international boundary and water commission united states section engineering services division...

26
International Boundary and Water Commission United States Section Engineering Services Division November 18, 2014 Levee Rehabilitation Projects Lower Rio Grande Valley

Upload: violet-hodges

Post on 17-Dec-2015

214 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: International Boundary and Water Commission United States Section Engineering Services Division November 18, 2014 Levee Rehabilitation Projects Lower Rio

International Boundary and Water CommissionUnited States SectionEngineering Services Division

November 18, 2014

Levee Rehabilitation ProjectsLower Rio Grande Valley

Page 2: International Boundary and Water Commission United States Section Engineering Services Division November 18, 2014 Levee Rehabilitation Projects Lower Rio

International Boundary and Water CommissionEngineering Services Division

Submitted LRGV FEMA Review Packages

1. Common Levee 2. Mission Levee Phase I 3. Mission Levee Phase II 4. DHS Levee/Wall Segment O-04A 5. DHS Levee/Wall Segment O-04C 6. DHS Levee/Wall Segment O-05 7. DHS Levee/Wall Segment O-06A 8. DHS Levee/Wall Segment O-06B & C 9. DHS Levee/Wall Segment O-07

Page 3: International Boundary and Water Commission United States Section Engineering Services Division November 18, 2014 Levee Rehabilitation Projects Lower Rio

International Boundary and Water CommissionEngineering Services Division

Submitted LRGV FEMA Review Packages

10. DHS Levee/Wall Segment O-08 11. DHS Levee/Wall Segment O-09 Phase I 12. DHS Levee/Wall Segment O-09 Phase II13. DHS Levee/Wall Segment O-1014. North Banker Floodway Levee15. Mission Levee Improvements at Bentsen Palm Drive,

UID, Penitas RR Crossing16. Main Floodway 17. North Floodway – Two Structures 172 &41318. North Floodway Phase I

Page 4: International Boundary and Water Commission United States Section Engineering Services Division November 18, 2014 Levee Rehabilitation Projects Lower Rio

International Boundary and Water CommissionEngineering Services Division

Submitted LRGV FEMA Review Packages

19. North Floodway Phase II20. Arroyo Colorado Phase I21. Arroyo Colorado Phase II22. Lower Brownsville Levee – (Donna to Brownsville Reach # 5)

Page 5: International Boundary and Water Commission United States Section Engineering Services Division November 18, 2014 Levee Rehabilitation Projects Lower Rio

International Boundary and Water CommissionEngineering Services Division

• Accredited Levee System - A FEMA accredited levee system is a levee system that meets the requirements of 44CFR65.10 and therefore is shown on the Flood Insurance Rate Map (FIRM) as providing protection from the 1-percent-annual-chance flood.

• FEMA does not own, operate, maintain, or inspect levee systems or develop certified levee-related data for accreditation purposes.

FEMA Accreditation

Page 6: International Boundary and Water Commission United States Section Engineering Services Division November 18, 2014 Levee Rehabilitation Projects Lower Rio

International Boundary and Water CommissionEngineering Services Division

• As the levee owner, USIBWC will evaluate that the levees have been constructed to required design standards and are operated appropriately.

• For FEMA to accredit a levee system with 1%-annual-chance flood hazard reduction capability on a FIRM, the levee owner/local project sponsor must submit a package containing the required data and documentation to show that the levee system meets all design and operation requirements of 44CFR 65.10.

FEMA Accreditation

Page 7: International Boundary and Water Commission United States Section Engineering Services Division November 18, 2014 Levee Rehabilitation Projects Lower Rio

International Boundary and Water CommissionEngineering Services Division

• Interior Drainage - FEMA requires an Interior Drainage Analysis. To date, no analysis exists. USIBWC is only authorized to do work on the levees within USIBWC ROW and does not have authority in assessing the interior drainage issues.

• Levees need to tie into high ground• Levee/Roadway intersections • Intake / Drainage Channels

Accreditation “Speed Bumps”

Page 8: International Boundary and Water Commission United States Section Engineering Services Division November 18, 2014 Levee Rehabilitation Projects Lower Rio

International Boundary and Water CommissionEngineering Services Division

LRGV Construction Projects Under Administrative Close Out

1. Lateral A to Retamal Dike2. Hidalgo Phase I and II3.Upper Brownsville Levee - (Donna to

Brownsville Reach #4)

Page 9: International Boundary and Water Commission United States Section Engineering Services Division November 18, 2014 Levee Rehabilitation Projects Lower Rio

International Boundary and Water CommissionEngineering Services Division

FEMA Packages Submitted - Map

Page 10: International Boundary and Water Commission United States Section Engineering Services Division November 18, 2014 Levee Rehabilitation Projects Lower Rio

International Boundary and Water CommissionEngineering Services Division

LRGV FLOOD CONTROL PROJECTS

Page 11: International Boundary and Water Commission United States Section Engineering Services Division November 18, 2014 Levee Rehabilitation Projects Lower Rio

International Boundary and Water CommissionEngineering Services Division

• Upper Brownsville Levee Improvements- (Donna to Brownsville Reach # 4)

• Los Indios to San Pedro Levee Improvements– (Donna to Brownsville Reach #3)

• Santa Maria to Los Indios Levee Improvements- (Donna to Brownsville Reach #2)

• Progreso Levee Improvements (Donna to Brownsville Reach #1)

LRGV CONSTRUCTION PROJECTS

Page 12: International Boundary and Water Commission United States Section Engineering Services Division November 18, 2014 Levee Rehabilitation Projects Lower Rio

International Boundary and Water CommissionEngineering Services Division

UPPER BROWNSVILLE LEVEE

• 12.0 levee miles (from San Pedro to International Blvd in Brownsville)• $8.8 million contract to LECON Inc.• Notice to Proceed issued June 1, 2013• Completion Date of October 2, 2014• 100% Complete, Project is in Administrative Close Out

Page 13: International Boundary and Water Commission United States Section Engineering Services Division November 18, 2014 Levee Rehabilitation Projects Lower Rio

International Boundary and Water CommissionEngineering Services Division

UPPER BROWNSVILLE LEVEE

Page 14: International Boundary and Water Commission United States Section Engineering Services Division November 18, 2014 Levee Rehabilitation Projects Lower Rio

International Boundary and Water CommissionEngineering Services Division

LOS INDIOS TO SAN PEDRO LEVEE

• 11.9 levee miles• $11.5 million contract to LECON Inc.• Notice to Proceed issued December 26, 2013• Anticipated completion August 28, 2015• 52% Complete

Page 15: International Boundary and Water Commission United States Section Engineering Services Division November 18, 2014 Levee Rehabilitation Projects Lower Rio

International Boundary and Water CommissionEngineering Services Division

LOS INDIOS TO SAN PEDRO LEVEE

Page 16: International Boundary and Water Commission United States Section Engineering Services Division November 18, 2014 Levee Rehabilitation Projects Lower Rio

International Boundary and Water CommissionEngineering Services Division

SANTA MARIA TO LOS INDIOS LEVEE

• 11.7 levee miles total• $9.6 million contract to EISG Inc.• Notice to Proceed issued September 25, 2014.• Anticipated completion January 23, 2016 • 0% Complete

Page 17: International Boundary and Water Commission United States Section Engineering Services Division November 18, 2014 Levee Rehabilitation Projects Lower Rio

International Boundary and Water CommissionEngineering Services Division

SANTA MARIA TO LOS INDIOS LEVEE

Page 18: International Boundary and Water Commission United States Section Engineering Services Division November 18, 2014 Levee Rehabilitation Projects Lower Rio

International Boundary and Water CommissionEngineering Services Division

PROGRESO LEVEE

• 6.0 levee miles total (west segment is 2.0 miles; east segment is 4.0 miles)• $3.7 million contract to EISG Inc.• Notice to Proceed issued July 9, 2014• Anticipated completion August 13, 2015• 1% Complete

Page 19: International Boundary and Water Commission United States Section Engineering Services Division November 18, 2014 Levee Rehabilitation Projects Lower Rio

International Boundary and Water CommissionEngineering Services Division

PROGRESO LEVEE

Page 20: International Boundary and Water Commission United States Section Engineering Services Division November 18, 2014 Levee Rehabilitation Projects Lower Rio

International Boundary and Water CommissionEngineering Services Division

• Arroyo Colorado Levee, Phase 3• North Floodway North & South Levees

(Phase 3)• North Floodway North & South Levees

(Phase 4)• Edinburg Pump Levee Rehabilitation

LRGV DESIGN PROJECTS

Page 21: International Boundary and Water Commission United States Section Engineering Services Division November 18, 2014 Levee Rehabilitation Projects Lower Rio

International Boundary and Water CommissionEngineering Services Division

Arroyo Colorado Phase 3 – Brown Line

ARROYO COLORADO PHASE 3 DESIGN

• Design : 16.1 miles of levee

• $1.9 million design contract awarded to Tetra Tech Inc.

• Notice to Proceed issued on March 11, 2010

• Design completed Sept. 2013

• Construction will be done in 3 sub phases: 3A to 3C

Page 22: International Boundary and Water Commission United States Section Engineering Services Division November 18, 2014 Levee Rehabilitation Projects Lower Rio

International Boundary and Water CommissionEngineering Services Division

North Floodway Phase 3 – Light Blue Line

NORTH FLOODWAY PHASE 3 DESIGN

• Design : 23.5 miles of levee

• $5.6 million design contract URS Group, Inc. (NF Phases 3 and 4)

• Notice to Proceed issued on June 16, 2010

• Design completed Oct. 2013

• Construction will be done in 4 sub phases: Phases 3A to 3D

Page 23: International Boundary and Water Commission United States Section Engineering Services Division November 18, 2014 Levee Rehabilitation Projects Lower Rio

International Boundary and Water CommissionEngineering Services Division

North Floodway Phase 4 – Medium Blue Line

NORTH FLOODWAY PHASE 4 DESIGN

• Design : 29.2 miles of levee

• $5.6 million design contract URS Group, Inc. (NF Phases 3 and 4)

• Notice to Proceed issued on June 16, 2010

• Design completed Nov. 2013

• Construction will be done in 5 sub phases: Phases 4A to 4E

Page 24: International Boundary and Water Commission United States Section Engineering Services Division November 18, 2014 Levee Rehabilitation Projects Lower Rio

International Boundary and Water CommissionEngineering Services Division

Edinburg Pump – Yellow Line

EDINBURG PUMP LEVEE REHABILITATION DESIGN

• Design : .7 miles of levee

• $400,000.00 design contract URS Group, Inc.

• Notice to Proceed issued on October 1, 2014

• Design completion anticipated by June 25, 2015

• Construction will be done in 1 phase

Page 25: International Boundary and Water Commission United States Section Engineering Services Division November 18, 2014 Levee Rehabilitation Projects Lower Rio

International Boundary and Water CommissionEngineering Services Division

ACCOMPLISHMENTS

• 262 miles of levee improvements completed

• 22 certification packages submitted to FEMA

• Visit www.ibwc.gov to learn more about the Levee Improvement Status

Page 26: International Boundary and Water Commission United States Section Engineering Services Division November 18, 2014 Levee Rehabilitation Projects Lower Rio

International Boundary and Water CommissionUnited States SectionEngineering Services Division

Construction Projects InquiriesIsela Canava

Lead Civil Engineer(915) 832-4748

Jose A. NuñezPrincipal Engineer

IBWC – US Section Head Quarters(915) 832-4749

FEMA Certification InquiriesValentin ArzolaCivil Engineer

(915) 832-4712