Construction Works: 23 rd March to 6 th April Project Pegasus Issue #40 20 th March 2020 SRM Special Projects Site Team offices are now located within the basement of the building with access through the East hoarding opposite Kings Bench Walk where ‘Visitor Entrance:’ signage can be found on the hoarding door to assist. Please press the bell to attract attention. Site working hours will be from: 8.00am – 6.00pm Monday – Friday 9.00am – 2.00pm Saturday Project Manager: John Walker SRM Special Projects E: [email protected] T: 07866 783710 If unavailable contact, Chief Engineer: Joshua Murray T: 07875 190945 Contact Us Demolition of existing level 3 floor slab in the North East corner M&E installation within the basement plant rooms, kitchen and new book store Internal brickwork and blockwork infills throughout the building Brickwork for the new fire escape stairs on the North façade Scaffold tower to facilitate the formation of the new lift shaft brickwork Waterproofing within the basement Concrete work on level 3 to support the new structural steel Installation of structural steel Concrete Works on 3 rd Floor Structural Steel Installation

Upload: others

Post on 13-Aug-2020

18 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Internal brickwork and blockwork infills throughout ...€¦ · • Internal brickwork and blockwork infills throughout the building • Brickwork for the new fire escape stairs on

Construction Works: 23rdMarch to 6th April

Project Pegasus

Issue #4020th March 2020

SRM Special Projects Site Team offices

are now located within the basement

of the building with access through the

East hoarding opposite Kings Bench

Walk where ‘Visitor Entrance:’ signage

can be found on the hoarding door to

assist. Please press the bell to attract

attention.

Site working hours will be from:

8.00am – 6.00pm Monday – Friday

9.00am – 2.00pm Saturday

Project Manager: John Walker

SRM Special Projects

E: [email protected]

T: 07866 783710

If unavailable contact,

Chief Engineer: Joshua Murray

T: 07875 190945

Contact Us

• Demolition of existing level 3 floor slab in the North

East corner

• M&E installation within the basement plant rooms,

kitchen and new book store

• Internal brickwork and blockwork infills throughout

the building

• Brickwork for the new fire escape stairs on the North

façade

• Scaffold tower to facilitate the formation of the new lift

shaft brickwork

• Waterproofing within the basement

• Concrete work on level 3 to support the new structural

steel

• Installation of structural steel

Concrete Works on 3rd Floor

Structural Steel Installation