international journal of science and engineering research ... · and the wastage level in ......
TRANSCRIPT
International Journal of Science and Engineering Research (IJ0SER),
Vol 3 Issue 5 May -2015 3221 5687, (P) 3221 568X
Sasidharani,Jayanthi…. (IJ0SER) May - 2015
Material Waste Management In Construction Industries 1B.Sasidharani,
2 R. Jayanthi
1 ME (Construction engineering and Management), 2Asst.Professor,
RVS Technical Campus, Coimbatore Tamilnadu,India.
Abstract-The construction industry plays an important role in establishing the infrastructure required for socio-economic
development. It is one of the biggest environmental polluters and it also consumes large quantities of raw materials. And also it is
generate large amount of construction waste. Generation of construction waste constitute a major impact to the environment. The
awareness among contractors and builders regarding waste minimization is still low although various research have proved the
environment problems are getting more critical. This study is conducted to investigate the cause of waste, waste prevention method
and the wastage level in construction site. There are three concepts to manage the waste. They are reduce, reuse and recycle
(3R).Reduce is the most significant method for construction waste minimization. Targeting the potential areas for waste
generation in construction projects can help to significantly reduce the quantity of construction waste created. A structured
questionnaire survey was conducted to provide empirical evidence on levels of significant contribution of waste minimization
measures to waste reduction, and levels of practice of same measures using weighted average and coefficient of variation criteria.
The questionnaire is designed based on the attributes for material waste. Based on the study, suggestions for waste reduction in
construction sites are made. The study was conducted using a structured survey questionnaire. Waste attributes that lead to wastes
generation on building projects were identified and they include: Design and documentation attributes; Site management and
practices; Procurement attributes; Materials handling, storage and transportation; Operational attributes and Environmental and
other conditions. T-test statistical technique of comparing means was used in the analysis of data with SPSS version 12.0 software to
determine the major construction waste generation attributes. The study revealed that Changes made to the design while
construction is in progress; Improper material management over allowance Inappropriate and wrong storage facilities at site
leading to damage or deterioration; errors by tradesmen; and Severe weather conditions were the leading significant factors each in
their respective categories of waste generation. Adequate storage of material is one of the significant minimisation measures. A
simple construction waste management system that can provide data on waste quantities, identify areas that are problematic in
waste generation, and be able to analyse the causes of these wastes is recommended. The use of prefabrication of building elements
was thought to be very beneficial for resource efficiency/waste minimisation.
INTRODUCTION
The environmental implication of activities is now
well known. The construction sector is to be generating
unacceptable level of material waste generally construction
activities which lead to produce wastage can be grouped into
offsite and onsite operational activities. Off-site activities include mining and manufacturing of material and
components, transportation of material and components ,land
acquisition, storage place and project design. on-site
construction activities relate to construction are planning,
design and physical facility.
Both off-site and on-site activities generate pollution
under the categories of ecology, landscape, traffic, water, energy, limber consumption, noise, dust, sewage and health
and safety hazards. On the other hand, it also generates
severe impacts on the environment. Problems related to
environmental performance concern environmental problems
associated with construction activities. The construction
industry is associated with high energy consumption,
resource depletion, and a large amount of waste generation
.The industry is one of the biggest environmental polluters .
The construction industry also consumes large quantities of
raw materials. In order to manage such a huge quantity of
construction waste,Various studies in the construction
industry have developed best practices that are not only capable of improving organization‟s profit but also assist in
producing systematic work processes which encourage the
optimal use of resources.There are two types of construction
waste:
Inert construction waste
Non-inert construction waste
Inert construction waste is around 20% of the total
and usually comprises bamboo, timber, vegetation, packaging
waste and other organic materials. Some of these can be
recycled while others are disposed of at landfills. In contrast,
90% are inert waste - otherwise known as public fill - mainly
includes construction debris, rubble, earth, bitumen and
concrete, which can be used for land formation. Materials like concrete and asphalt can also be recovered for
construction use. Waste accounts for approximately 25% -
30% of all waste generated and consists of numerous
materials, including concrete, bricks, gypsum, wood, glass,
metals, plastic, solvents, asbestos and excavated soil, many of
which can be recycled. According to the Environment
protection department (EPD, 2000) in Hong Kong , 20% of
waste material was disposed of to landfills while the
remaining 80% was disposed to public filling area in Hong
Kong. Waste occurs on site for a number of reasons, most of
which can be prevented, particularly by changing the
attitudes of the construction workforce. Therefore, the attitude and perception of the construction workforce can
influence the generation and implementation of waste
management strategies.
In Construction waste management three concept
are important. They are recycle, reuse and reduce. Materials
can be recycled directly into the same product for reuse.
Others can be reconstituted into other usable products.
Unfortunately, recycling that requires reprocessing is not
usually economically feasible. Hence minimization of waste
is the significant method.
International Journal of Science and Engineering Research (IJ0SER),
Vol 3 Issue 5 May -2015 3221 5687, (P) 3221 568X
Sasidharani,Jayanthi…. (IJ0SER) May - 2015
The initial step in a construction waste reduction
strategy is good planning. Design should be based on
standard sizes and material should be ordered accurately.
Additionally, using high quality materials such as engineered products reduce rejects. This approach can reduce the amount
of material needing to be recycled and bolster profitability
and economy for the builder and costumer.
OBJECTIVES OF WASTE MANAGEMENT
The aim of this research verified the casuses of
construction, proposing appropriate waste prevention method
to the contractors to implementin the construction project.The
main objective of material waste management is to reduce the
material waste in on-site and off-site.
i. To identify the causes of material waste in construction.
ii. To suggest the waste prevention methods in
construction.
iii. Identifying importance of waste
recognition, barriers to implement waste
management and existing waste re-
ductiontechniques/strategies followed in
construction industry.
iv. To create an economical project by
minimizing the materials.
SCOPE OF THE PROJECT Scope of the study is todetermined the facilitate of
literature review, by focusing on certain field in literature
review and data collection process. This study covers:
i. Data of wastage level is collected base on
percentage;
ii. Wastage occurs on site;
iii. Focus on inert material waste in construction
such as – concrete, cement, sand, timber, steel,
plastic, glass, bricks, tiles and bamboo.
NEED FOR STUDY
The importance of the study is arising awareness of
contractors , engineers and site workers regarding to the waste management, which the effectiveness of
implementation of waste management into construction
project lead to construction cost and bad effects towards
environment.
The reduction of construction waste not only yield significant
benefit‟s to the environment, but also reducing cost of
construction.
It is absolutely imperative for the construction industry adopt
ecologically sound planning and construction practice for the
purpose of creating a healthy and sustainable built
environment.
GENERAL
Construction waste is defined as:
Any substance or object that you discard, intend and discard, or are required to discard is waste and as such is subject to a
number of regulatory requirements. Even if material is sent
for recycling and undergoes treatment in-house it can still be
waste. The term is discard has a special meaning, whether or
not a particular material is waste is for person producing it to
decide in accordance with the law.
Classification of Construction Waste
The waste in construction can be generated due to
many cause and situations.the following classification
consider all these factor to group the construction waste
forms of occurrence of it.
Waste according to the type of resource consumed
According to the consumed resource, the waste can
be classified in physical and financial waste as shown in
Figure 2.1 (Andrade, 1999). This classification considers the
following examples:
Physical waste of materials: additional
amount of material relative to the one
specified in the project;
Physical waste of man-hour: men hours
increased due to the delay in the arrival of
materials and overproduction;
Physical waste of equipment: equipment
hours increased in function of the problem
cited for the man power;
Financial waste in result of the physical
waste: determine the costs associated with
the physical waste;
Financial waste in result of material
purchase: relative additional cost to the use of a material with superior value of the
specified one.
Figure-Waste according to the type of resource consumed(source: Andrade 1999)
Waste according to its nature
According to Golkulnath and Janani(2013), there are
two types of waste i) direct waste related to, the Waste that
can be prevented and involves the actual loss or removal and
replacement of material”.Direct waste can be occurred at any
stage of the construction process before the delivery of
material to the site and after incorporating the materials at the
building ii) indirect waste related to the material does not get
International Journal of Science and Engineering Research (IJ0SER),
Vol 3 Issue 5 May -2015 3221 5687, (P) 3221 568X
Sasidharani,Jayanthi…. (IJ0SER) May - 2015
waste physically, but the payments for the material are
wasted partly or wholly. The indirect waste are characterized
by materials that are used in excess in the building, for
example:
TABLE - Indirect Waste
Category Reason Example
Substitution
waste
Substitution of materials
in work, which will incur
losses to either contractor
or client
Use of facing bricks
for com- mon bricks
Production waste Contractor does not
receive any payments for
the work he has carried
out
Use of excess
plastering to rectify the
un- even surfaces of
brick walls
Negligence waste Site errors because of the
condemned work or use
of additional material
Over excavation of
foundation, resulting
in the use of additional
concrete
Operational
waste
Unavailability of proper
quantities in the contract
document / the material
that are left in the site
Formwork
The direct waste corresponds to material damaged during the
execution or rest of materials. They have some forms of
occurrence according to the andrade (1999)
Table -Direct waste
Category Reason example
Delivery waste waste During the transportation
of material to the site,
unloading, and placing in to the
initial storage
Bricks,
glasses
Cutting and convention-
al waste
Cutting materials in to various
sizes and uneconomical shapes
Formwork,
tiles
Fixing waste Dropped, spoiled or discarded
material during fixing
Bricks,
roof tiles
. Application and
residue waste
Damages occurs by succeeding
trades
Painted
surfaces
Criminal waste Theft and vandalism Tiles,
Cement
bags
Management waste Lack of supervision or
incorrect decisions of the
management
Throwing
away
excess
material
Waste according to its control
Considering the possibility of controlling or
reducing the index of waste detected, the waste is classified
in two categories (Paliari, 1999): (i) avoidable or (ii)
unavoidable. The unavoidable waste is the one that the
necessary investment for its reduction is superior to the
economy obtained. Generally, this waste category represents an acceptable level of waste that its factors escape to the
control of the builder, depending on the development of each
company. On the other hand, is the one that its reduction is
economically viable because the cost of waste is significantly
higher than the cost to prevent it. According to Santos et al.
(1996) the avoidable waste is consequence of a process of
low quality, in which resources are used inadequately. Figure 2.2 shows the actual situation in which there is a significant
amount of avoidable waste and non value-adding activities
and the desired situation in which there is only unavoidable
waste and value-adding activities.
Waste according to its origin
Although waste is typically identified throughout the
production phase, also it can be originated by processes that
go before production such as: materials manufacturing,
design, materials supply, and planning. Examples of waste
that can occur in the different stages of the construction are:
Use of a smaller space between the studs in relation to
the considered correct standards or the extreme breaking of blocks during the execution, for example, can have
origin in the lack of modulation (conception phase);
Lack of necessary material in the moment of execution
(planning);
Low quality components (acquisition);
Cement mortar production in superior amount that the
one that will be used in the day of work or the use of
inadequate techniques (execution phase);
Repainting the building after one year of use, to modify
the color of the facade,when, in durability terms, it could
be done every 3 years (maintenance phase).
The execution phase, the most exploited in this study, is
related to the course of the material as shown in Figure 2.3,
since its arrival to the jobsite until becoming part of an
executed product. Such course is, generically: (i) act of
receiving, (ii) stocking, (iii) transporting, (iv) intermediate
processing, and (v) application, on which losses can happen.
According to Santos et al. (1996), during the construction execution, the following examples can be pointed: real
weight of the bags lesser than the specified one (act of
receiving); rotten lumber due to humidity (stocking); bigger
cement consumption per CY of concrete (intermediate
processing); material that falls in the soil (transporting); and
over thickness (applying).
Figure -Waste according to its origin (source: Formoso et al.,
1996)
International Journal of Science and Engineering Research (IJ0SER),
Vol 3 Issue 5 May -2015 3221 5687, (P) 3221 568X
Sasidharani,Jayanthi…. (IJ0SER) May - 2015
Types of Material Waste
Construction waste is defined as waste which arises
from construction, renovation and demolition activities
including land excavation or formation, civil and building
construction, site clearance, demolition activities, roadwork,
and building renovation. However, some defined directly to
solid waste: the inert waste which comprises mainly sand,
bricks, blocks, steel, concrete debris, tiles, bamboo, plastics,
glass, wood, paper, vegetation and other organic materials.
This type of waste consists a complete loss of materials, due
to the fact that they are irreparably damaged or simply lost.
The wastage usually removed from the site to landfills.(SasitharanNagapan, Ismail Abdul Rahman and Ade
Asmi 2012)
Cause of Waste Materials
The objectives of this study were to identify the major attributes of construction wastes on building projects in
Uganda and to propose the possible measures of minimizing
their occurrences. Waste attributes that lead to wastes
generation on building projects were identified and they
include: Design and documentation attributes; Site
management and practices; Procurement attributes; Materials
handling, storage and transportation; Operational attributes
and Environmental and other conditions. Approximately 40%
of the waste generated globally originates from the
construction of buildings.
Design and documentation attributes : Changes
made to the design while construction is in progress mean
4.02 , Selection of low quality products 3.13, Errors in the
contract documents 3.04, Incomplete contract documents at
commencement of the project 3.04, Lack of information in
the drawing 3.02, Lack of attention paid to dimensional
coordination of products 2.98, Designer‟s inexperience in
method and sequence of construction 2.92, Complexity of
detailing in the drawings 2.90, Lack of attention paid to the standard sizes available on the market 2.54, Designer‟s
unfamiliarity with alternative products 2.51, Waiting for
design documents and drawings 2.46.
Site management and practices : Changing
orders/instructions by supervisors 3.70, Improper planning
3.56, Lack of waste management plan 3.43, Lack of
supervisions and delay in inspections 3.33, Lack of quality management system aimed at waste minimization 3.31, Poor
communication coordination between parties involved in the
project. 3.13, Slow decision making by the site management
3.10, Poor site layout 3.09, Ineffective control of the project‟s
progress by the constructor 2.83, Lack of technical
professionals in contractor‟s organization. 2.81.(L. Muhwezi ,
L. M. Chamuriho and N. M. Lema 2012)
Material Wastage Level in Construction :
Construction waste is generated throughout the construction
process such as during site clearance, material use, material
damage, material non-use, excess procurement and human
error. The exact quantity and composition of construction
waste generated throughout the projects are difficult to be
identified as they are keep on changing due to the dynamic
nature of the construction activities. Different stages of
construction generates different types and composition of
waste. Therefore the trend of waste generated throughout the construction stages need to be identified., this paper propose
a method to quantify waste for conventional construction.
The proposed method comprises four steps. First is
identification of construction stages and expected waste
generated. Second is selection of construction sites with
similar characteristics for uniform investigation. Third is
sorting and weighing of mixed waste collected in a dumpster.
The last step is summation of the recorded quantity.
Considering the wastage of materials, the theoretical quantity
should be increased by using following formula
Total quantity of material to be provisioned
= theoretical quantity of materials x (100+standard waste)/100
Wastage depends on nature of work , type of materials,
method of application.
Wastage be controllable and uncontrollable.
Table -Expected Waste Generated From Conventional
Construction
No Construction
stage
Expected major
construction waste
1 Site clearance Soil, rock
2 Sub-structure
works
Reinforced concrete, steel
bar, concrete, wood
3 Super-structure
works
Wood, steel bar, cement,
sand, aggregate, brick
4 Finishing works Cement, sand, aggregate,
tile, paint,lime
5 Infrastructure
works
Bitumen materials, timber,
concrete
Calculation of Waste Generated According to Each Stage of
Construction.
C = W/GFA
where: W = total waste generated from each construction
stages of the project (tonne) GFA = gross floor area C =
waste generation rate (i.e. construction of 1 m2 gross floor
area generates C tonne of waste)( Siti Akhtar Mahayuddin and Wan AkmalZahri Wan Zaharuddin 2013)
According to Patel MitulNarendrakumar Pandya Minarva,
The component of materials waste cost comprises nearly
40%-60%.The weight of construction waste are Soil, Sand,
and Gravel 4.20-5.14 million tones/years, Bricks and
masonry 3.6-4.4 million tonnes/year Concrete 2.4-3.67
million tonnes/year Metals 0.60-0.73 million tonnes/year Bitumen 0.25-0.30 million tonnes/year Wood 0.25-0.30
million tonnes/year Others 0.10-0.15 million tonnes/year.
Waste Prevention Methods
International Journal of Science and Engineering Research (IJ0SER),
Vol 3 Issue 5 May -2015 3221 5687, (P) 3221 568X
Sasidharani,Jayanthi…. (IJ0SER) May - 2015
Currently there are not any type of practices adopted
for managing construction waste in India. Only for
contractors and builders with the help of their experiences
and previous data, during operation of the project itself, are concerned about material waste but not from the early stage
of the project. The waste management in construction have
three concept(3R). Defined waste minimisation as a set of
three options prioritized according to the waste hierarchy.
The first priority is waste prevention; the second is waste re-
use while the third priority is waste recycle. Reducing the
waste generated at source is considered as the first option to
be implemented for better protection of the environment, and
for better economic savings.(Ayarkwa, J, K. Agyekum and E.
Adinyira, 2013)
SWMP help to manage the materials and provide an incentive
to waste prevention/minimisation. A SWMP sets out how
resources will be managed and waste controlled at all stages
during a construction project.
A SWMP covers:
Who will be responsible for resource management.
What types of waste will be generated.
How the waste will be managed – will it be reduced,
reused or recycled?
Which contractors will be used to ensure the waste is
correctly recycled or disposed of responsibly and
legally.
How the quantity of waste generated by the project
will be measured
The most frequent measures practiced to minimise
material waste are: staff training; adequate storage; and just-
in time delivery of materials. Waste measurement and waste
segregation are areas that need more efficient implementation
to achieve material waste minimisation targets. Moreover,
contractors‟ perceptions towards the benefits of material
waste minimisation revealed that this waste is primarily
considered a financial problem and its minimisation a cost
cutting activity.. A review of the literature suggests the following measures as the main solutions for efficient
prevention of material waste on construction sites
areLogistics management, Supply chain management (SCM),
Modern construction methods, Training and incentivising.
Fig :Waste Hierarchy
The main direct causes of material waste in the UAE
construction sites are: workers' lack of awareness; poor
design resulting in excessive off-cuts; and the rework and
variations. In contrast, the factors emanating from poor
logistics management and procurement problems were
considered as being of low significance. 2. The indirect causes of material waste were found to be the lack of legal
and contractual incentives. 3. The current practices
implemented by contractors to minimise material waste on
construction sites are: adequate storage, staff training and
awareness, and „just- in time‟ delivery. 4. Material waste
recycling is rarely practiced. In addition, waste measurement
and waste segregation are two practices that need to be
implemented more efficiently in UAE construction sites. (Al-Hajj, A., &Hamani, K. 2011).
Reuse and recycling are usually treated together in
the literature. Both of these two practices require a separation
of waste streams in order to be accomplished (CIRIA, 1995).
In fact, the good practice of waste minimisation involves
segregation of key waste streams namely: timber,
plasterboard, packaging, general waste, inert waste, metal and
hazardous by using clearly labelled skips or bins (Wrap,
2007b). Once the waste material is segregated, the
possibilities of reuse or recycling on-site must be investigated
before considering any off-site recovery or disposal (DEFRA, 2008).
The chronic problems of construction include low
productivity, low quality, poor co-ordination and high costs.
High product cost is also associated with poor quality,
inefficiency and high waste generation. A structured
questionnaire survey was conducted to provide empirical
evidence on levels of significant contribution of waste minimization measures to waste reduction, and levels of
practice of same measures using weighted average and
coefficient of variation criteria. Purchasing raw materials that
are just sufficient(mean 4.96), using materials before expiry
dates(mean 4.88), and using more efficient construction
equipment(mean 4.42) are perceived by construction
professionals as three of twenty-six measures which most
significantly contribute to waste minimization, and also the
three most practiced waste minimization measures in Ghana.
Encouraging re-use of waste materials, use of low
waste technology and recycling of waste materials on site are,
however, considered as the three least significant measures
contributing to waste minimization and also least practiced.
Among various suggested recommendations, the construction
industry is encouraged to sort and re-use waste materials, and
adopt environmentally friendly and low waste technologies
on site. (Ayarkwa, J, K. Agyekum and E. Adinyira2013).
Value Engineering originates from the
manufacturing industry in order to deliver higher value and
quality to a product by means of an increase in efficiency.
„Lean Construction‟ (LC) concepts emerged as a
consequence of the application of VE philosophy,
specifically for construction industry. LC extends from the
objectives of a lean production system – to maximize value
and to minimize waste – in relation to specific techniques and
then applies them conceptually in a new project delivery
process. The aims of this paper are to present practical
International Journal of Science and Engineering Research (IJ0SER),
Vol 3 Issue 5 May -2015 3221 5687, (P) 3221 568X
Sasidharani,Jayanthi…. (IJ0SER) May - 2015
examples of the application of Value Engineering and Lean
Construction concepts within a green building construction
project and to qualitatively assess its benefits in terms of
environmental impact and waste minimization.
Meanwhile, the adoption of prefabrication
construction methods, intelligent excavation works, „Reduce-
Reuse-Recycle‟ principles, and simple „environmentally-
aware‟ on-site practices can minimize the waste produced
and the local environmental impact emitted during project
execution.(Ferry Firmawan,Fadil Othman, KhairulzanYahya
2012)
The construction workers to implement the reusing,
recycling and reducing construction materials, reward scheme
is used for measuring the results in the implementation and
encouraging the practices of it. Furthermore, with the
proposing landfill-charging scheme for the construction
environment, contractors will push to reduce the waste
generated by training and education. This paper examines the
cost benefit for the organization, in which to encourage the
workers by Stepwise Incentive System (SIS) for measuring the cost saving on purchasing material and waste generation.
It proved that SIS can help reduce wastage generation up to
23.60%.(Dr. Vivian W. Y. Tam 2006)
According to Branz study report, “define at least
two critical influences that can lead to more resource efficient
construction (reduced generation of waste material) To find
these critical influences, a survey was carried out based on a survey conducted in a similar construction environment.
From the results, the following critical influences were
identified:
There is very little importance placed by architects
on waste minimisation. In association with this there
is a lack of operational material waste minimisation
plans and strategies.
Architects and quantity surveyors think that creating a buildable design that allows for a logical sequence
in construction and avoids variations on site
minimises the amount of waste material generated.
Architects believe that accurate and integrated
project information and making waste reduction
efforts financially beneficial to the client, help
mitigate waste production.
CADD is seen by architects as a waste generator
rather than a waste reducer, both in terms of
materials (paper generated) and time (for all but
repetitive design).
Contractors cite the use of standardised forms (both
in the room and material sizes), so that cutting sheet
materials to fit can be reduced, as the most
important factor in reducing waste.
The most two critical issues are CADD and
prefabrication. Computer-aided drafting and design was not
seen to be important to most architectural practices because of its limited application, due to its slowness as a tool and
restricted applicability. CADD has greater application to
larger practices/repetitive work. Costs were the number one
reason for firms not using CADD. The use of prefabrication
of building elements was thought to be very beneficial for
resource efficiency/waste minimisation, by all the telephone
interviewees.The last result – on the use of prefabrication.(Roman Jaques 1999).
The widespread of prefabrication and IBS is
expecting to be important means of reducing waste. Concrete
and aggregate, soil and sand and brick and blocks are the
largest components of waste materials and this finding is
consistent in several researches. However, the proportion
differs among the components. A huge difference is found
between total waste generated in conventional project and IBS or prefabricated project and this finding is proven
consistent in several studies. As an effort to reduce material
waste, the largest components of waste appear to have
highest frequency of reusing and recycling .(KhorJie Cheng,
MdAzreeOthumanMydin 2014)
METHODOLOGY
Waste minimisation means reducing the amount and
environmental impact of waste generated, which can be
achieved by reducing the quantity of materials used (and
therefore potential for wastage) or by reusing existing
materials. Prevention of the waste means the effective use of
natural resources; energy needed to manufacture new
materials as well as reducing pollution.
This study are going to be conducted following
planned arrange that provides direction to search out the
solution of the study queries. A study methodology is
planned by stage in step with their priorities perform and
performance and function so as to assure the effectiveness of
the work. The 5 stages embrace preliminary stage, reviewing
literature, assembling knowledge, analysing knowledge and
drawing conclusion.
Following are totally different phases that are used
for the analysis study over this topic:
Identify the problems due to waste generation in
construction industries.
Establish the objectives and scope of the project.
Studying the causes of waste which contributes for
generation of those construction waste and waste
minimisation methods by literature survey.
Preparation of questionnaire survey
Formulating questionnaires and validating, data
collection by questionnaire survey.
Personal interviews are conduct with site engineers and
managers.
A detailed intensive studying of waste minimisation by
case study.
Analysing the collected data.
Discussion and interpretation of result.
Conclusion, recommendation and suggestions.
International Journal of Science and Engineering Research (IJ0SER),
Vol 3 Issue 5 May -2015 3221 5687, (P) 3221 568X
Sasidharani,Jayanthi…. (IJ0SER) May - 2015
METHOD OF SURVEYING
The empirical study involves a structured questionnaire,
administered via convenience sampling technique to
construction professional in selected building firms. Also
personal interviews will be conduct with construction
professionals. Identify the cause and minimisation measures
of material waste in construction industries by literature
survey.
This study has taken definition of construction waste
and cause of waste in literature. Based on literature survey
the questionnaire is formed. This means that the targeted
organizations can supply the required information for the
study.
Questionnaire Design
A structured questionnaire includes questions on the
respondent‟sorganization‟s profiles andthe identified waste
variables which had common features were grouped together
under the following categories: a) Design and documentation;
b) Site management and practices c)Procurement; d)
Materials handling; storage and transportation; e) Operational attributes;- measured on a 5-point Likert scale where 1
represents Strongly Agree, 2 is Agree, 3 is Neutral, 4 is
Disagree and 5 is Strongly Disagree; minimization measures
adopted by the firms via open-ended questions; the
contributions of the control techniques to waste minimization
measured on a 4-point Likert scale; and the contribution of
materials waste minimization to projects‟ outcome measured
on a 5-point Likert scale. Mean, ranking and frequency were
used to analyse the data.
Design and documentation
In this categories, Waste can be as a result of inadequacies of
design, specifications, the lack of cognizance of stock or
standard manufactured sizes of materials/or products on
market and errors in documentation.The waste arises at the
construction site due to the changes made by the clients at the
end of completion of projects. The contractor begins the
construction works at site, while the construction work is in
progress, the sudden requirement of the client will complicate
the near completion work and end up with rework.Errors in
documents and incomplete documents were affect the
procurement of material.(SasitharanNagapan 2012).
Site management and practices
Improper material management is due to lack of planning
skills of the site staff. Without detailed planning of
construction process, requirement of material can lead to the generation of waste. Besides that, delay in inspection/lack of
supervision factors also significantly contribute to waste.
This is because majority of construction waste is generated at
uncontrolled sites. For example, these problems related to
Slow in making decisions and Lack of a quality management
system. 3.2.3Procurement Attributes
Procurement categories were reveal procure and purchase of
materials. The waste generated over allowance materials in
construction projects are excessive allowance of bricks and
concrete mixture that end up as waste.Unskilled workers tend
to make more mistakes due to lack of skills and poor working
attitude. Sometimes, poor ordering of material without specification details and low quality materials also cause
waste.
Material Handling Attributes
In this categories, material handling attributes like wrong material storage, theft, damage during transportation, delay in
deliveries and material in loose form (brick, sand, steel and
tile ). Material were storage in open place was affected their
properties and damaged. Damage during transportation leads
to procure more material than estimated level.
Operational Attributes
In Operational stage,design were executed in site. While
execution, materials were waste due to error of tradesmen,
accident, malfunctioning breakdown of equipment,Required
quantity unclear sue to improper planning,Delay in passing
information to contractors and inclement weather also affect
the materials in site. Errors of tradesmen were leads to
increase wastage level in site.Improper planning form
required quantity unclear.
Analysis of results
Collected data were analysed by statistical tools analyse
method using SPSS software(Statistical package for the
social sciences).The mean and standard deviation were
calculated to rank waste causes and also the major waste attributes were analysed using paired sample T-Test at a
95% of confidence interval.Test value 3 was used to
compare the means. Those with mean values of 3 and
below were considered as major waste attributes and those
waste attributes found to have mean scores less than 3 were
considered insignificant.
RESULT AND DISCUSSION
All questionnaire got response from project manager, site
supervisor and store keeping and purchase manager and also
case studied was done in different construction.Collected data
were analysed using statistical tools analysis method, SPSS
(Statistical package for the social sciences) is a statistical
analysis and data management software package. SPSS can
take data from almost any type of file and use them to
generate tabulated reports, charts, and plots of distribution and trends, descriptive statistics, and conduct complex
statistical analyses. This was done to identify causes which
contributes most to material waste in that group and plot
chart for respective results.
DESIGN AND DOCUMENTATION
In this questionnaire I have consider design and
documentation attributes, mean and rank were calculated.
Thatstatistic result is depicted in table 4.1
International Journal of Science and Engineering Research (IJ0SER),
Vol 3 Issue 5 May -2015 3221 5687, (P) 3221 568X
Sasidharani,Jayanthi…. (IJ0SER) May - 2015
Table-Descriptive Statistics of design and
documentation
Attri
butes
N Mean
Std.
Deviati
on
Rank
frequent design
changes 36 2.17 1.08 1
changes in specification
36 2.53 1.11 2
selection of low
quality product 36 3.11 1.3 3
complexity of
details 36 3.36 1.31 4
lack of information in
drawing
36 3.56 1.27 5
incomplete
contract
document
36 3.92 1.13 6
error in contract
document 36 4.06 0.89 7
Valid N
(listwise) 36
By this above result, frequent design changes are most
significant attributes on design and documentation categories.
Table -Frequency Table Of Frequent Design
Changes
Frequency Perc
ent
Valid
Percen
t
Cumulativ
e Percent
Vali
d
1 9 25.0 25.0 25.0
2 18 50.0 50.0 75.0
3 6 16.7 16.7 91.7
5 3 8.3 8.3 100.0
Tot
al 36
100.
0 100.0
Inference
The inference made from response of construction workers
and contractors 25% are strongly agree the causes of waste in
construction site are due to design changes, 50% of the
respondent says agree,16.7% of the respondent says neutral
and 8.3 % of the respondents says strongly disagree.
Fig. Bar Chart Of Design And Documentation
Based on the factors in Table 4.1 , from highest frequency to
lowest frequency for construction waste factors were
presented in Figure 4.1. The highest factor contributes to the
waste generation is frequent design changes with 75%
researchers admit as contributory factor. The waste was
generated at construction site due to the changes made by the
clients at end of the project. First design and documentation
was approved by both parties and construction material were
procured with estimate while construction is in progress the
sudden requirement of the clients will end up with rework.
This behaviour is leads to generate demolition waste and also waste that procured materials.
SITE MANAGEMENT ATTRIBUTES
In this part I have made the question in site management
aspects, descriptive statistic tabulated their mean is shown in
table 4.3.
Table -Descriptive StatisticsOfSite Management
Attributes
Site Management Attributes N Mean
Std.
Deviation Rank
Improper material management 36 2.31 1.431 1
Lack of supervision & delay of
inspection 36 2.53 1.298
2
Poor coordination &
communication 36 3.19 1.117
3
Slow in making decisions 36 3.50 1 4
Lack of a quality management
system 36 3.81 1.327
5
Valid N (list wise) 36
From descriptive statistic of site management attributes,
improper material management as the major contributors for
waste generation in site.
Table4.3 indicated the most significant attributes in site
management categories, it represented in fig 4.2. improper
material management in the first positionas the most
significant waste attributes on sites in their respective
categories. The waste is increased due to site engineers was
International Journal of Science and Engineering Research (IJ0SER),
Vol 3 Issue 5 May -2015 3221 5687, (P) 3221 568X
Sasidharani,Jayanthi…. (IJ0SER) May - 2015
not properly utilise that issued materials, materials are
damaged while transport from storage area to work area and
also it were not placed safely in working area. For examples,
cements, steel and sand wrongly stored at work place or stored at any open space(fig 4.3). These cause the materials
to be exposed to moisture and rain. Without detailed planning
of construction process, requirement material from storage
department can lead to the generation of physical waste.site
supervisors have to manage the materials.
PROCUREMENT ATTRIBUTES
In this format I would include questions arriving from
procurement attributes. Below table indicate mean and rank
by descriptive statistic method.
Table Descriptive StatisticsOf Procurement Attributes
Procurement
Attributes N Mean
Std.
Deviation Rank
Over allowance 36 2.97 1.028 1
Item is not comply
with specification 36 3.25 1.079 2
Ordering error 36 3.39 1.128 3
Mistakes in
quantity survey 36 3.44 1.252 4
Valid N (list wise) 36
It was found that over allowance as the main contributor for
waste generation.
Based on the factors in Table 4.5 , from highest frequency to
lowest frequency for construction waste factors were
presented in Figure 4.5. The highest factor contributes to the
waste generation is over allowance with 55% researchers
admit as contributory factor.Unskilled workers tend to make
more mistakes due to lack of skills and poor working attitude
due to this attitude lot of material were waste hence over
allowance of material for that work than estimated
percentage.Lack of work plan leads to over allowance.
Different loose form material get collapsed due to un clear work place is main cause for over allowance.
MATERIAL HANDLING ATTRIBUTES
Here I have prepared the question ofmaterial handling
attributes problems. That statistic result is depicted in table
Table -Descriptive Statistics OfMaterial Handling
Attributes
Material
Handling N Mean
Std.
Deviation
Rank
wrong material
storage 36 2.36 1.246 1
Damage during
transportation 36 2.39 1.050 2
Delay during
delivery 36 2.42 .967 3
Theft 36 2.42 1.204 4
Material
supplied in loose
form
36 3.19 1.167 5
By descriptive statistics result, wrong material storage is the
major attributes in material handling attributes.
In this category, wrong material storage and poor
materials handling become key factors for waste generation.
Storage must of necessity be related to the sequence of
operations to ensure a minimum of movement and handling.
In his study(L. Muhwezi 2012)Inappropriate storage can
result from say when materials are stacked without pallets such as bricks/blocks, bags of cement, gypsum, lime etc
Exposing materials to inclement weather such as
steel bars which rust and may get damaged unpacked supply
of materials like bricks, glass and tiles often increase wastage
during transportation due to their fragile nature. Excessive or
unnecessary inventories which lead to material waste by
robberyand vandalism. Damage during transportation is
another main significant attributes in this categories.
OPERATIONAL ATTRIBUTES
In this part the question asked were operational
attributes.That statistic result is depicted in table 4.9
Table Descriptive Statistics of Operational Attributes
Operational Attributes N Mean Std. Deviation Rank
Errors by tradesmen 36 2.19 .889 1
Damages to work done due to
subsequent traders 36 2.22 .898 2
Inclement weather 36 2.53 1.207 3
Required quantity unclear due to
improper planning 36 2.97 1.230 4
Malfunction breakdown of
equipment 36 3.03 .878 5
Delay in passing information to
contractors 36 3.11 1.326 6
Accidence due to negligence 36 3.25 1.251 7
Use of incorrect material thus
requiring replacement 36 4.28 .944 8
Valid N (listwise) 36
By this above result, error by trades man are most significant
attributes on operational attributes categories.
International Journal of Science and Engineering Research (IJ0SER),
Vol 3 Issue 5 May -2015 3221 5687, (P) 3221 568X
Sasidharani,Jayanthi…. (IJ0SER) May - 2015
MAIN WASTE CATEGORIES
The results are presented in Tables 4.11, where
lower values of sum of mean ranking the major category of
waste attribute.
Table Main waste categories
Main Waste Categories Mean Rank
Material Handling
Attributes 2.56 1
Site Management
Attributes 2.97 2
Operational Attributes 3.02 3
Procurement Attributes 3.26 4
Design and
documentation 3.29 5
Building construction have five stage respect to material
management. Each stage haveprocess of cycle. That process have to done correctly. From these stages material handling
attributes are major attributes to causes of waste in
construction.
In this stage materials are attained more damages
and workers done mistakes. Materials were damaged due to
transportation. Loose form of material are waste enormously.
Theft is one of the causes of material waste.
WASTE MINIMISATION MEASURES
TABLE Descriptive Statistics ofWaste Minimisation
Measures
waste minimisation
measures N Mean Std. Deviation Rank
Adequate storage of
materials 36 1.64 .639 1
Ordering only needed of
material 36 2.00 .862 2
Ordering material to size 36 2.11 .747 3
Take back arrangement
with suppliers 36 2.28 .914 4
Recycling off site 36 2.50 .845 5
Segregation of waste on
site 36 2.53 .878 6
Appointment of waste
manager on site 36 2.61 .964 7
Reuse on site of off cut
materials 36 2.72 1.111 8
Prefabrication of
components off site 36 2.81 1.142 9
Incentives to site
personnel 36 2.97 1.000 10
Recycling on site 36 3.03 1.082 11
Using mechanical
handling of materials 36 3.36 1.291 12
Valid N (listwise) 36
MATERIALWASTAGE RATE ON PERCENTAGE
Each and every construction material have some
wastage level as per ISO 456 code. Construction companies
were consider these percentage of wastage in their estimation.
I was conducted case study on three sites in Chennai.
From results on case study in three sites regarding
the wastage level of some important material of construction
industry are as shown in following table, the results shown below were ready statistics provided by the employees of
each site. These are approximate data from then experience.
Table Waste Rate On Percentage In Different Sites
Material Site 1 Site2 Site3
Cement 3 3 5
Concrete 1 2 2
Sand 10 12 25
Course
aggregate 5 3 10
Tile 5 10 7
Plastic 1 5 1
Metal 5 3 1
Timber 2 - 2
Brick 15 1.5 5
FIG Bar Chart Of Different Site Wastage Percentage
In construction site, inert material wasteincreases than active
materials.In my case study of three sites waste percentage
was different from one another site. Sand is the one of the
most significant waste in constructions.Because it‟s a loose
from material.Sand mostly waste in transportation stage and storage.
CASE STUDY ON MATERIAL WASTE MANAGEMNT AT
PROJECT SITE
A field was conducted on the following sites to
study wastage; the sites were(Chennai)
Residential building A
Residential building B
Residential building C
02468
10121416182022242628
site 1
site2
site3
International Journal of Science and Engineering Research (IJ0SER),
Vol 3 Issue 5 May -2015 3221 5687, (P) 3221 568X
Sasidharani,Jayanthi…. (IJ0SER) May - 2015
All the three sites were under construction stage and
involve huge work of concreting and civil work, which
required sufficient manpower, machinery and equipment.
The study carried out on these sites was done by keeping in mind that the main objectives is to collect wastage level
of material, causes and minimisation measures in sites.
Due to few constraint, only limited data were collected
and these data were used for analysing the cause, wastage
level and measures. The site name is not mentioned as
these data were provide only after a commitment of not
disclosing their name in the case.
GENERAL OBSERVATION
SITE A:
In this site, most of material were reuse, scrap steel were gone for recycling. But work place was unclear.
Waste material were dumped improperly. RMC is using in
this site. Hence concrete and cement waste were low. They
have department for each and every stages. wastage was
calculated at storage department and purchase department.
Purchase department was ensure the drawing and
estimation procurement. Due to this reason over ordering
was perevented.Bytheir analyse wastage was generated due
to site labour and lack of supervision. They weretried to
decreases wastage by give penalties to workers for
improper work and generate wastage of materials. It was decrease some amount of wastage and also increases labour
awareness in waste management.
SITE B:
Site B was using batching plant, with transit mixer
and concrete pump. This building is not a conventional. It is
A RBC structure That building was constructing on
concrete only. Basement andstilt only made by brick wall.
They were using aluminium formmethod. Aluminium form
was shuttering for wall as per drawing. concrete was
pouring from one edge, that concrete are flow all over wall
panel.self compacting concrete was using in that site. Due
to this method larger amount of wastage of inter waste were avoided. Instead of straight rod coil form are
used(8,10,12mm). Hence wastage of reinforcement was
minimised.It have more stability than conventional
building.
They are procure and purchase material by using online
marketing. over ordering are avoided by this method. If
material was damaged or low quality, it was return to
vendor( condition was noted).Non moving stocks were
transported to other work site, transport report was sent to purchase department. Here waste material were segregated
with their respective category. Hazards material was stored
at separate place. Bar bending was done at their central yard
as bar bending schedule.
SITE C :
It is a luxuries apartment .In this site consider project
specification and client satisfaction are very important. They
not concentrate on waste minimisation. Storage of material
was properly done at site, They was using two side opening
container for cement storage, it was reduced non moving
stock and wastage of cement bags. In site C wastage
produced mostly by transportation and theft.
CONCLUSION
From the study it is concluded that wastageof material in
construction industry are usually because of attitude design
and documentation,site management, procurement stage,
material handling and operational attributes.waste generation
is mostly attributed tofrequent design changes;changing
designs when works have already progressed and also the un
coordinated activities between main contractors and
subcontractors and even amongst different crews. There is
need for designers to remain in touch with clients in the
design stages to avoid issues of changing drawings when
work has already commenced as this results into wastes in redoing work or buying extra materials because of the design
changes introduced. The improper methods of handling
materials and poor storage facilities to protect them from
damage and deterioration; Improper material management
was increased waste due to site engineers was not properly
utilise that issued materials, materials are damaged while
transport from storage area to work area and also it were not
placed safely in working area. Over allowance ,Procurement
of products that do not comply with specifications in the
procurement category contribute significantly to waste
generation on sites. Procurement needs to be done by knowledgeable personnel about the project and has to be in
conformity with project specifications and in right quantities.
Constant interaction between site staff and purchasing
department should be encouraged. Changing attitude towards
labour about their work method. Wrong material storage is
main attributes in material handling category .wrong material
storage for waste generation are aggressive handling of bricks
and blocks during construction leads to cracks and spoil
.Loose form of materials( cement and sand) were stored at
open place. These cause the materials to be exposed to
moisture and rain. Materials should be stored as per supplier
instructions. Errors by tradesmen is causes of waste in operational category. The most of tradesmen fail to read the
instruction or drawing, the mistakes include wall frame
improperly cut or assembled.and lack quality in work. Site
investigations need to be properly designed and carried out
for collect the right, quality and quantity of information
before starting any projects.In Material handling stage waste
was generate more compare to other stages. Adequate storage
of material, ordering only needed material and use take back
arrangements are most significant methods to minimise waste
at site.
RECOMMENDATION AND SUGGESTIONS
Based on the findings study, a number of recommendation
can be made to reduce material waste on construction sites to
a minimum. The recommendation are stipulated in table
below, but the following are specifically noted:
They the materials deliveries should be properly planned and
also adequate care should be taken in storing materials.
Storage areas and site transport route should be properly
planned.A number of security precautions are also
International Journal of Science and Engineering Research (IJ0SER),
Vol 3 Issue 5 May -2015 3221 5687, (P) 3221 568X
Sasidharani,Jayanthi…. (IJ0SER) May - 2015
recommended for minimizing the risk of theft and pilferage
and the most important that care and proper handling in the
use of materials is essential. Proper control and regular
accounting of materials are also recommended.
The need for material control policies is thereby emphasized,
It is proposed that the firms should draw up working
procedures for waste to guide site personnel in the use of
materials on site.It is also stressed that both head office
personnel and site personnel should be educated waste
prevention.During material delivery,before unloading of
material from vehicle inspection of materialshould done.
Contractors and other stakeholders must be educated and
sensitized about the strategies and benefits of waste
minimization on construction projects and the cost saving
measures that can be followed in waste reduction which can
ultimately result in increased profit margins.
I would also recommend having a waste officer in the
organisation will dedicatedly work on waste preventions.
Finally, in view of the important of material waste to the
economy of the world the following recommendation are
made with respect to the different aspects.
Delivery of material on time
Waste control policy
Proper storage and internal transportation
Worker should be encouraged to handling material
with care during transportation on site.
Proper site supervision
Site accounting and reconciliation has to calculate in
every month.
Material reconciliation and stock accounting should be done regularly.
All people working on site should be educatedon
waste prevention.
REFERENCES
1. Al-Hajj, Assem; Hamani, Karima “Material Waste in the UAE
Construction Industry: Main Causes and Minimisation Practices “
journal of Architectural Engineering and Design Management
2011.
2. SasitharanNagapan, Ismail Abdul Rahman1, Ade Asmi , Aftab
Hameed Memon , Rosli Mohammad Zin “Identifying Causes of
Construction Waste “ International Journal of Integrated
Engineering, Vol. 4 No. 2 (2012)
3. Prof.B.Prakash Rao Shivakumar B H S Suresh “Waste
Minimisation in Construction Industry “ Research paper June
2014.
4. Job Thomas1, Wilson P. M.2 “Construction waste management
in India “American Journal of Engineering Research (AJER)
2013.
5. SasitharanNagapan, Ismail Abdul Rahman, Ade AsmiFactors“
Contributing to Physical and Non-Physical Waste Generation in
Construction Industry “ International Journal of Advances in
Applied Sciences (IJAAS) Vol.1, No.1, March 2012.
6. L. Muhwezi , L. M. Chamuriho and N. M. Lema “An
investigation into Materials Wastes on Building Construction
Projects in Kampala-Uganda “ Scholarly Journal of Engineering
Research Vol. 1(1), pp. 11-18, April 2012.
7. Gokulnath.VJanani.K “Material Waste Management in
Construction Sites” Resaearch paper Volume : 3,Issue : 11,Nov
2013.
8. Roman Jaques “Construction Site Waste Generation – The
Influence of Design and Procurement in Auckland “BRANZ
1999.
9. Ferry Firmawan, Fadil Othman, KhairulzanYahya ”Improving
Project Performance And Waste Reduction In Construction
Projects” International Journal of Technology (2012)
10. Ayarkwa, J, K. Agyekum and E. Adinyira “Exploring Waste
Minimization Measures in the Ghanaian Construction
Industry”2010.
11. Li Yinga, Zhen Yin, TingtingGuo, Jing Zhou “Study of the
Resource Utilization Management of Construction
Waste”Procedia Environmental Sciences 11 (2011)
12. KhorJie Cheng, MdAzreeOthumanMydin “Best Practice of
Construction Waste Management and Minimization” ANUL
XXI, NR.1,2014.
13. KosmopoulosPanos,Georgiadoui.Danai “Survey Regarding
Control and Reduction of Construction Waste “November 2012.
14. Siti Akhtar Mahayuddin and Wan AkmalZahri Wan Zaharuddin
“Quantification of Waste in Conventional Construction
“International Journal of Environmental Science an d
Development, Vol. 4, No. 3, June 2013.