introduction and charge barry barish gde meeting frascati 7-dec-05
DESCRIPTION
7-Dec-05GDE Frascati - Introduction & Charge3 GDE Frascati – Why are we here? Discuss progress since Snowmass Finish the BCD Organize the GDE and the broader R&D and Design efforts for next yearTRANSCRIPT
![Page 1: Introduction and Charge Barry Barish GDE Meeting Frascati 7-Dec-05](https://reader035.vdocuments.net/reader035/viewer/2022062905/5a4d1ae27f8b9ab0599779b5/html5/thumbnails/1.jpg)
Introduction and Charge
Barry BarishGDE Meeting
Frascati 7-Dec-05
![Page 2: Introduction and Charge Barry Barish GDE Meeting Frascati 7-Dec-05](https://reader035.vdocuments.net/reader035/viewer/2022062905/5a4d1ae27f8b9ab0599779b5/html5/thumbnails/2.jpg)
7-Dec-05 GDE Frascati - Introduction & Charge 2
The GDE after ~3 Months
• How are we doing?– BOTTOM LINE is that we are on track to produce
a BCD by end of 2005 that will provide a sound basis for entering into a reference design effort, globally coordinate R&D program, begin industrialization, determine costs, etc. next year
• What are our biggest problems?– communication, communication, communication
• Where are we going next?– Stay tuned for my next talk
![Page 3: Introduction and Charge Barry Barish GDE Meeting Frascati 7-Dec-05](https://reader035.vdocuments.net/reader035/viewer/2022062905/5a4d1ae27f8b9ab0599779b5/html5/thumbnails/3.jpg)
7-Dec-05 GDE Frascati - Introduction & Charge 3
GDE Frascati – Why are we here?
• Discuss progress since Snowmass
• Finish the BCD
• Organize the GDE and the broader R&D and Design efforts for next year
![Page 4: Introduction and Charge Barry Barish GDE Meeting Frascati 7-Dec-05](https://reader035.vdocuments.net/reader035/viewer/2022062905/5a4d1ae27f8b9ab0599779b5/html5/thumbnails/4.jpg)
7-Dec-05 GDE Frascati - Introduction & Charge 4
GDE Began at Snowmass
670 Scientists attended two week
workshopat
Snowmass
![Page 5: Introduction and Charge Barry Barish GDE Meeting Frascati 7-Dec-05](https://reader035.vdocuments.net/reader035/viewer/2022062905/5a4d1ae27f8b9ab0599779b5/html5/thumbnails/5.jpg)
7-Dec-05 GDE Frascati - Introduction & Charge 5
Global Design Effort
– The Mission of the GDE • Produce a design for the ILC that includes a
detailed design concept, performance assessments, reliable international costing, an industrialization plan , siting analysis, as well as detector concepts and scope.
• Coordinate worldwide prioritized proposal driven R & D efforts (to demonstrate and improve the performance, reduce the costs, attain the required reliability, etc.)
![Page 6: Introduction and Charge Barry Barish GDE Meeting Frascati 7-Dec-05](https://reader035.vdocuments.net/reader035/viewer/2022062905/5a4d1ae27f8b9ab0599779b5/html5/thumbnails/6.jpg)
7-Dec-05 GDE Frascati - Introduction & Charge 6
GDE Organization for Snowmass
•W
G1 LET bdyn.
•W
G2 M
ain Linac•
WG
3a Sources•
WG
3b DR
•W
G4 B
DS
•W
G5 C
avity• GG1 Parameters• GG2 Instrumentation• GG3 Operations & Reliability• GG4 Cost & Engineering• GG5 Conventional Facilities• GG6 Physics Options
Technical sub-systemWorking Groups
Global Group
Provide input
![Page 7: Introduction and Charge Barry Barish GDE Meeting Frascati 7-Dec-05](https://reader035.vdocuments.net/reader035/viewer/2022062905/5a4d1ae27f8b9ab0599779b5/html5/thumbnails/7.jpg)
7-Dec-05 GDE Frascati - Introduction & Charge 7
Goals of the Snowmass Workshop• Recommendations for the Baseline Configuration
• Identify - Alternative Configurations
• Identify R&D– To support the baseline– To develop the alternatives
• Priorities for detector R&D
![Page 8: Introduction and Charge Barry Barish GDE Meeting Frascati 7-Dec-05](https://reader035.vdocuments.net/reader035/viewer/2022062905/5a4d1ae27f8b9ab0599779b5/html5/thumbnails/8.jpg)
7-Dec-05 GDE Frascati - Introduction & Charge 8
Guidance for Baseline Configuration
Baseline: A forward looking configuration which we are reasonably confident can achieve the required performance and can be used to give a reasonably accurate cost estimate by mid-end 2006 in a “Reference Design Report.”
![Page 9: Introduction and Charge Barry Barish GDE Meeting Frascati 7-Dec-05](https://reader035.vdocuments.net/reader035/viewer/2022062905/5a4d1ae27f8b9ab0599779b5/html5/thumbnails/9.jpg)
7-Dec-05 GDE Frascati - Introduction & Charge 9
What are Alternatives and Why?
Alternates: Technologies or concepts, which may provide a significant cost reduction, improved performance (or both), but which will not be mature enough to used in baseline by end 2006
Alternatives will be part of the RDR, will form an important element in the R&D program and are the key to evolving the design
![Page 10: Introduction and Charge Barry Barish GDE Meeting Frascati 7-Dec-05](https://reader035.vdocuments.net/reader035/viewer/2022062905/5a4d1ae27f8b9ab0599779b5/html5/thumbnails/10.jpg)
7-Dec-05 GDE Frascati - Introduction & Charge 10
Baseline Configuration Document
• Our ‘Deliverable’ by the end of 2005
• A structured electronic document– Documentation (reports, drawings etc)– Technical specs.– Parameter tables– …
• A ‘printable / readable’ summary document (~100 pages) (ready in early 2006)
![Page 11: Introduction and Charge Barry Barish GDE Meeting Frascati 7-Dec-05](https://reader035.vdocuments.net/reader035/viewer/2022062905/5a4d1ae27f8b9ab0599779b5/html5/thumbnails/11.jpg)
7-Dec-05 GDE Frascati - Introduction & Charge 11
Structure of the BCDSummary-like overview for those who want to understand the choice and the why
Technical documentation of the baseline, for engineers and acc. phys. making studies towards RDR
![Page 12: Introduction and Charge Barry Barish GDE Meeting Frascati 7-Dec-05](https://reader035.vdocuments.net/reader035/viewer/2022062905/5a4d1ae27f8b9ab0599779b5/html5/thumbnails/12.jpg)
7-Dec-05 GDE Frascati - Introduction & Charge 12
Alternatives Section(s)
Note ACD is part of the BCD
![Page 13: Introduction and Charge Barry Barish GDE Meeting Frascati 7-Dec-05](https://reader035.vdocuments.net/reader035/viewer/2022062905/5a4d1ae27f8b9ab0599779b5/html5/thumbnails/13.jpg)
7-Dec-05 GDE Frascati - Introduction & Charge 13
The Key Decisions
Critical choices: luminosity parameters & gradient
![Page 14: Introduction and Charge Barry Barish GDE Meeting Frascati 7-Dec-05](https://reader035.vdocuments.net/reader035/viewer/2022062905/5a4d1ae27f8b9ab0599779b5/html5/thumbnails/14.jpg)
7-Dec-05 GDE Frascati - Introduction & Charge 14
Making Choices – The Tradeoffs
Many decisions are interrelated and require input from several WG/GG groups
![Page 15: Introduction and Charge Barry Barish GDE Meeting Frascati 7-Dec-05](https://reader035.vdocuments.net/reader035/viewer/2022062905/5a4d1ae27f8b9ab0599779b5/html5/thumbnails/15.jpg)
7-Dec-05 GDE Frascati - Introduction & Charge 15
From Snowmass to a Baseline
August September October November December
2005Snowmass
WW/GG summariesResponse to list of 40+ decisions
All documented ‘recommendations available on ILC Website (request community feedback)
Review by BCD EC BCD EC publishes‘strawman’ BCD
PublicReview Frascati
GDE meeting
BCD Executive Committee:BarishDugan, Foster, Takasaki Raubenheimer, Yokoya, Walker
![Page 16: Introduction and Charge Barry Barish GDE Meeting Frascati 7-Dec-05](https://reader035.vdocuments.net/reader035/viewer/2022062905/5a4d1ae27f8b9ab0599779b5/html5/thumbnails/16.jpg)
7-Dec-05 GDE Frascati - Introduction & Charge 16
Baseline Configuration Document Review Process
• BCD executive committee has monitored BCD progress– Review WG/GG summary write-ups (recommendations)– Review each question on the list of 40+ decisions
• BCD EC identified and solicited needed additional input– Commissioned 5 “white papers” – Invited independent reviewers (Oide, Richter & Rivkin)
• Strawman BCD available mid-November• Presentation of strawman BCD at Frascati GDE meeting
(Dec. 10-12)
• Final agreed BCD to be documented by end of 2005• Final BCD becomes property of ‘Change Control Board’ in
early 2006• Reference Design to be completed by end of 2006
![Page 17: Introduction and Charge Barry Barish GDE Meeting Frascati 7-Dec-05](https://reader035.vdocuments.net/reader035/viewer/2022062905/5a4d1ae27f8b9ab0599779b5/html5/thumbnails/17.jpg)
7-Dec-05 GDE Frascati - Introduction & Charge 17
The Prospects for the ILC
• The science motivation for the ILC is our strongest weapon
• The technical basis for the ILC is very stong• A global effort to design the ILC is underway and
working• Establishing a baseline will make the ILC more
real and taken more seriously--------------------------
• A sound design must be established with convincing and affordable costing.
• Global R&D program to demonstrate the ILC, improve over the baseline and reduce costs.