: Bloomberg, PhillipCapital India Research Estimate  We note higher leverage has opened up significant inorganic opportunities within the sector. Many leveraged developers have sold assets to address cash flow issues. We expect merger and asset sale to continue, however we note many assets continue to struggle  due  to  unremunerative  PPA  and  coupled  with  cost  escalation  the  ROE;s continue to be suppressed.  M&A in the Power sector has picked up with IPP’s looking to deleverage  Asset  Capacity  Developer  Acquirer  Amount Rs/MWBaspa & Karcham  1391  JPVL  JSW Energy              94,260                  68 Budhil  70  Lanco Infra  Tejassarnika Hydro Energies Private               6,240                  89 Udupi  1200  Lanco Infra  Adani Power              60,000                  50 Korba West  600  Avantha Power  Adani Power              42,000                  70 Karcham and Baspa  1391  JPVL  JSW Energy              97,000                  70 Bela TPS  540  Ideal Energy  Tata Power               NA NAJangir Champa  1200  DB Power  IDFC PE(15% stake)               5,000  28

Source: PhillipCapital India Research  Like  in  previous  plans,  we  expect  capacity  addition  to  be  driven  by  coal  sector. Limited availability of  indigenous gas would  impact capacity additions. We also note that hydro based capacity in India continue to be impacted by lack of clearances and local issues.  Capacity addition estimate‐ Fuel wise Fuel   FY08   FY09   FY10   FY11   FY12   FY13   FY14   FY15E   FY16E   FY17E   FY18E   FY19E   FY20E Coal         5,620         2,010         6,655         9,225       17,884       18,115       15,095       18,765       10,525         8,620       12,730       11,540       10,460 Lignite              ‐              ‐            335            635            520            540              ‐           250              ‐             ‐              ‐              ‐             ‐Gas         1,000            475         2,116         1,391            674         1,457         1,672         1,189              ‐             ‐         2,400            770              ‐Thermal         6,620         2,485         9,106       11,251       19,078       20,112       16,767       20,204       10,525         8,620       15,130       12,310       10,460 Hydro         2,423            969              39            690         1,423            501         1,060            872         1,496         1,671         1,190            900            400 Nuclear            220              ‐            440            220              ‐             ‐             ‐        1,000         1,000              ‐              ‐              ‐           500 Total         9,263         3,454         9,585       12,161       20,501       20,613       17,827       22,076       13,021       10,291       16,320       13,210       11,360 

Source:  CEA, PhillipCapital India Research Estimate  We note capacity addition would be driven by the private sector in the 12th plan and its share in overall capacity mix would increase. However based on ordering it is likely 

0

1

2

3

4

5

6

7

8

NTPC  TPWR  RPWR  NHPC  ADANI  JSW  JPVL  NLC  SJVN 

Debt Equity (x)

Leverage continues to be elevated across most private players  

Page 10: INSTITUTIONAL EQUITY RESEARCH India Utilitiesbackoffice.phillipcapital.in/...Utilities_Sector... · post FY18. Thus, we expect all India demand for coal to rise at 7% CAGR during

  

Page | 10 | PHILLIPCAPITAL INDIA RESEARCH 

UTILITIES SECTOR 

that share of private sector could stagnate by end of 12th plan and capacity addition from state and central utilities would pick up.  Capacity addition estimate‐ Ownership wise Ownership   FY08   FY09   FY10   FY11   FY12   FY13   FY14   FY15E   FY16E   FY17E   FY18E   FY19E   FY20E Centre         3,240            750         2,180         3,780         5,820         5,397         2,575         4,405         4,315         2,300         3,710         5,360         7,400 State         5,273         1,821         3,118         3,259         3,761         3,958         3,367         3,416         3,930         2,595            750              ‐             ‐Private            750            883         4,287         5,122       10,920       11,258       11,885       14,255         4,776         5,396       11,860         7,850         3,960 Total         9,263         3,454         9,585       12,161       20,501       20,613       17,827       22,076       13,021       10,291       16,320       13,210       11,360 

   Capacity addition break‐ up 

 Source: CEA, PhillipCapital India Research Estimates  

State wise capacity addition (MW) MW  FY08  FY09  FY10  FY11 FY12 FY13 FY14E FY15E FY16E  FY17E  FY18E  FY19E FY20EAndhra Pradesh  249  39  1,516  1,586 1,189 300 300 2,190 2,120  960  3,060  1,430 ‐Arunachal Pradesh  ‐  ‐  ‐  ‐ ‐ ‐ ‐ ‐ 300  410  ‐  ‐ ‐Assam  ‐  ‐  ‐  ‐ 37 ‐ ‐ 250 250  250  ‐  ‐ ‐Bihar  500  ‐  500  ‐ ‐ ‐ 660 1,105 445  500  1,320  1,980 660Chhattisgarh  1,500  1,000  850  500 1,490 1,345 3,530 3,135 1,020  960  3,780  3,060 1,600Delhi  1,072 286 250 500 ‐ ‐  ‐  ‐  ‐ ‐Gujarat  40  383  1,874  1,570 4,481 5,024 1,151 776 ‐  250  760  ‐ ‐HARYANA  600  ‐  600  1,100 1,160 1,160 ‐ ‐ ‐  ‐  ‐  ‐ ‐HP  ‐  ‐  ‐  192 1,100 301 597 437 500  675  ‐  640 400J&K  ‐  450  ‐  120 ‐ 44 285 ‐ ‐  ‐  330  ‐ ‐Jharkhand  ‐  ‐  500  ‐ 1,550 1,040 ‐ ‐ 500  ‐  1,740  1,860 2,640Karnataka  720  230  600  1,070 1,100 ‐ ‐ ‐ ‐  ‐  1,600  800 ‐Kerala  ‐  ‐  ‐  100 ‐ ‐ ‐ 30 30  ‐  ‐  ‐ ‐Madhya Pradesh  1,020  210  ‐  ‐ ‐ 2,350 2,875 3,240 660  600  400  1,200 1,980Maharashtra  990  500  500  1,005 2,481 3,580 2,760 1,500 1,860  2,220  500  ‐ 1,320Manipur  ‐  ‐  ‐  ‐ ‐ ‐ ‐ ‐ ‐  ‐  ‐  ‐ ‐Meghalaya  ‐  ‐  ‐  ‐ 84 42 ‐ ‐ 40  ‐  ‐  ‐ ‐Mizoram  ‐  ‐  ‐  ‐ ‐ ‐ ‐ ‐ ‐  ‐  ‐  ‐ ‐Orissa  150  ‐  ‐  1,200 600 950 700 1,200 350  700  1,050  660 2,260Punjab  250  250  ‐  ‐ ‐ ‐ 700 1,360 660  930  ‐  ‐ ‐Rajasthan  220  ‐  1,395  635 270 650 1,570 900 600  ‐  ‐  ‐ ‐Sikkim  510  ‐  ‐  ‐ ‐ ‐ 100 96 200  320  200  ‐ ‐Tamil Nadu  ‐  92  ‐  ‐ 750 1,865 1,295 2,350 2,100  150  660  ‐ 500TRI  ‐  ‐  ‐  21 ‐ 363 ‐ 363 ‐  ‐  ‐  ‐ ‐Uttar Pradesh  ‐  ‐  790  790 2,410 1,250 500 500 1,160  660  660  1,320 ‐Uttarakhand  304  ‐  ‐  200 200 ‐ ‐ 99 166  166  260  260 ‐West Bengal  2,210  300  460  1,000 1,313 99 283 900 1,020  540  ‐  ‐ ‐Total  9,263  3,454  9,585  12,161 20,501 20,613 17,806 20,431 13,981  10,291  16,320  13,210 11,360

Source: PhillipCapital India Research Estimates 

   

Center33%

State 40%

Private27%

FY14

Center33%

State 32%

Private35%

FY20

Page 11: INSTITUTIONAL EQUITY RESEARCH India Utilitiesbackoffice.phillipcapital.in/...Utilities_Sector... · post FY18. Thus, we expect all India demand for coal to rise at 7% CAGR during

  

Page | 11 | PHILLIPCAPITAL INDIA RESEARCH 

UTILITIES SECTOR 

Mapping electricity demand and supply India’s electricity  growth has historically  shown  an  average elasticity of 0.7‐0.8x of GDP growth. We note even during period of FY04‐08 when  India experienced 7‐8% GDP  growth,  demand  growth  as  reported  by  CEA, was  in  range  of  6‐8%,  implying lower elasticity. Demand elasticity 

Source: PhillipCapital India Research Estimates  Base and Peak Deficit(%) 

Source: CEA, PhillipCapital India Research Estimates  We  understand  India’s  lower  demand  elasticity  could  be  attributed  to  weak distribution. Due  to weak  financial health, state discoms’ preferred  to shed demand rather  than  meet  incremental  demand  and  strain  finances.  Thus,  during  FY14  in addition  to  robust  supply  led  by  strong  capacity  addition,  demand was  also weak leading  to  sharp  reduction  in deficit. This has continued  into FY15 as well. Further, lower demand elasticity  is also attributed  to  India’s electricity demand composition that  is different as compared to other countries due to contribution of  industry and services  in  GDP.  Thus  based  on  sector  classification,  services  contribute  57%  and industry at 26% to India’s economy as against 44% for industry and 46% for services to China’s economy.    

0.20 

0.40 

0.60 

0.80 

1.00 

1.20 

1.40 

1.60 

FY02 FY03 FY04 FY05 FY06 FY07 FY08 FY09 FY10 FY11 FY12 FY13 FY14

Demand elasticity

0

5

10

15

20

25

30

FY02 FY03 FY04 FY05 FY06 FY07 FY08 FY09 FY10 FY11 FY12 FY13 FY14 FY15

Base Deficit Peak Deficit

Page 12: INSTITUTIONAL EQUITY RESEARCH India Utilitiesbackoffice.phillipcapital.in/...Utilities_Sector... · post FY18. Thus, we expect all India demand for coal to rise at 7% CAGR during

  

Page | 12 | PHILLIPCAPITAL INDIA RESEARCH 

UTILITIES SECTOR 

Demand Composition – FY13 

Source: PFC  In  order  to  project  future  demand,  we  analyzed  demand  growth  in  key  cities  of Mumbai, Kolkata, Ahmedabad and Surat which could be used as best case reference to project  India’s demand. Our  analysis of demand  in  these  cities  indicates during FY02‐14, demand in Mumbai, Kolkata and Ahmedabad and Surat grew 6‐8%. We have used similar nos. to project future electricity demand growth on a pan India basis.  Demand growth (mn units) 

 Source: SERC, PhillipCapital India Research Estimates  Based  on  historic  demand  and  assumption  of  GDP  of  6%  (old  series)  we  expect demand to grow at 8% during FY15‐17E implying elasticity 1.33 (higher than 12 years average  of  0.7x).  Our  demand  estimate  incorporates  pent  up  demand  due  to improvement  in  discoms  finances  and  rising  electrification. We  note  demand was relatively  subdued  in  FY14  and  FY15  due  to weak  financial  health  of  discoms  and weak industrial demand.  

Domestic28%

Commercial10%

Industry35%

Railways2%

Agriculture25%

5,000 

10,000 

15,000 

20,000 

25,000 

30,000 

FY01 FY02 FY03 FY05 FY06 FY07 FY08 FY09 FY10 FY11 FY12

Kolkatta Ahmedabad + Surat Mumbai

Page 13: INSTITUTIONAL EQUITY RESEARCH India Utilitiesbackoffice.phillipcapital.in/...Utilities_Sector... · post FY18. Thus, we expect all India demand for coal to rise at 7% CAGR during

  

Page | 13 | PHILLIPCAPITAL INDIA RESEARCH 

UTILITIES SECTOR 

Deficits to inch up….... Based on our estimate of 86GW  capacity addition during  FY15‐20E  (83GW  in XIIth plan)  we  expect  supply  at  8.5%  CAGR.  Supply  would  be  driven  by  coal  based generation at 9.3% CAGR. As economic recovery gains  traction, demand would pick up and  this would  lead  to  increase  in deficit during FY16‐17E. We expect utilization would  also  pick  up;  however  PLF’s  would  still  continue  to  remain  sub  ‐  optimal.  Transmission constraints,  limited availability of  indigenous fuel and under utilisation would  continue  to  cap merchant  rates.  Further  unlike  during  FY07‐10, we  expect deficit  to  be  largely  concentrated  in  regions  where  state  government  have  not proactively planned power procurement and/or are  facing  transmission constraints. Thus,  based  on  our  capacity  addition we  expect  higher  deficits  to  prevail  in Uttar Pradesh and Southern region particularly Telangana, Tamil Nadu and Karnataka.  We expect aggregate utilization  to pick up  to historic high of 50‐55%  from  current 48%  in  FY14. We  expect  coal  plant  utilization  to  increase  to  65‐67%  from  current 60%.Thus we expect India to attain equilibrium in electricity by FY20. However we do note that for India to maintain this equilibrium in XIIIth and XIVth plan it is necessary to commence equipment ordering during FY16‐17E.   Projected deficit 

Source: CEA, PhillipCapital India Research Estimates  Base and Peak Deficits (%) 

Source: CEA, PhillipCapital India Research Estimates 

2.0 

4.0 

6.0 

8.0 

10.0 

12.0 

FY07 FY08 FY09 FY10 FY11 FY12 FY13 FY14 FY15 FY16 FY17 FY18 FY19 FY20

Demand Growth (%) Base Deficit(%)

0%

2%

4%

6%

8%

10%

12%

14%

FY10 FY11 FY12 FY13  FY14  FY15E  FY16E  FY17E  FY18E  FY19E  FY20E 

Base Deficit Peak Deficit

We expect utilization to pick gradually led by improvement in fuel supply and demand pick up.  

Deficit to stay elevated during FY15‐17E but reduce post FY18 and reach equilibrium by FY20  

Deficit to inch up during FY16‐17E  

Page 14: INSTITUTIONAL EQUITY RESEARCH India Utilitiesbackoffice.phillipcapital.in/...Utilities_Sector... · post FY18. Thus, we expect all India demand for coal to rise at 7% CAGR during

  

Page | 14 | PHILLIPCAPITAL INDIA RESEARCH 

UTILITIES SECTOR 

Also despite higher deficit we maintain cautious stance on merchant power. We note lower  utilization  of  existing  plants  would  continue  to  put  pressure  on  merchant markets.  Further  we  expect merchant  capacity  would  face  headwinds  on  offtake front due to availability of competitively priced power post auction of captive mines.  Merchant Price 

Source: CERC, PhillipCapital India Research Estimates  Demand – Supply dynamics 

FY10  FY11  FY12 FY13 FY14 FY15E FY16E FY17E  FY18E  FY19E FY20EEnergy Available ‐ Ex Bus (MU)  746,645  788,355  857,928 908,329 962,916 1,036,176 1,117,046 1,214,058  1,320,404  1,442,862 1,549,530Growth (%)  5.6  8.8 5.9 6.0 7.6 7.8 8.7  8.8  9.3 7.4Energy Demand (MU)  830,594  861,591  936,913 995,491 1,002,257 1,082,438 1,169,033 1,262,555  1,363,560  1,472,644 1,549,530Growth (%)  6.9  3.7  8.7 6.3 0.7 8.0 8.0 8.0  8.0  8.0 8.0Energy Deficit (MU)  83,949  73,236  78,985 87,162 39,341 46,261 51,987 48,497  43,156  29,783 ‐Energy Deficit  10.1%  8.5%  8.4% 8.8% 3.9% 4.3% 4.4% 3.8%  3.2%  2.0% 0.0%Peak Demand  119,166  122,287  130,006 135,453 135,918 146,791 158,535 171,218  184,915  199,708 215,685Growth (%)  2.6  6.3 4.2 0.3 8.0 8.0 8.0  8.0  8.0 8.0Peak Avbl  104,249  110,256  116,191 123,294 129,815 141,403 149,735 160,868  177,234  194,126 215,685Growth (%)  5.8  5.4 6.1 5.3 8.9 5.9 7.4  10.2  9.5 11.1Peak Deficit  14,917  12,031  13,815 12,159 6,103 5,388 8,799 10,350  7,680  5,582 ‐Peak Deficit  12.5%  9.8%  10.6% 9.0% 4.5% 3.7% 5.6% 6.0%  4.2%  2.8% 0.0%

Source: CEA, PhillipCapital India Research Estimates 

0

1

2

3

4

5

6

7

8

FY09 FY10 FY11 FY12 FY13 FY14

Price Traders (Rs/kwh) Price ‐Exchange  (Rs/kwh)

Page 15: INSTITUTIONAL EQUITY RESEARCH India Utilitiesbackoffice.phillipcapital.in/...Utilities_Sector... · post FY18. Thus, we expect all India demand for coal to rise at 7% CAGR during

  

Page | 15 | PHILLIPCAPITAL INDIA RESEARCH 

UTILITIES SECTOR 

Fuel: Challenges to persist We expect challenges to persist in fuel supply both on Gas and Coal. India has had an adhoc approach towards capacity addition due to which pace of capacity addition has been sporadic. During FY07‐09 although  India planned for 50GW+ capacity addition, we  note  similar  follow  through  arrangement  was  not  done  on  fuel  front. Consequently,  a  large  part  of  India’s  capacity  was  planned  based  on  “Letter  of Assurances’  (LoA)  from Coal  India; however  these  LoA were not  converted  to  FSA. Thus CIL struggled to meet  increased demand with production growth of 4% during FY07‐14.  Thus,  large  capacity has been  synchronized with  limited  fuel  availability which has stranded capacity to a great extent. Also India’s had  limited success on captive coal. The  problem of  existing  inefficiency was  further  aggravated by  delayed  clearances leading  to stagnant coal production  from CIL. Thus during FY04‐14,  India witnessed 22% CAGR growth in coal imports (coking and non‐coking coal)  Coal Imports 

 Source: CEA, PhillipCapital India Research Estimates  Limited  availability  of  domestic  gas  impacted  gas  based  generation  leading  to suboptimal PLF. ~ 10 GW of gas based capacity remains stranded for want of gas. As against  the  requirement  of  107mmmscmd,  gas  availability  has  dropped  to  32 mmscmd from indigenous sources.  Gas requirement 

 Source: CEA, PhillipCapital India Research Estimates  

22 29 

39  44  51 59 

68  69 

103 

146 158 

20 

40 

60 

80 

100 

120 

140 

160 

180 

FY04  FY05  FY06  FY07  FY08  FY09  FY10  FY11  FY12  FY13 FY14

22%

9.0 

9.4 

9.9 

10.2 

10.2 

10.9 

12.4 

13.4 

13.6 

15.8 

16.6 

16.9 

18.4 

21.7 

45  46  48  49  50  53 61 

66  67 

78  81  81 91 

107 

24  24  25  26 31 

35  35  38  37 

55  59  56 

40 32 

20 

40 

60 

80 

100 

120 

0

5

10

15

20

25

FY01 FY02 FY03 FY04 FY05 FY06 FY07 FY08 FY09 FY10 FY11 FY12 FY13 FY14

Gas‐based Capacity (GW)Gas required (mmscmd)*Gas supplied (mmscmd)

Page 16: INSTITUTIONAL EQUITY RESEARCH India Utilitiesbackoffice.phillipcapital.in/...Utilities_Sector... · post FY18. Thus, we expect all India demand for coal to rise at 7% CAGR during

  

Page | 16 | PHILLIPCAPITAL INDIA RESEARCH 

UTILITIES SECTOR 

Gas ‐ PLF 

 Source: CEA  We expect India will continue to be net importer of coal unless India makes progress to  improve domestic supply. We note during FY07‐14, even as demand for coal was up  6.7%,  supply was  up mere  4.5%  due  to  subdued  captive  production  and weak production from CIL leading to higher imports. With aggregate production of ~50mn per  annum  as  against  potential  1.2bn  tonne,  share  of  captive  coal  in  India’s  coal production is significantly lower at ~10‐15%.  The problem of  shortage  in  indigenous  coal  supply was  further  aggravated due  to logistic  constraints  leading  to  lower  despatches. We  note  lack  of  clearances  has delayed construction of critical rail links of 450km connecting key coal bearing states leading  to  lower  despatch.  Thus  India  had  planned  Tori‐Shivpuri‐Kathotia  in North Karanpura in Jharkand in 2000; however line is yet to see light of day and is expected by  FY18.  Similar  delay  is witnessed  in  Jharsuguda‐Barpalli‐Sardega  railway  line  (53 kms))  and  Bhupdevpur‐Korichapan‐Dharamjaigarh(180  kms)  in  Mand‐Raigarh coalfield, Chhattisgarh.  Although the new government has shown strong  intent  in speeding up construction of  these  lines,  however  benefits  of  these  lines will  accrue  post  FY18‐19.  Together these  lines will  contribute  to  ~100mn  tones  coal.   We  expect  construction  to  gain traction with the election of BJP government in Jharkand leading to better Centre and State co‐ordination.  We expect all India demand for Coal  at 7% CAGR during FY14‐20E to 1.1 bn tones by FY 20 driven by demand by Power utilities  and supply at 7.4% CAGR, implying  6% CAGR in import to 226 mn tone by FY20. We note supply from captive mines could surprise on upside with faster clearances.  For Power Utilities, we expect demand to grow 8% CAGR during FY14‐20E to 780 mn tone and supply to grow to 681 (8% CAGR) during same period leading to 7% CAGR growth in import.      

10 

20 

30 

40 

50 

60 

70 

80 

FY08 FY09 FY10 FY11 FY12 FY13 FY14

Gas based PLF have been down significantly due to lower indigineous gas supply.  

Logistic constraints has also impacted supply  

Page 17: INSTITUTIONAL EQUITY RESEARCH India Utilitiesbackoffice.phillipcapital.in/...Utilities_Sector... · post FY18. Thus, we expect all India demand for coal to rise at 7% CAGR during

  

Page | 17 | PHILLIPCAPITAL INDIA RESEARCH 

UTILITIES SECTOR 

All India Coal Demand Supply Dynamics FY12  FY13  FY14E FY15E FY16E FY17E FY18E  FY19E  FY20E CAGR FY14‐20E

Coal consumption / Demand Coking coal                 47                 52                 52                 55                 58                 62               65              69              74                        6.0 Power (Utilities)               412               457               504               538               571               604             652            722            780                        7.5 Power (Non‐Utilities)                 47                 55                 47                 50                 53                 56               59              63              67                        6.0 Cement                 23                 24                 24                 26                 28                 30               32              34              37                        7.0 Sponge Iron / CDI                 22                 25                 22                 24                 25                 27               28              30              32                        6.0 BRK & Others/Fert/Export/SSF/NLW                 88               107                 80                 85                 90                 95             101            107            113                        6.0 Non‐Coking coal               591               668               678               723               766               812             873            956         1,028                        7.2 Raw coal consumption / demand               638               721               730               778               825               873             938         1,026         1,102                        7.1 

Coal Supply CIL (Offtake)               433                466               471               491               531               568             602            638            677                        6.2 SCCL                 51                 53                 48                 50                 52                 54               56              58              61                        4.0 Others                 51                 56                 52                 59                 57                 78               97            118            139                      17.8 TOTAL INDIGENOUS COAL SUPPLY               535               575               571               600               640               700             756            814            876                        7.4 

Imports               103               146               158               178               184               173             183            211            226                        6.1 

Source: CEA, PhillipCapital India Research Estimates    Coal demand for Power Utilities 

FY12  FY13 FY14 FY15E FY16E FY17E FY18E  FY19E  FY20E CAGR FY14‐20EConsumption / Demand from Power utilities  412  457 488 538 570 604 652  722  780 8.1Growth (%)  6.0  10.8 6.8 10.3 5.9 6.0 8.0  10.7  8.0

CIL ‐ Offtake  433  466 471 491 531 568 602  638  677 6.2Growth (%)  2.0  7.7 1.1 4.1 8.2 6.9 6.0  6.0  6.0CIL ‐ Offtake to Power Utilities  312  347 355 401 417 433 459  511  541 7.3Growth (%)  2.5  11.2 2.2 13.1 4.0 3.8 6.0  11.2  6.0Supply to PU as prop. Of Total offtake of coal  72  74 75 82 79 76 76  80  80SCCL ‐ Offtake to Power Utilities  37  35 37 38 39 40 41  43  44 3.0Captive Mines ‐ Offtake to Power Utilities  18  25 30 37 35 42 65  81  96 21.3Total Indigenious Coal ‐ Power Utilities  367  407 421 476 491 516 565  634  681 8.3

Coal to be imported(GCV adjusted volumes)  36  40 53 49 63 71 70  70  79

Source: CEA, PhillipCapital India Research Estimates     

Page 18: INSTITUTIONAL EQUITY RESEARCH India Utilitiesbackoffice.phillipcapital.in/...Utilities_Sector... · post FY18. Thus, we expect all India demand for coal to rise at 7% CAGR during

  

Page | 18 | PHILLIPCAPITAL INDIA RESEARCH 

UTILITIES SECTOR 

Addressing fuel supply challenges Post 2012, government initiated several measures such as mandating CIL to sign FSA and attempted  for  coal/gas price pooling on  fuel  front. We note however most of these measures would address fuel supply issue in long run, but in 13th plan India too continue to be net importer of coal. We highlight below few such measures:  Coal Price pooling: remains a non‐starter In  2013  to  address  shortage  of  indigenous  fuel  supply  government  decided  to undertake  coal  price  pooling.  The mechanism  included  blending  of  domestic  and imported coal by CIL and supplying coal at pooled price. The excess cost paid for the imported coal would be borne by the consumers of domestic coal.   Although  it  didn’t  take  off  in  2013,  however  it  has  been  proposed  and  shelved multiple  times  in  recent years. Key difficulty was opposition  from discoms as  tariffs would  increase.  Also  we  believe  administering  coal  price  mechanism  would  be significant  challenge  due  to  its  complexity  of mechanism.  The  coal  price  pooling mechanism will lead to increase in cost of coal supplied by CIL to all the power plants and will lower the cost of blended coal for new plants with LoA/FSA and consequently improve the PLF of new plants.   Thus mechanism  implicitly  involved subsidizing new plants  by  old  plants. We  expect  noises  in  favor  of  implementation  of  coal  price pooling  to  reduce  going  forward  if  CIL  improves  dispatches  and/or  government successfully undertake coal block auction.   E‐auction of captive coal mines: Fuel security over economics? In Sept 2014, the SC cancelled 204 captive coal blocks allotted on discretionary basis since  1993.  In December  the  government  issued  regulation  to  allot  coal  blocks  in transparent manner.  In  first  stage  government  intends  to  auction,  101  coal blocks with capacity of 340mntonne of peak production capacity during next  few months. We highlight the entire auction process has been drafted with adequate checks and balances  to  ensure  that  captive  coal  production  that  has  been  relatively  stagnant gains  traction.  We  note  penalty  for  deviation  from  mining  targets  and  end  use restriction ensures only serious players will participate  in auction. Further, we note early stage auction will most likely lead to re allotment of operational blocks and will unlock  stuck projects. However new  capex  cycle will  commence once pending 103 blocks are auctioned. We expect 22% CAGR during FY14‐20E.  We  note  operational  blocks  auctioned  in  initial  stage  have  witnessed  aggressive biddings  with  participants  quoting  negative  bids  to  win  coal  blocks.  This  implies bidders  are willing  to  forego mining  costs  and  instead  pay  a  premium  in  order  to ensure fuel security.  In case of regulated plants; claiming pass through  for negative bids become  further difficult unlike  in  case of plants with open  capacity wherein utility  can  incorporate mining cost in its fixed cost while signing PPA. We note the bidding strategy indicates, participants have prioritised  fuel  security over economics,  implying RoE’s  for  these projects will continue to be on lower side.     

Page 19: INSTITUTIONAL EQUITY RESEARCH India Utilitiesbackoffice.phillipcapital.in/...Utilities_Sector... · post FY18. Thus, we expect all India demand for coal to rise at 7% CAGR during

  

Page | 19 | PHILLIPCAPITAL INDIA RESEARCH 

UTILITIES SECTOR 

We highlight below sensitivity of RoE for to various parameters.   Impact of fuel cost under‐ recovery on RoE Ceteris paribus; every Rs100/ton under recovery due to negative bid impacts RoE by 2%, implying utility has to offset this with efficiency.  ROE/Under Recovery(Rs/ton)              400              300              200              100                 0Impact  8.08%  9.93%  11.79% 13.64% 15.50%   Impact of savings in SHR Ceteris paribus; every 50kcal/kwh improvement in SHR improves RoE by 0.55%.   ROE/SHR(kcal)  300              250              200              150              100                50  0

Impact  18.79%  18.24% 17.69%  17.14% 16.60% 16.05% 15.50%

  Impact of savings in O&M Ceteris paribus; every 3% savings in O&M cost improves RoE by 0.21%  ROE/O&M  15%  12%  9% 6% 3% 0%Impact  15.5%  16.5%  16.3%  16.1% 15.9% 15.7% 15.5%

  Recent coal bids Mine  State  Capacity Developer  Bids (Rs/tone)Gare‐Palma‐IV/2  Chhattisgarh ‐MandRaigarh  II  6.25 Jindal Power             (108)Tokisud North  Jharkhand ‐South Karanpura  II  2.32 Essar Power           (1,110)Amelia (North)   Madhya Pradesh‐Singrauli  II  2.8 JPVL             (715)Talabira‐I  Orissa ‐IB Valley  II  3 GMR Chattisgarh             (478)Sarisatolli  West Bengal ‐ Raniganj  II  3.5 CESC             (470)Trans Damodar  West Bengal ‐Barjora  II  1 Durgapur Projects             (940)Mandakini  Orissa ‐Talcher   III  7.5 Mandakini exploration and mining Company             (650)Utkal‐C  Orissa ‐Talcher   III  3.37 Monnet Power Company             (770)Jitpur  Jharkhand ‐ Rajmahal   III  2.5 Adani Power             (302)Ganeshpur  Jharkhand ‐North Karanpura   III  4 GMR Energy Chhatisgarh             (704)Tara   Chhattisgarh‐HasoAnand   III  6 Jindal Power             (126)

Source: Coal Ministry    

Page 20: INSTITUTIONAL EQUITY RESEARCH India Utilitiesbackoffice.phillipcapital.in/...Utilities_Sector... · post FY18. Thus, we expect all India demand for coal to rise at 7% CAGR during

  

Page | 20 | PHILLIPCAPITAL INDIA RESEARCH 

UTILITIES SECTOR 

Reviving stranded gas assets In order to revive stranded gas based assets, CCEA has come out with mechanism to import  gas  and  supply  to  stranded  assets  subject  to  a  price  cap.    The  current mechanism was devised as earlier mechanism of “Gas Price Pooling” did not take off.   The  mechanism  envisages  importing  regasified  Liquified  Natural  Gas  (RLNG)  for supply to these plants so that they can generate power. Imported gas will be supplied to both stranded assets as well plant with domestic gas allocation and commensurate to  30%  PLF.    In  order  to  secure  fuel  supply,  generation  companies will  require  to participate  in  reverse  bidding  with  net  purchase  price  for  discoms  capped  at  Rs 5.5/kwh  for  stranded  assets  and  Rs  4.19/kwh  for  plants  running  on  domestic  fuel. Developers will have to quote per unit price support and incremental generation that they would undertake. Price support will be provided through PSDF.   For FY16, the ceiling price  for stranded plants will be Rs 0.94/kwh and Rs 1.26/kwh for plants receiving domestic gas and for FY17 at Rs 0.95/kwh and Rs 1.28/kwh. The bidders will have to quote lower support from the ceiling price. The government has targeted  PLF  of  25‐30%  for  plants  and  PSDF  support  has  been  capped  at  Rs 35bn/40bn  for  FY16/FY17  respectively.  Further  the  mechanism  also  envisages reduction  in  transportation  tariff, marketing margin  and  re‐gasification  charges  on the incremental RLNG of gas transporters and re‐gassification terminal operators.  An  empowered  pool  management  committee  (EPMC)  will  oversee  the  auction process and release the subsidy support to the discoms buying power from successful bidders. The discoms, in turn, will pay the gross value of purchased power (including the amount received from PSDF). The lead banker to the developer will control a trust and  retention  account  (TRA) which will  oversee  payment  to  the  firm.  Under  this mechanism developers will be allowed to recover only variable cost, O&M and debt servicing cost after capping fixed cost.  We note off the 24 GW gas based installed capacity, 14 GW is stranded due to lack of gas and balance  capacity  is also operating at  suboptimal PLF. These 14 GW  that  is facing  under  recovery  will  require  20mmscmd  gas  at  30%  PLF.  Since mechanism involves reverse auction, we note developers will require to sacrifice RoE to compete for gas. This  implies except  lenders, equity holders  in power plant are not  likely  to benefit significantly from these measures.    KG‐D6 production (mmscmd)  Gas‐ PLF 

 Source: CEA PhillipCapital India Research Estimates  We note even under reverse bidding the least developer will recover is variable cost and  interest cost. We note at  landed price of USD 10/mmbtu  fuel cost stands at Rs 4.5/kwh. Further at Rs 50mn/MW cost of capacity, for gas based capacity running at 

5

47 46

60 59 5855

51 49 4651

34 3228

2319

15 15 14 14 13 13 12

Q1FY10

Q2FY10

Q3FY10

Q4FY10

Q1FY11

Q2FY11

Q3FY11

Q4FY11

Q1FY12

Q2FY12

Q3FY12

Q4FY12

Q1FY13

Q2FY13

Q3FY13

Q4FY13

Q1FY14

Q2FY14

Q3FY14

Q4FY14

Q1FY15

Q2FY15

Q3FY15

58  58 

67  66 60 

40 

25 

10 

20 

30 

40 

50 

60 

70 

80 

FY08 FY09 FY10 FY11 FY12 FY13 FY14

Page 21: INSTITUTIONAL EQUITY RESEARCH India Utilitiesbackoffice.phillipcapital.in/...Utilities_Sector... · post FY18. Thus, we expect all India demand for coal to rise at 7% CAGR during

  

Page | 21 | PHILLIPCAPITAL INDIA RESEARCH 

UTILITIES SECTOR 

30% PLF, fixed cost (interest and O&M) would be Rs 1.7/kwh, implying cost of power of  Rs  6.2/kwh.  Thus  we  note  at  Rs  6.2/kwh  based  power  continues  to  be uneconomical proposition even compared to 100% imported coal and weak discoms’ financials will make absorption of such expensive power difficult.   The current policy would most likely favour plants with lower fixed cost and will not benefits  stranded  assets with  higher  capital  cost. New  plants will  require  support from  lenders  too  to ensure  selling price  remains  viable  to discoms.  Southern  India could  see  marginal  demand  for  expensive  gas  based  power  due  to  transmission constraints and higher deficit. However unless government introduce “peaking power policy”  gas  based  capacity would  continue  to  operate  at  suboptimal.  Further  gas plants would continue to face headwinds from underutilized coal based capacity.  Variable cost for running a gas based power plant 

Natural Gas  IDR Coal e‐auction Linkage Indonesia Coal

Power Capacity  1000 MW  1000 1000 1000 MW PLF  30% %  90% 90% 90% % Gross Gen  2,628 mn kwh  7,884 7,884 7,884 mn KWH AUX  3.0% %  8.0% 8.0% 8.0% % Net Gen  2,549 mn KWH  7,253 7,253 7,253 mn KWH Calorific Value  9,000  kcal / scm of gas  4,800 3,600 3,600 Kcal / Kg SHR ‐ GCV  1,760  kcal / kwh  2,400 2,250 2,250 kcal / kwh Fuel Reqd  1.4 mmscmd  3.94 4.93 4.93 mn MT INR / USD  62  x  62 62 62 x Fuel Cost                 10.00 USD / mmbtu  60 42 24 USD / Tonne Fuel Cost                 2,460  Rs / mn kcal  775 722 417 Rs / mn kcal Fuel Cost                    620  Rs / mmbtu  3,720 2,600 1,500 Rs/ Tonne Fuel Cost  11,380  Rs mn  14,664 12,812 7,391 Rs mn Energy Charge                     4.5  Rs / kwh  2.02 1.77 1.02 Rs / kwh 

Source: PhillipCapital India Research Estimates   Fixed cost at different level of utilization Capacity (MW)  1,000  1,000 1,000Cost /MW  50  50 50Rs mn  50,000  50,000 50,000Equity  15,000  15,000 15,000Debt  35,000  35,000 35,000PLF  30%  50% 70%MU  2,628  4,380 4,380  Fixed Cost  Rs/kwh  Rs/kwh  Rs/kwh RoE  0.9  0.5 0.4Interest  1.3  0.8 0.6Depreciation  0.7  0.4 0.3O&M  0.4  0.3 0.2Total  3.3  2.0 1.4

Source: PhillipCapital India Research Estimates    

   

Page 22: INSTITUTIONAL EQUITY RESEARCH India Utilitiesbackoffice.phillipcapital.in/...Utilities_Sector... · post FY18. Thus, we expect all India demand for coal to rise at 7% CAGR during

  

Page | 22 | PHILLIPCAPITAL INDIA RESEARCH 

UTILITIES SECTOR 

Distribution ‐ Weakest link in the value chain Distribution  remains  the  weakest  link  in  Indian  Power  Sector  value  chain.  Higher interference of state government coupled with unremunerative tariffs has resulted in losses to the tune of Rs1060bn (FY13) to state discoms. Chronic under investment in distribution due to weak financial health of discoms ensures~25% of power  input  in system remains unbilled. Thus in FY13, only 4 discoms of 30 discoms reported profit on ex subsidy basis.  Vicious circle of weak distribution                      Source: PhillipCapital   AT&C loss 

 Source: PFC    

0

5

10

15

20

25

30

35

40

FY04 FY05 FY06 FY07 FY08 FY09 FY10 FY11 FY12 FY13

Under recovery of tariffs 

Higher cash losses 

Under investment in T&D infrastructure 

Higher T&D losses 

Higher AT&C losses due to under investment in distribution infrastructure…..  

Page 23: INSTITUTIONAL EQUITY RESEARCH India Utilitiesbackoffice.phillipcapital.in/...Utilities_Sector... · post FY18. Thus, we expect all India demand for coal to rise at 7% CAGR during

  

Page | 23 | PHILLIPCAPITAL INDIA RESEARCH 

UTILITIES SECTOR 

Average Cost of Supply and Realisation 

  Discoms Losses (Rsbn)

 Source: PFC  We  note  six  states  viz.  Rajasthan,  UP,  TN  ,  AP  ,  Haryana,  Jharkand  and  Punjab  contribute    80%  of  losses.  Despite  undergoing  restructuring  exercise  in  FY02  and unbundling of state utilities, lack of political willingness ensured distribution sector in remains  in abysmal  state.Further high debt  (Rs 57000bn as on FY13)  largely  led by short term debt to meet opertional cost continue to  hit discoms.   We note continuing with stance of earliergovernment, current government continue to accord high priority to distribution sector.  Modernizing transmission and distribution (T&D) infrastructure will help in overcoming the electricity crisis, The meeting reinforced my belief that 

power crisiscan be solved to a large extent by modernizing T&D infrastructure. 

‐Power Minister Piyush Goyal addressing conference in Rajahasthan  We are planning investments of Rs 3 lakh crore in the T&D sector and have already started the Deen Dayal Grameen Jyoti Yojana and Integrated Power 

Development Scheme, with all this I think we will be able to reach the length and breadth of the country and enhance the T&D network and make 

sure everybody gets adequate power Power Minister Piyush Goyal in Press release to PTI 

0.00

1.00

2.00

3.00

4.00

5.00

6.00

FY19

81FY19

85FY19

90FY19

91FY19

92FY19

93FY19

94FY19

95FY19

96FY19

97FY19

98FY19

99FY20

00FY20

01FY20

02FY20

03FY20

04FY20

05FY20

06FY20

07FY20

08FY20

09FY20

10FY20

11FY20

12FY20

13

Rs /kwh

Average Cost of Supply (Rs/kwh) Average Realisation (Rs /kwh)

-293-212 -197 -240 -209

-271 -319

-537-645

-752

-1024 -1060-1200

-1000

-800

-600

-400

-200

0

FY02 FY03 FY04 FY05 FY06 FY07 FY08 FY09 FY10 FY11 FY12 FY13

Limited tariff hike resulting in realisation lower than cost of supply  

Leading to higher losses  

Page 24: INSTITUTIONAL EQUITY RESEARCH India Utilitiesbackoffice.phillipcapital.in/...Utilities_Sector... · post FY18. Thus, we expect all India demand for coal to rise at 7% CAGR during

  

Page | 24 | PHILLIPCAPITAL INDIA RESEARCH 

UTILITIES SECTOR 

Distribution reforms…lack execution at state level: We note  that with power being on concurrent  list, despite  top down  reforms  from Centre to State at the end of day execution remains in hand of state. States that were willing  to  bite  bullet  and  take  hard measures  have  succeeded  in  reforming  power sector. Further with success of Mr. Narendra Modi from Chief Minister of Gujarat to Prime Minister or successive election of Mr. Shivraj Singh Chouhan as CM of MP, lot of states’ CM have gradually acknowledged the political leverage that can be gained by addressing  the basic necessity of electricity. Consequently we expect  significant improvement in political willingness to institute reforms in states.   We highlight below few measures taken over past few years to address distribution segment and their impact: • Tariff hike: We note tariff hikes have become more pronounced over past few 

years as state discoms pursue the path to reduce their losses. State with higher losses has  taken  tariff hike  to  tune of 15‐20%  since  FY11. Due  to elections  in several states in FY15 along with the general elections, tariff hikes were taken in very few states.  

Tariff hikes Name of state  FY12  FY13  FY14 FY15 FY16Andhra Pradesh                          4                  20                  23  5Arunachal Pradesh                        19                    5                    6                   ‐ NAAssam                  ‐                    2                   ‐ NABihar     ‐                  12                    7                   ‐ 3Chandigarh     ‐                  10                   ‐                  ‐ ‐Chhattisgarh                         14                  18                   ‐                 21  12Delhi     ‐                  21                    5                    8  NAGujarat     1.5‐3.5                    2                    6                   ‐ 2Haryana                         17                  18                  13                   ‐ NAHimachal                         10                  13                  13                   ‐ ‐J&K                         12                    6                    9                   ‐ NAJharkhand                         11                    9     ‐ NAKarnataka                          6                    3                   ‐                 10  5Kerala                        ‐                  30                    8                  16  NAMadhya Pradesh                         11                    7                    1                   ‐ 10Maharashtra                          3                  17  NAManipur                         15                    8    ‐                   8  5Mizoram                         11                  10    ‐ 2Orissa                         20                  12                    2                   ‐ 5Punjab                          8                  12                    9                    3  NARajasthan                   19                  10                   ‐ NATamil Nadu                         11                  37                   ‐                 15  NATripura                    3                  21  NAUP                         14                    9                    8                  20  NAUttarakhand                         3                    7                    5                   ‐ 7West Bengal                         11                  ‐                   ‐ ‐ NA

Source: SERC  However we note tariff hikes would work in short term and going forward to ensure sustainable  turnaround  SEB’s  need  to  address  key  issue  of  higher  T&D  losses  and limited recovery of dues. We note current tariff hikes have largely been concentrated on  industrial  and  commercial  segments  that  have  continue  to  cross  subsidise residential  segment.  Thus  India’s  industrial  segments  tariff  are  higher  relative  to purchasing power and compared to other countries.  • Financial Restructuring Plan: With an objective to  improve  financial conditions 

of  discoms  and  ensure  sustainable  turnaround,  government  came  out  with Financial  Restructuring  Plan.  The  Restructuring  of  SEB  is  the  second  such exercise undertaken by  government  after 2001.  The Plan  entails  restructuring Short  Term  Liabilities  of  discoms  in  assistance  with  State  and  Central 

Page 25: INSTITUTIONAL EQUITY RESEARCH India Utilitiesbackoffice.phillipcapital.in/...Utilities_Sector... · post FY18. Thus, we expect all India demand for coal to rise at 7% CAGR during

  

Page | 25 | PHILLIPCAPITAL INDIA RESEARCH 

UTILITIES SECTOR 

Government and  lenders. As per  the  scheme, 50% of Short Term  Liabilities of State Discoms  outstanding  as  on March  2012, would  be  taken  over  by  State Governments.  This  involves  converting  STL  into  bonds  backed  by  State Government  guarantee  and  to  be  issued  to  lenders.  The  State  Government would gradually take over liability (50%) over next 2‐5 years in phased manner. The bond issuance would take place such that States do not breach FRBM limit. The  balance  50%  of  STL  would  be  rescheduled  by  lenders  and  serviced  by DISCOMS  with  moratorium  of  3  years.  The  restructuring  exercise  would  be accompanied  suitable  actions  from  discoms  end  to  improve  their  operational performance.  The  FRP  scheme  would  be  aided  by  Transitional  Finance Mechanism  (TFM)  to  be  set  up  by MoP.  The  transitional  finance mechanism would provide grants  to State government  conditional  to achieving prescribed reduction in AT&C losses and reducing gap between ARR and ACS.   

We note eight states viz. Tamil Nadu, Uttar Pradesh, Rajasthan, Haryana, Jharkhand, Bihar, Andhra Pradesh and Telangana availed FRP; however implementation has met with  limited  success.  Most  of  these  states  failed  to  meet  requisite  condition  of reduction in T&D losses, consistent tariff hike or reducing power purchase cost. Thus FRP simply infused cash in discoms without concomitant measures from discoms end. Further even as power ministry  introduced “Model State Electricity Distribution Bill” that  entailed  prudent  measures  from  state  discoms  to  improve  financial performance, discoms failed to implement bill at state level. Also we note apart from interest cost Power purchase cost and employee cost significant portion of discoms’ expenditure  and unless  these  costs  are not  addressed,  turnaround of discoms will remain pipe dream.  Break up of Expenditure of discoms 

 Source: PFC  • Feeder  separation  scheme:  The  government  launched  the  “Deen  Dayal 

Upadhyaya Gram  Jyoti Yojna”  (DDUGY) with an aim  to strengthen distribution. We  note  agriculture  remains  the  biggest  bane  for  discoms  and  political compulsion  ensured  tariffs  for  this  segment  significantly  lower  than  cost  of supply.  Consequently  a  significant  chunk  of  power  meant  for  agriculture  is transferred for household purpose leading to higher losses. With an objective to put lid to this DDUGY  was launched  so as to ensure  a. Separate  agriculture  and  non‐agriculture  feeders  and  ensuring  reliable 

supply to farmers. b. Strengthening  and  augmentation  of  sub  transmission  and  distribution 

infrastructure in rural areas, including metering of distribution c. Also  existing  rural  electrification  (RGVVY)  scheme would  be  subsumed  in 

this scheme.  

Power Purchase Cost 63%Fuel Cost

12%

Employee cost8%

Interest cost8%

O&M1%

Others8%

Page 26: INSTITUTIONAL EQUITY RESEARCH India Utilitiesbackoffice.phillipcapital.in/...Utilities_Sector... · post FY18. Thus, we expect all India demand for coal to rise at 7% CAGR during

  

Page | 26 | PHILLIPCAPITAL INDIA RESEARCH 

UTILITIES SECTOR 

We note RGVVY had cost of Rs392bn including budgetary support of Rs 354bn. Apart from  this DDUGY had overall outlay of Rs 430bn  including budgetary  support of Rs 334bn.  Further  the overall  scheme of DDUGY has been designed  in  such  a way  to ensure financial burden on states remain minimal. Further scheme involves milestone based payment of grants so as ensure effective implementation.  Funding Mechanism Agency  Grant  % support for non special states  % support for non special statesCentre  60  85Discom contribution  Own Fund  10  5Lenders(FI/Banks)  Loan  30  10Additional grants on achievement of prescribed milestones  Grant  50% of total loan =15%  50% of total loan =5%Maximum grant by GoI including additional grants  Grant  75%  75%

Source: Power Ministry  We note  implementation of  feeder  separation  scheme  through  Jyoti gram Yojna  in Gujarat has played key  role  in  turnaround of discoms  in Gujarat. Feeder separation ensured  that  farmers get quality power at  fixed  time and  leakages are  curtailed.  It ensured accurate measurement of the power used for agricultural purposes as well, thus ensuring proper targeting of subsidies.  Gujarat SEB 

 Source: PFC  Introduction of revised Standard Bidding Document: Earlier SBD for projects introduced during 10th plan ushered the way for competitively bid power projects. However the document had short comings due to which fuel risks was  largely  borne  by  generation  utilities.  ~18‐20  GW  capacity  suffered  due  to aggressive bidding resulting in lower than expected return. In FY13, taking cognizance of shortcoming and risk aversion from discoms to call for bids government introduced Case II bids. However despite introduction of new bids discoms continue to focus on short  term  power  rather  than  procure  long  term  power.  The  revised  SBD  altered earlier provision and allowed  for  fuel cost pass through and  involved bidding based on  capacity  charge.    Further  unlike  previous  SBD  that  selected  bids  based  on levellised  tariff,  new  SBD  require developers  to  indicate  first  year  tariffs. However despite  government  inviting  bids  for  TN  and Orissa  UMPP  based  on  revised  SBD, interest of private players was significantly low due to DBOT provision that called for transfer of project back to state as against earlier provision that allowed developer to maintain ownership; thus inviting criticism from lenders.     

8 7

1 1

3

5

65

0

1

2

3

4

5

6

7

8

9

FY06 FY07 FY08 FY09 FY10 FY11 FY12 FY13

Gujarat Losses subsidy recd basis (Rs bn)

15

16

17

18

19

20

21

22

23

24

FY07 FY08 FY09 FY10 FY11 FY12 FY13

AT&C loss (Gujarat )

Page 27: INSTITUTIONAL EQUITY RESEARCH India Utilitiesbackoffice.phillipcapital.in/...Utilities_Sector... · post FY18. Thus, we expect all India demand for coal to rise at 7% CAGR during

  

Page | 27 | PHILLIPCAPITAL INDIA RESEARCH 

UTILITIES SECTOR 

Transmission‐ Bright Spot Despite  the  pain  that  sector  went  through,  transmission  segment  of  value  chain continue to remain relatively buoyant  led by strong capex from PGCIL. We continue to  remain  optimistic  on  this  segment  as  strong  capacity  addition will  also  require necessary evacuation system. Thus, we expect transmission capex to remain robust in 13th plan  too. We note going  forward PGCIL’s capex would be geared  towards high end equipment.   Transmission Capex Capex details  ________10thplan_______ _______11th plan_______ _______12th plan_______  _______13th plan_______Rsbn  Total PGCIL  Share Total PGCIL Share Total PGCIL  Share  Total  PGCIL ShareInter State  200 190  95% 564 553 98% 1,250 1,100  80%  1,350  675 50%Intra State  255 664 0% 550 112  9%  950  238 25%Green Energy Corridor Intra state  200  20 10%Interstate  220  22 10%Total  455 190  42% 1,228 553 25% 1,800 1,212  23%  2,720  955 35%

Source: Power Ministry  We note similar to generation, government introduced competitive based bidding in transmission  projects.  We  note  in  initial  bids  competition  had  been  significantly intense.  Recent  bids  however  indicate  lower  competitive  intensity.  Also  some projects  have  been  awarded  to  PGCIL  on  nomination  basis  to  ensure  timely completion of project  Transmission bids 

Developer  Award Date No. of 

bidders Date of LoILevellised

Revenue (L1)Sterlite Technologies   Jan‐10   8 Jul‐10               1,188 Sterlite Transmission Projects   Jan‐11   33 Jan‐11               1,421 Sterlite Transmission Projects   Jan‐11   22 Jan‐11               1,995 PGCIL   Mar‐12   22 Mar‐12                  987 Techno Electric and Engineering  7 Sep‐13                  274 Sterlite Grid   Sep‐13   10 Sep‐13                  365 Sterlite Grid   Sep‐13   7 Sep‐13                  589 EsselInfraprojects Ltd  10 Oct‐13               1,174 PGCIL  Dec‐09                     1,440 PGCIL  Dec‐09                     2,580 Patel Engg, Simplex Infra & BS Transcomm  Dec‐10   35 Dec‐10                  293 PGCIL   Mar‐12                 1,197 PGCIL   Jul‐13   14 Jul‐13               2,311 L&T IDPL   Jul‐13   11 Jul‐13               1,796 Sterlite Grid   May‐14  6 Feb‐14               4,377 PGCIL  7 Feb‐14                  594 EsselInfraprojects Ltd  7 Feb‐14                  887 

Source: REC, PFC  

Page 28: INSTITUTIONAL EQUITY RESEARCH India Utilitiesbackoffice.phillipcapital.in/...Utilities_Sector... · post FY18. Thus, we expect all India demand for coal to rise at 7% CAGR during

INSTITUTIONAL EQUITY RESEARCH  

Page | 28 | PHILLIPCAPITAL INDIA RESEARCH 

Coal India (COAL IN) Play for volume recovery  INDIA | POWER | Initiating 

 

  

28 April 2015 

Investment Rationale We initiate coverage on COAL INDIA with a BUY rating and a target price of Rs475. CIL enjoys competitive advantage of captive mines with one of the lowest strip ratios. Also CIL is likely to be the direct beneficiary of the Indian government’s policies to addresses fuel constraints and  undertake  measures  to  remove  bottlenecks  of  rake  availability  and  environmental clearance.   Production  growth  to  revive: We  expect  CIL  to  ramp  up  production  as  the  government provides  speedier environment  clearances and higher  rake availability by  Indian Railways. Accordingly CIL  is  likely  to  report 6% CAGR  in production during FY15‐17E higher  than 2% growth reported during FY11‐14E. Our confidence stems from the fact that during FY06‐10 CIL had reported CAGR production of 6% driven by faster clearances, post which production declined  as  norms  for  clearance  became  stringent.  Additional  measures  taken  by government such as PMG for coal production, expediting critical rail links and increase in CIL capex on equipment will support production growth.   Incentives earnings to dip but unlikely to miss commitment: CIL had earned Rs 13bn and Rs 8bn  incentives  during  FY13  and  FY14  respectively  as  it  supplied more  than  90%  ACQ  to plants commissioned before 2009. Our analysis of  India’s capacity addition and those with FSA  commitment with CIL  indicates due  to delay  in  commissioning, CIL would be  able  to meet  its  FSA  commitment  albeit by  reducing  supply  to plants  commissioned  till 2009.We note in absence of critical logistic support despatches might suffer in 13th plan. We believe in case plants within 78GW  list do not commence on time, CIL will divert supply to pre 2009 FSA and earn incentive.  E‐auction sale to drive realization: The decision by SC that led to de‐allocation of coal blocks will lead to increase in demand under e‐auction. The government had in early 2015 reduced supply under e‐auction to increase supply to power plants. We note this restriction has been removed and expect  supply  to  increase under e‐auction. We expect  realization  to  remain robust as incremental demand from erstwhile captive mine owners is diverted to e‐auction.     Earnings and Valuations: We like CIL as it is expected to achieve 13% CAGR PAT during FY15‐17E led by 7% production growth. Although CIL’s pricing remains at discount to international prices, however we believe CIL would be able to maintain steady margins as significant sale being  undertaken  at  notified  price  and  as  e‐auction  sales  witness  gradual  increase  in demand. We note CIL remains proxy play on railway capex that could lead to improvement in despatches. At CMP of Rs376, CIL trades at 6xFY17 EV/EBITDA adjusted for OBR. We value CIL at 7x times EV/EBITDA to arrive at target price of Rs475 and initiate coverage with BUY rating on the stock.  Key  risks  to  our  BUY  call:  Key  risks  to  our  BUY  call  are:  a)  Lower  production  growth  b) government  mandating  CIL  to  sign  FSA’s  more  than  it  can  commit  (less  probability)  c) inability  to  take  price  hike  d)  Correction  in  international  coal  prices  impacting  e‐auction realization d) opening up of coal sector for commercial mining. 

BUY  CMP RS 376 TARGET RS 475 (+24%)  COMPANY DATA O/S SHARES (MN) :  6316MARKET CAP (RSBN) :  2376MARKET CAP (USDBN) :  37.352 ‐ WK HI/LO (RS) :  424 / 275LIQUIDITY 3M (USDMN) :  35.8PAR VALUE (RS) :  10 SHARE HOLDING PATTERN, % PROMOTERS :  79.7FII / NRI :  8.3FI / MF :  9.1NON PROMOTER CORP. HOLDINGS :  1.1PUBLIC & OTHERS :  1.8 PRICE PERFORMANCE, % 

  1MTH 3MTH 1YRABS  1.6 ‐4.5 24.6REL TO BSE  4.1 1.7 4.5 PRICE VS. SENSEX 

 Source: Phillip Capital India Research  KEY FINANCIALS Rs mn  FY15E FY16E FY17ENet Sales  729,642 835,306 943,069EBIDTA  164,498 216,024 254,773Net Profit  149,971 184,415 210,949EPS, Rs  23.7 29.2 33.4PER, x  15.8 12.9 11.3EV/EBIDTA, x  11.2 8.2 6.6P/BV, x  5.7 4.8 4.1ROE, %   36.0 37.4 36.4Debt/Equity (%)  0.4 0.3 0.3

Source: PhillipCapital India Research Est.  AnkurSharma(+ 9122 6667 9759) [email protected]  HrishikeshBhagat(+ 9122 6667 9986) [email protected] 

 

60

80

100

120

140

160

Jan‐11 Mar‐12 May‐13 Jul‐14Coal India BSE Sensex

Page 29: INSTITUTIONAL EQUITY RESEARCH India Utilitiesbackoffice.phillipcapital.in/...Utilities_Sector... · post FY18. Thus, we expect all India demand for coal to rise at 7% CAGR during

  

Page | 29 | PHILLIPCAPITAL INDIA RESEARCH 

COAL INDIA INITIATING COVERAGE 

Policy action to aid production growth We  expect  CIL’s  subdued  production  growth  to  be  a  thing  of  past  and  expect production  trajectory  to  improve. We note post  formation of new government,  the emphasis has shifted  to  improvement  in coal production and  increasing availability. Accordingly the government has taken initiatives to aid production growth.   We note  in 2010, government  introduced “Go” and “No‐Go” policy of environment clearance that effectively brought to halt to coal mining as 203 blocks with capacity of 660 mn ton were brought under ambit of “No‐Go” area.  Environmental Clearances granted Sectors   FY10  FY11 FY12 FY13 FY14 9MFY15Industrial projects   360  241 196 305 118 82Infra & Misc. projects & CRZ   83  88 74 150 60 31Thermal projects   60  63 51 34 8 12Coal mining   56  36 22 41 34 25Mining projects   93  87 46 34 73 35New constr. projects & Industrial estates   63  40 27 37 11 6River valley & Hydroelectric projects   15  8 5 3 5 1Nuclear projects   1  1 3 1 0Grand Total   731  564 421 607 310 192

Source: MOEF  Consequently,  there was significant decline  in environment clearances during FY11‐12,  thus  impacting  CIL’s  production  growth.  CIL  reported  production  CAGR  of  6% during  FY06‐10 when  environment  norms were  relatively  relaxed,  however  during FY11‐14,  the  production  CAGR  stood  at  1.62%  as  introduction  of  stringent environmental  norms  hampered  production.   We  expect  production  CAGR  of  7% during  FY16‐17E  led  by  speedier  environmental  clearances  and  softening  of environmental norms since 2HFY13. Thus, CIL would reach production of 566mn ton by FY17e. Further CIL enjoys competitive advantage of one of the lowest strip ratio in its mine and significant production  (88%  in FY14) being driven by open cast mines, thus leading to faster ramp up.   Coal Production 

 Source: Company, PhillipCapital India Research Estimates   We highlight few measures taken by MOEF • Exemption from Public Hearings: MOEF has allowed for one time expansion of 

production  for mines with  capacity upto 20 MT  to expand production by upto 50% without public hearing. 

(1)

100 

200 

300 

400 

500 

600 

FY07 FY08 FY09 FY10 FY11 FY12 FY13 FY14 FY15E FY16E FY17E

Production Growth (%) (rhs)

Page 30: INSTITUTIONAL EQUITY RESEARCH India Utilitiesbackoffice.phillipcapital.in/...Utilities_Sector... · post FY18. Thus, we expect all India demand for coal to rise at 7% CAGR during

  

Page | 30 | PHILLIPCAPITAL INDIA RESEARCH 

COAL INDIA INITIATING COVERAGE 

• Cluster  Clearances:  As  against  earlier  approach  that  required  separate environmental  approvals  for  each mine  in  coalfield,  the MOEF has  considered allowing group clearances for adjacent mines. The Ministry has identified 94 such clusters  in various CIL units. CIL mines which already have  clearance would be rearranged into clusters for future clearance. 

• Mine  prospecting  norms  relaxed:  The  norms  for  prospecting  forest  areas exempted  from  tribal  consent.  Further  compensatory  afforestation  have  been done away with and no government  inspection  is required for prospecting upto 100 hectares 

  

 

Page 31: INSTITUTIONAL EQUITY RESEARCH India Utilitiesbackoffice.phillipcapital.in/...Utilities_Sector... · post FY18. Thus, we expect all India demand for coal to rise at 7% CAGR during

  

Page | 31 | PHILLIPCAPITAL INDIA RESEARCH 

COAL INDIA INITIATING COVERAGE 

Dispatches lead by Power Sector Dispatches from CIL have witnessed CAGR 4.5% during FY07‐14 led by 4.5% growth in supply  to  power  sector. We  note  supply  to  power  sector  accounts  for  79%  of  CIL dispatches. A  significant portion of  supply  is undertaken under FSA basis  to Power sector. We expect CIL to maintain dispatches at CAGR of 6.2% led by improvement in demand from power sector and materialization of FSA’s for plants commissioned till FY15.  In line with power ministry notification, sales through e‐auction was reduced from 58 mn tonne and capped at 7% of sales  in early FY15. CIL did 45mn tone (9% of sales). However,  reducing  the  e‐auction  quantity  to meet  higher  requirement  of  power sector has led to sharp increase in e‐auction realization and also impacted fuel supply to other sectors (steel, cement) that depend on e‐auction supply. Further evacuation constraint  continues  to  impact despatches  for CIL. We note  government has done away with  cap  on  e‐auction  and  accordingly  expect  e‐auction  sales  at  55mn  tone during FY16‐17E.  Sector‐wise Off take 

  Coal off take 

  CIL sales 

FY10  FY11 FY12  FY13 FY14 FY15E FY16E FY17EFSA  320.9  328.2 362.1  397.1 396.3 429 441.1 470.8Proportion (%)  78.3  78.1 83.7  85.6 84.0 87.6 84.2 82.8E‐Auction  45.7  47.7 50.9  49.1 58.0 45.0 55.0 55.0Proportion (%)  11.2  11.4 11.8  10.6 12.3 9.2 10.5 9.7Washed Coal  14.6  15.5 16.9  14.1 12.9 12.1 21.3 33.0Proportion (%)  3.6  3.7 3.9  0.3 2.7 2.5 4.1 5.8

Source::Company, PhillipCapital India Research Estimates 

Power75%

Steel/hard Coke 2%

Others 23%

 ‐

 1

 2

 3

 4

 5

 6

 7

 8

 9

 10

 ‐

 100

 200

 300

 400

 500

 600

 FY07  FY08  FY09  FY10  FY11  FY12  FY13  FY14  FY15E  FY16E  FY17E

Offtake Growth (%) (rhs)

Dispatches to Power Sector constitute significant portion of sales  

We expect dispatches to grow CAGR 6.5% during FY15‐17E led by private sector. Dispatches during FY14 were subdued due to weak demand from power sector  

We expect supply through E‐auction to increase post removal of cap on   e‐ auction coal.  

Page 32: INSTITUTIONAL EQUITY RESEARCH India Utilitiesbackoffice.phillipcapital.in/...Utilities_Sector... · post FY18. Thus, we expect all India demand for coal to rise at 7% CAGR during

  

Page | 32 | PHILLIPCAPITAL INDIA RESEARCH 

COAL INDIA INITIATING COVERAGE 

Increasing FSA commitment to reduce incentives A) Coal  India  incentives  in FY14 reduced on account of  lower supply to pre 2009 

FSA’s CIL used to supply >100% ACQ to pre 2009 FSA’s. CIL earned incentives of Rs 13bn in FY13 for 305mton of quantity supplied for Pre 2009 FSA’s implying per ton incentives of  Rs  40.  Similarly,  CIL  earned  Rs  8bn  incentives  in  FY14  due  to  increase  in commitment to plant under new FSA arrangement. We expect  incentives to decline as additional FSA materializes with commissioning of new capacity.  CIL 4Q realization is higher led by higher incentives 

 Source: Company, PhillipCapital India Research  The incentives would reduce from FY15 onwards. We highlight below two scenarios of  commitment  that  CIL  may  be  required  to  meet.  Case  I  highlights  coal requirement based on CIL’s assumption of CoD and Case II (base case) is based on our assumption.    Case  I: As per CIL’s FSA  list ~11GW of  capacity would get  commissioned by end of FY14 and ~20.5GW of capacity would get commissioned in FY15. Assuming that most of  the  capacity  is  commissioned  at  the  end  of  the  years  and  also  considering  the optimal  utilization  of  capacity  with  a  year  lag,  CIL  would  require  ~45mton  of additional  coal  in  FY15  and  ~90mton  of  additional  coal  in  FY16  to meet  its  FSA requirements.  This would be the worst case scenario for CIL which really seems to be difficult. It is possible only if discoms sign PPA’s aggressively and all the idle capacities are tied up and secondly all the capacities commission within the time frame which is difficult to materialize as delay in commissioning would continue.   Estimated commissioning of the capacity as per the MoP for FSA’s: 

Sector wise break up  FY10  FY11  FY12  FY13 FY14 FY15Tapering linkages Total

C  1,990  2,490  4,870  4,660 1,695 2,855 1,700 20,260S  2,505  1,310  2,750  2,700 2,050 2,120 2,250 15,685P  1,150  1,905  4,877  3,830 7,330 15,574 5,890 40,556Total  5,645  5,705  12,497  11,190 11,075 20,549 9,840 76,501

Source: Company, PhillipCapital India Research Estimates  Case II: Further analyzing these capacities on the basis of commissioning schedule as per our estimates and considering coal supply to only those projects which have  PPA in place, we estimate the coal requirement for utilities from CIL at 387mn ton in FY15 and 434mntonne  in FY16 and 459 by FY17E. This would cap  the coal supply  to Pre 2009 capacity at the trigger level of 90%, completely wiping out the incentives by the 

1,02

1,04

986 

1,13

1,18

1,22

1,17

1,33

1,26

1,28

1,23

1,40

1,29

1,26

1,27

1,40

1,32

1,26

1,29

900 

1,000 

1,100 

1,200 

1,300 

1,400 

1,500 

1QFY11

2QFY11

3QFY11

4QFY11

1QFY12

2QFY12

3QFY12

4QFY12

1QFY13

2QFY13

3QFY13

4QFY13

1QFY14

2QFY14

3QFY14

4QFY14

1QFY15

2QFY15

3QFY15

CIL realisation

INR145

INR165

INR171 INR86

Page 33: INSTITUTIONAL EQUITY RESEARCH India Utilitiesbackoffice.phillipcapital.in/...Utilities_Sector... · post FY18. Thus, we expect all India demand for coal to rise at 7% CAGR during

  

Page | 33 | PHILLIPCAPITAL INDIA RESEARCH 

COAL INDIA INITIATING COVERAGE 

CIL. We have assumed despite de‐allocation of coal blocks by SC, CIL would continue to honor tapering  linkage based on trigger  level of 75%, 50% and 25% during three years. We note CIL might increase supply to pre 2009 FSA to earn higher incentives as domestic capacities are delayed.  Coal requirement and availability as per our estimates Description  FY14  FY15 FY16 FY17Pre 2009  270  270 270 270FSA Post 20009  90  105 127 153Total requirement                        367                      387                     406                     425 Total supply                        353                      386                     411                     445 (Shortfall)/Surplus for incentives  ( 14 )  ( 2)                      5                    19

Source: Company, PhillipCapital India Research Estimates  Limited possibility of penalty unless tapering linkages are converted: We do not estimate significant shortage under new FSA arrangement as diversion of E‐auction coal coupled with delayed commissioning will  lead  to  lower  requirement. We maintain that despite de allocation of captive coal mines by SC, CIL’s commitment towards  tapering  linkages  would  be  under  erstwhile  arrangement.  However  if tapering  linkages are converted to FSA, this would entail shortfall of 23mn tonne  in FY17 assuming none of the companies are able to retain captive blocks. Under such CIL would be liable for marginal penalty.  Penalty structure as per the model FSA Penalty Structure  FY14  FY15 FY16 FY1775‐70  ‐  ‐ ‐ 0‐570‐67  ‐  ‐ ‐ 5‐1067‐65  ‐  ‐ 0‐2 5‐1065‐60  0‐5  0‐5 2‐7 10‐2060‐55  5‐10  5‐10 7‐20 20‐4055‐50  10‐20  10‐20 20‐40 20‐40Below 50  20‐40  20‐40 20‐40 20‐40

Source: Company, PhillipCapital India Research Estimates  Logistics support critical to meet off take targets: CIL has production target of 615 mntonne by end of FY17, implying production CAGR 8.5% per annum during FY14‐17E. We note this is aggressive, considering CIL’s ability to  ramp‐up production would be contingent on availability of  logistic  infrastructure and  rake  availability  to  aid  evacuation.  In  absence  of  timely  completion  of  rail infrastructure,  CIL’s  production  would  be  50‐55mn  tonne  lower  than  target.  The following   rail links are very crucial for CIL to meet its offtake/production targets as they will potentially lead to offtake of 83mn tonne. 

 Critical Rail Links Rail Link  Distance Coal Fields  State  CIL subsidary  Production Tori ‐Shivpur‐ Kathautia  93.5 North Karanpura  Jharkhand  CCL  32 Jharsuguda‐Barpalli‐Sardega  53 IB Valley  Odisha  MCL  19 Bhupdevpur‐Korichapar‐Dharamjaigarh(East Corridor)  180 Mand‐Raigarh  Chhattisgarh  SECL  32 Gevra Road to Pasan (East‐ West Corridor)  122 Korba ‐Gevra  Chhattisgarh  SECL Total  448.5 83 

Source: Ministry of Railways  Tori  Shivpur  –Kathautia  and  Jharsuguda‐Sardega  is  being  constructed  by  Eastern railways  and  South  Eastern  railways.  The  East  Corridor  and  East West  corridor  is being  constructed  by  JV  of  SECL,  IRCON  international  and  Government  of Chhattisgarh with equity of 64%, 26% and 10% respectively.  Although  these  lines  have  been  accorded  priority  status  by  ministry  of  railways, however  the  commissioning  is  likely  to  be  delayed.  Based  on  revised  CoD,  Tori  –

CIL may most likely end up paying penalty if capacity with tapering linkages are converted into long‐term FSA or if capacity are commissioned earlier than our expectation  

Page 34: INSTITUTIONAL EQUITY RESEARCH India Utilitiesbackoffice.phillipcapital.in/...Utilities_Sector... · post FY18. Thus, we expect all India demand for coal to rise at 7% CAGR during

  

Page | 34 | PHILLIPCAPITAL INDIA RESEARCH 

COAL INDIA INITIATING COVERAGE 

Shivpur  is expected by Dec 2016  and  Jharsuguda –Sardega by  June 16. We expect only partial benefit  to CIL  from  these  lines  in 12th plan and expect major gains  to accrue  in 13th plan during FY18. We note although Tori‐Shivpur  (Phase  I) has most clearances in place; however land acquisition has been delayed.   Rake availability 

 Source: Company 

157  162  168 184  190 

20 

40 

60 

80 

100 

120 

140 

160 

180 

200 

FY10 FY11 FY12 FY13 FY14

Rakes/Day

The improvement in rake availability is also attributed to weak mining activity in FY14  

Page 35: INSTITUTIONAL EQUITY RESEARCH India Utilitiesbackoffice.phillipcapital.in/...Utilities_Sector... · post FY18. Thus, we expect all India demand for coal to rise at 7% CAGR during

  

Page | 35 | PHILLIPCAPITAL INDIA RESEARCH 

COAL INDIA INITIATING COVERAGE 

E‐auction – Drivers to margin  In sweet spot, supply squeeze to drive realization The  government’s  drive  to meet  incremental  demand  of  power  sector  has  led  to reduction of supply under e‐auction. We note supply under e‐auction was reduced to 40mn ton (8% of supply) during FY15 lower than 58 mn ton (12% of supply) in FY14. We note E‐auction coal contributes ~40% of the EBITDA for CIL.   Recent SC decision to scrap captive coal mines will further fuel additional demand for e‐auction,  leading  to  significant demand  supply mismatch  in  this market. We note government has relaxed cap on e‐auction sales, however we expect demand pull to continue  in  FY16  led  by  companies  that  failed  to  retain  coal  block  in  auction. Accordingly, we expect realization in this segment to rise during FY16 and FY17.  E‐auction Quantity and realization  

   Source: Company,PhillipCapital India Research Estimates  International coal prices at lowest since 2009; impacting e‐auction realization International coal prices have declined 13%  in  last 1 year and are at  lowest  level  in past five years. The declining trend  in  international coal prices  is negative for the E‐auction coal prices as it would lead to the shifting of customers from E‐auction coal to imported (depending upon the feasible logistics). The overall decline in the RB index prices in rupee terms is 15% in last 1 year. Despite substantial decline in international coal prices, weak currency offset decline in coal prices.  Coal price 

 Source: Bloomberg 

46  48  51  49  58  45  55  55 ‐

500 

1,000 

1,500 

2,000 

2,500 

3,000 

10 

20 

30 

40 

50 

60 

70 

FY10 FY11 FY12 FY13 FY14 FY15E FY16E FY17E

E‐auction Qty (mn tonne) Realisation (Rs/tonne) (rhs)

20 

40 

60 

80 

100 

120 

140 

1,000 

2,000 

3,000 

4,000 

5,000 

6,000 RB Index Rs/tonne RB Index ‐USD/Tonne

3,000 

3,500 

4,000 

4,500 

5,000 

5,500 

6,000 

1,500 1,700 1,900 2,100 2,300 2,500 2,700 2,900 3,100 3,300 

1QFY11

3QFY11

1QFY12

3QFY12

1QFY13

3QFY13

1QFY14

3QFY14

1QFY15

3QFY15

E auction realisation (INR/ton) RB index (INR/ton) (rhs)

Page 36: INSTITUTIONAL EQUITY RESEARCH India Utilitiesbackoffice.phillipcapital.in/...Utilities_Sector... · post FY18. Thus, we expect all India demand for coal to rise at 7% CAGR during

  

Page | 36 | PHILLIPCAPITAL INDIA RESEARCH 

COAL INDIA INITIATING COVERAGE 

Cost analysis We highlight CIL  ‘s  revenue during FY06‐14 had CAGR of 11.5% and CIL has  largely been able  to maintain EBITDA margins of 23‐25% as CIL has been able  to  take hike  albeit with a lag  to offset cost impact. However, we note that in FY15 with no price hikes taken in FSA supplies and a fall in e auction volumes, margins have declined.   History of price hikes Oct  2009  CIL takes 11% price hike Feb‐11  CIL takes 12% price hike across all categories of coal and applicable to all sectors Jan‐12  Transition to GCV based price mechanism May‐13  Price hike of 10% for low grade coal except for WCL  Dec‐13  CIL takes 10% price hike at WCL, also revises loading charges Apr‐14  CIL revises price at Rajmahal mine due to grade classification 

Source: Coal Ministry   Cost Structure 

 Source: Company  We note employee cost constitute ~ 50% of overall cost as CIL has employee strength of 0.35 mn. Wage hike   lead to ~ 15.5% CAGR increase in employee cost during FY07‐14. CIL  intends  to rationalize 50000 employees, over  five years  that would result  in operating leverage.   Number of employees 

 Source: Company 

Stores and Spares14%

Employee Cost54%

Power & Fuel  4%

Welfare expenses1%

Repairs 2%

Contractual Expenses 13%

Provisions6%

OBR adjustments6%

100,000 

200,000 

300,000 

400,000 

500,000 

FY07 FY08 FY09 FY10 FY11 FY12 FY13 FY14

Employees

During FY07‐14 CIL has reduced employee strength by 92000.  

Page 37: INSTITUTIONAL EQUITY RESEARCH India Utilitiesbackoffice.phillipcapital.in/...Utilities_Sector... · post FY18. Thus, we expect all India demand for coal to rise at 7% CAGR during

  

Page | 37 | PHILLIPCAPITAL INDIA RESEARCH 

COAL INDIA INITIATING COVERAGE 

Wage agreement NCWA II  Signed on  Duration of agreement (years) Period of agreementNCWA II  Dec‐74  4 Jan 1975‐Dec 1978NCWA II  Aug‐79  4 Jan 1979‐Dec 1982NCWA III  Nov‐83  4 Jan 1983‐Dec 1986NCWA IV  Jul‐89  4.5 Jan 1987‐June 1991NCWA V  Jan‐96  5 July 1991‐June 1996NCWA VI  Dec‐00  5 July 1996‐June 2001NCWA VII  Jul‐05  5 July 2001‐June 2006NCWA VIII  Jan‐09  5 July 2006‐June 2011NCWA IX  Jan‐12  5 July 2011‐June 2016

Source: Coal Ministry  Since 1970’s the   wage  structure  and other  conditions  of  service  such as  fringe  benefits,   welfare   measures   etc. of the non‐executive grade employees  in the Coal Industry  have  been  settled  by    Bipartite   Wage    Negotiations    by    a  committee  constituted   by   Govt. Of  India. The committee  is    functioning  in  the name of  Joint Bipartite Committee  for    the   Coal    Industry    consisting   of  representatives   of    5  Central  Trade Unions  and  the  management  of  Coal Companies. The wage revision has happened every  five years and next wage  revision  is due  in FY17 and becomes the key factor to monitor.     

Page 38: INSTITUTIONAL EQUITY RESEARCH India Utilitiesbackoffice.phillipcapital.in/...Utilities_Sector... · post FY18. Thus, we expect all India demand for coal to rise at 7% CAGR during

  

Page | 38 | PHILLIPCAPITAL INDIA RESEARCH 

COAL INDIA INITIATING COVERAGE 

A) Recovery in EBITDA margins after fall in FY15  CIL enjoys EBITDA margins of 30‐34% as 80‐85% of sales are driven by notified prices that are relatively  immune to  international coal prices. The sales through e‐auction however are key lever to margins. We expect price hike in FSA coal to be relatively muted during FY14‐17E and expect e‐auction coal to drive margins. We note margins have declined in FY15 due to lower e‐auction sales and expect them to improve as cap is removed. 

 EBITDA margins 

 Source: Company, PhillipCapital India Research Estimates  B) Strong Cash generation ensuring healthy dividend payout: CIL generates cash flow of Rs 150bn with significant sales under notified price regime. We note CIL has strong debt free balance sheet with Rs523bn cash (Rs 83 per share), 50% of asset ensuring healthy dividend payout.   During FY14, CIL’s dividend payout was relatively  large to meet promoters’  (GOI’s) financing need. We expect dividend payout  to  stabilize  at  50%  during  FY15‐17  as  government  raises  fund  through divestment.  Stron Cash Generation

 Source: Company, PhillipCapital India Research Estimates     

25  24 

32 35 

33  33 32 

29 33 

35 

10 

15 

20 

25 

30 

35 

40 

FY08  FY09  FY10  FY11  FY12  FY13  FY14  FY15E FY16E FY17E

Adjusted EBITDA margin

20 

40 

60 

80 

100 

120 

140 

(300)(250)(200)(150)(100)(50)‐50 

100 150 200 250 

FY11 FY12 FY13 FY14 FY15E FY16E FY17E

CFO (Rs bn) CFI(Rs bn) CFF (Rs bn) Dividend payout (%)

Page 39: INSTITUTIONAL EQUITY RESEARCH India Utilitiesbackoffice.phillipcapital.in/...Utilities_Sector... · post FY18. Thus, we expect all India demand for coal to rise at 7% CAGR during

  

Page | 39 | PHILLIPCAPITAL INDIA RESEARCH 

COAL INDIA INITIATING COVERAGE 

C) Healthy returns profile: CIL‘s  dominant  monopoly  position  in  India’s  coal  market  coupled  with  relative immunity  from  volatile  international  prices  ensure  healthy  return  of  30‐35%. We expect  return  to  remain  robust  and  led  by  operating  leverage  driven  by  volume recovery, return ratio to improve.  RoE and RoCE 

Source: Company, PhillipCapital India Research Estimates   

0%

5%

10%

15%

20%

25%

30%

35%

40%

45%

50%

FY06  FY07  FY08  FY09  FY10  FY11  FY12  FY13  FY14  FY15e  FY16e FY17e

RoE ROCE

Page 40: INSTITUTIONAL EQUITY RESEARCH India Utilitiesbackoffice.phillipcapital.in/...Utilities_Sector... · post FY18. Thus, we expect all India demand for coal to rise at 7% CAGR during

  

Page | 40 | PHILLIPCAPITAL INDIA RESEARCH 

COAL INDIA INITIATING COVERAGE 

Key sensitivities  Change in FSA price hike to target price 

0%  1%  3%  5%  7%  10% 460  463  469  475 481 491

 Change in FSA price hike to EPS 

0%  1%  3%  5% 7%30  31  32  33 35

 Sensitivity of EPS to 10mn tonne increase in production 

546  556  566  576  586 596 54633  33  33  34  34 34 33

 Sensitivity of target to 10mn increase in production 

546  556  566  576  586 596 546391  433  475  521  567 614 391

Source: PhillipCapital India Research Estimates   Sensitivity of e‐auction realization and volume to EPS 

  EPS   25  30  35  40  45  50  55 

E‐au

ction realisation  2,550  29  30  30  31  31  32  33 

2,600  29  30  30  31  32  32  33 2,650  29  30  31  31  32  32  33 2,700  29  30  31  31  32  33  33 2,750  30  30  31  32  32  33  34 2,800  30  30  31  32  33  33  34 2,850  30  31  31  32  33  34  34 

Source: PhillipCapital India Research Estimates   Sensitivity of e‐auction realisation  and volume to target price 

  EPS   25  30  35  40  45  50  55 

E‐au

ction realisation  2,550  457  459  462  464  466  469  471 

2,600  458  460  462  465  467  470  472 2,650  458  461  463  466  468  471  473 2,700  459  461  464  466  469  472  475 2,750  459  462  465  467  470  473  476 2,800  460  462  465  468  471  474  477 2,850  460  463  466  469  472  475  479 

Source: PhillipCapital India Research Estimates      

Page 41: INSTITUTIONAL EQUITY RESEARCH India Utilitiesbackoffice.phillipcapital.in/...Utilities_Sector... · post FY18. Thus, we expect all India demand for coal to rise at 7% CAGR during

  

Page | 41 | PHILLIPCAPITAL INDIA RESEARCH 

COAL INDIA INITIATING COVERAGE 

1year forward P/E band   P/BV band 

Source: Company, PhillipCapital India Research  We  like CIL as  it  is expected  to achieve 13% CAGR PAT during FY15‐17E  led by 7% production growth. Although CIL’s pricing remains at discount to international prices, however we believe CIL would be able to maintain steady margins  led by significant sale at notified price and as e‐auction sales witness higher volume and realization.   At CMP of Rs376, CIL trades at 5.5x time EV/EBITDA adjusted for OBR. We value CIL at 7x EV/EBITDA adjusted for OBR to arrive at target price of Rs473.We initiate coverage with BUY rating on the stock. Key risks to our target price  is government mandating CIL to sign FSA’s more than it can commit (less probability), inability to take price hike and  further  decline  in  international  coal  prices  thus  impacting  e‐auction margins; opening up sector for commercial mining.  Consensus 

___________Consensus___________ ___________PC Estimates___________ ___________Deviation___________FY15E  FY16E  FY17E FY15E FY16E FY17E FY15E  FY16E FY17E

Sales         717,728.9    793,288.6    883,514.0          729,642       835,306       943,069  2%  5% 7%EBITDA         154,156.3    184,526.7    217,575.4          164,498       216,024       254,773  7%  17% 17%PAT         147,689.7    173,239.6    194,063.4          149,971       184,415       210,949  2%  6% 9%

Source: Bloomberg, PhillipCapital India Research Estimates   International peers 

Mkt Cap (USD bn)  P/E RoE EV/EBITDACoal India                                37.9                   13.4         35.3                      9.2 GMDC                                  0.5                     7.1         14.4                      4.7 China Shenhua Energy Ltd                                75.9                   10.0         10.6                      7.4 China Coal Energy                                16.9                  226.3           0.7                    21.2 Yanzhou Coal Mining Ltd                                10.8                   36.1           2.8                    16.5 Shanxi Xishan  Coal                                  5.2                   79.4           2.5                    11.2 Yangquan coal Industry                                  4.6                   47.2           4.6                    11.7 Adaro Energy Tbk PT                                  2.4                   10.5           7.2                      5.5 Indo TambangrayaMegahTbk                                  1.2                     8.1         17.2                      3.9 Average  26 9 11.8

Source: Bloomberg   

 

10x

12x

14x16x

0

50

100

150

200

250

300

350

400

450

500

Apr‐11 Apr‐12 Apr‐13 Apr‐14

Rs

3x

4x

5x

6x

0

50

100

150

200

250

300

350

400

450

500

Apr‐11 Apr‐12 Apr‐13 Apr‐14

Rs

Page 42: INSTITUTIONAL EQUITY RESEARCH India Utilitiesbackoffice.phillipcapital.in/...Utilities_Sector... · post FY18. Thus, we expect all India demand for coal to rise at 7% CAGR during

  

Page | 42 | PHILLIPCAPITAL INDIA RESEARCH 

COAL INDIA INITIATING COVERAGE 

Financials  

Income Statement Y/E Mar, Rs mn  FY14  FY15e  FY16e FY17eNet sales  688,100 729,642  835,306 943,069Growth, %  1 6  14 13Total income  688,100 729,642  835,306 943,069Raw material expenses  ‐71,147 ‐70,242  ‐80,281 ‐90,518Employee expenses  ‐277,694 ‐296,299  ‐316,152 ‐337,334Other Operating expenses  ‐170,657 ‐198,602  ‐222,850 ‐260,444EBITDA (Core)  168,602 164,498  216,024 254,773Growth, %              (6.8)             (2.4)             31.3           17.9 Margin, %             24.5             22.5             25.9           27.0 Depreciation  ‐19,964 ‐22,031  ‐25,391 ‐28,751EBIT  148,638 142,468  190,634 226,023Growth, %              (8.6)             (4.2)             33.8           18.6 Margin, %             21.6             19.5             22.8           24.0 Interest paid  ‐580 ‐72  ‐68 ‐64Pre‐tax profit  228,795 227,228  279,417 319,620Tax provided  ‐77,679 ‐77,258  ‐95,002 ‐108,671Profit after tax  151,116 149,971  184,415 210,949Others (Minorities, Associates)  0 0  0 0Net Profit  151,116 149,971  184,415 210,949Growth, %              (7.7)             (6.3)             23.0           14.4 Net Profit (adjusted)      160,072      149,971      184,415     210,949 Unadj. shares (m)           6,316           6,316          6,316         6,316 Wtdavg shares (m)           6,316           6,316          6,316         6,316   Balance Sheet Y/E Mar, Rs mn  FY14 FY15e  FY16e FY17eCash & bank  523,895 531,826  594,763 689,716Debtors  82,411 87,387  100,042 112,948Inventory  55,680 55,454  64,984 73,368Loans & advances  77,594 77,594  77,594 77,594Other current assets  54,375 57,658  66,008 74,524Total current assets  793,956 809,918  903,390 1,028,149Investments  37,749 37,749  37,749 37,749Gross fixed assets  408,970 458,970  528,970 598,970Less: Depreciation  ‐263,022 ‐285,052  ‐310,443 ‐339,193Add: Capital WIP  45,053 45,053  45,053 45,053Net fixed assets  191,001 218,971  263,580 304,830Total assets  1,042,424 1,086,355  1,224,437 1,390,445

  Current liabilities  616,028 667,941  729,512 808,001Total current liabilities  616,028 667,941  729,512 808,001Non‐current liabilities  2,351 2,351  2,351 2,351Total liabilities  618,379 670,291  731,863 810,352Paid‐up capital  63,164 63,164  63,164 63,164Reserves & surplus  360,881 352,900  429,411 516,929Shareholders’ equity  424,045 416,064  492,574 580,093Total equity & liabilities  1,042,424 1,086,355  1,224,437 1,390,445 Source: Company, PhillipCapital India Research  Estimates 

Cash Flow Y/E Mar, Rs mn  FY14  FY15e FY16e FY17ePre‐tax profit  228,795  227,228 279,417 319,620Depreciation  19,964  22,031 25,391 28,751Chg in working capital  3,625  43,881 31,036 48,684Total tax paid  ‐74,846  ‐77,258 ‐95,002 ‐108,671Cash flow from operating activities  177,539  215,882 240,842 288,383Capital expenditure  ‐41,349  ‐50,000 ‐70,000 ‐70,000Chg in investments  ‐13,799  0 0 0Cash flow from investing activities  ‐55,149  ‐50,000 ‐70,000 ‐70,000Free cash flow  122,390  165,882 170,842 218,383Debt raised/(repaid)  ‐9,063  0 0 0Dividend (incl. tax)  ‐211,427  ‐157,951 ‐107,905 ‐123,430Other financing activities  ‐364  0 0 0Cash flow from financing activities  ‐220,855  ‐157,951 ‐107,905 ‐123,430Net chg in cash  ‐98,465  7,930 62,937 94,953  Valuation Ratios 

FY14  FY15e FY16e FY17ePer Share data EPS (INR)             25.3             23.7             29.2            33.4 Growth, %              (7.7)             (6.3)            23.0            14.4 Book NAV/share (INR)             67.1             65.9             78.0            91.8 FDEPS (INR)             25.3             23.7             29.2            33.4 CEPS (INR)             29.9             27.2             33.2            37.9 CFPS (INR)             13.9             20.7             24.1            30.8 Return ratios          Return on assets (%)             14.1             14.1             16.0            16.1 Return on equity (%)             37.7             36.0             37.4            36.4 Return on capital employed (%)            32.8             35.5             40.4            39.2 Turnover ratios          Asset turnover (x)              (4.2)             (4.5)             (5.1)            (5.9)Sales/Total assets (x)                0.6               0.7               0.7              0.7 Sales/Net FA (x)                3.8               3.6               3.5              3.3 Working capital/Sales (x)              (0.5)             (0.5)             (0.5)            (0.5)Receivable days             43.7             43.7             43.7            43.7 Inventory days             29.5             27.7             28.4            28.4 Working capital days         (183.5)        (195.0)        (183.9)       (181.7)Liquidity ratios          Current ratio (x)                1.3               1.2               1.2              1.3 Quick ratio (x)                1.2               1.1               1.1              1.2 Interest cover (x)           256.3        1,971.3        2,806.1       3,539.4 Total debt/Equity (%)                0.4               0.4               0.3              0.3 Net debt/Equity (%)         (123.1)        (127.4)        (120.4)       (118.6)Valuation          PER (x)             14.8             15.8             12.9            11.3 PEG (x) ‐ y‐o‐y growth              (1.9)             (2.5)               0.6              0.8 Price/Book (x)                5.6               5.7               4.8              4.1 EV/Net sales (x)                2.7               2.5               2.1              1.8 EV/EBITDA (x)             11.0             11.2               8.2              6.6 EV/EBIT (x)             12.5             12.9               9.3              7.5 

Page 43: INSTITUTIONAL EQUITY RESEARCH India Utilitiesbackoffice.phillipcapital.in/...Utilities_Sector... · post FY18. Thus, we expect all India demand for coal to rise at 7% CAGR during

INSTITUTIONAL EQUITY RESEARCH  

Page | 43 | PHILLIPCAPITAL INDIA RESEARCH 

NTPC (NTPC IN) Slowing capacity addition + Uncertainty on incentives =Neutral  INDIA | POWER | Initiating 

 

  

28 April 2015 

Investment Rationale We  initiate coverage on NTPC with a neutral rating and a target price of Rs 160. Stringent tariff norms under new regulation will ensure RoE trajectory likely to be lower over next few years. Coupled with slowing capacity addition we expect NTPC’s earnings growth to remain weak over the next few years.  New tariff norms  limit scope  for RoE’s:  Implementation of CERC tariff norms 2015‐19 has significantly  altered  earnings  trajectory  for  NTPC.  Tightening  of  operational  parameters, removal of tax arbitrage and transition from PAF based  incentive mechanism to PLF based mechanism  will  significantly  impact  incentive  earnings  for  NTPC. We  note  due  to  huge capacity addition  from private  sector, NTPC’s  share  in overall generation will  reduce  thus impacting  its  PLF  and  savings.  Consequently  we  expect  core  RoE’s  under  new  tariff regulation to decline to 17‐18% as against 22‐24%, it accrued under earlier norms.  Pace of capacity addition to drop: NTPC has commissioned 7GW during FY13‐15. We expect capacity addition of 10.7GW during 12th plan  lower than NTPC’s target of 14GW as slower pace of captive mine expansion coupled with limited availability of indigenous fuel will lead to slippages. Thus we expect capacity addition of 4.7GW during FY15‐17E, however we do note that 12GW capacity equipment order already tendered lends visibility for 13th plan.  

Coal blocks cancellation – delay 13thplan.The SC in September,2014 has cancelled four coal blocks  allotted  to NTPC. NTPC was  not  exposed  to  private  competition  under  e‐auction; however  these  blocks  have  been  re‐allotted  to  NTPC.  The  cancellation  does  not  impact capacity addition expected in 12th plan; however it does raise possibility of delay in capacity addition in 13th plan pending clarity on fuel supply.  

 

Earnings and Valuations: We believe during FY15‐17E, operational parameters more  than capacity  addition  would  be  key  to  earnings  of  NTPC. With  capacity  addition  of  3.5GW (parent) during  FY15‐17E, we expect NTPC’s  regulated equity  to achieve 4% CAGR during FY15‐17E  and  subdued  earnings  CAGR  of  4%  during  the  same  period  as  RoE‘s  drop with implementation of new tariff norms.  At CMP of Rs 150, NTPC trades at 1.3X FY17 P/B. We value NTPC at 1.8x FY17E regulated asset base and cash and liquid assets to arrive at target price of Rs 160. 

 Key  risks  to our Neutral call: 1) Major changes  in  tariff  regulation2) Better  than expected operational parameters  leading to higher  incentive earnings complete 3) NTPC  loses all de‐allocated mines. 

Neutral  CMP RS 150 TARGET RS 160 (+7%)  COMPANY DATA O/S SHARES (MN) :  8245MARKET CAP (RSBN) :  1228MARKET CAP (USDBN) :  19.552 ‐ WK HI/LO (RS) :  169 / 114LIQUIDITY 3M (USDMN) :  17.6PAR VALUE (RS) :  10 SHARE HOLDING PATTERN, % PROMOTERS :  75.0FII / NRI :  10.5FI / MF :  12.1NON PROMOTER CORP. HOLDINGS :  0.3PUBLIC & OTHERS :  2.2 PRICE PERFORMANCE, % 

  1MTH 3MTH 1YRABS  ‐1.6 5.8 22.9REL TO BSE  0.9 12.0 2.9 PRICE VS. SENSEX 

 Source: Phillip Capital India Research  KEY FINANCIALS Rs mn  FY15E FY16E FY17ENet Sales  732,489 801,747 836,639EBIDTA  160,997 184,031 200,381Net Profit  82,499 93,181 100,729EPS, Rs             10.0             11.3            12.2 PER, x             15.0             13.3            12.3 EV/EBIDTA, x             12.6             11.8            11.5 P/BV, x                1.5               1.4               1.3 ROE, %              10.2             10.8            11.0 Debt/Equity (%)           118.4           129.2          138.1 

Source: PhillipCapital India Research Est.  Ankur Sharma(+ 9122 6667 9759) [email protected]  Hrishikesh Bhagat(+ 9122 6667 9986) [email protected] 

 

5070

90

110

130

150

170

Apr‐11 Jun‐12 Aug‐13 Oct‐14NTPC BSE Sensex

Page 44: INSTITUTIONAL EQUITY RESEARCH India Utilitiesbackoffice.phillipcapital.in/...Utilities_Sector... · post FY18. Thus, we expect all India demand for coal to rise at 7% CAGR during

  

Page | 44 | PHILLIPCAPITAL INDIA RESEARCH 

NTPC INITIATING COVERAGE 

Capacity addition  target of 14GW during 12th plan; decent visibility in the 13th plan Capacity addition target for 12th plan stands at 14GW NTPC  targets  to  add  14GW  of  capacity  during  the  12th  plan.  It  has  already  added ~7GW  of  capacity  during  FY13‐15  including  4.1GW/1.8GW/1.3GW  during FY13/FY14/FY15  respectively,  implying addition of 7GW  in  remaining 12th plan. We estimate 3.4GW  capacity  addition during  FY16‐17E  as we  expect  execution  to  slip.  NTPC’s current capacity addition estimate has  incorporated 1.32GW Barh  I, even as project  faces  headwinds  due  to  issue  with  Russian  equipment  supplier  TPE. Diplomatic  compulsion  has  made  termination  of  contract  of  equipment  supplier difficult. We expect this project to slip to the 13th plan. Further amongst bulk tender projects, we  expect only 800 MW Unit  1 of  Kudgi  to  commission  in  12th plan  and balance in 13th plan.  List of projects expected to commissioned and estimated to be commissioned during the 12th plan (MW)   FY13  FY 14 FY15E FY16E FY17EVallur JV (1000 MW)   500  ‐ ‐ ‐ ‐ Indira Gandhi JV (1500 MW)   500  ‐ ‐ ‐ ‐ MAUDA TPP (1000 MW)   1,000  ‐ ‐ ‐ ‐Rihand III (1000 MW)   500  500 ‐ ‐ ‐Sipat Stage I (1980 MW)   660  ‐ ‐ ‐ ‐Vindhyachal Stage 4 (1000 MW)   1,000  ‐ ‐ ‐ ‐Barh ‐ II  (1320 MW)   ‐  660 660 ‐ ‐MTPS    110 ‐ ‐ ‐Vallur Phase II JV (500 MW)   ‐  500 ‐ ‐ ‐Muzaffarpur JV (390 MW)   ‐  ‐ 195 195 ‐Kol Dam   ‐  ‐ 400 400 ‐Bongaigaon (750 MW)   ‐  ‐ ‐ 500 250Nabinagar TPP JV (1000 MW)   ‐  ‐ ‐         500         250 Tapovan Vishnu Garh  ‐  ‐ ‐ ‐ ‐Barh ‐ I  (1980 MW)   ‐  ‐ ‐ ‐ ‐Kudgi (2400 MW) ‐ BT   ‐  ‐ ‐ ‐ 800Vindhyachal Stage 5 (500 MW)   ‐  ‐ ‐ 500 ‐Solar PV (Andaman & Nicobar)              5            ‐           ‐           ‐           ‐Solar PV(Dadri)              5            ‐           ‐           ‐           ‐Ramagundam Solar PV            ‐            10            ‐           ‐           ‐Talcher Solar PV            ‐            10            ‐           ‐           ‐Faridabad Solar PV            ‐              5            ‐           ‐           ‐Unchahar Solar PV            ‐            10            ‐           ‐           ‐Rajgarh Solar PV            ‐            30            20            ‐           ‐Singrauli Solar PV            ‐            ‐           15            ‐           ‐Singrauli Hydro PV            ‐            ‐ ‐ 8           ‐ Standalone   3,170  1,225 1,095 1,408 1,050 JV   1,000  610 195 695 250 Total   4,170  1,835 1,290 2,103 1,300

Source: Company, PhillipCapital India Research  

   

The  capacity  addition  in  12th  plan  isexpected to grow ~1.1x from the 11th

plan  despite  revising  the  targetcapacity  for  few  times.  The  positivefor  NTPC  is  capacity  addition  isexpected  to  be  front  ended  assuringaddition  of  the  projects  within  the12th plan even if there are slippages 

Page 45: INSTITUTIONAL EQUITY RESEARCH India Utilitiesbackoffice.phillipcapital.in/...Utilities_Sector... · post FY18. Thus, we expect all India demand for coal to rise at 7% CAGR during

  

Page | 45 | PHILLIPCAPITAL INDIA RESEARCH 

NTPC INITIATING COVERAGE 

NTPC’s capacity to grow at CAGR of 5% during 12th Plan                Targetted capacity addition in 12th plan ~14GW 

 Source: Company, PhillipCapital India Research Estimates  Actual vs Planned Plan  Actual  Planned Achievement(%)XII  10698*  14228 75%XI  9610@  9220 104%X  7155  9370 76%IX  2700  5300 51%

*PhillipCapital India Research Estimates @In XIth plan NTPC was able to exceed capacity addition as target was revised to 9.2 GW post mid‐ term review  The  key  difference  in  XIIth plan  is NTPC’s  capacity  addition  has  been  largely  front ended as compared to earlier.  Additional  ~  22GW  of  projects  are  under  construction,  5GW  under  awarding process and ~20GW feasibility report approved provides visibility in the 13th plan NTPC has 22GW of capacity under construction  including 4GW capacity expected to commission during 12th plan. We expect large part of bulk tender projects awarded in FY13 to commission in 13th plan, thus lending long term growth visibility for NTPC.  Gross fixed assets grow aided by increased commissioning (Rsbn)   Type  Capacity NTPC/JVSolapur  Coal  1320 NTPCMouda II  Coal  1320 NTPCKudgi  Coal  1600 NTPCLara  Coal  1600 NTPCGadarwara  Coal  1600 NTPCLataTapovan  Hydro  171 NTPCNabhinagar  Coal  1980 JVMeja  Coal  1320 JV

Source: Company, PhillipCapital India Research Estimates  

Along with  the 11GW under  construction projects estimated  to  commission  in  the 13th plan NTPC also has 5GW of capacity under awarding process and has feasibility report  prepared  for  18GW  of  capacity  providing  better  visibility  on  the  future capacity addition plans.    

0

2

4

6

8

10

12

14

0

5000

10000

15000

20000

25000

30000

35000

40000

45000

50000

FY00

FY01

FY02

FY03

FY04

FY05

FY06

FY07

FY08

FY09

FY10

FY11

FY12

FY13

FY14

FY15

FY16

EFY17

E

Capacity addition (MW)

Growth (%)

3.1

8.2

5.5

3.4

7.2

9.6

14

0

2

4

6

8

10

12

14

16

VIth VIIth VIIIth IXth Xth Xith XIIth

Plan wise Estimated capacity addition (GW)

NTPC has ~ 22GW of capacity under construction estimated to commission in initial years of 13th plan 

NTPC also has 5GW of capacity under awarding process and feasibility report prepared for 20GW 

Page 46: INSTITUTIONAL EQUITY RESEARCH India Utilitiesbackoffice.phillipcapital.in/...Utilities_Sector... · post FY18. Thus, we expect all India demand for coal to rise at 7% CAGR during

  

Page | 46 | PHILLIPCAPITAL INDIA RESEARCH 

NTPC INITIATING COVERAGE 

 Coal based capacity to drive the growth (GW) 

 Source: Company, PhillipCapital India Research Estimates   Better commercialization in FY13‐14 due to slippages NTPC commercialized 4.8GW of capacity during FY13, 2.7GW  in FY14 and 1.2GW  in FY15.  Better  commercialization  than  commissioning  was  mainly  led  by  higher slippages/delays  in  the  previous  years.  The  gap  between  the  commissioning  and commercialization  of  a  capacity  for  NTPC  is  ~6‐8  months. We  expected  pace  of commercialization  to  slow  down  as  limited  progress  over  captive  mines,  limited indigenous  fuel  availability  as well  as  lower  demand will  reduce  pace  of  capacity addition.  Commercialization (Consol) has been higher than the commissioning 

 Source: Company, PhillipCapital India Research Estimates           

0%

20%

40%

60%

80%

100%

FY09 FY10 FY11 FY12 FY13 FY14 FY15 FY16E FY17E

Coal  Hydro  Gas 

0

1000

2000

3000

4000

5000

6000

FY09  FY10  FY11  FY12  FY13  FY14  FY15E  FY16E  FY17E 

Commissioning Commercialisation

NTPC’s coal based capacity would drive the capacity addition growth. The hydro capacities would also start contributing from FY15. The gas based capacity would remain stagnant which is a positive for NTPC looking at the macro environment where most of the gas based capacity are non operating or operating at a lower PLF due to lower availability of the gas 

The  better  commercialization  thancommissioning  In  FY13  and  FY14  wasled  by  higher  slippages/delays  in  thecommissioning in the previous years. 

Page 47: INSTITUTIONAL EQUITY RESEARCH India Utilitiesbackoffice.phillipcapital.in/...Utilities_Sector... · post FY18. Thus, we expect all India demand for coal to rise at 7% CAGR during

  

Page | 47 | PHILLIPCAPITAL INDIA RESEARCH 

NTPC INITIATING COVERAGE 

Fuel availability    A) FSA with Coal India 25GW tied up for capacity commissioned till FY09 with 90% trigger levels NTPC has FSA for 25GW of  its capacity with Coal  India with 90% trigger  levels. Coal India  has  supplied  coal  for  these  capacities  at  more  than  100%  levels.  With requirement  for  coal  supply  substantially  increasing,  CIL  may  reduce  the  supply levels. However we believe that it would continue to supply coal to NTPC above 90% as it helps to avoid the penalty and add to incentives earning of Coal India.   The gap between 100% requirement and actual supply widens 

 Source: Company, PhillipCapital India Research Estimates  NTPC’s  9GW of  standalone  capacity  has  entered  into  FSA with  Coal  India  as  per President’s directive NTPC has signed FSA with Coal India for 9GW (post 2009) of  its coal based capacity, assuming that these projects needs to be supplied coal at 80% requirement of 85% PLF,  then  the cumulative coal  requirement  for  these projects come  to 33mton. We expect  that  there  would  be  lesser  requirement  as  we  estimate  slower  pace  of capacity addition.  Additional coal requirement for new FSA’s  

Commissioning Capacity 

(MW) Coal req. 

(Avg) Coal req. 

(Full) Coal req. 

(Cum)CIL commitment 

(%)Approxsupply

FY10  990  2.54  5.07  3FY11  1,990  5.1  10.2  10FY12  1,820  4.66  9.33  20FY13  3,160  8.1  16.19  33 8FY14  500  1.28  2.56  42 65                   14 FY15  ‐  ‐  ‐  43 65                   15 FY16  500  1.28  2.56  43 67                   29 FY17  43 75                   33 

Source: Company, PhillipCapital India Research Estimates   

50 

100 

150 

200 

250 

5,000 

10,000 

15,000 

20,000 

25,000 

30,000 

35,000 

FY07 FY08 FY09 FY10 FY11 FY12 FY13 FY14 FY15

Capacity Domestic supply actual At 100% requirement The domestic coal supply has increased YoY but it has come down as % of 100% requirement of average commercial capacity. This is mainly due to lower off take from the SEB’s despite more than 100% availability of the ACQ coal for plant under FSA till FY09 

Page 48: INSTITUTIONAL EQUITY RESEARCH India Utilitiesbackoffice.phillipcapital.in/...Utilities_Sector... · post FY18. Thus, we expect all India demand for coal to rise at 7% CAGR during

  

Page | 48 | PHILLIPCAPITAL INDIA RESEARCH 

NTPC INITIATING COVERAGE 

B) Captive mines to commission production in FY16; 4 new mines allocated taking overall reserves to 5bn ton 

The development on  captive mines has been  significantly disappointing. NTPC was awarded  8  coal  blocks  during  2004‐2007;  however  none  of  the  blocks  have commenced production. Off the 8 block, 2 blocks Bhahmini and ChichroPastim were deallocated in 2011 due to lack of progress.  Pakrih Barwadih mine was allotted to NTPC in 2004; however production is yet to see light  of  day.  Production  was  delayed  due  to  delayed  clearances.  Also  mine  was subjected  to  de‐allocation  along  with  ChhatiBariatu,  ChatiiBariatu  (South)  and Kerandari block in FY13 and was re‐allocated again.  In 2010, NTPC appointed Thiess Minecs  as MDO,  however  due  to  delay  in  development  of mine  the  contract was cancelled  recently.  NTPC  intends  to  reappoint MDO.  Further,  the  production  got delayed due to  law and order  issue  in Jharkand state. We expect PakrihBarwadih to commence operation  in  FY17. The Chatti‐Bariatu block also  faced  similar problems even as mine has all statutory clearances  in place and mine developer and operator (MDO)  has  been  appointed.  In  Kerandari,  the  company  is  seeking  a  fresh  forest clearance  after  the  earlier  one  lapsed.  The  Dulanga  block  ran  into  a  Go  No‐Go controversy  and  in  Talaipalli,  the  appointment  for MDO  is  still  awaited  with  the previous developer, Singareni Collieries, exiting project. Although these blocks were again de allocated due  to SC  ruling  in September 2014 however government has again realloted to NTPC.   We expect NTPC to commence operation at Chhati Bariatu in FY16 and expect NTPC to achieve peak production of 53 mn ton in FY22.  Captive mines 

 Capacity  Environmental  

clearance Forest  

Clearance Land  

acquisition  MDO Pakri Barwadih  15  Received  Received  Done  In process Chatti‐Bariatu  7  Received  Received  Done  appointed Kerandari  6  Received  Stage I received  Done  In process Talapalli  18  Received  Received  Done  In process Dulanga  7  Received  Stage I received  Done  In process 

Source: Company, PhillipCapital India Research Estimates  NTPC allocated 4 new mines that would help reducing dependency on Coal India NTPC has been allocated 4new captive mines for 8 GW of its upcoming capacity. The combine  reserves  of  these mines  stands  at  ~2bn  tonne  and  the  peak  capacity  is estimated ~40m  tone. These mines would  start  contributing  in  the 13th plan but  it provides visibility on the domestic coal availability and at the same time reduces the dependency on the Coal India.   Allocation of 4 new mines takes to proved reserves to 5bn ton   Reserves  Capacity GCV estimated  Status CommissioningBanai  629  12 3200‐5400  exploration in process 13th planBhalmuda  550  14.4 3600‐5400  unexplored 13th planChandrabila  550  10.8 3200‐5400  unexplored 13th planKudanali‐Laburi  266  7.8 3200‐5400  unexplored 13th plan

Source: Company, PhillipCapital India Research    .

We expect mines to commence production earliest by FY16 and to reach peak capacity by FY22. 

Page 49: INSTITUTIONAL EQUITY RESEARCH India Utilitiesbackoffice.phillipcapital.in/...Utilities_Sector... · post FY18. Thus, we expect all India demand for coal to rise at 7% CAGR during

  

Page | 49 | PHILLIPCAPITAL INDIA RESEARCH 

NTPC INITIATING COVERAGE 

Import to fulfill the shortfall NTPC currently has FSA  for FY09 capacity with 90%  trigger  level  (~125mton).  It has also entered for post FY09 capacity at 80% trigger level at 85% PLF. We note in FY13, NTPC had planned  to achieve 33mn  tonne coal production  from captive mines and target has been reduced to 13mn tonne in FY14. We expect contribution from captive coal  to overall  fuel mix  to gain  traction  in 13th plan.  Lower  captive  coal availability coupled with  limited  supply  from  CIL would  increase  dependence  on  imports  for NTPC.  Pre ACQ quantity may come down to the trigger level (90%)   FY13 FY14 FY15E FY16E FY17EDomestic      ‐Annual Contracted Quantity(ACQ)for pre FY09  133.8 131 125.0 118.8 118.8     ‐LOA/MOU ‐ 65% supply post signing FSA's in July  8.0 14 15.0 29.0 32.5     ‐Captive ‐ 50% of target  ‐ ‐ ‐ 1.2 3.0     ‐Others ‐ Bilateral/E auction  2.3 4.8 4.8 4.8 4.8Total domestic  146.0 150 144.8 153.7 159.0Imported  9.0 10.8 15.2 22.9 23.6Total  153.0 160.6 159.9 176.6 182.6

Source: Company, PhillipCapital India Research Estimates  The  imported  coal  mix  is  expected  to  increase  for  NTPC.  We  estimate  that  the imported coal consumption as % of domestic coal consumption would increase from ~3‐4% in FY07 to 10‐12% during the latter part of the 12th plan.   Import as % of domestic supply would increase 

 Source: Company, PhillipCapital India Research Estimates 

0

2

4

6

8

10

12

14

16

100 

110 

120 

130 

140 

150 

160 

170 

FY07 FY08 FY09 FY10 FY11 FY12 FY13 FY14 FY15E FY16E FY17E

Domestic Imported as % of domestic supply

Page 50: INSTITUTIONAL EQUITY RESEARCH India Utilitiesbackoffice.phillipcapital.in/...Utilities_Sector... · post FY18. Thus, we expect all India demand for coal to rise at 7% CAGR during

  

Page | 50 | PHILLIPCAPITAL INDIA RESEARCH 

NTPC INITIATING COVERAGE 

Lower generation growth/PLF major concern We analyzed the macro changes that might have  impacted the NTPC’s generation growth. This is important as we see a structural shift wherein NTPC may not be able to see higher PLF’s and  this could cap  the  incentives under new  tariff  regulations wherein incentives are linked to PLF.  A) Emergence of the private sector: NTPC’s generation during FY11‐14 was CAGR 2%. The subdued growth was driven by the decline in the gas based generation. Also coal based generation during the same period reported CAGR of 4.2% as against all  India average of 10%. We note NTPC’s generation share of the overall coal based generation has declined from 36% in 2011 to 30% in FY14. PLF came off from 91% in FY10 to 82% in FY14 lowest in last 10 years. 11th plan also saw the higher addition of the Private capacity with capacity increasing almost  2.5x  contributing  to  the  overall  generation  growth.  Consequently  private sector  coal based generation witnessed CAGR of 64% during FY11‐14 and  share of private sector increased to 24% in FY14 from 7% in FY11. Further in the 12th plan as per CEA  estimates more  than half of  the 88GW  estimated  to be  added by private Players. We believe that higher contribution from private sector would reduce higher dependency on NTPC.  However, we do not expect NTPC’s PLF to substantially decline led by the low cost but  there may be a  structural  shift were NTPC’s PLF would  range  from 80%‐85% instead of historic average  90% and above.  60% capacity contributed by the state….                                       ……..Central sector pie increases 

   

… Pvt. Sector increases it base by 2.5x:               As per CEA guidance Pvt sector would add more than 50% of capacity 

 Source: Company, PhillipCapital India Research Estimates  

Central31,899 30%

State62,460 60%

Pvt10,643 10%

9th plan

Central45,121 36%

State69,521 56%

Pvt9,927 8%

10th Plan

Central59,683 34%

State82,405 47%

Pvt34,086 19%

11th Plan

Central78,676 22%

State199,295 55%

Pvt80,971 23%

12th plan

Page 51: INSTITUTIONAL EQUITY RESEARCH India Utilitiesbackoffice.phillipcapital.in/...Utilities_Sector... · post FY18. Thus, we expect all India demand for coal to rise at 7% CAGR during

  

Page | 51 | PHILLIPCAPITAL INDIA RESEARCH 

NTPC INITIATING COVERAGE 

B) Lower off take from SEB’s impacting overall demand scenario Demand  from  the  SEB’s  has  declined  in  the  recent  past.  Newly  commissioned capacities in the power sector are operating at lower PLF’s due to lower offtake from the SEB’s. Also discoms are reluctant to purchase the high cost power and have also reduced  supply  in  the  pockets  with  higher  commercial  losses.  Further  the  FRP initiated in 2013 and that was adopted by 7 states did not succeed as anticipated as states  failed  to meet  conditions.  During  the  recent  elections  in  the  5  states  also power demand did not showed any  increase which could be possibly due structural shift  in  the  demand  pattern  as  discoms  become more  responsible.  This  could  be negative  for  overall  generation  companies  and  especially  for  NTPC  with  its  high standards of 85‐90% of PLF.  Demand growth declining…   … Deficit down to 4.5% 

 Source: Company, PhillipCapital India Research Estimates  

 Higher dependency on Northern and Western states… State  Region  % of total revenuesUP  North  13.7%Delhi  North  13%Maharastra  West  8%AP  South  8%Gujarat  West  6%MP  West  6%Bihar  East  5%T Nadu  South  5%Haryana  North  5%Orrisa  East  4%Kerala  South  4%Punjab  North  3%Others    21%Source: Company, PhillipCapital India Research Estimates   C) Changes in macro environment to reduce the PLF’s by 2‐5 ppt for NTPC  We believe that due to the changes in the macro environment 1) substantial capacity addition  and  Private  Sector  becoming  more  dominant  2)  SEB’s  reducing  power purchase to reduce loses would impact the NTPC’s generation by 5‐10 ppt over next few years.   Although NTPC would be beneficiary led by its low cost generation and might able to maintain relatively better PLF’s as compared to its peers but they would come down from historic average of 85‐90% to 80‐85%.  

0%1%2%3%4%5%6%7%8%9%

10%

FY07

FY08

FY09

FY10

FY11

FY12

FY13

FY14

FY15

 YTD

Demand growth

3%

4%

5%

6%

7%

8%

9%

10%

11%

12%

FY07

FY08

FY09

FY10

FY11

FY12

FY13

FY14

FY15

 YTD

Deficit

Page 52: INSTITUTIONAL EQUITY RESEARCH India Utilitiesbackoffice.phillipcapital.in/...Utilities_Sector... · post FY18. Thus, we expect all India demand for coal to rise at 7% CAGR during

  

Page | 52 | PHILLIPCAPITAL INDIA RESEARCH 

NTPC INITIATING COVERAGE 

Generation & Growth 

 Source: Company, PhillipCapital India Research Estimates   Generation loss for NTPC due to back down from SEB’s 

 Source: Company, PhillipCapital India Research Estimates   PLF declined despite higher availability:             

 Source: Company, PhillipCapital India Research Estimates 

0

2

4

6

8

10

12

14

130 

150 

170 

190 

210 

230 

250 

270 

290 

FY05

FY06

FY07

FY08

FY09

FY10

FY11

FY12

FY13

FY14

FY15

FY16

E

FY17

E

Generation  Growth (rhs)

0

4

8

12

16

20

0

10

20

30

40

50

FY11 FY12 FY13 FY14

Loss due to demand backdown (BU) % of NTPC generation

80 

82 

84 

86 

88 

90 

92 

94 

FY10 FY11 FY12 FY13 FY14 FY15 FY16E FY17E

Coal‐PAF Gas‐PAF

f . n e k 

n g d ‐

The  gap  between  PLF  and  PAF  hasincreased  significantly  in  recent  yearsimplying  fuel  availability  has  beenstable  for  NTPC  but  offtake  has  takenhit due to weak SEB financials. 

Page 53: INSTITUTIONAL EQUITY RESEARCH India Utilitiesbackoffice.phillipcapital.in/...Utilities_Sector... · post FY18. Thus, we expect all India demand for coal to rise at 7% CAGR during

  

Page | 53 | PHILLIPCAPITAL INDIA RESEARCH 

NTPC INITIATING COVERAGE 

New tariff regulation limits RoE expansion CERC released tariff regulation for 2015‐19. We note with the aim of bringing efficiency CERC has tightened operational parameters in line with draft regulations. We highlight below the key changes that were introduced in tariff regulation over past few years.       2004‐09  2009‐14  2015‐19 Capital Cost  Capital expenditure based on actual 

cost incurred Capital cost based on actual cost and allowed for truing up. Norms allowed for IDC due to delay, as pass through subject to prudence check.  

As per new norms IDC and IEDC due to delay on account of uncontrollable factor shall be allowed as part of Capital cost.  

Tax gross up  NA  Norms allowed utility to recover corporate tax rate from beneficiaries even if actual incidence of tax was lower due to MAT rate. 

RoE gross up at effective tax rate based on actual tax paid 

Sharing of financial gains due to controllable factors 

NA  Saving on account of SFO to be shared with beneficiaries in ratio of 50:50 

 Sharing of all gains due to controllable factors between Gencos and discoms in ratio of 60% and 40% respectively.  

Incentives  Rs0.25/Kwh for  generation above  80% PLF 

Based on PAF over and above  normative PAF at 85% 

Rs0.50Kwh for generation above 85% PLF 

Energy charges     Calculated on  "as received basis"  Calculated on "as fire basis" CapitalStructure   Debt : Equity = 70%:30%   Debt : Equity = 70%:30%  Debt : Equity = 70%:30% RoE   14%     15.5%    15.5% 

           Working capital components          Cost of Coal  1.5 mnths (pit head)‐1.5 months 

(non‐pit had) 1.5 mnths (pit head)‐2 months (non‐pit had) 

15 days (pit head)‐30days (non‐pit had) 

Cost of SFO  2 months   2 months   2 months  Maintenance Spares  1.5% of capital cost  20% of O&M  20% of O&M Receivables  Two Months of capacity charges and 

energy charges Two Months of capacity charges and energy charges 

Two Months of capacity charges ( excluding RoE) component and energy charges 

O&M expenses  1 month  1 month  1 month Interest on working capital  SBI PLR  SBI PLR/SBI base rate plus 350 bps  Bank rate as on April 2014 Escalation in O&M expenses  4.00%  5.72%  6.35% Water Charges      Water charges allowed as O&M  Water charges to be recovered 

separately SHR  2450 kcal/kwh  2425 kcal/kwh  2375 kcal/kwh Auxilary Consumption  9  8.5  7.75 SFO Consumption  2 ml/kwh   1 ml/kwh   0.5 ml/kwh (pit head) Fixed cost recovery  80% PAF for fixed cost recovery  85% PAF for fixed cost recovery  83% PAF for fixed cost recovery Special allowance  NA  Special allowance in lieu of  R&M  at 

Rs  0.5mn/MW/year and escalation  at 5.72% 

Special allowance in lieu of  R&M  at Rs  0.75mn/MW/year and escalation  at 6.35% 

Source: Company, PhillipCapital India Research Estimates 

Page 54: INSTITUTIONAL EQUITY RESEARCH India Utilitiesbackoffice.phillipcapital.in/...Utilities_Sector... · post FY18. Thus, we expect all India demand for coal to rise at 7% CAGR during

  

Page | 54 | PHILLIPCAPITAL INDIA RESEARCH 

NTPC INITIATING COVERAGE 

The  regulation  for  2015‐19  has  once  again  introduced  PLF  based  incentive  and tightened  operational  parameters  thus  impacting  incentive  earnings  of NTPC. Also removal of  tax  arbitrage  coupled with  introduction of  incentive  sharing norms will limit scope for RoE expansion. We estimate core RoE to reduce from 20‐22% under earlier tariff regime to 17‐18% under new regulation. Although NTPC has appealed in  high  court  against  CERC  for  reversal  of  norms,  we  do  not  expect  significant changes.  Key highlights of regulations: A) Introduction of Controllable and Uncontrollable factors 

The  commission  has  specified  controllable  and  uncontrollable  factors  in determination  of  capital  cost  Controllable  factors:  variation  in  capex  due  to time/cost  overrun  due  to  land  acquisition  issue,  delay  in  execution  by contractors  appointed.  Uncontrollable  factors  viz.  Force  majeure  events  and Change  in  law.  We  believe  the  introduction  of  controllable  factors  in determination  of  capital  cost  has  introduced  the  risk  of  under‐recovery  in upcoming projects in case CERC does not allow increased in capex.  

B) PLF incentives now to be earned on generation: NTPC earlier used to earn incentive on the availability above 85% but now it has been linked to the generation. NTPC is able to maintain higher PAF levels even as PLF’s  have  declined  due  to  back  down  from  discoms. We  have  assumed  that some of the NTPC’s older plant would be able to maintain higher PLF’s but the PLF  of  other  and  newly  commissioned  plant  would  be  below  85%.  Thus  we expect transition from PAF to PLF would impact core RoE by 100‐150bps.  

Estimated PLF’s for the projects   FY10  FY11 FY12  FY13 FY14 FY15 FY16e FY17eBadarpur  83  74 77  74 67               53  80 80Barh II                     61  60 60Bongaigaon          60 60Dadri  98  84 89  82 83               77  85 85Farakka  76  81 70  64 72               73  72 72Kahalgaon  67  71 65  72 71               76  78 78Korba  97  93 79  90 91               88  88 88Kudgi        60Mauda      17               26  55 60Ramagundem  96  89 93  91 87               89  88 88Rihand  96  93 92  87 84               81  88 88Simhadri  98  96 94  84 84               86  96 96Singrauli  94  97 89  93 92               83  88 88Sipat  93  96 95  75 73               83  90 90Talcher  90  92 91  94 93               94  94 94Talcher  93  85 83  82 83               90  88 88Tanda  94  93 88  84 93               82  88 88Unchahar  96  93 90  93 86               83  90 90Vindhyachal  96  94 90  90 87               79  90 90

Source: Company, PhillipCapital India Research Estimates  C) Savings on the fuel: NTPC due to its superior operational performance is able to maintain better than the normative SHR  thus aiding NTPC  to  save on  the  fuel. The normative SHR has been reduced  from 2425kcal/kwh  to 2375kcal/kwh; and would hence  reduce  savings  for NTPC. We  estimate  that  reduction  in  SHR  would  have  substantial  impact  on  the additional gains of NTPC. We estimate lower savings to impact RoE by 300bps.  D) O&M escalation increased, water charges allowed as pass through: Under new  regulation, O&M  escalation has been  increased  to 6.35%  from  current level of 5.72%. Further water charges have been separately allowed as pass through. 

Page 55: INSTITUTIONAL EQUITY RESEARCH India Utilitiesbackoffice.phillipcapital.in/...Utilities_Sector... · post FY18. Thus, we expect all India demand for coal to rise at 7% CAGR during

  

Page | 55 | PHILLIPCAPITAL INDIA RESEARCH 

NTPC INITIATING COVERAGE 

We  estimate  ~  Rs  5bn  reduction  in  under  recovery  led  by  pass  through  of water charges.  E) No more arbitrage on RoE gross up: NTPC grossed up the RoE on the corporate tax and the actual tax payment is on the MAT rate. Hence it is able to make arbitrage on the difference between the corporate and MAT rate. As per  the draft regulation NTPC would be able gross up  the Roe at effective tax rate based on the actual tax paid. This we believe would be a major blow to NTPC and would have the impact of ~300‐350bps on NTPC’s profit.  Core RoE 

 Source: Company, PhillipCapital India Research Estimates 

 

5%

10%

15%

20%

25%

30%

FY11 FY12 FY13 FY14 FY15E FY16E FY17E

Core RoE

We estimate NTPC’s core RoE to decline with implementation of new tariff norms. 

Page 56: INSTITUTIONAL EQUITY RESEARCH India Utilitiesbackoffice.phillipcapital.in/...Utilities_Sector... · post FY18. Thus, we expect all India demand for coal to rise at 7% CAGR during

  

Page | 56 | PHILLIPCAPITAL INDIA RESEARCH 

NTPC INITIATING COVERAGE 

Strong balance sheet to support the growth NTPC has the strongest balance sheets among its peers providing confidence on the growth prospect of the company.  A) Lowest Debt Equity among peers: NTPC’s debt /equity ratios lowest among the peers and it has been able to maintain it in a narrow range despite robust capex  incurred by the company. The other utilities have  been  impacted  due  to  higher  leverage  and  had  to  dilute  equity or monetize asset to meet their  further capex requirement. NTPC debt/equity stood at 0.8x and would  help  it  in  meeting  its  growth  requirement  (20GW  of  capacity  under construction). We note strong balance sheet also opens up opportunity of  inorganic growth  for  NTPC.  NTPC  has  indicated  it  is  evaluating  ~  8‐9GW  of  opportunities. Assuming 4GW opportunities materializes and acquired project accrue similar RoE as existing projects, the accretion to SOTP would be Rs 2‐3 per share.   D:E of major utilities 

 Source: Company, PhillipCapital India Research Estimates  B) Debtor days: NTPC has been able to maintain debtor days down to 30‐35 lower than normative 60 days period that regulation grants; implying timely recovery of dues. NTPC has been able  to achieve 100%  realization of dues. Most of  the discoms have maintained LC equal  to or more  than 10% of billing as per OTSS agreement. NTPC has resorted  to regulation/diversion of power supply to third party at the risk and cost of defaulting utilities in case of non‐payment of dues. Debtor days stable stood at 30‐35 days   Debtors days 

 Source: Company, PhillipCapital India Research Estimates 

0

2

4

6

8

10

NTPC NHPC JSW Reliance JPVL PWGR Adani

FY11 FY12 FY13 FY14

10 

20 

30 

40 

50 

60 

FY05 FY06 FY07 FY08 FY09 FY10 FY11 FY12 FY13 FY14

Debtor days

NTPC  stands  out  among  its  peers  on comparing the D:E. Most of the utilities have opted for equity dilution or looking for  asset  sell  to  improve  its  balance sheet 

Page 57: INSTITUTIONAL EQUITY RESEARCH India Utilitiesbackoffice.phillipcapital.in/...Utilities_Sector... · post FY18. Thus, we expect all India demand for coal to rise at 7% CAGR during

  

Page | 57 | PHILLIPCAPITAL INDIA RESEARCH 

NTPC INITIATING COVERAGE 

C) Regulated earnings ensure stable cash flow and dividend payout NTPC accrue regulated earnings based on CERC norms that ensure steady EBITDA of 24‐26% and also generate  robust cash  flow of ~ Rs 150bn aided by steady capacity addition.  Further  with  variable  cost  pass  through,  risk  of  fuel  under  recovery  is unlikely  case  of  NTPC  like  private  players. We  expect  NTPC  to maintain  its  FY14 payout of 43%.   EBITDA margins (%) 

 Source: Company, PhillipCapital India Research Estimates   Cash flow from operations 

 Source: Company, PhillipCapital India Research Estimates     

5%

10%

15%

20%

25%

30%

FY11 FY12 FY13 FY14 FY15E FY16E FY17E

EBIDTA margin

(300)(250)(200)(150)(100)(50)‐50 

100 150 200 

FY11 FY12 FY13 FY14 FY15E FY16E FY17E

Cashflow from Operation (Rs bn) Cash flow from investments (Rs bn)

Cash flow from Financing (Rs bn)

Regulated business ensuring stable margins 

Aiding steady cash generation

Page 58: INSTITUTIONAL EQUITY RESEARCH India Utilitiesbackoffice.phillipcapital.in/...Utilities_Sector... · post FY18. Thus, we expect all India demand for coal to rise at 7% CAGR during

  

Page | 58 | PHILLIPCAPITAL INDIA RESEARCH 

NTPC INITIATING COVERAGE 

Dividend payout 

 Source: Company, PhillipCapital India Research Estimates   1year forward band charts 

 Source: Company, PhillipCapital India Research 

Phillip Capital vs consensus estimates 

____________PC Estimates____________ ____________Consensus____________ ____________Deviation____________(Rs mn)  FY15E  FY16E  FY17E FY15E FY16E FY17E FY15E  FY16E FY17ESales  743,023  810,272  884,614 809,671 897,891 999,892 ‐8%  ‐10% ‐12%EBITDA  169,127  188,152  208,679 187,427 210,113 235,824 ‐10%  ‐10% ‐12%PAT  90,930  96,871  103,705 94,538 99,680 109,178 ‐4%  ‐3% ‐5%EPS  11.0  11.7  12.6 11.5 12.1 13.2 ‐4%  ‐3% ‐5%

Source: Company, PhillipCapital India Research 

We  believe  during  FY16‐17,  operational  parameters  more  than  capacity  addition would be key to earnings of NTPC. With capacity addition of 3.5GW (parent) during FY15‐17E, we expect NTPC’s  regulated equity  to achieve 4% CAGR during FY15‐17E and  subdued  earnings  CAGR  of  4%  during  the  same  period  as  RoE‘s  drop  with implementation of new tariff norms.   We value NTPC at 1.8x FY17E regulated asset base and cash and liquid assets to arrive at target price of Rs 160. We initiate overage with neutral rating. At CMP of Rs 150, NTPC trades at 1.3x FY16E P/B. Key risks to our call  are    major  changes  in  tariff  regulation,  better  than  expected  operational parameters leading to higher incentive earnings .   

5%

15%

25%

35%

45%

FY11 FY12 FY13 FY14 FY15E FY16E FY17E

Dividend payout

8x

12x

16x20x

20

70

120

170

220

270

320

Apr/08 Apr/09 Apr/10 Apr/11 Apr/12 Apr/13 Apr/14

Rs P/E Band

1.5x

2x

2.5x

3x

50

100

150

200

250

300

350

Apr/08 Apr/09 Apr/10 Apr/11 Apr/12 Apr/13 Apr/14

Rs P/BV Band

NTPC has been able to maintain steady dividend payout.

Page 59: INSTITUTIONAL EQUITY RESEARCH India Utilitiesbackoffice.phillipcapital.in/...Utilities_Sector... · post FY18. Thus, we expect all India demand for coal to rise at 7% CAGR during

  

Page | 59 | PHILLIPCAPITAL INDIA RESEARCH 

NTPC INITIATING COVERAGE 

 SOTP Description  FY17 Regulated Equity (Parent)   Rs mn  411,005 Regulated Equity (Parent)   Rs  50 Multiple   x  1.8 Value Parent    Rs mn  724,120 Value Parent   Rs  88 Regulated Equity (JV)   Rs mn  49,814 Regulated Equity (JV)   Rs  6 Multiple   x  2 Value JV   Rs mn  87,764 Value JV   Rs  11 Cash   Rs mn  202,524 Cash   Rs  25 OTSS Bonds   Rs mn  32,884 OTSS Bonds   Rs  4 Value of equity   Rs mn  1,047,291 CWIP   35 Value of equity   160

  

 

Page 60: INSTITUTIONAL EQUITY RESEARCH India Utilitiesbackoffice.phillipcapital.in/...Utilities_Sector... · post FY18. Thus, we expect all India demand for coal to rise at 7% CAGR during

  

Page | 60 | PHILLIPCAPITAL INDIA RESEARCH 

NTPC INITIATING COVERAGE 

Financials  

Income Statement Y/E Mar, Rs mn  FY14  FY15e  FY16e FY17eNet sales  716,027 732,489  801,747 836,639Growth, %  11 2  9 4Total income  716,027 732,489  801,747 836,639Raw material expenses  ‐458,297 ‐487,783  ‐527,811 ‐540,933Employee expenses  ‐38,680 ‐36,624  ‐41,691 ‐43,505Other Operating expenses  ‐45,439 ‐47,085  ‐48,214 ‐51,819EBITDA (Core)  173,612 160,997  184,031 200,381Growth, %             10.5             (7.3)             14.3              8.9 Margin, %             24.2             22.0             23.0            24.0 Depreciation  ‐41,422 ‐47,561  ‐52,495 ‐55,866EBIT  132,190 113,435  131,536 144,516Growth, %                7.3           (14.2)             16.0              9.9 Margin, %             18.5             15.5             16.4            17.3 Interest paid  ‐24,066 ‐31,012  ‐44,531 ‐49,652Pre‐tax profit  139,176 109,984  118,106 127,932Tax provided  ‐29,299 ‐27,485  ‐24,924 ‐27,203Profit after tax  109,877 82,499  93,181 100,729Net Profit  109,877 82,499  93,181 100,729Growth, %                9.3           (24.9)             12.9              8.1 Net Profit (adjusted)      109,877         82,499        93,181     100,729 Unadj. shares (m)           8,245           8,245          8,245         8,245 Wtdavg shares (m)           8,245           8,245          8,245         8,245   Balance Sheet Y/E Mar, Rs mn  FY14 FY15e  FY16e FY17eCash & bank  153,114 163,690  174,043 202,415Debtors  52,201 53,401  58,450 60,994Inventory  53,734 54,969  60,166 62,785Loans & advances  158,933 162,587  177,960 185,705Other current assets  109,987 112,516  123,154 128,514Total current assets  527,968 547,163  593,774 640,412Investments  97,579 107,579  117,579 127,579Gross fixed assets  1,169,921 1,208,146  1,291,636 1,368,636Less: Depreciation  ‐448,812 ‐496,374  ‐548,869 ‐604,735Add: Capital WIP  448,887 671,230  807,740 950,740Net fixed assets  1,169,995 1,383,002  1,550,506 1,714,641Total assets  1,795,542 2,037,743  2,261,859 2,482,631           Current liabilities  239,072 242,687  257,898 265,560Total current liabilities  239,072 242,687  257,898 265,560Non‐current liabilities  698,317 986,783  1,143,783 1,300,783Total liabilities  937,389 1,229,470  1,401,680 1,566,343Paid‐up capital  82,455 82,455  82,455 82,455Reserves & surplus  775,699 725,819  777,724 833,834Shareholders’ equity  858,153 808,273  860,179 916,288Total equity & liabilities  1,795,542 2,037,743  2,261,859 2,482,631 Source: Company, PhillipCapital India Research  Estimates 

Cash Flow Y/E Mar, Rs mn  FY14  FY15e FY16e FY17ePre‐tax profit  139,176  109,984 118,106 127,932Depreciation  41,422  47,561 52,495 55,866Chg in working capital  ‐5,585  ‐5,003 ‐21,047 ‐10,604Total tax paid  ‐24,278  ‐24,485 ‐21,924 ‐24,203Cash flow from operating activities  150,735  128,058 127,629 148,991Capital expenditure  ‐210,962  ‐260,568 ‐220,000 ‐220,000Chg in investments  10,022  ‐10,000 ‐10,000 ‐10,000Cash flow from investing activities  ‐200,939  ‐270,568 ‐230,000 ‐230,000Free cash flow  ‐50,205  ‐142,510 ‐102,371 ‐81,009Debt raised/(repaid)  90,241  285,466 154,000 154,000Dividend (incl. tax)  ‐55,459  ‐42,296 ‐41,276 ‐44,619Other financing activities  ‐140  0 0 0Cash flow from financing activities  34,641  243,170 112,724 109,381Net chg in cash  ‐15,563  100,659 10,353 28,372  Valuation Ratios 

FY14  FY15e  FY16e FY17ePer Share data EPS (INR)             13.3             10.0             11.3            12.2 Growth, %                9.3           (24.9)             12.9              8.1 Book NAV/share (INR)           104.1             98.0          104.3         111.1 FDEPS (INR)             13.3             10.0             11.3            12.2 CEPS (INR)             18.3             15.8             17.7            19.0 CFPS (INR)             14.5             12.2             11.7            14.1 Return ratios           Return on assets (%)                7.4                5.3               5.7              5.6 Return on equity (%)             12.8             10.2             10.8            11.0 Return on capital employed (%)               8.5                6.1               6.4              6.3 Turnover ratios           Asset turnover (x)                0.6                0.5               0.5              0.5 Sales/Total assets (x)                0.4                0.4               0.4              0.4 Sales/Net FA (x)                0.7                0.6               0.5              0.5 Working capital/Sales (x)                0.2                0.2               0.2              0.2 Receivable days             26.6             26.6             26.6            26.6 Inventory days             27.4             27.4             27.4            27.4 Payable days           105.8           102.7          104.0         105.4 Working capital days             69.2             70.2             73.7            75.2 Liquidity ratios           Current ratio (x)                2.2                2.3               2.3              2.4 Quick ratio (x)                2.0                2.0               2.1              2.2 Interest cover (x)                5.5                3.7               3.0              2.9 Total debt/Equity (%)             78.3           118.4          129.2         138.1 Net debt/Equity (%)             60.4             98.2          108.9         116.0 Valuation           PER (x)             11.3             15.0             13.3            12.3 PEG (x) ‐ y‐o‐y growth                1.2             (0.6)               1.0              1.5 Price/Book (x)                1.4                1.5               1.4              1.3 EV/Net sales (x)                2.5                2.8               2.7              2.7 EV/EBITDA (x)             10.1             12.6             11.8            11.5 EV/EBIT (x)             13.3             17.9             16.5            15.9   

Page 61: INSTITUTIONAL EQUITY RESEARCH India Utilitiesbackoffice.phillipcapital.in/...Utilities_Sector... · post FY18. Thus, we expect all India demand for coal to rise at 7% CAGR during

INSTITUTIONAL EQUITY RESEARCH  

Page | 61 | PHILLIPCAPITAL INDIA RESEARCH 

Power Grid Corporation (PGCILIN) Increased focus on capitalization  INDIA | UTILITIES | Initiating Coverage 

 

  

28 April 2015 

Investment Rationale We initiate coverage on Power Grid Corporation of India Ltd (PGCIL) with a BUY rating and a target  price  of  Rs  176  based  on  FY17e  estimates.  PGCIL  is  play  on  transmission  capex offering  steady earning quality and  is  relatively  immune  to problems  faced by  sector. We believe PGCIL is well placed to capitalize on under investment in transmission sector.  Focus  shifts  to  increased  capitalization: Based on  investment approvals of Rs1025bn and cumulative order  awards of Rs925bn  till  FY15, we  expect  strong  capex  and  capitalization over the 12th plan. Our analysis of the Rs1,100bn capex  in the 12th plan (of which Rs820bn linked to generation projects) reveals that ~65% of these projects will commission by FY17; therefore  a  high  likelihood  of  PGCIL  achieving  its  target  capex.   We  note  transmission projects involves multiple beneficiary, implying 65% of project commissioning is satisfactory achievement.  Thus  we  build  Rs1,100bn  of  capex  in  our  estimates  in  line  with  the management  expectation  and    led  by  capitalization  of  Rs1015bn, we  expect  CAGR  22% growth in regulated equity over FY13‐17e.   Insulated  from  the problems  in  the power sector:   PGCIL  is  insulated  from  fuel  risks  that brought  the  power  sector  to  its  knees.  Being  a  transmission  utility,  it  bears  no  risk  of shortage  of  fuel  and  fuel  pricing. While  it  certainly  bears  a  degree  of  risk  for  payment collections  from  transcos and discoms, however PGCIL’s  receivables are covered under LC ensuring timely collection. Also, in the recent past it has curtailed power supply to discoms where payments have been delayed to ensure timely payments.   Equity dilution sufficient to meet 12th plan capex: PGCIL diluted 13% equity in FY14 to meet the revised capex target of Rs 1.1tn as compared to Rs 1tn previously. PGCIL raised Rs 53bn; this combined with operating cash flows of Rs 100‐120bn during FY15‐17 leads us to believe that PGCIL would be able to meet its equity requirements. The capex of PGCIL would remain stable during  FY14‐17 but operating  cash  flows will  increase  led by  increase  in  regulated equity  base; hence we  believe  that  PGCIL would  be  able  to meet  its  equity  requirement without further dilution in the 12th plan.  Earnings and Valuations: We model a 19% CAGR in EPS over FY14‐17E and expect regulated asset base to grow at a CAGR of 21% on back of higher capex and capitalization. The stock currently trades at 1.7x Y17e P/B and 10x FY17e EPS. We value stock at 1.6x regulated equity and add liquid assets to arrive at target price of Rs 176. We initiate coverage with BUY rating on the stock.  Key  risks  to  our  BUY  call:  Key  risks  to  our  BUY  call  are:  a)  Weaker  than  expected capitalization due to right of way and/or delay In generation projects that leads to a further dilution  of  equity  to  fund  the  ongoing  capexprogramme,  b)  RoE’s may  shrink  as  the mix changes  in the 13th plan to competitive bid projects, c) flattening of capex  in the 13th plan which would lead to lower growth in earnings. In our view, however it is too early to take a call on the same and we await more clarity on new projects being bid out to understand the potential impact on PGCIL. 

BUY CMP RS 150 TARGET RS 176 (+18%)  COMPANY DATA O/S SHARES (MN) :  5262MARKET CAP (RSBN) :  763MARKET CAP (USDBN) :  12.352 ‐ WK HI/LO (RS) :  159 / 102LIQUIDITY 3M (USDMN) :  6.4PAR VALUE (RS) :  10 SHARE HOLDING PATTERN, % PROMOTERS :  57.9FII / NRI :  27.9FI / MF :  7.7NON PROMOTER CORP. HOLDINGS :  2.6PUBLIC & OTHERS :  3.9 PRICE PERFORMANCE, % 

  1MTH 3MTH 1YRABS  ‐1.4 ‐2.4 38.5REL TO BSE  1.1 3.8 18.4 PRICE VS. SENSEX 

 Source: Phillip Capital India Research  KEY FINANCIALS Rs mn  FY15E FY16E FY17ENet Sales  174,387 212,133 246,405EBIDTA  150,440 184,593 214,734Net Profit  51,989 64,789 75,838EPS, Rs                9.9            12.4            14.5 PER, x             15.1            12.1            10.3 EV/EBIDTA, x             11.3              9.8              8.9 P/BV, x                2.1              1.9              1.7 ROE, %              14.4            16.2            17.0 Debt/Equity (%)           250.9         261.8         258.8 

Source: PhillipCapital India Research Est.  AnkurSharma(+ 9122 6667 9759) [email protected]  HrishikeshBhagat(+ 9122 6667 9986) [email protected] 

60

80

100

120

140

160

Apr‐11 Jun‐12 Aug‐13 Oct‐14Power Grid BSE Sensex

Page 62: INSTITUTIONAL EQUITY RESEARCH India Utilitiesbackoffice.phillipcapital.in/...Utilities_Sector... · post FY18. Thus, we expect all India demand for coal to rise at 7% CAGR during

  

Page | 62 | PHILLIPCAPITAL INDIA RESEARCH 

POWER GRID CORPORATION INITIATING COVERAGE 

Strong capex and capitalization  to continue backed by strong investment approvals and orders  Our investment thesis for PGCIL is based on the premise that capex and capitalization would continue to remain strong over the 12th plan. We believe India‘s massive under investment  in transmission capacity      (~40 GW  inter regional  transmission capacity) and robust capacity addition of 88 GW expected in 12th plan will require investment in evacuation facility. We believe PGCIL is well placed to capitalize on this opportunity and estimate robust pace of capitalization to continue driven by:  a. Investment approvals by the board of 93% of targeted spending of Rs1.1tn  in 

the  12th  plan  done  by March’15. We  however,  do  note  that  board  approvals have  slowed down over  the past  few  years  (ordering  in  FY13  at Rs126bn  and Rs78bn in FY14); this could be due to lack of clarity on generation projects likely to be commissioned  in the  last few years of the 12th plan and the 13th plan. An increased focus on capitalization has also meant that both investment approvals and  ordering  have  started  to  slow  down. We  expect  ordering  to  pick  up  led improved clarity on 13th plan 

Investment approvals by the board slows down as focus shifts to commissioning (Rsbn) 

 Source: Company, PhillipCapital India Research FY15 Includes 196 bn pertaining to 13th plan     b. 90% of the orders have already been placed.   PGCIL has already placed orders 

worth Rs972bn – 90% of its targeted capex in the 12th plan by FY14.  The focus has now shifted  to execution of  these orders on a  timely basis –  to ensure  the same,  PGCIL  has  introduced  new  bidding  norms  for  vendors  to weed  out  the weak players and also restricted new orders to vendors who have not completed 50%  of  existing  order  backlog.  Further  with  focus  on  execution,  PGCIL  has ensured payment to vendors only on erection. 

 

260 

135 

211 

430 

126 

78 

242 

100 

200 

300 

400 

500 

FY09 FY10 FY11 FY12 FY13 FY14 FY15

Rs bn

Page 63: INSTITUTIONAL EQUITY RESEARCH India Utilitiesbackoffice.phillipcapital.in/...Utilities_Sector... · post FY18. Thus, we expect all India demand for coal to rise at 7% CAGR during

  

Page | 63 | PHILLIPCAPITAL INDIA RESEARCH 

POWER GRID CORPORATION INITIATING COVERAGE 

Ordering and capex incurred by PGCIL – FY03‐15e 

 Source: Company, PhillipCapital India Research Estimates  We expect capitalization to stabilize at ~Rs200‐250bn during FY15‐17E each year as orders  placed  in  earlier  years  are  commissioned  and move  from  CWIP  into  fixed assets.  During  FY07‐14E  PGCIL’s  GFA  grew  19%  CAGR,  however  lead  by  focus  on capitalization  we  expect  GFA  to  grow  19.5%  CAGR  during  FY14‐17E.  We  expect accrual to CWIP to reduce as capitalization improves.  Gross fixed assets grow aided by increased commissioning (Rsbn) 

 Source: Company, PhillipCapital India Research Estimates  Gap between capitalization and capex to reduce (bn) 

 Source: Company, PhillipCapital India Research Estimates 

0

50

100

150

200

250

300

FY03 FY04 FY05 FY06 FY07 FY08 FY09 FY10 FY11 FY12 FY13 FY14 FY15

Capex Orders

0

200

400

600

800

1000

1200

1400

1600

1800

FY07 FY08 FY09 FY10 FY11 FY12 FY13 FY14 FY15E FY16E FY17E

GFA Capitalisation

0

10

20

30

40

50

60

70

80

90

Q113 Q213 Q313 Q413 Q114 Q214 Q314 Q414 Q115 Q215 Q315

Capex  Capitalisation

Page 64: INSTITUTIONAL EQUITY RESEARCH India Utilitiesbackoffice.phillipcapital.in/...Utilities_Sector... · post FY18. Thus, we expect all India demand for coal to rise at 7% CAGR during

  

Page | 64 | PHILLIPCAPITAL INDIA RESEARCH 

POWER GRID CORPORATION INITIATING COVERAGE 

c. Analysis of Rs1, 100bn of spending on  individual projects  reveals  that 65% of the generation projects are  largely on  track. PGCIL  is  targeting  capex of Rs 1, 100bn in the 12th plan that will earn a regulated return of 15.5% ROE.  Of this Rs 1,100bn,  Rs820b  is  towards  evacuation  of  power  from  new  generation capacity,Rs180b for strengthening of existing transmission systems and Rs 100bn for  competitive  bid  projects,  new  projects  allocated  by  GoI,  Green  energy corridor, intrastate projects etc. 

 Our  analysis of  the Rs1,100bn  capex  in  the 12th plan  (of which Rs820bn  linked  to generation projects) reveals that ~64% of these projects would commission by FY17; implying a higher likelihood of PGCIL achieving its target capex.   Planned Capex in 12th plan of Rs1, 100bn; ~50% towards HCTC for IPP’s Description  RsbnCentral government generation schemes  250UMPP – Sasan, Mundra, Krishnapatnam  90HCTC corridors – IPP  480Grid Strengthening  180Others  100Total planned capex (Rsbn)  1,100

Source: Company, PhillipCapital India Research  Our analysis highlights that: a. Two of the three UMPP’s (12GW of total capacity for the 3 UMPP’s) have started 

generation with a substantial portion of the transmission works for each of these lines also getting completed. However,  the  likelihood of Krishnapatnam getting commissioned within the 12th plan is extremely low. 

b. Of the central government projects scheduled to commission in the 12th plan, we expect  ~70% of  the projects  to  be  commissioned within  the  12th  plan.    PGCIL intends to spend Rs250bn on these transmission projects. 

c. We  estimate  that  64%  of  the  total  generation  capacity  envisaged  to  be evacuated  via  the HCTC’s  should  get  commissioned by  FY17.We note    captive coal  based  capacity  of  IPP’s  linked  to  these  transmission  corridor    stands  at 4.5GW and could speed up if coal auction  takes place in time. 

 Status and expected completion of HCTC linked generation projects Description   Planned  % commissioned by FY17 % delayed of total HCTCIPPs Total  58,973  64% 36%HCPTC I, Orissa  10,090  53% 8%HCPTC II, Jharkhand  4,540  38% 5%HCPTC III, Sikkim  2,162  72% 1%HCPTC IV, MP and Chhattisgarh  4,370  49% 4%HCPTC V, Chhattisgarh  15,485  76% 6%HCPTC VI, Andhra Pradesh  4,320  86% 1%HCPTC VII, Tamil Nadu  2,520  100% 0%HCPTC VIII,Tamil Nadu  3,960  33% 4%HCPTC IX, Various Regions  11,526  68% 6%

Source: Company, PhillipCapital India Research Estimates 

Page 65: INSTITUTIONAL EQUITY RESEARCH India Utilitiesbackoffice.phillipcapital.in/...Utilities_Sector... · post FY18. Thus, we expect all India demand for coal to rise at 7% CAGR during

  

Page | 65 | PHILLIPCAPITAL INDIA RESEARCH 

POWER GRID CORPORATION INITIATING COVERAGE 

Relatively insulated from the problems in the power sector PGCIL  is relatively  insulated from the problems currently plaguing the power sector. The  three  key  issues  hurting  the  power  sector  are  those  of  lack  of  fuel  supply, delayed  payments  from  customers,  (State  discoms)  and  non  ‐  remunerative  PPA’s signed with customers that need to be revised. PGCIL is not exposed to any fuel risk as it is a transmission utility that earns a fixed post tax  return of 15.5% on its regulated equity.  As we highlight below, PGCIL has been able to efficiently collect  its receivables on a timely basis.  It allows 2 month of credit (60 days  is  the billing/collection  cycle)  and  its debtor days  are  currently  at 41 days of sales. Payments beyond 2 months attract a surcharge of 18%.  Debtor collection remains very impressive with Rs6bn >60days The  average  monthly  billing  by  PGCIL  to  its  customers  is  ~Rs12bn.  However,  its debtors as of Dec’14 stood at Rs 21bn, of which 4bn are outstanding for more than six months. We note PGCIL is relatively well placed on receivables front as compared to other utilities  that have  faced payment delays. Further  receivables  to PGCIL are covered by letter of credit pursuant to one time settlement scheme.  In the past, PGCIL has also curtailed supplies to discoms where payments have been delayed as was done with BSES Rajdhani and BSES Yamuna in March’ 13 on delays in release of payments to PGCIL.  Debtor days lower than normative 

 Source: Company, PhillipCapital India Research Estimates  Delayed capacity will not derail transmission capex Although  we  do  acknowledge  the  reforms  under  taken  in  power  sector  such  as signing of FSA, compensatory tariffs for unremunerative PPA, automatic pass through of  imported  coal  cost  in  lieu  of  domestic  shortage,  FRP  to  address weak  discom financials,  however we  expect health  of  sector  to  improve  gradually.  Even  though liberal  environmental  clearance  norms  will  aid  coal  output,  however  limited evacuation facility will delay pace of capacity addition. The delayed capacity addition does not impact PGCIL as under Bulk Power Transmission Agreement (BPTA)  signed with  IPPs,   as per which  IPPs are under obligation bear  the  transmission charges as approved by CERC from the effective date of LTA. 

88 

113 

138 

84 

41  38  40  40  40 

20 

40 

60 

80 

100 

120 

140 

160 

FY09 FY10 FY11 FY12 FY13 FY14 FY15E FY16E FY17E

Debtor days

Transition from Postage Stamp to PoC method for tariff calculation lead to higher receivables as same was challenged by few states. 

Page 66: INSTITUTIONAL EQUITY RESEARCH India Utilitiesbackoffice.phillipcapital.in/...Utilities_Sector... · post FY18. Thus, we expect all India demand for coal to rise at 7% CAGR during

  

Page | 66 | PHILLIPCAPITAL INDIA RESEARCH 

POWER GRID CORPORATION INITIATING COVERAGE 

Equity dilution adequate  to meet 12th plan equity requirements PGCIL has capex plan of Rs 1.1tn in 12th plan. It has already incurred cumulative capex of Rs 587bn  till 3QFY15. Hence  it would  incur additional  capex of Rs 600bn during FY15E‐17E  period  implying  equity  requirements  of  Rs  180b.  Also  there  would  be some  additional  equity  infusion  required  in  the  projects  were  higher  debt  was deployed during FY12‐13 to bring it to normative rate of 70:30.  We estimate PGCIL to generate operational cash flows of Rs 100‐150b during FY15‐17e; additionally it raised ~ Rs 54bn in FY14 through FPO. Hence we believe that even after maintaining  the dividend payout  ratio  at  current  rates  (unlikely  to  reduce)  it would be able to meet its equity requirement at least for the 12th plan  Cash flow calculation for dilution purposes Cash flow calculation for dilution purposes  FY15e FY16e FY17eCash flow from operations        121,841        131,238        150,215 Less: Dividends  (18224) (22710) (26583)Less: Debt repayment  (36796) (43531) (56184)Add: Cash available         44,175          40,398          75,437 Cash available after financing activities       110,996        105,395        142,885  Equity commitment needed for funding capex         72,000          67,500         67,500 Shortfall/(Surplus) if any (vs target capex)        (38,996)        (37,895)       (75,385)

Source: Company, PhillipCapital India Research Estimates  Net D:E ratio 

 Source: Company, PhillipCapital India Research Estimates  PGCIL net Debt  to Equity  ratio would  improve post  the  fund  raising undertaken  in FY14. We expect the net Debt to equity ratio to  increase during FY15‐17  led by the nature of the business (capex intensive) but we estimate that it would stabilize ~ 2.3‐2.4:1 due  to 1)  flat  growth  in  capex:  Flat  capex  target during  FY15‐17;  , 2) Better capitalization: We estimate PGCIL  to  continue  the  capex  and  capitalization  ratio  it had in FY12‐13 and 3) Increase in regulated equity: The regulated equity rising every year would help  in  improving  the operating cash  flows and with capex stabilizing  it would be positive for PGCIL. 

1.3 1.4  1.4 

1.7 

1.5 

1.8 

2.0 

1.7 

2.2 

2.5 

2.3 2.4 2.4 

2.4 

1.0 

1.2 

1.4 

1.6 

1.8 

2.0 

2.2 

2.4 

2.6 

2.8 

FY04 FY05 FY06 FY07 FY08 FY09 FY10 FY11 FY12 FY13 FY14 FY15E FY16E FY17E

IPO

FPO

FPO

Net D:E ratio stabilises reduces the risk of

further dilution

Page 67: INSTITUTIONAL EQUITY RESEARCH India Utilitiesbackoffice.phillipcapital.in/...Utilities_Sector... · post FY18. Thus, we expect all India demand for coal to rise at 7% CAGR during

  

Page | 67 | PHILLIPCAPITAL INDIA RESEARCH 

POWER GRID CORPORATION INITIATING COVERAGE 

Payout ratio at ~ 30%; suboptimal leading to strain on balance sheet Since its listing PGCIL has maintained average dividend payout of 30% leading to total outgo of Rs 70bn. We note PGCIL’s dividend policy has placed unnecessary strain on its capital structure. As a promoter it is necessary for government to respect PGCIL’s equity and also consider its growth plan. Higher dividend payout although helped GoI in short  term  to meet  its budget shortfall, however  in  long  run  it has  led  to equity shortfall for PGCIL  leading to dilution on consistent basis. A much rational approach would be to create value and accrue higher proceeds through disinvestment at higher value. We note based on our profit assumption, overall dividend payout could be ~Rs 70bn over FY15‐17E at 30% payout.  Payout ratio maintained at 30%; Yield improves 

 Source: Company, PhillipCapital India Research Estimates  Higher dividend payout leading to dilution Date   Issue Price  Amount   (Rsbn) Comment FY08                            52                  20  IPO Funding FY08‐11                  17  Dividend Paid FY11                            90                  38  FPO proceeds FY11‐13                  33  Dividend Paid FY14                            90                  54  FPO proceeds FY14  15 Dividend Paid 

Source: Company, PhillipCapital India Research Estimates 

0.0%

0.2%

0.4%

0.6%

0.8%

1.0%

1.2%

1.4%

1.6%

1.8%

2.0%

10%

15%

20%

25%

30%

35%

40%

FY07 FY08 FY09 FY10 FY11 FY12 FY13 FY14

Payout Yield

Page 68: INSTITUTIONAL EQUITY RESEARCH India Utilitiesbackoffice.phillipcapital.in/...Utilities_Sector... · post FY18. Thus, we expect all India demand for coal to rise at 7% CAGR during

  

Page | 68 | PHILLIPCAPITAL INDIA RESEARCH 

POWER GRID CORPORATION INITIATING COVERAGE 

Marginal Impact under new norms The  tariff  regulation  2015‐19  has  tightened  operational  parameters  for  regulated utilities; however  its  impact on transmission utilities  is relatively  lower as compared to generation utilities. Under new norms, normative availability factor for fixed cost recovery and incentive has been raised and also O&M norms tightened.    Escalation allowed under new tariff regulation is lower as compared to earlier norms 

FY10  FY11  FY12  FY13  FY14 FY15 FY16 FY17 FY18 FY19Sub station 765kV  7.34  7.76  8.20  8.67  9.17 8.44 8.72 9.01 9.31 9.62escalation  5.7%  5.7%  5.7%  5.8% ‐7.9% 3.3% 3.3% 3.3% 3.3%400kV  5.24  5.54  5.86  6.19  6.55 6.03 6.23 6.44 6.65 6.87escalation  5.7%  5.7%  5.7%  5.7% ‐7.9% 3.3% 3.3% 3.3% 3.3%220kV  3.67  3.88  4.10  4.33  4.58 4.22 4.36 4.51 4.66 4.81escalation  5.7%  5.7%  5.7%  5.7% ‐7.9% 3.3% 3.3% 3.3% 3.3%132kV and Belo  2.62  2.77  2.93  3.10  3.27 3.02 3.12 3.22 3.33 3.44escalation  5.7%  5.7%  5.7%  5.7% ‐7.9% 3.3% 3.3% 3.3% 3.3%

Source: Company, PhillipCapital India Research Estimates  Similarly O&M norms are tightened for other components of transmission system viz AC/HVDC lines and HVDC station.  Normative Transmission Availability Factor 

__________2010‐14__________ _________2015‐19_________TAF for fixed cost 

recovery  TAF for incentiveTAF for fixed cost 

recovery TAF for incentiveAC system  98  98 98 98.5HVDC bi‐pole links  92  92 95 96HVDC back‐to‐back stations  95  95 95 96

Source: Company, PhillipCapital India Research Estimates   The  transmission  availability norms have been  tightened under new  regulation  for HVDC bi‐pole links and norms for incentive recognition are higher as compared to old regulation.  Further new  regulation has  capped  incentive  to maximum  transmission availability of 99.75%.  Due to removal of STOA  income coupled with tightening of norms, we expect PGCIL to accrue core RoE of 16% as against 17‐19% under earlier norms.  Core RoE 

Source: Company, PhillipCapital India Research Estimates 

02468

1012141618202224

FY10 FY11 FY12 FY13 FY14 FY15E FY16E FY17E

Core RoE (%)

Page 69: INSTITUTIONAL EQUITY RESEARCH India Utilitiesbackoffice.phillipcapital.in/...Utilities_Sector... · post FY18. Thus, we expect all India demand for coal to rise at 7% CAGR during

  

Page | 69 | PHILLIPCAPITAL INDIA RESEARCH 

POWER GRID CORPORATION INITIATING COVERAGE 

Competitive bid to change the mix in 13th plan Acquiring competitive bid projects with decent RoE’s remains the key: PGCIL would  need  to  acquire  the  projects  through  competitive  bid  process  in  the 13th  plan  instead  of  nomination  basis.  It would  impact  the  share  of  PGCIL  in  the central transmission projects (earlier had a monopoly). Secondly the RoE’s would also reduce if competition remains intense.  We  note  through  tariff  based  competitive  bidding  7  projects were won  by  PGCIL. These  include  1)  Vemagiri  A  Transmission  Sytem,2)  Vizag  Transmission System,3)NRSS XXXI (A)  4)Nagapatinam‐Madhugiri Project 5) Unchahar Transmission 6) Gadarwara transmission and 7) Vindhyachal V transmission. The Vemagiri project has been put on hold on CERC orders due  to  lack of  clarity over  gas based plants associated with the projects. Talcher II and North Karanpura Transmission that were earlier  awarded  to  Reliance  Transmission  are  now  awarded  to  PGCIL  on  cost  plus basis. Also ATS Associated with project of Nagarjuna Power  is awarded to PGCIL on cost plus basis. Also additional TN HVDC  line was awarded  to PGCIL on nomination basis.  List of Projects Awarded Project  Developer  No. of bidders (L1)  L2 L3East North Interconnection transmission project  Sterlite Technologies  8 1,188  1,676 2,400Jabalpur Transmission project  Sterlite Transmission Projects  33 1,421  1,441 1,499Bhopal Dhule Transmission Co Ltd  Sterlite Transmission Projects  22 1,995  2,185 2,449Nagapattinam‐Madhugiri  PGCIL  22 987  1,529 2,082Patran Transmission Co. Ltd.  Techno Electric and Engineering  7 274  398 595Transmission System for Part ATS of RAPP U‐7 & 8  Sterlite Grid  10 365  523 385Eastern Region System Strengthening Scheme‐VII  Sterlite Grid  7 589  1,624ERSS VI  EsselInfraprojects Ltd  10 1,174  1,295 1,480Talcher‐II Transmission Co Ltd  PGCIL    1,440 North Karanpura Transmission Co Ltd  PGCIL    2,580 Raichur Sholapur Transmission Co Ltd  Patel Engg, Simplex Infra & BS Transcomm 35 293  315 316Vemagiri A Transmission System Ltd  PGCIL  1,197 Vizag Transmission Ltd  PGCIL  14 2,311  2,590 3,888Kudgi Transmission Ltd  L&T IDPL  11 1,796  2,130 2,186NRSS XXiX  Sterlite Grid  6 4,377  4615 NANRSS XXXI (A)  PGCIL  7 594  598 818NRSS XXXI (B)  EsselInfraprojects Ltd  7 887  963 987Unchahar Transmission  PGCIL  6 167  296Vindhyachal V  PGCIL  8 2109  2182 2646Gadarwara STPS (Part A)  PGCIL  NA NA  NA NAGadarwara STPS (Part B)  PGCIL  NA NA  NA NA

Source: Company, PhillipCapital India Research Estimates  Our analysis of Vizag Transmission, Unchahar Transmission, Nagapatinam ‐Madhugiri and NRSS XXXI  (A)  imply weak RoE due  to competitive pressure. We get a negative value  from these projects however PGCIL management  indicate that they would be able  to  earn  decent  RoE’s  from  the  same  led  by  better  execution  capability  and operational efficiency.   However we do note that competitive  landscape has changed significantly since the time first project was awarded in 2010. The number of participants has reduced from 20+  to 7‐8. We note  these projects  form  very  small proportion of extant projects. Thus  it  is too early to take call on competitive bid projects and their contribution  is very negligible to impair RoE in 12th plan.     

Page 70: INSTITUTIONAL EQUITY RESEARCH India Utilitiesbackoffice.phillipcapital.in/...Utilities_Sector... · post FY18. Thus, we expect all India demand for coal to rise at 7% CAGR during

  

Page | 70 | PHILLIPCAPITAL INDIA RESEARCH 

POWER GRID CORPORATION INITIATING COVERAGE 

Project Analysis Vemagiri  Vizag Nagapattinam‐Madhugiri

Cost of project  INRm         13,000         12,777                         10,250 D:E               4.0               4.0                               4.0 Debt  INRm         10,400         10,222                           8,200 Equity  INRm           2,600           2,555                           2,050 O&M exp  %             12.0             12.0                             12.0 Escalation  %               5.0               5.0                               5.0 Debt repayment  No. of years                15                15                             15.0 Depereciation  %               4.0               4.0                               4.0 Interest rate  %               7.0               7.0                               7.0 Expected CoD  Year   FY16   FY16   FY16 Discounting factor  %             13.0             13.0                             13.0 NPV  INRm          (2,213)           2,209                         (1,595)

Source: Company, PhillipCapital India Research Estimates  Flattish capex growth estimated  in 13thplancapex v/s 2x growth  in previous 5 year plans The total transmission capability expected in the 13th plan is ~ Rs 2.3tn out of which the inter‐state capex estimate is ~ Rs 1.35tn. Hence even if PGCIL is able to win 70% of the same it would have flattish capex growth due to higher base during 13th plan as  compared  to  capex  of  almost  doubling  in  the  previous  5  year  plans.  PGCIL  has under taken various new initiatives which may help in increasing the capex target and improve the growth visibility however there  is  lack of clarity on the same. However we note 13th plan capex could be higher as investment in transmission sector would be skewed towards high value 765kV and HVDC.  Capex almost grew 2x in every 5 year plan 

Source: Company, PhillipCapital India Research Estimates  

1.7 

2.2 

2.9 

2.0 

0.0

0.5

1.0

1.5

2.0

2.5

3.0

3.5

200 

400 

600 

800 

1,000 

1,200 

8th  9th 10th 11th 12th

Capex (Rs bn) Growth

Page 71: INSTITUTIONAL EQUITY RESEARCH India Utilitiesbackoffice.phillipcapital.in/...Utilities_Sector... · post FY18. Thus, we expect all India demand for coal to rise at 7% CAGR during

  

Page | 71 | PHILLIPCAPITAL INDIA RESEARCH 

POWER GRID CORPORATION INITIATING COVERAGE 

Other potential opportunities  for PGCIL  to drive  the  growth  in  13th plan • Green  Energy  Corridor:  PGCIL  has  prepared  a  detail  report  on  Green  Energy 

Corridor with  investment  capability  of  ~Rs430bn  to  upgrade  and  develop  the transmission  system  for  adequate  supply  of  renewable  energy.  Green  Energy Corridor  opportunity  for  interstate  transmission  network  stands  at  Rs224bn. These projects can be taken up on bidding basis, as no new projects can now be awarded  to  PGCIL  on  nomination  basis.  However,  the Ministry  of  Power  can include  the  scope  of  such  work  under  "urgent/important"  projects  and  can override provision to hand over the work to PGCIL. Currently, there is no visibility on  the  same.  The  project  already  has  Euro1b  loan  from  kfw  Bankengruppe (banking group) under consideration. The approval of the project  is expected  in FY15.  It  could  be  a  big  boost  for  PGCIL  if  the  project  is  awarded  to  it  on nomination basis. 

 • Telecom:  PGCIL  diversified  into  Telecom  business  under  the  brand  name 

‘POWERTEL’  to  expand  its  revenue  stream  by  installing  overhead  optic  fibre network using OPGW (Optical Ground Wire), leveraging its existing countrywide transmission  infrastructure.  It has an all  India Broad Band Telecom Network of about 29,640 km, providing connectivity to all metros, major cities, towns, State capitals  including remote areas of North‐Eastern Region, Jammu & Kashmir etc. and  covering  about  317  Points  of  Presence  (PoPs)  across  the  country.  Key projects undertaken under  this arm  include National Knowledge Network with the purpose to provide a unified high speed network backbone  for educational institutions  in  India  and  National  Optical  Fiber  Network  (NOFN)  to  provide connectivity to all Gram panchayats in India 

 • JV with states: PGCIL has entered  in  to  JV’s with  two states –Bihar and Odhisa 

with  share  of  50%.  Total  planned  capex  for  2  JVs  is  estimated  at  Rs88bn  at normative D:E ratio equity requirement would be ~Rs 26bn limiting PGCIL scope of  investment    to  INR13b  (50%). PGCIL  is also under process  to  form  JV’s with other states. It would benefits the state also  in 1) Better execution visible from PGCIL track report, 2) Operational synergy as it has the broader network set up throughout  the  country  3)  Financial  synergy  as most of  the  SEB’s  are  already going  through  restructuring process or  suffering  from poor  financial conditions hence  JV  would  help  in  getting  loans.  Hence  the  JV  structure  provide  good growth opportunities however we expect only the financially distressed SEB’s to form JV’s with PGCIL.  

 • Other opportunities: Smart Grid pilot project developed  in Pondicherry, Desert 

Power assessing potential in states like J&K, HP, Gujarat and Rajasthan. Residuals of  High  speed  transmission  corridor  projects.  Distribution  opportunities  in various states. Although these all opportunities are at nascent stage and needs further clarity. 

 • Consultancy:  Under  consultancy  PGCIL  undertake  domestic  and  international 

assignments. In domestic PGCIL assist the State Utilities in development of their Transmission & Distribution (T&D) infrastructure. Also it undertake international assignments in more than 15 countries 

Page 72: INSTITUTIONAL EQUITY RESEARCH India Utilitiesbackoffice.phillipcapital.in/...Utilities_Sector... · post FY18. Thus, we expect all India demand for coal to rise at 7% CAGR during

  

Page | 72 | PHILLIPCAPITAL INDIA RESEARCH 

POWER GRID CORPORATION INITIATING COVERAGE 

Earnings and Valuation Strong capitalization to drive earnings We model  19%  EPS  CAGR  over  FY15‐FY17  driven  by  22%    CAGR  in  the  regulated equity  from  Rs257bn  in  FY14  to  Rs461bn  in  FY17e  as  we  estimate  annual capitalization  to grow along with  the  increase  in capex. We estimate  core RoE’s  to decline  to 15.8 %  from erstwhile 18% driven by  tightening of operating norms and lower STOA income.  Growth in regulated equity to drive earnings  

Source: Company, PhillipCapital India Research Estimates 

Higher RoE led by contribution from new capacity We note that reported ROE in FY13 is at 15% despite 30% of its CWIP (Rs350bn) being funded by equity which does not earn any return. This is possible on account of higher ROE’s being earned in its other segments – namely telecom and consultancy.    ROE’s at 16%‐17% despite high CWIP on higher ROE’s in telecom and consultancy 

Source: Company, PhillipCapital India Research Estimates 

   

50 

100 

150 

200 

250 

300 

350 

400 

450 

500 

FY09 FY10 FY11 FY12 FY13 FY14 FY15E FY16E FY17E

Regulated Equity (Rs bn)

10%

11%

12%

13%

14%

15%

16%

17%

18%

FY10 FY11 FY12 FY13 FY14 FY15E FY16E FY17E

RoE

Page 73: INSTITUTIONAL EQUITY RESEARCH India Utilitiesbackoffice.phillipcapital.in/...Utilities_Sector... · post FY18. Thus, we expect all India demand for coal to rise at 7% CAGR during

  

Page | 73 | PHILLIPCAPITAL INDIA RESEARCH 

POWER GRID CORPORATION INITIATING COVERAGE 

Cash generation to improve We expect cash generation to  improve  for PGCIL as capitalization gathers pace and new capacity adds to profits. Accordingly we expect PGCIL to accrue FCFE of Rs  47bn, implying cash flow yield of ~6% (FY17E).    FCFE 

Source: Company, PhillipCapital India Research Estimates 

 

(30)

(20)

(10)

10 

20 

30 

40 

50 

60 

70 

FY10 FY11 FY12 FY13 FY14 FY15E FY16E FY17E

bn

FCFE

Page 74: INSTITUTIONAL EQUITY RESEARCH India Utilitiesbackoffice.phillipcapital.in/...Utilities_Sector... · post FY18. Thus, we expect all India demand for coal to rise at 7% CAGR during

  

Page | 74 | PHILLIPCAPITAL INDIA RESEARCH 

POWER GRID CORPORATION INITIATING COVERAGE 

Key Risks Synchronization Risk with Generation Projects: Lack of clarity over fuel coupled with issues over PPA due to weak financial health of discoms has  resulted  in significant delay  in capacity addition.   This has often  led  to situation  wherein  transmission  system  has  come  ahead  of  generation  project. Continued delay in generation capex could also put risk on PGCIL’s capex. In order to mitigate  this  risk,  PGCIL  has  signed  agreement  with  generators  to  recover transmission  charges  from  generators  from  the  date  of  actual  commissioning  of transmission assets.  Once PPA’s are signed, then applicable transmission charges are to be paid by respective beneficiaries.   Revenue Risk PGCIL’s  revenue  recognition  is  based  on  CERC  norms  that  introduce  Point  of Connection (PoC) method for collection of transmission charges. States namely Bihar, Odisha,  West  Bengal,  Maharashtra  and  Jharkhand  had  challenged  the  aforesaid sharing methodology  in  the  court of  law  and  final decision  is  awaited.  In  terms of interim  order  of  the  Delhi  High  Court,  all  the  above  States  are  however making payment  as per  said Regulation, but under protest. Also CERC  regulation  for  tariff block 2015‐19 has classified  land acquisition as controllable factor  implying any cost escalation on account of that would not be allowed as pass through. This could impair RoE under upcoming projects.   Tariff based competitive biddings:  As  discussed  earlier,  the  Tariff  based  competitive  bidding  norms  introduced  has challenged monopoly status of PGCIL and exposed it to competitive risk. However we note  competitive  intensity has dropped  significantly over past  few years as private players  have  faced  execution  issues  due  to  irrational  bid.  We  note  limited maneuverability  to  accrue  incentive  in  transmission  projects  as  compared  to generation projects has reduced participation from private players. Further we note the  competitively  bid  projects  would  form  very  small  portion  of  PGCIL’s  project portfolio during FY15‐17E.    Right of Way: The  enactment  of  Land Acquisition Act  and  R&R Act  (2011)  has  lead  to  execution difficulty  for PGCIL.  Further obtaining  forest  clearance under  Forest  (Conservation) Act,  1980  involves  a  steep  and  tedious  hierarchy.  Apart  from  the  legislative framework,  social  issues  like  RoW  are  contributing  to  prolonged  delays  in  the commissioning of projects.   

Page 75: INSTITUTIONAL EQUITY RESEARCH India Utilitiesbackoffice.phillipcapital.in/...Utilities_Sector... · post FY18. Thus, we expect all India demand for coal to rise at 7% CAGR during

  

Page | 75 | PHILLIPCAPITAL INDIA RESEARCH 

POWER GRID CORPORATION INITIATING COVERAGE 

Valuation At CMP of Rs 150, PGCIL  trades  at 1.6x  FY17 P/B  and 10x  FY17E. With  a 14% EPS CAGR over FY14‐FY17 driven by 22%  increase  in the regulated equity from Rs213bn to Rs461bn  in FY17, PGCIL  is our  top pick  in  the power utilities. We value PGCIL at 1.6x  regulated book  and  add  cash  and  liquid  assets  to  arrive  at  target price of Rs 176.We  initiate  coverage on  the  stock with a BUY  rating. Key  risks  include a  sharp slowdown  in capex and/or capitalization and  increase  in competition  in competitive bidding.  SOTP Description   FY17E    Multiple   Value(Rs mn)   Per Share Regulated Equity (Operational Project )            461,244               1.6           753,431              144 Equity in JV project                3,307               1.6               5,402                  1 OTSS Bond                3,786                  1               2,740                  1 Consultancy and Telecom(PAT)                3,487                10             34,873                  7 Cash (ex ‐cash held for Consultancy)              37,644                  1                  7 CWIP‐Equity invested              89,184                  1                17 Total value per share                    176 

Source: Company, PhillipCapital India Research Estimates  PGCIL vs 10 years Bond 

 Source: Company, PhillipCapital India Research Estimates   We are marginally above consensus estimates. Description  __________PC Estimates_________  ___________Consensus___________ __________Deviations__________(Rs mn)  FY15E  FY16E  FY17E  FY15E FY16E FY17E FY15E  FY16E  FY17ESales         174,387.1               212,132.9         246,404.6             175,631.6             207,565.1             241,790.2  ‐1%  2%  2%EBITDA         150,439.6               184,593.3         214,734.0             150,726.2             179,086.9             209,503.4  0%  3%  2%PAT           51,988.9                 64,789.4           75,837.8               51,293.7               61,239.9               71,657.5  1%  6%  6%EPS              9.9                12.4            14.5                 9.8               11.7               13.7  1%  6%  6%

Source: Company, PhillipCapital India Research Estimates   International Peers Name  Mkt Cap  P/BV  RoE P/E Dividend Yield

(USD bn)  FY17  FY17 FY17 FY17Power Grid Corp                12.3                  1.6               16.4         10.5           3.0 RedesEnergeticasNacionais                  1.7                  1.4               10.0         12.9           6.1 Red Electrica Corporacionsa                11.7                  3.6               22.6         15.8           4.5 Terna SPA                  9.5                  2.5               14.6         17.1           4.7 

Source: Company, PhillipCapital India Research Estimates 

0

2

4

6

8

10

020406080

100120140160180

Mar‐08

Jul‐0

8

Nov

‐08

Mar‐09

Jul‐0

9

Nov

‐09

Mar‐10

Jul‐1

0

Nov

‐10

Mar‐11

Jul‐1

1

Nov

‐11

Mar‐12

Jul‐1

2

Nov

‐12

Mar‐13

Jul‐1

3

Nov

‐13

Mar‐14

Jul‐1

4

Nov

‐14

Mar‐15

PGCIL price 10 years bond yield

Page 76: INSTITUTIONAL EQUITY RESEARCH India Utilitiesbackoffice.phillipcapital.in/...Utilities_Sector... · post FY18. Thus, we expect all India demand for coal to rise at 7% CAGR during

  

Page | 76 | PHILLIPCAPITAL INDIA RESEARCH 

POWER GRID CORPORATION INITIATING COVERAGE 

1 year forward band charts 

Source: Company, PhillipCapital India Research Estimates         

 

8x

12x

16x

20x

20

70

120

170

220

270

Apr/08 Apr/09 Apr/10 Apr/11 Apr/12 Apr/13 Apr/14

Rs P/E Band

1.5x

2x

2.5x

3x

50

70

90

110

130

150

170

190

210

230

250

Apr/08 Apr/09 Apr/10 Apr/11 Apr/12 Apr/13 Apr/14

Rs P/BV Band

Page 77: INSTITUTIONAL EQUITY RESEARCH India Utilitiesbackoffice.phillipcapital.in/...Utilities_Sector... · post FY18. Thus, we expect all India demand for coal to rise at 7% CAGR during

  

Page | 77 | PHILLIPCAPITAL INDIA RESEARCH 

POWER GRID CORPORATION INITIATING COVERAGE 

Financials  

Income Statement Y/E Mar, Rs mn  FY14  FY15e  FY16e FY17eNet sales  151,527  174,387  212,133 246,405Growth, %  19  15  22 16Total income  151,527  174,387  212,133 246,405Raw material expenses  0  0  0 0Employee expenses  ‐9,417  ‐10,358  ‐11,912 ‐13,699Other Operating expenses  ‐13,323  ‐13,589  ‐15,627 ‐17,972EBITDA (Core)  128,788  150,440  184,593 214,734Growth, %  18.3            16.8           22.7           16.3 Margin, %  85.0            86.3           87.0           87.1 Depreciation  ‐39,957  ‐51,277  ‐62,244 ‐72,248EBIT  88,831  99,163  122,349 142,486Growth, %  17.9            11.6           23.4           16.5 Margin, %  58.6            56.9           57.7           57.8 Interest paid  ‐31,675  ‐40,412  ‐47,628 ‐54,715Other Non‐Operating Income  5,687  6,055  6,060 6,789Pre‐tax profit  62,843  64,807  80,780 94,560Tax provided  ‐17,663  ‐12,818  ‐15,991 ‐18,722Profit after tax  45,179  51,989  64,789 75,838Net Profit  45,179  51,989  64,789 75,838Growth, %  7.3            15.1           24.6           17.1 Net Profit (adjusted)  45,179        51,989       64,789       75,838 Unadj. shares (m)  5,232          5,232         5,232         5,232 Wtdavg shares (m)  5,232          5,232         5,232         5,232   Balance Sheet Y/E Mar, Rs mn  FY14 FY15e  FY16e FY17eCash & bank  44,175 40,398  75,437 88,952Debtors  15,785 19,111  23,247 27,003Inventory  7,124 9,555  12,786 16,202Loans & advances  50,250 64,499  78,460 91,136Other current assets  42,262 40,611  49,401 57,382Total current assets  159,596 174,175  239,332 280,675Investments  9,987 9,987  9,987 9,987Gross fixed assets  965,037 1,216,955  1,431,738 1,642,658Less: Depreciation  ‐233,496 ‐284,773  ‐347,017 ‐419,265Add: Capital WIP  494,767 467,849  478,066 492,146Net fixed assets  1,226,308 1,400,031  1,562,787 1,715,538Total assets  1,395,891 1,584,192  1,812,105 2,006,200

  Current liabilities  135,068 171,998  206,321 236,278Provisions  14,924 14,924  14,924 14,924Total current liabilities  149,992 186,922  221,245 251,202Non‐current liabilities  856,128 973,734  1,125,245 1,240,128Total liabilities  1,006,120 1,160,656  1,346,490 1,491,330Paid‐up capital  52,316 52,316  52,316 52,316Reserves & surplus  292,280 326,046  368,125 417,379Shareholders’ equity  389,771 423,536  465,615 514,870Total equity & liabilities  1,395,891 1,584,192  1,812,105 2,006,200 Source: Company, PhillipCapital India Research  Estimates 

Cash Flow Y/E Mar, Rs mn  FY14  FY15e FY16e FY17ePre‐tax profit  62,843  64,807 80,780 94,560Depreciation  39,957  51,277 62,244 72,248Chg in working capital  45,275  18,575 4,205 2,129Total tax paid  ‐12,825  ‐12,818 ‐15,991 ‐18,722Cash flow from operating activities  135,249  121,841 131,238 150,215Capital expenditure  ‐304,022  ‐225,000 ‐225,000 ‐225,000Chg in investments  1,488  0 0 0Cash flow from investing activities  ‐302,534  ‐225,000 ‐225,000 ‐225,000Free cash flow  ‐167,285  ‐103,159 ‐93,762 ‐74,785Equity raised/(repaid)  6,019  0 0 0Debt raised/(repaid)  149,820  117,606 151,511 114,883Dividend (incl. tax)  ‐15,765  ‐18,224 ‐22,710 ‐26,583Other financing activities  46,768  0 0 0Cash flow from financing activities  194,841  99,382 128,801 88,300Net chg in cash  27,556  ‐3,777 35,039 13,515  Valuation Ratios 

FY14  FY15e  FY16e FY17ePer Share data EPS (INR)                8.6               9.9            12.4            14.5 Growth, %              (5.0)             15.1            24.6            17.1 Book NAV/share (INR)             65.9             72.3            80.4            89.8 FDEPS (INR)                8.6               9.9            12.4            14.5 CEPS (INR)             16.3             19.7            24.3            28.3 CFPS (INR)             24.8             22.1            23.9            27.4 Return ratios     Return on assets (%)                5.2               5.2              5.6              5.8 Return on equity (%)             14.8             14.4            16.2            17.0 Return on capital employed (%)               5.8               5.8              6.3              6.5 Turnover ratios     Asset turnover (x)  0.1  0.1  0.1 0.2Sales/Total assets (x)  0.1  0.1  0.1 0.1Sales/Net FA (x)  0.1  0.1  0.1 0.2Working capital/Sales (x)  (0.1)  (0.2)  (0.2) (0.2)Receivable days  38.0  40.0  40.0 40.0Inventory days  17.2  20.0  22.0 24.0Payable days  361.3  360.0  355.0 350.0Working capital days  (47.3)  (80.0)  (73.0) (66.0)Liquidity ratios     Current ratio (x)  1.2  1.0  1.2 1.2Quick ratio (x)  1.1  1.0  1.1 1.1Interest cover (x)  2.8  2.5  2.6 2.6Total debt/Equity (%)  241.4  250.9  261.8 258.8Net debt/Equity (%)  228.5  240.2  243.9 239.9Valuation     PER (x)  ‐             15.1            12.1            10.3 PEG (x) ‐ y‐o‐y growth              (3.5)               1.0              0.5              0.6 Price/Book (x)                2.3               2.1              1.9              1.7 EV/Net sales (x)             10.4               9.7              8.5              7.8 EV/EBITDA (x)             12.2             11.3              9.8              8.9 EV/EBIT (x)             17.7             17.1            14.8            13.4   

Page 78: INSTITUTIONAL EQUITY RESEARCH India Utilitiesbackoffice.phillipcapital.in/...Utilities_Sector... · post FY18. Thus, we expect all India demand for coal to rise at 7% CAGR during

INSTITUTIONAL EQUITY RESEARCH  

Page | 78 | PHILLIPCAPITAL INDIA RESEARCH 

PTC India (PTC IN) Unlocking subsidiary value  INDIA | UTILITIES | Initiating Coverage 

 

  

28 April 2015 

Investment Rationale We initiate coverage on PTC with BUY rating and a target price of Rs120.We expect increase in volume driven by commissioning of long term PPAs and a change in earning composition with  significant profitability being driven by PFS will be key  factors  for  re‐rating. We note PTC India remains good play on distribution reforms due to  its significant volume exposure to discoms.  • Strong  volume  growth: We  expect  PTC  to  report  12%  CAGR  in  volumes  driven  by 

commissioning of long term PPAs that would grow to 48 BUs by FY17E.  On conservative basis, our volume growth does not factor in capacity expected to commission on captive coal blocks. We expect volume mix  to be  skewed  towards  long  term as capacity with long term PPA’s are expected to commission during FY15‐17E. Improvement in discoms’ financial  and  introduction  of  reforms  in  distribution  segment  would  further  boost volumes of PTC.  

• Stable margins: We expect core  trading margins  to  range Rs4.2‐4.5/kwh during FY15‐17E. We  note  decline  in  prices  in  Southern  India  post  grid  integration would  impact margins  in  erstwhile  tolling  project,  however  higher  contribution  from  long  term volumes will lend stability to margins. 

 • PFS – capitalizing on late mover advantage: Due to its late start, the exposure of PFS to 

stressed assets is very low as compared to its peers. We expect PFS to report 28%CAGR in  loan book during FY15‐17E. We note PFS has  increased  its exposure significantly  to renewable  sector  and  could  be  an  important  beneficiary  of  government  thrust  on renewable sector. We expect PFS to report 43% CAGR PAT lead by healthy NIMs. 

 

• Earnings and Valuations: We expect PTC to report earnings CAGR of 12% led by higher contribution  of  long  term  volumes  in  core  business,  strong  growth  in  subsidiary  PFS driven by healthy loan book growth. We believe PTC remains key play on improvement in health of discoms and distribution  reforms.   PTC  India  trades at 6x FY17E and 0.6x P/B. We value PTC on SOTP to arrive at target price of Rs120. We initiate coverage with BUY rating on the stock. 

 • Key  risks  to  our  BUY  call:  :  1) Higher  than  expected working  capital  requirement  in 

business 2) Further deterioration of discoms’  financials 3)   Delay  in commissioning of  capacities with long term PPA 4) Asset quality impairment in PFS. 

BUY (Maintain) CMP RS 75 TARGET RS 120(+50%)  COMPANY DATA O/S SHARES (MN) :  296MARKET CAP (RSBN) :  22MARKET CAP (USDBN) :  0.452 ‐ WK HI/LO (RS) :  105 / 65LIQUIDITY 3M (USDMN) :  3.1PAR VALUE (RS) :  10 SHARE HOLDING PATTERN, % PROMOTERS :  16.2FII / NRI :  26.4FI / MF :  36.6NON PROMOTER CORP. HOLDINGS :  7.7PUBLIC & OTHERS :  13.0 PRICE PERFORMANCE, % 

  1MTH 3MTH 1YRABS  ‐2.4 ‐21.2 8.4REL TO BSE  0.1 ‐15.0 ‐11.7 PRICE VS. SENSEX 

 Source: Phillip Capital India Research  KEY FINANCIALS Rs mn  FY15E FY16E FY17ENet Sales  133,572 151,103 168,281EBIDTA  9,546 11,179 13,360Net Profit  3,190 3,229 3,776EPS, Rs             10.8             10.9            12.8 PER, x                7.9                7.8               6.6 EV/EBIDTA, x                6.9                7.1               7.2 P/BV, x                0.8                0.7               0.7 ROE, %              10.1                9.6            10.3 Debt/Equity (%)           173.0           190.8          225.5 

Source: PhillipCapital India Research Est.  AnkurSharma(+ 9122 6667 9759) [email protected]  HrishikeshBhagat(+ 9122 6667 9986) [email protected] 

 

30507090

110130150170

Apr‐11 Jun‐12 Aug‐13 Oct‐14PTC India BSE Sensex

Page 79: INSTITUTIONAL EQUITY RESEARCH India Utilitiesbackoffice.phillipcapital.in/...Utilities_Sector... · post FY18. Thus, we expect all India demand for coal to rise at 7% CAGR during

  

Page | 79 | PHILLIPCAPITAL INDIA RESEARCH 

PTC INDIA INITIATING COVERAGE 

Strong Volume Growth Increase in proportion of long term volumes The short term volume market has witnessed CAGR of 26% during FY07‐14 and PTC has been one of  the key beneficiaries of exponential growth  in  short  term market. The overall short term market as percentage of generation has remained constant at 10‐11% of overall generation over past few years.   Short Term Volume 

 Source: CERC  PTC has reported 12% volume CAGR during FY04‐14 driven by higher proportion of trade through short term/bilateral contracts. We expect PTC to report 12% CAGR  in volume  driven  by  commissioning  of  long  term  PPA  that would  lead  to  48  BU  by FY17E.    We do note that volume growth trajectory during FY13‐14 was impacted as exposure to weak discoms such as TN, UP lead to delay in recovery of dues. In our estimates for FY15‐17E we have not factored in PPA’s with plants that are expected to commission on captive coal blocks.  In case, the auction of coal blocks  is done speedily, volumes would further increase.  Unit sold (including tolling) 

 Source: Company, PhillipCapital India Research Estimates 

10 

12 

20 

40 

60 

80 

100 

120 

FY07 FY08 FY09 FY10 FY11 FY12 FY13 FY14

Short term volumes % of Total generation (rhs)

1418

24 2429

35 37

4348

FY09 FY10 FY11 FY12 FY13 FY14 FY15E FY16E FY17E

The overall share of short term market as percentage of generation has remained at 10‐11%  

Strong volume growth driven by commissioning of long term PPA. Our volume growth assumption is lower than PTC’s target of 75 BU in FY17 due to delay in commissioning of tied up capacity.  

Page 80: INSTITUTIONAL EQUITY RESEARCH India Utilitiesbackoffice.phillipcapital.in/...Utilities_Sector... · post FY18. Thus, we expect all India demand for coal to rise at 7% CAGR during

  

Page | 80 | PHILLIPCAPITAL INDIA RESEARCH 

PTC INDIA INITIATING COVERAGE 

Volume mix  We note short term volumes constituted 61% of total volume in FY14 and we expect the  contribution  to  decline  to  40%  in  FY17.  The  contribution  from  cross  border contracts with Nepal, Bhutan and Bangladesh will further boost volumes.  Volume Break up 

 Source: Company, PhillipCapital India Research Estimates   Key capacities expected to contribute to long term volumes Developer  Capacity  Capacity PPA with PTC)GMR Energy  Kamalanga TPS  1050 323JPVL *  Karcham Wangtoo  HEP  1000 704Hinduja Power  Vizag TPS  1040 585Teesta Urja Ltd  Teesta Stage III HEP  1200 1056DB Power  Baradarha TPS  1200 520Ideal Energy  Ideal Energy  540 240Krishna Godavari Power  Krishna Godavari Power  144 60ACB India  TRN Energy  300 100ACB India  Bandakhar TPS  200 250KVK Energy  Nilachal TPS (Phase‐II)  700 350

*Earlier sold through short term  We have not  factored  in volume  contribution  from  capacities  that are expected  to commission on captive coal blocks. These constitute 1.5GW of PTC’s PPA.   PPA based on captive mines Company  Plant  Block  Location  Plant Capacity (MW)  PPA with PTC

Adhunik Power  Adhunik TPS  Ganeshpur  Jharkhand  270  100Adhunik Power  Adhunik TPS  Ganeshpur  Jharkhand  270  100Athena Power  Singhitarai TPS  Fatehpur/Fatehpur East  Chattisgarh  1,200  750Monnet Power  Malibrahmani TPS  Mandakini  Orissa  1,050  600

    2,790  1,550

Source: Company PhillipCapital India Research Estimates     

Short Term/Bilateral61%

Cross Border18%

Long Term Contracts

16%

Tolling Projects

5%

FY14

Short Term/Bilater

al39%

Cross Border15%

Long Term Contracts

39%

Tolling Projects

7%

FY17

PTC has 11GW PPA on long term basis 11GW out of which it has tied up 7.1 GW  

Page 81: INSTITUTIONAL EQUITY RESEARCH India Utilitiesbackoffice.phillipcapital.in/...Utilities_Sector... · post FY18. Thus, we expect all India demand for coal to rise at 7% CAGR during

  

Page | 81 | PHILLIPCAPITAL INDIA RESEARCH 

PTC INDIA INITIATING COVERAGE 

Going forward, few factors that could contribute to volume growth:  Open Access: Currently very few states have allowed open access and even those states that have introduced open access the discoms do not allow consumers seamless transition to open  access  platforms.  We  believe  open  access  `  can  be  a  significant  volume contributor to PTC. Currently the contribution  from open access  is very negligible ~ 2BU  for  PTC.  The  introduction  of  competition  in  distribution  segment  through separation of “carriage” and “content “could open up significant opportunity for PTC India  We do acknowledge  the  failure  in  implementation “Open access  reforms”  in  Indian Power sector. However currently at a time when PLF’s across India are at all‐time low due to weak financials of discoms leading to demand suppression, implementation of open access is inevitable 

 Improvement in discoms financial: The  financials’  of  discoms  have  been  impacted  badly  due  to  political  intervention resulting  in  delayed  tariff  hike.  Higher  AT&C  losses  coupled  with  higher  power purchase cost lead to SEB’s reporting Rs1060bn losses in FY13. We note government has  taken  few  steps  such  as  implementation  FRP  to  improve  health  of  discoms. Further discoms have also taken tariff hike over past few years that would  improve financial position and purchasing power.  

 Tariff hikes Name of state  FY12  FY13  FY14 FY15 FY16Andhra Pradesh                          4                  20                  23  5Arunachal Pradesh                        19                    5                    6                   ‐ NAAssam                  ‐                    2                   ‐ NABihar     ‐                  12                    7                   ‐ 3Chandigarh     ‐                  10                   ‐                  ‐ ‐Chhattisgarh                         14                  18                   ‐                 21  12Delhi     ‐                  21                    5                    8  NAGujarat     1.5‐3.5                    2                    6                   ‐ 2Haryana                         17                  18                  13                   ‐ NAHimachal                         10                  13                  13                   ‐ ‐J&K                         12                    6                    9                   ‐ NAJharkhand                         11                    9     ‐ NAKarnataka                          6                    3                   ‐                 10  5Kerala                        ‐                  30                    8                  16  NAMadhya Pradesh                         11                    7                    1                   ‐ 10Maharashtra                          3                  17  NAManipur                         15                    8    ‐                   8  5Mizoram                         11                  10    ‐ 2Orissa                         20                  12                    2                   ‐ 5Punjab                          8                  12                    9                    3  NARajasthan                   19                  10                   ‐ NATamil Nadu                         11                  37                   ‐                 15  NATripura                    3                  21  NAUP                         14                    9                    8                  20  NAUttarakhand                         3                    7                    5                   ‐ 7West Bengal                         11                  ‐                   ‐ ‐ NA

Source: SERC 

Page 82: INSTITUTIONAL EQUITY RESEARCH India Utilitiesbackoffice.phillipcapital.in/...Utilities_Sector... · post FY18. Thus, we expect all India demand for coal to rise at 7% CAGR during

  

Page | 82 | PHILLIPCAPITAL INDIA RESEARCH 

PTC INDIA INITIATING COVERAGE 

Core trading margins seems to have bottomed Intense competition impacted margins As per CERC’s  (Fixation of Trading Margin) Regulations, 2010,  trading  licensees are allowed to charge trading margin up to Rs0.07/kWh in case the sale price >Rs3/kWh, and Rs0.04/kWh where the sale price is <Rs3/kWh. We note however due to intense competitions margins have  come down  in  short  term market.  In FY14, margins  for sale  price  <Rs  3/kwh  was  Rs  0.02/kwh  and  for  sale  price  >Rs  3/kwh  the  trading margin was less Rs 0.04/kwh.  In  line with  industry volumes, PTC  India’s core  trading margins were down  from Rs 4.7/kwh to Rs 4.2/kwh. We expect higher contribution of  long term volumes to add stability to margins  Core Trading Margins 

  A) Tolling Business to boost consolidated margins PTC had entered into tolling arrangement under which it has tied up 350 MW of 600 MW Simhapur TPS (including expansion) and 150 MW of 300 MW Meenakshi TPS. In FY13, PTC altered its tolling arrangement and converted it into long term PPA under which margins was contingent on realization. Since most of this capacity is being sold in Southern market, PTC enjoys higher realizations and consequently higher margins. This  arrangement  also  eliminated  fuel  risk  that  PTC was  bearing  under  the  earlier arrangement.  In FY13, PTC earned EBITDA of Rs 0.8/kwh under tolling arrangement and  we  expect  EBITDA  margin  of  Rs  0.2/kwh  during  FY15‐17  as  realization  in Southern India would correct post grid integration.  Tolling EBITDA (Rs/kwh) 

 Source: Company, PhillipCapital India Research Estimates 

3.83.6

4.74.4

3.9 4.1

4.8 4.7 4.6

FY09 FY10 FY11 FY12 FY13 FY14 FY15E FY16E FY17E

0.80 

0.44 

0.32 0.27 

0.21 

0.10 

0.20 

0.30 

0.40 

0.50 

0.60 

0.70 

0.80 

0.90 

FY13 FY14 FY15 FY16E FY17E

Tolling EBITDA (Rs/kwh)

Margins have been relatively stable in range of rsrs 4.4kwh‐Rs 4.6/kwh  

Integration of Southern grid will impact margins in erstwhile tolling project  

Page 83: INSTITUTIONAL EQUITY RESEARCH India Utilitiesbackoffice.phillipcapital.in/...Utilities_Sector... · post FY18. Thus, we expect all India demand for coal to rise at 7% CAGR during

  

Page | 83 | PHILLIPCAPITAL INDIA RESEARCH 

PTC INDIA INITIATING COVERAGE 

Key Risks Weak Discoms Financials With significant distribution being undertaken through state discoms in most states, PTC’s  volumes  are driven by discoms’ purchase. Weak  financials have  significantly impaired  purchasing  power  of  discoms  and  consequently  the  volumes  for  PTC.  In FY12 PTC did face risks of rising receivables due to delay in recovery of dues from TN and UP leading to higher working capital investments. As on Q315 receivables stood at Rs30bn.  Receivables 

 Source: Company,PhillipCapital India Research Estimates  Capital allocation decision  We highlight Rs 6bn cash on books of PTC represents 22% of asset. PTC can either increase payout through higher cash or  it can  invest  in business by paying suppliers before  due  date  and  earning  rebate  on  power  purchase.  Further  PTC  also  had intention  of  acquiring  coal mines.   We  highlight  such  decision  to  be  beyond  core competency and increases business risks.   State elections: Empirically state discoms have shown significant exuberance in short term market at time of elections thus providing opportunity to PTC. We note however PTC has been able to manage risks in recent state election as well as general elections and has kept its receivables under check. FY17 will most  likely witness election  in  larger state UP that  has  historically  been  suffered  from  chronic  power  deficit  and  hence  higher purchases  in  short  term  markets.  Although  based  on  past  experience  PTC  has reduced its exposure to UP discoms, however this becomes key factor to monitor in near future.  UP‐Short Term Purchase (MU) 

 Source: CERC 

10 

15 

20 

25 

30 

FY08 FY09 FY10 FY11 FY12 FY13 FY14

Debtors (Rs bn)

0

1000

2000

3000

4000

5000

6000

7000

FY11 FY12 FY13 FY14

Debtors increased due to delayed payments from SEB’s.  

Page 84: INSTITUTIONAL EQUITY RESEARCH India Utilitiesbackoffice.phillipcapital.in/...Utilities_Sector... · post FY18. Thus, we expect all India demand for coal to rise at 7% CAGR during

  

Page | 84 | PHILLIPCAPITAL INDIA RESEARCH 

PTC INDIA INITIATING COVERAGE 

Long term volumes to increase working capital requirement too: We expect working  capital  investment also  to  increase as  contribution of  volumes from long term PPA’s increase for PTC. Thus net working capital days would increase during FY15‐17E. We model Net working Capital days of 18‐20 days during FY15‐17E. Lead by recovery of dues, we expect working capital days to fall in FY15E and expect gradual rise led by increase in contribution of long term volumes.  Long Term volumes 

 Source: Company, PhillipCapital India Research Estimates 

    

10 

20 

30 

40 

50 

60 

70 

10 

15 

20 

25 

FY10 FY11 FY12 FY13 FY14 FY15E FY16E FY17E

LongTerm Volumes (BU) Net Working Capital Days

Page 85: INSTITUTIONAL EQUITY RESEARCH India Utilitiesbackoffice.phillipcapital.in/...Utilities_Sector... · post FY18. Thus, we expect all India demand for coal to rise at 7% CAGR during

  

Page | 85 | PHILLIPCAPITAL INDIA RESEARCH 

PTC INDIA INITIATING COVERAGE 

PTC Financial Service (PFS)‐ Late mover advantage PTC Financial services (PFS)  is 60% subsidiary of PTC  India  involved  in total financial services to the entities in energy value chain, that  includes investing in equity and/or extending  debt  to  power  projects  in  generation,  transmission,  distribution;  fuel sources, fuel related infrastructure. PFS also has strategic investment in IEX and IPP’s such as East Coast Energy TPS, IndBharath Energy.  a) Growth driven by loan book growth Although PFS was set up in 2006, it attained “Infrastructure Finance Company” status in FY10. We note delayed entry into lending business has helped PFS to some extent as although it missed infra lending boom during 2007‐11, however it also did not get exposure to risky assets  in power sector  like banks. We note due to  lower base PFS had CAGR 100% in loan book during FY10‐14. As on Dec 2015, PFS had Rs59bn loan book with  38%  loan  book  exposed  to  renewable  and  30%  to  thermal  assets. We model a 27% CAGR in loan book during FY15‐17.We note with new government focus on renewable space; the opportunity for growth is significant.  Loan book 

 Source: Company, PhillipCapital India Research Estimates  b) Healthy NIMS We note PFS has been able to maintain healthy NIM’s driven by competitive cost of funds and better yields. Thus NIM’s have gone up from 2.9% in FY11 to 7% in FY14. On  back  of  loan  book  growth,  healthy  NIM’s  and  adjusted  for  sale  of  strategic divestments, PFS reported 76% CAGR  in PAT during FY11‐14E.We expect 43% CAGR PAT during FY15‐17E led by healthy NIM’s and improvement in yields.  NIMS 

 Source: Company, PhillipCapital India Research Estimates 

0

20

40

60

80

100

120

FY10 FY11 FY12 FY13 FY14 FY15E FY16E FY17E

Loan Book (Rs bn)

0

2

4

6

8

10

12

14

16

Q213 Q313 Q413 Q114 Q214 Q314 Q414 Q115 Q215 Q315

Yield Cost of Funds NIM Spread

Healthy Loan book growth  

Page 86: INSTITUTIONAL EQUITY RESEARCH India Utilitiesbackoffice.phillipcapital.in/...Utilities_Sector... · post FY18. Thus, we expect all India demand for coal to rise at 7% CAGR during

  

Page | 86 | PHILLIPCAPITAL INDIA RESEARCH 

PTC INDIA INITIATING COVERAGE 

Key investments by PFS Over past  few years PFS has sold stake  in projects where  it had equity  investment thus  leading  to  value unlocking.  In  FY14,  PFS divested  its  16.7%  stake  in Meenaxi Energy,  thus  for Rs 2bn.  In FY11, PFS divested 14% stake  in  IEX  for Rs 7bn  (16x  its original investment).  PFS investments  Rs mnIEX  15.2700 MW Ind Bharat Utkal  10501320 MW East Coast Energy Pvt Ltd  1333.899 MW RS India Wind Energy  611.2Varam Bio               44 Total          3,054 

   PFS SOTP (FY17)  Rs mnABV        19,090 ABV        19,090 Mutiple  1.7Core Business        32,452 Investments          4,254 IEX 5% stake at latest deal value          1,125 Total        37,832 Value               67 

   Asset Composition 

 Source: Company, PhillipCapital India Research Estimates  

Others24%

Hydro8%

Renewables38%

Thermal30%

Page 87: INSTITUTIONAL EQUITY RESEARCH India Utilitiesbackoffice.phillipcapital.in/...Utilities_Sector... · post FY18. Thus, we expect all India demand for coal to rise at 7% CAGR during

  

Page | 87 | PHILLIPCAPITAL INDIA RESEARCH 

PTC INDIA INITIATING COVERAGE 

Key drivers for a re ‐rating  a) Change in business mix: We note for PTC, the overall profitability mix has shifted with significant profit being driven  by  PFS  since  FY11.  Thus  adjusted  for  one  off  pertaining  to  gain  on  sale  of strategic  investment, the overall contribution  in consolidated PBT has gone up from 19% in FY11 to 33% in FY14.  We note FY14 standalone PBT for PTC was also boosted by significantly higher surcharge  income which may not be sustainable. Thus,  led by strong growth in PFS we expect it to contribute to 69% of consolidated PBT by FY17E.  PBT break up 

 Source: Company, PhillipCapital India Research Estimates   b) RoE expansion to continue: We expect RoE expansion  to continue  lead by strong volume growth  in standalone business, expansion of loan book in PFS and increasing spread. 

 RoE 

 Source: Company, PhillipCapital India Research Estimates    

PFS, 33

PTC‐Standalone, 

63

PBT Break up‐FY14

PFS, 69

PTC‐Standalone, 

29

PBT Break up‐FY17

10 

12 

FY09 FY10 FY11 FY12 FY13 FY14 FY15E FY16E FY17E

ROE

Page 88: INSTITUTIONAL EQUITY RESEARCH India Utilitiesbackoffice.phillipcapital.in/...Utilities_Sector... · post FY18. Thus, we expect all India demand for coal to rise at 7% CAGR during

  

Page | 88 | PHILLIPCAPITAL INDIA RESEARCH 

PTC INDIA INITIATING COVERAGE 

c) Strong earnings growth We expect PTC  to  report earnings CAGR of 11%  led by higher contribution of  long term  volumes  in  core business,  strong  growth  in  subsidiary  PFS driven by healthy loan book growth and healthy spread in lending business. We have not incorporated liquidation of strategic investments in our numbers.   PAT growth 

 Source: Company, PhillipCapital India Research Estimates   Outlook and Valuations: We expect PTC to report earnings CAGR of 9% led by higher contribution of long term volumes  in  core  business,  strong  growth  of  subsidiary  PFS  driven  by  healthy  loan book growth. We believe PTC becomes key play on improvement on improvement in health of discoms and distribution reforms. We value PTC on SOTP basis to arrive at target  price  of  Rs120.  Key  risks  involve:  1)  Higher  than  expected working  capital requirement  in  business  2)  Further  deterioration  of  discom  financials  3)  Delay  in commissioning of capacities with long term PPA 4) Asset quality impairment in PFS. 

  

SOTP based target price   Rs mn  FY17 

Rs mn Rs/share   Assumptions  Trading Business          7,045               24   PE 6x to FY16E Core EPS  PTC energy             174                 1   PE 10x to FY16E Core EPS  PFS        18,159               61    20% holding company discount to PFS SOTP  Athena Energy Ventures                ‐               ‐   At book value  Teesta Urja          1,907                 6   At 1x  Krishna Godavari Power             376                 1   At book value  Cash          7,889               27   At book value  Value of PTCIN             120 

Source: PhillipCapital India Research Estimates      

‐60

‐40

‐20

0

20

40

60

80

100

120

140

0

500

1000

1500

2000

2500

3000

3500

4000

FY11 FY12 FY13 FY14 FY15E FY16E FY17E

PAT Growth (rhs)

Page 89: INSTITUTIONAL EQUITY RESEARCH India Utilitiesbackoffice.phillipcapital.in/...Utilities_Sector... · post FY18. Thus, we expect all India demand for coal to rise at 7% CAGR during

  

Page | 89 | PHILLIPCAPITAL INDIA RESEARCH 

PTC INDIA INITIATING COVERAGE 

 1 year forward band charts 

Source: Company, PhillipCapital India Research Estimates   

5x

10x

15x

20x

0

50

100

150

200

250

300

350

400

450

Apr‐10 Apr‐11 Apr‐12 Apr‐13 Apr‐14

Rs P/E band

0.5x

1x

1.5x

2x

0

50

100

150

200

250

Apr‐10 Apr‐11 Apr‐12 Apr‐13 Apr‐14

Rs P/BV band

Page 90: INSTITUTIONAL EQUITY RESEARCH India Utilitiesbackoffice.phillipcapital.in/...Utilities_Sector... · post FY18. Thus, we expect all India demand for coal to rise at 7% CAGR during

  

Page | 90 | PHILLIPCAPITAL INDIA RESEARCH 

PTC INDIA INITIATING COVERAGE 

Financials  

Income Statement Y/E Mar, Rs mn  FY14 FY15e  FY16e FY17eNet sales  119,774 133,572  151,103 168,281Growth, %  31 12  13 11Total income  119,774 133,572  151,103 168,281Raw material expenses  ‐110,014 ‐121,853  ‐137,742 ‐152,677Employee expenses  ‐246 ‐186  ‐168 ‐186Other Operating expenses  ‐1,475 ‐1,987  ‐2,014 ‐2,057EBITDA (Core)  8,039 9,546  11,179 13,360Growth, %  (5.1) 18.7  17.1 19.5Margin, %  6.7 7.1  7.4 7.9Depreciation  ‐85 ‐98  ‐94 ‐94EBIT  7,954 9,448  11,085 13,266Growth, %  (5.2) 18.8  17.3 19.7Margin, %  6.6 7.1  7.3 7.9Interest paid  ‐2,237 ‐4,219  ‐5,391 ‐6,310Pre‐tax profit  6,535 6,101  6,617 7,889Tax provided  ‐1,921 ‐2,013  ‐2,184 ‐2,603Profit after tax  4,614 4,088  4,433 5,285Others (Minorities, Associates)  ‐863 ‐898  ‐1,205 ‐1,509Net Profit  3,751 3,190  3,229 3,776Growth, %  (40.4) (15.0)  1.2 17.0Net Profit (adjusted)  3,751 3,190  3,229 3,776Unadj. shares (m)  295 295  295 295Wtdavg shares (m)  295 295  295 295  Balance Sheet Y/E Mar, Rs mn  FY14  FY15e  FY16e FY17eCash & bank  6,168  13,639  9,699 11,887Debtors  20,923  16,541  19,422 21,492Loans & advances  49,713  64,662  80,828 98,610Other current assets  733  750  750 750Total current assets  77,536  95,593  110,698 132,739Investments  8,657  8,657  8,657 8,657Gross fixed assets  1,083  1,133  1,183 1,233Less: Depreciation  ‐528  ‐627  ‐720 ‐814Net fixed assets  554  506  462 419Total assets  86,747  104,756  119,818 141,815

    Current liabilities  11,849  11,420  13,026 12,780Provisions  1,331  1,000  1,000 1,000Total current liabilities  13,180  12,420  14,026 13,780Non‐current liabilities  39,137  54,659  64,659 82,659Total liabilities  52,317  67,079  78,685 96,439Paid‐up capital  2,960  2,960  2,960 2,960Reserves & surplus  26,129  28,528  30,829 33,612Shareholders’ equity  34,430  37,676  41,132 45,375Total equity & liabilities  86,747  104,756  119,818 141,815 Source: Company, PhillipCapital India Research  Estimates 

Cash Flow Y/E Mar, Rs mn  FY14  FY15e FY16e FY17ePre‐tax profit  6,535  6,101 6,617 7,889Depreciation  85  98 94 94Chg in working capital  ‐27,331  ‐11,345 ‐17,440 ‐20,098Total tax paid  ‐1,836  ‐2,013 ‐2,184 ‐2,603Cash flow from operating activities  ‐22,547  ‐7,160 ‐12,913 ‐14,719Capital expenditure  ‐94  ‐50 ‐50 ‐50Chg in investments  1,164  0 0 0Cash flow from investing activities  1,070  ‐50 ‐50 ‐50Free cash flow  ‐21,476  ‐7,210 ‐12,963 ‐14,769Debt raised/(repaid)  23,083  15,523 10,000 18,000Cash flow from financing activities  22,691  15,473 9,950 17,950Net chg in cash  1,215  8,263 ‐3,013 3,181  Valuation Ratios 

FY14  FY15e FY16e FY17ePer Share data EPS (INR)             12.7             10.8             10.9            12.8 Growth, %            (40.4)           (15.0)               1.2            17.0 Book NAV/share (INR)             98.6           106.7           114.5          124.0 FDEPS (INR)             12.7             10.8             10.9            12.8 CEPS (INR)             13.0             11.1             11.3            13.1 CFPS (INR)            (79.2)           (27.2)           (46.9)          (53.1)Return ratios          Return on assets (%)                8.3                7.1                7.0               7.1 Return on equity (%)             12.9             10.1                9.6            10.3 Return on capital employed (%)               9.9                8.1                7.9               7.9 Turnover ratios          Asset turnover (x)                2.6                2.0                1.9               1.7 Sales/Total assets (x)                1.7                1.4                1.3               1.3 Sales/Net FA (x)           217.7           252.0           312.1          382.0 Working capital/Sales (x)                0.5                0.5                0.6               0.6 Receivable days             63.8             45.2             46.9            46.6 Payable days             35.6             30.1             30.1            26.1 Working capital days           181.4           192.7           212.5          234.4 Liquidity ratios          Current ratio (x)                6.5                8.4                8.5            10.4 Quick ratio (x)                6.5                8.4                8.5            10.4 Interest cover (x)                3.6                2.2                2.1               2.1 Total debt/Equity (%)           133.9           173.0           190.8          225.5 Net debt/Equity (%)           112.7           129.7           162.1          193.0 Valuation          PER (x)                6.7                7.9                7.8               6.6 PEG (x) ‐ y‐o‐y growth              (0.2)             (0.5)               6.3               0.4 Price/Book (x)                0.9                0.8                0.7               0.7 EV/Net sales (x)                0.5                0.5                0.5               0.6 EV/EBITDA (x)                7.2                6.9                7.1               7.2 EV/EBIT (x)                7.3                7.0                7.2               7.2   

Page 91: INSTITUTIONAL EQUITY RESEARCH India Utilitiesbackoffice.phillipcapital.in/...Utilities_Sector... · post FY18. Thus, we expect all India demand for coal to rise at 7% CAGR during

  

Page | 91 | PHILLIPCAPITAL INDIA RESEARCH 

PTC INDIA INITIATING COVERAGE 

 

  

Contact Information (Regional Member Companies)  

SINGAPORE Phillip Securities Pte Ltd 

250 North Bridge Road, #06‐00 RafflesCityTower, Singapore 179101 

Tel : (65) 6533 6001 Fax: (65) 6535 3834 www.phillip.com.sg 

MALAYSIA Phillip Capital Management Sdn Bhd B‐3‐6 Block B Level 3, Megan Avenue II, 

No. 12, Jalan Yap Kwan Seng, 50450 Kuala Lumpur Tel (60) 3 2162 8841 Fax (60) 3 2166 5099 

www.poems.com.my 

HONG KONG Phillip Securities (HK) Ltd 

11/F United Centre 95 Queensway Hong Kong Tel (852) 2277 6600 Fax: (852) 2868 5307 

www.phillip.com.hk  

JAPAN Phillip Securities Japan, Ltd 

4‐2 Nihonbashi Kabutocho, Chuo‐ku Tokyo 103‐0026 

Tel: (81) 3 3666 2101 Fax: (81) 3 3664 0141 www.phillip.co.jp 

INDONESIA PT Phillip Securities Indonesia 

ANZTower Level 23B, Jl Jend Sudirman Kav 33A, Jakarta 10220, Indonesia 

Tel (62) 21 5790 0800 Fax: (62) 21 5790 0809 www.phillip.co.id 

CHINA Phillip Financial Advisory (Shanghai) Co. Ltd.  

No 550 Yan An East Road, OceanTower Unit 2318 Shanghai 200 001 

Tel (86) 21 5169 9200 Fax: (86) 21 6351 2940 www.phillip.com.cn 

THAILAND Phillip Securities (Thailand) Public Co. Ltd. 

15th Floor, VorawatBuilding,  849 Silom Road, Silom, Bangrak, Bangkok 10500 Thailand 

Tel (66) 2 2268 0999  Fax: (66) 2 2268 0921 www.phillip.co.th 

FRANCE King & Shaxson Capital Ltd. 

3rd Floor, 35 Rue de la Bienfaisance  75008 Paris France 

Tel (33) 1 4563 3100 Fax : (33) 1 4563 6017 www.kingandshaxson.com 

UNITED KINGDOM King & Shaxson Ltd. 

6th Floor, Candlewick House, 120 Cannon Street London, EC4N 6AS 

Tel (44) 20 7929 5300 Fax: (44) 20 7283 6835 www.kingandshaxson.com 

UNITED STATES Phillip Futures Inc. 

141 W Jackson Blvd Ste 3050 The Chicago Board of TradeBuilding 

Chicago, IL 60604 USA Tel (1) 312 356 9000 Fax: (1) 312 356 9005 

AUSTRALIA PhillipCapital Australia 

Level 37, 530 Collins Street Melbourne, Victoria 3000, Australia 

Tel: (61) 3 9629 8380  Fax: (61) 3 9614 8309 www.phillipcapital.com.au 

SRI LANKA Asha Phillip Securities Limited 

Level 4, Millennium House, 46/58 Navam Mawatha, Colombo 2, Sri Lanka 

Tel: (94) 11  2429 100 Fax: (94) 11 2429 199 www.ashaphillip.net/home.htm 

INDIA PhillipCapital (India) Private Limited 

No. 1, 18th Floor, Urmi Estate, 95 Ganpatrao Kadam Marg, Lower Parel West, Mumbai 400013 Tel: (9122) 2300 2999 Fax: (9122) 6667 9955 www.phillipcapital.in 

   

Management (91 22) 2300 2999

Kinshuk Bharti Tiwari (Head – Institutional Equity) (91 22) 6667 9946(91 22) 6667 9735

Research Economics Retail, Real Estate

Dhawal Doshi (9122) 6667 9769 Anjali Verma  (9122) 6667 9969 Abhishek Ranganathan, CFA (9122) 6667 9952Priya Ranjan (9122) 6667 9965 Rohit Shroff (9122) 6667 9756

Infrastructure & IT ServicesVibhor Singhal (9122) 6667 9949 Portfolio Strategy

Manish Agarwalla (9122) 6667 9962 Deepan Kapadia (9122) 6667 9992 Anindya Bhowmik (9122) 6667 9764Pradeep Agrawal (9122) 6667 9953Paresh Jain (9122) 6667 9948 Logistics, Transportation & Midcap Technicals

Vikram Suryavanshi (9122) 6667 9951 Subodh Gupta, CMT (9122) 6667 9762Consumer, Media, TelecomNaveen Kulkarni, CFA, FRM (9122) 6667 9947 Metals Production ManagerJubil Jain (9122) 6667 9766 Dhawal Doshi (9122) 6667 9769 Ganesh Deorukhkar (9122) 6667 9966Manoj Behera (9122) 6667 9973 Ankit Gor (9122) 6667 9987

Database ManagerCement Oil&Gas,  Agri Inputs Deepak Agarwal (9122) 6667 9944Vaibhav Agarwal (9122) 6667 9967 Gauri Anand (9122) 6667 9943

Deepak Pareek (9122) 6667 9950 Sr. Manager – Equities SupportEngineering, Capital Goods Rosie Ferns  (9122) 6667 9971Ankur Sharma (9122) 6667 9759 PharmaHrishikesh Bhagat (9122) 6667 9986 Surya Patra (9122) 6667 9768

Mehul Sheth (9122) 6667 9996

Sales & Distribution Ashvin Patil (9122) 6667 9991 Sales Trader Zarine Damania (9122) 6667 9976Shubhangi Agrawal (9122) 6667 9964 Dilesh Doshi (9122) 6667 9747 Kishor Binwal (9122) 6667 9989 Suniil Pandit (9122) 6667 9745Sidharth Agrawal (9122) 6667 9934 ExecutionBhavin Shah (9122) 6667 9974 Mayur Shah (9122) 6667 9945

Corporate Communications

Vineet Bhatnagar (Managing Director)

Jignesh Shah (Head – Equity Derivatives)

Automobiles

Banking, NBFCs

Page 92: INSTITUTIONAL EQUITY RESEARCH India Utilitiesbackoffice.phillipcapital.in/...Utilities_Sector... · post FY18. Thus, we expect all India demand for coal to rise at 7% CAGR during

  

Page | 92 | PHILLIPCAPITAL INDIA RESEARCH 

PTC INDIA INITIATING COVERAGE 

Disclosures and Disclaimers  PhillipCapital  (India) Pvt. Ltd. has  three  independent equity  research groups:  Institutional Equities,  Institutional Equity Derivatives and Private Client Group. This  report has been prepared by Institutional Equities Group. The views and opinions expressed in this document may or may not match or may be contrary at times with the views, estimates, rating, target price of the other equity research groups of PhillipCapital (India) Pvt. Ltd.   This report is issued by PhillipCapital (India) Pvt. Ltd. which is regulated by SEBI. PhillipCapital (India) Pvt. Ltd. is a subsidiary of Phillip (Mauritius) Pvt. Ltd. References to "PCIPL" in this  report  shall mean  PhillipCapital  (India)  Pvt.  Ltd  unless  otherwise  stated.  This  report  is  prepared  and  distributed  by  PCIPL  for  information  purposes  only  and  neither  the information contained herein nor any opinion expressed should be construed or deemed to be construed as solicitation or as offering advice for the purposes of the purchase or sale of any security,  investment or derivatives. The  information and opinions contained  in the Report were considered by PCIPL to be valid when published. The report also contains information provided to PCIPL by third parties. The source of such information will usually be disclosed in the report. Whilst PCIPL has taken all reasonable steps to ensure that this information  is correct, PCIPL does not offer any warranty as to the accuracy or completeness of such  information. Any person placing reliance on the report to undertake trading does so entirely at his or her own risk and PCIPL does not accept any liability as a result. Securities and Derivatives markets may be subject to rapid and unexpected price movements and past performance is not necessarily an indication to future performance.  This report does not have regard to the specific investment objectives, financial situation and the particular needs of any specific person who may receive this report. Investors must undertake  independent analysis with  their own  legal,  tax and  financial advisors and  reach  their own  regarding  the appropriateness of  investing  in any  securities or  investment strategies discussed or  recommended  in  this  report and  should understand  that  statements  regarding  future prospects may not be  realized.  In no  circumstances  it be used or considered as an offer to sell or a solicitation of any offer to buy or sell the Securities mentioned in it. The information contained in the research reports may have been taken from trade and statistical services and other sources, which we believe are reliable. PhillipCapital (India) Pvt. Ltd. or any of its group/associate/affiliate companies do not guarantee that such information is accurate or complete and it should not be relied upon as such. Any opinions expressed reflect judgments at this date and are subject to change without notice  Important: These disclosures and disclaimers must be read  in conjunction with the research report of which  it forms part. Receipt and use of the research report  is subject to all aspects of these disclosures and disclaimers. Additional information about the issuers and securities discussed in this research report is available on request.  Certifications: The research analyst(s) who prepared this research report hereby certifies that the views expressed  in this research report accurately reflect the research analyst’s personal views about all of the subject issuers and/or securities, that the analyst have no known conflict of interest and no part of the research analyst’s compensation was, is or will be, directly or indirectly, related to the specific views or recommendations contained in this research report. The Research Analyst certifies that he /she or his / her family members does not own the stock(s) covered in this research report.  Independence/Conflict: PhillipCapital (India) Pvt. Ltd. has not had an investment banking relationship with, and has not received any compensation for investment banking services from,  the subject  issuers  in  the past  twelve  (12) months, and PhillipCapital  (India) Pvt. Ltd does not anticipate  receiving or  intend  to seek compensation  for  investment banking services from the subject issuers in the next three (3) months. PhillipCapital (India) Pvt. Ltd is not a market maker in the securities mentioned in this research report, although it or its employees,  directors,  or  affiliates may  hold  either  long  or  short  positions  in  such  securities.  PhillipCapital  (India)  Pvt.  Ltd may  not  hold more  than  1%  of  the  shares  of  the company(ies) covered in this report.  Suitability and Risks: This research report is for informational purposes only and is not tailored to the specific investment objectives, financial situation or particular requirements of any individual recipient hereof. Certain securities may give rise to substantial risks and may not be suitable for certain investors. Each investor must make its own determination as to the appropriateness of any securities referred to in this research report based upon the legal, tax and accounting considerations applicable to such investor and its own investment objectives or strategy, its financial situation and its investing experience. The value of any security may be positively or adversely affected by changes in foreign exchange or interest rates, as well as by other financial, economic or political factors. Past performance is not necessarily indicative of future performance or results.  Sources, Completeness and Accuracy: The material herein is based upon information obtained from sources that PCIPL and the research analyst believe to be reliable, but neither PCIPL nor the research analyst represents or guarantees that the information contained herein is accurate or complete and it should not be relied upon as such. Opinions expressed herein are current opinions as of the date appearing on this material and are subject to change without notice. Furthermore, PCIPL  is under no obligation to update or keep the information current.  Copyright: The copyright in this research report belongs exclusively to PCIPL. All rights are reserved. Any unauthorized use or disclosure is prohibited. No reprinting or reproduction, in whole or in part, is permitted without the PCIPL’s prior consent, except that a recipient may reprint it for internal circulation only and only if it is reprinted in its entirety.  Caution: Risk of loss in trading in can be substantial. You should carefully consider whether trading is appropriate for you in light of your experience, objectives, financial resources and other relevant circumstances.  For U.S. persons only: This research report is a product of PhillipCapital (India) Pvt Ltd. which is the employer of the research analyst(s) who has prepared the research report. The research analyst(s) preparing the research report is/are resident outside the United States (U.S.) and are not associated persons of any U.S. regulated broker‐dealer and therefore the analyst(s)  is/are not subject to supervision by a U.S. broker‐dealer, and  is/are not required to satisfy the regulatory  licensing requirements of FINRA or required to otherwise comply with U.S. rules or regulations regarding, among other things, communications with a subject company, public appearances and trading securities held by a research analyst account.  This report is intended for distribution by PhillipCapital (India) Pvt Ltd. only to "Major Institutional Investors" as defined by Rule 15a‐6(b)(4) of the U.S. Securities andExchange Act, 1934 (the Exchange Act) and interpretations thereof by U.S. Securities and Exchange Commission (SEC) in reliance on Rule 15a 6(a)(2). If the recipient of this report is not a Major Institutional  Investor as  specified above,  then  it  should not act upon  this  report and  return  the  same  to  the  sender. Further,  this  report may not be  copied, duplicated and/or transmitted onward to any U.S. person, which is not the Major Institutional Investor.  In reliance on the exemption from registration provided by Rule 15a‐6 of the Exchange Act and interpretations thereof by the SEC in order to conduct certain business with Major Institutional  Investors, PhillipCapital (India) Pvt Ltd. has entered  into an agreement with a U.S. registered broker‐dealer, Marco Polo Securities  Inc. ("Marco Polo").Transactions  in securities discussed in this research report should be effected through Marco Polo or another U.S. registered broker dealer.  PhillipCapital (India) Pvt. Ltd. Registered office:No. 1, 18th Floor, Urmi Estate,95 GanpatraoKadamMarg,Lower Parel West, Mumbai 400013