internal monitoring report - asian development bank proceeding of grievance redressal committee of...
TRANSCRIPT
Internal Monitoring Report Lower Bari Doab Canal Improvement Project
Internal Monitoring Report
Project Number: 2299-PAK
June 2013
Islamic Republic of Pakistan: Lower Bari Doab Canal Improvement Project
This report does not necessarily reflect the views of ADB or the Government of the Punjab, and the ADB and the Government cannot be held liable for its contents
Internal Monitoring Report Lower Bari Doab Canal Improvement Project
ABBREVIATIONS
ADB : Asian Development Bank
AP : Affected Person
COI : Corridor of Impact
EA : Executing Agency
GRC : Grievance Redress Committee
HH : Household
IOL : Inventory of Loss
LAR : Land Acquisition and Resettlement
PIU : Project Implementation Unit
PMU : Project Management Unit
ROW : Right of Way
RP : Resettlement Plan
TOR : Terms of Reference
PIU : Project Implementation Unit
Internal Monitoring Report Lower Bari Doab Canal Improvement Project
GOVERNMENT OF THE PUNJAB
IRRIGATION DEPARTMENT
ADB LOAN No. 2299-Pak
Internal Monitoring Report
RESETTLEMENT PLANS IMPLEMENTATION
OF
ALL ON-GOING SUB-PROJECTS NCB-01, NCB-02, BB/ICB-01, ICB-01, ICB-02, ICB-03,
ICB-04, ICB-05, ICB-06 (A) & (B)
June, 2013
PROJECT MANAGEMENT UNIT (PMU)
LOWER BARI DOAB CANAL IMPROVEMENT PROJECT (LBDCIP)
Internal Monitoring Report Lower Bari Doab Canal Improvement Project
i
CONTENTS
EXECUTIVE SUMMARY ............................................................................................................... 1
1 INTRODUCTION .......................................................................................................................... 3
2 SUB-PROJECT NCB-01 JANDRAKA DISTRIBUTARY ........................................................... 6
3 SUB-PROJECT NCB-02 15-L DISTRIBUTARY ....................................................................... 10
4 SUB-PROJECT ICB-01 MAIN CANAL ..................................................................................... 15
5 SUB-PROJECT ICB-02 MAIN CANAL ..................................................................................... 21
6 SUB-PROJECT ICB-03 MAIN CANAL ..................................................................................... 29
7 BB/ICB-01 (COMPONENT-1) .................................................................................................... 31
8 INVENTORY OF STRUCTURES OF ICB-04 ........................................................................... 33
9 DETAILS OF LAND TO BE OCCUPIED ON TEMPORARY BASIS - ICB-04 ...................... 34
10.1 INVENTORY OF STRUCTURES OF ICB-05 ........................................................................... 35
10.2 DETAILS OF LAND TO BE OCCUPIED ON TEMPORARY BASIS - ICB-05 ...................... 37
11 COMMUNITY STRUCTURES ................................................................................................... 42
12 IMPACT ASSESSMENT OF STRUCTURE APs ....................................................................... 42
13 GRIEVANCE REDRESSAL........................................................................................................ 43
LIST OF TABLES
TABLE 2.1: STATUS OF COMPENSATION TO APS OF TEMPORARY LAND OCCUPATION ............ 6
TABLE 2.2: COMPENSATION FOR DOMESTIC STRUCTURES .................................................... 7
TABLE 2.3: COMPENSATION FOR IMPACTED BUSINESS STRUCTURES ................................ 8
TABLE 2.4: COMPENSATION FOR PRIVATE FIXTURES .............................................................. 8
TABLE 2.5: COMPENSATION TO APS FOR PRIVATE TREES ...................................................... 9
TABLE 3.1: COMPENSATION TO APS STRUCTURES & FIXTURES ......................................... 10
TABLE 4.1: COMPENSATION FOR AFFECTED STRUCTURES .................................................. 15
TABLE 4.2: COMPENSATION TO APS FOR TEMPORARY OCCUPATION OF LAND ............ 18
TABLE 5.1 STATUS OF COMPENSATION TO APS OF TEMPORARY LAND OCCUPATION21
TABLE 5.2 STATUS OF COMPENSATION TO APS FOR IMPACTED STRUCTURES ............. 22
TABLE 6.1 STATUS OF COMPENSATION TO APS FOR IMPACTED STRUCTURES ............. 29
TABLE 7.1 STATUS OF COMPENSATION TO APS FOR IMPACTED STRUCTURES ............. 31
Internal Monitoring Report Lower Bari Doab Canal Improvement Project
ii
LIST OF ANNEXURE
1 IMPACT ASSESSMENT OF REMAINING APS OF JANDARAKA DISTY. (NCB-01) 44
2 IMPACT ASSESSMENT OF REMAINING APS OF 15-L DISTY. (NCB-02) 45
3 IMPACT ASSESSMENT OF STRUCTURE APS OF ICB-01 46
4 IMPACT ASSESSMENT OF STRUCTURE APS OF ICB-02 47
5 IMPACT ASSESSMENT OF STRUCTURE APS OF ICB-03 50
6 NOTIFICATION OF MANAGEMENT COMMITTEE FOR RELOCATION AND
RECONSTRUCTION OF COMMUNITY STRUCTURES
51
7 CONSENT FOR RELOCATION OF MADRISSAHS BY RESPECTIVE
MANAGEMENT
52
8 NOTIFICATION OF GRC ICB 02 MAIN CANAL 53
9 NOTIFICATION OF GRC ICB 03 MAIN CANAL 54
10 NOTIFICATION OF GRC ICB 04 MAIN CANAL 55
11 NOTIFICATION OF GRC ICB 05 MAIN CANAL 56
12 NOTIFICATION OF GRC ICB BB 57
13 LETTER TO DD, PIU OKARA REGARDING HOSTING OF MEETING OF GRC 58
14a PROCEEDING OF GRIEVANCE REDRESSAL COMMITTEE OF ICB-01 59
14b ATTENDANCE SHEET OF PROCEEDING OF GRIEVANCE REDRESSAL
COMMITTEE ICB-01
60
15a PROCEEDING OF GRIEVANCE REDRESSAL COMMITTEE OF ICB-02 61
15b ATTENDANCE SHEET OF PROCEEDING OF GRIEVANCE REDRESSAL
COMMITTEE ICB-02
62
16a PROCEEDING OF GRIEVANCE REDRESSAL COMMITTEE OF ICB-03 63
16b ATTENDANCE SHEET OF PROCEEDING OF GRIEVANCE REDRESSAL
COMMITTEE ICB-03
64
17 ATTENDANCE SHEET OF PROCEEDING OF GRIEVANCE REDRESSAL
COMMITTEE ICB-04
65
18 ATTENDANCE SHEET OF PROCEEDING OF COMMUNITY CONSULTATION &
GRIEVANCE REDRESSAL COMMITTEE ICB-05
66
19 ATTENDANCE SHEET OF PROCEEDING OF COMMUNITY CONSULTATION
ICB-06 AT VILLAGE 91/10R
67
20 LETTER TO CONTRACTOR FOR DETAIL LIST OF LAND OWNERS FALLING IN
THE DIVERSION OF ICB-04
68
Internal Monitoring Report
Lower Bari Doab Canal Improvement Project
1
EXECUTIVE SUMMARY
1. The Lower Bari Doab Canal Improvement Project (LBDCIP) involves rehabilitation of
Lower Bari Doab Canal and its Distributary System. The LBDC originates from River
Ravi at Balloki Barrage about 75 km south west of Lahore. Its total length is 201 km.
2. The Project Management Unit (PMU) of LBDCIP has overall responsibility for project
implementation and financing of all resettlement tasks and cross-agency coordination.
The specific institutional arrangements are made in accordance with mechanism
provided in Resettlement Plans to carry out specific LAR activities.
3. The Main Canal is further divided into three separate contract packages to facilitate the
implementation process under the financial facility. The first package (ICB-01 Main
Canal) is from RD 000+500 to RD 227+000, second package ICB-02 (Main Canal)
starts from RD 227+000 and terminates at RD 527+000, third package (ICB-03 Main
Canal) starts from RD 527+000 and terminates at RD 661+000.
4. The ICB-04 contains all distributaries and minors off taking from the reach of
ICB-01 (main canal). It has 84 distributaries and minors. The ICB-04 falls into three
irrigation divisions, namely Balloki, Okara and Sahiwal .Total CCA of this package is
483662 acres. There are 1122 outlets irrigating the command area. Revised SRP for ICB-
04 was approved by ADB on 26.07.2012. Contractor is asked to provide its work plan
and shop drawing of the diversions to finalize the land falling in diversions and to
conduct joint real time impact assessment.
5. The ICB-05 sub-project mainly comprised of distributaries and minors off taking from
the reach of ICB-02 LBDC main canal. It has 85 distributaries and minors. The ICB-05
falls into Sahiwal Irrigation Division. Total CCA of this package is 610738 acres. There
are 1003 outlets irrigating the command area. Revised SRP for ICB-05 was approved by
ADB on 03.04.2013. SRP is under implementation. Contractor is asked to submit work
plan to finalize the area of land falling in diversions and approved shop drawings.
6. The ICB-06 has 2 parts; ICB 06 A comprises the distribution system of Khanewal
Irrigation Division excluding 10-R branch canal and its distribution system. SRP for ICB
06 (A) was approved by ADB on 30.03.2013. Contract award is under process. ICB 06-B
comprises 10-R branch canal of Khanewal Irrigation Division. The ICB-06 (B) comprises
the distribution system of 10-R branch canal and its distribution system of Khanewal
Internal Monitoring Report
Lower Bari Doab Canal Improvement Project
2
Irrigation Division. SRP for ICB 06 (B) was approved by ADB on 30.03.2013. Contract
award is under process.
7. This Internal Monitoring Report (IMR) is till June 2013. IMR has been prepared for
providing detail about implementation of Resettlement Plans of all on-going sub-projects
of LBDCIP i.e.; NCB-01, NCB-02, ICB-01, ICB-02, ICB-03, ICB-04, ICB-05, ICB-06
(A) and (B) & BB ICB-Balloki (component-1& 2). The status of implementation of
Resettlement Plans is provided in the table below:
Sr.
No. Contract No.
Compensation Due Implementation %
Implementation
Total
APs
APs To
be Paid
Amount
Due
APs
Paid
Amount
Paid
APs
Paid
Amount
Paid
1 Jandraka Disty.
NCB-01 95 89 0.810 89 0.810 100% 100%
2 15-L Disty.
NCB-02 65 53 1.209 53 1.209 100% 100%
3 Balloki Barrage-
ICB/BB-01 12 12 1.746 12 1.746 100% 100%
4 Main Canal ICB-01 55 29 5.333 29 5.299 100% 100%
5 Main Canal – ICB-02 70 59 2.955 33 1.759 61% 59%
6 Main Canal ICB-03 11 05 0.208 04 0.165 80% 89%
7
Distribution System of
Balloki & Okara
Divisions – ICB-04
Revised SRP for ICB-04 was approved by ADB on 26.07.2012.
Contractor is asked to provide its work plan and shop drawing of
the diversions to finalize the land falling in diversions and to
conduct joint real time impact assessment.
8
Sahiwal Division
Distribution
System/CB-05
Revised SRP for ICB-05 was approved by ADB on 03.04.2013.
SRP is under implementation
9
Dist. System of
Khanewal Division –
LBDC/ICB-06 A
Revised SRP for ICB-06 (A) was approved by ADB on
30.03.2013. Contract award is under process.
10
Dist. System of
Khanewal Division –
LBDC/ICB-06 B
Revised SRP for ICB-06 (B) was approved by ADB on 03.04.2013
Contract award is under process.
Internal Monitoring Report
Lower Bari Doab Canal Improvement Project
3
1 INTRODUCTION
1. The civil work of the sub-project Jandraka LBDC NCB-01 is in progress. The
assessment of sub-project impact on structures of remaining 14 APs has been jointly
conducted by representatives of contractor, Project Implementation Unit (PIU), Design &
Construction Supervision Consultants (DCSC) and Land Acquisition and Resettlement
Unit (LARU). It is found out that 06 APs will not be impacted due to project activity. The
copy of impact assessment is placed at Annex-01. The Rs.0.810 million has been paid to
actually affected APs 89 out of 95 APs for compensating project impact. The LARU has
assisting these APs to get CNIC and acquisition of land documents.
2. The civil work on sub-project NCB-02 15-L Distributary System is in progress. The
assessment of sub-project impact on structures of remaining 12 APs has been jointly
conducted by the representatives of contractor, PIU, DCSC and LARU. The copy of
impact assessment is placed at Annex-02. An amount of Rs.1.209 Million has been paid
to all the actually affected APs 53 out of 65 APs falling in various categories.
3. The third sub-project is LBDC Main Canal (ICB-01). The civil work is in progress for
construction of diversion channels. The APs whose land has been temporarily occupied
under section-35 of LAA, 1894 have already been paid. The assessment of sub-project
impact on structures of APs listed in SRP has been jointly conducted by the Support
Resettlement Expert, Deputy Director (CR), Deputy Director (SG) and Deputy Director
(PIU). Out of 28 APs, only 02 have been identified to be impacted due to project activity.
The copy of impact assessment is added as Annex-03. The actually affected APs 29 out
of 55APs have been paid in this sub-project. An amount of Rs.5.333 Million has been
disbursed in this regard. Addendum to Short Resettlement Plan LBDC Main Canal (ICB
01) has been sent to ADB for approval dated 20.06.2013
4. The forth sub-project is LBDC Main Canal ICB-02. The civil work is in progress on
diversion channels, all the APs whose land has been temporarily occupied under section-
35 of LAA, 1894 for construction of diversion channels have already been paid. The
assessment of sub-project impact on structures of APs listed in the SRP has been jointly
conducted by representatives of contractor, PIU, DCSC, LARU. The 43 out of 59 APs
have been identified to be impacted due to project activity. The copy of impact
assessment is placed at Annex-04. An amount of Rs.2.955 million has been disbursed to
Internal Monitoring Report
Lower Bari Doab Canal Improvement Project
4
33 out of 59 identified APs. The implementation of SRP of ICB-02 synchronized with
civil work activity is in progress. The remaining 22 APs will be paid before mobilization
of contractor at their respective reaches so that encroachers located in the area may not
take advantage of gap between payment to APs and start of civil work and moved to the
Corridor of Impact (CoI).
5. The fifth sub-project is LBDC Main Canal ICB-03. The civil work is in progress on
diversion channels. The diversion channels falls in the land of Punjab Irrigation
Department (PID) therefore temporary occupation of land is not involved in this sub-
project. The assessment of impact of sub-project on structures of 11 APs listed in the SRP
has been jointly conducted by the representatives of contractor, PIU, DCSC, LARU. It
was found out that only 05 APs will be impacted due to project activity. Out of these, 04
APs have already been paid and an amount of Rs.0.208 million has been disbursed. The
copy of impact assessment is placed at Annex-05. The remaining 01 APs with the
assistance of LARU is in the process of obtaining CNIC. External Monitor pointed out in
the 3rd
External Monitoring Report, a structure which is likely to be impacted but missing
in the inventory of SRP for ICB-03. A meeting of GRC was held on this issue. It was
found out that it is an abandoned structure with no one living in it. Moreover this
structure is not being impacted by the project activities.
6. The sixth sub-project is BB/ICB-01. All 12 APs of this sub-project have been paid and an
amount of Rs.1.746 Million has been disbursed. Baloki Barrage Component 2 is under
process in Revenue Department for Section 5 of LAA 1894.
7. The contract for seventh sub-project ICB-04 is awarded. Revised SRP for ICB-04 was
approved by ADB on 26.07.2012. Contractor is asked to provide its work plan and shop
drawing of the diversions to finalize the land falling in diversions and to conduct joint
real time impact assessment. Copy of the Letter is Annex-20.
8. The eighth sub-project ICB-05 was approved by ADB on 03.04.2013. SRP is under
implementation and will be synchronized with the civil work activities as it has very long
distribution network and full implementation of SRP at once is not possible in this sub-
project.
9. The ninth sub-project is ICB-06 (A). ICB 06 was divided into two parts as ICB-06 (A)
and (B). SRP for the ICB-06 (A) was approved by ADB on 30.03.2013. Contract award
Internal Monitoring Report
Lower Bari Doab Canal Improvement Project
5
is under process. SRP will be implemented soon after the completion of contract award.
10. The tenth sub-project is ICB-06 (B). SRP for the ICB-06 (B) was approved by ADB on
03.04.2013. Contract award is under process. SRP will be implemented soon after the
completion of contract award.
11. The Grievance Redressal Committees (GRCs) have been notified separately on all the
sub-projects and are operational (Annex 8-12).
Internal Monitoring Report
Lower Bari Doab Canal Improvement Project
6
2 SUB-PROJECT NCB-01 JANDRAKA DISTRIBUTARY
12. The detail of compensation payment made to APs for occupying private land for
rehabilitation of Jandraka Distributary is provided in the Table 2.1:
TABLE 2.1: STATUS OF COMPENSATION TO APs OF TEMPORARY LAND
OCCUPATION
S.# Name RD/ Address
Land
Encroached Compensation
Amount (Rs)
Remarks
Marlas Kanals
1 Fida Hussain s/o Bakar Fateh Pur Sharif 58.2 2.91 11549 Paid
2 Bukhtawar s/o Bahdar Fateh Pur Sharif 72.7 3.64 14436 Paid
3 Sadiq s/o Ismail Fateh Pur Sharif 43.6 2.18 8662 Paid
4 Abdul Khaliq s/o Noora Fateh Pur Sharif 29.1 1.45 5775 Paid
5 Zahoor Ahmed s/o Ahmed Khan Fateh Pur Sharif 43.6 2.18 8662 Paid
6 Amanat Ali s/o Idrees Fateh Pur Sharif 29.1 1.45 5775 Paid
7 Iqbal s/o Jan Muhammad Fateh Pur Sharif 14.5 0.73 2887 Paid
8 Imarn s/o Zawar Fateh Pur Sharif 174.5 8.73 34647 Paid
9 Haji Ajmal s/o Anwar Khan Fateh Pur Sharif 29.1 1.45 5775 Paid
10 Anwar s/o Waryam Fateh Pur Sharif 43.6 2.18 8662 Paid
11 Akram s/o Abdullah Fateh Pur Sharif 14.5 0.73 2887 Paid
12 Mohsan s/o Chamma Fateh Pur Sharif 14.5 0.73 2887 Paid
13 Gahra s/o Waryam Fateh Pur Sharif 14.5 0.73 2887 Paid
14 Ghulam Rasoul s/o Nawab Fateh Pur Sharif 29.1 1.45 5775 Paid
15 Haji Mukhtar s/o Jafar Fateh Pur Sharif 14.5 0.73 2887 Paid
16 Ch. Masood Shafqat Fateh Pur Sharif 29.1 1.45 5775 Paid
17 Haji Usman Khan Fateh Pur Sharif 43.6 2.18 8662 Paid
18 Mehtab Fateh Pur Sharif 29.1 1.45 5775 Paid
19 Aslam s/o Peera Channu Matam 14.5 0.73 2887 Paid
20 M. Nawaz s/o Fazal Channu Matam 29.1 1.45 5775 Paid
21 Akbar / Mian Khan s/o Sadan Channu Matam 58.2 2.91 11549 Paid
22 M. Saeed s/o Shameer Channu Matam 14.5 0.73 2887 Paid
23 Nazar Hussain s/o Murad Channu Matam 14.5 0.73 2887 Paid
24 Iman s/o Muhammad Channu Matam 14.5 0.73 2887 Paid
25 Jhangeer Bukhtawar Channu Matam 14.5 0.73 2887 Paid
26 Haji Shar s/o Ameer Channu Matam 14.5 0.73 2887 Paid
27 Bashir s/o Ameer Channu Matam 14.5 0.73 2887 Paid
28 Jafar s/o Shameer Channu Matam 14.5 0.73 2887 Paid
29 Ameer s/o Shair Channu Matam 14.5 0.73 2887 Paid
30 Mulazam Hussain s/o Shair Channu Matam 14.5 0.73 2887 Paid
31 Jahan Khan s/o Dolat Khan Channu Matam 29.1 1.45 5775 Paid
32 Akbar s/o Sadan Channu Matam 43.6 2.18 8662 Paid
33 Nazar Hussain s/o bakar Channu Matam 14.5 0.73 2887 Paid
34 Bashir s/o Ameer Channu Matam 14.5 0.73 2887 Paid
35 Anwar s/o Fazal Channu Matam 14.5 0.73 2887 Paid
36 Jafar s/o Shameer Channu Matam 14.5 0.73 2887 Paid
37 Amanat Ali s/o Noor Channu Matam 29.1 1.45 5775 Paid
Internal Monitoring Report
Lower Bari Doab Canal Improvement Project
7
S.# Name RD/ Address
Land
Encroached Compensation
Amount (Rs)
Remarks
Marlas Kanals
38 Munwar s/o Sahir Channu Matam 29.1 1.45 5775 Paid
39 Jahngeer s/o Noora Channu Matam 43.6 2.18 8662 Paid
40 M. Yar s/o Ahmad Khan Nmdar Jassokey Kalasan 21.8 1.09 4331 Paid
41 Alla yar s/o Ahmed Khan Jassokey Kalasan 32.7 1.64 6496 Paid
42 Muhammad Aslam s/o Baga Jassokey Kalasan 10.2 0.51 2021 Paid
43 Muhammad Anwar s/o Torez Jassokey Kalasan 6.5 0.32 1283 Paid
44 Noor Mohd s/o Mumraiz Jassokey Kalasan 6.5 0.32 1283 Paid
45 Mohd Abbas s/o Mumraiz Jassokey Kalasan 17.0 0.85 3368 Paid
46 Allah Ditta s/o Choghata Jassokey Kalasan 5.7 0.28 1123 Paid
47 Saeed s/o Muhammad Kharal Fatehpur Minor 8.1 0.40 1604 Paid
48 Shabir s/o Lal Fatehpur Minor 4.0 0.20 802 Paid
49 Bukhush s/o Lal Fatehpur Minor 4.0 0.20 802 Paid
50 Shameer s/o Warayam Fatehpur Minor 8.1 0.40 1604 Paid
51 Muhammad Ali s/o Karmal Fatehpur Minor 8.1 0.40 1604 Paid
52 Ramzan s/o Khan Fatehpur Minor 8.1 0.40 1604 Paid
53 Munza s/o Ali Sheir Fatehpur Minor 8.1 0.40 1604 Paid
54 Jalla s/o Ghulam Fatehpur Minor 8.1 0.40 1604 Paid
55 Ahmad Ali s/o Ghulam Fatehpur Minor 8.1 0.40 1604 Paid
56 Ameer Ali s/o Sultan Fatehpur Minor 8.1 0.40 1604 Paid
13. The compensation payment made to APs that includes relocation and vulnerable
allowances for compensating project impacts to the private structures is detailed below:
TABLE 2.2: COMPENSATION FOR DOMESTIC STRUCTURES
S.
# Name of AP Address
Location
(RD)
Detail of
Structures
Type
Kacha
/
Pacca
Area
(Sq.ft)
Standard
Rates
Relocation
Allowance/
Subsidy
Cost
Compens
ation
to be
awarded
(Rs.)
Vulnera
ble Total Remarks
57 Noor Lakhu Abadi Fateh
Pur 87 Room K 180 200.0 5000.0 36000 6000 47000 Paid
58 M. Iqbal Bhata Stop
Colony 12-13
Boundary
wall P 342 50.0 0.0 17100
17100 Paid
59 Sikandar
Hayat
Moza
Tariqabad 10-20 Shed K 420 200.0 0.0 84000
84000 Paid
60 Basara Pul Peer Ali 32-33 Shed K 294 200.0 0.0 58800
58800 Paid
61 M. Sharif Masan Ke 48-49 Chaper K 150 200.0 0.0 30000
30000 Paid
62 M. Anwar Basti Kasia 10-11 Patio K 345 100.0 0.0 34500 6000 40500 Paid
Internal Monitoring Report
Lower Bari Doab Canal Improvement Project
8
14. The payment made to APs that includes applicable allowances for compensating on
Jandraka Distributary sub-project impact on the business structures is detailed below:
TABLE 2.3: COMPENSATION FOR IMPACTED BUSINESS STRUCTURES
Sr.
No Name of AP
Address
Location
(RD)
Detail of
Structure
Dislocation
&
Relocation
Valuation
(Rs.)
Income
Impact
Valuation
(Rs.)
Total
Compensation
to be awarded
(Rs.)
Remarks
63 Walayat Mohd. Fateh Pur 87-88 Chapper 5000 9000 14000 Paid
64 M. Mushtaq Kot Sultan Pur 7-8
Chapper+
Table
Chair
5000 9000 14000 Paid
65 Bashir Ahmed Kot Sultan Pur 7-8
Chapper
Table
Chair
5000 9000 14000 Paid
66 M. Arshad Kot Sultan Pur 7-8 Chapper+
Table 5000 15000 20000 Paid
67 Sajeel Ahmad Kot Sultan Pur 7-8 Wooden
Table 5000 24000 29000 Paid
15. The following APs of Jandraka sub-project have been paid for compensating project
impact on their private fixtures:
TABLE 2.4: COMPENSATION FOR PRIVATE FIXTURES
Sr.No Address Location
(RD)
Detail of
Infrastructure
Type of
Structure
(K,P)
Est.
Cost
(Rs.)
Owner's
Name Occupation
Remarks
68 Thatha Dhaku
Wala 2-3 Hand Pump with cistern P 6000 Faazal Dhaku Agriculture Paid
69 Fathe Pur 87-88 Hand Pump with cistern P 6000 Manzoor
Watoo Labour Paid
70 Thatha Dhaku
Wala 2-3 Hand Pump with cistern P 6000
Muhammad
Niaz Agriculture Paid
71 Chah Hashmat
Wala 8-9 Hand Pump with cistern P 6000
Hussain
Muhammad Agriculture
AP not
Affected
72 Moza Padhar
(Abadi Judge) 35-36 Hand Pump with cistern P 6000 Pehlwan Agriculture Paid
73 Moza Padhar
(Abadi Judge) 40-41 Hand Pump with cistern P 6000 Sanatta Agriculture
AP not
affected
74 Moza Masan ke 43-44 Hand Pump with cistern P 6000 Zafar Iqbal Agriculture Paid
75 Moza Masan ke 43-44 Hand Pump with cistern P 6000 M. Jaffar Agriculture Paid
76 Moza Masan ke 43-44 Hand Pump with cistern P 6000 Daulat Ali Agriculture Paid
77 Moza Masan ke
(Basti Abdullah) 44-45 Hand Pump with cistern P 6000 Yousaf Agriculture Paid
78 Masan ke (Thatha) 45-46 Hand Pump with cistern P 6000 M. Sharif Preacher Paid
79 Van Dabbo ke 60-61 Hand Pump with cistern P 6000 M. Iqbal Agriculture Paid
80 Van Dabbo ke 60-61 Hand Pump P 12000 Pervaiz Agriculture Paid
Internal Monitoring Report
Lower Bari Doab Canal Improvement Project
9
Sr.No Address Location
(RD)
Detail of
Infrastructure
Type of
Structure
(K,P)
Est.
Cost
(Rs.)
Owner's
Name Occupation
Remarks
Boundary wall Ahmad
81 Van Dabbo ke 61-62 Hand Pump with cistern P 6000 Ali Ahmad Agriculture AP not
affected
82 Van Dabbo ke 62-63 Hand Pump with cistern P 6000 Javaid Agriculture Paid
83 Thatha Roshan Ke 65-66 Hand Pump with cistern P 6000 Ghulam Farid Agriculture Paid
84 Thatha Roshan Ke 65-66 Hand Pump with cistern P 6000 Mushtaq
Ahmad Agriculture
AP not
affected
85 Thatha Roshan Ke 65-66 Hand Pump with cistern P 6000 M. Akram Agriculture Paid
86 Thatha Roshan Ke 65-66 Hand Pump
Boundary Wall P 12000 Subah Sadiq Agriculture Paid
87 Thatha Roshan Ke 66-67 Hand Pump with cistern P 6000 Sanatta Agriculture AP not
affected
88 Thatha Roshan Ke 66-67 Hand Pump
Boundary wall P 12000 M. Abbas Agriculture
AP not
affected
89 Thatha Roshan Ke 66-67 Hand Pump
Boundary wall P 12000 Ahmad Ali Agriculture Paid
90 Thatha Roshan Ke 66-67 Hand Pump
Boundary wall P 12000 Abdullah Agriculture Paid
91 Thatha Roshan Ke 67-68 Hand Pump
Boundary wall P 12000 Waris Agriculture Paid
92 Thatha Roshan Ke 67-68 Hand Pump
Boundary wall P 12000 Ahmad Ali Agriculture Paid
93 Thatha Pehlwan
Ke 12-13 Hand Pump with cistern P 6000
Maqbool
Ahmed Agriculture
Paid
16. The following APs have been compensated for their private trees to be removed for
implementation of the sub-project. They were allowed to salvage the wood.
TABLE 2.5: COMPENSATION TO APs FOR PRIVATE TREES
Sr.
No.
Owner Location
Kind of
Trees
Avg.
Age
(Years)
No. of
Trees
Re-Plantation
Compensation
(Rs.) Location Remarks
94 M. Anwar Abadi Mazharabad
Bohr 4 1 1350 R
Paid Toot 7 2 2700 R
Beri 3 1 1350 R
95 Nazeer Ahmad Abadi Mazharabad Shisham 5 2 2700 R Paid
96 Bashir Ahmad Abadi Mazharabad Shisham 5 1 1350 R Paid
97 M. Ali Mochi Kot Tufail Wala Bohr 5 1 1350 R Paid
98 Master Sikandar Kot M. Anwar Popular 10 6 8100 R Paid
99 Sayyad Ikhtayar
Hussain
Basti Sayyadan, Kot
Sultan Pur Popular 10 4 5400 R Paid
100 Noor Samand Abadi Joya Khichi Shisham 5 1 1350 R Paid
101 M. Niaz Asif Thath Dhakku Wala Shisham 5 1 1350 L Paid
Internal Monitoring Report Lower Bari Doab Canal Improvement Project
10
3 SUB-PROJECT NCB-02 15-L DISTRIBUTARY
17. The following APs of 15L-Distributary System have been compensated for loss to their private structures & fixtures.
TABLE 3.1: COMPENSATION TO APs STRUCTURES & FIXTURES
ID.
No RD Location Name of AP
Structure
Category
Structure
Type
Structure
Affected
Size
Unit
Rate
Estimated
Cost (Rs)
Livelihood
Allowance
Transport
Allowance
Vulnerable
Allowance Total Remarks
L W Area
(S.ft)
1 2 42-15L Dildar Residential Kacha
100% Sub Total 88’440
7’442 2’000 7’442 105’324 Paid Room 15 19 285 300 85’500
Wall 42 - 42 70 2’940
2 88 95-15L Din
Muhammad Commercial Kacha
Hand
Pump Sub Total 6’000 6’000 N/A - - 6’000 Paid
3 88 95-15L Munawar
Hussain Commercial Kacha
Boundary
Wall 48 - 48 70 3’360 N/A - 3’360 Paid
4 88 95-15L Muhammad
Saleem Commercial
Counter+
Cage N/A* - - N/A N/A N/A 14’884 2’000 - 16’884 Paid
5 88 95-15L Muhammad
Javed Employee N/A N/A - - N/A N/A N/A 22’326 - - 22’326 Paid
6 106 Jandiali Muhammad
Akram Commercial
Chair
Table N/A - - N/A N/A N/A 14’884 2’000 - 16’884 Paid
7 106 Jandiali Riaz Ahmed Commercial Poultry
Cage N/A - - N/A N/A N/A 14’884 2’000 - 16’884 Paid
8 106 Jandiali Intazar Ali Commercial 2 Tables N/A - - N/A N/A N/A 14’884 2’000 - 16’884 Paid
9 106 Jandiali Shah Mohd Commercial Adda N/A - - N/A N/A N/A 14’884 2’000 - 16’884 Not
Affected
10 106 Jandiali Muhammad
Imran Commercial Kiosk N/A - - N/A 5’000 5’000 14’884 2’000 - 21’884 Paid
11 106 Jandiali Muhammad
Iqbal Commercial Kiosk N/A - - N/A 5’000 5’000 14’884 2’000 7’442 29’326 Paid
Internal Monitoring Report Lower Bari Doab Canal Improvement Project
11
ID.
No RD Location Name of AP
Structure
Category
Structure
Type
Structure
Affected
Size
Unit
Rate
Estimated
Cost (Rs)
Livelihood
Allowance
Transport
Allowance
Vulnerable
Allowance Total Remarks
L W Area
(S.ft)
12 106 Jandiali Haq Nawaz Commercial Kiosk /
Table N/A - - N/A 5’000 5’000 14’884 2’000 - 21’884 Paid
13 106 Jandiali Muhammad
Yasin Commercial Kiosk N/A - - N/A 5’000 5’000 14’884 2’000 - 21’884 Paid
14 106 Jandiali Muhammad
Yousaf Commercial Adda N/A - - N/A N/A N/A 14’884 7’442 7’442 22’326 Paid
15 106 Jandiali Asif Javed Commercial Kiosk N/A - - N/A 5’000 5’000 14’884 2’000 21’884 Paid
16 106 Jandiali Muhammad
Nadeem Commercial Kiosk N/A - - N/A 5’000 5’000 14’884 2’000 21’884 Paid
17 106 Jandiali Ghulam
Rasool Commercial Kiosk N/A - - N/A 5’000 5’000 14’884 2’000 - 21’884 Paid
18 115 57-15L Abdul
Rasheed Commercial
Table
Chair N/A - - N/A N/A N/A 14’884 2’000 7’442 22’326 Paid
19 116 57-15L Abu-ul-
Hassan Commercial Kiosk N/A - - N/A 5’000 5’000 14’884 2’000 - 21’884 Paid
20 116 57-15L M. Zafar Commercial Kiosk N/A - - N/A 5’000 5’000 14’884 2’000 - 21’884 Paid
21 132 59-15L Mulazim
Hussain Commercial Kiosk N/A - - N/A 5’000 5’000 14’884 2’000 - 21’884
Not
Affected
22 132 59-15L Rab Nawaz Commercial Shed N/A - - N/A N/A N/A 14’884 2’000 - 16’884 Paid
23 132 59-15L Muzzafar
Iqbal Commercial
Table
Chair N/A - - N/A N/A N/A 14’884 2’000 - 16’884 Paid
24 132 59-15L Qamar
Abbas Commercial
Table
Chair N/A - - N/A N/A N/A 14’884 2’000 7’442 24’326 Paid
25 132 59-15L Rab Nawaz Commercial
Kiosk+
Table
Chair
N/A - - N/A 5’000 5’000 14’884 2’000 - 21’884 Paid
26 132 59-15L
Khan
Shamir
Ahmed
Commercial Table
Chair N/A - - N/A N/A N/A 14’884 2’000 - 16’884
AP not
affected
Internal Monitoring Report Lower Bari Doab Canal Improvement Project
12
ID.
No RD Location Name of AP
Structure
Category
Structure
Type
Structure
Affected
Size
Unit
Rate
Estimated
Cost (Rs)
Livelihood
Allowance
Transport
Allowance
Vulnerable
Allowance Total Remarks
L W Area
(S.ft)
27 132 59-15L Muhammad
Murad Commercial Adda N/A - - N/A N/A N/A 14’884 - 7’442 22’326 Paid
28 132 59-15L Ghulam
Abbas Commercial
Kiosk +
Table N/A - - N/A 5’000 5’000 14’884 2’000 - 21’884 Paid
29 132 59-15L Abdul
Rehman Commercial
Kiosk
Table N/A - - N/A 5’000 5’000 14’884 2’000 7’442 29’326 Paid
30 132 59-15L Muhammad
Mazahar Commercial Kiosk N/A - - N/A 5’000 5’000 14’884 2’000 - 21’884 Paid
31 132 59-15L Suleman Commercial 2 Kiosks N/A - - N/A 5’000 10’000 14’884 2’000 - 26’884 Paid
32 132 59-15L Bashir
Ahmed Commercial Kiosk N/A - - N/A 5’000 5’000 14’884 2’000 7’442 29’326 Paid
33 132 59-15L Muhammad
Riaz Commercial Kiosk N/A - - N/A 5’000 5’000 14’884 2’000 7,442 29’326 Paid
34 158 Chab Muhammad
Aslam Commercial Kiosk N/A - - N/A 5’000 5’000 14’884 2’000 - 21’884 Paid
35 158 Chab Iftikhar
Ahmed Commercial Kiosk N/A - - N/A 5’000 5’000 14’884 2’000 - 21’884 Paid
36 158 Chab Muhammad
Tariq Commercial Kiosk N/A - - N/A 5’000 5’000 14’884 2’000 - 21’884 Paid
37 158 Chab Muhammad
Akram Commercial Kiosk N/A - - N/A 5’000 5’000 14’884 2’000 - 21’884 Paid
38 158 Chab Abdul
Shakoor Commercial Adda N/A - - N/A N/A N/A 14’884 2’000 7’442 22’326 Paid
39 158 Chab Maqbool
Ahmed Commercial Table N/A - - N/A N/A N/A 14’884 2’000 - 16’884 Paid
40 158 Chab Ghulam
Abbas Commercial Kiosk N/A - - N/A 5’000 5’000 14’884 2’000 7’442 29’326 Paid
41 158 Chab Sher
Muhammad Commercial Kiosk N/A - - N/A 5’000 5’000 14’884 2’000 7’442 29’326 Paid
Internal Monitoring Report Lower Bari Doab Canal Improvement Project
13
ID.
No RD Location Name of AP
Structure
Category
Structure
Type
Structure
Affected
Size
Unit
Rate
Estimated
Cost (Rs)
Livelihood
Allowance
Transport
Allowance
Vulnerable
Allowance Total Remarks
L W Area
(S.ft)
42 158 Chab Muhammad
Zakariya Commercial Kiosk N/A - - N/A 5’000 5’000 14’884 2’000 - 21’884 Paid
43 158 Chab Muhammad
Amjad Commercial Kiosk N/A - - N/A 5’000 5’000 14’884 2’000 - 21’884
Not
affected
44 158 Chab Muhammad
Bashir Commercial Kiosk N/A - - N/A 5’000 5’000 14’884 2’000 - 21’884 Paid
45 158 Chab Muhammad
Aslam Commercial Kiosk N/A - - N/A 5’000 5’000 14’884 2’000 7’442 29’326 Paid
46 158 Chab Muhammad
Khurshid Commercial Kiosk N/A - - N/A 5’000 5’000 14’884 2’000 - 21’884 Paid
47 158 Chab Muhammad
Akram Commercial Adda N/A - - N/A N/A N/A 14’884 2’000 - 16’884 Paid
48 158 Chab Haq Nawaz Commercial Adda N/A - - N/A N/A N/A 14’884 - 7’442 22’326 Paid
49 158 Chab Muhammad
Bukhsh Commercial
Table
Chair N/A - - N/A N/A N/A 14’884 2’000 7’442 24’326 Paid
50 158 Chab M. Imran Commercial Kiosk N/A - - N/A 5’000 5’000 14’884 2’000 - 21’884 Paid
51 158 Chab Muhammad
Ajmal Commercial Adda N/A - - N/A N/A N/A 14’884 - 7’442 22’326 Paid
52 158 Chab Muhammad
Yasin Commercial Adda N/A - - N/A N/A N/A 14’884 2’000 - 16’884 Paid
53 158 Chab Nasar Ullah Commercial Kiosk N/A - - N/A 5’000 5’000 14’884 2’000 - 21’884 Paid
54 158 Chab Ikram Ullah Commercial Table +
Cage N/A - - N/A N/A N/A 14’884 - 7’442 22’326 Paid
55 175 82-15L M. Ameer Residential
Bathing
Place Structure
Sub Total 10800
- - - 10800 Paid 4 6 24 200 4’800
H. Pump - - - 6’000 6’000
56 2 2R-15L Binyameen Residential S. Pacca H. Pump - - - 6’000 6’000 7442 - - 13442 Not
affected
Internal Monitoring Report Lower Bari Doab Canal Improvement Project
14
ID.
No RD Location Name of AP
Structure
Category
Structure
Type
Structure
Affected
Size
Unit
Rate
Estimated
Cost (Rs)
Livelihood
Allowance
Transport
Allowance
Vulnerable
Allowance Total Remarks
L W Area
(S.ft)
57 2 2R-15L Abdul Sattar Residential Kacca H. Pump - - - 6’000 6’000 - - - 6000 Paid
58
3 2R-15L Shabbir
Ahmad Residential S. Pacca
B. Wall Sub Total 12500
- - 12,500
Not
affected
40 - - 100 4000
B. Wall 25 - - 100 2500
H. Pump - - - 6000 6000
59 9 2R-15L Lal Din Residential Semi
Pacca
Sub Total 46’800
- - - 46800 Not
affected
Animal
Shed 12 12 124 200 28’800
Thara 12 15 180 100 18’000
60 66 2R-15L Mushtaq
Ahmad Residential S. Pacca H. Pump - - - 6’000 6’000 - - - 6000
Not
affected
61 3 2R-15L Mazhar
Hussain Residential Pacca H. Pump - - - 6’000 6’000 - - - 6000
Not
affected
62 21 3R-15L Asif Hussain Commercial Table H. Pump - - - 6’000 6’000 - 2’000 - 6000
Not
affected
63 18 1L-2R Muhammad
Afzal Residential S.Pacca H. Pump - - - 6’000 6’000 - - - 6000
Not
affected
64 2 3L-15L Muhammad
Asghar Commercial S. Paaca Tharah 6 6 36 100 3’600 14’884 2’000 7’442 27’926
Not
affected
65 11 3L-15L Abdul
Ghafoor Commercial Shed Moveable - - - - - 14’884 2’000 - 16’884 Paid
Internal Monitoring Report Lower Bari Doab Canal Improvement Project
15
4 SUB-PROJECT ICB-01 MAIN CANAL
18. The payment made to APs that includes livelihood & transport allowances for compensating sub-project impact affected
structures is detailed below:
TABLE 4.1: COMPENSATION FOR AFFECTED STRUCTURES
ID
No. RD Location
Canal
Side Name of AP
Structure
Category
Structure
Type
Structure
Affected
Size Unit
Rate
Estimated
Cost
Total Cost of
Affected
Structures
Livelihood
Allowance
Transport
Allowance
Additional
Assistance for
Vulnerable
Total Remarks L W H
Area
(sq.ft)
1 58 Tibba
Piran Da RS
Muhammad
Aslam Cattle Sheds
Shed Thatched 25 10 8 250 100 25,000
32,000
2,000
34,000 Not Affected Boundary
Wall Mud 100 0 5 100 70 7,000
2 62 Halla
Bridge RS
Abdul
Ghafoor Comercial Shed Thatched 15 9 13 135 100 13,500 13,500 15,600 2,000
31,100 No affected
3 78 Lakho
Daher RS
Naeem
Hussain
Shah
Cattle Sheds
Cattle Shed S.Pacca 31 15 12 465 200 93,000
204,600
2,000
206,600 No affected
Cattle Shed S.Pacca 23 13 11 287.5 200 57,500
Cattle Shed Kacha 18 14 11 252 150 37,800
Shed Thatched 12 10 11 120 100 12,000
Boundary
Wall S.Pacca 43 0 6 43 100 4,300
4 104 K.plot RS M.Nawaz Residential
Boat Moveable N/A 5,000 5,000
6,050 15,600
7,800 29,450 No affected Boundary
Wall Mud 15
15 70 1,050
5 162 Renala
Khurd RS M. Hanif Commercial Khokha Moveable N/A 5,000 5,000 5,000 15,600 2,000 7,800 30,400
6 162 Renala
Khurd RS
Faiz
Muhammad Commercial
Khokha+
Table Moveable N/A 5,000 5,000 5,000 15,600 2,000 7,800 30,400
7 162 Renala
Khurd RS M. Ali Commercial
Table+
Chair Moveable N/A
15,600 2,000 7,800 25,400
8 162 Renala RS Malik Commercial Khokha+ Moveable N/A 5,000 5,000 5,000 15,600 2,000 7,800 30,400
Internal Monitoring Report Lower Bari Doab Canal Improvement Project
16
ID
No. RD Location
Canal
Side Name of AP
Structure
Category
Structure
Type
Structure
Affected
Size Unit
Rate
Estimated
Cost
Total Cost of
Affected
Structures
Livelihood
Allowance
Transport
Allowance
Additional
Assistance for
Vulnerable
Total Remarks L W H
Area
(sq.ft)
Khurd M.Ashfaq Rehri
Reach not
included in
LBDCIP
9 162 Renala
Khurd Ls M. Safadar Commercial Rehri Moveable N/A
5,000 15,600
7,800 28,400
10 162 Renala
Khurd RS Noor Ahmad Commercial Adda Moveable N/A
15,600
15,600
11 162 Renala
Khurd RS Wajid Ali Commercial
Table+
Chair Moveable N/A
15,600 2,000 7,800 25,400
12 162 Renala
Khurd RS
M.Naveed
Akhter Commercial
Khokha
+Table
+Chair
Moveable N/A 5,000 5,000 5,000 15,600 2,000 7,800 30,400
13 162 Renala
Khurd RS M. Rafiq Commercial Khokha Moveable N/A 5,000 5,000 5,000 15,600 2,000 7,800 30,400
14 162 Renala
Khurd RS Zulifiqar Ali Commercial
Khokha+
Table Moveable N/A 5,000 5,000 5,000 15,600 2,000 7,800 30,400
15 162 Renala
Khurd RS M.Asif Commercial
Table+
Chair Moveable N/A
15,600 2,000 7,800 25,400
16 162 Renala
Khurd RS
Umer
Farooq Commercial
Table+
Chair Moveable N/A
15,600 2,000 7,800 25,400
17 162 Renala
Khurd RS
Dil
Muhammad Commercial
Khokha+
Table Moveable N/A 5,000 5,000 5,000 15,600 2,000
22,600
18 162 Renala
Khurd RS M. Shafiq Commercial
Table+
Chair Moveable N/A
15,600 2,000 7,800 25,400
19 162 Renala
Khurd LS M. Naeem Commercial Shed Thatched 25 15
375 100 37,500 37,500 15,600 2,000 No affected 55,100
20 162 Renala
Khurd RS
M. Hanif
Masih Commercial Khokha Moveable N/A 5,000 5,000 5,000 15,600 2,000 7,800 30,400
21 162 Renala
Khurd RS M, Ilyas Commercial
Table+
Chair Moveable N/A
15,600 2,000 7,800 25,400
22 162 Renala
Khurd LS M. Adnan Commercial Table Moveable N/A
15,600 2,000 7,800 25,400
Internal Monitoring Report Lower Bari Doab Canal Improvement Project
17
ID
No. RD Location
Canal
Side Name of AP
Structure
Category
Structure
Type
Structure
Affected
Size Unit
Rate
Estimated
Cost
Total Cost of
Affected
Structures
Livelihood
Allowance
Transport
Allowance
Additional
Assistance for
Vulnerable
Total Remarks L W H
Area
(sq.ft)
23 162 Renala
Khurd LS Daryafat Ali Commercial Khokha Moveable N/A 5,000 5,000 5,000 15,600 2,000
22,600
24 162 Renala
Khurd LS M. Siddiq Commercial Table Moveable N/A
15,600 2,000 7,800 25,400
25 162 Renala
Khurd LS Liaqat Ali Commercial Khokha Moveable N/A 5,000 5,000 5,000 15,600 2,000 7,800 30,400
26 162 Renala
Khurd LS Abdul Sattar Commercial
Khokha+
Cage Moveable N/A 5,000 5,000 5,000 15,600 2,000
22,600
27 178 23/1R LS M. Afzal Commercial
Boat Moveable N/A 5,000 5,000
23,600 93,600 2,000
119,200 Paid Hut Kacha 14 9
126 100 12,600
Hand Pump Moveable N/A 6,000 6,000
28 188 24/2R LS Ali Sher
Shah Commercial
Boat Moveable N/A 5,000 5,000
35,000 93,600 2,000
130,600 Paid Room kacha 10 10
100 300 30,000
Internal Monitoring Report Lower Bari Doab Canal Improvement Project
18
19. The detail of payment made to APs that includes private tree compensation for occupation of private land on temporary basis
for a period of 03 years under section-35 of Land Acquisition Act, 1894 is detailed below:
TABLE 4.2: COMPENSATION TO APs FOR TEMPORARY OCCUPATION OF LAND
ID
No. RD Location
Canal
Side Name of AP Category
Structure
Affected
Area
Lease
Rate/
Acre per
year
Estimated
Cost of 1
Years Lease
Estimated
Cost of 3
Years Lease
Total Trees
Estimated
Cost of
Trees
Total Cost Remarks
Kanal Marla Acre RS Rs Rs Young Adult
1 28 Jajja Kalan RS Hukam Din Agri. Land Temp.
Land Acq 11 8 1.43 50,000 71,250 213,750 - - - 213,750 Paid
2 28 Jajja Kalan RS Muhammad
Din Agri. Land
Temp.
Land Acq 13 18 1.74 50,000 86,875 260,625 12 5 8,806 269,448 Paid
3 29 Jajja Kalan RS Khair Din Agri. Land Temp.
Land Acq 15 5 1.91 50,000 95,313 285,938
6 7,140 293,084 Paid
4 29 Jajja Kalan RS Zafar Din Agri. Land Temp.
Land Acq 7 0 0.88 50,000 43,750 131,250 1
238 131,489 Paid
5 30 Jajja Kalan RS
Nabian Bibi
(Donated to
a Mosque)
Agri. Land Temp.
Land Acq 2 0 0.25 50,000 12,500 37,500 - - - 37,500 Paid
6 30 Jajja Kalan RS Jan
Muhammad Agri. Land
Temp.
Land Acq 5 6 0.66 50,000 33,125 99,375
2 2,380 101,757 Paid
8 30 Jajja Kalan RS Jabar Din Agri. Land Temp.
Land Acq 3 0 0.38 50,000 18,750 56,250 - - - 56,250 Paid
7 30 Jajja Kalan RS Nizam
Din,etc Agri. Land
Temp.
Land Acq 13 3 1.64 50,000 82,188 246,563 - - - 246,563 Paid
9 31 Jajja Kalan RS Nazir
Ahmed Agri. Land
Temp.
Land Acq 25 7 3.17 50,000 158,438 475,313
3 3,570 478,886 Paid
10 31 Jajja Kalan RS
Sardar
Kamaran
Nakai
Agri. Land Temp.
Land Acq 11 11 1.44 50,000 72,188 216,563 - - - 216,563 Paid
11 31 Jajja Kalan RS Asghar Agri. Land Temp. 2 10 0.31 50,000 15,625 46,875 - - - 46,875 Paid
Internal Monitoring Report Lower Bari Doab Canal Improvement Project
19
ID
No. RD Location
Canal
Side Name of AP Category
Structure
Affected
Area
Lease
Rate/
Acre per
year
Estimated
Cost of 1
Years Lease
Estimated
Cost of 3
Years Lease
Total Trees
Estimated
Cost of
Trees
Total Cost Remarks
Kanal Marla Acre RS Rs Rs Young Adult
Ali,etc Land Acq
12 63 Halla Bridge LS Abdul
Majeed Agri. Land
Temp.
Land Acq 43 10 5.44 50,000 271,875 815,625 2 1 1,666 817,294 Paid
13 63 Halla LS
Haji
Muhammad
Hussain
Agri. Land Temp.
Land Acq 3 10 0.44 50,000 21,875 65,625 - - - 65,625 Paid
14 63 Lakho Der LS Muhammad
Hussain Agri. Land
Temp.
Land Acq 4 0 0.50 50,000 25,000 75,000 - - - 75,000 Paid
15 64 Halla LS Muhammad
Anwar Agri. Land
Temp.
Land Acq 13 8 1.68 50,000 83,750 251,250 47 1 12,376 263,674 Paid
16 64 Halla LS Muhammad
Sarwar Agri. Land
Temp.
Land Acq 13 4 1.65 50,000 82,500 247,500 28 2 9,044 256,574 Paid
17 64 Halla LS Razia Bibi Agri. Land Temp.
Land Acq 7 2 0.89 50,000 44,375 133,125 11
2,618 135,754 Paid
18 64 Lakho Der LS Muhammad
Arshad Agri. Land
Temp.
Land Acq 7 6 0.91 50,000 45,625 136,875 - - - 136,875 Paid
19 65 Halla LS
Deenar
Ahmad
Mateen
Agri. Land Temp.
Land Acq 4 15 0.59 50,000 29,688 89,063 - - - 89,063 Paid
20 65 Halla LS Muhammad
Bashir Agri. Land
Temp.
Land Acq 12 0 1.50 50,000 75,000 225,000 8 1 3,094 228,103 Paid
21 65 Kot Umer
Din LS
Hasan
Muhammad Agri. Land
Temp.
Land Acq 16 15 2.09 50,000 104,688 314,063
1 1,190 315,254 Paid
22 111 Qili Jamal
Singh RS
Muhammad
Luqman Agri. Land
Temp.
Land Acq 6 2 0.76 50,000 38,125 114,375 60 4 19,040 133,479 Paid
23 111 Qili Jamal
Singh RS Umer Hayat Agri. Land
Temp.
Land Acq 1 8 0.18 50,000 8,750 26,250 - - - 26,250 Paid
24 112 Qili Jamal RS Muhammad Agri. Land Temp. 7 8 0.93 50,000 46,250 138,750 7
1,666 140,423 Paid
Internal Monitoring Report Lower Bari Doab Canal Improvement Project
20
ID
No. RD Location
Canal
Side Name of AP Category
Structure
Affected
Area
Lease
Rate/
Acre per
year
Estimated
Cost of 1
Years Lease
Estimated
Cost of 3
Years Lease
Total Trees
Estimated
Cost of
Trees
Total Cost Remarks
Kanal Marla Acre RS Rs Rs Young Adult
Singh Alam Land Acq
25 112 Qili Jamal
Singh RS
Muhammad
Irshad Agri. Land
Temp.
Land Acq 1 12 0.20 50,000 10,000 30,000 27
6,426 36,453 Paid
26 113 Qili Jamal
Singh RS
Muhammad
Idrees Agri. Land
Temp.
Land Acq 6 3 0.77 50,000 38,438 115,313 25
5,950 121,288 Paid
27 113 Kot
Muhammad Rs Muhammad Agri. Land
Temp.
Land Acq 10 17 1.36 50,000 67,813 203,438 4 6 8,092 211,540 Paid
Internal Monitoring Report Lower Bari Doab Canal Improvement Project
21
5 SUB-PROJECT ICB-02 MAIN CANAL
20. The detail of payment made to APs that includes additional assistance/vulnerable allowance and private tree compensation for
occupation of private land on temporary basis for a period of 03 years under section-35 of Land Acquisition Act, 1894 is
detailed below:
TABLE 5.1 STATUS OF COMPENSATION TO APs OF TEMPORARY LAND OCCUPATION
ID
No. RD Location
Canal
Side Name of AP
Monthly
Income
(Rs.)
Area Lease Rate/
Acre per year
Estimated Cost
of 3 Years
Lease
Private
Trees Additional
Assistance
Total
Cost Remarks
Kanal Marla Acre RS Rs Rs
1 258 60/4-R RS M. Siddiq s/o M.Abdullaha 3,000 4 5 0.53 50,000 79,688 - 9,620 89,308 Paid
2 258 60/4-R RS M. Haji s/o M.Abdullaha 3,500 4 5 0.53 50,000 79,688 - 9,620 89,308 Paid
3 258 60/4-R RS Bashir Ahmed s/o
M.Abdullaha 3,500 4 4 0.53 50,000 78,750 - 9,620 88,370 Paid
4 258 60/4-R RS M. Rafiq s/o M.Abdullaha 3,500 4 4 0.53 50,000 78,750 - 9,620 88,370 Paid
5 258 60/4-R RS Ashiq Ali s/o Umer Din 2,000 2 4 0.28 50,000 41,250 - 9,620 50,870 Paid
6 258 60/4-R RS Liaqat Ali s/o Sajawal 6,000 0 7 0.04 50,000 6,563 - 9,620 16,183 Paid
7 285 Sahiwal RS Mushataq Mughal s/o
Khurshid 70,000 4 17 0.61 50,000 90,938 1190 - 92,128 Paid
8 354 96/6-R RS M.Aslam s/o Rehmat Ali 53,000 2 10 0.31 50,000 46,875 - - 46,875 Paid
9 354 95/6-R RS Mubashar Hassan s/o
Mubarak Ali 40,000 1 10 0.19 50,000 28,125 - - 28,125 Paid
10 432 9/11-L LS Abdul Razaq s/o Abdullah 43,000 0 7 0.04 50,000 6,563 - - 6,563 Paid
11 432 9/11-L LS Khuram Shahzad s/o
Mushtaq Ahmad 41,000 8 2 1.01 50,000 151,875 - - 151,875 Paid
Internal Monitoring Report Lower Bari Doab Canal Improvement Project
22
21. The payment made to APs that includes livelihood, transport and vulnerable allowances for compensating sub-project impact
affected structures is detailed below:
TABLE 5.2 STATUS OF COMPENSATION TO APs FOR IMPACTED STRUCTURES
S # RD Name of AP Structure
Category
Structure
Affected
Structure
Type
Area
(Sq.
ft)
Unit
Rate
Estimated
Cost
Total Cost
of Affected
Structures
Livelihood
Allowance
Transport
Allowance
Vulnerable
Allowance Total Remarks
1 236 M.Sarfraz s/o
Bashir Ahmad Commercial Moveable Boat 0 - 5,000 5,000 19,240 - 9,620 33,860 Not Affected
2 243 Shoukat Ali s/o
M.Din Commercial
Shed Kacha 195 150 29,250
36,700 19,240 2,000 9,620 67,560
Cheques have been
prepared but not
issued due to
construction drawings
B. Wall Kacha 35 70 2,450
Moveable Boat 0 - 5,000
3 248 M. Iqbal s/o
Bashir Ahmad Com/Res
Room Kacha 154 300 46,200
104,000 115,440 2,000 9,620 138,060
Cheques have been
prepared but not
issued due to
construction drawings
Shed Kacha 312 150 46,800
H. P N/A 0 - 6,000
Moveable Boat 0 - 5,000
4 248 M. Iqbal s/o M.
Hassan Residential
Room Kacha 120 300 36,000
136,800 19,240 2,000 9,620 1,67,660
Not Affected
Room Kacha 140 300 42,000
Room Kacha 192 300 57,600
B. Room Pacca 8 150 1,200
5 258 Mian Khan s/o
M.Ali Commercial Adda N/A 0 - - - 19,240 - 9,620 28,860
Cheques have been
prepared but not
issued due to
construction drawings
6 258 M. Siddique s/o
Mehtab Din Commercial Patio Pacca 48 100 4,800 4,800 19,240 2,000 9,620 35,660
Cheques have been
prepared but not
issued due to
construction drawings
7 258 M.Ramzan
s/oAbdullah Residential
Room Kacha 308 300 92,400
98,910 9,620 2,000 9,620 1,20,150
Not Affected Kitchen Kacha 28 70 1,960
B. Wall Kacha 65 70 4,550
8 258 Gulzar Hussain
s/o Ahmed Shah Residential
Room Pacca 294 700 205,800
354,100 9,620 2,000 9,620 3,75,340
Not Affected Room S.Pacca 252 500 126,000
Bath
Room Pacca 16 700 11,200
Internal Monitoring Report Lower Bari Doab Canal Improvement Project
23
S # RD Name of AP Structure
Category
Structure
Affected
Structure
Type
Area
(Sq.
ft)
Unit
Rate
Estimated
Cost
Total Cost
of Affected
Structures
Livelihood
Allowance
Transport
Allowance
Vulnerable
Allowance Total Remarks
B. Wall S.Pacca 51 100 5,100
H. P 0 0 6,000 6,000
9 258 M. Shareef s/o
Khushi Mohd Residential
Room Kacha 105 300 31,500
203,900 9,620 2,000 - 2,15,520 Not Affected
Room S.Pacca 270 500 135,000
Room S.Pacca 60 500 30,000
B Room Kacha 20 70 1,400
H. P 0 0 6,000 6,000
10 258 Mumtaz Ahmed
s/o Said Ali Residential
Room S.Pacca 168 500 84,000
111,700 9,620 2,000 9,620 1,32,940 Not affected Shed Kacha 156 150 23,400
B. Wall S.Pacca 15 100 1,500
B. Wall Kacha 40 70 2,800
11 258
Niaz Shah
Chishti s/o
Ahmed Shah
Residential
Room S.Pacca 266 500 133,000
184,500 9,620 2,000 9,620 68,640
Payments
Synchronized with
Civil Work
Room Kacha 158 300 47,400
B. Wall S.Pacca 41 100 4,100
12 258 Shabeer Ahmed
s/o M. Ramzan Residential
Room Kacha 200 300 60,000
79,580 9,620 2,000 9,620 100,820 Payments
Synchronized with
Civil Work
Shed Kacha 117 150 17,550
B. Wall Kacha 29 70 2,030
13 258 Abdul Sattar s/o
Ahmed Shah Residential
Room Pacca 300 700 210,000
566,400 9,620 2,000 - 578020 Not Affected
Room Pacca 270 700 189,000
Kitchen S.Pacca 222 500 111,000
B Room Pacca 45 700 31,500
B. Wall Pacca 56 150 8,400
Turbine 0 3,000 3,000
Washing
Place Pacca 90 150 13,500
14 258 M. Khaliq s/o
Bashir Ahmed Residential
Room S.Pacca 195 500 97,500
173,800 9,620 2,000 9,620 195040 Not Affected Room S.Pacca 143 500 71,500
B. Wall Pacca 32 150 4,800
Internal Monitoring Report Lower Bari Doab Canal Improvement Project
24
S # RD Name of AP Structure
Category
Structure
Affected
Structure
Type
Area
(Sq.
ft)
Unit
Rate
Estimated
Cost
Total Cost
of Affected
Structures
Livelihood
Allowance
Transport
Allowance
Vulnerable
Allowance Total Remarks
15 271 Sabir Ali s/o
Inayat Commercial Moveable Boat 0 5,000 5,000 5,000 19,240 - 9,620 33860 Not Affected
16 299 M. Hanif s/o Shah
Muhammad Commercial Moveable Boat 0 5,000 5,000 5,000 115,440 0 9,620 130,060
Payments
Synchronized with
Civil Work
17 299 M. Tariq s/o Sarf
Din Commercial
Rehri Moveable 0 - -
5,000 19,240 - 9,620 33860
Not Affected Wood
Shed Moveable 80 - 5,000
18 322 Allah Ditta s/o
Abdul Haq Commercial
Moveable Boat 0 5,000 5,000 24,200 19,240 2,000 - 26,240
Payments
Synchronized
with Civil Work Room Kacha 64 300 19,200
19 330 Arshad Ali s/o
M.Anwer Commercial Shed Kacha 99 150 14,850 14,850 19,240 2,000 9,620 45,710 Not Affected
20 330
Muhammad
Sarwer s/o M.
Ibrahim
Com/Res Room Kacha 198 300 59,400
64,400 19,240 2,000 9,620 95,260
Payments
Synchronized
with Civil Work Moveable Boat 0 5,000 5,000
21 331 Tariq Saeed s/o
Said Muhammad Commercial Shed Pacca 100 300 30,000 30,000 19,240 2,000 9,620 60860 Not Affected
22 332 Himayat Ali s/o
Pehalwan Commercial Moveable Boat 0 - 5,000 5,000 19,240 - - 24240 Not Affected
23 333 Ali Gohar s/o
M.Yaqoob Commercial Moveable Boat 0 - 5,000 5,000 19,240 - 9,620 33,860
Cheques have
been prepared
but not issued
due to
construction
drawings
24 337 Tariq Ali s/o
M.Sarwer Commercial Shed Kacha 187 150 28,050 28,050 19,240 2,000 9,620 58,910
Cheques have
been prepared
but not issued
due to
construction
drawings
25 337 Iftikhar-ul-Haq
s/o Ch.M.Ali Commercial
Iron Shed Moveable 204 - 5,000
14,000 - - -
14,000
Cheques have
been prepared
but not issued
due to
construction
drawings
Hand
pump Moveable 0 - 6,000
Electric
Water
Pump
Moveable 0 3,000 3,000
Internal Monitoring Report Lower Bari Doab Canal Improvement Project
25
S # RD Name of AP Structure
Category
Structure
Affected
Structure
Type
Area
(Sq.
ft)
Unit
Rate
Estimated
Cost
Total Cost
of Affected
Structures
Livelihood
Allowance
Transport
Allowance
Vulnerable
Allowance Total Remarks
26 337 M.Sarwar s/o
M.Khalil Commercial Adda N/A 0 0 0 0 19,240 0 9,620 28,860
Payments
Synchronized
with Civil Work
27 337 M.Anwar s/o
Abul Ghafoor Commercial Adda N/A 0 0 0 0 19,240 0 9,620
28,860
Cheques have
been prepared
but not issued
due to
construction
drawings
28 337 M.Ihsan s/o
Qurban Commercial Adda N/A 0 0 0 0 19,240 0 0 19,240 Not Affected
29 337 M.Tufail s/o
M.Suleman Commercial Adda N/A 0 0 0 0 19,240 0 0 19,240
Cheques have
been prepared
but not issued
due to
construction
drawings
30 337 Zafar Abbas s/o
Qumbar Ali Commercial Adda N/A 0 0 0 0 19,240 0 9,620 28,860
Cheques have
been prepared
but not issued
due to
construction
drawings
31 337 M.Naeem s/o
Soukat Ali Commercial Adda N/A 0 0 0 0 19,240 0 9,620 28,860
Cheques have
been prepared
but not issued
due to
construction
drawings
32 338 Manzoor Ahmad
s/o Mian Lal Residential
Animal
Shed Moveable 140 - 5,000 5,000 - - - 5,000
Payments
Synchronized
with Civil Work
33 338 Pehlwan s/o
Ibrahim Com/Res Tent Moveable 0 - 5,000 5,000 19,240 - 9,620 33,860
Payments
Synchronized
with Civil Work
Internal Monitoring Report Lower Bari Doab Canal Improvement Project
26
S # RD Name of AP Structure
Category
Structure
Affected
Structure
Type
Area
(Sq.
ft)
Unit
Rate
Estimated
Cost
Total Cost
of Affected
Structures
Livelihood
Allowance
Transport
Allowance
Vulnerable
Allowance Total Remarks
34 338 Naeem Meboob
s/o M.Sharif Commercial Moveable Iron Kiosk 319 - 5,000 5,000 - - - 5,000
Cheques have
been prepared
but not issued
due to
construction
drawings
35 338 Allah Yar s/o
Ameer Ahmad Commercial Patio Pacca 39 150 5,850 5,850 19,240 2,000 9620 36,710
Payments
Synchronized
with Civil Work
36 338 M.Aslam s/o
Noor Ahmad Commercial Patio Pacca 30 150 4,500 4,500 19,240 2,000 9,620 35,360
Payments
Synchronized
with Civil Work
37 338 M.Iqbal s/o Falk
Sher Commercial Kiosk Moveable 0 - 5,000 5,000 19,240 - 9,620 33,860
Payments
Synchronized
with Civil Work
38 339 Munawar Shah
s/o Asghar Ali Com/Res
Shed S.Pacca 189 200 37,800
42,100 19,240 2,000 - 15,532
Cheques have
been issued due
to construction
drawings B. Wall S.Pacca 43 100 4,300
39 339 Shakir Ali s/o
Zakir Ali Residential Tent Moveable 0 - 5,000 5,000 9,620 - 9,620 24,240
Cheques have
been prepared
but not issued
due to
construction
drawings
40 338 Ali Sher s/o
Himayat Res/Com
Room Kacha 224 300 67,200
122,290 19,240 2,000 9,620 153,150
Cheques have
been prepared
but not issued
due to
construction
drawings
Shed Kacha 312 150 46,800
B. Wall Kacha 47 70 3,290
Moveable Boat 0 - 5,000
41 339 M.Arshad s/o
M.Shrif Commercial Shed S.Pacca 140 200 28,000 28,000 19,240 2,000 9,620 58,860
Cheques have
been prepared
but not issued
due to
construction
drawings
42 339 Habib s/o Nawaz Residential Room Pacca 154 700 107,800
146,300 9,620 2,000 9,620 167,540
Payments
Synchronized
with Civil Work Open Yard Pacca 770 50 38,500
Internal Monitoring Report Lower Bari Doab Canal Improvement Project
27
S # RD Name of AP Structure
Category
Structure
Affected
Structure
Type
Area
(Sq.
ft)
Unit
Rate
Estimated
Cost
Total Cost
of Affected
Structures
Livelihood
Allowance
Transport
Allowance
Vulnerable
Allowance Total Remarks
43 339 M.Idrees s/o
M.Yousaf Residential
Animal
Shed S.Pacca 154 200 30,800 30,800 9,620 2,000 9,620 52,040
Payments
Synchronized
with Civil Work
44 339 Abdul Sattar s/o
Niamat Ali Commercial
Table+
Chair Moveable 0 - - - 19,240 - 9,620 28,860
Cheques have
been prepared
but not issued
due to
construction
drawings
45 339 Rahat Hussain
s/o Talib Hussain Commercial Adda 0 - - - 19,240 - 9,620 28,860
Cheques have
been prepared
but not issued
due to
construction
drawings
46 340 Shahbaz Ali s/o
Zakir Hussain Commercial Patio Pacca 24 150 3,600 3,600 19,240 2,000 9,620 34,460
Payments
Synchronized
with Civil Work
47 340
Nazir
Muhammad s/o
Sardar
Muhammad
Commercial Adda 0 0 - - - 19,240 - 9,620 28,860
Cheques have
been prepared
but not issued
due to
construction
drawings
48 341 M.Arif s/o
M.Yousaf Commercial Moveable Boat 0 5,000 5,000 5,000 19,240 - 9,620 33,860
Cheques have
been prepared
but not issued
due to
construction
drawings
49 344 M.Ashraf s/o
M.Hassan Commercial Moveable Boat 0 5,000 5,000 5,000 19,240 - 9,620 33,860
Payments
Synchronized
with Civil Work
50 348 M.Sabir s/o
M.Hassan Commercial Moveable Boat 0 5,000 5,000 5,000 19,240 - 9,620 33,860
Payments
Synchronized
with Civil Work
51 361
M.Younas s/o
Haji Shahbaz
Ahmad
Commercial Moveable Boat 0 5,000 5,000 5,000 19,240 - - 24,240
Payments
Synchronized
with Civil Work
52 385 Faiz Muhammad Commercial Moveable Boat 0 5,000 5,000 5,000 19,240 - 9,620 33,860 Cheques have
Internal Monitoring Report Lower Bari Doab Canal Improvement Project
28
S # RD Name of AP Structure
Category
Structure
Affected
Structure
Type
Area
(Sq.
ft)
Unit
Rate
Estimated
Cost
Total Cost
of Affected
Structures
Livelihood
Allowance
Transport
Allowance
Vulnerable
Allowance Total Remarks
s/o Sardar
Muhammad
been prepared
but not issued
due to
construction
drawings
53 423 Chiragh Ali s/o
Mast Ali Commercial
Shed Kacha 22 150 3,300 8,300 19,240 2,000 - 29,540
Payments
Synchronized
with Civil Work
Moveable Boat 0 5,000 5,000
Payments
Synchronized
with Civil Work
54 440 M. Akram s/o
Zardar Commercial Moveable Boat 0 5,000 5,000 5,000 19,240 - 9,620 33,860
Payments
Synchronized
with Civil Work
55 474 Mureed Hussain
s/o M.Hassan Commercial Moveable Boat 0 5,000 5,000 5,000 19,240 - 9,620 33,860
Payments
Synchronized
with Civil Work
56 477 Rana M. Tariq
s/o Sardar Khan Dera
Room S.Pacca 676 500 338,000
497,600 - 2,000 - Nil Not Affected
Animal
Shed S.Pacca 280 200 56,000
Animal
Shed S.Pacca 518 200 103,600
57 477
Anees-ur-
Rehman s/o
Abdul Qadeer
Dera
Room S.Pacca 574 500 287,000
387,750 - 2,000 - Nil
Not Affected
Animal
Shed S. Pacca 338 200 67,600
Water
Course Pacca 105 150 15,750
Manger Pacca 96 150 14,400
Manger Pacca 20 150 3,000
58 483 Ghulam Farid s/o
Ghulam Hassan Commercial Moveable Boat 0 - 5,000 5,000 115,440 120,440
Payments
Synchronized
with Civil Work
59 501 Ghulam Farid s/o
M.Hussain Commercial Moveable Boat 0 - 5,000 5,000 115,440 9,620 130,060
Payments
Synchronized
with Civil Work
Internal Monitoring Report Lower Bari Doab Canal Improvement Project
29
6 SUB-PROJECT ICB-03 MAIN CANAL
22. The payment made to APs that includes livelihood, transport and vulnerable allowances for compensating sub-project impact
affected structures is detailed below:
TABLE 6.1 STATUS OF COMPENSATION TO APs FOR IMPACTED STRUCTURES
S # RD Cana
l side Name of AP
Structure
Category
Structure
Affected
Structure
Type
Area
(Sq.ft)
Unit
Rate
Estimate
d Cost
Total
Cost of
Affected
Structures
Self
Relocation
Allowance
Livelihood
Allowance
Transport
Allowance
Vulnerab
le
Allowanc
e
Total Remarks
1 527 RS
M. Afzal
Khan s/o M.
Khan
Commercial
Latrine S. Pacca 13 100 1,300
61,150 - 15,600 2,000 - 78,750 Paid Shed Kacha 322 150 48,300
Patio Pacca 77 150 11,550
2 527 RS M. Shaban
s/o M.Sultan Commercial Adda Moveable 0 - - - - 15,600 - 7,800 23,400 Paid
3 527 RS Abdul Jabbar
s/o Farzand Commercial Shop S.Pacca 160 500 80,000 80,000 - 6,000 2,000 7,800 95,800
Not
Affected
4 527 RS
M. Naseeb
s/o Ameer
Muhammad
Commercial Tenant N/A 0 - - - - 15,600 2,000 7,800 25,400 Not
Affected
5 527 RS
M. Mumtaz
s/o Peer
Bukhash
Commercial Kiosk Moveable 0 - 5,000 5,000 - 15,600 - 7,800 28,400 Not
Affected
6 527 RS M. Habib s/o
Said Ullah Commercial
Shed Kacha 240 150 36,000
45,000 - 15,600 2,000 - 62,600 Paid Patio S.Pacca 40 100 4,000
Kiosk Moveable 0 - 5,000
7 527 LS +
RS
Manak Ali
s/o Mohabat
Ali
Res+Com
Shop Kacha 192 300
57,600
182,140 23,400 109,200 2,000
-
316,740
Not
Affected
Shed Kacha 105 150
15,750
Room Kacha 270 300
81,000
Shed Kacha 154 150
23,100
B.Wall Kacha 67 70
4,690
Internal Monitoring Report Lower Bari Doab Canal Improvement Project
30
S # RD Cana
l side Name of AP
Structure
Category
Structure
Affected
Structure
Type
Area
(Sq.ft)
Unit
Rate
Estimate
d Cost
Total
Cost of
Affected
Structures
Self
Relocation
Allowance
Livelihood
Allowance
Transport
Allowance
Vulnerab
le
Allowanc
e
Total Remarks
8 528 RS Nawab s/o
Rajab Ali Residential
Room Kacha 180 300 54,000
235,000 23,400 15,600 2,000
-
276,000
Not
Affected
Room Kacha 300 300 90,000
Room Kacha 225 300 67,500
B.Wall Kacha 90 70 6,300
Manger S.Pacca 112 100 11,200
H. Pump Moveable 0 6,000 6,000
9 528 RS
Allah Ditta
s/o Imam
Deen
Residential
Room Kacha 225 300 67,500
139,620 23,400 15,600 2,000
-
180,620
Not
Affected Room Kacha 225 300 67,500
B.Wall Kacha 66 70 4,620
10 571 RS
Shakil
Ahmad s/o
Naseer
Ahmad
Commercial Table+
Chair Moveable 0 - - - - 15,600 -
7,800
23,400
CNIC not
available
11 632 RS M. Nawaz s/o
Chiragh Din Commercial Boat Moveable 0 - - 5,000 - 15,600 -
-
20,600
Cheques
have been
prepared
but not
issued due
to
constructio
n drawings
Internal Monitoring Report Lower Bari Doab Canal Improvement Project
31
7 BB/ICB-01 (COMPONENT-1)
23. The payment made to APs that includes livelihood, transport and vulnerable allowances for compensating sub-project impact
on affected structures is detailed below:
TABLE 7.1 STATUS OF COMPENSATION TO APs FOR IMPACTED STRUCTURES
S
# Name of AP
Structure
Category
Structure
Affected
Structure
Type
Area
(Sq.ft)
Unit
Rate
Estimated
Cost
Total Cost of
Affected
Structures
Livelihood
Allowance
Transport
Allowance
Additional
Assistance for
Vulnerable
Total Remarks
1 Ameer Khan Residential
Shed S.Pacca 100 200 20,000
98,300 8,671 2,000 8,671 117,642 Paid
Latrin Pacca 60 150 9,000
B.Wall S.Pacca 48 100 4,800
Cattle Shed S.Pacca 240 200 48,000
Fish Store Pacca 90 100 9,000
Hen Cage Pacca 15 100 1,500
H. Pump Moveable 6,000 6,000
2 Hasan Khan Residential Room S.Pacca 240 500 120,000 120,000 8,671 2,000 130,671 Paid
3 Yousaf Khan Residential 8,671 2,000 8,671 19,342 Paid
4 Yasin Khan Residential 8,671 2,000 8,671 19,342 Paid
5 Allah Ditta Residential
Room Pacca 221 700 154,700
594,500 8,671 2,000 8,671 613,842 Paid
Room S.Pacca 240 500 120,000 Room S.Pacca 156 500 78,000 Shed S.Pacca 120 200 24,000
Shed S.Pacca 312 200 62,400
Kitchen S.Pacca 99 500 49,500
Bath Room S.Pacca 36 500 18,000
B.Wall S.Pacca 30 100 3,000
Fish Store Pacca 24 100 2,400 Brick Flor S.Pacca 1050 70 73,500
H. Pump Moveable 6,000
Donky
Pump Moveable 3,000
6 Muhammad
Ashraf Residential
Cattle Shed Thatched 375 100 37,500 122,000 8,671 2,000 132,671 Paid
Room S.Pacca 169 500 84,500
7 Muhammad
Aslam Residential
Room S.Pacca 169 500 84,500 212,000 8,671 2,000 8,671 231,342 Paid
Room S.Pacca 195 500 97,500
Internal Monitoring Report Lower Bari Doab Canal Improvement Project
32
S
# Name of AP
Structure
Category
Structure
Affected
Structure
Type
Area
(Sq.ft)
Unit
Rate
Estimated
Cost
Total Cost of
Affected
Structures
Livelihood
Allowance
Transport
Allowance
Additional
Assistance for
Vulnerable
Total Remarks
Kitchen S.Pacca 24 500 12,000 Bath Room S.Pacca 36 500 18,000
8 Shakir Shah
Saleemi Residential
Shed Pacca 156 300 46,800
236,200 8,671 2,000 246,871 Paid
Bath Room S.Pacca 66 500 33,000
B.Wall S.Pacca 130 100 13,000
Cattle Shed S.Pacca 168 200 33,600
Brick Floor S.Pacca 1440 70 100,800
H. P Moveable 6,000
Donky
Pump Moveable 3,000
9 Muhammad Asif Residential
Hen Cage Pacca 12 100 1,200
37,340 8,671 2,000 8,671 56,682 Paid
Latrin Pacca 30 150 4,500
Bath Room S.Pacca 16 500 8,000
Brick Floor S.Pacca 252 70 17,640
H. P Moveable 6,000
10 Muhammad
Safdar Residential
Latrin Pacca 24 150 3,600
40,200 8,671
2,000 8,671
59,542 Paid
B.Wall Pacca 36 150 5,400
Cattle Shed S.Pacca 54 200 10,800
Brick Floor Pacca 144 100 14,400
Hand Pump Moveable 6,000
11 Pervaiz Akhtar Residential
Shed S.Pacca 169 200 33,800
76,800 8,671 2,000 8,671 96,142 Paid
Bath Room S.Pacca 44 500 22,000
B.Wall Pacca 28 150 4,200
Cattle Shed Thatched 126 100 12,600
Donky
Pump Moveable 3,000
Washing
Place Pacca 12 100 1,200
12 Muhammad
Sarfraz Residential
Shed Pacca 28 300 8,400 11,200 8,671 2,000 21,871 Paid
B.Wall S.Pacca 28 100 2,800
Internal Monitoring Report Lower Bari Doab Canal Improvement Project
33
8 INVENTORY OF STRUCTURES OF ICB-04
SrNo RD Location Canal
Side Name of AP
Structure
Category
Structure
Affected
Structure
Type
Area Unit
Rate
Estimated
Cost
Total Cost
of Affected
Structures
Transport
Allowance Total
W L Area
(sq.ft)
Chuchak Disty
1 26
Faazal
Wala RS
Abdullaha
s/o Nawab Residential Shed Kacha 12 24 288 150 43,200 43,200 2,000 45,200
Sub Total 288 43,200 43,200 2,000 45,200
Gugera Disty
2
20
3 48/GD
RS Babar Hussain
s/o M. Arshad Commercial Shop Kacha 10 20 200 310 62,000 62,000 2,000 64,000
3 RS Javed Iqbal s/o
M. Yousaf Comme Shop Kacha 10 20 200 310 62,000 62,000 2,000 64,000
4 RS M. Aslam s/o
M Arshad
Khan
Comm Shop Kacha 12 15 180 310 55,800
61,800 2,000 63,800
H. P Moveable 0 0 0 - 6,000
5 22
5 50/GD
RS M. Hanif s/o
Ahmad Saeed Residental
B Room Kacha 5 4 20 310 6,200
12,200 2,000 14,200
H. P Moveable 0 0 0 - 6,000
6 RS M. Sharif s/o
Ahmad Saeed Comm
Brick
Floor S.Pacca 27 10 270 80
21,600
21,600 -
21,600
Sub Total 870 219,600 219,600 8,000 227,600
Bhawani Minor
7 21 Shadi RS
Anwar s/o
Waryam Residential Room Kacha 12 14 168 310
52,080 50,400 2,000 54,080
8 26 Kaura
Shah RS
Jaffar s/o
Ahmad Ali Residential Shed Kacha 12 12 144 150 21,600 21,600 2,000 23,600
9
54 Kher
Shah
RS
Manzoor
Ahmad s/o
Noor Mohd
Comm Shop S.Pacca 13 27 351 525 184,275 184,275 2,000 186,275
10 RS
Nazar
Ahmad s/o
Ahmad
Residential Room S.Pacca 13 14 182 525 95,550 95,550 2,000 97,550
Sub Total 845 353,505 353,505 8,000 361,505
Total 12 2003 616,305 616,305 18,000 634,305
Internal Monitoring Report Lower Bari Doab Canal Improvement Project
34
9 DETAILS OF LAND TO BE OCCUPIED ON TEMPORARY BASIS - ICB-04
Sr.
No.
ID
No. RD Location
Cana
l Side Name of AP
Monthly
Income
(Rs.)
Total
Land
(Acre)
Affected Land Lease
Rate/
Marla
per year
Estimated
Lease for 1
Years
Total Cost of
3 years Kanal Marla
Total
Marlas
Equal to
Acre
Gogera Branch
1 32 32+500 Mehlo Ke,
Renala RS
Mazhar Iqbal
s/o M.Mustafa 37,900 16 15 14 314 1.9 312.5 98,125 294,375
2 33 32+500 Guba
Faazal RS
Jahangir s/o
M.Rafique 6,000 2 6 8 128 0.81 312.5 40,000 120,000
3 34 32+500 Guba
Faazal RS
Abdur Razaq
s/o M.Siddique 7,000 5 1 7 27 0.17 312.5 8,437 25,312
4 37 60+250 Karm Ka
Kot, Okara LS
Ahmad Ali s/o
M.Khan 25,000 20 5 0 100 0.63 312.5 31,250 93,750
5 38 60+250 Ahmad
Khan, RS
M. Mushtaq
s/o Arif Ali 20,000 20 9 0 180 1.12 312.5 56,250 168,750
6 44 81+150 Uthwal
Jagir RS
Faheem Sajjad s/o
Nazar Mohd 34,000 25 16 12 332 2.08 312.5 103,750 311,250
7 45 88+250 Joya,
Okara RS
Ali Yaseen s/o
Rana M.Shahbaz 79,000 27 3 0 60 0.38 312.5 18,750 56,250
8 46 88+250 Joya,
Okara RS
Shahamad Ali
s/o Ali
Muhammad
11,000 3.5 11 0 220 1.25 312.5 68,750 206,250
Gogera Disty
9 48 102+000 27/GD,
Okara RS
Noor Ahmad
s/o Fazal
Muhammad
16,000 12 2 0 40 0.25 312.5 12,500 37,500
10 49 102+001 27/GD,
Okara RS
Bashir Ahmad s/o
Waryam 10,500 3.38 13 4 264 1.65 312.5 82,500 247,500
11 50 117+500 Jaboka,
Okara RS
Sardar M.Yaqoob
s/o Ghulam
Rasool 72,000 22 14 10 290 1.8 312.5 90,625 271,875
12 51 185+500 Akber,
Okara RS
Sakhi M.Hamid
s/o M.Ismail Khan 183,000 3 13 0 260 1.63 312.5 81,250 243,750
13 52 199+450 48/GD,
Okara RS
Allah Rakha s/o
Ghulam Hussain 24,800 2 5 0 100 0.63 312.5 31,250 93,750
14 53 199+451 48/GD,
Okara RS
Najabat Ali
s/o Pir 7,500 2 5 0 100 0.63 312.5 31,250 93,750
Total 618,500 179.88 118 55 120.75 15.09 0 754,688 2,264,063
Internal Monitoring Report Lower Bari Doab Canal Improvement Project
35
10.1 INVENTORY OF STRUCTURES OF ICB-05
ID
No
Sr.
No RD Location
Canal
Side
Affected
Person Occupation
Structure
Category
Structure
Affected
Structure
Type
Area Unit
Rate
Estimat
ed Cost
Total Cost of
Affected
Structures
Transport
Allowance Total
W L Area
(sq.ft)
4-R Jhilwala Distributary
1 1 32+000 Adda
64/4R LS
Khalil
Ahmad s/o
Bashir
Ahmad
Shopkeeper Commercial
Khokha Wooden 5,000
9,840 2,000 11,840 Patio S.Pacca 4 8 32 110 3,520
Bench S.Pacca 2 6 12 110 1,320
2 2 43+000 68/4R RS Mamora s/o
Wahab Farming Residential
Kitchen Kacha 9 11 99 110 10,890
23,290 2,000 25,290 B.wall Kacha
15
5 155 80 12,400
Sub Total 298 33130 33130 4000 37,130
3R/5L Minor
3 1 4+904 58/5L RS
Shahbaz
Ahmad s/o
Shamas Din
Farming Residential B.Wall Kacha 0 0 80 80 6,400 6,400 2,000 8,400
Sub Total 80 6,400 6,400 2,000 8,400
Bahab Distributary
4 30 Tulla
Bulla RS
M.Arif s/o
Allah Ditta Farming Residential
Room Kacha 15 18 270 310 83,700 87,700 2,000 89,700
B.Wall Kacha 50 80 4,000
Sub Total 320 87,700 87,700 2,000 89,700
2L/Bahab Minor
5 1 2+600 Dera
Zarein RS
Ameeran
Bibi w/o
Sultan
(Late)
Farming Residential
Shed Kacha 15 13 195 150 29,250
35,170 2,000 37,170 B.Wall Kacha 0 0 74 80 5,920
Sub Total 269 35,170 35,170 2,000 37,170
1-L/3L/9L Sub Minor
6 1 1+300 139/9L RS
Asmat Bibi
w/o Hafiz
M.Din
(Late)
Labor Residential
Shed Kacha 8 8 64 150 9,600
11,600 2,000 13,600 B.Wall Kacha 25 25 80 2,000
Sub Total 89 11,600 11,600 2,000 13,600
Internal Monitoring Report Lower Bari Doab Canal Improvement Project
36
5-L/9L Minor
7 1 9+200 161/9L RS
M.Haroon
s/o
M.Rafique
Tea Stall Commercial Shed Kacha 13 13 169 150 25,350 25,350 2,000 27,350
8 2 9+200 Adda
162/9L RS
Ghulam
Shabbir s/o
Bashir
Ahmad
Tea Stall Commercial Shed Kacha 14 16 224 150 33,600 33,600 2,000 35,600
Sub Total 393 58,950 58,950 4,000 62,950
10-L Harrapa Distributary
9 1 10+000 LS
Malik Tariq
Aziz s/o
Abdul Aziz
Govt. Job Dera Wall S.Pacca 0 20 20 110 2,200 2,200 2,000 4,200
Sub Total 20 2,200 2,200 2,000 4,200
Grand Total 1,469 235,150 235,150 18,000 253,150
Internal Monitoring Report Lower Bari Doab Canal Improvement Project
37
10.2 DETAILS OF LAND TO BE OCCUPIED ON TEMPORARY BASIS - ICB-05
Sr.
No. RD Location
Canal
Side Name of AP Category
Total
Area
(Kanas)
Affected Area Lease
Rate/
Kanal
per
year
Estimated
Lease for
1 Years
Estimated
Lease for
three
Years
Compensation
of Trees Estimated
Cost of
Trees
Total
Cost Kanal Marla
Equal
to
Kanal
Equal
to Acre
Affected
Area %
Type
of
Tree
Total
1 2+050 54/4-R RS
Mumtaz
Hussain s/o
Ahmad
Khan
Temp.
Land
Acq.
8 2 3 2.15 0.27 26.88 6,250 13,438 40,313 - - - 40,313
2 2+050 54/4-R RS
Allah Yar
s/o Manzoor
Ali
Temp.
Land
Acq.
8 2 12 2.60 0.33 32.50 6,250 16,250 48,750 - - - 48,750
3 2+050 54/4-R RS Manik Khan
s/o Waryam
Temp.
Land
Acq.
12 0 7 0.35 0.04 2.92 6,250 2,188 6,563 - - - 6,563
4 8+200 55/4-R LS Ilam Din s/o
Noor Mohd
Temp.
Land 44 4 11 4.55 0.57 10.34 6,250 28,438 85,313 - - - 85,313
9-L Ganjibar
5 34+136 136/9L RS M.Afzal s/o
Khushi ad
Temp.
Land
Acq.
64 7 0 7 0.88 10.94 6,250 43,750 131,250 - - - 131,250
6 34+136 136/9L RS
Zulifaqar Ali
s/o Sardar
Mohd
Temp.
Land
Acq.
12 6 0 6 0.75 50.00 6,250 37,500 112,500 - - - 112,500
7 34+136 136/9L RS
Majeedan
Bibi w/o
M.Aslam
Temp.
Land
Acq.
14 3 0 3 0.38 21.43 6,250 18,750 56,250 - - - 56,250
8 81+400 142/9-L LS
M. Akram
etc s/o M.
Ibrahim
Temp.
Land
Acq.
21 6 0 6 0.75 28.57 6,250 37,500 112,500 - - - 112,500
9 93+000 144/9-L LS
Hameedan
Bibi w/o
Zahoor
Ahmad
Temp.
Land
Acq.
18 5 0 5 0.63 27.78 6,250 31,250 93,750 - - - 93,750
10 113+084 146/9-L LS
Azmat Ali
s/o Fateh
Mohd
Temp.
Land
Acq.
24 1 10 1.5 0.19 6.25 6,250 9,375 28,125 - - - 28,125
11 113+084 146/9-L LS
M. Anwar
s/o M.
Shafi
Temp.
Land
Acq.
22 3 0 3 0.38 13.64 6,250 18,750 56,250 - - - 56,250
Internal Monitoring Report Lower Bari Doab Canal Improvement Project
38
12 113+084 146/9-L LS
M. Ramzan
s/o M.
Jhanda
Temp.
Land
Acq.
8 0 10 0.5 0.06 6.25 6,250 3,125 9,375 - - - 9,375
13 117+515 175/9-L RS
Muhammad
Waseem s/o
M. Ameen
Temp.
Land 84 4 10 4.50 0.56 5.36 6,250 28,125 84,375 - - - 84,375
14 117+515 175/9-L RS
Bashir
Ahmad s/o
M. Abdullah
Temp.
Land 40 0 10 0.50 0.06 1.25 6,250 3,125 9,375 - - - 9,375
15 127+420 161/9-L LS
Mohd Yasin
s/o Ghulam
Dastgir
Temp.
Land 56 2 10 2.50 0.31 4.46 6,250 15,625 46,875 - - - 46,875
16 127+420 161/9-L LS
Amanat Ali
etc s/o Mohd
Din
Temp.
Land 108 0 10 0.50 0.06 0.46 6,250 3,125 9,375 - - - 9,375
17 137+825 162-9L LS
Tariq
Mehmood
s/o Mohd
Shafi
Temp.
Land 30 2 10 2.50 0.31 8.33 6,250 15,625 46,875 - - - 46,875
18 142+570 162/9-L LS
Javaid
Mumtaz s/o
Mumtaz
Akhtar
Temp.
Land 64 2 10 2.50 0.31 3.91 6,250 15,625 46,875 - - - 46,875
1L/9L Pandatwala Disty
19 11+974 93/9L RS
M. Yousaf
s/o Ahmad
(Punnu s/o
Samanda)
Temp.
Land 12 9 0 9.00 1.13 75.00 6,250 56,250 168,750 - - - 199,557
20 11+974 93/9L RS
Pir Mohd
s/o Sardar
Ameer Ali
Temp.
Land 296 4 8 4.40 0.55 1.49 6,250 27,500 82,500 - - - 82,500
21 16+457 99/9L RS Bashir/Hoot Temp.
Land 72 6 0 6.00 0.75 8.33 6,250 37,500 112,500 - - - 112,500
22 16+457 99/9L RS
Abdul
Rasheed s/o
Mohd
Munshi
Temp.
Land 4.4 4 0 4.00 0.50 90.91 6,250 25,000 75,000 - - - 75,000
11-L Dad Fatiana Distributary
23 15+200 9/11-L RS
Muzaffar
Hussain s/o
Jalal Din
Temp.
Land 84 4 0 4.00 0.50 4.76 6,250 25,000 75,000 - - - 75,000
24 15+200 9/11-L RS Ghulam Temp. 24 4 0 4.00 0.50 16.67 6,250 25,000 75,000 - - - 75,000
Internal Monitoring Report Lower Bari Doab Canal Improvement Project
39
Qadir s/o
Sharafat Ali
Land
25 24+500 9/11-L RS
Manzoor
Qadir s/o
Mehmood
Ali
Temp.
Land 24 1 0 1.00 0.13 4.17 6,250 6,250 18,750 - - - 18,750
26 24+500 9/11-L RS
Ghulam Ali
s/o Nazir
Ahmad
Temp.
Land 24 3 10 3.50 0.44 14.58 6,250 21,875 65,625 - - - 65,625
27 33-300 8/11-L LS
Des Mohd
s/o Ahmad
Din
Temp.
Land 20 0 10 0.50 0.06 2.50 6,250 3,125 9,375 - - - 9,375
28 33+300 8/11-L LS
Naseem
Vincent
Masih s/o
Rehmat
Temp.
Land 8.8 3 10 3.50 0.44 39.77 6,250 21,875 65,625 - - - 65,625
29 36+590 8/11-L LS
Malik Lal
Khan s/o
Rang Ali
Temp.
Land 100 3 0 3.00 0.38 3.00 6,250 18,750 56,250 - - - 56,250
30 36+590 8/11-L LS
Naseem
Hassan s/o
Khuda Bux
Temp.
Land 36 1 0 1.00 0.13 2.78 6,250 6,250 18,750 - - - 18,750
31 42+500 12/11-L LS
Ejaz Ahmad
s/o Wali
Mohammad
Temp.
Land 56 2 0 2.00 0.25 3.57 6,250 12,500 37,500 - - - 37,500
32 42+500 12/11-L LS
Allah Ditta
s/o Fazal
Ahmad
Temp.
Land 32 1 0 1.00 0.13 3.13 6,250 6,250 18,750 - - - 18,750
33 47+250 13/11-L LS M.Khurshid
s/o M.Din
Temp.
Land 80 4 2 4.10 0.51 5.13 6,250 25,625 76,875 - - - 76,875
34 52+725 13/11-L LS
M.Asif s/o
Ghulam
Dastgir
Temp.
Land 28 1 0 1.00 0.13 3.57 6,250 6,250 18,750 - - - 18,750
35 59+200 18/11-L LS
Manzoorn
Begum w/o
Faiz Meeran
Temp.
Land 200 5 4 5.20 0.65 2.60 6,250 32,500 97,500 - - - 97,500
12-L Chichawatni Disty
36 25+200 38/12-L RS
Muhammad
Riaz s/o
Khusi Mohd
Temp.
Land 72 4 0 4.00 0.50 5.56 6,250 25,000 75,000 - - - 75,000
37 50+350 42/12-L RS M. Ikram
Cheema
Temp.
Land 208 12 0 12.00 1.50 5.77 6,250 75,000 225,000 - - - 225,000
Internal Monitoring Report Lower Bari Doab Canal Improvement Project
40
38 54+700 44/12-L LS
Muhammad
Afzal s/o
Abdullah
Temp.
Land 100 1 0 1.00 0.13 1.00 6,250 6,250 18,750 - - - 18,750
39 98+200 Deh
Kameean LS
Anayat Babu
s/o Ali
Ahmad
Temp.
Land 100 1 10 1.50 0.19 1.50 6,250 9,375 28,125 - - - 28,125
40 98+200 Deh
Kameean LS
M. Yousaf
s/o Raj
Mohd
Temp.
Land 56 1 10 1.50 0.19 2.68 6,250 9,375 28,125 - - - 28,125
41 98+200 Deh
Kameean LS
Baqir Ali s/o
Noor Mohd
Temp.
Land 16.8 3 0 3.00 0.38 17.86 6,250 18,750 56,250 - - - 56,250
1R/12L Minor
42 30+970 110/12-L RS
M. Maqsood
Khan s/o M.
Iqbal Khan
Temp.
Land 12.5 8 0 8.00 1.00 64.00 6,250 50,000 150,000 - - - 150,000
43 38+385 111/12-L RS
Rana Javaid
s/o Rana
Riaz
Temp.
Land 16 5 0 5.00 0.63 31.25 6,250 31,250 93,750 - - - 93,750
44 38+385 111/12-L RS
Faqeer
Mohd s/o
Delawar
Temp.
Land 36 3 0 3.00 0.38 8.33 6,250 18,750 56,250 - - - 56,250
45 72+000 101/12-L RS Mohd Afzal
s/o Manzoor
Temp.
Land 4.6 2 0 2.00 0.25 43.48 6,250 12,500 37,500
Non-
Fruit
Trees
71 84,490 121,990
46 72+000 101/12-L RS Jan Mohd
s/o Dilbar
Temp.
Land 18.5 5 7 5.35 0.67 28.92 6,250 33,438 100,313 - - - 100,313
47 72+000 101/12-L RS
Bashir
Ahmad s/o
Bootay
Khan
Temp.
Land 3.4 2 0 2.00 0.25 58.82 6,250 12,500 37,500 - - - 37,500
48 72+000 101/12-L RS
Bashrian
Bibi d/o
Bootay
Temp.
Land 2 2 0 2.00 0.25 100.00 6,250 12,500 37,500 - - - 37,500
49 76+411 101/12-L RS
Ghulam
Mustafa s/o
M. Nawaz
Temp.
Land 208 6 9 6.45 0.81 3.10 6,250 40,313 120,938 - - - 120,938
50 76+411 101/12-L RS M.Akram
s/o M. Sher
Temp.
Land 203 9 7 9.35 1.17 4.61 6,250 58,438 175,313 - - - 175,313
14-L Kassowal Disty
51 9+500 3/14-L RS
Din Mohd
s/o Sher
Mohd
Temp.
Land 72 16 0 16.00 2.00 22.22 6,250 100,000 300,000 - - - 300,000
Internal Monitoring Report Lower Bari Doab Canal Improvement Project
41
52 27+650 9/14-L RS Ali Mohd
s/o Kamoon
Temp.
Land 56 16 8 16.40 2.05 29.29 6,250 102,500 307,500 - - - 307,500
53 27+950 9/14-L RS
Mohd Irshad
s/o Rehmat
Ali
Temp.
Land 15 3 2 3.10 0.39 20.67 6,250 19,375 58,125 - - - 58,125
54 39+900 14/14-L RS
Noor Mohd
s/o Fazil
Khokhar
Temp.
Land 136 16 0 16.00 2.00 11.76 6,250 100,000 300,000 - - - 300,000
Wahab Disty
55 4+865 100 WM RS
Bashir
Ahmad s/o
Allah Ditta
Jutt
Temp.
Land 78 2 0 2.00 0.25 2.56 6,250 12,500 37,500 - - - 37,500
56 4+865 100WM RS
Mohd Afzal
etc s/o
Ghulam
Sarwar Jutt
Temp.
Land 78 1 0 1.00 0.13 1.28 6,250 6,250 18,750 - - - 18,750
Total 222 210 232.5 29.0625 0 1,453,125 4,359,375 - 71 84490 4,359,375
Internal Monitoring Report
Lower Bari Doab Canal Improvement Project
42
11 COMMUNITY STRUCTURES
24. The community structures carry significance importance for the public. The LARU is,
therefore, trying its level best to diligently avoid project impacts to these structures. In
this regard LARU is working closely with DCSC, PIU and relevant Contractor. However,
till date no community structures has not been removed or damaged.
25. If any of the community structures will come under the project impact, then the
replacements for these community structures will be built at same or nearby locations
already identified by the local community. The structures will be constructed through the
management committees consisting of community representatives. Such committees have
already been formed at various locations. The notification of a management committee is
placed at Annex-6 and consent for relocation of Madrissa by respective Management
Committee is Annex- 07.
12 IMPACT ASSESSMENT OF STRUCTURE APs
26. The Corridor of Impact (CoI) was assumed as the area to be affected based on the
engineering/technical requirements of design at the design stage of the canal. In an effort
to reduce resettlement impacts on APs to the possible extent and reduce financial burden
on exchequer, a real time impact assessment study was conducted before mobilization of
the contractor at particular sites in light of contractor’s work plan. The copies of Impact
Assessments are placed at Annex-1 to 5.
27. These assessments were conducted by Resettlement Expert, Design Consultants, Resident
Engineer Supervision Consultants, Contractor’s Representative, Deputy Director Project
Implementation Unit, Deputy Director Community Relations PMU and Deputy Director
Social Safeguard PMU. Presence of Resident Engineer Supervision Consultant, Deputy
Director Project Implementation Unit and Contractor in the team ensured that APs to be
impacted are identified accurately. Findings of this assessment have already been shared
with ADB in External Monitoring Report.
Internal Monitoring Report
Lower Bari Doab Canal Improvement Project
43
13 GRIEVANCE REDRESSAL
28. In order to provide assistance to APs for redressal of their grievances, number of
Grievance Redress Committees (GRC) have been notified and are operational on all
ongoing sub-projects. The Deputy Director (Community Relations) PMU is the focal
person and responsible for co-ordination between members of the committee and
complainant, maintain record of meeting convened and decisions arrived in all such
meetings. Deputy Director Social Safeguard, Deputy Director Concerned Project
Implementation Unit are the members of GRCs. The Affected Persons (APs) representing
all the relevant canal reaches of a sub-project area are also members of GRCs.
Notifications of GRC are Annex-08 to 12.
29. The meetings of the GRCs are being held on monthly basis and minutes are being
recorded regularly. Due to smooth implementation of the project, no major issues have
been brought to agenda of the GRC by the APs. The discussions generally involve minor
issues. Minutes of meeting and Attendance sheets are Annexed 13 to 19.
Internal Monitoring Report
Lower Bari Doab Canal Improvement Project
44
Annexure 1: Impact Assessment of Remaining APs of Jandaraka Disty. (NCB-01)
Internal Monitoring Report
Lower Bari Doab Canal Improvement Project
45
Annexure 2: Impact Assessment of Remaining APs of 15-L Disty. (NCB-02)
Internal Monitoring Report
Lower Bari Doab Canal Improvement Project
46
Annexure 3: Impact Assessment of Structure APs of ICB-01
I.D Name of AP RD Location Updated status 01 Muhammad Aslam 58 Tibba Pian
Da The structure of the AP was previously falling inside the designated COI. However, the final cross section of that particular reach confirms that the structure will not be affected during execution of the civil works. Structure of AP is intact and present at site therefore the AP does not qualify for the compensation.
02 Abdul Ghafoor 62 Halla Bridge The structure of the AP was previously falling inside the designated COI. However, the final cross section of that particular reach confirms that the structure will not be affected during execution of the civil works. Structure of AP is intact and present at site therefore the AP does not qualify for the compensation.
03 Naeem Hussain Shah 72 Lakho Dher The structure of the AP was previously falling inside the designated COI. The Rd due to typographical mistake has been mentioned as 78, which is corrected as 72. However the final cross section of that particular reach confirms that the structure will not be affected during execution of the civil works. Structure of AP is intact and present at site therefore the AP does not qualify for the compensation.
04 Muhammad Nawaz 104 K Plot The AP was squatter and has moved from the area to an unknown location. Efforts were made to locate him but could not find.
05 M. Hanif 162 Renala
The APs falling from Sr. No. 05 to 26 in this reach, previously identified by DCSC in the designated COI for SRP of ICB 01, do not qualify for compensation as now according to the final design and tender documents (Annex-9), this particular reach that start from RD 160+000 to 164+000 do not fall in the engineering scope of work of LBDCIP. It, therefore, confirms that no civil work activity is required under ICB 01 by LBDCIP.
06 Faiz Muhammad 162 Renala
07 Muhammad Ali 162 Renala
08 M. Ashfiq 162 Renala
09 M. Safdar 162 Renala
10 Noor Ahmad 162 Renala
11 Wajid Ali 162 Renala
12 Naveed Akhtar 162 Renala
13 M. Rafique 162 Renala
14 Zulifqar Ali 162 Renala
15 M. Asif 162 Renala
16 Umar Farooq 162 Renala
17 Dil Muhammad 162 Renala
18 M. Shaiq 162 Renala
19 M. Naeem 162 Renala
20 Hanif Masih 162 Renala
21 M. Ilyas 162 Renala
22 M. Adnan 162 Renala
23 Diryafat Ali 162 Renala
24 M. Siddique 162 Renala
25 Liaquat Ali 162 Renala
26 Abdul Sattar 162 Renala
27 M. Afzal 178 23-1R Paid
28 Ali Sher Shah 188 24-2R Paid
Internal Monitoring Report Lower Bari Doab Canal Improvement Project
47
Annexure 4: Impact Assessment of Structure APs of ICB-02
Internal Monitoring Report Lower Bari Doab Canal Improvement Project
50
Annexure 5: Impact Assessment of Structure APs of ICB-03
Internal Monitoring Report
Lower Bari Doab Canal Improvement Project
51
Annexure 6: Notification of Management Committee for Relocation and Reconstruction of
Community Structures
Internal Monitoring Report
Lower Bari Doab Canal Improvement Project
52
Annexure 7: Consent for relocation of Madrissahs by respective Management
Committees
Internal Monitoring Report
Lower Bari Doab Canal Improvement Project
58
Annexure- 13 Letter to DD, PIU Okara regarding Hosting of Meeting of GRC
Internal Monitoring Report
Lower Bari Doab Canal Improvement Project
59
Annexure- 14a Proceeding of Grievance Redressal Committee of ICB-01
Internal Monitoring Report
Lower Bari Doab Canal Improvement Project
60
Annexure- 14b Attendance Sheet of Proceeding of Grievance Redressal Committee ICB-01
Internal Monitoring Report
Lower Bari Doab Canal Improvement Project
61
Annexure- 15a Proceeding of Grievance Redressal Committee of ICB-02
Internal Monitoring Report
Lower Bari Doab Canal Improvement Project
62
Annexure- 15b Attendance Sheet of Proceeding of Grievance Redressal Committee ICB-02
Internal Monitoring Report
Lower Bari Doab Canal Improvement Project
63
Annexure- 16a Proceeding of Grievance Redressal Committee of ICB-03
Internal Monitoring Report
Lower Bari Doab Canal Improvement Project
64
Annexure- 16b Attendance Sheet of Proceeding of Grievance Redressal Committee ICB-03
Internal Monitoring Report
Lower Bari Doab Canal Improvement Project
65
Annexure- 17 Attendance Sheet of Proceeding of Grievance Redressal Committee ICB-04
Internal Monitoring Report
Lower Bari Doab Canal Improvement Project
66
Annexure- 18 Attendance Sheet of Proceeding of Community Consultation & Grievance
Redressal Committee ICB-05
Internal Monitoring Report
Lower Bari Doab Canal Improvement Project
67
Annexure- 19 Attendance Sheet of Proceeding of Community Consultation ICB-06 at
Village 91/10R