interoperability unit study: traction … interoperability unit study: traction current settlement...
TRANSCRIPT
ERA INTEROPERABILITY UNIT STUDY: TRACTION CURRENT SETTLEMENT SYSTEM
PAGE 1 OF 42
INTEROPERABILITY UNIT
STUDY: TRACTION CURRENT SETTLEMENT SYSTEM
Reference: ERA/REP/07-2011/INT Document type: Final Report
Version: 1.0
Date: 14.04.2011
Prepared by Reviewed by Approved by
Name
Stanislaw LIS
Ignacio BALLESTER
Wouter MALFAIT
Airy MAGNIEN
Andrzej HARASSEK
Jean – Charles PICHANT
Position Project Officers Head of Economic Evaluation Unit
Head of Fixed Installations Sector
Head of Interoperability Unit
Date
&
Signat.
14/04/2011 14/04/2011 14/04/2011
ERA INTEROPERABILITY UNIT
PAGE 2 OF 42
CONTENTS
EXECUTIVE SUMMARY
1. STUDY ON TRACTION SETTLEMENT SYSTEM ................................................................... 6
1.1 Mandate of the agency ..................................................................................................................... 6
1.2 Reference documents ....................................................................................................................... 7
1.3 Abbreviations and definitions ........................................................................................................... 8
1.4 Scope ............................................................................................................................................... 9
1.5 Working method .............................................................................................................................. 9
1.6 Reporting ...................................................................................................................................... 10
2. INTRODUCTION .................................................................................................................... 11
2.1 Main role of the Railway Traction Electric Energy network ............................................................ 11
2.2 Traction current supply systems ..................................................................................................... 12
2.3 Traction current billing .................................................................................................................. 13
2.4 Energy Settlement system, concept. ................................................................................................ 13
3. LEGAL BASIS AND SUPPORTING DOCUMENTS ................................................................ 14
3.1 Legal background .......................................................................................................................... 14
3.2 Energy Market & Railway Market ................................................................................................. 14
3.2.1 Railway market .......................................................................................................................................................... 14
3.2.2 Energy Market ........................................................................................................................................................... 17
3.2.3 Interaction between the Rail sector directives and the Energy Directive 2009/72 ............................................................... 19
4. ERA SURVEY QUESTIONNAIRE .......................................................................................... 21
4.1 Scope ............................................................................................................................................. 21
4.2 Structure ....................................................................................................................................... 21
4.3 Analysis ......................................................................................................................................... 22
4.3.1 Is the railway electric energy network considered to fall within the scope of energy market directives? ............................... 23
4.3.2 What is the actual status and role of the IM in relation to the energy market, according to energy market Directive
2003/54? ................................................................................................................................................................... 23
4.3.3 Do you have Third Party Access rules implemented for access to the IM’s electric energy network (to allow a choice
of energy supplier)? .................................................................................................................................................... 24
4.3.4 What methods are used for traction current billing? ........................................................................................................ 24
4.3.5 How many electric traction units are in use? .................................................................................................................. 25
4.3.6 In your network, an on – board meter is mandatory or optional........................................................................................ 25
4.3.7 In case of international traffic: what is the process to exchange data between IMs, between IM/RUs? ................................. 26
4.3.8 Will the IM’s electric energy network be considered as a ‘closed distribution system’ (according to art 28 of 2009/72
directive)? ................................................................................................................................................................. 26
4.3.9 General comments ...................................................................................................................................................... 27
5. TRACTION CURRENT SUPPLY ............................................................................................ 28
5.1 TPA NOT YET implemented (SCENARIO 0) ................................................................................. 28
ERA INTEROPERABILITY UNIT
PAGE 3 OF 42
5.2 Implementation of Third Party Access for traction current ............................................................. 29
5.2.1 Scenario 1: Energy directive. ...................................................................................................................................... 29
5.2.2 Scenario 2: railway directive. ....................................................................................................................................... 31
5.2.3 Additional comments to both scenarios ......................................................................................................................... 32
6. FUNCTIONAL REQUIREMENTS OF THE SETTLEMENT SYSTEM ................................... 33
7. EXCHANGE OF DATA BETWEEN DIFFERENT ACTORS AND EXISTING
AGREEMENTS OF THE INDUSTRY...................................................................................... 35
7.1 Data exchange between different actors .......................................................................................... 35
7.1.1 Introduction ............................................................................................................................................................... 35
7.1.2 Public grid connection ................................................................................................................................................ 35
7.1.3 Supplier ..................................................................................................................................................................... 35
7.1.4 Balancing .................................................................................................................................................................. 35
7.1.5 Data exchange ............................................................................................................................................................ 36
7.1.6 Recognition of data from on board measurement equipment ........................................................................................... 36
8. ECONOMIC EVALUATION ................................................................................................... 37
9. CONCLUSIONS ....................................................................................................................... 38
9.1 Opportunity and consequences to include requirements from settlement system in ENE TSI ............ 39
9.1.1 Introduction ............................................................................................................................................................... 39
9.1.2 TSI – Functional versus structural approach .................................................................................................................. 39
9.2 Railway – energy markets interface ................................................................................................ 40
9.3 Implementation of TPA .................................................................................................................. 40
9.3.1 Proposal for further actions to be undertaken: ................................................................................................................ 41
10. LIST OF ANNEXES ........................................................................................................... 42
ERA INTEROPERABILITY UNIT
PAGE 4 OF 42
EXECUTIVE SUMMARY
This report contains the Agency’s findings in relation to the tasks detailed in clause 2.2.e of the
Mandate received from the European Commission.
The main focus of this report is:
(i) the legal and technical aspects associated with application of the Third Party Access
concept (TPA) in relation to the supply of traction current to railway undertakings;
(ii) exploring the possibility of specifying, within the Technical Specifications for
Interoperability (TSI), the requirements for a railway traction energy settlement system;
(iii) assessing the likely scale of costs associated with implementing TPA in relation to
settlement and on-board metering. However, it does not seek to fully assess and
quantify the wider impact of TPA on the railway business;
In preparing this report the Agency has also sought information from, and taken into
consideration, input from a number of relevant stakeholders which include, Member States,
National Safety Authorities, rail sector actors and European rail sector organisations. In
addition, the Agency has also assembled a Task Force comprised of rail sector experts with
specific knowledge in this area to help support development of this report.
The analysis undertaken within this report is mainly based on examination of the relevant parts
of the existing rail and energy sector directives, and feedback from stakeholders in response to
the Agency’s questionnaire which was prepared specifically for this study.
In developing this report it has become increasingly clear that if under TPA the supplier of
traction current (i.e. the energy) to individual railway undertakings is located from outside the
rail sector, this will have impacts on actors within both the energy sector and rail sector.
Consequently there are associated legal and technical issues which impinge on both of these
sectors and those actors who have to comply with directives applicable to these sectors.
In order to facilitate the analysis, the report uses conceptual scenarios as a basis for exploration
of the main legal and technical aspects associated with the provision of TPA, settlement and
metering. The first scenario seeks to capture the current position in much of the European rail
sector where TPA is not widely adopted in relation to traction current supply. Two further
scenarios are used to explore the provision of TPA in the context of using the existing Railway
Directive (2001/14/EC) or by using the existing Energy Directive (2009/72/EC).
Based on the analysis and available information, the report sets out a number of conclusions.
The key findings are summarised below:
a) with regard to traction current, the existing rail and energy directives overlap;
b) the conceptual scenarios demonstrate that it is not possible to provide TPA at railway
undertaking level by simply applying the existing energy directive or existing railway
directive;
c) currently, within the rail sector, the Infrastructure Manager (IM) is usually the supplier
to railway undertakings, and most vehicles do not have on board energy metering;
d) at present much of the European rail sector is not yet technically ready to implement
TPA in the area of traction current. The technical constraints include factors such as the
ERA INTEROPERABILITY UNIT
PAGE 5 OF 42
availability and deployment of suitable on-board metering and associated ground based
settlement systems;
e) the costs associated with widely deploying on board metering and settlement systems to
facilitate TPA in accordance with the study scenarios is estimated, on average, to
increase the annual cost of the total traction energy cost by 2.3% when compared with
the scenario without TPA. However, this percentage is subject to some uncertainty and
can vary substantially between member states;
f) there is currently a divergence between Member States in the application of the energy
directive to the rail sector and in particular to traction current;
g) if guidance is not available, the transposition of the energy directive within Member
States may be suboptimal for the rail sector and adversely impact domestic and
international railway passenger and freight business;
h) future implementation of TPA should be done in such a way that it does not conflict
with the Commissions objectives to ensure the rail sector becomes more competitive.
Adjustment to the existing legal framework based on Railway Directive 2001/14 is
likely to be necessary to achieve TPA in the railway sector;
i) given the structural nature of the relevant Technical Specifications for Interoperability
(TSI) and the requirements associated with a suitable settlement system, the existing
TSIs do not present a suitable opportunity to include settlement system requirements.
Such requirements would be better placed in separate documents, the exact nature of
which will also be influenced by the decisions taken in respect of the eventual legal
framework for implementing TPA.
Consequently, in light of the conclusions reached within this report there are a range of issues
which need to be addressed and further actions have been identified in order to progress towards
a more competitive and liberalised railway market.
ERA INTEROPERABILITY UNIT
PAGE 6 OF 42
1. STUDY ON TRACTION SETTLEMENT SYSTEM
This report has been prepared jointly by the Interoperability and the Economic Evaluation Units
of the European Railway Agency; the Impact Assessment (Annex 2) has been elaborated by the
Economic Evaluation Unit.
1.1 MANDATE OF THE AGENCY
The Article 1 of the Commission Decision C (2010)2576 final, concerning a mandate to the
European Railway Agency to develop and review Technical Specifications for Interoperability
with a view to extending their scope to the whole rail system in the European Union states that:
“The mandate for extending the scope of technical specifications for interoperability ("TSI") to
be issued in accordance with Article 8(2) of Directive 2008/57/EC is hereby adopted by the
Commission.”
The Annex, Section 2.2. of the Mandate 2010 states that:
“The Agency shall carry out the following complementary studies:
(...)
e) “Complementary study on the opportunity and the consequences to specify, in the TSI on
Energy, requirements concerning the infrastructure part of the traction energy billing system.
This study should cover at least the following aspects: the interface with the energy suppliers,
the interaction between the interoperability directive and the energy directive (Directive
2009/72/EC), the implementation of the Third Party Access in the rail sector, the requirements of
the settlement system, the exchange of data between the different actors, the existing agreements
of the industry.”
The final reports concerning the abovementioned complementary studies shall be delivered as
set out in section 3.2 (...). Where appropriate, on the basis of the results of these studies, the
present mandate will be updated by the Commission in accordance with the procedure set out in
Article 29(3) of Directive 2008/57/EC.”
ERA INTEROPERABILITY UNIT
PAGE 7 OF 42
1.2 REFERENCE DOCUMENTS
Ref. Document Reference Official
Journal
Last
Modification Version
[1] Commission Decision C(2010)2576 final of 29.4.2010
concerning a mandate to the European Railway Agency to
develop and review Technical Specifications for
Interoperability with a view to extending their scope to the
whole rail system in the European Union
[2] Council Directive 91/440/EEC on the development of the
Community´s railways
L 237, p 25
[3] Directive 2001/14/EC of the European Parliament and of
the Council on the allocation railway infrastructure capacity
and the levying of charges for the use of railway
infrastructure and safety certification
L 75, p. 29
[4] Proposal for a Directive of the European Parliament and of
the Council establishing a single European railway area
(Recast) SEC(2010) 1043, SEC(2010) 1042
[5] Directive 2003/54/EC of the European Parliament and of
the Council concerning common rules for the internal
market in electricity and repealing Directive 96/92/EC
L 176, p. 37
[6] Directive 2009/72/EC of the European Parliament and the
Council concerning common rules for the internal market in
electricity and repealing Directive 2003/54/EC
L 211, p. 55
[7] Directive 2008/57/EC of the European Parliament and of
the Council of 17 June 2008 on the interoperability of the
rail system within the Community (with amendments done
in 2011)
L 191, p.1
L 57, p.21
[8] Regulation (EEC) No 2598/70 of the Commission of 18
December 1970 specifying the items to be included under
the various headings in the forms of accounts shown in
Annex I to Council Regulation (EEC) No 1108/70 of 4 June
1970
L 278, p.1
[9] Regulation (EC) No 881/2004 of the European Parliament
and of the Council of 29 April 2004 establishing a
European railway agency (Agency Regulation)
L 164, p. 1
[10] Regulation (EC) No 1335/2008 of the European Parliament
and of the Council of 16 December 2008 amending
Regulation (EC) No 881/2004 establishing a European
Railway Agency (Agency Regulation)
L 354, p.51
[11] “Economic Methodology Guidelines”, 15/12/2006,
Document approved by the Article 21 Committee on 26
April 2007.
ERA INTEROPERABILITY UNIT
PAGE 8 OF 42
1.3 ABBREVIATIONS AND DEFINITIONS
ABBREVIATION FULL TEXT / DEFINITION
AC Alternating current
Agency The European Railway Agency (ERA)
CBA Cost Benefit Analysis
CENELEC European Committee for Electrotechnical Standardisation
CDSO Close Distribution System Operator
CR Conventional Rail
DC Direct current
DSO Distribution System Operator
ECJ European Court of Justice
EE Economic Evaluation
EMS Energy Measuring System
EN European Norm
ENE Energy
ERA The European Railway Agency
HV High Voltage
IA Impact assessment
IEM Internal Electricity Market
IM Infrastructure Manager
INF Infrastructure
LOC&PAS Locomotive and passenger carriages
MS Member State
NoBo Notified Body
NSA National Safety Authority
OCL Overhead contact line
ERA INTEROPERABILITY UNIT
PAGE 9 OF 42
RST Rolling stock
RU Railway Undertaking
TEN Trans – European Network
TEU Treaty of the European Union
TPA Third Party Access
TSI Technical Specifications for Interoperability
TSO Transmission System Operator
UIC International Union of Railways
WP Working Party
WWII World War II
1.4 SCOPE
According to COMMISSION DECISION of 29.4.2010, the study should cover at least the
following aspects:
Analysis of the opportunity and the consequences to specify, in the TSI on Energy,
requirements concerning the infrastructure part of the traction energy billing system;
the interface with the energy suppliers;
the interaction between the interoperability directive and the energy directive (Directive
2009/72/EC);
the implementation of the Third Party Access in the rail sector;
the requirements of the settlement system;
the exchange of data between the different actors;
existing agreements of the industry.
1.5 WORKING METHOD
The analysis has been carried out by the Fixed Installations Sector of the Interoperability Unit of
the European railway Agency in collaboration with other Sectors and Units of the Agency,
particularly with the Economic Evaluation Unit.
To draft the study a task force was created in order to collaborate with ERA. ERA
requested from CER, EIM and UNIFE candidates.
A questionnaire was created by ERA, and was sent and addressed to the railway sector
via NSAs and Representative Bodies. The purpose of the questionnaire was to have an
overview of the current situation on traction energy settlement system in the European
Union and consequences of the implementation of the energy market directives in the
railway sector.
ERA INTEROPERABILITY UNIT
PAGE 10 OF 42
1.6 REPORTING
The report for this study will be delivered to the European Commission by 4 May 2011.
Comments received from NSAs and Representative Bodies have been taken into account in the
final version.
The report summarises the conclusions of the study, highlights the problems to be solved in the
current situation and proposes further actions to be undertaken.
ERA INTEROPERABILITY UNIT
PAGE 11 OF 42
2. INTRODUCTION
2.1 MAIN ROLE OF THE RAILWAY TRACTION ELECTRIC ENERGY
NETWORK
The main objective and business of the railway sector it is to provide a transport service to
passengers and freight customers, utilizing the railway network, in a safe way.
As propulsion the railway uses different sources of energy. In the past it was steam, generated in
the locomotive taking heat from burning coal or oil. Now diesel and electric engines are in use.
The last one can be supplied from internal – installed batteries on the vehicle – or external
sources – via contact lines. It should be underlined that majority of today traffic is done by
traction units taking electric power from external sources via contact lines.
Though, as it is estimated, a significant 10% of total costs spent by railway operators are traction
costs, it should be highlighted that delivery of power – including also electric energy – has to be
considered as an ancillary service in order to achieve the main objectives.
The railway traction network seems to look similar to public electric energy system, but there are
major differences. Some important aspects were given below.
Traction current network was exclusively invented and designed to meet propulsion
requirements and also railway restrictions. Among the most important aspects which should have
been addressed, were the support for the reliability and punctuality of transport, increase of line
capacity, train speed, safety of passengers, staff and third parties along the electrified track.
Since the very beginning it was clear that 3 phase – used in the energy market – is not suitable
for railway because of technical difficulties. Instead 1 phase/DC systems were introduced.
It should be added that majority of different railway supply systems were developed before the
WWII, taking into account technologies available at that time. Moreover the decision, on
choosing the supply system by particular country, was also based on national, military, strategic
reasons.
Though today the technological progress reduces some limitations but does not eliminate them
completely.
Contact line – particularly overhead contact line – systems not only convey energy (like in the
public transmission/distribution systems) but they should also fulfil complicated mechanical
requirements (like e.g.: as much as possible constant height over a track, higher tensions, more
frequent supports). It has to assure the delivery of current without, as much as possible,
interruptions, with the best collection quality to mobile objects.
This requires the use of much more expensive materials (mainly copper/copper alloy) compared
to energy market (mainly aluminium/iron). Due to the contact with current collectors the life
cycle of a contact line is significantly lower than overhead/cable lines and apart from costs, the
replacement creates also transport (the core railway business) disruptions.
Substation equipment has to be tailored to the railway needs: traction supply system, voltage and
current levels which are not spotted outside, more frequent appearance of short circuits and other
failures compared to public energy system, higher safety requirements due to voltage level and
possible availability by people and animals.
ERA INTEROPERABILITY UNIT
PAGE 12 OF 42
Mobile customers have to accept higher ranges of voltages and frequencies and more often
supply interruptions (intentional – in separation sections and unintentional – during i.e. short
circuits or overloads) in comparison to energy market.
On the other hand it should be underlined that the railway electrification had (and still has) the
immense impact on the development of public electric grid in different countries. To deliver
significant power to the trains, parallel to contact line, substations and overhead lines owned by
the railway – power, transformer stations and connecting HV lines of public network were built,
giving base for future investments in infrastructure, industry, accommodation, etc.
Particular exception creates low frequency 16,7 Hz system, which was developed independently
from public 3 phase 50 Hz. This system owns its power plants, HV network and even
international HV interconnectors. Today, together with technology progress, it is supported by
converter substations 3~50 Hz/1~16,7Hz.
The energy system of the IM is not only used for traction reasons. Part of the energy is used for
other equipment and tasks that are also essential to let the trains drive, for example;
signalisation,
switches (including heating),
pre – heating of passenger trains,
maintenance and other technical facilities (from IM and RU),
passenger stations (including shops),
communication,
lighting,
etc.
The technical requirements for these installations are more comparable with those of the public
grid (AC, tension, fixed off – take points). Nevertheless also in this case, the energy must be
considered as an ancillary service in order to achieve the main objectives.
2.2 TRACTION CURRENT SUPPLY SYSTEMS
As it was mentioned above electric energy is one of the sources of propelling a train. For traction
purposes the main railway lines in Europe are electrified in majority (about 98% of the railway
networks in EU27, Norway, and Switzerland) with four systems:
1~AC 25kV 50Hz,
1~AC 15kV 16,7Hz,
DC 3kV,
DC 1.5kV
In case of traction current, the energy taken from the public grid – transmission and distribution
system – is later, on the railway side, transformed/converted in substations and delivered to
electric vehicles via contact lines and rails.
In countries using traction current with reduced frequency – 16,7 Hz – there is also a separate
high voltage network (which includes dedicated generators).
ERA INTEROPERABILITY UNIT
PAGE 13 OF 42
2.3 TRACTION CURRENT BILLING
The invoice for traction current can be issued on the two different bases:
The consumption of energy, which is delivered for traction purposes, is measured by the
meters (fulfilling the requirements on the energy market) on the primary side of the
substations. Later on it is distributed to vehicles and RUs are billed on the basis of their
train operations and associated payload (passengers / freight). Typically these estimated
methods take into account the characteristic of the vehicle, track profile and layout etc.;
The other method is to charge RUs on the basis of energy measurement by meters
installed on – board of the vehicles. In this case the railway IM normally needs access to
data from the vehicles to support activities such as settlement and billing relating to all
energy distributed and traded via the traction current supply system.
The deeper analyses of this issue will be given in following chapters.
2.4 ENERGY SETTLEMENT SYSTEM, CONCEPT.
The terms billing and settlement are often imprecisely used and can be subject to different
interpretations. Below we explain the differences in the aim to eliminate doubts and
misunderstanding.
The ‘energy settlement system’ is defined as the process by which data from measured points
are attributed to the particular point of the energy supply chain, combining with tariff
information, providing a basis for payments for the volume of energy, the use of system charges
associated with transmission and distribution networks, and also the contractual trade
arrangement between the actors of the energy chain (e.g. generators, transmission / distribution
system operators, suppliers, customers etc.).
The ‘energy billing system’ is the financial transaction inside the supply chain, based on
accountancy, taking data collected from energy settlement system.
Therefore, data used by energy billing system to invoice the various actors, including the final
customers, will be provided by energy settlement system.
Simplifying – the settlement system deals with acquisition and allocation of energy data while
the billing system is a financial tool (normally applied by each company) to create invoices
based on the settlement system data.
Taking all into account in the report we will further analyse the requirements in relation to
settlement but not billing system.
ERA INTEROPERABILITY UNIT
PAGE 14 OF 42
3. LEGAL BASIS AND SUPPORTING DOCUMENTS
3.1 LEGAL BACKGROUND
Though both railway and energy markets have been developed separately, in each case the
approach to create common, open, competitive market seemed to be similar.
Due to their strategic importance, as a base for development and security of each Member State,
for a long time railway and energy supply were controlled and supervised by state authorities and
tightly protected from any foreign influences.
To break this rule, steps were introduced to split the national organisations into independent
undertakings, dealing, generally, with:
Delivering of ‘service’ – it means: electricity supply (in energy market) or transport of
passengers/freight (in railway market)
Operating and maintenance of infrastructure/network, which enables to provide the
abovementioned ‘service’ to the customers – energy consumers or individual
passengers/freight receivers.
Those steps were undertaken by the Commission by issuing legal acts on European level in the
form of railway and energy packages.
To support the European legislations creating common rules for internal markets – both energy
and railway, independent regulators – in each Member State – were established to oversee,
control and ensure the competitive and non – discriminatory access to those markets.
Additionally the law foresees the cooperation of each market regulatory bodies at European
level.
3.2 ENERGY MARKET & RAILWAY MARKET
It is important to identify the link between both markets, railway market and energy market, and
to identify the roles that RUs and IMs take according to energy market definitions.
3.2.1 RAILWAY MARKET
Among the legal documents referring to the railway market we would concentrate on those
relating to the actors and their relations to access and ownership of railway infrastructure with
particular focus on energy subsystem.
Within the railway market there are two groups of directives, one dealing with organisation and
operation of the market (e.g. 1991/440 and 2001/14), and the other dealing with specifications to
safeguard interoperability and technical compatibility (e.g. 2008/57 with amendments).
3.2.1.1 RAILWAY INFRASTRUCTURE
At the beginning we should raise a question what is behind this term. The complex definition
was given in the Council Directive 91/440/EEC on the development of the Community’s
railways (considered as the first act encouraging competitiveness and market opening):
‘railway infrastructure’ shall mean all the items listed in Annex I.A to Commission Regulation
(EEC) N° 2598/70 of 18 December 1970 specifying the items to be included under the various
headings in the forms of accounts shown in Annex I to Regulation (EEC) N° 1108/70(1), with the
exception of the final indent which, for the purposes of this Directive only, shall read as follows:
'Buildings used by the infrastructure department'
ERA INTEROPERABILITY UNIT
PAGE 15 OF 42
To complement this view, the relevant indent in the abovementioned regulation referring to
traction current energy supply says:
Railway infrastructure consists of the following items, provided they form part of the permanent
way, including sidings, but excluding lines situated within railway repair workshops, depots or
locomotive sheds, and private branch lines or sidings:
- Ground area;
- Track and track bed
(...)
- Plant for transforming and carrying electric power for train haulage: sub – stations, supply
cables between sub – stations and contact wires, catenaries and supports; third rail with
supports;
(...)
3.2.1.2 RAILWAY ACTORS
The main activities in the railway market are:
- management of railway infrastructure – performed by IM´s.
- rail transport activities – fulfilled by RU´s.
The definition of both actors was also given in Directive 91/440/EEC but hereunder it is cited its
more developed version, which appeared in Directive 2001/14/EC:
‘Infrastructure manager’ means any body or undertaking that is responsible in particular for
establishing and maintaining railway infrastructure. This may also include the management of
infrastructure control and safety systems. The functions of the infrastructure manager on
a network or part of a network may be allocated to different bodies or undertakings;
‘Railway undertaking’ means any public or private undertaking, licensed according to
applicable Community legislation, the principal business of which is to provide services for the
transport of goods and/or passengers by rail with a requirement that the undertaking must
ensure traction; this also includes undertakings which provide traction only;
It should be underlined, that performing above activities does not require the ownership of either
infrastructure or vehicles.
Infrastructure manager/railway undertaking rights and obligations in relation to traction current
supply
From the rights and obligations imposed by European railway legislation we would stress those
referring to access to supply equipment for traction current, and the provision of the traction
current. These aspects are covered by Directive 2001/14/EC on the allocation of railway
infrastructure capacity and the levying of charges for the use of railway infrastructure and safety
certification.
The art.5, together with Annex II, defined ‘services’ which can be provided by IM for RU´s.
Some of them are inside compulsory access package, others as ‘additional services’ provided
upon the RU request.
In case of traction current supply ‘use of electrical supply equipment for traction current, where
available’ is among items listed in Annex II, point 2.
ERA INTEROPERABILITY UNIT
PAGE 16 OF 42
As it is set out in the art.5, point 1 – The supply of services referred to in Annex II, point 2 shall
be provided in a non – discriminatory manner and requests by railway undertakings may only be
rejected if viable alternatives under market conditions exist.
The traction current itself is considered as ‘additional service’ (see Annex II, point 3).
But according to the art.5, point 2 – Where the infrastructure manager offers any of the range of
services described in Annex II, point 3 as additional services he shall supply them upon request
to a railway undertaking.
Proposal for a Directive of the European Parliament and of the Council establishing a single
European railway area (Recast) COM(2010) 475 final.
This new directive will repeal, among others, Directives 91/440 and 2001/14. It is a reaction of
the Commission on the result of implementation of first railway package (which included also
Directive 2001/14) in Member States. But it also reflects a need for legal simplification and
clarification of some provision, to eliminate doubts in application. In this report we would
concentrate on aspects – already mentioned and changes implemented in COM(2110) 475 final.
Definitions:
The definitions of ‘railway undertaking’ and ‘infrastructure manager’ were adapted. The
definition of railway infrastructure appeared again as adaptation of definition from dir. 91/440.
As an important modification the new Annex I was added, listing the items belonging to the
railway infrastructure to be in accordance with 2598/70 Regulation.
Services:
The article 13 of new directive (corresponding to art. 5 of Directive 2001/14) referring to
‘conditions of access to service’ and accompanied with the Annex III (former Annex II of
Directive 2001/14) extended significantly provisions addressing access to service facilities and
the supply of the services (see Art.13 point.2).
The important changes were introduced to aspects relating to energy supply. The Commission
proposed, in the context of the recast of the first railway package (COM(2010) 475 final), to
include the use of electrical supply equipment for traction current in the so-called "minimum
access package", the minimum set of services to which all railway undertakings are entitled in a
non-discriminatory manner upon payment of a charge set at the cost directly incurred as a result
of operating the train service (direct cost).
The traction current can still be offered as additional service but charges for which shall be
shown on the invoices separately from charges for using the electrical supply equipment.
Furthermore, the draft text states that where this service is offered by only one supplier the
charge imposed shall not exceed the cost of supplying it, plus reasonable profit (see art.31.8).
It should also be noted that the supply of ‘traction current’ is generally exempt from the
principles of charging (art.31), except for the ‘single supplier’ situation mentioned in the
previous sentence.
3.2.1.3 REGULATORY BODY
Responsibilities of railway market regulatory body are defined in the relevant articles of above
mentioned Directives.
ERA INTEROPERABILITY UNIT
PAGE 17 OF 42
In case of charges the regulatory body shall ensure that they comply with provisions referred in
chapter ‘infrastructure charges’ and are non – discriminatory (see art. 30.3 of Directive 2001/14
corresponding to art. 56.3 of the recast).
Additionally Member States shall take the measures necessary to ensure that decisions taken by
the regulatory body are subject to judicial review (see art. 30.6 of Directive 2001/14
corresponding to art. 56.6 of the recast).
3.2.2 ENERGY MARKET
3.2.2.1 ENERGY MARKET LIBERALISATION
The liberalisation of energy market in the European Union is a process driven by the Directives
of the European Parliament and of the Council (Directive 96/92/EC, Directive 2003/54/EC,
Directive 2009/72/EC).
The Directives laid down the general conditions that should be in place to assure the creation of
a single internal electricity market (IEM) in Europe.
The way to reach this goal started with Directive 96/92/EC, by introducing the concept of
eligible customers, being consumers who have the legal capacity to contract volumes of
electricity from any supplier.
This process was accelerated by Directive 2003/54/EC, introducing the Third Party Access
principle, by which suppliers and generators will have access to the grid to settle negotiated
electrical energy transactions for delivering electric energy.
Therefore, TPA constitutes one of the keys on the liberalisation of the electricity market in
Europe. Under the energy market liberalisation all eligible customers benefit from this
liberalisation from 2007.
3.2.2.2 THIRD ELECTRICITY PACKAGE
In this context, on July 13th 2009 the European Parliament and the Council of the European
Union published the Third Electricity Package in which there was a new Directive 2009/72/CE –
concerning common rule for the internal market in electricity and repealing Directive
2003/54/EC. This directive needs to be transposed to law in all Member States by March 2011.
Among the significant changes this new electricity directive introduced, it was the new concept
of ‘Closed Distribution Systems’ which can be applicable for nearly all electricity networks
that aren’t public – transmission or distribution grids (article 28).
This concept was introduced after the ECJ ruling related to the Citiworks AG case (Case number
C – 439/06). See also clause 3.2.2.4
Main actors in the energy market
If we look at the energy market similarly to railway market – from service provider and manager
of infrastructure point of view – we can distinguish following actors (definitions after art.2 of
Directive 2009/72/EC):
‘producer’ means a natural or legal person generating electricity;
‘supplier’ who ‘supplies’ which means the sale, including resale, of electricity to
customers;
ERA INTEROPERABILITY UNIT
PAGE 18 OF 42
‘transmission system operator’ (TSO) means a natural or legal person responsible for
operating, ensuring the maintenance of and, if necessary, developing the transmission
system in a given area and, where applicable, its interconnections with other systems,
and for ensuring the long – term ability of the system to meet reasonable demands for
the transmission of electricity;
‘distribution system operator’ (DSO) means a natural or legal person responsible for
operating, ensuring the maintenance of and, if necessary, developing the distribution
system in a given area and, where applicable, its interconnections with other systems
and for ensuring the long – term ability of the system to meet reasonable demands for
the distribution of electricity;
‘wholesale customer’ means a natural or legal person purchasing electricity for the
purpose of resale inside or outside the system where he is established;
‘final customer’ means a customer purchasing electricity for his own use;
Detailed obligation for TSO and for DSO are given in chapters – respectively – IV, V and VI of
abovementioned Directive.
3.2.2.3 REGULATORY BODY
Chapter IX of Directive 2009/72/EC specifies the role and duties of national energy regulatory
authorities towards energy market underlining their independence and power in relation to
consumer protection and effective competition.
Directive also stresses the need of cooperation energy market regulators – at the European level
and fostering the cross – border links.
3.2.2.4 CLOSED DISTRIBUTION SYSTEMS (ARTICLE 28)
The concept of a close distribution system was introduced to facilitate third party access on
certain distribution systems with specific characteristics, where slightly less onerous and
proportionate requirements are considered appropriate. This gives an opportunity to final energy
customers, located ‘within a geographically confined industrial, commercial or shared services
site’ to benefit from TPA rule. As a consequence it also enables any energy suppliers to have
access to these potential customers.
Article 28 of Energy Directive 2009/72 provides the legal basis for Member States to classify
a system which distributes electricity, in these areas, as a closed distribution system if:
for specific technical or safety reasons, the operations or the production process of the
users of that system are integrated, or
the system distributes electricity primarily to the owner or operator of the system or
their related undertakings.
More details what ‘can include closed distribution systems’ indicates recital (30) of the
Directive:
‘Industrial, commercial or shared services sites such as train station buildings, airports,
hospitals, large camping sites with integrated facilities or chemical industry sites’.
It should be underlined that the operator of a closed distribution system shall fulfil the DSO
requirements set in chapter VI of above mentioned Directive but Member States may exempt it
from following obligations:
ERA INTEROPERABILITY UNIT
PAGE 19 OF 42
to procure the energy it to cover energy losses and reserve capacity in its system;
to approve tariffs prior to their entry into – force.
In addition the Commission issued the Interpretative Note on Directive 2009/72 EC concerning
common rules for the internal market in electricity. Clause 5 of this document provides further
interpretation regarding closed distribution systems.
3.2.2.5 THIRD – PARTY ACCESS (TPA)
The idea of third party access (TPA) – so strongly highlighted by energy market directives – is
a consequence of opening for competition the internal EU market. In the context of creation of
an internal open market, with a principle proposed by article 3 of the Treaty of the European
Union (TEU) together with the Protocol 27 of the TEU, many economic sectors within the
European Union have undergone a liberalisation process over the past decades. Also the
electricity sector and the railway sector, both referred to as ‘network industries’, belong to this
category.
The liberalisation process in these ‘network industries’ leads to provide third parties with access
to the network, to certain ‘essential facilities’ that cannot be duplicated for economic reasons.
In the electricity sector, this means that the end – user, which is connected to the network, has
a free choice of energy supplier and that the supplier/producer has free access to this network
and all customers connected to it.
Important aspect, which should be mentioned in the process of supply, is the balancing – the
comparison between the amount of energy injected (import or production) within discrete time
period with the real off take (export or consumption). This balancing process can have financial
consequences. More details about the process in the case of traction current supply are described
in clause 7.
3.2.3 INTERACTION BETWEEN THE RAIL SECTOR DIRECTIVES AND THE
ENERGY DIRECTIVE 2009/72
To address current supply issue in interaction with energy directive 2009/72 we will take into
account Directive 2001/14 and Interoperability Directive 2008/57. At the beginning we will
compare energy directive 2009/72 with Directive 2001/14.
Both directives – the Electricity and the Railway – deal with different markets. In case of
implementation of the principle of free access to infrastructure they are compliant with idea of
opening each market for competition. But the scopes are different.
The scope of Directive 2009/72 is to establish ‘common rules for the generation, transmission,
distribution and supply of electricity, together with consumer protection provisions, with a view
to improving and integrating competitive electricity markets in the Community’.
Directive 2001/14 ‘concerns the principles and procedures to be applied with regard to the
setting and charging of railway infrastructure charges and the allocation of railway
infrastructure capacity’. It deals with all issues relating to the access to railway infrastructure
and the traction current supply is only one of aspects addressed in art.5.2 and Annex II point 3.
ERA INTEROPERABILITY UNIT
PAGE 20 OF 42
If we concentrate on current supply, both directives do not contain the same principles. One
states that the free choice of electricity supplier is mandatory; the other does not give such an
obligation however free supplier choice is not ruled out entirely. But it should be underlined that
Directive 2001/14 (though even older than Directive 2003/54, introducing TPA rule in energy
market) was the first one taking into account possible option for RU not to be supplied by IM by
including traction current in additional services offered by IM.
The Electricity Directive 2009/72 and the Railway Directive 2001/14 foresee both a detailed way
to implement the principle of opening the market, for example:
- an independent regulator;
- possible combination of different roles;
- contracts;
- tariffs;
- procedure to treat complaints.
It should also be noted (as it was mentioned above) that though there are similarities, the current
supply to mobile customers is a different task compared to supply fixed customers from public
grid.
These specific issues are not taken into account by energy market directive organizing generally
the market.
What’s more, train operators would like to benefit from harmonized rules in international traffic.
Those rules are implemented in the whole railway sector with the provisions of the
Interoperability Directive (last version 2008/57) and application of relevant TSIs.
In the case of energy supply, to avoid variety of solutions, appropriate requirements referring on
– board meters were set out in the TSI.
But the interoperability issues as they are understood in railway field are not addressed in the
energy market. Energy market directive concentrates only on creating a general legal framework
(which later on is filled by national implementation) and rules with more freedom. In this sense
European railway legislation is much stricter, limiting MS’ activity.
With this different approach we would face more problems in the future in development of
international and domestic railway traffic.
ERA INTEROPERABILITY UNIT
PAGE 21 OF 42
4. ERA SURVEY QUESTIONNAIRE
4.1 SCOPE
ERA developed a questionnaire and sent it to National Safety Authorities and Representative
Bodies with the aim of getting an overview of the current situation on traction energy settlement
system in the European Union, and consequences of the implementation of the energy market
directives in the railway sector.
4.2 STRUCTURE
The questionnaire was divided in six parts, as follows:
Energy market – current situation and the consequences of application of energy
directives for IM and for RU;
Railway traction current supply – current situation in railway traction and non–
traction current supply, with indication of actors and their role in this process,
implementation of Third Party Access rules;
Traction energy billing system – the relative share of bills based on the carried load
versus bills based on energy on – board meters;
Vehicles – the number of vehicles equipped with on – board meters/used for billing and
its characteristics;
Billing system/data transfer based on on–board meters – the current requirements of
traction energy settlement systems, data exchange, the current status of utilisation, and
the technical and legal requirements for existing on– board meters;
Questions to assess the future situation – consequences of application energy market
Directive 2009/72, ‘DSO’ or ‘closed distribution system’ and Measuring Instruments
Directive.
ERA INTEROPERABILITY UNIT
PAGE 22 OF 42
4.3 ANALYSIS
At the process of the analysis of the questionnaires’ answers we focused on aspects relating to
traction current and its relationship between energy and railway market.
The following table summarizes the answers received with reference to countries and taking into
account the source: national safety authority (NSA), railway undertaking (RU), infrastructure
manager (IM)
Questionnaires Countries Number NSA RU IM
1 DE 2 1*) 1
2 PT 1 1
3 FR 2 1 1
4 UK 1 1
5 PO 2 2
6 IT 2 1 1
7 A 2 1
1
8 FI 1 1
9 BE 2 1 1
10 SL 3 2 1
11 CS 1 1
12 ET 1 1
13 NL 2 1 1
14 RO 1 1
15 SV 1 1
16 HU 1 1
17 ES 2 1 1
18 NOR 1 1
28 9 8 11
*) The answer was prepared with cooperation of Federal Network Agency.
Below we would comment some questions and their answers, giving an overview on current
status of traction current supply.
NOTE: in following diagrams ‘NA’ means – No Answer provided
ERA INTEROPERABILITY UNIT
PAGE 23 OF 42
4.3.1 IS THE RAILWAY ELECTRIC ENERGY NETWORK CONSIDERED TO FALL
WITHIN THE SCOPE OF ENERGY MARKET DIRECTIVES?
The significant numbers of answers consider the railway electric energy network and particularly
that related to traction current supply as not (or not completely) falling under energy market
regulation.
In case of answers YES, the new concept of Closed Distribution system (created by Directive
2009/72), was taken into account as possibly applicable for traction railway system.
4.3.2 WHAT IS THE ACTUAL STATUS AND ROLE OF THE IM IN RELATION TO
THE ENERGY MARKET, ACCORDING TO ENERGY MARKET DIRECTIVE
2003/54?
In majority of countries, the role of IM, according to former energy directive, is limited to final
customer or private network owner, not being a subject of energy market directive.
The answer indicated as DSO + final customer should be understood that IM is considered as
DSO in relation to 3 – phase 50 Hz grid belonging to IM but final customer for traction current
installations.
Particular attention should be given to the case where IM has DSO license and plays an active
role on the energy market. In this example, IM has a special branch or is an independent
company which main business and activities are inside the energy market and is supervised by
the energy market regulator.
YES 38.9%
NO (or not completely)
50.0%
YES BUT EXCLUDING OCL
5.6% NA 5.6%
DSO 11.1%
FINAL CUSTOMER / PRIVATE NETWORK
OWNER 66.7%
DSO+FINAL CUSTOMER
16.7%
NA 5.6%
ERA INTEROPERABILITY UNIT
PAGE 24 OF 42
4.3.3 DO YOU HAVE THIRD PARTY ACCESS RULES IMPLEMENTED FOR
ACCESS TO THE IM’S ELECTRIC ENERGY NETWORK (TO ALLOW A
CHOICE OF ENERGY SUPPLIER)?
The answers clearly reflected the present situation – traction current supply, due to particular
features and dedicated installations, is considered as a service naturally delivered by IM. As
main reasons behind are:
national legal situation – clearly indicating IM as the only supplier;
European legal situation – some member states consider that traction current supply is
out of the scope of energy market directive (see clause 4.3.1);
lack of alternative solutions: organisational, standards, equipment;
only IM has the knowledge about the railway traffic – number of trains, carried load and
passengers etc. – which is needed to calculate the energy consumption on the base of
estimations (see also clause 4.3.4).
It is important to underline that among answers YES for implementation of rules, not all IM have
already prepared technical solutions (meters on board, settlement system).
4.3.4 WHAT METHODS ARE USED FOR TRACTION CURRENT BILLING?
Due to the fact that currently only small number of vehicles are equipped with meters for billing
purposes (see clause 3.3.5), in majority cases bills for traction current consumption are based on
different estimated methods. Inside combination there have been included cases that the data
coming from the meters are used not to invoice but to measure the consumption that will be later
used as an input in the estimated method. It must be highlighted that there is no possibility to
avoid estimated methods completely – they will always be used for vehicles not equipped with
meters.
But even in the case of vehicles equipped with meters, the data from them may not be available
(damage of on – board installations or lack of communication) or trustful.
YES 29,4%
NO 70,6%
TRACTION CURRENT
ESTIMATED METHOD
82,4%
COMBINATION 11,8%
METERS 5,9%
ERA INTEROPERABILITY UNIT
PAGE 25 OF 42
4.3.5 HOW MANY ELECTRIC TRACTION UNITS ARE IN USE?
This calculation was done taking into account questionnaire answers and data on total number of
electrical RST – units in Europe: 70.000 RST – units (Table 21 ‘Tractive Stock’ – Railway
International Statistics 2008) and represents the current situation.
It should be underlined that any future change in the share of metered vehicles depends, among
others, on:
availability of standard on – board equipment;
costs of installation, maintenance, legal limits (new homologations) particularly for
retrofitting rolling stock;
age of rolling stock;
purpose – energy saving, billing;
preparation of IM;
Member State policy.
4.3.6 IN YOUR NETWORK, AN ON – BOARD METER IS MANDATORY OR
OPTIONAL
This diagram reflexes the current approach – generally on – board meter is considered as
‘optional’ equipment of the vehicle. The answer – ‘mandatory’ – represents one MS. But in
some MS the implementation plans exist for on board meters installations, referring new RST in
the next years.
Equipped with meters acc. TSI 0,39%
Equipped with meters acc. with national
standards 11,96%
NON EQUIPPED 87,65%
MANDATORY 5,56%
OPTIONAL 77,78%
NA 16,67%
ERA INTEROPERABILITY UNIT
PAGE 26 OF 42
4.3.7 IN CASE OF INTERNATIONAL TRAFFIC: WHAT IS THE PROCESS TO
EXCHANGE DATA BETWEEN IMS, BETWEEN IM/RUS?
For international traffic, the exchange of consumption data between IM´s / IM´s and IM´s /
RU´s, has a great importance for the application of TPA.
UIC organised a group, which later on developed a leaflet 930 titled: Exchange of data for cross
– border railway energy settlement. Its aim was to establish a voluntary standard for exchanging
data for cross – border traffic.
Though it makes a step forward in creation of common agreement on this issue and gains
popularity among IM´s, but according to answers still the majority does not recognize it as
a common standard. This is obviously also caused by the small amount of interoperable meters,
being already operational (see clause 4.3.5).
Some countries indicated that this protocol is being implemented or has been implemented but is
still not in use (considered in both cases as YES).
4.3.8 WILL THE IM’S ELECTRIC ENERGY NETWORK BE CONSIDERED AS
A ‘CLOSED DISTRIBUTION SYSTEM’ (ACCORDING TO ART 28 OF 2009/72
DIRECTIVE)?
This question asked for future possible implementation of new energy market directive in the
railway field and in this case application of close distribution system as a solution (see also
clause 3.2.2.4 – Closed distribution systems). Half of answers indicated YES. As it was
underlined above – the introduction of directive 2009/72 into Member States law was foreseen in
March 2011. During drafting this report, the results and obligations which would be put on the
IM as CDSO were not clear.
For countries that considered that closed distribution systems is not applicable for railway market
the main arguments behind were that it: does not match with IM’s electric energy network and
refers to “geographically confined industrial, commercial or shared services site”
YES 33,33%
NO 11%
NA 56%
YES 50% NO
27,78%
NA 22,22%
ERA INTEROPERABILITY UNIT
PAGE 27 OF 42
4.3.9 GENERAL COMMENTS
Summarising received answers we would like to draw attention to some aspects:
There are legal uncertainties in adoption of Third Party Access for traction current:
European legal situation – some Member States consider that traction current supply is
out of the scope of energy directive (see clause 4.3.1); however the Energy Directive
2009/72 is still in process of implementation by Member States;
existing legal national environment referring to traction current supply (IM – only
supplier);
metrological cross– acceptance unclear;
application of energy directives to traction current and role of IM in energy market
according to those directives – particularly unclear implementation of CDSO;
overlapping of directives covering activities and regulation of energy and railway
sectors.
Railway sector is now not technically ready to charge for the traction energy consumption basing
on the on – board meters base because of:
relatively small number of vehicles are equipped with meters used for invoicing;
relevant standard and TSI referring on– board installations are still pending;
only few IMs have settlement system enabling use of on– board data for invoicing;
need of data exchange harmonisation and acceptance between RU/IM, IM/IM etc.
ERA INTEROPERABILITY UNIT
PAGE 28 OF 42
5. TRACTION CURRENT SUPPLY
The issue of the traction current supply crosses the border between two sectors, railway and
energy.
In majority of countries, the supply of RUs with traction current usually was a duty of IM (or
dedicated railway company), and stayed inside the railway scope. However it should be noted
that there are differences, which can be derived from the particular implementation of European
railway and energy packages into national law.
With the opening of energy market and common implementation of the rule that the customer,
using any grid, has access to any supplier, the approach in the railway field is also changing.
This report does not question the applicability of TPA in traction current supply.
The following clauses describe the general processes but not taking into account particular
national solutions.
5.1 TPA NOT YET IMPLEMENTED (SCENARIO 0)
This is a standard current approach – reflecting existing technical and (in some countries) legal
situation. Energy and railway market are clearly separated – from energy market point of view
IM is considered as the final customer.
RU´s are not able to apply TPA and have to buy their traction energy at the IM and follow the
predefined framework. When the IM is the only provider of traction current to the RU, the RU is
protected because this activity is regulated under directive 2001/14.
IM owns the connections to the public grid (TSO or DSO). The IM can freely choose its
electricity supplier (direct contract or via a power exchange) on the energy market with fully
implemented TPA rule. The IM buys all the electricity delivered to Contact Lines (its own
losses, but also the consumptions for all the RU´s).
The energy consumption at the substations of the IM is measured by the TSO or DSO (or a party
fulfilling this role on request of these public grid operators) with application of meters fully
accepted on the energy market. Later on this energy is attributed to RU depending on:
a) If there is no meter on– board (or is failed)
IM estimates the consumption of each RU. In most countries this is based on traffic
category (freight, local passengers, intercity, high speed …), ton– km, km, temperature,
etc.
b) If there is meter on– board
IM receives energy data coming from the on– board energy meters. This might be
directly or via an intermediate server of the RU. It is the IM who is responsible for
checking the quality of the metered data and the meter reading process. He also
validates the energy data.
IM normally defines the framework regarding the additional service – traction current – inside
the Network Statement. The regulator of the railway market is competent to check this
framework. This framework might be a cost splitting model or some published tariffs.
ERA INTEROPERABILITY UNIT
PAGE 29 OF 42
5.2 IMPLEMENTATION OF THIRD PARTY ACCESS FOR TRACTION
CURRENT
In this case the RU should be recognized by the energy market as an eligible customer. As
a consequence the IM for this RU should play the role of grid owner/manager – the real legal
status of IM depends on which of the following scenarios is applied.
The scenarios given below are conceptual scenarios to illustrate the provision of TPA:
- one using existing energy market directives;
- a second using the existing railway directives.
These hypothetical scenarios have been developed to explore the legal aspects, conditions and
consequences of introducing TPA for RU´s. Consequently these scenarios are not intended to be
considered as a practical implementation of TPA.
5.2.1 SCENARIO 1: ENERGY DIRECTIVE.
In this scenario the energy directive applies to the provision of traction current for the purpose of
ensuring TPA for RU.
In addition this will also allow suppliers’ access to eligible customers such as RU´s.
Legal aspects
According to energy directive definitions, IM should be considered as DSO for RUs
which want to apply TPA, with all consequences and obligations set by the European
law and its transposition into national law;
If the IM supplies traction current to RU´s, IM will also be considered as
a wholesale customer;
In addition IM will also be considered as a final customer for his own consumption;
Railway traction current supply has to comply with rules of the energy market;
Energy market has to accept and adapt to special features like: mobile customers
changing distribution zones, international traffic, mutual recognition of metrological
acceptance for on– board metering etc.
If TPA is applied according to energy directive, this directive also covers the railway
infrastructure.
Conditions:
a) RU (applying TPA)
Energy measurement Traction current energy on – board measurement should be accepted in the energy
market.
Data transfer Data transfer from on – board measurement system, their acceptance, validation and
availability should be done according to the energy market rules.
b) RU (not applying TPA)
The arrangements in clause 5.1 continue to apply.
c) IM
Having a Settlement system, accepted by the energy market and being able to:
- handle and exchange the data with energy market according to its rules;
ERA INTEROPERABILITY UNIT
PAGE 30 OF 42
- manage and verify all data (IT software/ hardware to manage all data) coming from
meters from the primary side of substations, traction current energy on– board
measurement, any other energy consumed from traction current installations for other
than traction purposes;
- take into account the energy (calculated on the base of estimated methods) used by
the vehicles not equipped with on– board meters;
- take into account losses in the installations;
- prepare invoices to those RUs who are not applying TPA (IM is the supplier);
- prepare invoices (use of grid charge, possible balancing of energy, metering costs) to
those RUs who are applying TPA (IM is not the supplier but the grid operator);
- prepare invoices for suppliers or RU’s relating to charges for transporting energy via
the IM’s Distribution System;
- exchange data between IM/IM;
- exchange data between IM/RU (according to energy market if RU applies TPA).
Having a system to exchange specific information with the energy market (e.g. in
case of the change of the supplier or the change of consumption profiles)
Having additional qualified staff to deal with energy matters to be active on the
energy market:
- trading energy (acting as a supplier of energy to those end customers connected to
the grid of IM);
- verification and handling the data and to transmit these data to all parties involved;
- development of estimation methods when necessary.
Consequences
Benefits
Rules of TPA as implemented in the energy market are legally clear with clear
obligations/rights for various actors (e.g. TSO, DSO, supplier, customer, Member State,
energy market regulator etc.);
RU has similar legal rights to other final customers in the energy market;
Additional business opportunities for IM in another market (apart from railway), unless
IM is designated as a CDSO.
Drawbacks
Energy directive and existing national regulations and rules do not readily accommodate
certain rail sector features e.g. currently unable to accommodate the mobile consumer
concept;
Problems in harmonisation rules in case of international traffic – energy market is
developed on national level;
Energy market requests energy meters on all connections of end users to the grid of a
DSO;
Rail sector only has modest levels of on– board metering at present;
Risk regarding the acceptance of technical solutions, developed specifically for the
railway market, in the energy market like on– board energy measurement system, rail
settlement system etc.;
Problems with splitting responsibilities and obligations between railway and energy
directives and regulatory arrangements e.g. implementing the railway directives to the
electrical supply equipment and energy directives to the traction current;
ERA INTEROPERABILITY UNIT
PAGE 31 OF 42
Additional burdens (and extra costs) on IM to fulfil the DSO and supplier requirements
according to energy market on European and national level (like e.g. licence
requirement in some countries);
5.2.2 SCENARIO 2: RAILWAY DIRECTIVE.
In this scenario the railway directive applies to the provision of traction current for RU.
Legal aspects
Application of art. 5.1 and 5.2 of dir. 2001/14
Scope of energy subsystem according to interoperability directive (2008/57)
Conditions
a) RU (applying TPA)
Energy measurement system (EMS) EMS as specified in LOC & PAS TSI (or in national laws), and metrologically tested
according to national calibration law.
Data transfer Data transfer between vehicle and data collecting system.
b) RU (not applying TPA)
The arrangements in clause 5.1 continue to apply.
c) IM
Having a Settlement system, being able to:
- handle and exchange the data with energy market according to its rules;
- manage and verify all data (IT software/ hardware to manage all data) coming from
the meters from the primary side of substations, traction current energy on– board
measurement, any other energy consumed from traction current installations for other
than traction purposes;
- take into account the energy (calculated on the base of estimated methods) used by
the vehicles not equipped with on– board meters;
- take into account losses in the installations;
- prepare invoices to those RUs who are not applying TPA (IM is the supplier)
- prepare invoices (use of grid charge, possible balancing of energy, metering costs) to
those RUs who are applying TPA;
- exchange data between IM/RUs and IM/IM (e.g. according with UIC leaflet 930) and
between IM / energy market according to its rules.
Consequences
Benefits
Avoidance of excessive burdens in relation to application of the energy market directive
within the railway sector;
More freedom within TPA application for taking into account specific features of
railway field (e.g. mobile customers);
ERA INTEROPERABILITY UNIT
PAGE 32 OF 42
Opportunity to reach clear separation between railway and energy market and between
railway and energy market regulator responsibilities;
Easier harmonisation of rules for international traffic on the base of railway
interoperability directive;
Less additional qualified staff needed to be able to implement TPA;
In future, opportunity to improve rights of RU regarding energy market aspects inside
the railway regulation and under supervision of railway regulator.
Drawbacks
Weaknesses in the legal status and regulation of TPA according to railway market
directive (RU rights and protection are very limited in relation to traction current
supply);
No clear role of IM according to energy market directive in facilitating TPA;
Risk of non – acceptance of data from RUs having the role as end customers within the
energy market.
5.2.3 ADDITIONAL COMMENTS TO BOTH SCENARIOS
Each scenario requires adaptation of existing energy and railway (European and
national) laws to fulfil TPA within the railway sector because of special features
e.g. mobile customers, international traffic;
Existing legal frameworks in some countries do not allow the supply traction current
from sources other than IM;
Existing European legal framework does not safeguard vulnerable RU´s (small RU´s are
not guaranteed their supply at reasonable cost);
Additional burdens on IMs (and associated costs) can endangered the competiveness of
the railway market;
Problem of metrological cross acceptance of on – board metering, particularly for
international traffic exists for both scenarios. Inclusion of EMS in the revised
Metrological Instrument Directive has been proposed, but the outcome is not yet
known;
According to answers from the questionnaire, the railway sector is not technically ready
to implement TPA, e.g. most trains are still unmetered.
For the foreseeable future metered and unmetered trains will need to be accommodated;
Different implementation of TPA may become a hindrance in the international traffic;
ERA INTEROPERABILITY UNIT
PAGE 33 OF 42
6. FUNCTIONAL REQUIREMENTS OF THE SETTLEMENT
SYSTEM
The settlement system, which must be introduced by IM, should collect data (i) from vehicles’
EMS, (ii) data (energy imported/exported) from each meter on the connection point in the
substations, (iii) meters measuring non – traction loads using the traction current distribution
system.
The settlement system must be able to:
- handle and exchange the data with energy market according to its rules;
- manage and verify all data.
- take into account the energy (calculated on the base of estimated methods) used by
the vehicles not equipped with on– board meters;
- take into account losses in the installations;
- prepare invoices to those RUs who are not applying TPA (IM is the supplier);
- prepare invoices (use of grid charge, possible balancing of energy, metering costs) to
those RUs who are applying TPA;
- prepare invoices for suppliers or RU’s relating to charges for transporting energy via
the IM’s Distribution System;
- exchange data between IM/IM;
- exchange data between IM/RU.
In relation to data coming from on board EMS (i), the settlement system should consist of the
following three processes:
1- Data collecting from on board measurement systems (energy consumed and regenerated)
2- Exchange of data with other settlement systems;
3- Attributing energy consumptions to the consumers.
It has also to fulfil the energy market requirements for:
content of data;
exchange format;
time limit for data access for all partners being involved in the process of energy
delivery.
The figure below illustrates the data flow from on board energy measurement system to and
through settlement system.
ERA INTEROPERABILITY UNIT
PAGE 34 OF 42
Requirements for EMS are specified in the CR LOC&PAS TSI. The detailed requirements for
data exchange should be further specified within the development of the requirements of the
settlement system.
Given below is an indication of the current state of standardisation which could be used as a
basis for future development.
1. Interface from on – board data handler to on ground Data Collecting
- General requirements are defined in EN.
2. Data Collecting
- EN has some essential requirements regarding data security and basic functionalities that
should be implemented.
- UIC leaflet 930 also has some essential requirements, e.g. regarding pre – validation of the
collected data.
- UIC leaflet 930 appoints the IM as the responsible party1 for the data.
- UIC leaflet 930 gives the RU the right of access to this data.
3. Exchange of data between IM´s.
- UIC leaflet 930 defines a protocol for these interfaces.
- UIC leaflet 930 describes the tasks to be fulfilled (e.g. validation of location data and
splitting consumptions towards the networks of different IM´s).
4. Attributing energy consumptions.
- Supporting document 2 to UIC leaflet 930 describes the information needed to be able to
make a correct validation or estimation for unmetered trains, and gives recommendations
for estimation systems.
- Supporting document 3 to UIC leaflet 930 describes the right access of RU to his
consumption data (validated data coming from energy meter or estimated data).
- Exchange of data between IM and energy market is defined at the national level.
1 Data may be collected by other parties, but IM remains responsible for data security.
ERA INTEROPERABILITY UNIT
PAGE 35 OF 42
7. EXCHANGE OF DATA BETWEEN DIFFERENT ACTORS AND
EXISTING AGREEMENTS OF THE INDUSTRY
This chapter describes the general exchange of information between actors involved in traction
current supply.
7.1 DATA EXCHANGE BETWEEN DIFFERENT ACTORS
7.1.1 INTRODUCTION
On board equipment of trains must fulfil other sets of requirements defined in the railway field
different than standard industrial meters. Railway sector is developing procedures to exchange
data of mobile end customers on an international basis.
Track access conditions and the minimum service package including the access to railway
energy installations are offered by IM, published in the Network Statement and accepted by the
railway regulator. Traction current is considered as an additional service provided by IM.
In case of traction current consumption, the IM on whose network the consumption took place is
responsible for handling the data and to transmit this data to all parties involved.
7.1.2 PUBLIC GRID CONNECTION
The IM has the access points to the public grid (DSO or TSO). He is responsible for all the
necessary contracts with these operators of public grids and transmitting the necessary data to the
public grid operators.
7.1.3 SUPPLIER
At present, if the IM sells energy to one RU, he must offer this service to all RUs. In this case,
the RU has the right to choose the IM as supplier. The IM has different options to provide
himself of this energy:
- buy it on the power exchange;
- buy it from a trader or a supplier;
- produce the energy itself;
- import the energy from another country.
In any case, the IM is responsible for sending the necessary information in accordance with the
national energy market rules. In some countries the supply information must be sent to the
electricity regulator.
7.1.4 BALANCING
Balancing is an important process in energy data exchange.
As electricity cannot be stored easily, the injection of energy must at all the time be the same as
the off – take. This obligation must be fulfilled for each balancing zone.
In general, there is one balancing zone for each country. Nevertheless, it is possible that one
country is divided in more than one balancing zones. In most of the countries, the TSO is the
main responsible party to control and check the global balance of his zone.
He is also responsible for the settlement of imbalances. In some countries the Imbalance
Settlement Party can be another independent body.
ERA INTEROPERABILITY UNIT
PAGE 36 OF 42
For each injection and off – take point in a certain balancing zone the grid operator, user or his
supplier must appoint a Balancing Responsible Party. In most of the cases this will be the
producer or the supplier himself. The Balancing Responsible Party must keep the energy balance
for all his injections and off – take points for which he is responsible.
Nevertheless, there could be in imbalance for a certain time period. If he has a shortage of
energy, he gets automatically energy from the system. In this case the Imbalance Settlement
Party will send him a bill. If he has a surplus of energy, the system will absorb this. In most of
the time, he will be paid for this energy by the Imbalance Settlement Party.
The time period to control the imbalance can be different for each balancing zone. In most of the
balancing zones, a period of 15 minutes is taken.
The settlement can only be done if the Imbalance Settlement Party receives all the necessary
information from all the grid operators (TSO and DSO).
In the railway sector, the IM sends the information about the injection/off – take to each
Balancing Responsible Party active at the IM – grid for each time period.
In case of applying TPA in the railway sector the introduction of mobile access points needs
a change of the existing balancing rules.
7.1.5 DATA EXCHANGE
The IM has always to use national energy market rules for data exchange with energy market
actors. Currently there are no European standards used throughout Europe for this type of
information. Also the part data exchange in the new grid codes (under development) will not
result in a European data exchange format for this data flow.
Other requirements can also be different:
- time period to be used for time series;
- deadline for transmitting time series for previous month;
- methods for corrections;
- conditions regarding minimal quality level of energy meters;
- etc.
Within the railway sector, for international traffic, data exchange between IM/IM and between
IM/RU for billing and settlement purposes, are specified in UIC leaflet 930. This allows the
consumption to be correctly accounted for within each MS.
7.1.6 RECOGNITION OF DATA FROM ON BOARD MEASUREMENT
EQUIPMENT
EMS as a part of the RST subsystem has to be assessed and certified according to requirements
set in CR LOC&PAS TSI by application of procedure for establishing the ‘EC’ declaration of
verification.
Additionally, sensors and energy meter have to be tested by a metrological laboratory in the MS.
Following issues should be addressed to eliminate barriers in the international traffic:
mutual recognition of the metrological assessment among MS;
cross acceptance of the re – verification framework. (including frequency, responsible
bodies, etc)
ERA INTEROPERABILITY UNIT
PAGE 37 OF 42
8. ECONOMIC EVALUATION
Traction energy represents 5 – 10% of total cost within RU. In absolute values, the total amount
of annual traction energy cost within Europe lies between 5 – 10 G€.
The share of traction energy costs in relation to total costs of RU is increasing due to the
tendency of an increase of electricity unit price over the last years.
TPA is technically feasible with the use of on – board meters, although a legal framework has
to be further developed to apply TPA in the traction energy market. In this legal framework,
RUs not choosing to apply TPA, must get traction energy supplied at reasonable cost and
overheads in order not to create barriers for these RUs (in particular small RUs with limited
means to act on the energy market).
It is very unlikely that suppliers and other parties in the electricity market (e.g. party responsible
for settling the imbalance on the grid) will accept big end consumers not using energy meters.
This assumption must be evaluated with the stakeholders of the energy market (DG ENER).
In scenarios 1 and 2, the overall increase in costs of metering and settlement to support TPA
based on one case study is estimated in average at 2.3 % of total traction energy costs (with
current traction energy prices) in comparison with scenario 0. However this percentage will vary
substantially between Member States, depending upon national requirements. The choice to
apply TPA or not would be made by the individual RUs by evaluating their balance between
costs and benefits.
Large investment costs may be necessary for the IM in its role as Distribution System Operator
according to the energy market directive (scenario 1). These costs could vary by two orders of
magnitude, according to national legislations and circumstances. Costs could then be recovered,
at least partly, by new users (other than RUs) getting their energy supply from the railway
electricity grid owned by the IMs. But increased charges for existing users (RUs) may result if
income from new users does not cover the IM’s additional costs. Therefore, the business case at
national level must consider to what extend the IM has to fulfil the obligations of DSO
(subsidiarity principle).
Full Impact Assessment is attached in Annex 2.
ERA INTEROPERABILITY UNIT
PAGE 38 OF 42
9. CONCLUSIONS This report has been prepared in accordance with the study mandate, and is therefore based on
the understanding that the Commission intends TPA to be implemented within the rail sector and
to traction current in particular. Therefore it does not seek to quantify the benefits of TPA.
In conducting this study, following key issues have been identified:
- with regard to traction current there is an overlapping of railways and energy sector
directives;
- the two scenarios demonstrate that it is not possible to provide TPA at RU level by
simple application of energy directive or railway directive;
- within the rail sector currently the IM is usually a supplier to RUs and most vehicles are
unmetered;
- at present much of the European rail sector is not yet technically ready to implement
TPA in the area of traction current. The technical constraints include factors such as the
availability and deployment of suitable on-board metering and associated ground based
settlement systems;
- a transition period will be necessary to enable TPA within the rail sector which will
allow the necessary legal, technical and commercial changes to be undertaken;
- in scenarios 1 and 2, the overall increase in costs of metering and settlement to support
TPA based on one case study is estimated in average at 2.3 % of total traction energy
costs (with current traction energy prices) in comparison with scenario 0. However this
percentage will vary substantially between Member States, depending upon national
requirements. The choice to apply TPA or not would be made by the individual RUs by
evaluating their balance between costs and benefits;
- future implementation of TPA should be done in such a way that it does not conflict with
the Commission objectives to ensure the rail sector becomes more competitive.
Adjustment to the existing legal framework is likely to be necessary to achieve this;
- there is currently a divergence between Member States in application of the energy
directive to the railway sector and particularly in traction current;
- if guidance is not available, the transposition of the energy directive within Member
States may be suboptimal for the railway sector and adversely impact the domestic and
international railway passenger and freight business.
In light of the above, there is a need to address these issues in order to progress towards a more
competitive and liberalised railway market.
ERA INTEROPERABILITY UNIT
PAGE 39 OF 42
9.1 OPPORTUNITY AND CONSEQUENCES TO INCLUDE REQUIREMENTS FROM
SETTLEMENT SYSTEM IN ENE TSI
9.1.1 INTRODUCTION
How the legal framework and interactions between railway and energy sectors are developed
will influence how and where the settlement system requirements are best addressed. For
example, if the energy directive were to be used as the main legal basis for introducing TPA
within the railway sector, settlement system requirements would be defined within this
framework and there will be no need to include requirements within TSI.
This decision has a fundamental impact on further activity.
Alternatively, if the settlement system was to be included in the ENE TSI, then the scope and
time schedule would be affected. Also it would have an impact on the timeframe of other
structural TSI´s, covering Infrastructure and Rolling Stock subsystems, with which the Energy
TSI has an interface.
9.1.2 TSI – FUNCTIONAL VERSUS STRUCTURAL APPROACH
The Energy TSI in general deals with energy subsystem which is considered as one of structural
subsystems. It sets out requirements for:
- traction current supply fixed installations and its impact on rolling stock;
- OCL to interact properly with pantograph profiles defined in TSIs for rolling stock.
All those requirements are ‘line’ related – it means that they refer to installations which are over
and close to the track (OCL with masts) or on track side (substations) but strictly connected with
particular railway line.
The TSI with its assessment process, involvement of NoBo, applied modules, can be
implemented together with ‘line construction or improvement’ in the procedure for ‘placing in
service’.
The traction current settlement system is independent of any fixed energy subsystem installations
e.g. OCL or substations. Its “infrastructure part” should be understood as the software and
hardware that is needed to allocate data between actors in the relevant railway and energy
market. It is not related to the process of ‘construction new, upgrading or renewal’ of the
subsystem and could be placed anywhere (even outside EU) with the application of new
technologies.
The conclusions from the 15th
meeting of CSG (Conformity Survey Group) on 6 of October
2010 with NB Rail regarding traction current settlement system are given below:
The track – side equipment and the transmission of data will cover operational issues
and the requirements will be functional. Therefore track – side equipment is not in the
scope of NoBos activities which may asses products with clearly defined technical
parameters.
It is preferable to specify traction current settlement system in a specific legal document
with guidelines. Otherwise if specified in an existing TSI there will be a risk the subject
to be bulked together with other important issues and not to be paid sufficient attention.
Taking into account the suggestions of CSG group, in case of the settlement system only
functional requirements can be set. Following the example of functional TSIs we believe it
would be necessary to develop a separate document devoted to this system. As a consequence we
would achieve a clear split between:
ERA INTEROPERABILITY UNIT
PAGE 40 OF 42
- structural (in existing Energy TSI – related to current collector/contact line interaction and
fixed installations) and functional approach;
- requirements assessed and not assessed by NoBos;
- different implementation scenarios.
9.2 RAILWAY – ENERGY MARKETS INTERFACE
The principal issue is the fact that the main recipient of the consumption data is the energy
market. As a consequence the data should be delivered to and accepted by this market – fulfilling
the existing requirements and legal obligations for this sector.
To harmonise them and to clearly define the interface between railway and energy market can be
a difficult task. It is very unlikely that the railway sector will be able to force a standardisation on
these topics in the energy market.
To solve it, this should be done with close collaboration with experts from energy market.
9.3 IMPLEMENTATION OF TPA
The idea of Third Party Access derives from the competition law, giving the right of
free access to the open market by both: the service provider and the customer.
The main business in the railway market is to transport passengers and freight using the
railway infrastructure. RU´s have free access to railway infrastructure and provide
services to passengers and freight customers in accordance with relevant European and
national law (implementation of railway packages) and railway market regulators.
Traction current is one of the sources of energy to drive a train. In general it is
generated/converted from 3~50 Hz public electric system and supplied, primarily for
this purpose, through installations – substations, feeders, contact line – which are part of
the railway infrastructure, usually owned/managed by IM.
Due to that the traction current is delivered to mobile objects (i.e. trains) its
requirements are different from those present in the public transmission/distribution
system, supplying fixed installations.
RU must have a non – discriminatory access to traction current installations (art.5.1
Directive 2001/14).
To give possibility for RU to be supplied with traction current, the Directive 2001/14 (it
is also present in the recast) indicates it as an additional service (art.5.2). If this
additional service is offered by the IM it must be delivered to any RU upon request, but
this Directive does not oblige the IM to be a default supplier.
Current role of the IM on the energy market depends on:
- implementation of the European railway package into national law. For example –
it is possible that the incumbent RU (with or without other RUs) buys energy for
its/their own purposes on the energy market;
- its involvement in the energy market and the national implementation of energy
market directives in the railway field.
After analyses of the questionnaire answers, the railway sector is now (with few
exemptions) not yet ready to implement TPA in traction current supply.
It is related to:
ERA INTEROPERABILITY UNIT
PAGE 41 OF 42
- legal framework – which directive – energy or railway – is used to introduce TPA,
current legal national framework, metrological cross– acceptance, clear role for
IM in this process, adaption of energy market rules to accept data from rail sector
which includes features such as mobile consumers etc.;
- technical equipment – lack of suitable on – board meters, lack of implemented
settlement systems for collecting and distributing the consumption data, etc.;
To allow RU the free traction current supplier choice (under TPA), following basic
requirements should be fulfilled:
- Vehicle should be equipped with a suitable on – board energy measuring system
(EMS) e.g. according to TSI;
- IM must have implemented the settlement system;
- Access, energy transportation rules and tariffs to railway traction current
installation should be known;
- IM should be recognized as an actor on the energy market.
According to the answers to the questionnaire, one country claims that TPA is currently
implemented without the need for on board metering. However we envisage on board
metering will be required for TPA in the future for RUs to be billed based on the
measured real consumption.
In any case, the introduction of TPA rule in the traction current requires relevant
adaptation of railway and energy laws. It should also take into account both TSI and non
TSI conform systems. In order not to create any obstacles for international traffic (and
interoperability) those changes should be done on the European and MS level.
The consequences of implementation of TPA in the traction current on the core railway
business should be analysed in detail. Particularly in terms of legal obligations,
additional costs (both for RU and IM) which later on would be transferred to passengers
and freight customers. The analysis should also consider how the energy market will
function when factors within the rail sector outside of RU control can affect the load
profile.
Some Member States consider that in the implementation of Energy Directive 2009/72,
the IMs distribution systems might also be regarded as a closed distribution system,
but the resulting obligations on IM are not yet clear.
9.3.1 PROPOSAL FOR FURTHER ACTIONS TO BE UNDERTAKEN:
Adapt the Railway Directive 2001/14 to include provisions to enable TPA to be applied
in the railway sector and adjust the energy market directive accordingly.
Clarify the interface between the energy directive and adapted railway directive.
Develop safeguard to ensure traction current supply to those RUs not wishing to adopt
TPA.
Clarify regulatory arrangements for traction current.
Develop settlement system requirements under the railway directive.
Resolve metrological aspects of cross acceptance of on board metering regarding
placing on the market and continued operation.
Develop appropriate transition arrangements.