introduction to trenchless methods presented by glenn m. boyce, phd, pe senior associates presented...
TRANSCRIPT
Introduction to Trenchless Methods
Introduction to Trenchless Methods
Presented by
Glenn M. Boyce, PhD, PESenior Associates
Presented by
Glenn M. Boyce, PhD, PESenior Associates
April 21, 2009
Presentation Objectives
• Provide a better understanding of trenchless methods used for new installations
• Learn the advantages and limitations of the methods
• Discuss contractor qualifications
Types of Infrastructure
• Gas – Pressure
• Water – Pressure
• Sewer – Gravity
• Drainage – Gravity
• Power – Non-gravity
• Communications – Non-gravity
Trenchless Methods• Impact moling• Pipe ramming• Auger boring• Pilot tube• Pipe jacking / Microtunneling• Conventional tunneling• Horizontal directional drilling• Pipe bursting
Generic Size and Length
• Method Size LengthMoling 2” - 12” 150’Ramming 8” - 72” 300’Auger Bore 8” - 60” 250’Pilot Tube 6” - 42” 300’Microtunneling 12” - 108” 1,500’Pipe Jacking >54” 3,000’HDD 2” - 48” 6,500’Tunneling >60” Any length
What to Do?
• Choose the right method
• Use established “Standards”
• Collect information/investigate
• Plan ahead
• Conduct risk assessments
• Include mechanisms to handle conflicts
Use the Right Method• Open cut• Horizontal Directional Drilling• Auger boring• Pipe ramming• Pipe jacking• Microtunneling• Tunneling
1996
Pilot Tube
Auger Boring
• Road crossings
• Cohesive soils
• Short distances
• Above water table
• Need steel casing
• Minor steering
60-inch Diameter SBU-A
Pilot Tube Method
• Medium distances
• Straight alignments with good accuracy
• Variety of soils
• Smaller shafts
• Moderate equipment costs
Step 1
•
•
•
Step 2•
Pilot Tube + “Plus”
• Now used as a guide for other method– Auger boring
– Pipe Ramming
Pipe Ramming• Wide range of
diameters• Soils only• Continuously
supported• Typically < 300’• Above and below
water table• Need steel casing• No steering control
Installation Method• Ramming in continuous length or segments
Rammingin
Progress
Pilot tube
Pipe Jacking
• Large diameters • Soils and mixed
ground• Face supported• Long distances• Above the water
table• Steerable
Microtunneling
• Range of diameters (> 12”)
• All ground types
• Continuous face support
• Long distances
• Above or below water table
• Range of pipe materials
• Steerable to line and grade
Micro vs Utility TunnelingRemotely operatedPrecise guidancePipes jacked from launch pitContinuous support to face
Conventional Rib & Lagging Tunnel
Microtunnel
Tunnel Shield Construction
Lining is built within shield. Lining does not move longitudinally after placement.
Required Axial Thrust versus Length of Drive for Same Diameter
Opposite Approaches
• Open Cut
• What happens happens
• Trenchless
• Understand and plan
What to Do?
• Understand the site history and potential obstructions
• Look at old aerial photos• Conduct a
geotechnical program
• Locate all utilities
Potential Obstructions
• Cobbles or Boulders
• Wood
• Fill materials
• Hard zones
• Mixed faces
Typical Machine Sizes
• Piercing – 2 to 3 inches
• Pilot Tube – 6 to 36 inches
• HDD – 6 to 54 inches
• Auger Boring – 10 to 60 inches
• Pipe Jacking/MT – 12 to 96 inches
• Pipe Ramming – 12 to 144 inches
• Shield – 60 to 144 inches
Typical CMP Culverts
Replacement Issues
• Need to increase size for aquatic passage
• Must keep existing culvert active during construction
• Minimize costs
• Develop the best cross section
• Use the right materials
Possible Solutions
Consume the Culvert
Use Liner Plate Tunnel
Design Solutions
• Built a parallel pipe barrel – Increases capacity
– Allow the existing to remain in service
– Get to use the materials you want
• Slipline the existing after new
• Built a new entry and exit apron
Closing Thoughts
• Methods still evolving
• Many hybrid methods emerging
• Better alignment control emerging in auger boring applications
• Must identify potential obstructions (or get X-ray vision)
HORIZONTAL DIRECTIONAL DRILLING (HDD)
Samuel T. Ariaratnam, PhD, PEArizona State University
Background Lengths up to 8,400 feetLengths up to 8,400 feet
Diameters of 2” – 54”Diameters of 2” – 54”
Applications:Applications: Utility conduitsUtility conduits PipelinesPipelines Gravity sewersGravity sewers Force mainsForce mains Horizontal remediation wellsHorizontal remediation wells Geotechnical investigationsGeotechnical investigations
Pilot Bore and Tracking
Pilot Bore
Drill Bits
Reaming/Hole Enlargement
Reaming
Reamers
CLAY
ANNULAR SPACE REGION
SAND
ANNULAR SPACE REGION
Pipe Material Distribution
Underground Construction Magazine9th Annual Survey, June 2007
Conclusions• HDD is a minimally-intrusive trenchless
construction method suited for highly congested urban areas and high traffic zones
• Horizontal Directional Drilling equipment is capable of installing a wide range of utilities
• HDD will never replace traditional open-cut methods; however, they complement each other
PIPE BURSTING
Samuel T. Ariaratnam, Ph.D., P.E.Arizona State University
Pipe Bursting
• Lengths typically 300-600 ftLengths typically 300-600 ft
• Diameters up to 42”Diameters up to 42”
• Applications:Applications:– replacement of force mainsreplacement of force mains– replacement of gravity replacement of gravity
sewerssewers
Static HeadStatic Head
Pneumatic HeadPneumatic Head
Pneumatic Systems - Usually include a pneumatic tool and winch and bursts the pipe using the kinetic energy of the tool. The pipe is usually attached to either the burst head or tool.
Static Systems – Usually include a hydraulic power source and a rod shuttling system and use high tonnage to pull new line into place.
Small Portable Systems - Either pneumatic or static for doing small diameter and short runs (e.g. laterals).
Common Types of Bursting Systems
IntroductionIntroduction
Emerging field of pipe replacement “Replacement of the host pipe by
fragmenting the existing conduit and installing a completely new pipe of equal diameter or larger in its place.”
ApplicationsApplications
Total pipe replacement Typical upsize as much as 20 – 30% Industrial & Municipal - Main Line &
Laterals Various host and product pipe materials Continuous or Sectional pipe installation
Pipe Bursting Feasibility
May achieve lower costs compared to open trench Less construction time Minimal excavation Social cost savings Reduces ground settlement Low environmental impact
Static Method (Continuous)
Static Method (Sectional)
Pneumatic Method
Almost all types of pipe can be burst …
• Cast iron• Steel• Ductile iron• High Density
Polyethylene• Polyvinylchloride
• Concrete• Reinforced
concrete• Asbestos cement• Clay
Various Host
MaterialsSTEEL
CAST IRON
VITRIFIED CLAY
350mm350mm(14”)(14”)
750mm750mm
(30”)(30”)
650mm650mm(26”)(26”)
Conclusions• Pipe bursting is the only trenchless
method capable of installing a new pipe of equal or larger diameter as a replacement option
• Almost any type of existing pipe can be burst and replaced with most pipe materials
• Proper planning is critical to project success!
CONTRACTOR QUALIFICATIONS & PRE-QUALIFICATION
Introduction
• The majority of trenchless contractors are reliable and follow good installation practices
• However, agencies must be aware of those few “cowboy” contractors
• Qualifying contractors is a recommended practice for trenchless projects to ensure use of competent contractors
Specifications
• Manufacturers Recommended Specifications
• Industry/Association Specification Guidelines
• Project Specific
Testing & Inspection Quality Assurance & Controls in Specifications Trained Inspectors Testing by Owner Laboratory Final CCTV Inspection of the Installed Pipe
Protection of Existing Utilities
• Call in Locates• Obtain As-Built Maps (Shared Responsibility)• Mark Utilities (Utility Owners)• Confirm Utilities (Pothole) (Excavator)• Protect (Excavator)
Protection of Existing Utilities – Locate Marks
As-Builts, Operator Logs, Notes
• Contractor is responsible for marking the plans to indicate any and all vertical and horizontal deviations between the design and actual installation
• Operator logs/notes should be maintained and updated daily by the Contractor and should include–Pipe number, depth, pitch, steering
commands, and notes
Logbook/Field Notes
Contractor Submittals Proof of success on prior similar projects
Pipe material, diameter, length Make/model of equipment, guidance equipment, fluid
mixture Slurry disposal plan Contingency plan Safe plan and protocols Certification by the manufacturer that the Contractor’s
personnel are trained in the use of the equipment Training certification for pipe installation Fusion training certification for HDPE Construction Plan & Installation Schedule Traffic Control Plan
Damage Avoidance
Trenchless Training Courses
• Horizontal Directional Drilling Good Practices
• Pipe Bursting Good Practices• New Installation Methods Good Practices• Cured-in-Place Pipe (CIPP) Good Practices• Sewer Laterals Rehabilitation &
Replacement
(www.nastt.org)
Caltrans Inspector Training
Classroom
Field Exercises
Conclusions• Well-written specifications
are important to minimize claims
• Hiring a competent contractor can be achieved through pre-qualification
• There are numerous available trenchless technology options