Welcome to this presentation.
It is part of a suite of Engineering training modules.
It shows the activities and deliverables of the Instrumentation & Control discipline.
Comments are most welcome ([email protected]), which I will incorporate for the benefit of all.
Please download this file so that you can see my trainer’s notes in the top left corner – latest Acrobat Pro feature.
Hervé
© 2015 – Hervé Baron
HERVE BARON
Engineering Training
PROCESS
PLANT LAYOUT
EQUIPMENT
SAFETY & ENVIRONMENT
CIVIL
PIPING
PIPELINE
INSTRUMENTATION
ELECTRICAL
© 2015 – Hervé Baron
HERVE BARON
Process design
PFDs
H&M balance
Rotating Pressure vessels Fired equipment Heat exchangers Packages etc.
P&IDs
Piping
Instrumentation
Layout
Civil
Electrical
Process data sheet
Equipment specification
Vendor drawings
We are here
© 2015 – Hervé Baron
HERVE BARON
Engineering disciplines: activities and deliverables
PROCESS
PLANT LAYOUT
EQUIPMENT
SAFETY & ENVIRONMENT
CIVIL
PIPING
PIPELINE
INSTRUMENTATION
The discipline is commonly split in 3 specialties. Which ones?
© 2015 – Hervé Baron
HERVE BARON
Engineering disciplines: activities and deliverables
PROCESS
PLANT LAYOUT
EQUIPMENT
SAFETY & ENVIRONMENT
CIVIL
PLANT LAYOUT & PIPING
PIPELINE
INSTRUMENTATION • Field instrumentation • Systems • Installation
© 2015 – Hervé Baron
HERVE BARON
Engineering disciplines: activities and deliverables
PROCESS
PLANT LAYOUT
EQUIPMENT
SAFETY & ENVIRONMENT
CIVIL
PIPING
PIPELINE
INSTRUMENTATION • Field instrumentation • Systems • Installation
© 2015 – Hervé Baron
HERVE BARON
Piping & Instrumentation Diagram (P&ID)
© 2015 – Hervé Baron
HERVE BARON
Piping & Instrumentation Diagram (P&ID)
© 2015 – Hervé Baron
HERVE BARON
Instrument list
© 2015 – Hervé Baron
HERVE BARON
Instrument data sheet
© 2015 – Hervé Baron
HERVE BARON
Level sketch
© 2015 – Hervé Baron
HERVE BARON
Engineering disciplines: activities and deliverables
PROCESS
PLANT LAYOUT
EQUIPMENT
SAFETY & ENVIRONMENT
CIVIL
PLANT LAYOUT & PIPING
PIPELINE
INSTRUMENTATION • Field instrumentation • Systems • Installation
© 2015 – Hervé Baron
HERVE BARON
Engineering disciplines: activities and deliverables
INSTRUMENTATION • Field instrumentation • Systems:
Process Control System Unit Control System Emergency Shutdown System Fire & Gas System Other systems
• Installation
© 2015 – Hervé Baron
HERVE BARON
PCS (Process Control System)
© 2015 – Hervé Baron
HERVE BARON
System requisition
© 2015 – Hervé Baron
HERVE BARON
System architecture drawing
© 2015 – Hervé Baron
HERVE BARON
Control narrative Gas inlet
Gas outlet
93-E161
© 2015 – Hervé Baron
HERVE BARON
Functional diagram
© 2015 – Hervé Baron
HERVE BARON
Mimic display drawings
© 2015 – Hervé Baron
HERVE BARON
Process automations & Process Shut Down (PSD)
© 2015 – Hervé Baron
HERVE BARON
Engineering disciplines: activities and deliverables
INSTRUMENTATION • Field instrumentation • Systems:
Process Control System Unit Control System Emergency Shutdown System Fire & Gas System Other systems
• Installation
© 2015 – Hervé Baron
HERVE BARON
Package instrumentation & control
© 2015 – Hervé Baron
HERVE BARON
Package instrumentation & control
© 2015 – Hervé Baron
HERVE BARON
Package control
Package controlled by Central Process Control System
© 2015 – Hervé Baron
HERVE BARON
Package control
Package controlled by Central Process Control System
© 2015 – Hervé Baron
HERVE BARON
Package control
Package controlled by own Unit Control System
© 2015 – Hervé Baron
HERVE BARON
Package control
What documents from the package Vendor are needed by the DCS Vendor in this case?
Package controlled by own Unit Control System
© 2015 – Hervé Baron
HERVE BARON
Package control
Package controlled by Central Process Control System
What documents from the package Vendor are needed by the DCS Vendor in this case?
© 2015 – Hervé Baron
HERVE BARON
Process Control System
Process Control System Engineering by Vendor
Hardware Software The Process Control System is engineered by the Vendor based on information supplied by Engineer.
© 2015 – Hervé Baron
HERVE BARON
Process Control System
Process Control System Engineering by Vendor
Hardware Software The Process Control System is engineered by the Vendor based on information supplied by Engineer. Which documents are needed by the Vendor?
© 2015 – Hervé Baron
HERVE BARON
Process Control System
Process Control System Engineering by Vendor
Hardware Software The Process Control System is engineered by the Vendor based on information supplied by Engineer. Which documents are needed by the Vendor?
Engineering documents
Vendor documents
© 2015 – Hervé Baron
HERVE BARON
Process Control System
Process Control System Engineering by Vendor
Hardware Software The Process Control System is engineered by the Vendor based on information supplied by Engineer. Which documents are needed by the Vendor?
Vendor documents
P&IDs
Control Narratives
Cause & Effects
© 2015 – Hervé Baron
HERVE BARON
Process Control System
Process Control System Engineering by Vendor
Hardware Software The Process Control System is engineered by the Vendor based on information supplied by Engineer.
P&IDs
Control Narratives
Cause & Effects
Packages with Unit Control System:
Exchange table with PCS
P&IDs
Control Narratives
Cause & Effects
Control & logic diagrams
Packages controlled by Central Control System:
© 2015 – Hervé Baron
HERVE BARON
Engineering disciplines: activities and deliverables
INSTRUMENTATION • Field instrumentation • Systems:
Process Control System Unit Control System Emergency Shutdown System Fire & Gas System Other systems
• Installation
© 2015 – Hervé Baron
HERVE BARON
Emergency Shutdown (ESD) System
© 2015 – Hervé Baron
HERVE BARON
Emergency shutdown (ESD)
© 2015 – Hervé Baron
HERVE BARON
Emergency shutdown (ESD) SIL study
Have you heard about SIL studies? What does it mean?
What does SIL, SIF and SIS mean?
Terms defined in ANSI/ISA-84.00.01-2004 (IEC 61511-1) Functional Safety: Safety Instrumented Systems for the Process Industry Sector
SIF: Safety Instrumented Function
SIS: Safety Instrumented System: Sensor + logic solver + final element
SIL: Safety Integrity Level: Level used for specifying the safety integrity requirement of SIFs. There are 4 levels:
© 2015 – Hervé Baron
HERVE BARON
Emergency shutdown (ESD) SIL study
Have you heard about SIL studies? What does it mean?
What does SIL, SIF and SIS mean?
Terms defined in ANSI/ISA-84.00.01-2004 (IEC 61511-1) Functional Safety: Safety Instrumented Systems for the Process Industry Sector
SIF: Safety Instrumented Function
SIS: Safety Instrumented System: Sensor + logic solver + final element
SIL: Safety Integrity Level: Level used for specifying the safety integrity requirement of SIFs. There are 4 levels:
© 2015 – Hervé Baron
HERVE BARON
Emergency shutdown (ESD) SIL study
Have you heard about SIL studies? What does it mean?
What does SIL, SIF and SIS mean?
ANSI/ISA-84.00.01-2004 (IEC 61511-1)
Functional Safety: Safety Instrumented Systems for the Process Industry Sector
SIF: Safety Instrumented Function
SIS: Safety Instrumented System: Sensor + logic solver + final element
SIL: Safety Integrity Level: Level used for specifying the safety integrity requirement of SIFs. There are 4 levels:
© 2015 – Hervé Baron
HERVE BARON
Emergency shutdown (ESD) SIL study
Have you heard about SIL studies? What does it mean?
What does SIL, SIF and SIS mean?
ANSI/ISA-84.00.01-2004 (IEC 61511-1)
Functional Safety: Safety Instrumented Systems for the Process Industry Sector
SIF: Safety Instrumented Function
SIS: Safety Instrumented System: Sensor + logic solver + final element
SIL: Safety Integrity Level: Level used for specifying the safety integrity requirement of SIFs. There are 4 levels:
© 2015 – Hervé Baron
HERVE BARON
Emergency shutdown (ESD) SIL study
Step 1: SIL Determination, “assignment workshop”
Identification of Instrumented Interlocks on the P&IDs = inventory of Safety Instrumented Function (SIF)
For each SIF: • Qualitative evaluation of consequences if the event the SIF is
designed to safeguard from • Qualitative evaluation of the likelihood of the event • Determination of risk level (likelihood * consequence) and
resulting SIF required performance (SIL level)
Deliverable: SIL assignment logsheet / worksheets
© 2015 – Hervé Baron
HERVE BARON
Emergency shutdown (ESD)
© 2015 – Hervé Baron
HERVE BARON
Emergency shutdown (ESD) SIL study
LIKELIHOOD CATEGORY DEFINITION POTENTIAL FREQUENCY
A Possibility of repeated incidents 20 or more times per Facility life B Possibility of isolated incidents 5 times per Facility life C Possibility of occurring sometime Once in Facility life D Not likely to occur Once every 10 Facility lives E Practically impossible Once every 100 Facility lives
CONSIDERATIONS CONSEQUENCE CATEGORY Health/Safety Public Disruption Environmental Impact Financial Impact
Abbreviation S – Safety P – Public E – Environmental F – Financial
I Fatalities/ Serious Impact on Public
Large Community (10,000+)
Major/Extended Duration/ Full Scale
Response
Major Impact to Company
(>$50 million)
II Serious Injury to
Personnel/ Limited Impact on Public
Small Community (1,000 to 10,000)
Serious/Significant Resource
Commitment
Significant Impact To Company ($2 - $50 million)
III Medical Treatment for Personnel/ No Impact
on Public
Minor (10 to 100)
Moderate/Limited Response of Short
Duration
Moderate Impact To Company
($500M - $2 million)
IV Minor Impact on Personnel
Minimal to None
(1 or 2)
Minor/Little or No Response Needed
Minor Impact To Company
($50M-$500M)
© 2015 – Hervé Baron
HERVE BARON
SIL Study
Step 1: SIL Determination, “assignment workshop”
Deliverable: SIL assignment logsheet / worksheets
Summary:
What is the second step of the SIL?
© 2015 – Hervé Baron
HERVE BARON
SIL Study
Step 2: calculations and recommendation
SIS Performance Verification
Evaluate the performance of each SIF, based on device selection, architecture, voting, testing etc.
Compare to required SIL level and specify modifications to the SIF design (device selection, component redundancy) or testing intervals
Deliverable: SIS Performance Verification Results and recommendations
© 2015 – Hervé Baron
HERVE BARON
SIL Study Step 2 – SIS Performance verification Results
© 2015 – Hervé Baron
HERVE BARON
SIL Study
Step 2: calculations and recommendation - Summary
© 2015 – Hervé Baron
HERVE BARON
Engineering disciplines: activities and deliverables
INSTRUMENTATION • Field instrumentation • Systems:
Process Control System Unit Control System Emergency Shutdown System Fire & Gas System Other systems
• Installation
© 2015 – Hervé Baron
HERVE BARON
Fire & Gas system
© 2015 – Hervé Baron
HERVE BARON
Fire & Gas system
© 2015 – Hervé Baron
HERVE BARON
Engineering disciplines: activities and deliverables
INSTRUMENTATION • Field instrumentation • Systems:
Process Control System Unit Control System Emergency Shutdown System Fire & Gas System Other systems
• Installation
© 2015 – Hervé Baron
HERVE BARON
Systems
The main systems are: the Process Control System (DCS), and Emergency Shutdown System (ESD),
usually integrated: ICSS (Integrated Control and Safety System) the Fire & Gas system (F&G)?
What other systems do we find?
What does SIL, SIF and SIS mean?
Terms defined in ANSI/ISA-84.00.01-2004 (IEC 61511-1) Functional Safety: Safety Instrumented Systems for the Process Industry Sector
SIF: Safety Instrumented Function
SIS: Safety Instrumented System: Sensor + logic solver + final element
SIL: Safety Integrity Level: Level used for specifying the safety integrity requirement of SIFs. There are 4 levels:
© 2015 – Hervé Baron
HERVE BARON
Systems
The main systems are: the Process Control System (DCS), and Emergency Shutdown System (ESD),
usually integrated: ICSS (Integrated Control and Safety System) the Fire & Gas system (F&G)?
What other systems do we find? Packaged equipment Control systems Machinery Monitoring System (MMS) for vibration & temperature monitoring Burner Management System (BMS) Compressor Anti-Surge System (CCC) Analyzers Data Acquisition system Fiscal Metering Systems afor Custody transfer and allocation Storage tank data acquisition (gauging) system Continuous Emissions Monitoring System (CEMS) Process Operator and Information System (POIS) / SCADA Advance Process Control (APC)
© 2015 – Hervé Baron
HERVE BARON
Engineering disciplines: activities and deliverables
PROCESS
PLANT LAYOUT
EQUIPMENT
SAFETY & ENVIRONMENT
CIVIL
PIPING
PIPELINE
INSTRUMENTATION • Field instrumentation • Systems • Installation
© 2015 – Hervé Baron
HERVE BARON
Field Instrumentation
PT JB
Process line
Field Marshalling
cabinet System
cabinet
Equipment room Control room
Operator
station
Secondary cable
Multi cable
© 2015 – Hervé Baron
HERVE BARON
Main cable routings and Junction Box (JB) location drawing
© 2015 – Hervé Baron
HERVE BARON
Instrument location & secondary cable routing drawings
© 2015 – Hervé Baron
HERVE BARON
Telecommunication equipment layout drawing
© 2015 – Hervé Baron
HERVE BARON
Typical installation drawings
© 2015 – Hervé Baron
HERVE BARON
Junction box wiring
© 2015 – Hervé Baron
HERVE BARON
Instrument location & secondary cable routing drawings Cable list
© 2015 – Hervé Baron
HERVE BARON
Cable routing / section
© 2015 – Hervé Baron
HERVE BARON
Instrumentation installation standards
© 2015 – Hervé Baron
HERVE BARON
Instrument bulk material take-off
ITEM QUANTITY DESIGNATION
1 195 Gauge adapter – ½” x ½”
2 37 Block manifold 2 valves (Gas) – ½”
3 23 Block manifold 5 valves (Gas) –½”
4 0 Ball valve ½” – 12mm
5 300m Tubing – 12mm OD x 1mm
6 200 Reducer – 12mm x ¼”
7 50 Union tee – 12 x 12 x 12mm
8 50 Female connector – 12mm x ½”
9 350 Male connector – 12mm x ½”
10 9 Plug – ½” NPTF
11 8 Plug – ½” NPTM
© 2015 – Hervé Baron
HERVE BARON
Equipment layout drawings
© 2015 – Hervé Baron
HERVE BARON
Instrument loop diagram
© 2015 – Hervé Baron
HERVE BARON
Main schedule Milestone for Instrumentation
The main schedule Milestones are the commitments to the Control System Contractor. There are 2 commitments: - Hardware freeze, for the manufacturing of the marshalling and I/O cabinets,
- Software freeze, for the configuration of the DCS
PT JB
Process line
Marshalling
Cabinet System
Cabinet
Secondary cable
Multi cable
Operator
station
© 2015 – Hervé Baron
HERVE BARON
Main schedule Milestone for Instrumentation
The main schedule Milestones are the commitments to the Control System Contractor. There are 2 commitments: - Hardware freeze, for the manufacturing of the marshalling and I/O cabinets,
- Software freeze, for the configuration of the DCS
© 2015 – Hervé Baron
HERVE BARON
Main schedule Milestone for Instrumentation
The main schedule Milestones are the commitments to the Control System Contractor. There are 2 commitments: - Hardware freeze, for the manufacturing of the marshalling and I/O cabinets,
- Software freeze, for the configuration of the DCS In your opinion, which Milestone is required to be reached first?
© 2015 – Hervé Baron
HERVE BARON
Main schedule Milestone for Instrumentation
The main schedule Milestones are the commitments to the Control System Contractor. There are 2 commitments: - Hardware freeze, for the manufacturing of the marshalling and I/O cabinets,
- Software freeze, for the configuration of the DCS In your opinion, which Milestone is required to be reached first? What are the Engineering documents required to reach each Milestone?
© 2015 – Hervé Baron
HERVE BARON
Main schedule Milestone for Instrumentation
The main schedule Milestones are the commitments to the Control System Contractor. There are 2 commitments: - Hardware freeze, for the manufacturing of the marshalling and I/O cabinets,
- Software freeze, for the configuration of the DCS In your opinion, which Milestone is required to be reached first? What are the Engineering documents required to reach each Milestone? What is challenging to meet the schedule?
© 2015 – Hervé Baron
HERVE BARON
The Oil & Gas Engineering Guide 2nd edition
Do you want to know more... Much more?
© 2015 – Hervé Baron
HERVE BARON
The Oil & Gas Engineering Guide - 2nd edition
Table of Contents
© 2015 – Hervé Baron
HERVE BARON
The Oil & Gas Engineering Guide - 2nd edition
Table of Contents
This suite of training modules covered the discipline chapters of the book...
© 2015 – Hervé Baron
HERVE BARON
The Oil & Gas Engineering Guide - 2nd edition
Table of Contents
The Guide contains much more:
The overall picture, interfaces, methods & tools, etc.
© 2015 – Hervé Baron
HERVE BARON
The Oil & Gas Engineering Guide 2nd edition
Order direct from the publisher:
http://www.editionstechnip.com/en/catalogue-detail/1111/oil-gas-engineering-guide-the.html