introduction to building estimating in south australia 1
TRANSCRIPT
1
Introduction to building Estimating in South Australia
2
ArchitecturalFloor plan
3
Architectural plan building details
4
Architecturalelevations
5
Truss Layout via Pryda software
6
Truss Report via Pryda software
7
Conventional manual layout with trusses
8
Production Truss plan used for manufacture- Critical measurements shown
Council Truss plans- Loads and engineering shown
Truss “T4”
9
Truss “T10”
10
How the plans look on site
11
12
13
Truss to conventional hip end
Truss T 4
14
Truss to conventional hip end (close up)
Truss “T4”
15
Truss to conventional hip end(Halfway point)
Truss “T10”
16
Truss T10
Truss to conventional hip end(side view truss “T10”
17
Steel Facia
Hip end & Steel Facia
18
Valley boards
19
Panel “N”
Pryda software wall layout
20Wall frame panel “N” Engineering for the lintel, for the size
Pryda software Engineering-Based on wind speed and loading
21
Wind speed is indicated on the architectural drawings
Residential categories are:28 Km/h (N1)33 Km/h (N2)41 Km/h (N3)
The wind speed determines both bracing and beam loading for the building
Strip bracing OS panel bracing
22
OS Bracing
Lintel
23
Timber take-off list
Computer Manual
24
The Building process on site
25
Strip bracing
Top plate bracing
Bottom plate
Truss tie down
26
Finished valley , Facia and gutters
Underside of eaves, facia and gutter
Brick work Tied to frame
27
Fully trussed roof
Non-load bearing internal wall
28
Typical multi dwellingMulti storey site- Scaffolding
29
Floor trusses
2 StoreyBracing &Tie downs
Plumbing to be taken into considerationwith floor trusses
30
Party fire walls between buildings
Fire check13 & 16mm
Shaft liner25mm