integrated pollution prevention and control (ippc)/waste ...the site boundary must be outlined on...
TRANSCRIPT
Galmoy Mines Ltd.
Integrated Pollution
Prevention and Control
(IPPC)/Waste Licensing
Review Form and Guidance
Note
for the purposes of
EC Environmental Objectives (Surface Waters) Regulations
2009
Environmental Protection Agency
P.O. Box 3000, Johnstown Castle Estate, Co. Wexford
Lo Call: 1890 335599 Telephone: 053-9160600 Fax: 053-9160699
Web: www.epa.ie Email: [email protected]
EPA Reg. No: (Office use only)
Introduction
INTRODUCTION
This Form is for the purposes of a review of an IPPC/Waste Licence in order to
ensure that all authorisations under the EPA Act 1992 to 2007 and the Waste
Management Acts 1996 to 2010 having discharges liable to cause water pollution
are in compliance with the EC Environmental Objectives (Surface Waters)
Regulations 2009.
While every effort has been made to ensure the accuracy of the material
contained in the Review Form, the EPA assumes no responsibility and gives no
guarantees; undertakings and warranties concerning the accuracy, completeness
or up-to-date nature of the information provided herein and does not accept any
liability whatsoever arising from any errors or omissions.
The Review Form and all supporting information shall be submitted to the
Headquarters of the Agency in a format of a signed original, one hardcopy and
two copies on CD-Rom. In cases where an Environmental Impact Statement
(EIS) is required in support of the Review Form, a signed original, one hardcopy
plus 16 copies (or 18 copies if the activity is within Energy sector) on CD-Rom
shall be submitted.
All pages, including maps/drawings/plans, shall be no larger than A3 size. All
files on CD-Rom shall be submitted in searchable PDF format and be no larger
than 10MB each in size. All CD-Roms shall be labelled with the Licensee’s name,
Licence Register Number, address of the activity and name of the file (i.e.
Review Form).
Introduction
CONTENTS
SECTION A: GENERAL ....................................................................................... 1
SECTION B: EMISSIONS ................................................................................... 3
SECTION C: CONTROL & MONITORING .............................................................. 8
SECTION D: EXISTING ENVIRONMENT & IMPACT OF THE
ACTIVITY ....................................................... ............................ ..15
SECTION E: STATUTORY REQUIREMENTS ........................................................ 38
SECTION F: APPROVED ADJUSTMENTS & CONDITIONS .................................... 44
SECTION G: DECLARATION ............................................................................. 46
ANNEX 1: TABLES/ATTACHMENTS ................................................................... 47
Galmoy Mines Ltd.
1
SECTION A: GENERAL
A.1 Licensee
Name*: Galmoy Mines Ltd
Address: Galmoy via Thurles
Galmoy
Co Kilkenny
IPPC Licence P0517-01
Tel: 056 8837100
Fax: 056 8837105
e-mail: [email protected]
* This should be the name of the Licensee which is current on the date this IPPC/Waste
Licence Review Form is lodged with the Agency. It should be the name of the legal entity
(which can be a limited company or a sole trader). A trading/business name is not
acceptable.
Name and Address for Correspondence
Only documentation submitted by the Licensee and by the nominated person will be deemed to
have come from the Licensee.
Name: Galmoy Mines Ltd
Address: Galmoy via Thurles
Galmoy
Co Kilkenny
Tel: 056 8837122
Fax: 056 8837105
e-mail: [email protected]
Address of registered or principal office of Body Corporate (if applicable)
Address: Lundin Mining Corporation
Company Registered Number: 131188
Corporate Head Office
150 King Street West,
Suite 1500, PO Box 38
Toronto, ON M5H 1J9
Company
Register No.
Lundin Mining Corporation
131188
Tel: 00 1 416 342 5560
Fax: 00 1 416 348 0303
e-mail: [email protected]
Galmoy Mines Ltd.
2
A.2 Location of Activity
Name: Galmoy Mines ltd
Address*:
Castletown, Whiteswall, Rathreargh,
Garrylaun and Rathpatrick
Galmoy
Co Kilkenny
Tel: 056 8837100
Fax: 056 8837105
Contact Name: Peter Small
Position: Mine Manager
e-mail: [email protected]
* Include any townland.
National Grid Reference
(12 digit 6E,6N)
E 227 329 N 173 226
Location maps (no larger than A3), appropriately scaled, with legible grid references should
be enclosed in Attachment No A.2. The site boundary must be outlined on the map in red
colour.
Geo-referenced digital drawing files (e.g. AutoCAD files) in Irish Grid projection of the site
boundary and overall site plan, including labelled emission points to surface water and
their monitoring and sampling locations, are also required.
Galmoy Mines Ltd.
3
SECTION B: EMISSIONS
B.1 Emissions to Surface Waters &/or Ground
Historically Galmoy Mines Ltd extracted and processed minerals (lead and zinc) from four
Orebodies (G, K, R and CW). The ore was processed in the mill to produce separate lead
and zinc concentrates. This was achieved by crushing, grinding, flotation and dewatering.
Separation of the zinc and lead minerals from the host rock took place in a flotation
process with lead being removed first using aeration and reagents. A similar process was
repeated for the removal of zinc. The resulting products were dewatered and stored
ready for shipment to smelters abroad. The tailings produced in this process were either
pumped to the tailings impoundment dam or mixed with cement and pumped
underground as a backfill paste.
In May 2009, due to economic circumstances, Galmoy Mines Ltd ceased production. The
Mine Closure Plan was implemented in early June 2009 and the mill processing plant and
surface ancillaries were dismantled and removed from the mine plant site.
Mining has since ceased in October 2012 with the underground pumps switched off in a
phased manner, with the final pumps in the G orebody turned off in March 2013.
Groundwater levels are currently recovering to natural levels and should conservatively
be fully recovered by 2015 based on modelling predictions by K.T. Cullen (1992).
Progressive restoration of the Tailings Management Facility (TMF) is ongoing. Phase 1
was completed in 2011 and Phase 2 will be completed in 2013. An integrated constructed
wetland is proposed for the Phase 3 of the TMF in 2013.
Photo 1 –Rehabilitation works showing capped TMF prior to spreading of topsoil on the
glacial till cap.
Galmoy Mines Ltd.
4
Photo 2 –Phase 1 of the Rehabilitated TMF
Photo 3 – Weir from Phase 2 to Phase 3 with TMF rehabilitation in background and
HDPE lined phase 3 in the foreground
Galmoy Mines Ltd.
5
Photo 4 – Mowing grass for silage on Phase 1 of the Rehabilitated TMF – 2012 and
cattle grazing in the background.
Historically Clean Water (GW1) was segregated and pumped to the surface for
treatment, re-use or disposal. Groundwater entering the mine through fissures was
collected and pumped to a conditioning pond on the surface. This water was intercepted
before entering the mine workings to ensure that it was not contaminated. After
conditioning, this water was used for augmenting the flow in local streams including the
Glasha and mixed with treated mine water as final Discharge effluent (SW1).
In April 2010 the stream augmentation to the Coady’s Castle stream which feeds into the
Glasha River (Referred to as the Rathdowney River in the WFD) ceased on instruction
from the EPA, as clean water could no longer be collected and segregated from
underground sources. The proposed discharge to the Glasha will in part replace the SW1
discharge to the River Goul along with restoration of groundwater baseflow to the river
following recovery of groundwater levels.
Previously, Treated Mine Water (PS3) and Treated Process Water (PS5) were discharged
to the River Goul (SW1). As the mine is no longer mining and processing ore and is not
abstracting groundwater, the volume and flow is greatly reduced. It is proposed to retain
the discharge point to the River Goul pending the development of an alternative
enterprise on the industrial site, however the volume and effluent loading is <10% of the
Licenced discharge and will be subject to the approval of the Local Authority and the
EPA.
As part of the rehabilitation plan, surface water runoff generated from the rehabilitated
TMF will discharge to the River Glasha at SW2. Extensive measures are in place to
Galmoy Mines Ltd.
6
minimise any potential impact of the discharge from the TMF. Phase 1 and Phase 2 of the
TMF will be capped for the purpose of grazing cattle and any runoff from the capped
rehabilitated area will be treated by a constructed wetland system in Phase 3 of the TMF.
The wetland system will further reduce metal and organic concentrations from Phases 1
and 2. Previous information submitted as part of the TMF rehabilitation studies have
indicated the low leachability of the tailings and the absence of acid mine drainage1.
The installation of the wetland in Phase 3 is designed treat the surface water from phase
1 and phase 2. The location of the wetland within phase 3 will reduce the footprint of the
tailings runoff area and cap Phase 3 at the same time. However, the treated runoff to be
generated by the site contains primarily agricultural runoff with some shorter term runoff
of water from the interface of the cap which contains compost (Phase1) and the tailings
surface.
Based on the assimilative capacity study, the discharge at SW2 will meet the criteria as
set out in S.I. 272 of 2009 in the River Glasha for most parameters. An Appropriate
Assessment of the potential impact on the River Nore SAC is included as part of this
report. In conclusion there is a negligible impact on the River Nore SAC. It is considered
that no significant adverse effects will arise from the proposed surface water discharge
from the TMF at Galmoy Mines to the stream and that this development can be screened
out from further Appropriate Assessment or EIS.
A summary list of the emission points, together with maps/drawings (no larger than A3)
and supporting documentation should be included as Attachment No B.1.
1 Golders, 2011 – TMF Rehabilitation and Closure Plan
Galmoy Mines Ltd.
7
B.2 Tabular Data on Emission Points to surface water
Licensees should submit the following information for each emission point to surface
water:
Point Code Easting Northing Verified Emission
SW1
Surface
Emission
Point
E227329 N173226 Y Suspended solids,
Lead, Zinc,
Cadmium, Arsenic,
Ammonia (as
N), Nitrate (as N),
Nitrite (as N),
Biochemical oxygen
demand,
Copper,
Sulphate,
Orthophosphate (as
P)
SW 2 226439 170638 Y Suspended solids,
Lead, Zinc,
Cadmium, Arsenic,
Ammonia (as N),
Nitrate
(as N), Nitrite (as N),
Biochemical oxygen
demand, Copper,
Sulphate,
Orthophosphate (as
P), Total Alkalinity
* SW = Surface Water
An individual record (i.e. row) is required for each emission point. Acceptable file formats
include Excel, Access or other upon agreement with the Agency.
Galmoy Mines Ltd.
Page 8
SECTION C: CONTROL & MONITORING
Describe the proposed technology and other techniques for preventing or,
where this is not possible, reducing emissions from the installation/facility.
C.1 Treatment, Abatement and Control Systems
An overview/summary of treatment/abatement systems for effluent emissions should be
included together with schematics as appropriate.
For each Surface Water Emission Point identified complete Table C.1(i).
Supporting information should form Attachment No C.1.
Normal operation and variations for start-up and shutdown should be described.
Anticipated malfunctions and known problems associated with the treatment should be
highlighted.
Proposed monitoring to be undertaken for influent(s) to treatment plant, and in-
treatment monitoring required for the management of the treatment plant should be
detailed.
C.1 Treatment, Abatement and Control Systems
Wetlands
It is proposed to treat runoff from the Phase 1 and 2 of the rehabilitated TMF by means of
a constructed wetland system (located in Phase 3) and a surface water attenuation
lagoon. Constructed wetland treatment systems are engineered systems designed and
constructed to utilize the natural processes involving wetland vegetation, soils, and their
associated microbial assemblages to assist in treating wastewater. They are designed to
take advantage of many of the same processes that occur in natural wetlands, but do so
within a more controlled environment. Constructed wetlands consist of former terrestrial
environment that have been modified to create poorly drained soils and wetlands flora
and fauna for the primary purpose of contaminant or pollution removal from wastewater.
Constructed wetlands are essentially wastewater treatment systems and are designed
and operated as such, though many systems do support other functional values.
A major part of the treatment process for degradation of organics is attributed to the
microorganisms living on and around the plant root systems. Once microorganisms are
established on aquatic plant roots, they form a symbiotic relationship in most cases with
the higher plants. This relationship normally produces a synergistic effect resulting in
increased degradation rates and removal of organic compounds from the wastewater
surrounding the plant root systems. Also, microorganisms can use some or all
metabolites released through plant roots as a food source. By each using the others
waste products, this allows a reaction to be sustained in favor of rapid removal of
organics from wastewater.
Galmoy Mines Ltd.
9
Wetland trial data by VESI Environmental Ltd. (included in Attachment C.1.) and
reference material indicates that high removal rates of organics and metals are
achievable. Controls systems will be incorporated to ensure optimum removal of lead and
zinc, and suspended solids from the surface water. Suspended Solids are removed from
solution by the physical act of settling via large hydraulic resident times in the lagoons.
The lagoons within the wetland are laid out in a series to increase the retention of
suspended soils and allow for an even well distributed water flow. Following treatment of
surface water in the constructed wetlands, water will flow towards the surface water pond
to the north. Further settlement and treatment will occur in the settlement pond. The
treated water will be discharged via an outfall pipe to the Glasha River.
Once the water is discharged from the wetland at PS 9, the water will be discharged to
the Glasha Stream provided the water meets the allowable discharge quality.
As an interim measure while the wetland is being established and in the unlikely event
that water quality does not meet the discharge standards, water from PS 9 will be
recycled back to the Galmoy water treatment plant for further treatment.
Attenuation Pond (Surface Water Lagoon)
The attenuation pond will be located downstream from the wetlands on the North West
corner of Phase 2 and will be used for final polishing prior to discharge into the Glasha
Stream. It is expected that water quality of the influent into the attenuation pond will
meet EPA guidelines.
The surface area of the attenuation pond is approximately 2.4Ha. All the material from
the excavation works was used to construct the dome of Phase 2. The depth of the pond
will be variable due to the undulating nature of the limestone bedrock below the glacial
till. Based on current activities, the average depth of the attenuation pond will be
approximately 2 metres2. The attenuation pond capacity is 50,000m3.
2 Golders 2011 - TMF Rehabilitation and Closure Plan
Galmoy Mines Ltd.
10
No
PS 9 -Water quality meets standards?
Yes
Phase 2- Rehabilitated TMF
River Glasha Sampling of Glasha @ ASW3
Attenuation Pond
Phase 3 – Constructed Wetland
Phase 1- Rehabilitated
TMF
PS 9
Water
Treatment
Plant
SW 1
Galmoy Mines Ltd.
11
C.2 Monitoring and Sampling Points
Identify monitoring and sampling points and outline proposals for monitoring emissions to
surface water bodies.
Table C.2(i) should be completed (where relevant) for emissions to surface water.
Where ambient environment monitoring is carried out or proposed, Table C.2(ii) should
be completed as relevant for each environmental medium and at least 12 samples should
be taken at regular intervals.
Include details of monitoring/sampling locations and methods.
Supporting information should form Attachment No C.2.
C.2 Monitoring and Sampling Points
Currently there are ten monitoring and sampling points outlined in IPPC Licence P0517-
01, Technical Amendment B and EPA correspondence P0517-01/ap23pos{GW1}.docx for
monitoring. These include Mine Water (PS1), Reclaim Water (PS4), Treated Mine Water
(PS3), Lamella, Treated Process Water (PS5), Effluent Pond Discharge (PS8) and
Discharge Effluent (SW1). Effluent Pond Discharge is a combination of Treated Mine
Water, Lamella and Treated Process Water. The locations of the monitoring points are
outlined in Drawing B-1. Ambient monitoring points are located at ASW1 (upstream) and
ASW2 (downstream) and are outlined in Drawing C-2. Many of these monitoring points
will become redundant and will be retired as part of the Mine Closure Plan (MCP). PS1,
PS4, PS3 and PS5 monitoring points will no longer apply as all processing of materials
and pumping and treatment of mine water will cease very soon.
As the proposal outline will deal with discharge of the treated surface water from the
surface of the TMF to the Glasha River, an additional 3 monitoring locations will be
required. PS9 treated water from the wetland, SW2 (discharge from attenuation pond)
and ASW3 (downstream monitoring on the Glasha River) as outlined in the monitoring
programme and aftercare management plan.
During each working week visual checks are carried out by the Environmental
Department on a daily basis to ensure that the Water Treatment Systems are functioning
correctly. These checks are recorded on the Daily Environmental Site Sheet. This
monitoring process is supported by daily checks carried out and recorded by the on duty
Environmental Staff to ensure compliance with IPPC licence. This monitoring process is
supported by daily checks carried out and recorded by the on duty Water Treatment
Operator (WTO) every day of the week. Two hourly checks are carried out by the WTO on
parameters in the Lamella, Mine Water and Reclaim Water Treatment Plants which
include pH, ferric sulphate, flocculant, water clarity and underflows and two checks (at
10am and 10pm) for pH are carried out at Discharge Effluent and Effluent Pond Discharge
to ensure compliance with IPPC licence.
Galmoy Mines Ltd.
12
C.3 Tabular Data on Monitoring and Sampling Points
Licensees should submit the following information for each monitoring and sampling
point:
Point Code Point Type Easting Northing Verified Pollutant
Provide label
ID’s
M=Monitori
ng
S=Sampling
6E-digit
GPS Irish
National
Grid
Reference
6N-digit
GPS Irish
National
Grid
Reference
Y = GPS
used
N = GPS
not used
e.g.
Ammonia
(as N),
Biochemical
oxygen
demand
An individual record (i.e. row) is required for each monitoring and sampling point.
Acceptable file formats include Excel, Access or other upon agreement with the Agency.
Point source monitoring/sampling refers to monitoring from specific emission points (e.g.
from a wastewater treatment plant). Ambient monitoring includes monitoring of river
quality upstream/downstream of an effluent discharge.
Galmoy Mines Ltd.
13
C.3 Tabular Data on Monitoring and Sampling Points
Point
Code
Point Type Easting Northing Verifie
d
Pollutant
SW1
Surface
Emission
Point
E227329 N173226 Y Suspended solids, Lead, Zinc,
Cadmium, Arsenic, Ammonia
(as N), Nitrate (as N), Nitrite
(as N), Biochemical oxygen
demand, Copper, Chemical
oxygen demand, Sulphate,
PS1 Emission
Point
E227342 N172839 Y Suspended solids, Lead, Zinc,
Nitrate (as N), Nitrite (as
N),Ammonia (as N), Chemical
Oxygen Demand, Sulphate,
Mercury, Arsenic, Cadmium,
Aluminium, Iron, Copper,
Magnesium and Chromium
PS4 Emission
Point
E227368 N172825 Y Suspended solids, Lead, Zinc,
Nitrate (as N), Nitrite (as
N),Ammonia (as N), Chemical
Oxygen Demand, Sulphate,
Mercury, Arsenic, Cadmium,
Aluminium, Iron, Copper,
Magnesium and Chromium
ASW1 Ambient
Monitoring
E6230031 N170170 Y Suspended solids, Lead, Zinc,
Cadmium, Arsenic, Ammonia
(as N), Nitrate (as N), Nitrite
(as N), Iron, Copper, Sulphate,
Orthophosphate (as P), Total
Alkalinity
ASW2
Ambient
Monitoring
E230386 N170243 Y Suspended solids, Lead, Zinc,
Cadmium, Arsenic, Ammonia
(as N), Nitrate (as N), Nitrite
(as N), Iron, Copper, Sulphate,
Orthophosphate (as P), Total
Alkalinity
PS 9 Ambient
Monitoring
E226544 N170638 Y Suspended solids, Lead, Zinc,
Cadmium, Arsenic, Ammonia
(as N), Nitrate (as N), Nitrite
(as N), Iron, Copper, Sulphate,
Orthophosphate (as P), Total
Alkalinity
SW2 Emission
Point
E226735 N172626 Y Suspended solids, Lead, Zinc,
Cadmium, Arsenic, Ammonia
(as N), Nitrate (as N), Nitrite
(as N),Iron, Copper, Sulphate,
Galmoy Mines Ltd.
14
Point
Code
Point Type Easting Northing Verifie
d
Pollutant
Orthophosphate (as P), Total
Alkalinity
ASW3 Ambient
Monitoring
E226964 N173716 Y Suspended solids, Lead, Zinc,
Cadmium, Arsenic, Ammonia
(as N), Nitrate (as N), Nitrite
(as N), Iron, Copper, Sulphate,
Orthophosphate (as P), Total
Alkalinity
PS1 & PS4 will no longer be water sources at Galmoy Mines
Galmoy Mines Ltd.
15
SECTION D: EXISTING ENVIRONMENT & IMPACT OF THE ACTIVITY
D.1 Assessment of Impact
Describe the existing environment in terms of water quality with particular reference to
environmental quality objectives and standards as specified in the EC Environmental
Objectives (Surface Waters) Regulations 2009 S.I. No. 272 of 2009. Table D.1(i) should
be completed as appropriate.
Indicate whether or not the activity complies with the requirements of the EC
Environmental Objectives (Surface Waters) Regulations 2009 S.I. No. 272 of 2009 and
the EC Environmental Objectives (Groundwater) Regulations 2010 S.I. No. 9 of 2010.
The Licensee should conduct an assessment of impact of discharge(s) from the
installation/facility on receiving surface water and/or groundwater. In undertaking this
assessment the Licensee shall have particular regard to substances used in the
manufacturing processes likely to result in discharges. The licensee shall have regard for
the environmental quality objectives and standards specified for protected areas and/or
the standards specified in the Schedules of the EC Environmental Objectives (Surface
Waters) Regulations 2009 S.I. No. 272 of 2009. When completing any assimilative
capacity calculations have regard to the Water Services Training Group ‘Guidance to
Applicant – Discharge to Surface Waters’ available at
http://www.wsntg.ie/publications/index.asp and other standard guidance.
If the process discharges are to coastal, transitional waters or lakes, the assessment may
require a modelling study. The modelling study shall include estimates on what the
resultant concentrations of the permitted substances in the receiving water body will be
upon discharge at the current licence limits.
Regardless of the receiving water body type, determine the maximum allowable
discharge concentrations to achieve compliance with the 95%ile good status limits. N.B.
If the discharge is to a water body that is already achieving high status, or if the
discharge is to waters draining to the surface water bodies identified under the First
Schedule of the EC Environmental Objectives (Freshwater Pearl Mussel) Regulations
2009, compliance must be with 95%ile high status limits.
State distance from the process discharges to a nearest downstream water dependent
Protected Area. Include the name and code of this Protected Area.
Full details of the assessment, including a copy of an Environmental Impact Statement if
it was required for the purposes of obtaining planning permission(s), should be submitted
as Attachment No D.1.1.
Where necessary, the Licensee should supply detailed information on the proposals to
comply with the requirements of the EC Environmental Objectives (Surface Waters)
Regulations 2009 S.I. No. 272 of 2009 including a detailed timeframe for any proposed
works in Attachment No D.1.2.
Galmoy Mines Ltd.
16
D.1 Assessment of Impact
An extensive monitoring programme has been ongoing since 1996 to assess the impact
of mining activity on receiving surface water and to examine relevant aspects of the
surface water environment in the vicinity of the Galmoy Mines Ltd. The work programme
involves individual ongoing surveys of streams and rivers and documents their water
quality, biotic status, flow regimes and beneficial uses in order to define the basic
characteristics of the local freshwater environments.
The Galmoy Mines mining project is located within the townsland of Castletown,
Whiteswall, Rathreargh, Garrylaun and Rathpatrick close to the village of Galmoy in
North County Kilkenny (Drawing A-2).The area lies in the watershed of the Erkina River a
tributary of the River Nore. The River Glasha to the north and River Goul to the east are
both tributaries of the River Erkina.
The water body is located within the Special Area of Conservation 20 of the Nore River
Basin District (SAC 002162). The Erkina system consists of a network of tributaries
draining an area of approximately 387 km2 at Durrow. The Goul rises in the Slieve
Ardagh Hills and flows for 38km through Urlingford to Ballyboodin (near Durrow). The
Glasha River rises close to Galmoy and flows to the north towards Rathdowney and the
confluence with the River Erkina.
The treated water from the mining operations is discharged to the River Goul. Following
the cessation of mining and the turning off the groundwater pumps and following the
construction of the wetland the discharge to the River Goul will reduce by over 90%. The
current discharge point is approximately 350m west of Fertagh Bridge (Drawing C-2).
Consequently, the Goul system has been studied in greater detail.
The north and west of the site drain to tributaries of the Glasha Stream, which drains to
the north, into the River Erkina, which then flows eastwards towards the River Nore. In
accordance with the Mine Closure Plan schedule the discharge to the River Goul will cease
in 2013. The proposed discharge point from the TMF, as outlined in earlier application, is
the adjacent Glasha Stream via the wetland treatment system and the attenuation pond.
The catchment area for the Glasha Stream, the Glasha Stream in the vicinity of the TMF
and the TMF are given below:
• Total catchment area of the Glasha Stream is approximately 1,300 Hectares;
• Catchment area of the Glasha Stream at the discharge point is 335 Hectares; and
• Surface catchment area of the TMF excluding the downstream and wetland walls is
23.4 Hectares.
Surface Area of top embankment of TMF is 33.64 Ha. Phase 1: 9.36 Ha. Phase 2: 14.02
Ha. Phase 3: 8.285 Ha. Total Footprint of TMF is 33.745 Ha. Areas are calculated based
on the EPA Hydrotool for the total catchment and the discharge location while the TMF
area is based on the surveyed data from Galmoy (Q4, 2012).
An appropriate assessment was undertaken on the River Glasha and the potential impact
on the River Nore SAC located. The Glasha flows into the Erkina River and eventually
Galmoy Mines Ltd.
17
flows into the River Barrow and Nore SAC/SPA. The approximate distance of the
discharge point to the River Barrow and Nore SAC is 13km. The approximate distance to
the River Nore SPA is 16km. The potential impact of the surface water discharge is
negligible and will not affect the WFD target of reaching good status by 2021.
Water Flow
Historical hydrometrics data in this region is moderate. There are no active hydrometric
stations within the Glasha Catchment with one inactive staff gauge at Glasha Cross
Roads. The nearest EPA monitoring station is at Glasha Cross Roads on the River
Rathdowney, approximately 4km downstream from the site boundary.
A baseline survey and a hydrometric monitoring program were undertaken as part of the
EIS for the development in 1992. The hydrometric stations were installed at Coadys
Castle, Glasha Cross Roads and on the River Goul to the south. Data is also available for
mean runoff from Phase 1 of the TMF in 2012.
Equations to estimate low flows based on catchment areas (Martin and Cunnane (1977),
MacCarthaigh, 2002) are available and are calculated as part of the project. However,
these equations are largely guided by the values plotted for the larger catchments, that
the percentage scatter among values for small catchment is very large and that these
equations cannot be used reliably for low flow on small catchment areas (Brogan and
Cunnane, 2005).
Hydrometric Data
A search of the Register of Hydrometric Stations in Ireland found the nearest flow
gauging stations on the River Glasha, downstream of Galmoy. The EPA, operates both
stations and details are provided in Table 1 below and shown in Figure 1-1 (Attachment
B.1.).
TABLE 1 LOW FLOW CHARACTERISTIC FROM RELEVANT GAUGING STATIONS
Station
Number
Waterbo
dy Location
DTM
Area
[Km2]
DWF
(m³/
s)
95
%ile
(m³/s)
Mean
Station Type
15005 Erkina Durrow 387 0.4 0.75 5.7124 Data logger 1954-
present
15043 Erkina Coolkerry 136.8 0.05 0.1 Staff Gauge 1990-
1997
15056 Erkina Coneyburrow
Bridge 132 NA NA NA
Staff Gauge 2002-
present
15042 Glasha Glasha Cross
Roads 10.4 NA NA NA
Staff gauge only
1990-1998
18
Data from the Coolkeery and Coneyburrow gauging stations on the River Erkina are
for limited flow periods and does not cover the low flow periods of 1975-1976. Long
term data, DWF and 95%ile data from the River Glasha is not available from the
EPA/OPW for Glasha cross roads. Previous monitoring was undertaken prior to the
start of mining at Galmoy. Data is available from Galmoy mines between July 1992
and October 1992. The data corresponds to the low flow period for 1992.
TABLE 2 GLASHA STREAM FLOW MEASUREMENT JUL-OCT 19923
Waterbody Location
DTM
Area
[Km2]
Average
l/s
Maximum
Flow
l/s
Minimum
Flow
l/s
Glasha Glasha Cross
Roads 10.4 75.79 244.01 4.01
Glasha Coadys Castle 2.3 4.21 39.74 0.22
The monitoring station at Coady’s Castle is located <1km downstream of the mine.
The monitoring station at Glasha Cross Roads is 2 km downstream of the Mine
consists of a staff gauge. Summary data from the station at Coady’s Castle and
Glasha cross roads corresponded to Dry Weather period in 1992 based on the
information from Durrow see Figure in Attachment B.1.
FIGURE 1 FLOW MONITORING AT DURROW GAUGING STATION 1992 - M3/SEC
3 Based on KT Cullen 1992
Corresponding 1992
Monitoring period at
Coady’s Castle and Glasha
cross roads
Galmoy Mines Ltd.
19
While the data for 1992 corresponds to low flow in 1992, data from Durrow and
rainfall data for 1992 suggests that the 95%ile and DWF will be lower for both
Coady’s castle and Glasha cross roads. Additionally applying the methodology as
outlined in Mundal and Cunnane (2009) the SAAR and MF calculations are included
in Table 3 below.
TABLE 3 MEAN AND 95%ILE FLOW ESTIMATES
Location Data source
DTM
Area
[Km2]
DWF
(litre/s)
95 %ile
(litre/s)
Mean
(litre/s)
Tailings Area
Phase 1 and 2
Area
0.234
SAAR4 NA 0.595
MF 5 NA 0.305
Pro-rata – Durrow
gauging station6 0.242 0.429 3.454
Pro rata- Hydrotool7 NA 0.534
Low limits of confidence -
Hydrotool NA 0.36
Upper limits – Hydrotool NA 0.79
Discharge Point-
Glasha
Area
3.35
SAAR 7.28
MF 4.37
Pro-rata – Durrow
gauging station 3.46 6.14 49.44
Pro rata- Hydrotool 7.64
Low limits of confidence -
Hydrotool 5.09
Upper limits – Hydrotool 11.28
A flow recording device will be installed at the discharge location SW2 by Galmoy
mines Ltd. In conjunction flow monitoring data for the River Glasha will be
recorded at Duggan’s Bridge. Flow monitoring at Phase 1 and Phase 2 has been
undertaken since 2011. A total of 76 flow measurements were taken from the thin
crested V shaped weir at Phase 1 in 2012. Data for Phase 1 in 2012 indicates that
the average flow rate is 1.23 l/s in comparison to a predicted mean flow of 1.38 l/s
based on longer term data from Durrow gauging station. Variances in mean flow
are accounted for by different flow monitoring periods and lower soil moisture
deficits in the summer of 2012.
4 As per empirical formulas, Mundal and Cunnane, 2009
5 As per empirical formulas, Mundal and Cunnane, 2009
6 Based on prorata flows at Durrow gauging station
7 Area = 9.2 km2
Galmoy Mines Ltd.
20
For the purposes of the assimilatory capacity calculations it is proposed to use the
pro-rata mean data based on the Long term data from Durrow gauging station.
Calculation based on the 95 %ile assimilative capacity are also included but are less
crucial in this case as the 95%ile flows from the tailings will decrease in proportion
to decreasing rainfall unlike a discharge from a typical Wastewater treatment plant.
Again the 95%ile is calculated based on a prorata basis.
It is likely that the pro-rata approach will be highly conservative for the 95%ile
data. River flow can be divided into two main components:
• Surface runoff from rainfall, and
• Baseflow recession from groundwater storage.
Surface runoff results from rainfall, resulting in an increase in river flow with rainfall
and a reduction when rainfall ceases. The baseflow recession is that part of the
river flow which comes from groundwater storage. In general there is a gradual
decrease in groundwater discharge during dry periods. The groundwater storage of
the moderately permeable subsoils (10-5 to 10-6 m/sec) and aquifer contributing to
Coady’s Castle is higher than the low permeability tailings and cap material (10-9
m/sec). As a consequence run off from the tailings cap will be primarily surface
water runoff with a minor component of baseflow. To illustrate this point a
calculation of groundwater infiltration was completed for Galmoy. The main
parameters involved in the estimation of recharge/groundwater infiltration are:
annual rainfall; annual evapotranspiration; and a recharge coefficient. The recharge
coefficient is estimated using Guidance Document GW5, Groundwater Working
Group 2005. The recharge over the extreme and high vulnerability areas and
moderately permeable till, peat and rock close to or at surface is in the order of
70% with 30% surface water runoff. Recharge/groundwater infiltration over the
tailings is lower at an estimated 25% with 75% runoff.
The recharge calculations are summarised as follows:
TABLE 4 RECHARGE CALCULATIONS FOR TAILINGS AND GALMOY AREA RECHARGE
CALCULATIONS FOR TAILINGS AND GALMOY AREA
Coady’s Castle area Tailings Phase 1 & 2
Average annual rainfall
(R)
826 mm 826 mm
Estimated A.E. (95% of
P.E.)
322 mm 322 mm
Effective rainfall
potential recharge
404 mm 404 mm
Recharge coefficient 70% 25%
Baseflow during low flow periods will be controlled and adjusted to mimic the
overall catchment by the storage in the constructed wetland and attenuation pond.
Galmoy Mines Ltd.
21
RUNOFF WATER QUALITY
Available qualitative and quantitative data for the River Glasha, in conjunction with
chemical monitoring results of the rehabilitated TMFs from Galmoy, form the basis
for the assimilative capacity calculations. Quality Data from Tailings Area 1 for 2012
are included below in Figure 1-6.
The water chemistry at the TMF taken from 2012 and 2013 show the following:
• pH concentrations are stable and between 7 and 8.5 pH units.
• Ammonia concentrations are significantly elevated above normal
background levels ranging from <0.05 mg/l as N to 86mg/l as NH4. This
is attributed to high ammonium content in the organic material used to
improve the growing medium on the capping layer. Low concentrations
of Nitrate in the runoff indicate reducing conditions in the organic
material.
• Dissolved oxygen concentrations are increasing since January 2012
possibly as a result of stabilisation of organic material in the TMF capping
layer. Dissolved Oxygen saturation levels are ~100%.
• Phosphate levels are consistently low with all runoff containing <0.02
mg/l.
• Concentrations of trace metals and in particular lead are low and
decreasing in the runoff from the TMF. Lead concentrations have
consistently decreased and are currently <10 µg/l. However some
isolated spikes are noted. Concentrations of arsenic were 55 µg/l on
average. Elevated concentrations appear to correlate to low flows.
• Sulphate concentrations were elevated at various periods which are
caused by oxidation of sulphite. Concentrations decreased to <500 mg/l
outside of the capping works. Elevated concentrations of Sulphate
appear to be correlated to lower flows (0.52).
• BOD and COD concentrations are decreasing and generally less than 5
mg/l since May 2012.
• Variations in runoff water quality appear to reflect rainfall patterns based
on the available data. Elevated concentrations of Ammonium appear to
be correlated to lower flows (0.37). Elevated Metals also appear to be
associated with lower flows while dissolved oxygen levels appear to be
correlated with higher flow rates.
Galmoy Mines Ltd.
22
FIGURE 2 NITRATE (NO3) AND AMMONIUM CONCENTRATIONS (NH4) AT TMF
Ammonium concentrations are highly variable in early 2012. A noticeable decrease
occurred since May 2012 however a spike in concentrations occurred in
August/September 2012. Concentrations in January - February 2013 (average 4.07
mg/l) were greatly reduced to the same period in 2012 (average of 61.85 mg/l).
FIGURE 3 ZINC AND IRON CONCENTRATIONS AT TMF
Galmoy Mines Ltd.
23
FIGURE 4 CONDUCTIVITY AND SULPHATE CONCENTRATIONS
Figure 5 COD and BOD concentrations at TMF
Galmoy Mines Ltd.
24
FIGURE 6 LEAD CONCENTRATIONS AT TMF
FIGURE 7 DISSOLVED OXYGEN (MG/L) AND PH CONCENTRATIONS AT TMF
Galmoy Mines Ltd.
25
FIGURE 8 SUSPENDED SOLIDS CONCENTRATIONS AT TMF
Data presented above corresponds to the data from 2012. Elevated concentrations
were noted in early 2012 however a noticeable decrease was noted since April
2012. It is anticipated that concentrations of sulphate, ammonium and organic
materials will decrease over the following years as the cap becomes established.
Based on the above the following averages were determined for runoff from the
TMF.
Concentrations of metals, ammonium and sulphate have decreased substantially
since October 2012(see recent data).
TABLE 5 PRE-TREATMENT WATER QUALITY FROM TAILINGS
Analyte units Average
Oct 2012
– Feb
2013
Average
Data
May 2012 –
Feb 2013
Conductivity uS/cm 793 1340
Sulphate mg/l 184 546
C.O.D. mg/l 60.35 109
T Ammonia mg/l 5.41 18.9
BOD mg/l 3.5 4.79
Zinc µg/l 248 284
Iron µg/l 320 478
Manganese µg/l 121 339
Potassium mg/l 14.5 29.5
Cadmium µg/l <1 <1
Galmoy Mines Ltd.
26
Analyte units Average
Oct 2012
– Feb
2013
Average
Data
May 2012 –
Feb 2013
Arsenic µg/l 36 62
Lead µg/l 9.3 17.5
pH pH units 7.61 7.64
D.O. mg/l 11.3 10.75
S.S. mg/l 19.5 108.8
Nitrate mg/l 4.5 7.74
Receiving water quality
Water quality data for the River Glasha available at Duggan’s Bridge (0.8 km
downstream) and Glasha Cross Roads (3.8 km downstream of Galmoy) were
assessed to characterise the background chemical and biological status of River
Glasha. Additional data is also provided in the extensive monitoring data of Galmoy
Mines in 1992. Monitoring data available pre and post mining is comparable in the
Glasha River. Chemical data is available for the mining period however while the
data is similar to pre/post mining concentrations; the surface water samples
includes augmentation flows and therefore not reflective of the natural surface
water quality. Biological, biotic and sediment data along with Q data of the Glasha
were undertaken on an annual basis during the operation of the mine (Aquens 1996
-2011).
TABLE 6 BACKGROUND SURFACE WATER QUALITY
units
Coady’s
Castle-
Average
pre mining
Glasha
Cross
Roads
Current
data
Conductivity uS/cm 727 729.64
Sulphate mg/l 28 141.91
C.O.D. mg/l 19 NA
T Ammonia mg/l 0.09 <0.05
BOD mg/l 2 NA8
Zinc µg/l 41 13.55
Ortho phosphate mg/l NA <0.02
Cadmium µg/l NA <1
Arsenic µg/l NA 4.00
Lead µg/l 7 2.33
pH pH units 7.8 7.56
D.O. mg/l NA 10.84
S.S. mg/l NA 8.44
8 Data from U/S of Rathdowney WWTP 2009 suggests BOD is approx 1.3 mg/l
Galmoy Mines Ltd.
27
Nitrate mg/l 15 14.82
Potassium mg/l NA 6.64
Iron µg/l NA 133
Surface water samples from 1992 and 2012/2013 show the following:
• Ammonia concentrations are elevated above normal background levels
ranging in 1992 and are greatly reduced during the current monitoring
period (<0.05 mg/l as NH4). The slightly elevated ammonium is
attributed to organic peat material present in 1992. However a sizeable
proportion of this material has been removed during the construction of
the TMF. Concentrations of Nitrate in the Glasha are comparable to pre
mining levels;
• Phosphate levels are consistently low with all runoff containing <0.02
mg/l;
• Concentrations of trace metals in the surface water reflect the presence
of a lead and zinc in the natural soils and geology of the area.
• pH concentrations are stable and between 7 and 8.5 pH units.
• Dissolved oxygen consistently high.
• Phosphate levels are consistently low at <0.02 mg/l.
• BOD and COD concentrations are generally below detection limits <2
mg/l.
Assimilative Capacity
The impact on the receiving water can be assessed by calculating the assimilative
capacity. Based on the discharge quality form the TMF runoff, a calculation of the
assimilative capacity was undertaken on the direct discharge to the Glasha River.
Most parameters as set out in the S.I. 272 of 2009 would be met in the discharge
with the exception of ammonium. The treatment provided in the wetlands and
attenuation pond will reduce the ammonium levels so that the assimilative capacity
for Good Status is achieved at the discharge point.
The Assimilative Capacity is calculated as follows:
Q(rev)C(rev) + Q(dis)C(dis) = C total (mg/l) Q(rev) + Q(dis)
Where: Q is the volume of flow/discharge
C is the concentration of indicator chemical parameters
(rev) is the receiving watercourse
(dis) is the discharge liquid)
(tot) is the mixed total.
The assimilative capacity of the receiving waters has been calculated using
available water quality data from the following sources:
• Estimation of the mean flow for the catchment area to point of
discharge;
• Water quality data from Duggan’s Bridge and Glasha Cross Roads;
Galmoy Mines Ltd.
28
• Nutrient parameters have been taken from runoff supplied by Galmoy.
These values do not take into account any further treatment in the
settlement lagoon.
• Treated effluent values have been taken from the treated runoff trial
where available, and guidelines values otherwise;
Available water quality data for the Glasha were used in the calculations. As
ammonium concentrations are below detection limits (<0.05) background
concentrations are assumed to be at nominally clean concentrations of 0.008 mg/l.
The results of the assimilative capacity calculations are included below for pre-
treatment and post treatment of the run-off water in the proposed wetland in the
Table 7 and 8 on the following page.
TABLE 7 PRE TREATMENT 95%ILE ASSIMILATIVE CAPACITY
Parameter
Units
Background Quality
Discharge Quality
Estimated Mean stream flow
l/s
Discharge m
ean Volume l/s Assimilative
Capacity
Relevant
standard
C total C Total
mg/l
SI 272 of
20099
Conductivity mS/c
m 727 1340 49.440 3.454 40571 767.03
Sulphate mg/l 141 546 49.440 3.454 8856.9 167.45
C.O.D. mg/l 19 109 49.440 3.454 1315.8 24.88
Total
Ammonical
Nitrogen
mg/l 0.00810 18.9 49.440 3.454 65.7 1.242 <0.065
BOD mg/l 1.311 4.79 49.440 3.454 80.8 1.53 <1.5
Zinc µg/l 43.6 284 49.440 3.454 3136.5 59.30 10012
Ortho
phosphate mg/l 0.02 0.02 49.440 3.454 1.1 0.02 <0.075
Cadmium µg/l 1 1 49.440 3.454 52.9 1.00
Arsenic µg/l 1.57 62 49.440 3.454 291.8 5.52 25
Lead µg/l 1.07 17.5 49.440 3.454 113.3 2.14 7.2
pH pH
units 7.64 7.64 49.440 3.454 404.1 7.64
9 Mean concentrations used as mean flow is the crucial parameter
10 Notionally clean river. Data from Rathdowney WWTP indicates upgradient BOD = 1.3mg/l
11 Notionally clean river
12 High Alkalinity in the surface water runoff <150 mg/l
Galmoy Mines Ltd.
29
Parameter
Units
Background Quality
Discharge Quality
Estimated Mean stream flow
l/s
Discharge m
ean Volume l/s Assimilative
Capacity
Relevant
standard
C total C Total
mg/l
SI 272 of
20099
D.O. mg/l 10 10.75 49.440 3.454 531.5 10.05
S.S. mg/l 20.77 108 49.440 3.454 1399.9 26.47
Nitrate mg/l 17.8 7.74 49.440 3.454 906.8 17.14
The elevated ammonium concentrations are a function of the type of organic material
used in the TMF cap. Ammonium concentrations in Phase 1 and 2 will reduce over the
following 1-2 years and fall below 5 mg/l on average based on recent data. To further
reduce the ammonium concentrations on the TMF cap, it is proposed to non-intensively
farm the rehabilitated TMF area. Nitrogen inputs will be below 170kg/hectare to help
achieve the objective of the Nitrates Directive (91/676/EEC) to curtail nitrate/ammonium
losses from agriculture to surface and ground waters. Concentrations of BOD are also
slightly elevated above the mean limits as set out in SI272 of 2009. Concentrations of
BOD in the runoff are likely to decrease over the following years once the tailings cap is
established.
Removal rates are of 98% removal efficiency for ammonium and 80% BOD are
anticipated in the wetland area and a removal rate of 50% for metals and sulphate based
on trial data (VESI Environmental Ltd.) and previous studies. Given the low loading rates
in the proposed wetland system the above removal rates can easily be achieved. Similar
and higher rates have been achieved in wetland systems in Ireland at Glaslough13 and in
wetlands treating tailings facilities and metals in motorway runoff14. The suitability of
Typha and Phragmites for treating metals is well known15. A range of emergent and
floating aquatic plants is recommended to enhance the biodiversity.
13
Glaslough ICW
http://www.dublincity.ie/WaterWasteEnvironment/WasteWater/Documents/Glaslough_ICW__Dan_Doo
dy_et_al_-_Feb_09__.pdf 14
Kadlec, R.H. and Knight, R.L (1996). Treatment Wetlands 15 EA UK (2003) Guidance Manual for Constructed Wetlands
Galmoy Mines Ltd.
30
TABLE 8 REMOVAL RATES BASED ON TRIAL DATA AND PREVIOUS STUDS
Parameter Removal rates
% Removal
Lead 50%
Zinc 50%
Sulphate 50%
Total ammonia 98%
Arsenic 50%
BOD 80%
COD 50%
The proposed Hydraulic Retention times in the wetland area are very high at 4
litre/m2/day, therefore the removal rates can easily be achieved.
TABLE 9 POST TREATMENT 95%ILE ASSIMILATIVE CAPACITY
Parameter Units
Background Quality
Discharge Quality
Estimated Q95 stream flow
l/s
Treated Discharge Volume16
l/s
Assimilative
Capacity
Relevant
standard
C total
C Total
mg/l
SI 272 of
2009
Conductivity mS/c
m 727 1000 49.440 3.454 39396 744.83
Sulphate mg/l 141 273 49.440 3.454 7914.0 149.62
C.O.D. mg/l 19 54.5 49.440 3.454 1127.6 21.32
T Ammonia mg/l 0.008 0.6 49.440 3.454 2.5 0.047 <0.065
BOD mg/l 1.3 0.96 49.440 3.454 67.6 1.28 <1.5
Zinc µg/l 43.6 142 49.440 3.454 2646.1 50.03 10017
16
Figure conservatively does not take into account dilution via rainfall on the wetland or attenuation area 17 High Alkalinity in the surface water runoff <150 mg/l
Galmoy Mines Ltd.
31
Parameter Units Background Quality
Discharge Quality
Estimated Q95 stream flow
l/s
Treated Discharge Volume16
l/s
Assimilative
Capacity
Relevant
standard
C total
C Total
mg/l
SI 272 of
2009
Ortho
phosphate mg/l 0.02 0.01 49.440 3.454 1.0 0.02 <0.035
Cadmium µg/l 1 1 49.440 3.454 52.9 1.00
Arsenic µg/l 1.57 31 49.440 3.454 184.7 3.49 25
Lead µg/l 1.07 8.75 49.440 3.454 83.1 1.57 7.2
pH pH
units 7.64 7.64 49.440 3.454 404.1 7.64
D.O. mg/l 10 10.75 49.440 3.454 531.5 10.05
S.S. mg/l 20.77 21.6 49.440 3.454 1101.5 20.82
Nitrate mg/l 17.8 7.74 49.440 3.454 906.8 17.14
For a notionally clean river and an emission limit value of 0.6 mg/l of ammonia, Table 9
indicates the primary discharge would not cause deterioration in the environmental status
of the river. Approximately 72% of the hypothetically available assimilative capacity of
the River Glasha will be consumed at this ELV. Therefore the proposed emission limit
value of 0.6 mg/l of ammonia and a tighter limit of 0.5 mg/l to be achieved by 1st
January 2021.
For a notionally clean river and an emission limit value of 2.4 mg/l of BOD, Table 9
indicates the primary discharge would not cause deterioration in the environmental status
of the river. Approximately 80% of the hypothetically available assimilative capacity of
the River Glasha will be consumed at this ELV. Therefore the proposed emission limits
value of 2 mg/l of BOD and a tighter limit of 1.5 mg/l to be achieved by 1st January 2021.
While ortho-phosphate has not been an issue at Galmoy Mine, the TMF or in the Glasha
River it is proposed to monitor as part licence.
Galmoy Mines Ltd.
32
TABLE 10 PROPOSED MAXIMUM EFFLUENT STANDARDS FOR DISCHARGE
Parameter Units Discharge ELV
Total Ammonical N mg/l N 0.6
BOD mg/l 2
Zinc mg/l 0.5
Ortho phosphate mg/l 0.05
Arsenic µg/l 0.1
Lead mg/l 0.01
pH pH units >6
<9
S.S. mg/l 25
Nitrate mg/l 25
Galmoy Mines Ltd.
33
Ecological assessment
The site nearest aquatic based Designated Conservation Area hydrologically linked to the
river is the River Barrow and River Nore SAC and River Nore SPA, the boundary of which
is over 13 km and 16km downstream respectively. In addition to the assimilative capacity
findings these distances further rule out any significant alone and in-combination impacts
based on the fact that any material from the tailings ponds will be completely diluted and
likely undetectable before it reaches the SAC/ SPA. No toxic and or other effects are likely
even immediately downstream of the discharge.
It is considered that no significant adverse effects will arise from the proposed TMF
discharge from Galmoy Mines and that this development can be screened out from
further Appropriate Assessment.
In informing this it is an assumption that ongoing monitoring and careful design
approaches to minimise risks to local surface and groundwater quality will be
implemented.
Protected Species
Two species of aquatic vertebrates of national and international importance occur in the
Nore system, these are the white clawed crayfish: Austropotamobius pallipes and the
freshwater pearl mussel: Margaritifera margaritifera durrovensis. Both species are
protected under SI 112 of 1990 of the Wildlife Act (1976) species. The salmonid
populations were assessed in previous surveys and the white-clawed crayfish
Austropotamobius pallipes Lereboullet, following the population depletion in the
catchment as a result of a disease (Baars and Kelly-Quinn, 2008), has not been surveyed
at the monitoring sites in the past two years.
Pearl Mussel
The Nore Freshwater Pearl Mussel, Margaritifera durrovensis, has been studied by
Galmoy mine’s consultants, Ecoserve, over the period 1995 to 2000. The results of the
investigations show that not only is the population critically low but no recruitment has
been detected for over 20 years. An average of 72.5% of the mussel population inhabits
an area downstream of the confluence of the River Erkina and Nore at Durrow. Ecoserve
state that there is no suggestion of any change in the pearl mussel population which
could be attributed to the activities of the mine at Galmoy.
34
D.2 Environmental Considerations and Best Available Techniques (BAT)
Describe, in outline, the main alternatives, if any, to the proposals contained in the
Review Form.
Describe any environmental considerations which were made with respect to the use of
cleaner technologies, waste minimisation and raw material substitution.
Describe the measures proposed or in place to ensure that:
(a) the best available techniques are or will be used to prevent or eliminate or, where
that is not practicable, generally reduce an emission from the activity;
(b) no significant pollution is caused;
(c) waste production is avoided in accordance with Council Directive 75/442/EEC of
15 July 1975 on waste; where waste is produced, it is recovered or, where that is
technically and economically impossible, it is disposed of while avoiding or
reducing any impact on the environment;
(d) energy and other resources are used efficiently;
(e) the necessary measures are taken to prevent accidents and limit their
consequences; and,
(f) the necessary measures are taken upon definitive cessation of activities to avoid
any pollution risk and return the site of operation to a satisfactory state.
This section should present a statement on energy efficiency at the site to include,
where appropriate, an energy audit with reference to the EPA Guidance document on
Energy Audits. Licensees should have regard to Section 5 of the EPA Acts 1992 and
2003 in selecting BAT and in particular the following:
• The use of low-waste technology;
• The use of less hazardous substances;
• The furthering of recovery and recycling of substances generated and used in
the process and of waste where appropriate;
• Comparable processes, facilities or methods of operation, which have been
tried with success on an industrial scale;
• Technological advances and changes in scientific knowledge and
understanding;
• The nature, effects and volume of the emissions concerned;
• The commissioning dates for new or existing facilities;
• The length of time needed to introduce the BAT;
• The consumption and nature of raw materials, including water, used in the
process and their energy efficiency;
• The need to prevent or reduce to a minimum the overall impact of the
emissions on the environment and the risks to it;
• The need to prevent accidents and to minimize the consequences for the
Environment; and,
Galmoy Mines Ltd.
35
• The information published by the Agency in the form of sectoral BAT
Guidance documents and the relevant BREF documents published by the EC
(available for download at http://eippcb.jrc.es/ and at www.epa.ie).
Compliance with legislation and BAT
The EU Directive on the management of waste from the extractive industries,
(Directive 2006/21/EC of the European Parliament and of the Council of 15 March
2006) hereafter referred to as The Mine Waste Directive (Regulations) 2009,
applies to waste resulting from the extraction, treatment and storage of mineral
resources and sets minimum requirements on how waste from an extractive
industry is managed by specifically addressing environmental and human health
risks that may arise from its treatment and disposal. Mine waste facilities must be
subjected to the new provisions by 2012.
The current EU level framework for the safe management of waste from the
extractive industry comprises:
• The Mine Waste Directive as described above, together with;
• A best available techniques reference (BREF) document for the
Management of
• Tailings and Waste-Rock (MT–WR) in mining; and
• An amendment to the scope of the Seveso II Directive to include mineral
ore processing, and particularly, tailings dams or facilities used in
connection with such processing.
To operate, a company must obtain a permit issued by the competent authorities;
and in the event of modification to an existing waste facility this authority must
be satisfied that (amongst other conditions) arrangements have been made for
the closure of the facility, rehabilitation of the land and Post-Closure
maintenance/monitoring needs are catered for. A facility will only be regarded as
finally closed when the competent authority has carried out a final inspection,
assessed the reports produced by the operator and confirmed that
restoration/rehabilitation has been completed as planned.
The operator will be required to maintain and monitor the site for a period
determined by the competent authority. The cost of this aftercare must be met by
the operator. The closure plan and aftercare procedures should be included as
part of the required waste management plan (reviewed every five years) with
specific reference to the:
• Evaluation of leachate generation and quality;
• Prevention of leachate generation;
• Prevention of contamination of surface and groundwater; and
• Treatment of any contaminated waters prior to discharge.
• The general requirement for the safe management of extractive waste is
established by
• Article 4 of the Mine Waste Directive. Measures to be taken are to be
based on Best
Galmoy Mines Ltd.
36
• Available Techniques (BAT) as defined in Directive 96/61/EC (The
Integrated Pollution
• Prevention and Control Directive). In tandem with the development of the
Mine Waste
• Directive, the EU IPPC Bureau in Seville developed the BREF document for
Management of Tailings and Waste Rock in Mining Activities (MT – WR),
which was published in July 2004 and intended to be used as a reference
when trying to determine BAT for the management of mine waste.
The determination of appropriate BAT involves taking local and site specific
factors into account. Typically a risk assessment is applied in order to assess the
techniques used and to ensure they are most appropriate to the specific
circumstances in terms of environmental, safety, technical and engineering
aspects. Chapter 4 of the BREF document describes techniques that are
considered relevant in determining BAT and BAT-based measures. Section 4.2.4
of the BREF document deals specifically with the closure and aftercare phase.
A risk assessment for the failure of the Galmoy TMF has been carried out as
previously stated which includes the risk at closure. The probability of failure of
the Galmoy facility and release of either tailings water or tailings solids to the
environment as indicated by the risk assessment is less than that predicted for
the Active phase because of the reduction and near absence of water on top of
the dam at closure. The final cap profile for both Phases 1 and 2 will be shaped as
a dome and as such runoff migrates to the external walls and into a perimeter
interceptor drainage system. The drainage system and spillways have been
designed to cater for a 1 in 150 year storm event.
The cap for Phase 3 will be shaped with a gentle slope falling towards a low point
on the embankment wall where a spillway will be installed to transfer surface
water runoff from all phases to the attenuation pond. Therefore, the possibility of
the tailings being mobilised in the absent of any pond water on top of the facility
is negligible. Therefore, no financial provision will be required to address such an
event because of the negligible probability of occurrence.
Wetlands are specified as an appropriate BAT treatment for mining operation
under BREF guidance (pg 356).
In wetland technology the seepage waste are collected into a wetland area
constructed on an old pond or an swamp areas close to the operation. Using
neutralising construction materials (carbonate rocks) and natural specific
vegetation, the metals in seepage waters are precipitated and clean waters can
be lead towards local rivers/lakes.
The aim of the reclamation and closure plan for the Galmoy Mines tailings facility
is to reintegrate land that has been disturbed by construction, operational and
decommissioning activities into the surrounding landscape. It is intended that the
post reclamation quality of surface run-off water and capability of the disturbed
areas will, where possible resemble conditions prior to disturbance or allow an
alternative land use.
Galmoy Mines Ltd.
37
Galmoy Mines is currently in the process of taking necessary measures upon
definitive cessation of activities to avoid any pollution risk and return the mine
site to a satisfactory state as outlined in the Closure Restoration and Aftercare
Management Plan (CRAMP). Legislation requires that a Mine Closure Plan (MCP)
be prepared to facilitate a controlled exit from any redundant mine in order to
minimise the long term environmental impacts. Adequate financial provision has
been made for closure and the plan has incorporated physical rehabilitation,
pollution prevention and socio-economic considerations.
The Mine Closure Plan of December 2010 has been approved by the Authorities
and is now being implemented in agreement with the Mine Closure Plan Schedule.
A mine closure programme has been developed to implement the Mine Closure
Plan. In addition to the Closure Rehabilitation Aftercare and Management Plan
(CRAMP), a monitoring programme has been devised and the costs associated
with monitoring calculated.
The overall objective is to rehabilitate the mine site, TMF and underground and to
minimise the long term impacts on the environment. This is achieved by setting
objectives and implementing the Mine Closure Programme which consists of
decontamination, demolition, retention and rendering safe. Financial provision is
provided for the completion of this task.
Discharge of treated mine water to the River Goul will cease in 2013. A proposed
discharge point to the River Glasha (SW2) is included in this application for the
rehabilitated tailings management facility. The main objectives for the
rehabilitation of Phase 1 & 2 of the TMF are to achieve a sustainable, and
stabilizing vegetative cover, install an engineered, self draining cap and drainage
system, establish agricultural grassland and biodiversity habitat, long term
beneficial agricultural use and establish a physically, chemically and biologically
stable and sustainable structure. The main objectives for the rehabilitation of
Phase 3 are to achieve a sustainable and stabilizing vegetation cover, to establish
an integrated constructed wetland to treat Phase 1 and Phase 2 runoff and
provide a biodiversity habitat.
The integrated constructed wetland is a low waste sustainable treatment
technology which can adapt to conditions and deliver a high quality output. The
integrated constructed wetland can treat and reduce nitrate, ammonium,
phosphate, BOD and metals thereby substantially reducing the overall chemical
loading on the River Erkina. Wetland trails in 2009 indicated the high success rate
of the wetlands area. Wetlands recovery and recycle nutrients that would
otherwise be discharge to the surface water network.
Phase 3 (and, by extension, from Phases 1 and 2 which drain into Phase 3) will
remain, if required, during this period. Assuming normal rainfall and
evapotranspiration rates for grassland, surface water runoff from Phase 1 & 2 into
Phase 3 will be a relatively small volume. Surface water falling on Phase 3 will be
free of contamination. As a precautionary/interim measure the surface water post
treatment in the wetland r can be retained, if necessary, subject to approval by
Galmoy Mines Ltd.
38
EPA, and pumped back to the water treatment plant on site t until the discharge
meetings the standards as set out in this document. Water in the existing holding
ponds can be discharge to the River Goul to achieve full compliance at the final
discharge to the River Goul. This will be an interim measure while the integrated
constructed wetland is being established.
SECTION E: STATUTORY REQUIREMENTS
E.1 Best Environmental Practices – Compliance with Legislation
Demonstrate if the best environmental practices are in place for control of diffuse
emissions from the installation/facility as set out in the following legislation:
(a) a specification prepared by the Agency in accordance with Section 5 of the
Environmental Protection Agency Act 1992 as amended by Section 7 of
the Protection of the Environment Act 2003;
(b) the Urban Waste Water Treatment Regulations 2001 (S.I. No. 254 of
2001) as amended by the Urban Waste Water Treatment (Amendment)
Regulations 2004 (S.I. No. 440 of 2004) or any future amendment
thereof;
(c) the European Communities (Good Agricultural Practice for Protection of
Waters) Regulations 2009 (S.I. No. 101 of 2009) or any future
amendment thereof;
(d) the Local Government (Water Pollution) Act, 1977 (Control of Cadmium
Discharges) Regulations 1985 (S.I. No. 294 of 1985);
(e) the Local Government (Water Pollution) Act, 1977 (Control of
Hexachlorocyclohexane and Mercury Discharges) Regulations 1986 (S.I.
No. 55 of 1986);
(f) the Local Government (Water Pollution) Acts, 1977 and 1990 (Control of
Carbon Tetrachloride, DDT and Pentachlorophenol Discharges) Regulations
1994 (S.I. No. 43 of 1994); and,
(g) measures or controls identified in a pollution reduction plan for the river
basin district prepared in accordance with Part V of the EC Environmental
Objectives (Surface Waters) Regulations 2009 S.I. No. 272 of 2009 for the
reduction of pollution by priority substances or the ceasing or phasing out
of emissions, discharges and losses of priority hazardous substances.
Galmoy Mines Ltd.
39
E.1 Best Environmental Practices – Compliance with Legislation
This review is based on the requirement to comply with EC Environmental Objectives
(Surface Waters) Regulations 2009 S.I. No. 272 of 2009 and EC Environmental
Objectives (Freshwater Pearl Mussel) Regulations 2009. These regulations apply to the
habitats that are within the boundaries of sites designated as a Special Area of
Conservation, under the European Communities (Natural Habitats) Regulations, 1997
(S.I. No 94 of 1997).
Although compliance with Second Schedule of the Urban Waste Water Treatment
Regulations 2001 (S.I. No. 254 of 2001) as amended by the Urban Waste Water
Treatment (Amendment) Regulations 2004 (S.I. No. 440 of 2004) is required, the
limits for Total Nitrogen in particular have now been superseded by the Environmental
Objectives (Freshwater Pearl Mussel) Regulations 2009.
Based on the runoff water quality from the capped TMF and the results of the trial
wetlands, the final discharge will achieve the standards as set out under S.I. 272 of
2009. Proposed effluent discharge limits as set out in section D above can be easily
achieved following completion of capping works and establishment of the wetlands
area.
Section 5 of the Environmental Protection Agency Act 1992 as amended by Section 7 of
the Protection of the Environment Act 2003; states that the Best Available techniques
shall be construed as a reference to the most effective and advanced stage of
development of an activity and its methods of operation, which indicate the practical
suitability of particular techniques for providing, in principle, the basis for emission
limit values designed to prevent or eliminate, or where that is not practicable,
generally to reduce an emission and its impact on the environment as a whole. Mining
activities ceased onsite in October 2012. Results from initial cessation of mining since
June 2009 demonstrate the reduction in emission of Pb, Zn NH3 etc to surface water.
The mine has achieved 100 % compliance for ammonium and Pb and 99.2% Zn in
2012 at SW1. Extensive monitoring of the tailings and surface water has been
undertaken and is submitted as part of this application.
Water quality from the cap containing compost will improve with time as indicated from
the initial monitoring results. All surface water from the rehabilitated TMF will be
directed into the wetland, where any remaining elevated values will be removed.
Discharge from the wetland will flow towards an attenuation pond. If water quality
leaving the wetland is unsatisfactory, all waters will be pumped to the treatment plant
until satisfactory for discharge.
The success of the rehabilitation and closure works will be measured by its
performance during the 5 year active, 5 year passive and the 20 year stable phase.
In the introduction, reference is made to BREF- MTWR criteria and the work
undertaken by Galmoy is considered to comply with the BREF- MTWR guidelines.
Based on the BREF - MTWR criteria for success, the criteria for closure needs to include
Galmoy Mines Ltd.
40
physical, chemical and biological stability. The hydrological environment, geographical
influences, and local sensitivities also need to be considered together with future land
use. A financial mechanism has been agreed with the EPA and associated authorities.
Awareness of the socio-economic issues needs to be highlighted. These issues have
been discussed in this report and are briefly summarised below. BAT guidelines
outlined in BREF – MWTR 2005 will be used to assess that the criteria for closure are
being met (Table E-1.1).
41
Criteria for the Closure of Tailings Facilities (BREF MTWR Chapter 4, Table 4.2.4.1)
Table E-1.1: Criteria for Closure
Issue Closure Objectives TMF rehabilitation achievements/goals for Galmoy
Physical Stability All remaining anthropogenic structures are
physically stable
The TMF is designed to exceed the safety criteria given by
the ICOLD standard.
TMF audited by Golder for the past 10 years with
extensive data submitted to support the physical stability
of the TMF.
The formation of the dome for Phases 1 and 2 and the
completion of Phase 3 will minimise the risk of dam
failure.
Chemical Stability Physical structures remaining after closure are
chemically stable
Monitoring of herbage, the compost cap, tailings, and
water quality to continue in the Active Care period.
Monitoring data to support water quality emanating from
the TMF recorded and monitored over 10 years in TMF
annual Audit as per IPPC license.
Cap to include a minimum of 0.3m of glacial till/soil in
Phase 1, an average thickness of 0.8m in Phase 2 and
1.0m in Phase 3.
Reduced monitoring to occur in the Passive Care period
and further reductions in the Stable Phase.
Biological Stability The biological environment is restored to a
natural, balanced ecosystem typical of the area, or
is left in such a state so as to encourage and
enable the natural rehabilitation and/or
reintroduction of a biologically diverse, stable
environment
The rehabilitation programme will return the surface of
the TMF to a combination of agronomic and ecologically
sustainable land uses.
Monitoring to date substantiates the validity of these end
points.
Galmoy Mines Ltd.
42
Issue Closure Objectives TMF rehabilitation achievements/goals for Galmoy
Hydrological and
hydrogeological
environment
Closure aims at preventing physical and chemical
pollutants from entering and subsequently
degrading the downstream environment -
including surface and ground waters
Monitoring of groundwater and surface water to continue
in the Active and Passive Care periods. Water Treatment
Plant to remain operational as required. A land drainage
system may be incorporated into surface of TMF if
required. Construction of a wetlands and attenuation pond
for surface water prior to discharge to Glasha stream.
Geographical and
climatic influences
Closure is appropriate to the demands and
specifications of the location, in terms of climatic
(e.g., rainfall, storm events, seasonal extremes)
and geographic factors (e.g., proximity to human
habitations, topography, accessibility of the mine)
Rainfall and evapotranspiration rates have been taken
into consideration for drainage design as the impact of
extreme events.
Local sensitivities and
opportunities
Closure optimizes the opportunities for restoring
the land and the upgrade of land use is considered
whenever appropriate and/or economically
feasible.
Regionally sourced compost has been used to cap the
tailings on Phases 1 and 2 and glacial till soil used to form
the dome shapes, cap the tailings of Phase 3 and
installation of a wetland.
Land use Rehabilitation is such that the ultimate land-use is
optimized and is compatible with the surrounding
area.
Surface of the TMF will be returned to a mixed growing
economy; grazing and wetland biodiversity.
Socio-economic
considerations
Consideration must be taken of opportunities for
local communities whose livelihoods may depend
on the employment and economic fallout of the
mining activities. Adequate measures are made to
ensure that potential socio-economic advantages
associated with closure are maximized.
This issue is mainly related to the industrial area of the
mine site and will be dealt with separately as it does not
focus on the TMF.
43
The Closure Rehabilitation and Management Plan (CRAMP) was developed to reduce
the overall impact of emissions and risk to the environment during
decommissioning. It provides a detailed ordered approach to the closure process.
The CRAMP database is a detailed database used to keep track of the costs involved
in mine closure and record the progress of decommissioning, decontamination,
dismantling and rehabilitation of each specific area. This includes planning,
identification of success criteria, monitoring of progress, selling of equipment,
contractor management, and cost management. The CRAMP database allows
Galmoy Mines to manage costs and an Independent Third Party to audit costs and
review the progress of work achieved from the previous audits and provide a
statement of quality of the work undertaken in the intervening period.
Certification that works have been completed and are of the required standard will
be issued by Galmoy Mines personnel or by a Third Party as and when each mine
Closure Plan task Area has been completed. A transparent report prepared by the
Third Party on expenditure and costs is provided to the Authorities on a quarterly
basis and forms the basis for the request for drawdown of funds. Finally, within the
CRAMP database there is an outline of the monitoring proposals and a statement as
to the certification requirements. Final verification of rehabilitation will be
undertaken once all areas have been rehabilitated.
44
SECTION F: APPROVED ADJUSTMENTS & CONDITIONS
Where the Office of Environmental Enforcement (OEE) of the Agency has agreed any
variations or adjustments to the conditions of the existing licence, the licensee must
supply a schedule detailing these agreed variations and adjustments to the existing
licence conditions. An updated, scaled drawing of the site layout (no larger than A3)
providing visual information on such adjustments or variations where appropriate should
be included.
In the case of once-off assessments/ reports required under conditions of the existing
licence the licensee must supply a schedule detailing those assessments/ reports that
have been completed and agreed with the Office of Environmental Enforcement (OEE) or
as otherwise agreed.
Attachment No F1 shall include the schedule of variations and/or adjustments together
with the updated drawing.
Condition
No.
Existing
Condition
Proposed Wording
(where
appropriate)
OEE
Agreement
Reference
Description
45
Attachment No F1